Upload
zeno
View
80
Download
0
Tags:
Embed Size (px)
DESCRIPTION
Reminder of upcoming milestones. From meeting LIU-PS 18/09/2012. For all machines: Nov. 2012: Table of performance parameters Jan. 2013: Baseline activities defined Feb. 2013: Update APT/EVM (cost-to-completion) March 2013: Draft for Long and Mid Term Pls. - PowerPoint PPT Presentation
Citation preview
1Reminder of upcoming milestones
For all machines:• Nov. 2012: Table of performance
parameters
• Jan. 2013: Baseline activities defined
• Feb. 2013: Update APT/EVM (cost-to-completion)
• March 2013: Draft for Long and Mid Term Pls.
• May 2013: Technical design report
® Clarify LIU-PS baseline and update APT/EVM basically
From meeting LIU-PS 18/09/2012
NOW
2
• LIU-PS01: Management• LIU-PS02: Beam Dynamics• LIU-PS03: Magnets• LIU-PS04: RF systems (incl. longitudinal/transverse
damper)4.1 Low-level RF4.2 High power RF (long. damper kicker)4.3 Transverse damper4.4 RF controls
• LIU-PS05: Power converters• LIU-PS06: Beam instrumentation• LIU-PS07: Beam intercepting devices• LIU-PS08: Vacuum system• LIU-PS09: Injection• LIU-PS10: Extraction and transfer
• LIU-PS01: Management• LIU-PS02: Beam Dynamics• LIU-PS03: Magnets• LIU-PS04: RF systems (incl. longitudinal/transverse
damper)4.1 Low-level RF4.2 High power RF (long. damper kicker)4.3 Transverse damper4.4 RF controls
• LIU-PS05: Power converters• LIU-PS06: Beam instrumentation• LIU-PS07: Beam intercepting devices• LIU-PS08: Vacuum system• LIU-PS09: Injection• LIU-PS10: Extraction and transfer
EVM update of LIU-PS (1/2)
3EVM update of LIU-PS (2/2)
• LIU-PS11: Controls• LIU-PS12: Electrical Systems• LIU-PS13: Cooling and ventilation• LIU-PS14: Installation, transport and handling• LIU-PS15: Civil engineering• LIU-PS16: Radiation protection• LIU-PS17: Interlock systems• LIU-PS18: Alarms• LIU-PS19: Access system doors• LIU-PS20: Survey• LIU-PS21: Commissioning and operation• LIU-PS22: Dismantling
• LIU-PS11: Controls• LIU-PS12: Electrical Systems• LIU-PS13: Cooling and ventilation• LIU-PS14: Installation, transport and handling• LIU-PS15: Civil engineering• LIU-PS16: Radiation protection• LIU-PS17: Interlock systems• LIU-PS18: Alarms• LIU-PS19: Access system doors• LIU-PS20: Survey• LIU-PS21: Commissioning and operation• LIU-PS22: Dismantling
4Present baseline (1/3)
5Present baseline (2/3)
6Present baseline (3/3)
7Resonance compensation• Compensation of resonances
2Qh + Qv = 1, Qh + 2Qv = 1 and 3Qv = 1 requires skew sextupoles
• Plan: ‐ Re-install existing sextupole magnets during X-mas
stand-by‐ Proof-of-principle beam tests in early 2013 (before
LS1!)‐ Development of new compensation scheme during
LS1, potentially including also octupoles (for 4Qv = 1)
Include resonance compensation magnets in LIU-PS03 (magnets)
Include power supplies + cabling for resonance compensation in LIU-PS05 (power converters )
A. H
usch
auer
et
al.
8RF (high-power and low-level)
• Preliminary conclusion of PS-SPS transfer studies:‐ 2nd 40 MHz cavity will provide more margin
(longitudinal emittance and transmission)‐ Even if 2nd cavity not available, operation possible® Main priority on improving reliability of existing
cavities Keep additional 40 MHz cavity as optional in LIU-PS4.2
(RF, high power)
• No immediate justification for complete exchange of power amplifiers 10 MHz
Keep new 10 MHz power amplifiers optional in LIU-PS4.2 (RF, high power)
• 1-turn feedback most probably not required on 20 MHz cavities
Keep new 20 MHz 1-turn feedback optional in LIU-PS4.1 (RF, low-level)
9Transverse feedback on the flat-top
• Successful operation of transverse damper against FT instabilities
• Plan (next to fully commissioning the damper): ‐ Validate that observed instabilities are e-cloud driven‐ Estimate new requirements for the existing damper
or an additional dedicated wide-band feedback‐ Maximum damper strength in CW
Include transverse feedback as baseline action against electron cloud instabilities in LIU-PS4.4 (RF, transverse damper)
Remove coating from project baseline in LIU-PS08 (vacuum)
A. B
las,
G. S
terb
ini e
t al
.
10 ms!
horizontal
FB ONFBOFF
10Beam instrumentation
• Trajectory measurement of LHC-type beams shortly before ejection, when the beam is already bunches with 20/40 MHz
• Tentative plan:• Investigate possibility of adding 1/2 transverse
wide-band pick-up(s) as copies of existing pick-up in SS94
• Phase advance between pick-ups to be checked• Check needs for application software/LabView
read-out
Input to be provided for BI review board on trajectory measurements
Eventually add transverse wide-band pick-ups to LIU-PS06 (beam instrumentation)
11Beam dump replacing SS12 ralentisseur
• Dump to act as• a collimator to reduce losses at extraction (CT or
MTE)• a ralentisseur for the emittance measurements• a fast scraper to measure the tails of the LHC
beams• Replace internal dumps in SS47/48
• Alessandro Masi following-up development
To be included as baseline in work unit LIU-PS07 (beam intercepting devices)
12New vacuum chamber MU41
• Vacuum chamber of magnet unit 41 identified as aperture limitation, causing losses
New vacuum chamber MU41 as project baseline To be included in LIU-PS08 (vacuum) work unit
13Summary
• Cost-to-completion to be ready for early 2013• Relevant changes to LIU-PS baseline:
• Resonance compensation• High-power RF• Transverse feedback instead of e-cloud coating• Beam instrumentation• Beam dump replacing SS12 ralentisseur• New vacuum chamber MU41
• Minor changes and updates of all other work units
Please check \\cern.ch\dfs\Departments\BE\Projects\PSUpgrade\WorkPackages_2012-10-08
Thank you for updating the work units in APT/EVM