Preliminary Plans Presentation Rock Terrace School and Tilden Middle School Revitalization / Expansion Project Prepared for Montgomery County Board of Education May 2017 Associates, PC

Rock Terrace School and Tilden Middle School€¦ · Preliminary Plans Presentation Rock Terrace School and Tilden Middle School Revitalization / Expansion Project 6300 Tilden Lane,

  • Upload
    others

  • View
    8

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Rock Terrace School and Tilden Middle School€¦ · Preliminary Plans Presentation Rock Terrace School and Tilden Middle School Revitalization / Expansion Project 6300 Tilden Lane,

Preliminary Plans Presentation

Rock Terrace School and Tilden Middle SchoolRevitalization / Expansion Project

Prepared forMontgomery County Board of Education

May 2017

Associates, PC

Page 2: Rock Terrace School and Tilden Middle School€¦ · Preliminary Plans Presentation Rock Terrace School and Tilden Middle School Revitalization / Expansion Project 6300 Tilden Lane,

This page intentionally left blank

Page 3: Rock Terrace School and Tilden Middle School€¦ · Preliminary Plans Presentation Rock Terrace School and Tilden Middle School Revitalization / Expansion Project 6300 Tilden Lane,

Rock Terrace School and Tilden Middle School - Revitalization / Expansion Project

Associates, PC

Preliminary Plans Presentation

Rock Terrace School and Tilden Middle SchoolRevitalization / Expansion Project

6300 Tilden Lane,Rockville, Maryland 20852

Montgomery County Board of Education

Mr. Michael A. Durso PresidentDr. Judith Docca Vice PresidentMs. Jeanette E. Dixon MemberMrs. Shebra L. Evans MemberMrs. Patricia B. O’Neill MemberMs. Jill Ortman-Fouse MemberMrs. Rebecca Smondrowski MemberMr. Eric Guerci Student Member

Montgomery County Schools Administration

Dr. Jack Smith Superintendent of SchoolsMr. James C. Song Director, Department of Facilities ManagementMr. Seth P. Adams Director, Division of ConstructionMr. Michael P. Shpur Architect, Division of ConstructionMr. Dennis Cross Project Manager, Division of ConstructionMs. Deborah Szyfer Facility Planner, Division of Long-range Planning

Page 1

Page 4: Rock Terrace School and Tilden Middle School€¦ · Preliminary Plans Presentation Rock Terrace School and Tilden Middle School Revitalization / Expansion Project 6300 Tilden Lane,

Associates, PC

This page intentionally left blank

Page 5: Rock Terrace School and Tilden Middle School€¦ · Preliminary Plans Presentation Rock Terrace School and Tilden Middle School Revitalization / Expansion Project 6300 Tilden Lane,

Rock Terrace School and Tilden Middle School - Revitalization / Expansion Project

Associates, PC

Page 2

The preliminary plans for the Tilden Middle and Rock Terrace Schools collocation and revitalivation/expansion were developed based on the educational specifi cations prepared by Montgomery County Public Schools (MCPS). Through a series of public work sessions, several design alternatives were developed and evaluated. The proposed plans presented herein were modifi ed and evaluated in accordance with suggestions and recommendations received during the schematic design work sessions.

Mrs. Irina LaGrangeMrs. Kathy LertoraMr. Robert GoldMr. Adam Atwood Mr. Lawrence BassinMs. Deborah BergerMs. Loris BergerMr. Thomas H. BiggsMs. Mary Ellen BroderickMs. Jane BryanMs. Caroline CardoneMr. David CochranMs. Emily CullatherMs. Virginia CusterMs. Catherine Day Ms. Nermine DemopoulusMs. Ashley DoyleMs. Janice EisenbergMr. Ed FarberMs. Ellie FlyerMr. Ryan ForkertMs. Pam FountainMs. Claudia FraserMr. Bruce Fuchs

PrincipalPrincipalAssistant PrincipalStaffParentParentParentParentStaffNeighborStaffStaffStaffStaffStaffCluster CoordiantorStaffStaffNeighborNeighborPrincipalStaff StaffParent

Tilden Middle SchoolRock Terrace SchoolTilden Middle SchoolTilden Middle SchoolTilden Middle SchoolLuxmanor Elementary SchoolTilden Middle SchoolGreater Farmland Civic AssociationTilden Middle SchoolCommunityRock Terrace SchoolTilden Middle SchoolTilden Middle SchoolRock Terrace SchoolTilden Middle SchoolWalter Johnson Cluster Rock Terrace SchoolRock Terrace SchoolLuxmanor Civic AssociationLuxmanor Civic AssociationLuxmanor Elementary SchoolTilden Middle SchoolTilden Middle SchoolTilden Middle School

Facility Advisory Process Involvement

Participation

Participants in the Facility Advisory Process

Page 6: Rock Terrace School and Tilden Middle School€¦ · Preliminary Plans Presentation Rock Terrace School and Tilden Middle School Revitalization / Expansion Project 6300 Tilden Lane,

Rock Terrace School and Tilden Middle School - Revitalization / Expansion Project

Associates, PC

Page 2A

Ms. Yu-Hsin HuanyMs. Gillian Hulsizer Ms. Joanne KeeMs. Karen KulpinskiMr. Jeff LeamanMr. Wayne LeeMr. David LinMr. Phillip A. LynchMr. Nicolas MastMr. Jose MesaMs. Jannine MillerMs. Abbe MillsteinMr. David MilobskyMs. Kathy NaimonMs. Debby OrsakMr. Aaron ShinMr. Jerry OstronMs. Sharon PlotnickMs. Debbie PosnerMs. Elizabeth PyeattMs. Faustina Quist Ms. Lavonne ReddickMr. Lee RonisMr. Jason RosendergMs. Lori ScherrMs. Karen SchultzMs. Carol ScottMs. Tory ShawMr. Dave SolorioMs. Jane StaskoMs. Sheri Steisel Weiss

ParentStaffParentStaffStaffStaffNeighborDirectorStaffStaffStaffParentParent StaffParentStaffNeighborParentStaffStaffStaffStaffNeighborStaff ParentStaffParentStaff ParentStaffParent

Tilden Middle SchoolRock Terrace SchoolLuxmanor Elementary SchoolTilden Middle SchoolTilden Middle SchoolTilden Middle SchoolLuxmanor Civic Association Department of Special Education Services, MCPSTilden Middle SchoolRock Terrace SchoolRock Terrace SchoolTilden Middle SchoolRock Terrace SchoolTilden Middle SchoolTilden Middle SchoolTilden Middle SchoolCommunityRock Terrace SchoolRock Terrace SchoolRock Terrace SchoolRock Terrace SchoolRock Terrace SchoolLuxmanor Civic Association Rock Terrace SchoolTilden Middle SchoolRock Terrace SchoolRock Terrace SchoolTilden Middle SchoolWalter Johnson ClusterTilden Middle SchoolTilden Middle School

Facility Advisory Process Involvement (continued)

Facility Advisory Participants (continued)

Page 7: Rock Terrace School and Tilden Middle School€¦ · Preliminary Plans Presentation Rock Terrace School and Tilden Middle School Revitalization / Expansion Project 6300 Tilden Lane,

Rock Terrace School and Tilden Middle School - Revitalization / Expansion Project

Associates, PC

Ms. Jillian StormsMs. Melissa TeageMs. Susan Townsend-GrayMr. Mike ValentinMr. and Mrs. WalkerMs. Gabriela ZaralaMr. Mike Zarchin

School Facilities ArchitectStaffStaffStaffNeighborStaffDirector

Maryland State Department of EducationRock Terrace SchoolGreen Acres SchoolRock Terrace SchoolLuxmanor Civic Association Rock Terrace SchoolOffi ce of School Support & Improvement, MCPS

Facility Advisory Participants (continued)

Facility Advisory Process Involvement (continued)

Page 2B

Page 8: Rock Terrace School and Tilden Middle School€¦ · Preliminary Plans Presentation Rock Terrace School and Tilden Middle School Revitalization / Expansion Project 6300 Tilden Lane,

Rock Terrace School and Tilden Middle School - Revitalization / Expansion Project

Associates, PC

Project Information

Background/History

Page 3

Location:

Cluster:

History:

Site Size:

6300 Tilden Lane, Rockville, Maryland 20852

Walter Johnson Cluster

The property was once the original location of Tilden Middle School. The school relocated to former Charles W. Woodward High School in 1991 and the original Tilden location became the middle school holding site for Montgomery County Public Schools. Rock Terrace School, a special education school is currently located at 390 Martins Lane, Rockville, Maryland.

1958 Construction of Original School 116,400 square feet1991 Tilden Middle School Relocation -2018 Planned Demolition -116,400 square feet2019 Planned Collocated Facility 242,565 square feetTotal 242,565 square feet 19.75 acres

Current and Projected School Capacity and Student Enrollment for Tilden Middle School:

Actual Projections2016-2017 2017-2018 2018-2019 2019-2020 2020-2021 2021-2022

Program Capacity 939 939 939 939 1200 1200Enrollment 850 959 992 1,024 1,094 1,132Space Available/Defi cit 89 (20) (53) (95) 106 68

Current and Projected School Capacity and Student Enrollment for Rock Terrace School:

Actual Projections2016-2017 2017-2018 2018-2019 2019-2020 2020-2021 2021-2022

Program Capacity 100 100 100 100 150 150Enrollment 87 100 100 100 120 120Space Available/Defi cit 13 0 0 0 30 30

Page 9: Rock Terrace School and Tilden Middle School€¦ · Preliminary Plans Presentation Rock Terrace School and Tilden Middle School Revitalization / Expansion Project 6300 Tilden Lane,

Rock Terrace School and Tilden Middle School - Revitalization / Expansion Project

Associates, PC

Page 3A

Project Information (continued)

Educational Program ObjectivesThe purpose of the project is to collocate Tilden Middle School and Rock Terrace School to provide both schools with an up-to-date facility while increasing the capacity of Tilden Middle School to accommodate projected student enrollment. Currently, each school is at different locations and the site of the new school is utilized as a holding center for middle schools.

The proposed Tilden Middle School will meet the requirements of the educational specifi cations for a new middle school by providing fi fty-nine (59) teaching spaces for grades six through eight when completed in August 2020. The current student enrollment at Tilden Middle School is 850 and is projected to be approximately 1,094 by the 2020–2021 school year. The new school facility will increase the capacity of the school from the current 939 seats to approximately 1,215 seats with a core capacity for 1,500 students.

The proposed Rock Terrace School will meet the requirements of the educational specifi cations for a new special education school by providing eighteen (18) teaching spaces for middle, upper and high school aged students when completed in August 2020. The current student enrollment at Rock Terrace School is 87. The new school facility will accommodate the county’s special needs population with a capacity for approximately 120 students.

Stakeholder outreach efforts consisted of nine round table discussions during the winter of 2014, six community meetings during the feasibility study phase in the fall of 2015, and three schematic design work sessions in 2017 to elicit student, staff, and communites input. Participants were asked to share their ideas, goals and concerns for the project. Questions related to safety and neighborhood impact are addressed in the architectural design that incorporates both active and passive security measures. During construction, pedestrian paths around the site will be maintained. All egress paths, construction fencing, access, and contractor staging will be reviewed by the appropriate permitting agencies and implementation will be monitored to ensure safety and security are uncompromised with minimal impact to the neighborhood.

Page 10: Rock Terrace School and Tilden Middle School€¦ · Preliminary Plans Presentation Rock Terrace School and Tilden Middle School Revitalization / Expansion Project 6300 Tilden Lane,

Rock Terrace School and Tilden Middle School - Revitalization / Expansion Project

Associates, PC

Page 3B

Project Information (continued)

Educational Program Objectives (Continued)

Demographic Characteristics of Schools

Total Two or more Black or Mobility Schools Enrollment races % Afr. Amer. % Asian% Hispanic % White % FARMS%* ESOL%** Rate%***Walter Johnson HS 2350 5.9% 9.5% 11.5% 18.0% 54.7% 7.1% ≤ 5.0% 7.6%North Bethesda MS 1102 7.7% 7.0% 11.3% 12.8% 61.1% 5.9% ≤ 5.0% 7.0%Tilden MS 911 6.4% 11.2% 16.7% 18.7% 46.9% 11.6% 12.5% 10.0%Ashburton ES 905 9.7% 14.9% 15.0% 16.1% 43.8% 11.6% 12.6% 11.2%Farmland ES 755 ≤ 5.0% 5.3% 32.3% 8.7% 48.5% 7.2% 27.3% 19.2%Garrett Park ES 829 5.9% 12.4% 15.6% 23.4% 42.3% 15.9% 20.2% 11.8%Kensington-Parkwood ES 656 9.8% 5.3% 6.4% 12.3% 66.0% 5.3% 6.5% 8.1%Luxmanor ES 467 6.0% 11.8% 24.0% 18.6% 39.6% 16.6% 19.8% 15.7%Wyngate ES 739 8.5% ≤ 5.0% 10.8% 11.9% 64.0% ≤ 5.0% 6.2% 5.3%Elementary Cluster Total 4351 7.6% 9.2% 17.1% 15.2% 50.7% 9.6% 15.1% 11.6%Elementary County Total 76428 5.2% 21.3% 13.8% 32.0% 27.4% 40.1% 23.1% 13.0%

2016–2017 2015–2016

*Percent of students approved for Free and Reduced-priced Meals Program (FARMS) during the 2015–2016 school year.**Percent of English for Speakers of Other Languages (ESOL) during the 2015–2016 school year. High School students are served in regional ESOL centers.

***Mobility Rate is the number of entries plus withdrawals during the 2015–2016 school year compared to total enrollment.Notes: Native Hawaiian/Pacific Islander and American Indian/Alaskan Native categories total less than 1% and were therefore excluded from the table.

Due to federal and state guidelines, demographic characteristics of schools of less than or equal to 5.0% are reported as ≤ 5.0%.

The following data includes demographic characteristics compared to program capacity for schools in the Walter Johnson cluster for school year 2016-2017:

in Walter Johnson cluster

Page 11: Rock Terrace School and Tilden Middle School€¦ · Preliminary Plans Presentation Rock Terrace School and Tilden Middle School Revitalization / Expansion Project 6300 Tilden Lane,

Rock Terrace School and Tilden Middle School - Revitalization / Expansion Project

Associates, PC

Page 3C

Project Information (continued)

Educational Program Objectives (Continued)

(School Year 2016–2017)

Schools Gra

des

Ser

ved

Cap

acit

y (H

S @

90%

MS@

85%

)

To

tal R

oo

ms

Sup

po

rt R

oo

ms

Reg

ular

Sec

on

dar

y @

25

Reg

ular

Ele

men

tary

@23

CSR

Gra

des

1–2

@18

Pre

–K @

20

Pre

–K @

40

HS

@20

CSR

KIN

D @

18

KIN

D @

22

ESO

L @

15

MET

S @

15

HSM

@13

ELE

M L

AD

@13

ELC

@10

LA

NG

@12

LFI

@10

SC

B @

6

AA

C@

7

AU

T @

6

BR

IDG

E @

10

DH

OH

@7

ED

@10

EX

TEN

SIO

NS

@6

GT/

LD @

13

PD

@7

PEP

@6

PEP

@12

PEP

@18

VIS

ION

(El

emen

tary

) @

7

OTH

ER

Walter Johnson HS 9-12 2335 107 101 2 2 1 1

North Bethesda MS 6-8 864 42 39 1 2

Tilden MS 6-8 927 52 40 2 3 5 2

Ashburton ES K-5 651 34 3 18 6 3 1 3

Farmland ES K-5 714 37 4 24 6 3

Garrett Park ES K-5 776 37 3 28 6

Kensington-Parkwood ES K-5 472 27 5 15 4 3

Luxmanor ES K-5 411 24 4 13 4 2 1

Wyngate ES K-5 777 38 4 29 5

Program Capacity TableSpecial Education Services

Sch

oo

l Bas

ed

Clu

ster

Bas

ed

Quad Cluster Based County & Regional Based

Page 12: Rock Terrace School and Tilden Middle School€¦ · Preliminary Plans Presentation Rock Terrace School and Tilden Middle School Revitalization / Expansion Project 6300 Tilden Lane,

Rock Terrace School and Tilden Middle School - Revitalization / Expansion Project

Associates, PC

Project Information (continued)

Educational Program Objectives (Continued)

Page 3D

Demographic Characteristics of Schools

Total Two or more Black or Mobility Schools Enrollment races % Afr. Amer. % Asian% Hispanic % White % FARMS%* ESOL%** Rate%***Stephen Knolls School 89 ≤ 5.0% 30.3% 12.4% 34.8% 21.3% 36.6% 9.8% ≤ 5.0%Longview School 52 ≤ 5.0% 21.2% 11.5% 30.8% 34.6% 25.5% ≤ 5.0% 11.8%RICA 103 9.7% 25.2% ≤ 5.0% 18.4% 41.7% 40.5% ≤ 5.0% 77.5%Rock Terrace School 93 5.4% 30.1% 10.8% 18.3% 35.5% 36.5% 5.9% 11.8%Carl Sandburg Learning Center 93 ≤ 5.0% 33.3% 6.5% 34.4% 21.5% 38.2% 34.8% 22.5%Elementary County Total 76428 5.2% 21.3% 13.8% 32.0% 27.4% 40.1% 23.1% 13.0%

2016-2017 2015–2016

*Percent of students approved for Free and Reduced-priced Meals Program (FARMS) during the 2015–2016 school year.**Percent of English for Speakers of Other Languages (ESOL) during the 2015–2016 school year. High School students are served in regional ESOL centers.

***Mobility Rate is the number of entries plus withdrawals during the 2015–2016 school year compared to total enrollment.Notes: Native Hawaiian/Pacific Islander and American Indian/Alaskan Native categories total less than 1% and were therefore excluded from the table.

Due to federal and state guidelines, demographic characteristics of schools of less than or equal to 5.0% are reported as ≤ 5.0%.

The following data includes demographic characteristics compared to program capacity in special education centers for school year 2016-2017:

Special Education Center

Page 13: Rock Terrace School and Tilden Middle School€¦ · Preliminary Plans Presentation Rock Terrace School and Tilden Middle School Revitalization / Expansion Project 6300 Tilden Lane,

Rock Terrace School and Tilden Middle School - Revitalization / Expansion Project

Associates, PC

Project Information (continued)

Educational Program Objectives (Continued)

Page 3E

Schools Cap

acit

y (H

S @

90%

MS@

85%

)

To

tal R

oo

ms

Sup

po

rt R

oo

ms

Reg

ular

Sec

on

dar

y @

25

Reg

ular

Ele

men

tary

@23

CSR

Gra

des

1–2

@18

Pre

–K @

20

Pre

–K @

40

HS

@20

CSR

KIN

D @

18

KIN

D @

22

ESO

L @

15

MET

S @

15

HSM

@13

ELE

M L

AD

@13

ELC

@10

LA

NG

@12

LFI

@10

SC

B @

6

AA

C@

7

AU

T @

6

SPE

CIA

L SC

HO

OLS

@ 6

DH

OH

@7

ED

@10

EX

TEN

SIO

NS

@6

GT/

LD @

13

PD

@7

PEP

@6

PEP

@12

PEP

@18

VIS

ION

(El

emen

tary

) @

7

OTH

ER

Stephen Knolls School 190 19 4 1 7 6 1

Longview School 48 10 2 8

RICA 180 18 18

Rock Terrace School 100 16 2 10 4

Carl Sandburg Learning Center 79 16 3 1 12

Program Capacity Table

(School Year 2016–2017)

Special Education Services

Sch

oo

l Bas

ed

Clu

ster

Bas

ed

Quad Cluster Based County & Regional Based

Page 14: Rock Terrace School and Tilden Middle School€¦ · Preliminary Plans Presentation Rock Terrace School and Tilden Middle School Revitalization / Expansion Project 6300 Tilden Lane,

Rock Terrace School and Tilden Middle School - Revitalization / Expansion Project

Associates, PC

Project Information (continued)

Page 3F

Teaching Stations and Spaces Provided When Completed - Tilden Middle School

English/Foreign Language/Math/ Social Studies Standard Classrooms

ScienceScience LaboratoriesScience Prep/Project/StorageChemical Storage

Instructional Support AreasTeam WorkroomInterdisciplinary Textbook StorageDepartmental Textbook StorageForeign Language Textbook StorageMath InterventionDevelopmental Reading

ESOL ClassroomsESOL ClassroomESOL Team Room

Music SuiteInstrumental Music RoomGeneral Music/Choral RoomGeneral/Choral StorageMusic Offi ceMusic Practice Rooms

33

841

333111

21

11112

Special and Alternative EducationAspergers ClassroomsLearning for Independence Prep AreaGrooming RoomsSpecial Education Team RoomResource RoomSensory RoomSpeech and Language Therapy Occupational Therapy/Physical TherapyAccommodation RoomConference Room

Visual Arts SuiteArt RoomStorageKiln Room

Multipurpose Technology LaboratoryMultipurpose Technology LaboratoryComputer Technology LaboratoryTechnology Preparation/Storage

Multipurpose LaboratoryMultipurpose LaboratoryStorage

52222121131

111

111

11

Page 15: Rock Terrace School and Tilden Middle School€¦ · Preliminary Plans Presentation Rock Terrace School and Tilden Middle School Revitalization / Expansion Project 6300 Tilden Lane,

Rock Terrace School and Tilden Middle School - Revitalization / Expansion Project

Associates, PC

Project Information (continued)

Page 3G

Teaching Stations and Spaces Provided When Completed - Tilden Middle School (continued)

Physical EducationGymnasium (Equals 2 teaching stations)Second GymnasiumAuxiliary Gym (Fitness/Weight Room)Auxiliary GymHealth ClassroomLocker RoomsStorage RoomsToilet RoomsShower/Drying RoomsLaundry RoomOffi cesCommon Planning AreaGeneral StorageSecond Gymnasium StorageOutdoor StorageInteragency Coordinating Board Storage

Student ActivitiesSchool StoreStudent Government Storage Closet

Student DiningStudent DiningStageStorageChair Storage

1111123221212111

11

1111

Administration SuiteGeneral Offi ce Principal’s Offi ceAssistant Principal’s Offi ceAssistant School Admin. Offi ceStudent Support CenterAdministrative Secretary’s Offi ceWorkroomStorageConference RoomCopier WorkroomFinancial Secretary’s Offi ceStaff Development Offi ceInstructional Data Assistant Offi ceFinancial Seceratary’s Offi ceSecurity Offi ceTesting RoomUpper Floor Workroom

Guidance SuiteCounselor’s Offi ceWaiting RoomConference RoomRecords RoomItinerant Staff Offi ce

Staff FacilitiesStaff LoungeTelephone Room

11311111111111111

51111

11

Page 16: Rock Terrace School and Tilden Middle School€¦ · Preliminary Plans Presentation Rock Terrace School and Tilden Middle School Revitalization / Expansion Project 6300 Tilden Lane,

Rock Terrace School and Tilden Middle School - Revitalization / Expansion Project

Associates, PC

Project Information (continued)

Teaching Stations and Spaces Provided When Completed - Rock Terrace School

English/Foreign Language/Math/ Social Studies Standard Classrooms (Middle School)Standard Classroom (High/Upper School)Textbook StorageMiddle School team Offi ceHigh School Team Offi ceUpper School Team Offi ceWorkroom

ScienceScience Resource LaboratoriesScience PrepStorage RoomGreenhouseGreenhouse Prep Room

Support AreasCounselor’s Offi ceSpecial Needs CoordinatorSpeech & LanguageOT/PT RoomTransition Support TeacherSchool Psychologist Offi ceInstructional Data Assistant Sensory RoomStudent Support RoomConference Room

5611111

11111

1122211211

Specialty RoomsArt RoomArt Room StorageMusic RoomMusic Room Storage

Career Technology EducationHome Survival Skills LabHome Survival StorageWork Offi ce Skills LabTeam Offi ce

Culinary ArtsCulinary Arts Lab (4 Stations)Culinary Arts StorageRestaurant

1111

1111

111

Page 3H

Page 17: Rock Terrace School and Tilden Middle School€¦ · Preliminary Plans Presentation Rock Terrace School and Tilden Middle School Revitalization / Expansion Project 6300 Tilden Lane,

Rock Terrace School and Tilden Middle School - Revitalization / Expansion Project

Associates, PC

Project Information (continued)

Page 3I

Teaching Stations and Spaces Provided When Completed - Rock Terrace School (continued)

Physical EducationGymnasiumLocker AreaToilet RoomsStorageOutdoor StorageOffi ce

Student ActivitiesStudent Council Suite/Store

Staff Offi cesStaff Development Offi ceESOL TeacherItinerant Staff Offi cesStaff Room

122111

1

1131

Student Dining FacilitiesStudent Dining (4 Students/Round Table - 30 Student Stage)StageTable Storage

Administration SuiteGeneral Offi ce Principal’s Offi ceAssistant Principal’s Offi ceFinancial Assistant Offi ceStoragePaper StorageConference RoomOffi ce WorkroomPTG Storage RoomSecurity Offi ceTesting Room

111

11111111111

Page 18: Rock Terrace School and Tilden Middle School€¦ · Preliminary Plans Presentation Rock Terrace School and Tilden Middle School Revitalization / Expansion Project 6300 Tilden Lane,

Rock Terrace School and Tilden Middle School - Revitalization / Expansion Project

Associates, PC

Project Information (continued)

Page 3J

Teaching Stations and Spaces Provided When Completed - Collocated/Shared Spaces

Library Media CenterMain Learning EnvironmentWork/Production AreaStorage/Media GeneralIT Systems Specialist RoomMultimedia Production RoomControl Room

Tilden MS Health SuiteWaiting RoomTreatment/Medication AreaRest AreaToilet Area (collocated)StorageOffi ce/Health Assessment Room (collocated)Health Assessment/Isolation Room (collocated)

Rock Terrace School Health SuiteWaiting RoomTreatment/Medication RoomRest AreasStoragePersonal Care Room (collocated)

111111

112211

1

11111

Kitchen AreaService Area (5 Service Lines)Food PrepDry Food StorageRefrigeratorFreezerOffi ceLocker/Toilet RoomReceiving AreaChemical Storage Room

Building Service FacilitiesBuilding Services Offi ceLocker/Shower AreaPlant Equipment Operator Offi ceReceiving and Storage AreaGeneral StorageBuilding Services Outdoor Storage

OtherTelecommunication Equip. ClosetTelecommunication ClosetToilet Room / AdministrationLoading PlatformCompactor/Trash RoomBuilding Services Closets (min. 1/hallway)

111111111

111141

15111

Page 19: Rock Terrace School and Tilden Middle School€¦ · Preliminary Plans Presentation Rock Terrace School and Tilden Middle School Revitalization / Expansion Project 6300 Tilden Lane,

Rock Terrace School and Tilden Middle School - Revitalization / Expansion Project

Associates, PC

Page 3K

Project Information (continued)

Project Design ObjectivesBuilding design will encourage a collaboration to accommodate the educational programs for both schools. Each instructional area will have adequate learning spaces, work areas, restrooms, and storage facilities.

Building design goals include:

Creating a defi ned and welcoming entrance for each school with their own identity and administrative control and supervision Maintaining the student population from both schools separated while effi ciently sharing facilities and services Creating a building with functional spatial relationships Creating a building that allows easy supervision of students Allowing convenient and secure non-school hours access to activity areas of the building Designing a building that respects the surrounding neighborhood Minimizing the footprint of the building to preserve existing green space and trees

Page 20: Rock Terrace School and Tilden Middle School€¦ · Preliminary Plans Presentation Rock Terrace School and Tilden Middle School Revitalization / Expansion Project 6300 Tilden Lane,

Rock Terrace School and Tilden Middle School - Revitalization / Expansion Project

Associates, PC

Site Design

Site Features: Tilden Center, situated on a 19.75 acre property, is comprised of six parcels and is located at 6300 Tilden Lane, Rockville, Maryland. The site is surrounded by single-family residential buildings along Tilden Lane, Marcliff Road, and Cushman Road.

The existing site has a student drop-off area accessed via Tilden Lane and exits onto Marcliff Rd. Two existing driveway curb cuts from Marcliff Road serve the existing bus loop and site parking. These existing driveways will remain to serve the new schools. A new student drop off loop with stacking for 30 vehicles and a passing lane and 130 staff parking spaces will be constructed on the northern portion of the site to serve Tilden Middle School. Traffi c will enter via the existing entry and exit through a newly constructed driveway (both on Tilden Lane). The existing northern entry into the site from Marcliff Road will be a bus only entrance and exit supporting 20 buses for both Tilden Middle and Rock Terrace Schools. The southern access from Marcliff Road will provide a separate student drop-off loop and 75 staff parking spaces for Rock Terrace School, as well as access to the service area for both schools.

Stormwater management will be provided to meet Environmental Site Design (ESD) requirements to the maximum extent practicable and to meet the Montgomery County Department of Permitting Services requirements. ESD options include providing micro-bioretention facilities, and preserving existing natural forested areas. Underground structural facilities will be proposed in areas where no surface treatment options are viable.

Wall-mounted lighting fi xtures will be installed on the exterior of the new building and will be shielded to protect adjacent residences from intrusive glare while maintaining light levels for safety and security. Pole-mounted parking area lighting fi xtures will be 100% down-lighting to minimize light pollution into the night sky. All exterior light fi xtures will be light emitting diode (LED) type, and will operate on timers to conserve energy.

Project Information (continued)

Page 3L

Page 21: Rock Terrace School and Tilden Middle School€¦ · Preliminary Plans Presentation Rock Terrace School and Tilden Middle School Revitalization / Expansion Project 6300 Tilden Lane,

Rock Terrace School and Tilden Middle School - Revitalization / Expansion Project

Associates, PC

Project Information (continued)

Page 3M

Building DesignGeneral Description: The proposed three-story building is organized in three main sections, that include Tilden Middle School on the north, activities and shared/collocated spaces in the middle, and Rock Terrace School on the south. The main entrance to Tilden Middle School will face Tilden Lane and Marcliff Road. This corner entrance allows access to both the bus loop and the student drop off area. Rock Terrace School’s entrance faces Marcliff Road. This entrance projects out from the building to create a prominant and easily identifi able entrance from Marcliff Road. A secondary entrance for activities is located along the bus loop and provides convenient access to dining rooms, gymnasiums, and the media center. The students from each school have direct access to play fi elds from the dining rooms.

Tilden Middle School’s academic spaces are organized with one grade level per fl oor containing classrooms, team rooms, science labs and support spaces organized around a courtyard. Tilden’s administration and guidance suites are located on the fi rst fl oor near the main entrance to enhance security and supervision. Technology, art, and multipurpose labs are located on the second level.

The center portion of the school serves as a shared activities center for both schools. The fi rst fl oor houses both schools’ dining/multipurpose rooms, locker rooms, staff lounges, health suites, main gymnasiums, and stages. Also on the fi rst fl oor is Tilden’s music suite, Rock Terrace’s culinary arts suite, and a shared special education suite.The shared special education suite located between the two schools accommodates spaces such as conference rooms, speech and therapy rooms, psychologist, counselors, and transition teacher offi ces. The second level of the activities section has Tilden’s auxiliary gymnasiums, a media center with separate reading rooms for each school, and a TV production studio.

Rock Terrace School’s classrooms and support spaces are arranged around a courtyard on two levels. The orientation of Rock Terrace consists of an administration suite adjacent to the main entrance on the fi rst fl oor, a skills lab, garden, and greenhouse on the southwest end of the building, and the art and science labs on the second fl oor.

The fl exible building design for the school will promote a philosophy of adaptable classrooms, and facilitate various presentation formats and learning activities. Multi-purpose and fl exible spaces will be designed for both staff and students to collaborate on projects. Furniture that is easily reconfi gurable will be explored to maximize the fl exibility in the school. The collocation of Tilden Middle School and Rock Terrace School allows for collaboration between the students and staff of both schools and shared use of spaces.

Classrooms are designed to support interactive educational technology that includes controlled wireless computer access and interactive whiteboard systems. Individual classrooms will have distributed computer outlets on the walls and allow multiple group teaching areas within a classroom. Individual classrooms will be designed to provide fl exible teaching spaces, that include opportunities for small group sessions or lecture sessions. Students can be organized into small groups for project-oriented teaching or face a teacher in a traditional lecture-teaching method.

Page 22: Rock Terrace School and Tilden Middle School€¦ · Preliminary Plans Presentation Rock Terrace School and Tilden Middle School Revitalization / Expansion Project 6300 Tilden Lane,

Rock Terrace School and Tilden Middle School - Revitalization / Expansion Project

Associates, PC

Project Information (continued)

Sustainability

Page 3N

The proposed project will be designed and constructed with an emphasis on the environmental sustainability. The architecture and engineering systems will align with facility management sustainability principals to ensure long term operational effectiveness. The project will be registered with the United States Green Building Council (USGBC) and will be in compliance with Leadership in Energy and Environmental Design (LEED) standards to achieve Leadership in Energy and Environmental Design (LEED) Silver certifi cation or higher. Sustainability features will include the following:

• Encouraging alternative transportation to the school by providing conveniently located bike racks and preferred parking for low emitting/fuel effi cient vehicles and carpools • Preserving a high percentage of vegetated open space to protect the surrounding ecosystem • Managing stormwater to both reduce runoff quantity and improve quality • Using highly-refl ective roof surfaces to reduce heat island effect and heat gain to the building • Installing water conserving, low-fl ow plumbing fi xtures • Optimizing the energy performance of the building by providing a highly energy effi cient building envelope, lighting system and heating, ventilation and air conditioning (HVAC) system • Optimizing equipment selection, installation, and operation of HVAC equipment through enhanced commissioning of the building systems • Diverting construction “waste” from landfi lls that can instead be salvaged for reuse or recycled • Adhering to construction indoor air quality management plans and using low-emitting building materials to safeguard occupant health • Providing a high level of occupant control over individual lighting and thermal comfort to promote enhanced indoor environment • Using construction materials that are recycled and regionally manufactured • Implementing a Green Housekeeping plan • Maximizing daylight in classrooms • Minimizing background noise level from HVAC systems in classrooms and other core learning spaces and control reverberation time with suffi cient sound absorptive materials

One of the primary design factors required to achieve a sustainable facility is the conservation of energy. The importance andconsideration placed on energy conservation will be refl ected in the confi guration and orientation of the building, the use of energy modeling as a design tool, the selection of materials, and the mechanical/electrical systems utilized. The new building will be designed to meet or exceed 2015 International Energy Conservation Code (IECC), as well as Montgomery County energy conservation codes.

Page 23: Rock Terrace School and Tilden Middle School€¦ · Preliminary Plans Presentation Rock Terrace School and Tilden Middle School Revitalization / Expansion Project 6300 Tilden Lane,

Rock Terrace School and Tilden Middle School - Revitalization / Expansion Project

Associates, PC

Vicinity Map

Page 4

NRock Terrace School and Tilden Middle School6300 Tilden LaneRockville, Maryland 20852

0 2000

SITE

Page 24: Rock Terrace School and Tilden Middle School€¦ · Preliminary Plans Presentation Rock Terrace School and Tilden Middle School Revitalization / Expansion Project 6300 Tilden Lane,

Rock Terrace School and Tilden Middle School - Revitalization / Expansion Project

Associates, PC

Existing Site Plan

Page 5

BUILDING SETBACKBUILDING SETBACK

EntryEntry

Entry / ExitEntry / Exit

Entry / ExitEntry / Exit

EXISTING EXISTING SCHOOLSCHOOL

EXISTING FIELDSEXISTING FIELDS

PROPERTY LINEPROPERTY LINE

TILDEN LANETILDEN LANE

MA

RCLI

FF R

OA

D

MA

RCLI

FF R

OA

DCU

SHM

AN

ROA

D

CUSH

MA

N RO

AD

MMARCLIFF ROAD

ARCLIFF ROAD

Page 25: Rock Terrace School and Tilden Middle School€¦ · Preliminary Plans Presentation Rock Terrace School and Tilden Middle School Revitalization / Expansion Project 6300 Tilden Lane,

Rock Terrace School and Tilden Middle School - Revitalization / Expansion Project

Associates, PC

Proposed Site Plan

Page 5A

BUILDING SETBACKBUILDING SETBACK

PARKING (130)PARKING (130)

PARKING PARKING

(75)(75)

DROP OFF (30)DROP OFF (30)

DROP DROP OFF (4)OFF (4)

GARDENGARDEN

BUSE

S (2

0)BU

SES

(20)

3 STORY3 STORY

2 STORY2 STORY1 STORY1 STORY

SITE SITE ACCESSACCESS

SITE ACCESSSITE ACCESSAND EXITAND EXIT

SITE ACCESS SITE ACCESS AND EXITAND EXIT

SOFTBALLSOFTBALL

FUTURE FUTURE RELOCATABLERELOCATABLECLASSROOMSCLASSROOMS

FUTURE FUTURE ADDITIONADDITION

SOCCERSOCCERSOCCERSOCCER

SOFTBALLSOFTBALLTENNISTENNIS

360PROPERTY LINEPROPERTY LINE

TILDEN LANETILDEN LANE

MA

RCLI

FF R

OA

D

MA

RCLI

FF R

OA

D

CUSH

MA

N RO

AD

CUSH

MA

N RO

AD

MMARCLIFF ROAD

ARCLIFF ROAD

T

RT

EXITEXIT

4’ WALL4’ WALL

2’ WALL

2’ WALL

BASKETBALLBASKETBALL356.5

356.5354

Page 26: Rock Terrace School and Tilden Middle School€¦ · Preliminary Plans Presentation Rock Terrace School and Tilden Middle School Revitalization / Expansion Project 6300 Tilden Lane,

Rock Terrace School and Tilden Middle School - Revitalization / Expansion Project

Associates, PC

Page 6

N

Existing First Floor Plan

GYM

AUX. GYM

STAGE

KITCHEN

OFFICES & STORAGE V. ED.

HEALTH

DINING

MUSIC

CHOIR

V. ED.

V. ED.

ARTLAB

SCI.

SCI.

SCI.

SCI.

LAB

ARTADMIN.

SPEC.ED.

SPEC.ED.

GUIDANCE

ADMINISTRATIONAUXILIARY GYMNASIUMELECTRICALENGLISHEXTERIOR EQUIPMENTGYMNASIUMSCIENCE LABLANGUAGESLIBRARY MEDIA CENTERSCIENCESOCIAL STUDIESSPECIAL EDUCATIONSTORAGEVOCATIONAL EDUCATION

ADMINAUX GYMELECENGEXT EQUIPGYMLABLANGLMCSCISOCSPEC EDSTOV ED

BOILER

EXT. EQUIP. STO.

OFFICES

STORAGE

GIRL’S LOCKER & SHOWERS

BOY’S LOCKER & SHOWERS

UNEXCAVATED

ELEC.

RECEIVING

PARTIAL BASEMENT LEVELBU

S LO

OP

STUDENT DROP

SERVICEYARD

Page 27: Rock Terrace School and Tilden Middle School€¦ · Preliminary Plans Presentation Rock Terrace School and Tilden Middle School Revitalization / Expansion Project 6300 Tilden Lane,

Rock Terrace School and Tilden Middle School - Revitalization / Expansion Project

Associates, PC

350

350

360

360

D D

Proposed First Floor Plan

Page 6A

N

40. ESOL41. Special Educa on Team Room42. Special Educa on Resource Room43. Develop. Reading/Math Intervent. 44. Instruc onal Media Center45. Mul media Produc on Room46. Staff Room47. Greenhouse48. Home Survival Classroom49. Work Offi ce Skills Lab50. Outdoor Storage51. Culinary Arts Lab52. Restaurant

ElevatorST StairsT ToiletG Girl’s ToiletB Boy’s Toilet

1. Administra on Suite2. Work Room3. Conference Room4. Guidance Suite5. Security Ves bule6. Health Services Suite7. LFI Classroom8. Accomoda ons Room9. Health Classroom10. Aspergers’ Classroom11. Science Laboratory12. Science Prep Room13. Mechanical14. Storage15. Classroom16. Security Offi ce17. Gymnasium Storage18. Auxiliary Gymnasium19. Laundry20. Gymnasium21. Locker Room22. Physical Educa on Offi ce23. Art Room24. Kiln Room25. Music Suite26. Music Offi ce27. School Store28. Student Dining29. Stage30. Kitchen31. Building Service32. Team Resource Workroom33. Technology Laboratory34. Mul purpose Laboratory35. Computer Laboratory36. Telecom Room37. Chemical Storage38. Speech and Language Support39. Occupa onal/Physical Therapy

BUS

LOO

P

PARKING

STU

DEN

T DR

OP

STUDENT DROP

SERVICEYARD

GARDEN

ROCK TERRACE ENTRANCE

ACTIVITIESENTRANCE

FUTURE ADDITION

COURTYARD

COURTYARD

TILDENENTRANCE

2

1111

15

3

4

6

1

2

2521

222222

19

20

20

15

1521

28

28

29

30

10

10

15

15 15

13 31

2122

21

1717

14

14

14

14

14

1417

1717

29

25

48

48

49

7 7

47

2526 32

32

32

27

27

ST

ST

ST

ST

ST

ST

15

15

15

15

15T

T

T

T

T T

T T

T

T

15

T41

8

16

3

3

3

3

5

12

46

46

B

B

B

B

B

G

G

G

G

G

38393839

3839

505050

5152

14

14

14

14

14

14

Page 28: Rock Terrace School and Tilden Middle School€¦ · Preliminary Plans Presentation Rock Terrace School and Tilden Middle School Revitalization / Expansion Project 6300 Tilden Lane,

Rock Terrace School and Tilden Middle School - Revitalization / Expansion Project

Associates, PC

Page 7

N

Existing Second Floor Plan

ROOF

ROOF

LMCSOC.

SOC.

SOC.

SOC.SOC.

SOC.

MATH

MATH

MATH MATH

ENG.ENG.

ENG.

ENG.ENG.

LANGLANG

LANG

LANG

ADMINISTRATIONAUXILIARY GYMNASIUMELECTRICALENGLISHEXTERIOR EQUIPMENTGYMNASIUMSCIENCE LABLANGUAGESLIBRARY MEDIA CENTERSCIENCESOCIAL STUDIESSPECIAL EDUCATIONSTORAGEVOCATIONAL EDUCATION

ADMINAUX GYMELECENGEXT EQUIPGYMLABLANGLMCSCISOCSPEC EDSTOV ED

Page 29: Rock Terrace School and Tilden Middle School€¦ · Preliminary Plans Presentation Rock Terrace School and Tilden Middle School Revitalization / Expansion Project 6300 Tilden Lane,

Rock Terrace School and Tilden Middle School - Revitalization / Expansion Project

Associates, PC

Proposed Second Floor Plan

Page 7A

COURTYARD BELOW

OPEN TOBELOW

OPEN TOBELOW

OPEN TOBELOW

COURTYARD BELOW

ROOF BELOW

ROOF BELOW

ROOF BELOW

ROOF BELOW

GYMBELOW

GYMBELOW

FUTURE ADDITION

15

15

15

15 15

10

15

15

15

15

18

18

9

15

10

15 15

15

15

15

23

11 1112

ST

ST

24

15

15

15

15

1511

TT

36

T

ST

ST

ST

23

TT

3335

34814

14

TG

G

G

G

B

B

B

B

14

14

41

40

17

17

17

ST

14

14

14

12

45

44

44

18

N

40. ESOL41. Special Educa on Team Room42. Special Educa on Resource Room43. Develop. Reading/Math Intervent. 44. Instruc onal Media Center45. Mul media Produc on Room46. Staff Room47. Greenhouse48. Home Survival Classroom49. Work Offi ce Skills Lab50. Outdoor Storage51. Culinary Arts Lab52. Restaurant

ElevatorST StairsT ToiletG Girl’s ToiletB Boy’s Toilet

1. Administra on Suite2. Work Room3. Conference Room4. Guidance Suite5. Security Ves bule6. Health Services Suite7. LFI Classroom8. Accomoda ons Room9. Health Classroom10. Aspergers’ Classroom11. Science Laboratory12. Science Prep Room13. Mechanical14. Storage15. Classroom16. Security Offi ce17. Gymnasium Storage18. Auxiliary Gymnasium19. Laundry20. Gymnasium21. Locker Room22. Physical Educa on Offi ce23. Art Room24. Kiln Room25. Music Suite26. Music Offi ce27. School Store28. Student Dining29. Stage30. Kitchen31. Building Service32. Team Resource Workroom33. Technology Laboratory34. Mul purpose Laboratory35. Computer Laboratory36. Telecom Room37. Chemical Storage38. Speech and Language Support39. Occupa onal/Physical Therapy

32

32 32

Page 30: Rock Terrace School and Tilden Middle School€¦ · Preliminary Plans Presentation Rock Terrace School and Tilden Middle School Revitalization / Expansion Project 6300 Tilden Lane,

Associates, PC

This page intentionally left blank

Page 31: Rock Terrace School and Tilden Middle School€¦ · Preliminary Plans Presentation Rock Terrace School and Tilden Middle School Revitalization / Expansion Project 6300 Tilden Lane,

Rock Terrace School and Tilden Middle School - Revitalization / Expansion Project

Associates, PC

Proposed Third Floor Plan

Page 8A

COURTYARD BELOW

ROOF BELOW

ROOF BELOW

ROOF BELOW

ROOF BELOW

ROOF BELOW

ROOF BELOW

ROOF BELOWROOF

BELOW

GYMBELOW

COURTYARD BELOW

FUTURE ADDITION

15

15

15

15

15

15

15

15

15

10

ST

ST

ST

15 15 15 15

42

1111

11 11

141414

12

4343 8 14

37

12

N

40. ESOL41. Special Educa on Team Room42. Special Educa on Resource Room43. Develop. Reading/Math Intervent. 44. Instruc onal Media Center45. Mul media Produc on Room46. Staff Room47. Greenhouse48. Home Survival Classroom49. Work Offi ce Skills Lab50. Outdoor Storage51. Culinary Arts Lab52. Restaurant

ElevatorST StairsT ToiletG Girl’s ToiletB Boy’s Toilet

1. Administra on Suite2. Work Room3. Conference Room4. Guidance Suite5. Security Ves bule6. Health Services Suite7. LFI Classroom8. Accomoda ons Room9. Health Classroom10. Aspergers’ Classroom11. Science Laboratory12. Science Prep Room13. Mechanical14. Storage15. Classroom16. Security Offi ce17. Gymnasium Storage18. Auxiliary Gymnasium19. Laundry20. Gymnasium21. Locker Room22. Physical Educa on Offi ce23. Art Room24. Kiln Room25. Music Suite26. Music Offi ce27. School Store28. Student Dining29. Stage30. Kitchen31. Building Service32. Team Resource Workroom33. Technology Laboratory34. Mul purpose Laboratory35. Computer Laboratory36. Telecom Room37. Chemical Storage38. Speech and Language Support39. Occupa onal/Physical Therapy

T

T T

TG

G

B

B 40

32

Page 32: Rock Terrace School and Tilden Middle School€¦ · Preliminary Plans Presentation Rock Terrace School and Tilden Middle School Revitalization / Expansion Project 6300 Tilden Lane,

Rock Terrace School and Tilden Middle School - Revitalization / Expansion Project

Associates, PC

Existing Elevations

Page 9

East Elevation

West Elevation

North Elevation

South Elevation 0’ 40’ 80’

Page 33: Rock Terrace School and Tilden Middle School€¦ · Preliminary Plans Presentation Rock Terrace School and Tilden Middle School Revitalization / Expansion Project 6300 Tilden Lane,

Rock Terrace School and Tilden Middle School - Revitalization / Expansion Project

Associates, PC

Proposed Elevations

Page 9A

East Elevation

West Elevation

North Elevation

South Elevation 0’ 40’ 80’

Page 34: Rock Terrace School and Tilden Middle School€¦ · Preliminary Plans Presentation Rock Terrace School and Tilden Middle School Revitalization / Expansion Project 6300 Tilden Lane,

This page intentionally left blank

Page 35: Rock Terrace School and Tilden Middle School€¦ · Preliminary Plans Presentation Rock Terrace School and Tilden Middle School Revitalization / Expansion Project 6300 Tilden Lane,

Rock Terrace School and Tilden Middle School - Revitalization / Expansion Project

Associates, PC

Project Team, Schedule, and Estimated Construction Costs

Page 10

Design Team Member

Architect: Civil Engineer:Mechanical/Electrical/Plumbing Engineer:Structural Engineer:Kitchen Consultant:

Project Schedule

Preliminary Plans Presentation:Construction Documents Completed:Award Construction Contract:Building Completed:

Estimated Construction Costs

New Building:

Construction Cost Estimate for Buildingand Site:

Samaha Associates, P.C.Adtek Engineers, Inc.James Posey Associates Rathgeber/Goss AssociatesNyikos Associates, Inc.

May 2017April 2018July 2018June 2020

242,565 square feet

$70,000,000