B26 F - B26XL F BOOM
Page 1
SANDVIK TAMROCK SECOMA S.A.S19 avenue De Lattre-de-Tassigny - ZIB.P. 46 - 69881 MEYZIEU CedexTel : (33) 472 45 22 00 Fax : (33) 478 31 79 80
MAINTENANCE MANUAL
Page 2 E-04-07-2005 SR-MC-FLB26 F - B26XL F BOOM
SANDVIK TAMROCK SECOMA S.A.S19 avenue De Lattre-de-Tassigny - ZIB.P. 46 - 69881 MEYZIEU CedexTel : (33) 472 45 22 00 Fax : (33) 478 31 79 80
1 PRELIMINARY REMARKS 3
1/1 SAFETY 3
1/2 ABOUT THIS BOOKLET 5
2 DESCRIPTION 6
2/1 EXPLANATION 6
2/2 FEATURES 6
2/3 MAIN COMPONENTS 7
3 MAINTENANCE OPERATIONS 8
3/1 FIRST ENTRY INTO SERVICE 8
3/2 OPERATIONS AT EACH SHIFT 8
3/3 50-HOURS OR WEEKLY OPERATIONS 8
3/4 200-HOURS OPERATIONS 9
3/5 1200-HOURS OR ANNUAL OPERATIONS 9
3/6 3600-HOURS OPERATIONS OVERALL INSPECTION AND RECONDITIONING 9
4 TIGHTENING TORQUES 10
5 LUBRICATION 11
6 OPERATING METHODS 12
6/1 REMOVING AND REFITTING A EXPENDABLE PIN SET. 12
6/2 CHECKING CYLINDER EXPENDABLE PIN 13
6/3 REMOVING AND REFITTING A CYLINDER 14
6/4 REMOVING AND REFITTING A BOOM ASSEMBLY 14
6/5 REMOVING AND REFITTING ROTARY ACTUATOR 15
7 CHECK AND ADJUSTMENT 15
7/1 HOSE CONDITION CHECK 15
7/2 CHECK WELDING CONDITION USING CRACK DETECTOR PRODUCTS 15
7/3 CONTROL/ADJUSTMENT OF CLEARANCE BETWEEN ARMATURE AND EXTENSION TUBE 16
7/4 CONTROL THE WEAR OF THE EXTENSION TUBE 17
7/5 DISMANTLE THE BOOM EXTENSION CYLINDER 17
8 LIFTING - HANDLING 18
9 PERIODIC MAINTENANCE TABLE - B26 F AND B26XL F BOOM 19
Page 3E-04-07-2005 SR-MC-FL B26 F - B26XL F BOOM
SANDVIK TAMROCK SECOMA S.A.S19 avenue De Lattre-de-Tassigny - ZIB.P. 46 - 69881 MEYZIEU CedexTel : (33) 472 45 22 00 Fax : (33) 478 31 79 80
1 PRELIMINARY REMARKS
1/1 SAFETY
The informations contained in this manual must be studied and thoroughly assimilated before
undertaking any maintenance work on the equipment
WARNING Operation, maintenance and adjustments are only allowed to persons withspecific training in operation and maintenance of the equipment. Read the operatingand maintenance instructions before using or servicing the equipment.
WARNING: Before starting any maintenance operation ensure that the machine is in asafe location with good safety, ventilation and lighting conditions. Ensure that liftingequipments and pedestals are compatible with elements’ weight. Follow all the safetyinstructions and ware safety protections as gloves, goggle, helmet, safety boots, earprotectors.
WARNING: Before any operation stabilize and fix steadily all the elements on suitablepedestals. Stop the power packs, switch the general power breaker. Place a tag or aboard to warn other members of the personnel that maintenance work on the machineis in progress.
WARNING: Pressurized oil jets could cause severe injuries. Before any operation onhydraulic circuit, STOP the power packs and release remaining pressure incomponents by operating hydraulic control levers several times. Always release thestatic pressure in cylinders before disassemble them.NEVER WORK ON AN OPERATING CIRCUIT.
WARNING: While tests are in progress, do not allow any other member of thepersonnel to stand in the area surrounding the machine. Stay at the control station tobe able to stop the movement and switch off the power pack.
WARNING: Maintenance, adjustment and repairs are restricted to qualified personnelwith special training for the particular equipment. Always read the instructions carefullybefore starting any maintenance work.
CAUTION: Always use suitable tools and work in a clean place when dismantling andassembling hydraulic components. After removing cylinders the hydraulic inlet/outletports must be plugged to prevent dirt and air intrusion during operation.
WARNING: The operator must always wear required personal protection, such as safetyhelmet, protective overall, safety boots, hearing protectors, safety goggles etc.
WARNING: Danger of high pressure oil jets.High pressure oil jets can cause serious personal injuries.Release the pressure in the hydraulic circuits before opening caps or connections.(Accumulator, Cylinder and Hydraulic circuit)
Remember: SAFETY FIRST!Always observe the warnings accompanied by the following symbols.
WARNING
WARNING
WARNING
WARNING
WARNING
Page 4 E-04-07-2005 SR-MC-FLB26 F - B26XL F BOOM
SANDVIK TAMROCK SECOMA S.A.S19 avenue De Lattre-de-Tassigny - ZIB.P. 46 - 69881 MEYZIEU CedexTel : (33) 472 45 22 00 Fax : (33) 478 31 79 80
WARNING: Danger of hot surface.Hot surface can cause serious injuries.Components rod, shank or hydraulic component can be hot and beforestarting a maintenance work, please let them cool off. The operator must have adequate wears as gloves.
WARNING: Crushing hazard : do not stay in dangerous area, for instance: centralarticulation, front chassis and rear chassis.
WARNING
SAFETY
Do not attempt any such repairs or adjustments that you do not fullyunderstand.
ABOUT THE SAFETY OF REPAIRS
Certain workstages require the use of the feed mechanism during the repair.Make sure then that:
- no danger is caused to anybody.- the machine can be immediately stopped when necessary.- the powerpack is stopped again before the repair-work is continued.
Before starting any repair-work move away from the area where you have justdrilled.
Use proper tools.
Always wear protective clothing, eye protection, earmuffs, safety footwear, andother safety equipment required by the work.
Always follow the marked safety instructions, andobserve caution while working.
The following safety instructions are general rules.
Keep tools and drillingequipment clean.
Page 5E-04-07-2005 SR-MC-FL B26 F - B26XL F BOOM
SANDVIK TAMROCK SECOMA S.A.S19 avenue De Lattre-de-Tassigny - ZIB.P. 46 - 69881 MEYZIEU CedexTel : (33) 472 45 22 00 Fax : (33) 478 31 79 80
1/2 ABOUT THIS BOOKLET
The present manual is destined for the use of personnel in charge of carrying out, servicing and maintenance operations on Jumbos.
It contains maintenance operations schedule and operating methods concerning the main elements of
the B26 F - B26XL F BOOM.
Note that servicing and maintenance operations must be carried out by personnel with the required
qualifications, technical knowledge, and proper training on the machine.
Page 6 E-04-07-2005 SR-MC-FLB26 F - B26XL F BOOM
SANDVIK TAMROCK SECOMA S.A.S19 avenue De Lattre-de-Tassigny - ZIB.P. 46 - 69881 MEYZIEU CedexTel : (33) 472 45 22 00 Fax : (33) 478 31 79 80
2 DESCRIPTION
2/1 EXPLANATION
B26 F - B26XL F BOOM are multidirectional and telescopic booms fitted with an hydraulic parallelism
system. They can be used for face, wall, roof or floor drilling and for initiating cross-cuts, by swinging
the drill feed through a combination of 8 movements.
B26 F boom can extend with a 1200mm translation ( motion 3 ).
B26XL F boom can extend with a 1700mm translation ( motion 3 ).
2/2 FEATURES
SEE ENCLOSED TECHNICAL DATA SHEET.
1
2
3
4 5
6
78
Page 7E-04-07-2005 SR-MC-FL B26 F - B26XL F BOOM
SANDVIK TAMROCK SECOMA S.A.S19 avenue De Lattre-de-Tassigny - ZIB.P. 46 - 69881 MEYZIEU CedexTel : (33) 472 45 22 00 Fax : (33) 478 31 79 80
2/3 MAIN COMPONENTS
The boom is fixed to the chassis by the boom swing cradle 1.
The extension tube 8 slides in the armature tube 4 driven by the cylinder situated inside the armature.
The boom movements are controlled by the cylinders 2 and 3.
The rotation of the drill feed in relation to the boom’s axis is make wiht the rotary actuator 5 allows 360..
The drill feed support 7 is fitted with a feed cylinder 6. The cylinder 9 makes the divergency movement.
Hydraulic parallelism system enable to keep a constant drill feed’s direction while swinging the boom
on both vertical and horizontal motions. Parallelism by a vertical plane is obtained with an hydraulic link
between the master lifting cylinder 3 and the slave cylinder 10.
Parallelism by a horizontal plane is obtained with an hydraulic link between the master cylinder 11 and
the slave cylinder 12.
NOTE: The master cylinder 11 is not powered, its purpose is only to acquire boom swinging
movements and keep parallelism.
The articulations are featured with adjustable expendable pin sets.
12
3
5
67
8
9
4
10 11
12
Page 8 E-04-07-2005 SR-MC-FLB26 F - B26XL F BOOM
SANDVIK TAMROCK SECOMA S.A.S19 avenue De Lattre-de-Tassigny - ZIB.P. 46 - 69881 MEYZIEU CedexTel : (33) 472 45 22 00 Fax : (33) 478 31 79 80
3 MAINTENANCE OPERATIONS
CAUTION: The safety of users and the reliability of the boom depend on the maintenance operations
and imply the use of genuine SANDVICK TAMROCK SECOMA spare parts.
All defective parts must be immediately replaced.
WARNING: Maintenance, adjustment and repairs are restricted to qualified personnel with special training for the particular equipment. Always read the instructions carefully before starting any maintenance work.
WARNING: While tests are in progress, do not allow any other member of the personnel to stand in the area surrounding the machine. Stay at the control station to be able to stop the movement and switch off the power pack.
3/1 FIRST ENTRY INTO SERVICE
After 20 working hours or 1 week of service, check all the screws and tighten all the expendable pin.
3/2 OPERATIONS AT EACH SHIFT
Before starting up:
• Check that there is no obstruction to hinder the movement of the boom.
• Check the overall condition of the equipment (cylinders, hoses, tube, hydraulic unions,...).
• Search for leaks.
• Check the extension tube.
• Lubricate all the grease points. It is important to check that the rotary actuators grease discharge
valves are working properly.
After starting up:
• Move on handle the boom to check that it moves freely and operates correctly. Movement should be
regular and smooth.
3/3 50-HOURS OR WEEKLY OPERATIONS
• Check that there is no obstruction to hinder the movement of the boom.
• Check the overall condition of the equipment (cylinders, hoses, tube, hydraulic unions,...).
• Search for leaks.
• Check the extension tube.
• Lubricate all the grease points.It is important to check that the rotary actuator grease discharge
valves are working properly.
• Check the tightening torque of the cylinders and articulation’s expendable pin.
WARNING
WARNING
Page 9E-04-07-2005 SR-MC-FL B26 F - B26XL F BOOM
SANDVIK TAMROCK SECOMA S.A.S19 avenue De Lattre-de-Tassigny - ZIB.P. 46 - 69881 MEYZIEU CedexTel : (33) 472 45 22 00 Fax : (33) 478 31 79 80
3/4 200-HOURS OPERATIONS
• Carry out the 50-hours operations again.
• Check clearance between the boom extension tube and armature. Check the condition of the plastic
skids.
3/5 1200-HOURS OR ANNUAL OPERATIONS
• Check the overall condition of the equipment.
CAUTION: Check welding condition using crack detector products.
• Search for leaks.
• Check the condition of the hydraulic equipments (cylinders, hoses, hydraulic unions,...).
• Check the extension tube. Lubricate it.
• Lubricate all the grease points.It is important to check that the rotary actuator grease discharge
valves are working properly.
• Check the tightening torque of the cylinders and articulations’ expendable pin.
3/6 3600-HOURS OPERATIONS OVERALL INSPECTION AND RECONDITIONING
• Remove the boom assembly.
• Remove, dismantle and check the different parts. Remove all worn or defective parts.
• Change the seals, (bronze washers),washers and extension tube guide skids.
• Reassemble the boom.
• Test for correct operation.
NB: You can recover all these operations in the periodic maintenance table (last page of this manual)
we invite you to use this document.
Page 10 E-04-07-2005 SR-MC-FLB26 F - B26XL F BOOM
SANDVIK TAMROCK SECOMA S.A.S19 avenue De Lattre-de-Tassigny - ZIB.P. 46 - 69881 MEYZIEU CedexTel : (33) 472 45 22 00 Fax : (33) 478 31 79 80
4 TIGHTENING TORQUES
For basic genuine SANDVIK TAMROCK SECOMA™ screws and nut use the following tightening
torque:
metric dimension torque in Nm HEX BOLTSGRADE 8.8
torque in Nm “SIX CUT HOLLOW”
BOLTSGRADE 12.9
M6M8M10M12M14M16M18M20M22M24M27M33M36M39M42
10255085
13020028040053067010001780230030003700
164080140210330460650880113016502200385050506250
800
600 800
800
Tightenning torques of expendable pins, see page 13
400
Page 11E-04-07-2005 SR-MC-FL B26 F - B26XL F BOOM
SANDVIK TAMROCK SECOMA S.A.S19 avenue De Lattre-de-Tassigny - ZIB.P. 46 - 69881 MEYZIEU CedexTel : (33) 472 45 22 00 Fax : (33) 478 31 79 80
5 LUBRICATION
Use Mobilith SHC 220, Mobilgrease HP 222 or equivalent.
GREASE POINTS
There is a grease nipple on any expendable pin. There is two grease nipples at each end of any rotary
actuator.
• CAUTION: Check that the rotary actuator grease discharge valves are working properly. They are
situated at the opposite side of each grease nipple. Those valves must release excess grease to avoid over-pressure and over-stress on actuator’s seals and flanges.
.Remove fautly valves
Page 12 E-04-07-2005 SR-MC-FLB26 F - B26XL F BOOM
SANDVIK TAMROCK SECOMA S.A.S19 avenue De Lattre-de-Tassigny - ZIB.P. 46 - 69881 MEYZIEU CedexTel : (33) 472 45 22 00 Fax : (33) 478 31 79 80
6 OPERATING METHODS
WARNING: Before starting any maintenance operation ensure that the machine is in a safe location with good safety, ventilation and lighting conditions. Ensure that lifting equipments and pedestals are compatible with elements’ weight. Follow all the safety instructions and ware safety protections as gloves, goggle, helmet, safety boots, ear protectors.
WARNING: Maintenance, adjustment and repairs are restricted to qualified personnel with special training for the particular equipment. Always read the instructions carefully before starting any maintenance work.
6.1 REMOVING AND REFITTING ARTICULATION EXPENDABLE PIN SET.
Before removal :
• Lift or stand parts with adapted devices.
• Release static pressure in hydraulic circuit and cylinders.
• NOTE : Expendable blocking cones are not re-usable then you must manage their exchangebefore removing them.
• Grease all parts.
• Centre the expendable pin in its housing
• Position spacers, expendable blocking cone and caps.
• Torque tighten the screw according to the diameter (See specific tightening torques).
• Operate several movement cycles and retighten the screw.
• Check an retighten at weekly operation maintenance
session.
WARNING
Page 13E-04-07-2005 SR-MC-FL B26 F - B26XL F BOOM
SANDVIK TAMROCK SECOMA S.A.S19 avenue De Lattre-de-Tassigny - ZIB.P. 46 - 69881 MEYZIEU CedexTel : (33) 472 45 22 00 Fax : (33) 478 31 79 80
6/2 CHECKING CYLINDER EXPENDABLE PIN
The cylinder axis are expendable pin that are tightened without clearance to the bracket.
Check the tightening torque. The correct values are as follows :
Check the position of the cut in the expendable pin. the cut must be at 90° to the cylinder’s direction of
movement, see if the expendable pin is carfully lubricate before installing.
When a cylinder is removed, make sure that no part of the boom is left unsuported
TIGHTENING TORQUE OF THE CYLINDER EXPENDABLE PIN
SIZE OF CYLINDER AXIS USING TORQUE WRENCH USING PNEUMATIC TOOL
M 12 60 Nm 55 Nm
M 16 150 Nm 135 Nm
M 20 290 Nm 270 Nm
M 24 530 Nm 490 NM
BRACKETBRACKETEAR
CYLINDER
Page 14 E-04-07-2005 SR-MC-FLB26 F - B26XL F BOOM
SANDVIK TAMROCK SECOMA S.A.S19 avenue De Lattre-de-Tassigny - ZIB.P. 46 - 69881 MEYZIEU CedexTel : (33) 472 45 22 00 Fax : (33) 478 31 79 80
6/3 REMOVING AND REFITTING A CYLINDER
Removal:
• Lift or stand the boom with adapted devices to prevent a sudden fall of moving parts when operating
decompression.
• WARNING: Stop power packs and proceed an hydraulic circuit decompression.
• Disconnect hydraulic hoses and plug the inlet/outlet ports of the cylinder.
• Fasten the cylinder to prevent it’s fall.
• Remove expendable pin sets.
Refitting:
• Place the cylinder’s rear knuckle in the yoke, insert the expendable pin set and screw. Do not fully
tighten.
• Adjust rod extension to place the front knuckle on the other yoke. Insert axis set. Tighten both of them
(See "tightening torques" page 10).
• Reconnect hoses.
• Pressurize the circuit, bleed and test.
WARNING: While tests are in progress, do not allow any other member of the personnel to stand in the area surrounding the machine. Stay at the control station to be able to stop the movement and switch off the power pack.
For more informations about the cylinders mounting, see the cylinder maintenance manual in SECTION 1.
6/4 REMOVING AND REFITTING A BOOM ASSEMBLY
Removal :
• Line up the boom horizontally and align it with expendable pin.
• Remove the drill feed assembly.
• Sling boom.
• Stop the power pack and release remaining pressure in hydraulic components and hoses by
operating control levers several times.
• Disconnect hydraulic hoses and plug the inlet/outlet ports.
• Remove the boom swing cylinder.
• Extract swinging expendable pin set and remove the boom.
Refitting :
• Check elements condition, replace if necessary.
• Assemble and lubricate elements.
• Connect hoses.
• Bleed and breeze hydraulic circuit.
• Proceed tests.
WARNING
Page 15E-04-07-2005 SR-MC-FL B26 F - B26XL F BOOM
SANDVIK TAMROCK SECOMA S.A.S19 avenue De Lattre-de-Tassigny - ZIB.P. 46 - 69881 MEYZIEU CedexTel : (33) 472 45 22 00 Fax : (33) 478 31 79 80
6/5 REMOVING AND REFITTING ROTARY ACTUATOR
Removal:
• WARNING: Stop the power packs and proceed an hydraulic circuit decompression.
• Before removal mark the relative position of boom’s elements with actuator’s flanges.
• Sling or stand the elements with adapted devices to prevent a sudden fall of moving parts.
• Disconnect hydraulic hoses and plug the inlet/outlet ports.
• Secure an fasten the rotary actuator to prevent it’s fall.
• Remove it.
Refitting:
• Check expendable pin play, and adjust if necessary.
• Exchange all flanges screws.
• Apply LOCTITE ADHESIVE 317 on surfaces.
• Torque tighten flanging screws.
For more informations about the cylinders mounting, see the cylinder maintenance manual in SECTION 1.
7 CHECK AND ADJUSTMENT
7/1 HOSE CONDITION CHECK
Oil leakages may involve reliability and safety problems, it is imperative to exchange leaking elements immediately.
WARNING: Pressurized oil jets could cause severe injuries. Before any operation on hydraulic circuit, STOP the power packs and release remaining pressure in components by operating hydraulic control levers several times. Always release the static pressure in cylinders before disassemble them. NEVER WORK ON AN OPERATING CIRCUIT.
7/2 CHECK WELDING CONDITION USING CRACK DETECTOR PRODUCTS
Stress, vibrations, impacts, corrosive agents could cause invisible cracks in weldings.Then it is
extremely important to checks them in order to prevent breakdowns, accidents and injuries risks.
WARNING
Page 16 E-04-07-2005 SR-MC-FLB26 F - B26XL F BOOM
SANDVIK TAMROCK SECOMA S.A.S19 avenue De Lattre-de-Tassigny - ZIB.P. 46 - 69881 MEYZIEU CedexTel : (33) 472 45 22 00 Fax : (33) 478 31 79 80
7/3 CONTROL/ADJUSTMENT OF CLEARANCE BETWEEN ARMATURE AND EXTENSION TUBE
Gap check
• Line up the boom horizontally and align it with jumbo’s axis.
• remove plate 1 and dust seal 2.
• Fully extend the tube and clean it.
• Gauge the gap A between tube and armature.
• Sling the end of the tube and raise it.
• Gauge the gap B between tube and armature.
• The clearance between the tube and the armature is
estimated as following:
Skids’s clearance: J= A - B
CAUTION:
MAXIMUM CLEARANCE J= 2mm
Clearance adjustment
Untie and let the boom rest by its own weight then
remove plate, shims and skids LOWER2 and UPPER1.
• Measure the skid’s thickness, it must be above 27 mm.
• Measure the shims + skid stack, it must be above 37 mm
Minimum thickness of all the skids = 27mm
Minimum thickness of shims + skid stack = 37mm
• Replace all the 16 skids if one reaches the minimum thickness.
• It will be helpful to note for the next step: the thickness value of LOWER2 and UPPER1 stacks.
Maximum thickness difference between LOWER2 & UPPER1 stacks must not exceed 3mm.
UPPER1UPPER2
LOWER1LOWER2
LEFT1
LEFT2
RIGHT1
RIGHT2
2
1
Jeu A
Jeu B
GAP A
GAP B
Page 17E-04-07-2005 SR-MC-FL B26 F - B26XL F BOOM
SANDVIK TAMROCK SECOMA S.A.S19 avenue De Lattre-de-Tassigny - ZIB.P. 46 - 69881 MEYZIEU CedexTel : (33) 472 45 22 00 Fax : (33) 478 31 79 80
• Reassemble LOWER2 & UPPER1 shims and skids and affix plates.
• Sling the end of the tube and raise it. Remove LOWER1 & UPPER2 skids.
• Check skids condition and replace if they are beyond limits.
• Adjust shim stack in order to have the same thickness for LOWER1 & LOWER2. Then Adjust shim
stack in order to have the same thickness for UPPER1 & UPPER2.
This levelling ensure a good parallelism between tube and armature axis.
• Refit all parts and check J clearance, if it stays beyond limit value put shims on UPPER1 & UPPER2
stacks. (there are two type of shims: 0.5mm and 1mm).
NOTE: Tighten plates screws at 150Nm torque.
• Lubricate tube and proceed following tests:
Extend and retract tube in horizontal position. Gauge hydraulic operating pressure needed in cylinder
while operating backward and forward movements.
Max. pressure for forward translation: 120bar
Max. pressure for backward translation: 180bar
• In overpressure situation, free the tube translation by removing a 0.5mm shim in UPPER1 & UPPER2
stacks.
Proceed similar operations for lateral clearance adjustment.
7/4 CONTROL THE WEAR OF THE EXTENSION TUBE
Check the extension tube wear on the
contact area with skids. Wear must not
be superior to 1,5 mn.
7/5 DISMANTLE THE BOOM EXTENSION CYLINDER
The boom extension cylinder is inside the armature tube, and is fixed to the armature tube and to the
extension tube. To remove is cylinder you must have to take off the boom from the machine’s frame.
The figure show you the lay-out of the screws used to fixe the cylinder to the armature tube (Detail A).
A
A
SECTION A-ASECTION A-A
1,5mn
1,5mn
DETAIL A
Page 18 E-04-07-2005 SR-MC-FLB26 F - B26XL F BOOM
SANDVIK TAMROCK SECOMA S.A.S19 avenue De Lattre-de-Tassigny - ZIB.P. 46 - 69881 MEYZIEU CedexTel : (33) 472 45 22 00 Fax : (33) 478 31 79 80
8 LIFTING - HANDLING
LIFTING POINTS.
WARNING: WARNING: Before starting any maintenance operation ensurethat the machine is in a safe location with good safety, ventilation andlighting conditions. Ensure that lifting equipments and pedestals arecompatible with elements’ weight. Follow all the safety instructions andware safety protections as gloves, goggle, helmet, safety boots, earprotectors.
• WARNING: Check ties you use, they must be in good condition and fit the weight of the assembly
you are going to lift.
• Fasten correctly the elements before starting operations.
NO
YES
YES
NO
NONO
Page 19E-04-07-2005 SR-MC-FL B26 F - B26XL F BOOM
SANDVIK TAMROCK SECOMA S.A.S19 avenue De Lattre-de-Tassigny - ZIB.P. 46 - 69881 MEYZIEU CedexTel : (33) 472 45 22 00 Fax : (33) 478 31 79 80
9 PERIODIC MAINTENANCE TABLE - B26 F - B26XL F BOOM
BOOMFREQUENCY (PERCUSSION HOURS)
When completed
Daily 50 200 600 1200 1800 2400 3600Y
yesNno
All tightenning torques
All grease points
All weldings
Leakage
All equipments condition
Freedom and condition of moooving parts
Hoses / Union / Fitting
Extension tube
Dust seal
Skids (clearence between skids and tube)
Rotary actuator discharge valves
Rotary actuator flanges screw (tightening torque and axial play)
Overal inspection :
Remove the boom from the machine / Wash and check all the assembly / Exchange all worn out parts / Test the boom.
CHECKTEST
CLEANFLUSH
LUBRICATE SERVICECHANGEREPLACE
Page 20 E-04-07-2005 SR-MC-FLB26 F - B26XL F BOOM
SANDVIK TAMROCK SECOMA S.A.S19 avenue De Lattre-de-Tassigny - ZIB.P. 46 - 69881 MEYZIEU CedexTel : (33) 472 45 22 00 Fax : (33) 478 31 79 80
Technical Specification
B 26 F Boom4-200 S-C2003-10-21
APPLICATION
B 26 F boom is designed for Tamrock Axera D05, Axera
D06 and Axera LP jumbos.
B 26 F boom is a hydraulic universal roll-over boom for
mechanized tunnelling, drifting, cross-cutting and bolt-
hole drilling in medium sections. It can also be used for
production drilling with cut-and-fill and room-and-pillar
methods.
This parallel holding telescopic boom offer large «true»
rectangular face coverage area.
TECHNICAL DATA
Coverage with parallelism holding 29,2 m²
Coverage with manual override 38,9 m²
Weight, without hoses 1 850 kg
Weight allowed 1 050 kg
Boom telescopic extension 1 200 mm
Boom lift, up and down 45° and 16°
Boom swing, symmetric ± 45°
Feed tilt, up and down 25° and 50°
Feed swing, symmetric ± 50°
Divergence, up and down 3° and 90°
Feed extension 1 600 mm
Feed roll-over 360°
DESCRIPTION
The x-y coordinated boom movements together with
360° actuator roll-over make the use of the boom simple
and logical. Accurate automatic parallel holding both in
vertical and horizontal plane improves the drilling
performance and accuracy.
Large dimensioned rectangular profile,adjustable and
sealed boom extension wear-pieces, large diameter
bearings, sealed main joints, expanding pins in cylinder
joints and use of super strong cast pieces in most
stressed areas are some of the features that are
included to the boom design for improved reliability.
Boom Swing
Feed Roll-overFeed Tilt
Boom Lift
Boom Extension
Feed Swing
Divergence
Feed Extension
(slave)
Feed Swing(main)
Ensure horizontal //
Ensure vertical //
Page 21E-04-07-2005 SR-MC-FL B26 F - B26XL F BOOM
SANDVIK TAMROCK SECOMA S.A.S19 avenue De Lattre-de-Tassigny - ZIB.P. 46 - 69881 MEYZIEU CedexTel : (33) 472 45 22 00 Fax : (33) 478 31 79 80
Technical Specification
B 26 F Boom4-200 S-C
2003-10-21
COVERAGE AREA
GENERAL DIMENSIONS
6000 5300
1870
5510
6490
26001253
1200
572
1600
50°
50°
90°
25° 50°
45°
31°
3°
16°
(45°)
26°(45°)
356
360°
www.tamrock.sandvik.comSandvik Tamrock reserve the right to change this specificationwithout further notice
Page 22 E-04-07-2005 SR-MC-FLB26 F - B26XL F BOOM
SANDVIK TAMROCK SECOMA S.A.S19 avenue De Lattre-de-Tassigny - ZIB.P. 46 - 69881 MEYZIEU CedexTel : (33) 472 45 22 00 Fax : (33) 478 31 79 80
Technical Specification
B 26 XL F Boom4-300 S-C2003-10-21
APPLICATION
B 26 XL F boom is designed for Tamrock Axera D05,
Axera D06 and Axera LP jumbos.
B 26 XL F boom is a hydraulic universal roll-over boom
for mechanized tunnelling, drifting, cross-cutting and
bolt-hole drilling in medium sections. It can also be used
for production drilling with cut-and-fill and room-and-
pillar methods.
This parallel holding telescopic boom offer large «true»
rectangular face coverage area.
TECHNICAL DATA
Coverage with parallelism holding 41,4 m²
Coverage with manual override 52,7 m²
Weight, without hoses 1 960 kg
Weight allowed 850 kg
Boom telescopic extension 1 700 mm
Boom lift, up and down 45° and 16°
Boom swing, symmetric ± 45°
Feed tilt, up and down 25° and 50°
Feed swing, symmetric ± 50°
Divergence, up and down 3° and 90°
Feed extension 1 600 mm
Feed roll-over 360°
DESCRIPTION
The x-y coordinated boom movements together with
360° actuator roll-over make the use of the boom simple
and logical. Accurate automatic parallel holding both in
vertical and horizontal plane improves the drilling
performance and accuracy.
Large dimensioned rectangular profile,adjustable and
sealed boom extension wear-pieces, large diameter
bearings, sealed main joints, expanding pins in cylinder
joints and use of super strong cast pieces in most
stressed areas are some of the features that are
included to the boom design for improved reliability.
Boom Swing
Boom Extension
Feed Roll-over
Boom Lift
Feed Tilt
Feed Extension
Divergence
Feed Swing(slave)
Feed Swing(main)
Ensure horizontal //
Ensure vertical //
Page 23E-04-07-2005 SR-MC-FL B26 F - B26XL F BOOM
SANDVIK TAMROCK SECOMA S.A.S19 avenue De Lattre-de-Tassigny - ZIB.P. 46 - 69881 MEYZIEU CedexTel : (33) 472 45 22 00 Fax : (33) 478 31 79 80
Technical Specification
B 26 XL F Boom4-300 S-C
2003-10-21
COVERAGE AREA
GENERAL DIMENSIONS
7040 6340
2160
6530
7490
31701253
1700
572
1600
50°
50°
90°
25° 50°
45°
31°
3°
16°
(45°)
26°(45°)
356
360°
Page 24 E-04-07-2005 SR-MC-FLB26 F - B26XL F BOOM
SANDVIK TAMROCK SECOMA S.A.S19 avenue De Lattre-de-Tassigny - ZIB.P. 46 - 69881 MEYZIEU CedexTel : (33) 472 45 22 00 Fax : (33) 478 31 79 80