SAFETY AND HEALTH ASSESSMENT SYSTEM

IN CONSTRUCTION

SHASSIC

Ir.M.RAMUSERENCIDB

Page 2: SAFETY AND HEALTH ASSESSMENT SYSTEM IN CONSTRUCTION SHASSIC Ir.M.RAMUSEREN CIDB

WHAT IS SHASSIC ?

SAFETY AND HEALTH ASSESSMENT

SYSTEM IN CONSTRUCTION

Page 3: SAFETY AND HEALTH ASSESSMENT SYSTEM IN CONSTRUCTION SHASSIC Ir.M.RAMUSEREN CIDB

THE DEVELOPMENT PROCESS

SHASSIC was identified by National Technical Committee who developed the Master Plan for Occupational Safety and Health in Construction Industry. This Master Plan was approved by Cabinet on 2nd August 2006.

Technical Committee for Safety and Health in Construction ( formed by CIDB) directly involved in the development of SHASSIC

Members representation from:- CIDB, DOSH, JKR, JKT(KPKT), MBAM , PKMM,

PAM, REHDA, IJM, UM, KPPDIP, MOSHA, NIOSH,

Page 4: SAFETY AND HEALTH ASSESSMENT SYSTEM IN CONSTRUCTION SHASSIC Ir.M.RAMUSEREN CIDB

SHASSIC STANDARD = CIS 10

Page 5: SAFETY AND HEALTH ASSESSMENT SYSTEM IN CONSTRUCTION SHASSIC Ir.M.RAMUSEREN CIDB

SHASSIC OBJECTIVES

To benchmark the level of safety and health performance of construction industry in Malaysia

To have a common standard on safety and health assessment system for contractor (s) in construction industry

To assess safety and health performance of contractor based on approved standard by the industry stakeholders

Page 6: SAFETY AND HEALTH ASSESSMENT SYSTEM IN CONSTRUCTION SHASSIC Ir.M.RAMUSEREN CIDB

SHASSIC OBJECTIVES Continue….

To evaluate the performance of contractor(s) based on the safety and health practices; and

To compile data for statistical analysis on contractor’s safety and health management and performance at sites

Page 7: SAFETY AND HEALTH ASSESSMENT SYSTEM IN CONSTRUCTION SHASSIC Ir.M.RAMUSEREN CIDB

SHASSIC OBJECTIVES ( con..)

To study on which area contractors has failed or could not score higher points so that appropriate training can be organized

Part of preparation for OSH management system in long run

Page 8: SAFETY AND HEALTH ASSESSMENT SYSTEM IN CONSTRUCTION SHASSIC Ir.M.RAMUSEREN CIDB

CRITERIA CONSIDERED FOR THE DEVELOPMENT OF SHASSIC

Compliance to legal requirements

- OHSA 1994, FMA, BOWEC Reg, Safety,Health & Welfare Reg,etc

Based on approved Standard & good practice

- OSH MS such as OHSAS 18001 AND MS 1722 etc

Page 9: SAFETY AND HEALTH ASSESSMENT SYSTEM IN CONSTRUCTION SHASSIC Ir.M.RAMUSEREN CIDB

COMPONENT OF ASSESSMENT & WEIGHTAGE

Divided into 3 categories:-

DOCUMENT CHECK - 40% WORKPLACE INSPECTION - 40% EMPLOYEE INTERVIEW - 20%

Page 10: SAFETY AND HEALTH ASSESSMENT SYSTEM IN CONSTRUCTION SHASSIC Ir.M.RAMUSEREN CIDB

SHASSIC REQUIREMENT

Work Progress has to be within 25% to 75%

WHY ? Construction at peak Many activities Workers at full Strength Potential accidents

Page 11: SAFETY AND HEALTH ASSESSMENT SYSTEM IN CONSTRUCTION SHASSIC Ir.M.RAMUSEREN CIDB

DOCUMENT CHECK

Checking on documents and records - to determine the compliance of establishment of OSH program and activities

There are 63 questions/checklists Weightage is 40% of the total marks of 100

Page 12: SAFETY AND HEALTH ASSESSMENT SYSTEM IN CONSTRUCTION SHASSIC Ir.M.RAMUSEREN CIDB

WORKPLACE INSPECTION

This assessment shall provide visual comparison of evidence on the OSH program that being implementation, enforced and practiced at site.

There are 62 questions/checklists 5 (five) high risk areas shall be assessed

within the site ( areas to be decided by Assessor)

It carries 40% of overall weightage

Page 13: SAFETY AND HEALTH ASSESSMENT SYSTEM IN CONSTRUCTION SHASSIC Ir.M.RAMUSEREN CIDB

HOW TO IDENTIFY 5 AREAS?

Talk to Project Manager or SHO at Site to identity the areas

There must be construction activities going on

Working at height shall be given preferences Working in confine area Working at congested area Many people working within small area

Page 14: SAFETY AND HEALTH ASSESSMENT SYSTEM IN CONSTRUCTION SHASSIC Ir.M.RAMUSEREN CIDB

EMPLOYEES INTERVIEW

Employees shall be randomly selected for interview purpose

Divided into 3 categories of Employees, namely, management personal ( 1), safety & health personals (3) and finally workers(10) from various trades

The set of questions are different for each categories

There are 48 questions all together(12, 6, 30) It carries weightage of 20%

Page 15: SAFETY AND HEALTH ASSESSMENT SYSTEM IN CONSTRUCTION SHASSIC Ir.M.RAMUSEREN CIDB

METHOD TO CALCULATE SCORE FOR ASSESSMENT

Document Check Total compliance in the checklist / ( 63

minus Number of Not applicable items) X 40% = A ( score for document check )

Page 16: SAFETY AND HEALTH ASSESSMENT SYSTEM IN CONSTRUCTION SHASSIC Ir.M.RAMUSEREN CIDB

METHOD TO CALCULATE SCORE FOR ASSESSMENT

Workplace Inspection Total compliance in the checklist /

( 62X5=310 minus Number of Not applicable items) X 40% = B ( score for Workplace Inspection )

Page 17: SAFETY AND HEALTH ASSESSMENT SYSTEM IN CONSTRUCTION SHASSIC Ir.M.RAMUSEREN CIDB

METHOD TO CALCULATE SCORE FOR ASSESSMENT

Employees Interview Total compliance in the checklist / ( 330

minus Number of Not applicable items) X 20% = C ( score for Employees Interview )

Page 18: SAFETY AND HEALTH ASSESSMENT SYSTEM IN CONSTRUCTION SHASSIC Ir.M.RAMUSEREN CIDB

TOTAL CHECKLISTS

Document Check 63 Workplace Inspection310 ( 62 X 5 ) Employee Interviews 330 ( 12(x1) + 6(x3)+

30 (x10)

TOTAL = 63 + 310 + 330 703 / site

Page 19: SAFETY AND HEALTH ASSESSMENT SYSTEM IN CONSTRUCTION SHASSIC Ir.M.RAMUSEREN CIDB

RATING

The total score based on the document check, workplace inspection and employees interview ( A + B + C ) shall be used for rating purpose

The RATING has 1 to 5 stars based on total marks scored

85 – 100 = 5 stars, 70 – 84 = 4 stars, 55 – 69 = 3 stars , 40 – 54 = 2 stars and 1 star for 39 and less marks

Page 20: SAFETY AND HEALTH ASSESSMENT SYSTEM IN CONSTRUCTION SHASSIC Ir.M.RAMUSEREN CIDB

SCORE STARS

( RATING )

85 - 100

70 - 84

55 - 69

Page 21: SAFETY AND HEALTH ASSESSMENT SYSTEM IN CONSTRUCTION SHASSIC Ir.M.RAMUSEREN CIDB

SCORE STARS

( RATING )

40 - 54

39 and less

Page 22: SAFETY AND HEALTH ASSESSMENT SYSTEM IN CONSTRUCTION SHASSIC Ir.M.RAMUSEREN CIDB

JUSTIFICATION FOR RANKING STARS

5 STARS - Potential and significant workplace high risk/hazards are managed and documented

4 STARS - Potential and significant workplace high risk/hazards are managed and documented but there are few low risks work activities are neglected

Page 23: SAFETY AND HEALTH ASSESSMENT SYSTEM IN CONSTRUCTION SHASSIC Ir.M.RAMUSEREN CIDB

JUSTIFICATION FOR RANKING STARS ( continue )

3 STARS - Potential and significant workplace high risk/hazards are managed and documented but there are few medium risks work activities are neglected

2 STARS - Potential and significant workplace high risk/hazards are managed and but not documented.

Page 24: SAFETY AND HEALTH ASSESSMENT SYSTEM IN CONSTRUCTION SHASSIC Ir.M.RAMUSEREN CIDB

JUSTIFICATION FOR RANKING STARS ( continue )

1 STAR – workplace potential and significant risk/hazards poorly managed and not documented properly

Page 25: SAFETY AND HEALTH ASSESSMENT SYSTEM IN CONSTRUCTION SHASSIC Ir.M.RAMUSEREN CIDB

ASSESSOR

Who can be the SHASSIC Assessor (s) ? A person who has attended one day training and

passed exam and must have 5 years woking experience in construction industry

Attended and passed Lead Auditor OHSAS 18001/MS 1722 course and with 3 years working experience in Construction Industry

CSHO with 2 years working experience in construction industry

Page 26: SAFETY AND HEALTH ASSESSMENT SYSTEM IN CONSTRUCTION SHASSIC Ir.M.RAMUSEREN CIDB

HOW TO REGISTER AS SHASSIC ASSESSOR WITH CIDB

Submit evidence of work experience A copy of identity card Certified True Copy of Exam Result / Auditor

Certificate /DOSH Green Book + 5 days Must be Green Card holder

Page 27: SAFETY AND HEALTH ASSESSMENT SYSTEM IN CONSTRUCTION SHASSIC Ir.M.RAMUSEREN CIDB

Condition for Registration

Submit relevant documents to CIDB and copy of Green Card

CEP = 20 points ( 1 hour = 2 point )- for renewal

Can attend course/seminar organize by anyone BUT has to be related to Construction Safety & Health

Page 28: SAFETY AND HEALTH ASSESSMENT SYSTEM IN CONSTRUCTION SHASSIC Ir.M.RAMUSEREN CIDB

CIDB rights to De-Register Assessor

The Assessor declared bankrupt by Court Assessor passed away Assessor became unsound mind Sentence by court as Criminal Failed to renew

Page 29: SAFETY AND HEALTH ASSESSMENT SYSTEM IN CONSTRUCTION SHASSIC Ir.M.RAMUSEREN CIDB

POTENTIAL USER OF SHASSIC DOCUMENT

DOSH JKR LOCAL GOVERNMENT CLIENT OR DEVELOPER CONTRACTORS

Page 30: SAFETY AND HEALTH ASSESSMENT SYSTEM IN CONSTRUCTION SHASSIC Ir.M.RAMUSEREN CIDB

WHAT IS EXPECTED FROM THE USAGE OF SHASSIC ?

Good safety and health management at site Prevention exercise from incidents and

accidents Contractor knows where they are in term of

managing safety and health at sites To improve safety and health management

based on scores Easier inspection by authorities as procedure

already in place

Page 31: SAFETY AND HEALTH ASSESSMENT SYSTEM IN CONSTRUCTION SHASSIC Ir.M.RAMUSEREN CIDB

THANK YOU