SABIC – Installation of Expansion Vessel at EO Supply Line to the Ethoxylate
SENDAN International Company Ltd. Ref # PSD-SAB-064-15-02-AMF-QA
Contents:
1. Technical Proposal
2. List of possible sub-contractors
3. Project Schedule
4. Project Organization Chart
5. Project Deployment
6. HSE Plan and policy
7. QA/QC Plan and related documentation
8. SENDAN Experience List
SABIC – Installation of Expansion Vessel at EO Supply Line to the Ethoxylate
SENDAN International Company Ltd. Ref # PSD-SAB-064-15-02-AMF-QA
TECHNICAL PROPOSAL
SABIC – Installation of Expansion Vessel at EO Supply Line to the Ethoxylate
SENDAN International Company Ltd. Ref # PSD-SAB-064-15-02-AMF-QA
TABLE OF CONTENTS
1. Project Scope
1.1 Scope of Supply & Services
1.2 Exclusions from SENDAN Scope
1.3 Assumptions and Clarifications
2. Technical Specifications
2.1 Data / Drawings Basis
3. Project Execution
3.1 Project Schedule
3.2 Project Completion & Handover
SABIC – Installation of Expansion Vessel at EO Supply Line to the Ethoxylate
SENDAN International Company Ltd. Ref # PSD-SAB-064-15-02-AMF-QA
1.0 PROJECT SCOPE
The project scope includes Engineering, procurement, supply, installation, testing
and pre commissioning of new EO Thermal expansion vessel at SAUDI KAYAN
Plant. The brief scope of work is as below:
Design and detail engineering works for new EO Thermal expansion
vessel installation.
Supply of 01 EO Thermal expansion vessel, related piping and
instruments.
Civil foundation works for New EO Thermal expansion vessel.
Supply, fabrication, erection and modification of piping.
Painting and insulation works.
Cable laying for instruments.
Provision of instruments stanchions, transmitter sun shade and tube
fittings.
Configure new AO Card in the system.
DCS Configuration.
Scaffolding.
1.1 Scope of Supply and Services
1.1.1 SENDAN shall provide all the needful documents whenever required for
documentation
1.1.2 SENDAN shall comply with international standards as well as SABIC’s
standards for material / field execution.
1.1.3 SENDAN shall be required to provide all necessary equipment, tools,
skilled manpower and supervision for the job.
SABIC – Installation of Expansion Vessel at EO Supply Line to the Ethoxylate
SENDAN International Company Ltd. Ref # PSD-SAB-064-15-02-AMF-QA
1.1.4 All material and consumable items required for this job shall be part of the
scope of SENDAN except those mentioned in 1.2.
1.1.5 SENDAN will be responsible for safe handling of material and
implementation of safe work practices required to complete the job.
1.2 Exclusions from SENDAN Scope & Supply by SAUDI KAYAN
Following are excluded from SENDAN’s scope and are not covered under this proposal:
1.2.1 SABIC/SAUDI KAYAN will provide the access for SENDAN’s manpower
and equipment. SENDAN will provide the necessary documents.
1.2.2 SENDAN has not considered piling works in his quoted price.
1.2.3 SAFERAD for piping has not been considered, instead normal radiography
technique will be used.
SABIC – Installation of Expansion Vessel at EO Supply Line to the Ethoxylate
SENDAN International Company Ltd. Ref # PSD-SAB-064-15-02-AMF-QA
2. TECHNICAL SPECIFICATIONS This section specifies the technical specifications of work based on the scope of supply
and services specified in Section 1.0 of this technical proposal.
2.1 Data/Drawings/BOQ Basis
The subjected work proposed shall be based on the BOQ documents, drawings,
specifications and assumptions but on the conditions mentioned in Section 1.
3. PROJECT EXECUTION 3.1 Project Schedule 3.1 .1 Project Effective Date The Project Effective Date will be the start date of the Project and will be the date
by which the Purchase Order/LOI is received by SENDAN from client.
3.1.2 Project Completion Schedule a. The Project End Date will be the date of completion of the Project.
b. The project duration is as per attached schedule.
c. The Project completion schedule will be extended (at no cost to SENDAN) if:
· Client delays in fulfillment of its obligations specified in this proposal, and/or
· The accumulated delaying effects of the change orders, affect the overall
schedule; or
· The events of Force Majeure affect the Project schedule.
SABIC – Installation of Expansion Vessel at EO Supply Line to the Ethoxylate
SENDAN International Company Ltd. Ref # PSD-SAB-064-15-02-AMF-QA
List of possible Sub-contractors:
Following is the list of possible sub-contractors:
1. NDT (Cooper Heat)
2. Insulation (Binzagr / Al-Faghan)
3. Sandblasting and painting (Experts Arabia)