12
Shale Gas & Fracking Toolkit Planning Part 3

Shale Gas & Fracking Toolkit

  • Upload
    others

  • View
    8

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Shale Gas & Fracking Toolkit

Shale Gas & Fracking ToolkitPlanning

Part 3

Page 2: Shale Gas & Fracking Toolkit

5606

Part 3: PlanningIn 2013, the Prime Minister publically backed the burgeoning shale gas industry in the UK:

“If neighbourhoods can see the benefits – and are reassured about its effects on the environment – then I don’t see why fracking shouldn’t receive real public support.... We want people to get behind fracking and a transparent planning process is an important ingredient.” David Cameron, Daily Telegraph, 11 August 2013

More recently, in his speech to the Conservative Party Conference, the Chancellor publically pledged his Party’s support for the industry.

“[The party fully intend to exploit] the extraordinary shale gas reserves untouched beneath our feet.” Conservative Party Conference, 29 September 2014

Minerals Planning PolicyMinerals planning policy is set out in paragraphs 142-149 of the National Planning Policy Framework (NPPF) which requires Minerals Planning Authorities (MPAs) to identify and include policies for extraction of mineral resources in their area. This encompasses the extraction of unconventional hydrocarbons such a shale gas and the legal regime relating to hydraulic fracturing or ‘fracking’ of potential shale gas reserves in the UK, discussed in this Toolkit.

“Minerals are essential to support economic growth.”NPPF, 2012

1 www.pinsentmasons.com/shale

Page 3: Shale Gas & Fracking Toolkit

2

Shale Gas Toolkit | Shale Gas & Fracking Toolkit: Part 3

Planning practice guidance for hydrocarbonsOn 19 July 2013, the Department for Communities and Local Government (DCLG) published a 29 page document entitled “Planning Practice Guidance for Onshore Oil and Gas”. This guidance was welcomed by many who desired greater clarity and certainty regarding the planning process for shale gas exploration and extraction.

The guidance set out advice on planning issues associated with three identified phases of hydrocarbon extraction:• Exploration• Testing (appraisal)• Production.

The introduction specifically stated that it was not intended to be a source of definitive legal advice, nor was it intended to replace the need for judgment by MPAs and those making applications. As a result, some in the industry found that the guidance was in certain areas lacking; for example, in its failure to tackle key questions such as how planning boundaries should be drawn for directional and horizontal drilling once the appropriate rock formation is reached, how to deal with issues arising where the surface and subsurface are in different ownership and the way in which the guidance dealt with the consideration of ‘alternatives’ in the context of need and demand.

The guidance did, however, provide a basic run-through of the three phases of hydrocarbon extraction, with broad descriptions of what each entails and the timescales involved before going on to discuss in greater detail the regulatory function of the planning process in relation to each of the phases.

On 6 March 2014, DCLG announced the launch of a new online planning practice resource to support the NPPF. The new online guidance cancelled DCLG’s 2013 guidance and replaced it with “Planning for hydrocarbon extraction.” The new guidance broadly mirrors the 2013 guidance. It also encourages MPAs to make appropriate provision for hydrocarbons in Local Plans, highlighting areas where new proposals may come forward and managing potential conflicts for land use.

The minerals planning authority and the statutory frameworkThe requirement for planning permission is one of a number of regulatory consents which are required to authorise the shale gas extraction process. MPAs are expected to ensure that mineral extraction (be it through fracking or an alternative process) does not have an unacceptable adverse impact upon the environment or human health. This responsibility is carried out through the minerals planning process.

Page 4: Shale Gas & Fracking Toolkit

5606

The applicable statutory framework for obtaining planning permission for fracking operations is currently the Town and Country Planning Act 1990 in England and Wales and the Town and Country Planning (Scotland) Act 1997 in Scotland.

In England and Wales it is the MPAs in the first instance who will determine planning permission. In Scotland, it is the local planning authority and in Northern Ireland, the Minerals Unit has responsibility. In the majority of cases, the MPA is the County Council or Unitary Authority, however a National Park Authority is also an MPA.

A multi-stage processPlanning permission will be required at a number of stages throughout the lifetime of the fracking process from the initial exploratory phase through to the full development and production stage and finally abandonment.

As noted in part 1 of the Pinsent Masons’ Fracking Toolkit, there are 6 main stages to the process of shale gas extraction: • Stage 1 – Identification• Stage 2 – Exploration• Stage 3 – Appraisal• Stage 4 – Initial development• Stage 5 – Full development and production• Stage 6 – Production and abandonment

Stages 2 to 6 – the exploration, appraisal and production stages – can only be carried out in specified areas where the Department of Energy and Climate Change (DECC) has issued a Petroleum Exploration & Development Licence (PEDL) under the Petroleum Act 1998.

Planning policy & regulation – the main stages of the processThe Planning Context

Each of the 6 stages is considered in turn below setting out the key planning requirements and issues which need to be addressed.

1. IdentificationDeveloper identifies suitable sitesAs discussed above, the NPPF requires MPAs to identify and include policies for extraction of mineral resource of local and national importance in their area. Given that shale gas exploration and exploitation or fracking is still an emerging industry in the UK it is unlikely that many Local Plans will have specifically considered the potential for shale gas reserves and fracking operations in the Local Plan process.

The Local Plan is, therefore, unlikely to be of specific assistance in identifying shale gas reserves and sites for possible fracking operations in many areas. However, as Local Plans catch up with industry, MPAs will need to identify potential shale gas reserves and PEDL areas on their proposals maps and in criteria-based policies for stages 2 to 6 and the exploration, appraisal and production phases for shale gas fracking and extraction. Indeed, 2014 planning practice guidance encourages

3

Page 5: Shale Gas & Fracking Toolkit

4

Shale Gas Toolkit | Shale Gas & Fracking Toolkit: Part 3

MPAs to do so. The initial identification phase will largely be undertaken through the gathering and assessment of existing geological data (e.g. information gathered from earlier drilling and also through various geological surveys and reports that are published).

2. ExplorationThe drilling of exploratory holesDuring the exploratory phase, the promoter and developer will carry out seismic surveys, exploratory drilling and hydraulic fracturing in order to ascertain whether shale hydrocarbons and reserves are present in the land.

Whilst some of the initial seismic work may have deemed planning permission (i.e. when planning permission is not required as it is deemed to be granted under Part 22 of Schedule 2 to the Town and Country Planning (General Permitted Development) Order 1995) it is likely that the drilling of exploratory holes will require planning permission. The reason for this is two fold: firstly, it constitutes a change of use of the land which in many cases will be agricultural and secondly, the extent of drilling, both in terms of the number of holes and the length of time required for the drilling, is likely to be significant (certainly when compared to conventional hydrocarbons).

Whether the exploration phase will require an Environmental Impact Assessment (EIA) will depend on whether the nature, size and location of the operations will have a likely significant effect on the environment.

In the majority of cases an EIA will not be required, but the prudent approach would be to seek a screening opinion from the MPA as to whether or not an EIA should be carried out. However, there could be circumstances where it could be beneficial to carry out an EIA and these may not necessarily be due to the applicable tests for an EIA being met. For instance, carrying out an EIA could be one way of being seen to be “open” about the potential environmental impacts of a proposed project. An EIA would explain in more detail the proposed drilling operations and what is involved, and thus could assist in alleviating concerns that the local community may have about the processes involved. It is interesting to note that the planning applications submitted to MPAs to date have been accompanied by an EIA.

Infrastructure BillThe Bill is currently making its way through the Parliamentary process. The Labour Party tabled amendments to the Bill in August 2014 that would, if enacted, have meant that EIA would be required for all applications for planning permission (including for sites of less than 1 hectare) “for the purposes of extracting shale.” However, these amendments were not officially moved forward and are not included in the current version of the Bill to be debated by the House of Lords.

3. AppraisalDrilling of wells to assess commercial viability of gas production. Gas produced at this stage can be used for small-scale commercial electricity generationThe appraisal stage arises where shale gas has been identified and proved but further evidence is required in order to clarify the extent of the deposit or its production characteristics to assess whether or not it is economically viable. This stage may involve significant works, including longer term testing and additional drilling, further wells and hydraulic fracturing.

Planning permission will be required at this stage of the process for drilling operations and any associated infrastructure such as drilling platforms.

The potential nature and extent of operations during the appraisal stage means that it is critically important to consider whether an EIA is required. Any assessments and assumptions which were carried out in connection with the exploration phase will need further consideration and may require refreshing or additional assessments to be carried out.

Again, a screening opinion should be sought from the MPA at this stage of the process.

If the appraisal shows positive results, the well will be safely isolated while consideration is given to the need for more appraisal drilling or the potential for a permanent development. If the developer does wish to proceed with a permanent development, they will then proceed to the initial development stage discussed in more detail below.

If the appraisal stage shows that either hydrocarbons are not present or are present in quantities that are not commercially viable, the well will be “abandoned” at this point. See stage 6 below for further details relating to the abandonment process.

Page 6: Shale Gas & Fracking Toolkit

56065

4. Initial Development First production wells constructed as well as necessary infrastructure to facilitate the sale of shale gas. Early sales revenue generated and project tailored to maximise productionIf the appraisal stage yields positive results and the developer decides to proceed to a permanent development, it must submit a Field Development Plan to the MPA and DECC, outlining its planned method for hydrocarbon extraction. Only once consent has been given by both the MPA and DECC can the developer install the equipment to extract the trapped hydrocarbons at the site. The planning application at this stage is an application for commercial exploitation, but not on a large scale. In order for DECC to approve any Field Development Plan submitted, the MPA must have firstly granted planning permission in consultation with the Environment Agency (or Natural Resources Wales in Wales and SEPA in Scotland) and the assessment would have considered the need for an EIA and environmental permits.

The initial development stage takes place prior to full development and production stages and provides the developer/operator with a greater understanding of production trends as well as an opportunity to tailor the well design to fit the specific circumstances of the project.

As with the appraisal stage the nature of the works are now more significant and therefore similar strategic considerations will apply to the approach to be adopted in respect of EIA.

5. Full Development and ProductionDrilling of production wells across licence area and construction of commercial production facilities and infrastructure for large volumes of shale gasPlanning permission will be required for large scale commercial drilling of production wells and further site upgrades (e.g. the construction of associated equipment such as pipelines, processing, facilities and temporary storage tanks). In some cases, the production life of a gas field can be in excess of 20 years plus. Consequently, careful consideration will need be given to the potential impact of the proposed development and operations on the surrounding area and the local community.

In terms of strategy, developers will need to carefully consider whether or not to submit a comprehensive planning application to cover as many of the associated elements of the proposed project as possible or whether separate planning applications should be submitted for development proposals such as the pipelines. However, developers will need to be careful not to fall foul of the EIA Directive and accused of “salami-slicing”.

6. AbandonmentWell plugged and surrounding area rehabilitated in accordance with prescribed standardsWhen production at a site ceases it will be necessary for the site or sites to be restored or in some cases put to a new appropriate use.

As shale gas exploration and fracking has a limited impact above ground it is unlikely to be subject to the detailed restoration conditions which apply in relation to mining operations such as quarries which are normally subject to onerous landscaping restoration conditions. The specific conditions that require restoration works will have been contained in any planning permission authorising full development. In practice, there are likely to be requirements for the submission to the MPA of specific details and plans for restoration so that the MPA can grant its approval.

Page 7: Shale Gas & Fracking Toolkit

6

Shale Gas Toolkit | Shale Gas & Fracking Toolkit: Part 3

Key issues to considerThere are a number of common key issues which are relevant throughout the planning process.

Pre-application engagement and consultation Effective pre-application engagement and consultation will be essential. Such engagement must be deployed at a serious level in advance of even the early stages of the planning process and should continue and develop as the planning applications relate to more significant development.

An engagement and consultation strategy should be drawn up at the outset and subjected to critical analysis before it is deployed. Whilst the more onerous consultation process under the Planning Act 2008 does not currently apply, it would seem sensible to adopt a similarly robust approach in any planning applications. For instance, consultation should be undertaken with local communities and interested bodies in addition to the MPA and mandatory consultees.

Environmental Impact Assessment As noted above, EIA will be a key consideration at all stages of the fracking process.

The nature of the environmental information to be considered as part of the planning applications will be wide ranging and may include the following which is not an exhaustive list: geological data, ecology, water, transportation, access flood risk, archaeological, contamination and landscape character. Where an EIA is to be undertaken, a scoping request should be submitted to the MPA to ensure that the EIA addresses the relevant environmental issues.

Given that there are several elements to the fracking process each of these will need to be consented separately with the exception of abandonment which will be covered by the full development and production consent. This raises an interesting question over the extent of your environmental assessment – if you are carrying out an EIA for the exploratory stage – do you need to include in that assessment the appraisal stage? To answer this question, you have to consider whether the whole fracking process from stage 1 to stage 6 is a single project, or whether there is more than one project in that process. If all stages constitute a single project and you artificially sub-divide it into two or more projects, with each then being put forward in isolation, this is likely to fall foul of the EIA Directive’s requirements. Also, if the effect of sub-division is to mean that an EIA does not assess the full cumulative effects of the individual application, then the EIA will not be Directive-compliant. However, recent case law has shown that courts accept that some infrastructure proposals would be constructed in stages and this would not necessarily make them a single project which could only ever be assessed as such. Furthermore, the whole point of the exploratory stage is to ascertain whether there is a more permanent project, which would suggest that any EIA at the early stages of the process would not need to assess later stages.

Government Support The Government is supportive of fracking and has unveiled a number of incentives to ensure that it happens. This support is unsurprising given the benefits it will bring in being able to produce low cost gas in the UK whilst at the same time reducing greenhouse gas emissions. Whilst planning decisions will initially be considered on a local level, such support will play an important role should applications be determined by the Secretary of State either on appeal or call-in inquiry.

Page 8: Shale Gas & Fracking Toolkit

5606

Legal Challenge and Risk At all stages of the fracking process there is a risk of legal challenge against any of the planning permissions which may be granted. It is therefore imperative that a robust approach is taken in applying for planning permission at each stage of the fracking process. A successful legal challenge against any of the elements could have serious knock-on effects on the project as a whole.

The potential for legal challenge also reinforces the importance of carrying out effective pre-application engagement and consultation in order to try to allay any concerns that local residents/interested bodies may have about the proposed development. As explained above, careful consideration of the extent of your EIA is also recommended given EIA is one of the hottest areas for third parties to challenge.

Planning Performance Agreements (PPA) It is not mandatory to use a PPA, although as with any complex planning application serious consideration should be given to the use of one.

Interaction with other Regulatory Regimes The role of the planning system is to consider whether the development and use of the land is acceptable. This defined role is different from other regulatory regimes, for instance the requirement for an Environmental Permit, but at the same time will be complementary.

MPAs should take into account any relevant comments or information from other regulatory regimes where issues relate to the development and the land use. Otherwise, MPAs should assume that the other regulatory regimes will operate effectively.

7

Page 9: Shale Gas & Fracking Toolkit

8

Status as nationally significant infrastructure projectsThe Government confirmed in June 2013 that shale gas and fracking developments would not be treated as Nationally Significant Infrastructure Projects (NSIPs) under the Planning Act 2008. This means that planning applications will continue to be made to the MPA rather than to the Secretary of State.

For many this was viewed as a lost opportunity to include shale gas and fracking expressly within the scope of the NSIP regime and the Planning Act 2008. It would have allowed applications for development consent for shale gas extraction to be made directly to the Secretary of State with the benefit of the streamlined examination procedure and the possibility of wrapping up other consents. Greater certainty for projects would have been forthcoming with the benefit of national policy underpinning projects and schemes.

If fracking were brought within the remit of the Planning Act 2008 regime, it would seem plausible that stages 4, 5 and 6 could potentially be brought within the NSIP regime, with earlier stages remaining under the Town and Country Planning Act 1990 process.

Planning application notification requirements simplified for onshore operatorsFollowing DCLG’s 2013 consultation on simplifying and streamlining planning application requirements for onshore oil and gas operators, the Town and Country Planning (Development Management Procedure and Section 62A Applications) (England) (Amendment No.2) Order 2013 came into force in January 2014. The Order amends the procedures and requirements for planning applications associated with underground oil and gas operations. The changes have introduced a new national standard planning application form. Also, for onshore oil and gas planning applications (including exploratory drilling) applicants are no longer required to notify owners when soley underground operations are envisaged.

Shale Gas Toolkit | Shale Gas & Fracking Toolkit: Part 3

Page 10: Shale Gas & Fracking Toolkit

56069

The

Shal

e Gas

ext

ract

ion

Proc

ess,

from

iden

tifica

tion

of a

pot

entia

l dev

elop

men

t are

a to

the

full

com

mer

cial

exp

loita

tion

of th

at a

rea,

con

tain

s man

y st

ages

and

can

last

ove

r 30

year

s. A

t eac

h st

age

Dev

elop

ers m

ust m

eet a

num

ber o

f reg

ulat

ory

requ

irem

ents

that

are

set

out i

n th

e tim

elin

e be

low

.

SEIS

MIC

ITY:

this

issu

e ha

s the

pot

entia

l to

be a

stu

mbl

ing

bloc

k to

pro

pose

d or

com

men

ced

oper

atio

ns a

nd is

som

ethi

ng to

whi

ch D

evel

oper

s m

ust g

ive

cons

ider

able

thou

ght.

Dev

elop

ers

mus

t ass

ess t

he ri

sk o

f act

ivat

ing

faul

ts in

the

prop

osed

lice

nce

area

and

al

so m

onito

r bac

kgro

und

seis

mic

ity b

efor

e fr

acki

ng o

pera

tions

com

men

ce. R

eal t

ime

seis

mic

mon

itorin

g w

ill a

lso

be n

eces

sary

dur

ing

oper

atio

ns a

nd o

pera

tions

will

nee

d to

be

paus

ed o

r hal

ted

whe

re s

eism

icity

pas

ses

a ce

rtai

n le

vel

Acr

onym

sPE

DL

– Pe

trol

eum

Exp

lora

tion

& D

evel

opm

ent L

icen

ceC

A –

Coa

l Aut

horit

yD

ECC

– D

epar

tmen

t for

Env

ironm

ent &

C

limat

e C

hang

eEA

– E

nviro

nmen

t Age

ncy

EIA

– E

nviro

nmen

t Im

pact

sse

ssm

ent

EP –

Env

ironm

enta

l Per

mit

HSE

– H

ealt

h &

Saf

ety

Exec

utiv

eLP

A –

Loc

al P

anni

ng A

utho

rity

MPA

– M

iner

als

Plan

ning

Aut

horit

yPE

DL

– Pe

trol

eum

Exp

lora

tion

& D

evel

opm

ent L

icen

cePP

– P

lann

ing

Perm

issi

onPP

A –

Pla

nnin

g Pe

rfor

man

ce A

gree

men

tW

AL

– W

ater

Abs

trac

tion

Lice

nce

Oth

er R

equi

rem

ents

:• P

EDL

Exte

nsio

n fo

r fu

ll co

mm

erci

al e

xplo

itatio

n• A

gain

, onc

e PP

gra

nted

the

Dev

elop

er m

ust r

epea

t the

pr

oces

s of n

otify

ing

the

EA

and

HSE

prio

r to

drill

ing

befo

re

DEC

C g

ive

the

ultim

ate

gree

n lig

ht to

com

men

ce o

pera

tions

.

Oth

er R

equi

rem

ents

:• A

gain

, onc

e PP

gra

nted

the

Dev

elop

er m

ust r

epea

t the

pr

oces

s of n

otify

ing

the

EA a

nd

HSE

prio

r to

drill

ing

befo

re b

eing

th

e gr

een

light

by

DEC

C.

Oth

er R

equi

rem

ents

:• E

Ps d

ealin

g with

envir

onm

enta

l risk

s•

WAL

nee

ded

whe

re w

ater

for

frack

ing

oper

atio

ns so

urce

d fro

m

grou

ndw

ater

/sur

face

wat

er• C

A CO

NSE

NT

to d

rill t

hrou

gh

coal

seem

s whe

re n

eces

sary

• Wel

l Exa

min

atio

n Sc

hem

e im

plem

ente

d to

confi

rm W

ell

desig

ned

and

cons

truc

ted

in

acco

rdan

ce w

ith in

dust

ry• N

otify

EA

of in

tent

ion

to d

rill

• Not

ify H

SE o

f wel

l des

ign

and

oper

atio

ns 2

1 day

s prio

r to

drill

ing

• HSE

Con

sent

whe

re si

gnifi

cant

al

tera

tion

of w

ell n

eede

d• F

rack

ing

Plan

to a

ddre

ss th

e ris

k of

seism

icity

subm

itted

to D

ECC

• F

rack

ing

cons

ent f

rom

DEC

C.

1 –

3 Ye

ars

Oth

er R

equi

rem

ents

:• P

EDL

Exte

nsio

n• O

nce

PP g

rant

ed th

e D

evel

oper

m

ust r

epea

t the

pro

cess

of

notif

ying

the

EA a

nd H

SE o

f dr

illin

g be

fore

bei

ng th

e gr

een

light

by

DEC

C• A

dditi

onal

ly H

SE C

onse

nt

wou

ld b

e ne

cess

ary

whe

re

the

Dev

elop

er w

ishe

d to

si

gnifi

cant

ly a

lter e

xist

ing

wel

ls.

1 –

2 Ye

ars

2 –

3 Ye

ars

Ove

r 20

Year

s

Oth

er R

equi

rem

ents

:• R

ehab

ilita

tion

of a

rea

in

acco

rdan

ce w

ith P

P co

nditi

ons

• Wel

l Aba

ndon

men

t in

acco

rdan

ce w

ith

• HSE

stan

dard

s• A

fter

care

of t

he si

te in

ac

cord

ance

with

PP

cond

ition

s.

Aba

ndon

men

tW

ell p

lugg

ed a

nd

surr

ound

ing

area

re

habi

litat

ed in

acc

orda

nce

with

pre

scrib

ed s

tand

ards

.

Expl

orat

ion

Onc

e PE

DL

secu

red,

Dev

elop

er

iden

tifie

s lo

cati

ons

wit

hin

licen

ce a

rea

wit

h hi

ghes

t po

tent

ial f

or s

hale

gas

and

ex

plor

ator

y dr

illin

g un

dert

aken

.

App

rais

alD

rilli

ng o

f wel

ls t

o as

sess

co

mm

erci

al v

iabi

lity

of g

as

prod

ucti

on. G

as p

rodu

ced

at t

his

stag

e ca

n be

use

d fo

r sm

all-

scal

e co

mm

erci

al

elec

tric

ity

gene

rati

on.

Init

ial D

evel

opm

ent

Firs

t pr

oduc

tion

wel

ls

cons

truc

ted

as w

ell a

s ne

cess

ary

infr

astr

uctu

re to

faci

litat

e th

e sa

le o

f sha

le g

as. E

arly

sal

es

reve

nue

gene

rate

d an

d pr

ojec

t ta

ilore

d to

axi

mis

e pr

oduc

tion

.

Full

Dev

elop

men

t & P

rodu

ctio

n D

rillin

g of

pro

duct

ion

wel

ls a

cros

s lic

ence

are

a an

d co

nstr

uctio

n of

co

mm

erci

al p

rodu

ctio

n fa

cilit

ies

and

infr

astr

uctu

re fo

r lar

ge

volu

mes

of s

hale

gas

.

Oth

er R

equi

rem

ents

:• P

EDL

to s

earc

h fo

r, an

d ex

trac

t sha

le g

as. (

PED

L mirr

ors s

tage

s –

ther

efor

e PE

DL e

xten

sions

will

be

nece

ssar

y)• P

rope

rty

Righ

ts –

neg

otia

te w

ith L

ando

wne

rs to

pur

chas

e or

sec

ure

right

s (le

ase

or li

cens

e) o

ver l

and

to fa

cilit

ate

the

proc

ess.

Iden

tific

atio

nD

evel

oper

iden

tifies

suita

ble

area

s for

shal

e ga

s exp

lora

tion.

1 –

3 Ye

ars

Plan

ning

Req

uire

men

ts:

• Non

e.Pl

anni

ng R

equi

rem

ents

:• P

P fr

om M

PA (L

PA in

Sco

tlan

d)

for d

rillin

g EX

PLO

RATO

RY

wel

ls, c

hang

e of

use

in la

nd a

nd

any

asso

ciat

ed w

orks

• EIA

– d

epen

ding

upo

n na

ture

, si

ze a

nd lo

catio

n of

dev

elop

men

t pr

opos

als a

nd c

onsu

ltatio

n st

rate

gy to

be

adop

ted.

Plan

ning

Req

uire

men

ts:

• PP

from

MPA

for d

rillin

g of

A

PPRA

ISA

L w

ells

and

any

as

soci

ated

wor

ks a

nd u

pgra

des

(e.g

. dril

ling

plat

form

s)• E

IA –

dep

endi

ng u

pon

natu

re,

size

and

loca

tion

of d

evel

opm

ent

prop

osal

s and

con

sulta

tion

stra

tegy

to b

e ad

opte

d• S

ecti

on 1

06 p

lann

ing

oblig

atio

ns li

nked

to P

P an

d PP

As

if ap

prop

riate

.

Plan

ning

Req

uire

men

ts:

• PP

from

MPA

for d

rillin

g of

initi

al

PRO

DU

CTIO

N w

ells

as a

ny

asso

ciat

ed w

orks

and

site

upg

rade

s• E

IA• P

ossi

ble

Sect

ion

106

plan

ning

ob

ligat

ions

link

ed to

PP

• PPA

s if

appr

opria

te.

Plan

ning

Req

uire

men

ts:

• PP

from

MPA

for l

arge

sc

ale

com

mer

cial

dril

ling

of

PRO

DU

CTIO

N w

ells

and

any

as

soci

ated

wor

ks o

r site

upg

rade

s (i.

e. c

onst

ruct

ion

of la

rge

scal

e pr

oduc

tion

infr

astr

uctu

re)

• EIA

• Pos

sibl

e Se

ctio

n 10

6 pl

anni

ng

oblig

atio

ns li

nked

to P

P • P

PAs

if ap

prop

riate

.

Plan

ning

Req

uire

men

ts:

• PP

from

MPA

(if f

urth

er

cons

ent

requ

ired

for c

hang

es to

the

deve

lopm

ent

stra

tegy

from

th

at c

onse

nted

in P

P fo

r st

age

5)• P

ossi

ble

EIA

con

nect

ed to

PP

dep

endi

ng o

n th

e ch

ange

s th

at h

ave

been

mad

e.

Shal

e G

as E

xtra

ctio

n Pr

oces

s Tim

elin

e

Page 11: Shale Gas & Fracking Toolkit

Shale Gas Toolkit | Shale Gas & Fracking Toolkit: Part 3

This note does not constitute legal advice. Specific legal advice should be taken before acting on any of the topics covered.

Bob RuddimanPartner and Sector HeadEnergy & Natural ResourcesT: +44 (0)1224 377 925E: [email protected]

Paul RicePartner and Head of Client RelationshipsEnergy & Natural ResourcesT: +44 (0)20 7490 6282E: [email protected]

For further details and queries relating to Shale Gas or other matters, please contact:

Richard GriffithsPartnerPlanning & Environment Energy & InfrastructureT: +44 (0)20 7490 6981E: [email protected]

Richard FordPartnerPlanning & Environment Energy & InfrastructureT: +44 (0)20 7490 6241E: [email protected]

Robbie OwenPartnerPlanning & Environment Energy & InfrastructureT: +44 (0)20 7490 6420E: [email protected]

Michael PocockPartnerPlanning & Environment Energy & InfrastructureT: +44 (0)161 250 0223E: [email protected]

10

Page 12: Shale Gas & Fracking Toolkit

5606www.Out-Law.comwww.pinsentmasons.com

Pinsent Masons LLP is a limited liability partnership registered in England & Wales (registered number: OC333653) authorised and regulated by the Solicitors Regulation Authority and the appropriate regulatory body in the other jurisdictions in which it operates. The word ‘partner’, used in relation to the LLP, refers to a member of the LLP or an employee or consultant of the

LLP or any affiliated firm of equivalent standing. A list of the members of the LLP, and of those non-members who are designated as partners, is displayed at the LLP’s registered office: 30 Crown Place, London EC2A 4ES, United Kingdom. We use ‘Pinsent Masons’ to refer to Pinsent Masons LLP, its subsidiaries and any affiliates which it or its partners operate as separate

businesses for regulatory or other reasons. Reference to ‘Pinsent Masons’ is to Pinsent Masons LLP and/or one or more of those subsidiaries or affiliates as the context requires. © Pinsent Masons LLP 2015.

For a full list of our locations around the globe please visit our websites:

For more information please visit: pinsentmasons.com/shale