Shear Stud Cap in Steel Decks

  • Upload
    aarigon

  • View
    220

  • Download
    0

Embed Size (px)

Citation preview

  • 7/28/2019 Shear Stud Cap in Steel Decks

    1/20

    SHEAR STUD CAPACITY IN PROFILED STEELDECKS

    RAED J. ZAKI is theAssistant Structural Engineer

    at HERA. He obtained his

    BE at the University of

    Baghdad, Iraq and his

    Masters at the University of

    Auckland, New Zealand. He

    is currently working on the

    application of steel semi-

    rigid joints in a damage

    avoidance seismic system

    and on improved design

    provisions for shear studs in composite floor

    systems.

    JOHN BUTTERWORTHis Deputy Head,

    Department of Civil and

    EnvironmentalEngineering, University of

    Auckland. His research

    interests include behaviour

    of steel structures,

    earthquake engineering,

    passive seismic protection,

    structural dynamics, thin-

    walled metal sections,

    composites, structural

    stability and large scale dynamic testing of bridges

    and buildings.

    G. CHARLES CLIFTONheads the Structural

    Division of HERA (the

    New Zealand Heavy

    Engineering Research

    Association). His role there

    is to promote the proper

    and effective use of

    structural steel in New

    Zealand. His principal

    activities are research,

    development of design

    guidance and technicalpromotion. He runs HERAs fire and seismic

    research programme, which is aimed at improving

    the safety and cost-effectiveness of structural steel

    building performance in the high risk but infrequent

    events of severe fire and severs earthquake. He is a

    Fellow of the Institution of Professional Engineers

    New Zealand and of the New Zealand Society for

    Earthquake Engineering.

    ABSTRACT

    The New Zealand design procedure for composite

    beams incorporates provisions for headed, welded

    shear stud design shear capacity developed forNorth American standards in the 1970s, modified

    with a partial strength reduction factor incorporated

    in 1992. Following New Zealand and international

    tests which showed shortcomings with these

    equations, the topic of composite beam design

    using shear studs and trapezoidal decking was re-

    evaluated in 2003 and a series of experimental tests

    undertaken to determine the adequacy of proposed

    new provisions.

    This paper covers the following: the changes made,

    the previous reports on over-estimating the stud

    capacity, the testing of eleven shear stud push-

    through specimens and the results of these tests.

    Also included are constructional issues such as stud

    positioning, the effect of decking edge in primary

    beams and the influence of the self weight of the

    slab on the transverse bending moment acting on

    the beam and its effect on the shear studs. The

    results of these tests have allowed us to make

    recommendations for shear stud capacity, which

    more accurately reflect the failure modes that

    occurred, and to incorporate these into revisions to

    the composite beam design procedure for beams

    supporting concrete slabs on profiled steel decks.

    Raed J. Zaki

    ohn Butterworth

    G. Charles Clifton

  • 7/28/2019 Shear Stud Cap in Steel Decks

    2/20

    1. INTRODUCTION

    The use of composite steel beams with profiled

    steel decking and in-situ concrete floors has

    increased in recent years in New Zealand and

    around the world. This increased interest led to a

    critical review of current design procedures in

    (NZS 3404:1997) arising from concerns that theseprovisions overestimate the strength of shear studs

    in profiled steel decks. A number of studies, (Lin,

    et. al., 2001), (Jayas and Hosain, 1988 & 1989),

    have shown that many building codes over-estimate

    the predicted ultimate shear stud capacity, in

    comparison with the observed shear stud capacity.

    This has led to updating of standards; for example

    the latest (CSA S16-01: 2001) has been revised to

    correct this error.

    This paper presents an overview of research

    recently undertaken (Zaki, et. al., 2003) into the

    adequacy of current New Zealand design provisions

    for composite beams supporting profiled steel

    decks. Following a detailed comparison of the

    overall New Zealand composite design procedure

    (NZS 3404:1997) with that from the United

    Kingdom (BS 5950(1990)), Europe (Eurocode 4:

    ENV 1994-1-1:1994), and Canada (CSA

    S16:2001), recommendations for changes to the

    design provisions and to the equations for

    determining the capacity of headed, welded shear

    studs have been made. The latter were basedinitially on a review of the international standards

    mentioned above and an experimental testing

    programme was undertaken.

    Figure 2.1. Concepts of composite construction

    (Oehlers and Bradford 1995).

    That programme has led to further recommended

    changes to the shear stud capacity equations. The

    end result has been minor changes to the composite

    beam design provisions and a revision to the

    equations for determining shear stud capacity. The

    overall effect will be more accurate determination

    of the number of shear studs needed in a composite

    beam. Further areas of required research have also

    been identified.

    This paper firstly reviews, in section 2, the concepts

    involved in composite action. This includes the

    strength of shear connectors in solid slabs and in

    profiled slabs, covering the various failure modesidentified in the literature.

    While one of the main drivers behind this research

    was concern over the design capacity of shear studs

    as predicted by (NZS 3404:1997), it is important to

    note that the calculated shear strength of a welded

    stud is only one of the factors that determines the

    shear stud numbers and positions required in a

    composite beam. The first stage of the research

    therefore involved a comparative calculation study

    of the design requirements for a range of steel

    beams designed to New Zealand, British, European

    and Canadian practice. Section 3 presents details of

    this work. The conclusions from this research are

    presented in section 7, followed by the references.

    2. CONCEPTS OF COMPOSITE

    CONSTRUCTION

    2.1 Composite Steel-Concrete Sections:

    Composite construction is based upon connecting a

    concrete slab to a steel beam so that the twoelements act as one. By placing the steel beam in

    tension, the high tensile strength of the beam can be

    fully used, and the possibility of buckling of thin

    steel members can be reduced. Likewise, by placing

    concrete slabs in compression, the disadvantage of

    weak concrete tensile strength can be avoided and

    the advantage of good compression strength/cost

    fully utilised. Also, concrete slabs have good sound

    and fire insulation properties. A common form of

    construction is to use a steel beam to support the

    slab, as shown in figure. 2.1(a) and (b). It has been

    found that by bonding the steel beam to the

    steel/concrete interface

    strain distribution

    composite beam

    A

    (a)

    reinforced-concrete slab

    A

    (c)composite slab

    steel decking or profiled sheet

    composite beam

    steel beam

    (b)

    A-A

    B C B

    C

    concrete

    B

    cold formed ribs

    weff

    x

    x

    (a) Full composite beam

    beff

    Profiled, cold - formed steeldecking.

    (a) Full composite beam-strain distribution.

  • 7/28/2019 Shear Stud Cap in Steel Decks

    3/20

    concrete slab by shear connectors, the flexural

    strength and stiffness of the beam can be at leastdoubled (Oehlers and Bradford, 1995). This in turn

    leads to an increase in the span to depth ratio that

    can be used.

    Figure 2.1 (a) shows the strain distribution

    associated with full interaction between the steelbeam and the concrete slab. In this instance, there is

    no interface slip between them. In practise, a

    limited degree of interface slip is usually allowed

    and incorporated into the design; this is known as

    partial composite action.

    Another type of composite structure is formed

    when profiled steel decking is used as a permanent

    formwork for a concrete slab and is designed to act

    integrally with the concrete so that the two

    components act as one, as shown in figure 2.1 (c).

    Figure 2.2 Composite beam with profiled steel

    decking.

    The most commonly used composite section is the

    one that connects the concrete slab with the steel

    beam by welding connectors between them to

    achieve composite action, as shown in figure 2.2.

    The connector is welded through the troughs of the

    profiled decking to the flange of the steel beam

    (Oehlers and Bradford, 1995). The ribs of the

    profiled decking, through which the interaction

    Figure 2.3 Shear stud and transfer of connector

    force (Oehlers and Bradford 1995)

    between the steel decking and the concrete is

    achieved, can be placed either parallel, or

    transverse to the steel element. New Zealand is one

    of the very few countries to have all-weather stud

    welding capability, which elevates the economic

    viability of headed studs when compared with other

    anchor types as it allows these to be welded through

    the deck or directly onto the beam even in wetweather. The study reported herein focuses on this

    type of composite construction and specifically on

    the connector between steel beam and concrete slab

    known as the headed, welded shear stud (hereafter

    referred to as a shear stud).

    2.2 Shear Stud.

    The shear stud, as shown in figure 2.3 (a), is the

    most commonly used shear connector in composite

    construction. The shank and the weld-collar

    adjacent to the steel flange are designed to resist the

    longitudinal shear force, whereas the head is

    designed to resist the tensile force that is normal to

    the steel/concrete interface and to engage the

    concrete. The shank diameter of headed studs

    ranges from 10mm to 22mm. The most commonly

    used is the 19mm diameter. The length of headed

    studs before welding varies from 55mm to 250mm.

    After welding the stud length will have decreased

    by 3mm to 11mm, depending on the stud diameter

    and the stud application, i.e. welding through

    decking burns off some 2-4mm more than cleanbeam welding (Clifton, 1998).

    Oehlers and Bradford (1995) noted that shear studs

    are simply steel dowels embedded in a concrete

    medium. As the concrete slab tries to slip relative to

    the beam, the stud imposes a very high

    concentrated force, which is transferred from the

    dowel action of the stud into the concrete, as

    illustrated in figure 2.3(b). The resistance of a stud

    to this dowel action is known as the dowel strength,

    and this strength is specified in the New Zealand.

    Standard (NZS 3404:1997) as the nominal shear

    capacity of connectors. The dispersing of this

    force into the concrete element can induce tensile

    cracking particularly when the connector is also

    (c) plan view of slab

    showing crack formation

    Theight

    (a) stud

    diameter

    (b) dowel action

    C

    embedment

    cracking

    weld collar

    shank

    headsteel dowel

    steel element

    concrete element

    ripping

    C

    T

    shear splitting

    steel

    concrete

    Transversecracking

    Splitting

    Longitudinal

    (a) Ribs Parallel

    (b) Ribs Transverse

    Composite Slab

  • 7/28/2019 Shear Stud Cap in Steel Decks

    4/20

    resisting separation at the steel/concrete interface of

    the composite beam, which in turn is caused bytransverse cracking, shear and longitudinal splitting

    actions. Figure 2.3 (b) shows the tensile cracks that

    are also known as embedment cracks, and figure

    2.3 (c) shows the dispersal of the dowel action

    inducing a longitudinal splitting crack.

    These forms of tensile failure of the slab can affect

    both the dowel strength and ductility of the shear

    connection. With the absence of reinforcing bars

    crossing the planes of cracking, the strength of the

    dowel reduces immediately after cracking occurs

    and the slip capacity is also reduced. On the other

    hand, the presence of reinforcement across a crack

    plane makes failure more ductile and even allows

    increases in stud shear resistance after cracking.

    2.3 Mechanism of dowel action.

    Figure 2.4(a), from (Oehlers and Bradford, 1995),

    demonstrates the transfer of longitudinal shear by

    dowel action of shear studs. That figure shows the

    resulting mechanism where the stud is forced to the

    right when the steel beam moves to the right,

    causing the stud to bear on the concrete to the right

    of the stud. For the dowel action to work, the

    concrete adjacent to the bearing zone has to

    withstand compressive stresses up to seven times

    the cylinder strength, fc, which is only achieved by

    the triaxial restraint imposed on the region by thesteel element, the stud and the surrounding

    concrete.

    The resultant force in the bearing zone in figure

    2.4(a) is F, the centroid of which occurs at an

    eccentricity, e, from the steel/concrete interface.

    There is horizontal equilibrium between the force F

    and the shear force in the steel element and, to

    maintain the rotational equilibrium, a moment is

    induced at the base of the stud. Therefore, the steel

    stud must resist both flexural and shear forces,

    Figure 2.4 Dowel mechanism (Oehlers and

    Bradford 1995)

    which are the cause of high tensile stresses in the

    steel failure zone shown in figure 2.4 (c). Due to

    these forces the concrete can crush in the bearing

    zone and the steel can fracture in the steel failure

    zone, therefore the mechanism of dowel failure is

    governed by the interaction between the steel and

    concrete failure zones. This can be best described

    by considering the equivalent dowel mechanism infigure 2.4 (b). As shown in figure 2.4 (b), the dowel

    behaviour can be considered to be a steel beam

    resting on a concrete medium (Oehlers and

    Bradford, 1995), where section a-a at the midspan

    of the steel beam in figure 2.4(b) is equivalent to

    section a-a at the steel/concrete interface in figure

    2.4(a).

    Consider the distribution of pressure at the

    steel/concrete interface in (b), for a constant applied

    force 2F and for different configurations of the

    material properties. When the steel modulus Esapproaches infinity, the pressure at the interface can

    be considered uniform and hence the resultant force

    F in one shear span will act at an eccentricity e=h/2.

    The section at midspan has therefore to resist a

    shear force F and a moment Fh/2, and the dowel

    strength of the stud is determined at this section.

    Conversely, when Es approaches zero, the steel

    beam can be visualized as a layer of paper such that

    the resultant interface force in one shear span is

    now almost in line with the applied force, so that e

    tends to zero. Therefore, the midspan of the beamnow only resists a shear force F. It can therefore be

    seen that as Es increases relative to the concrete

    modulus Ec, shear stud capacity reduces because

    the flexural component Fe at midspan increases.

    On the other hand decreasing Ec is equal to

    increasing Es, by increasing e which in turn

    increases the flexural component Fe therefore

    reduces the shear stud capacity. Therefore, the

    shear stud capacity is proportional to the modular

    ratio parameter Es/Ec, no matter what the shape or

    size of the steel dowel.

    (b) equivalent dowel mechanism

    mid-span

    steel beam Es,fu

    (a) dowel mechanism

    FFe

    a ae

    cracktip

    concrete medium

    Ec,fc

    shear stud Es,fu

    F

    2F

    F1h F

    (c) dowel mechanism with weld collar

    Fe1

    concrete medium

    Ec,fc

    dh

    a a

    F

    e

    e

    steel failure

    zone

    e2F2

    concrete

    bearing zone

    dsh

    weld collar

    h co

    h st

  • 7/28/2019 Shear Stud Cap in Steel Decks

    5/20

    Since the studs are welded into the steel element

    and specifically in the flange of the steel beam, aweld collar with a diameter of about 1.3 times the

    shank diameter dsh and a height of about 0.3 dsh,as

    shown in Figure. 2.4 (c), is formed. This collar

    increases the shear stud capacity by increasing the

    bearing surface at the stud/concrete interface, which

    in turn reduces the stresses in the concrete for agiven force F. It also increases the shear stud

    capacity by raising the steel failure zone so that it

    occurs at the weld-collar/shank interface. Raising

    that zone will subject the zone to a portion F2 of the

    total shear force F. The weld collar also reduces the

    flexural stresses at the failure zone since the

    eccentricity e2 of F2 in (c) is less than the

    eccentricity e of F in (a).

    2.4. Strength of Shear Stud Connectors.

    2.4.1 Introduction.

    Since the stud is embedded in concrete, the shear

    stud capacity is dependent on the properties of the

    concrete slab in addition to the properties of the

    steel stud. If the concrete in the bearing zone splits

    or crushes, it will cause the base of the stud to

    move forward, while the head of the stud remains

    in the previous position. This will lead to a larger

    slip at the steel beam/concrete slab interface than

    that caused only by the deformation of the stud.

    This failure may also lead to rotation of the stud,whichwill generate flexural rotation actions and anadditional axial tensile force in the stud. The

    magnitude of this axial tensile force increases as the

    rotation of the stud increases, tending to pull the

    stud out of the concrete, according to (Hyland, et.

    al., 2000). The strength of the concrete that resists

    stud pullout is called the embedment strength of the

    shear stud, while the strength of the concrete that

    resists local splitting is known as Vsplit.

    If the shear stud doesnt fail in a push-through test

    by pulling out of the concrete (i.e. by embedment

    failure, in which the stud pulls out of the concrete

    along with a cone of surrounding concrete), then it

    will fail either through concrete crushing/stud

    fracture or through longitudinal splitting. The first

    case is governed by the dowel strength of the stud

    in uncracked concrete and this is described in

    section 2.4.2. The second case is covered in section

    2.4.3.

    2.4.2 Dowel Strength of Shear Studs in

    Uncracked Concrete

    Ollgaard, et. al. (1971) pioneered research on the

    dowel strength of shear stud connectors, and

    identified the important parameters that control the

    dowel strength. Using statistical analysis, they

    derived an equation to determine the mean dowel

    strength of shear stud connectors in push off

    specimens, in which the concrete slab had not failed

    prematurely through splitting, shear or embedment.

    This equation for the dowel strength as dictated by

    concrete crushing, Dmax, is given by:

    44.0c

    3.0cshmax EfA83.1D = (2.1)

    where the units are in N and mm, Ash is the cross-

    sectional area of the stud shank and Ec is theYoung's modulus of elasticity of the concrete,

    which is given by equation 2.2a

    c5.1

    c f043.0E = (2.2a)

    However, New Zealand Standard (NZS 3101:1995)

    gives another expression for Ec

    ( )5.1

    cc2300

    6900f3320E

    += (2.2b)

    where Ec and cf are in N/mm, and is the density

    of the concrete in kg/m3. There is not much

    difference between these two expressions,

    In adapting equation 2.1 to design use, the

    exponents were changed to make the equation

    dimensionally correct and simpler, although this led

    to a loss of accuracy. The altered equation is

    cc

    2sc

    ccscmax Ef8

    dEfA50.0D

    == (2.3)

    Certain types of stud welding procedure produce

    very small or no weld collars, and it would beunsafe to use equation 2.3 directly to determine

    their strengths. It was therefore suggested that theshear strength given by equation 2.3 should be used

    in conjunction with a reduction factor when the

    mean height of the weld collar is less than d sh/5(Oehlers and Bradford, 1995). The reduction factor

    Rco is given by

    sc

    coco

    d3

    h5

    3

    2R += (2.4)

    where hco is the mean height of the weld collar, anddsc is the shank diameter of the stud.

    Equation 2.3 was adopted by (NZS 3404:1997) forcalculating the nominal shear capacity of headed

    studs, along with a steel profile reduction factordc,as determined by (Slutter and Discoll, 1965). That

    factor related to the reduction in stud strength in a

    ribbed slab. Including dc, as specified in section13.3.2 of the standard, this gives:

  • 7/28/2019 Shear Stud Cap in Steel Decks

    6/20

    dcscuccscdcr AfEfA5.0q = (2.5)

    where qr is the nominal shear capacity, and Asc is

    the cross-section area of the stud shank which is

    equivalent to Ash in equation 2.3. dc is the deckingreduction factor, fu is the minimum tensile strength

    of the stud, which is equal to 415 MPa for studs

    manufactured to AS 1443 grades 1010 to 1020 orASTM A108 grades C1010 to C1020. A strength

    reduction factor (sc)is used to obtain the designcapacity of headed studs, which is equal to 0.8 for

    studs situated in positive moment regions and 0.6for studs situated in negative moment regions.

    The expression fuAsc in the second half of equation

    2.5 represents shear stud failure, i.e. due to steel

    failure in the zone shown in figure 2.4 (c). As

    described below, such steel failure is principally an

    ultimate shear failure and as such is over-estimatedby the expression fuAsc. This was fortuitouslyrectified through the incorporation of the partial

    strength reduction factor of 0.8, introduced into the1992 edition of NZS 3404. However, in the case of

    shear stud failure, that 0.8 should be part of the

    equation itself.

    Amendment No. 1 (2001) for Clauses 13.3.2.1 and

    13.3.2.2 stated changes to be made on equation 2.5

    by multiplying the reduction factor (sc) by (1/0.8)and (qr) by (0.8), as shown in equation 2.6. This

    brings the factor (0.8) directly into the equation for

    determining shear stud nominal capacity, which

    provides better agreement with experimental resultsissued in (Hyland, et. al., 2000) and makes the

    embedment equations;

    dcscuccscdcr Af8.0EfA4.0q = (2.6)

    In (Clifton, 2002), another recommendation to

    replace equation 13.3.2.1 of (NZS 3404:1997),

    shown here in equation 2.6, by:

    scuccscdcr Af8.0EfA5.0q = (2.7)

    This more correctly represents the dowel strength

    of a stud in solid concrete, with the left-hand side ofthe inequality representing concrete crushing and

    the right hand side shear failure, of the steel stud atthe top of the weld collar.

    For ribbed slabs, it has been noted (Slutter and

    Driscoll, 1965) that the shear stud shear capacity is

    reduced, with the reduction dependent on the

    orientation of the ribs. This reduction factor has

    been established experimentally, example equation

    2.8 for ribs perpendicular to the steel beam, (Grant,

    et. al., 1977), which has been adopted by (NZS3404:1997).

    =

    rc

    r

    rc

    sc

    rc

    dch

    b1

    h

    h

    n

    85.0(2.8)

    where nrc is the number of studs in a rib, hsc is the

    total height of the stud, hrc is the height of the rib

    and br is the mean width of the rib. However, thereduction factor given in draft Eurocode 4 (Johnson

    and Anderson, 1993) is more conservative, using

    0.7 as a reduction factor instead of 0.85

    =

    rc

    r

    rc

    sc

    rc

    dch

    b1

    h

    h

    n

    7.0(2.9)

    Equations 2.8 and 2.9 are presented as representing

    the reduced dowel capacity of the shear studs. They

    are experimentally determined on the premise that

    the concrete does not undergo longitudinal splittingat the base. However, review of the pictures from

    the Canadian push-off tests (Jayas and Hosain,

    1988) indicate that splitting was the likely limiting

    mode of failure for their tests. It is therefore

    considered likely by the authors that the Canadianreduction equations represent a splitting-induced

    loss of shear stud capacity due to the profiled natureof the concrete slab. The equation for primary beam

    application-which is not presented herein- is alsobased on a test configuration that is not

    representative of that used in practice.

    Given that splitting strength can often govern the

    shear stud capacity, the background to this is nowgiven.

    2.4.3 Splitting Strength of Concrete.

    a. Primary Beam.

    Splitting of the concrete happens when the high,concentrated dowel stress formed by the shear stud

    is dispersed laterally into the concrete element, as

    shown in figure 2.3(c). This dispersion isrepresented by the arrows marked as C and, to

    maintain equilibrium transverse tensile stresses are

    induced in the concrete, represented as T. When

    these transverse tensile stresses exceed the splitting

    tensile strength of the concrete, fcb, longitudinalcracks will form in the concrete prism in the

    bearing zone along the line of the shear connectors.

    The splitting tensile strength of the concrete fcb isobtained from cylinder split tests, as given by the

    following equation:

    ccb 'f5.0f = (2.10)

    A detailed background to the shear splitting

    provisions is given in section 11.3 of (Oehlers and

    Bradford, 1995). The relevant equation for the

  • 7/28/2019 Shear Stud Cap in Steel Decks

    7/20

    nominal concrete splitting resistance of a haunch ofconcrete of width bce is given by:

    +=

    c

    a

    2

    c

    a

    cbasc

    d

    cbeqce

    split

    h

    h

    h

    h1

    fhd6.0

    k

    fhb6.0V (2.12)

    where:

    bce = concrete effective haunch width,

    ha = 1.8dsc, effective stud bearing height. (2.13)

    fc = characteristic concrete cylinder compressionstrength (MPa).

    dsc = diameter of welded, headed shear stud (mm).

    Vsplit = nominal splitting capacity (N).

    kd =

    2

    ce

    sc

    b

    d1

    1

    , lateral force parameter. (2.14)

    hc = effective haunch height for splitting = min

    (4.5ha, to).

    The following dimensional constraints are requiredfor equation 2.12 to be valid:

    bc 3dsc (2.15)hc 3ha = 5.4dsc (2.16)

    hsc hc (2.17)

    where:

    bc = actual width of insitu concrete into which the

    shear stud is embedded (mm)

    hsc = height of shear stud after installation (mm)

    In addition, especially for individual concrete ribs

    containing studs, hsc 4.5ha = 8.1dsc is highly

    desirable, as this places the head of the stud, whichacts as the anchor for preventing vertical slip of the

    stud within the concrete, outside of the region ofhigh compression bearing stress where splitting

    initiates. This has benefits in increasing the post-

    splitting shear capacity, as given by (Oehlers andBradford, 1995).

    b. Secondary Beam.

    Splitting failure in the secondary beam

    configurations, ribs transverse to the beam, has

    been represented by some researchers as concretepullout failure. (Hawkins and Mitchell, 1984)

    proposed the following equation:

    ccc A'f45.0V = (2.18)

    where:

    Vc = shear capacity due to concrete pull-out failure(N).

    fc = concrete compressive strength (MPa).Ac = area of concrete pull out failure surface (mm

    2).

    Jayas and Hosain (1988) made further researchbased on this equation for 38 and 76mm decks,where they found out that instead of a fixed value

    of 0.45, separate coefficients should be used for the38 and 76mm decks.

    However, in our push-off tests on the secondary

    beams, the governing failure mode for thesecondary beam studs was a splitting failure mode,

    as shown by the classic longitudinal splitting crack

    developing in the concrete slab (see section 6.2).

    This has been approached through the use of

    equation 2.12, obtaining Vsplit experimentally and

    then back calculating to obtain the effective haunchwidth, for the secondary beam, bce,sb.

    3. COMPARATIVE CALCULATION PRIOR

    TO EXPERIMENTAL TESTING

    3.1 Introduction and Scope.

    When designing a composite beam, many factors

    govern the selection of steel beam size and the

    number of shear studs required. These factors maymean that a significant change in shear stud design

    shear capacity may not make much difference to thenumber of shear studs required for a given beam

    span, configuration and loading.

    The purpose of the comparative calculations was to

    determine the number of shear studs required for arange of typical primary and secondary beams

    designed in accordance with the strengthrequirements of new Zealand, Canadian, British

    and European standards. The range of parametersused in this study are given in Table 3.1.

    Each beam was designed to meet all the strengthand serviceability requirements of current New

    Zealand practise (NZS 3404:1997) and (Clifton,2002). The software HiBond Design Wizard, which

    covers use of the 55mm high trapezoidal deckingprofile used in the study, based on (NZS

    3404:1997), was used to achieve this.

    Having undertaken these designs and determined

    the number of shear studs required, the number of

    shear studs required for the same beam size andapplied loads to the requirements of the current

    Canadian Standard, British Standard and European

    Standard were then determined.

    The results of these comparisons were then

    tabulated in order to compare the current NewZealand requirements with those of three major

    international composite standards. This was done in

    order to give an indication as to the combined effect

    of the many parameters influencing the number ofstuds required on the design solution and to see

    what influence any change in shear stud design

  • 7/28/2019 Shear Stud Cap in Steel Decks

    8/20

    shear capacity would have against currentinternational best practice.

    Parameter

    Live Loads 3.5 kPa & 5 kPa

    Beam Span 8 m & 15 m

    Propping No

    Precambered NoPartial Shear

    Connection

    As stated in the respective

    Standard

    Slab Span 2.8 m

    Thickness 120 mm

    Deck Type 55 mm trapezoidal profile.

    Stud Height 100 mm

    Stud Diameter 19 mm

    Stud fu 415 MPa

    Concrete fc 25 MPa

    Table 3.1 Parameters used in the Study.

    Section 3.2 presents the New Zealand requirements

    for determining the ultimate limit state capacity of asteel beam and the number of shear studs required.

    Section 3.3 presents an overview of the strength

    design requirements of the other Standards used,

    highlighting the differences between these and the(NZS 3404:1997) requirements.

    Section 3.4 gives some of the comparative results,first in terms of shear stud design capacity and

    secondly in terms of the number of studs requiredin each beam size. Full details are in (Zaki, 2003).

    Following this work initial recommendation were

    proposed for the shear stud design shear capacityand also for the partial shear connection limits, inorder to keep the net changes to as-built details to a

    minimum. The initial recommendations arising atthe end of the comparative calculations are given in

    section 3.5.

    3.2 New Zealand Provision for Calculation of the

    Composite Ultimate Limit State Design Moment

    Capacity, Mrc

    This involves the following general steps:1. Calculation of the factored design loads and

    design actions (moment and shear).

    2. Calculating the maximum axial compressionand tension capacity of the various composite

    section components, known as componentcapacities.

    3. Calculating the shear stud capacity based on theorientation of decking and number of studs per

    set.

    4. Determining the percentage of compositeaction (PSC) to use.

    5. Calculation of the plastic neutral axis andcomposite section properties.

    6. Calculation of the nominal composite moment

    capacity.7. Multiplying by the global strength reduction

    factor to give the design composite momentcapacity.

    The full details of this procedure are given in

    section 2.2 of (Clifton, 2002).

    3.3 Design for Strength to Chosen International

    Standards.

    These international standards all follow the same

    general design procedure, with certain differences

    based on their specific development. These

    differences to the New Zealand requirements are

    given in section 3.3.1 to 3.3.3:

    One significant difference between all three

    international standards and New Zealand practice is

    the use of global strength reduction factors in New

    Zealand and the partial strength reduction factors inthe three international standards.

    In New Zealand, the design shear capacity of the

    shear stud (which does incorporate a partial

    strength reduction factor, although this is 1.0 forstuds in positive moment regions) is matched to the

    nominal component capacity when determining thenumber of shear studs required. The nominal

    moment capacity is determined and converted todesign moment capacity through the use of a global

    strength reduction factor.

    In the three international standards, the nominal

    capacity of the shear studs and internal componentsis converted to the design capacity through the use

    of a partial strength reduction factor, which ismaterial specific. (Typical values, from Canadian

    practice, are 0.8, 0.6, and 0.9 for the shear stud,concrete and steel beam components respectively).

    The design capacity of shear stud is matched to the

    design component capacity when determining the

    number of shear studs required. The design moment

    capacity of the composite section is then

    determined directly.

    This has important implications when determining

    the number of shear studs required by eachprocedure, as discussed in sections 3.4 and 3.5.

    3.3.1 Canadian Code (CSA S16-01: 2001).

    The first difference is the load factors where (1.25)

    is used for the dead load and (1.5) is for the live

    load (Clause 7.2.4). This is the same as for(AS/NZS 1170.1:2002) and is not a critical

    difference. The minimum shear connection ratio,

  • 7/28/2019 Shear Stud Cap in Steel Decks

    9/20

    (PSCmin), allowed is 40% and for the componentcapacity there is a factor of (0.6) added to thenominal concrete capacity in compression (Nccc)

    (Clause 17.9.3) and a factor of (0.9) for the nominaltensile steel capacity (Ntsc) (Clause 17.9.3). Finally,

    the shear stud capacity for the secondary beam iscalculated according to the following equations:

    uccscr Q'fA35.0q = 76mm decking. (3.1)

    uccscr Q'fA61.0q = 38mm decking. (3.2)

    where:

    qr= shear stud capacity.

    sc = factor that depends on the concrete type.(Clause 17.7.1). For normal weight concrete,

    positive moment action it is 0.8.

    Ac = area of concrete pullout surface (cone).

    Qu = Ultimate shear capacity, which is the

    following equation.

    ccscscu E'fA5.0Q = (3.3)

    While the primary beam equation is:

    uscscc'cscscr fAEfA5.0q = (3.4)

    3.3.2 British Standard (BS 5950:Part3:Section

    3.1:1990).

    The BS 5950:Part 3 differences with New Zealand

    practice are as follows. First the load factors are(1.4) used for the dead load and (1.6) for the live

    load. The minimum shear connection ratio (PSCmin)

    is taken from Clause 5.5.2 where up to 10m, PSCminis 40%, while for 16m and above it is 100%. For

    the spans between 10 to 16m, the followingrelationship between PSC and the span must be

    satisfied:

    ( )4.0PSCbut

    10

    6LPSC

    (3.5)

    where:

    PSC = Partial Composite Action.L = span in meters.

    As for the component capacity, the concrete

    compression stress is based on (0.45 fcu) fordetermining the design concrete capacity in

    compression (Nccc) (Clause B.2.1). To convert thecharacteristic cube strength of concrete (fcu) to

    cylinder strength (fc) a factor of (0.8) is used. Asfor the design tensile steel capacity (Ntsc) a factor of

    (1/1.1) is used (Clause B.2.1). Finally, the designshear stud capacity is calculated according to the

    following equation for both primary and secondarybeams, from Clause 5.4.3:

    kQ8.0Q kp = (3.6)

    where:

    Qp = Shear Stud Design Capacity.

    Qk = Characteristic resistance of the shearconnector, determined directly from experimental

    testing and read from a table.0.8 = strength reduction factor.

    k = reduction factor = 1.0 for both secondary andprimary beam configurations using 55mm

    trapezoidal decking.

    3.3.3Eurocode 4 (DD ENV 1994-1-1: 1994).

    The Eurocode also has similar differences to the

    British Standard. The load factors used are the same

    as the British (1.4) for dead load and (1.6) live load,

    while the shear connection ratio (PSC) is given byClause 6.1.2(2). Up to 10m, PSCmin is taken as

    40%, while for 25m and above its taken as 100%.

    For the spans between 10 to 25m the followingrelationship between PSC and span must be

    satisfied:

    L04.0PSC (3.7)

    Partial strength reduction factors of (1/1.5) are used

    on the calculation of design concrete capacity incompression (Nccc) (Clause 2.3.3.2(1)) and (1/1.1)

    for the nominal tensile steel capacity (Ntsc) (Clause

    2.3.3.2(1)). The shear stud capacity is given by the

    minimum of the following equations for both

    primary and secondary beams, from Clause 6.3.2.1:

    v

    2sc

    u1r 4

    d

    f8.0kq

    = (3.8)

    v

    cc2sc2r

    E'fd29.0kq

    = (3.9)

    where:dsc = diameter of shear connector.

    k= constant

    3.3.4 Comparative results.

    According to (Lin, et. al., 2001) the New Zealand

    Standard clearly overestimated the shear studcapacity, as shown in Figure.3.1, where the

    difference between the New Zealand Standard

    (NZS 3404:1997), the Canadian Standard (CSAS16-01:2001, added by the author) and test results

    from (Lin et. al., 2001) are clearly demonstrated,for 30 MPa concrete.

    The Canadians recognised the unconservative

    nature of their (CSA S16-01: 1984) shear stud

    capacity equation for secondary beam

    configurations, which prompted (Jayas and Hosain,

  • 7/28/2019 Shear Stud Cap in Steel Decks

    10/20

    1988) to undertake research on the shear studcapacity. In (Jayas and Hosain, 1988) they

    proposed the changes to the shear stud capacity

    equation for secondary beams from that given forprimary beams (equation 3.4) to the new equation

    3.1 and 3.2. This was followed by a full size test,details of which are published in (Jayas and Hosain,

    1989). These changes were implemented in theCanadian Code (CSA S16-01: 2001), in Clause

    17.7.2.3. As can be seen from Figure 3.1, these

    equations predicted much lower shear studcapacities than the (NZS 3404:1997) provisions,

    leading to the potential requirement for more studs

    on a given beam.

    The results of the comparative calculations are

    presented in (Zaki, 2003) with details of 2 cases

    given in Tables 3.1 and 3.2 below. These show the

    difference between the various standards for deck

    and strength reduction factors, shear stud capacity,number of studs required for the given beam and

    shear connection ratio used. The designation

    numbers 8/10/3.5 mean that the secondary beam

    length was 10 m, primary beam length 8 m and theload acting on the tributary area 3.5 kPa.

    Figure 3.1. Shear force-slip history for fc= 30 Mpa

    (taken from Figure 5.13-unit 120/N30/19R/12F/02

    (Lin, Y., et. al., (2001) with addition by author).

    In Table 3.1.a, even though the New Zealand

    determination for the primary beam shear studcapacity is higher than the rest, the number of studs

    used is less than the number of studs required by

    the British and Eurocode, as the PSC% used islower in this instance. Table 3.1.b shows that,

    although the New Zealand procedure gives the

    greatest shear stud capacity for this secondarybeam; the estimated number of studs is nearly

    similar to the other standards. This is largely

    determined by practical considerations of studspacing in a secondary beam supporting a profiled

    steel deck. Looking at table 3.2.a, the New Zealand

    shear stud capacity is still higher than the rest, but

    the number of studs is higher, as it took a 100%PSC to make the primary beam work. Table 3.2.b

    still has a high capacity, but the PSC is lower than

    the British and Eurocode, as they are governed byClause 5.5.2 and clause 6.1.2(2) respectively intheir respective standards, (BS 5950:Part3: Section

    3.1:1990) and (DD ENV 1994-1-1: 1994). Thesestate that the PSC is taken as a minimum of 40% till

    10m increasing to 100% at 16m and 25mrespectively. Minimum PSC ratio is typically a

    governing factor for secondary beam stud numbers.

    These comparisons show that research to improve

    the New Zealand composite design provisionsshould not just be limited to shear stud capacity but

    should address the following:

    1. The minimum value of PSC required.

    2. Whether factors should be added to the

    calculation of Nccc and Ntsc to be consistent

    with the approach used by the other standards

    that use partial material strength reduction

    factors to match design shear stud capacity todesign internal action.

    3.4.Initial Recommendation

    At the conclusion to the comparative studies, the

    recommendations on all these considerations

    proposed were as follows:

    1. For shear stud nominal shear capacity insecondary beams, use the new Canadian

    equations equations 3.1, 3.2 withinterpolation as required and equation 3.3. Use

    sc = 1.0 as for New Zealand practice.2. For shear stud nominal shear capacity in

    primary beams, use equation 2.7 and determine

    the potential for rib splitting from experimentaltesting.

    3. For limits on PSC, change to the Eurocode

    provision.4. Do not make changes to the calculation of

    component capacities and the matching ofshear stud design capacity to component

    nominal capacity.

    The next stage of this project involved an

    experimental testing programme to determine shear

    stud nominal and design shear capacity when used

    in a 55 mm deep trapezoidal deck concrete slab in a

    primary and in a secondary beam configuration.

    0

    30

    60

    90

    120

    150

    0 2 4 6 8 10 12 14 16 18 20

    Mean slip (mm)

    Shearforce/stud

    (kN)

    123 kN (NZS 3404)

    83 kN (80% of max)

    104 kN (max)

    73.2 (CSA S16-01)

    128 kN (Eq 2.6 )

    58 kN (splitting)

  • 7/28/2019 Shear Stud Cap in Steel Decks

    11/20

    Code Deck R.F. Strength R.F. Capacity No of Studs PSC%

    NZ 1 1 94.1 42 70

    Canada 1 0.8 89.5 28 75

    UK 1 0.8 76 49 100

    Eurocode 1 0.8 66.2 56 100

    Table 3.1.a. Primary Beam 8/10/3.5.

    Code Deck R.F. Strength R.F. Capacity No of Studs Practical No Studs* PSC%

    NZ 1 1 94.1 24 34 50

    Canada 0.54 0.8 68.5 24 34 40

    UK 1 0.8 76 23 34 42

    Eurocode 1 0.8 66.2 26 34 42

    * Practical number of studs is dictated by 1 stud per deck rib.

    Table 3.1.b. Secondary Beam 8/10/3.5

    Code Deck R.F. Strength R.F. Capacity No of Studs PSC%

    NZ 1 1 94.1 59 100

    Canada 1 0.8 89.5 29 80

    UK 1 0.8 76 39 80

    Eurocode 1 0.8 66.2 51 90

    Table 3.2.a. Primary Beam 8/15/5.

    Code Deck R.F. Strength R.F. Capacity No of Studs Practical No Studs PSC%

    NZ 1 1 94.1 42 49 50

    Canada 0.54 0.8 68.5 28 49 40

    UK 1 0.8 76 61 49 90

    Eurocode 1 0.8 66.2 47 49 60

    Table 3.2.b. Secondary Beam 8/15/5.

    4. SHEAR STUD TEST SET-UP

    4.1. Introduction

    Because of the complexity of composite action, ashas already been discussed in sections 2.3 and 2.4,

    the strength and ductility of shear studs are always

    determined experimentally. The details associatedwith the shear stud testing conducted at the

    University of Auckland are reported in this section.

    The test set-up adopted that previously used by(Butterworth, 2000), with changes made to the

    dimensions of the test units, the shape of the corbel,

    and the position of the test units on the test rig. Theshear force was applied by blocking one side of the

    test unit and adding a push force on the other side.The push force and the reaction force were

    positioned collinear with the steel-slab interface,

    such that the position of the test unit on the test righad no influence on test results.

    The associated details of the test set-up including

    test rig, test units, instrumentation, loading

    procedure, and corbel design are discussed insections 4.2 to 4.7.

    4.2. Shear Stud Testing Rig

    The test rig with mounted unit is shown in Figure.

    4.1. The frame had three components; the base

    frame, head frame and foot frame. The baseframe was bolted to the strong floor of the test hall.

    A 1000 kN jack was horizontally bolted to thehead frame. Centre lines of the push force and the

    reaction force were regulated by steel bearings,which were positioned collinear with the steel-slab

    interface and the horizontal stiffener in the head

    and foot frames.

    Test units were laid on packers with the slabpositioned on top and the steel section positioned

    underneath, representing the real situation.

    Thickness of the packers was carefully adjusted tomake the steel-slab interface collinear with the the

    centre line of the bearings (line of thrust). The steel

    corbel of the test units was positioned close to jack

    and the foot frame restrained the concrete corbel.

  • 7/28/2019 Shear Stud Cap in Steel Decks

    12/20

    Figure 4.1. Test rig with mounted test unit

    (Butterworth 2000)

    Slide rollers were placed between the packer and

    the lower surface of the steel beam, in order for the

    slab to freely slide during testing.

    4.3 Shear Stud Test Units

    4.3.1 General

    The push specimens are referred to here as shear

    stud test units. The test unit was composed of three

    main components steel beam, composite slab and

    studs. A typical shear stud test unit is shown in

    figure. 4.2, 4.3 and 4.4, for both secondary andprimary beams, with each test unit having small

    changes from that shown

    The design of shear stud test units adopted in thisresearch closely emulated the design used

    previously (Butterworth, 2000), although therewere some changes, these being:

    1. As a conventional profiled steel decking wasadopted in this study, the total thickness of the

    slab was much less than that previously tested,so studs with a length complying with (NZS

    3404:1997) Clause 13.3.2.2.1 (d)-ie hsc hr +

    40 mm were required. In this case hsc 95mmwas required.

    2. There was no concrete haunch over the steelbeam, which in previous testing had a width

    the same as the steel beam top flange.

    3. Especially for the secondary beam, stud

    spacing was controlled by the decking profile.

    4. Because of the reduced slab thickness, the

    section of the corbel became more critical, sothe corbel required redesign.

    5. Nominal mesh reinforcement complying with

    (NZS 3404:1997) was used.

    4.3.2 List of Shear Stud Test Units

    All test units used in this study are listed in Table

    4.1. Key results are presented in section 5, with full

    details in (Zaki, 2003).

    S is for the secondary beams and P is for theprimary beams. All the secondary beam slabs were

    1105mm by 1000mm with 120mm depth while the

    primary beams were 1240 mm by 1000 mm with

    120mm depth no matter how many studs were

    tested.

    For the secondary beams, Units S1, S2 and S3 are

    identical in the number of studs and concrete

    strength, while S4 has the same number of studs but

    different concrete strength. S5 has double thenumber of studs at the staggered position, while

    S6 has the same number of studs as the first 4 with

    a concrete strength of 25 MPa but the studs

    positioned in the unfavourable position.

    For the primary beams P2, P3 and P5 are identical

    while P1 is the same but with different concretestrength and finally, P4 has double the number of

    studs at double the spacing compared to P2, P3 andP4. These differences were intended to generate a

    good representation of shear stud capacity and test

    the influence of key parameters, but not change toomany variables to give meaningful results. Theshear connection devices used in this study wereheaded studs with a shank diameter of 19 mm and a

    before-weld length of 106mm, clean beam and 110mm through deck. These give an installed length of

    99-102mm in each instance.

    4.4 Loading procedure

    The test protocol was based on the Eurocode 4

    (1994) recommendation:

    1. Load the test unit to 40% of the expectednominal capacity (failure load) of the stud

    group.2. Cycle the load 25 times between 5% and 40%

    of the expected nominal capacity.

    3. Continue monotonic loading from 40%, such

    that 100% of the expected normal capacity isreached in under 15 minutes.

    4. Measure longitudinal interface slip

    continuously during loading, at least until theload has dropped to 20% below maximum.

    80 mm packers

    310UC158-HD bolts to strong floor

    610UB101295

    "foot" frame bearing

    610UB101loading plate

    "head" frame

    horizontal stiffer

    bearingload cell

    1000 kN jack

    2410

  • 7/28/2019 Shear Stud Cap in Steel Decks

    13/20

    5. Measure transverse separation between thesteel beam and the composite slab close to thegroup of shear studs.

    Summary Details of Test Units

    No. Code Slab

    Dimension

    fc No of

    Studs

    Comments

    1 S1 1105x1000x120

    25 3 Favourable

    2 S2 1105x1000x

    120

    25 3 Favourable

    3 S3 1105x1000x

    120

    25 3 Favourable

    4 S4 1105x1000x

    120

    30 3 Favourable

    5 S5 1105x1000x

    120

    25 6 Double

    Staggered

    6 S6 1105x1000x

    120

    25 3 Unfavourable

    7 P1 1240x1000x120

    30 4 Single Row

    8 P2 1240x1000x120

    25 4 Single Row

    9 P3 1240x1000x

    120

    25 4 Single Row

    10 P4 1240x1000x120

    25 4 Double Rowat Double the

    Spacing

    11 P5 1240x1000x120

    25 4 Single Row

    Table 4.1 Shear Stud Test Units.

    Figure 4.2 Unit 2 ready for concrete casting.

    Figure 4.3 Unit P2 ready for concrete casting.

    Figure 4.4 Test Unit S1 ready for testing.

    5. SHEAR STUD TEST RESULTS

    Reporting of the final shear force-slip history

    adopted the format shown in figure 5.1, while

    figure 5.2 is from the test results of unit S4.

    Figure 5.1 Typical shear force-slip history

    diagram.

    Figure 5.2 Unit S4 test results.

    The following observations were recorded during

    testing of the units. For the secondary beams, thecracks formed transverse to the beam especially at

    the first and third trough. The crack adjacent to the

    third trough typically was the first crack to form butdid not affect the results. The longitudinal crack,

    which is also shown in figure 5.3, typically formedat or near the peak shear stud strength achieved, it

    also shows an example of the crack formationtypical for a secondary beam. Delamination of the

    slab also occurred, figure 5.4, as well as an

    interesting phenomenon named the biting

    Phenomenon of the decking into the steel beam,

    see figure 5.5. Another interesting aspect of testingwas the wedging of the concrete between the

    0

    10

    20

    30

    40

    50

    60

    70

    80

    90

    100

    110

    120

    0 2 4 6 8 10 12

    Mean Slip (mm)

    Shearforce/stud

    (kN)

    100.21 kN (NZS 3404)

    86.6 kN (4.1)

    106 kN (max) and L1

    84.4 kN (80% of max)L2

    L3

    Mean slip (mm)

    Shearforce/stud

    (kN)

    Starting from end of first 25 cycles

    (qr)n (NZS 3404) (=1.0)

    Revised qr

    Q max (kN)

    80 % of max

  • 7/28/2019 Shear Stud Cap in Steel Decks

    14/20

    shear stud and the decking, see figure 5.6. Theseobservations were common for all secondary beamtest units.

    As for the primary beam, longitudinal cracks

    parallel to the beam occurred with curving of theslab due to the splitting of the concrete pushing

    against the stud. Figure 5.7 demonstrates thecurving while figure 5.8 shows the typical

    longitudinal cracks. Refer to (Zaki, 2003), Chapter

    6 for detailed observations of the test units.

    Figure 5.3 Secondary beam cracks.

    Figure 5.4 Delamination of the slab.

    Figure 5.5 Biting Phenomenon.

    Figure 5.6 Wedging of the concrete.

    Figure 5.7 Curving of the slab in the PrimaryBeam.

    Figure. 5.8 Primary Beam cracks.

    6. SHEAR STUD TEST RESULTS-

    DISCUSSION

    6.1. Introduction.

    This section discusses the shear stud failure modes

    and gives final recommendations for shear studcapacity and composite design provisions.

    6.2 Failure Mode.

    The main modes of failure described in theliterature are concrete pull out failure (stud

    embedment failure), concrete crushing failure,shear stud fracture, and concrete splitting failure.

    Of these, the major cause of failure in this series oftests was concrete splitting failure, with a case of

    concrete crushing and splitting (Unit P4) and two

    cases of a new mode of failure, which we arecalling Rolling Failure. This principally affected

  • 7/28/2019 Shear Stud Cap in Steel Decks

    15/20

    unit S2, which had Rib Rolling Failure and unitP3, which failed due to a construction defect. Thefollowing section talks about the reason why

    splitting and not cone pullout failure was the maincause of failure, even though the concrete cone

    shape was present in nearly all the units tested.

    6.2.1. Why Cone Pull Out Failure Was Not theMain Failure Mode.

    Our initial recommendations and calculations used

    to develop the test specimens were based on the

    Canadian study by (Jayas and Hosain, 1988 &

    1989) for the secondary beam, which in turn basedtheir equations on the reported embedment

    failure. For the primary beams, initial

    recommendations were based upon the longitudinal

    splitting concept from (Oehlers and Bradford,

    1995). However, embedment failure was not the

    observed failure mode for any of the specimenstested. Therefore a new set of recommendations has

    to be made, to better represent the failure mode that

    occurred in this series of tests. Embedment failure

    is the form of failure that always has a concretecone shape surrounding the shear studs where the

    concrete around the cone gets separated from the

    slab causing a drop in strength. It is not

    accompanied by a longitudinal splitting crack. In

    the tests conducted, although the cone shape waspresent in all the secondary beam units after

    dissecting the unit, it was not the observed failuremode that limited the stud shear strength. As

    previously reported, that was longitudinal splittingin all cases except for units S2 and P3 which failed

    prematurely and unit P4 which failed by combined

    crushing and splitting.

    Further support for this can be seen from a study ofthe parameters that govern embedment strength.

    According to (Oehlers and Bradford, 1995), theembedment strength is dependent on the ratio of the

    stud height to the stud diameter (see figure 6.1)

    while the strength can be derived from thefollowing equation.

    ( )beammaxhemb

    DKD = (6.1)

    Where, Demb is the shear strength that allows

    variation in shear embedment strength, Kh can be

    derived from line A-B-C in figure 6.1 and(Dmax)beam can be derived from equation 6.2.

    Equation 6.2 represents the strength of a shear stud

    in a solid concrete slab. It is also the original

    equation that (NZS 3404:1997) Equation 13.3.2.1 is

    derived from, as it incorporates both the concretecrushing and shear stud fracture resistance into one

    equation. It is determined from a curve fit of testdata on push-off tests in solid slabs, with allowance

    made for the test rig setup on the capacity. Details

    Figure 6.1 Shear Embedment Strength Relationship

    to find Kh (Oehlers and Bradford, 1995).

    are given in section (2.4.6.3) of (Oehlers and

    Bradford, 1995):

    ( )4.0

    s

    c35.0c

    65.0uscbeammax E

    EffA

    n

    1.13.4D

    = (6.2)

    where n is the total number of studs in the test

    sample. Using the values from experimental tests

    including the actual measured material properties,

    the Shear Embedment Strength is calculated and isshown in figures. 6.2 and 6.3 for the secondary and

    the primary beams, respectively.

    The values of the shear embedment strength (Demb)means that, if no other form of failure occurs before

    Demb is reached, then embedment failure will limit

    the available strength. However, with these studs,slab crushing and shear stud fracture would occur

    before embedment failure. In fact (Dmax)beam ,which

    incorporates both the concrete crushing and shearstud fracture, clearly was also greater than the testresults, demonstrating that the failure mode was notthe concrete crushing or fracture of the studs at the

    maximum stud strength. Therefore, according to the

    Figure 6.2 Comparison between the test results and

    the embedment, solid concrete failure modes for the

    secondary beams.

    results in Chapter 6 in (Zaki, 2003) and the

    comparison shown above in figures 6.2 and 6.3

    neither did shear embedment, concrete crushing or

    0

    10

    20

    30

    40

    50

    60

    70

    80

    90

    100

    110

    120

    130

    140

    0 1 2 3 4 5 6 7 8 9 10 11 12

    Mean Displacement (mm)

    Shearforce/stud

    (kN)

    (Dmax)beam = 123 kN

    Demb = 135.3kN

  • 7/28/2019 Shear Stud Cap in Steel Decks

    16/20

    Figure 6.3 Comparison between the test results and

    the embedment, solid concrete failure modes for the

    primary beams.

    stud fracturing initiate the failure, but longitudinal

    splitting did. It should be noted that stud fracture

    was observed in units S6 and P4, however this didnot occur until well after the peak load was reached

    and so was not the limiting factor in terms of stud

    design capacity. These results show that revision to

    (NZS 3404:1997) Equation 13.3.2.1 is needed.

    6.3 Proposed Revision of NZS 3404 Cl 13.3.2.1

    As mentioned in Section 2.4.3, equation 13.3.2.1 in

    (NZS 3404:1997) has been amended in 2001 fromthe old format of:

    dcscuccscdcr Af)Ef(A5.0q = (6.3)

    Into:

    dcscuccscdcr Af8.0)Ef(A4.0q = (6.4)

    where the first part is for concrete crushing while

    the second is for shear stud fracture. According toequation 6.3, from which this simplified equation is

    derived, the present equation 6.4 underestimates thetrue value of the concrete crushing. It is

    recommended that the equation 6.5, initiallyproposed by (Lin, et. al., 2001) as his equation 2.15,

    and referenced in (Clifton, 2002), be used:

    dcscuccscdcr Af8.0)Ef(A5.0q = (6.5)

    This equation gives a value that is consistent withthe test results and with the original equation putforth by (Oehlers and Bradford, 1995), equation

    6.2. Given that this is for a solid slab, dc=1.0 andthis term can be omitted giving equation 6.6 as the

    proposed replacement to NZS 3404 Equation13.3.2.1:

    scuccscr Af8.0)Ef(A5.0q = (6.6)

    Comparing equations 6.4, and 6.6 with 6.2 we getthe following results, using the actual material

    properties of the test:

    Ec = 24.8 GPa Asc = 283.4 mm2

    fu = 516 MPa fc = 24.3 MPa

    Eq. 6.4 qr= 88 kN 117 kN

    Eq. 6.6 qr= 110 kN 117 kNEquation 6.2 (Dmax)beam = 112 kN

    It is clear that equation 6.6 shows closer results toequation 6.2 than equation 6.4. Therefore, it is

    recommended that the present equation 13.3.2.1 in

    (NZS 3404:1997) should be amended to equation

    6.6, for welded studs in a solid concrete slab.

    6.4 Making Allowance for Concrete Splitting in

    Interior Beams.

    The experimental tests showed that concrete

    longitudinal splitting failure governed all tests

    involving a single row of studs, either in a straightline or staggered. The equation for calculating thesplitting strength, Vsh, of a stud within a concrete

    rib of effective width, bce, is given by (Oehlers and

    Bradford, 1995). Equation 2.12, which can betransformed into equation 6.8:

    +

    =

    c

    2

    c

    sc

    ce

    sc

    cecscsplit

    h

    8.1

    h

    d8.11

    b

    d1

    1

    b'fd54.0V

    (6.8)

    In this equation, bce is the effective width, dsc is the

    stud diameter, and hc the effective haunch height forsplitting, taken as the minimum of (5.4dsc,to), whereto is the slab height.

    In this instance, the actual splitting shear strength

    has been determined by experimental testing, using

    the process described on page 28, equation 55.26 of

    (Hyland, C., et. al. 2001).

    That equation is used to back-calculate and find the

    effective width, bce, for the interior secondary andprimary beam configurations.

    For the secondary beam, this results in the effective

    width using the results from our test. Resulting in

    the effective width being 440mm, for the presenttest conditions of the slab height being greater or

    equal to 120mm, stud height greater or equal to 4xthe stud diameter and stud diameter of 16 to 22mm.

    This effective width happens to be close to four

    times the stud height used in the tests. (Lin, et. al.

    2001) recorded that the concrete cone shape slope

    angle was around 24 to 29, while the slope anglefor this test with the effective width of 440 mm was

    0

    10

    20

    3040

    50

    60

    70

    80

    90

    100

    110

    120

    130

    0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21

    Mean Slip (mm)

    S

    hearforce/stud

    (kN)

    P2

    P4

    P5

    Demb = 125.4kN

    (Dmax)beam = 114 kN

  • 7/28/2019 Shear Stud Cap in Steel Decks

    17/20

    24.4. This indicated that there may be arelationship between effective rib width and studheight. Therefore, a recommendation future testing

    is to find if such a relationship between the stud

    height and effective rib width exists and itsinfluence on the shear stud capacity.

    Taking the effective width to be 440mm tocalculate the longitudinal splitting capacity, for the

    studs in the favourable position, another factor isrecommended to be added to this equation to make

    it consistent with the test results. This factor is the

    stud-positioning factor (sp)taken as:

    Favourable = 1.0

    Unfavourable = 0.94

    Double staggered = 0.84

    This factor is the position of the stud in the

    secondary beam, whether it is in the favourable,

    unfavourable or double staggered.

    Therefore, the recommended splitting equation tobe used for shear stud capacity estimation in the

    secondary beam configuration is:

    +

    =

    c

    2

    c

    sc

    ce

    sc

    cecscspsplit

    h

    8.1

    h

    d8.11

    b

    d1

    1

    b'fd54.0V

    (6.9)

    The following values and limits are required withthis equation:

    bce = 440 mmto 120 mm

    hsc 95 mmdsc from 16 mm to 22 mm.

    hsc/dsc 4.32

    Profile is 55mm trapezoidal deck. Where, bce =effective width to use for interior secondary beam

    (ie runs over decking).

    For the primary beam, splitting was clearly themain cause of failure for all single rows of studs.

    Therefore the recommended equation 6.8 is also

    used for the primary beam, back-calculating again

    to find the effective rib width. This is also 440mmfor the present test conditions of the slab heightbeing greater or equal to 120mm, stud height of

    greater or equal to 4 stud diameters, stud diameterof 16 to 22mm, and the deck fastened onto the

    beam flange within 10mm at the flange edge.

    Figure 6.4 demonstrates that edge distance. Thatequation is applicable to a single row of studs.

    It was noted in unit P1, which had 30 MPa concrete

    instead of 25 MPa, that the strength was 98 kN

    which was 1kN more than the equivalent specimenusing 25 MPa concrete. The unit S4, which was thesecondary beam with 30 MPa strength, was 106 kN

    which was approximately the same as the predictedvalue from equation 6.9. This difference in

    strength could be due to the different 30 MPa

    Figure 6.4 Edge distance of decking on Primary

    Beam.

    concrete batches used that were hand mixed, and

    might have had different compressive strengthsfrom the cylinder test values. It is an aspect for

    which future testing is recommended.

    Unit P4, with the double row of studs at doublespacing, clearly had a combination of crushing and

    splitting failure, as seen in figure. 6.5. The splitting

    crack is clearly seen, but is deflected by the stud,

    also the crushing of the concrete was also present.

    This is also consistent with the parameterscontrolling splitting, which show that a double stud

    row is not as susceptible to splitting is a single studrow.

    Therefore, for unit P4 which had double the studs at

    double the spacing, equation 6.6 is to be used to

    better represent the failure mode and it also givesthe best estimate for the shear stud capacity. Where

    equation 6.6 for crushing was 110 kN while our testresult was 104 kN, therefore equation 6.6 is slightly

    Figure 6.5 Crushing and splitting failure in unit P4.

    overestimating the value, which can be from the

    minimal splitting cracks that did occur but were

    deflected by the stud. A Double Stud safety

    factor of (0.9) is recommended until future tests are

    conducted to find the actual strength and whether afactor is needed or not.

    10 mm

  • 7/28/2019 Shear Stud Cap in Steel Decks

    18/20

    6.5 Extending Concrete Splitting Provision to

    Spandrel Beams

    6.5.1 Secondary Beam

    For the spandrel secondary beam, it is

    recommended to use equation 6.8 but taking theeffective width as:

    ofce bbb += (6.10)

    This is likely to be conservative but to an unknown

    extent. Because the decking is not continuous over

    the beam, its role in confining the concrete withinthe splitting zone of the stud (see figure. 2.4 (a))

    will be limited and is ignored in this

    recommendation. Also, using the post-splitting

    reinforcement shown below is recommended:

    Figure 6.6 Secondary Spandrel Beam.

    The DH12 @ 300 mm was calculated using thepost splitting provisions of (Oehlers and Bradford,1995). Finally, (NZS 3404:1997), Cl. 13.4.1.3(3)

    states that if the decking runs across the spandrel by

    greater or equal to 550mm then the spandrel beamis to be treated as an internal secondary beam. Thatis consistent with the experimental tests.

    6.5.2. Primary Beam

    Similarly with the primary spandrel beam, excepttaking the effective width as follows:

    oferiorint,ce

    ce b2

    b

    2

    bb ++= (6.11)

    Also, use of the post-splitting reinforcement as

    shown below is recommended:

    Figure 6.7 Primary Spandrel Beam.

    The DH12 @ 300 mm was calculated using the

    post splitting equation 2.19.

    6.6 Suppression of Rib Rolling Fracture

    Unit S2 had what is called Rib Rolling Fracture

    which is when the mesh depth is greater than theintended designed depth, setting the mesh

    reinforcement below the tension zone in the slab,

    causing the slab to tilt resulting in premature failure

    of the unit. It is called the Rib Rolling Fracture

    because the action of the forces in the slab cause the

    slab to roll caused by the rolling moment

    forces acting in the slab. This is demonstrated in

    figure 6.8.

    Figure 6.8 Rolling Fracture

    To explain this failure mathematically, the concrete

    elastic moment and the crack moment were

    calculated for both unit S1 and S2 to give a

    comparison between the two failure modes.

    First, for unit S2 it had the following

    characteristics: the transverse crack that caused the

    failure L5 occurred at a shear force/stud of 58 kN.

    The mesh depth at the crack was 50mm, making the

    centre of the reinforcement to the top of the slab

    height 56mm. Basing the calculations on that we

    get the following:

    Total area of mesh and reinforcement = 618mm2

    Elastic neutral axis = 34.75mm from the top of the

    slab.

    Resulting Elastic Concrete Moment before cracking

    is thus 2.23kNm

    While the post-splitting moment, calculated in

    accordance with figure 6.9, using the conventional

    reinforced concrete theory, is 3.953 kNm

    This indicate that the concrete will develop a crack,which actually happened, but when the result of this

    unit is compared to unit S1 which had the following

    characteristics, the transverse crack that caused the

    failure L4 occurred at a shear force/stud of 92 kN.

    The mesh depth at the crack was 40 mm making the

    centre of the reinforcement to the top of the slab

    height 46 mm. Basing the calculations on that we

    get the following:

    DH 12 @ 300 mm

    bobf

    50

    DH12

    bce,interior/2 bobf/2

    DH 12 @ 300 mm

    DH12

    < 220 mm

    a. Mesh Depth at 35 mm; Unit S1

    .

    ActuatorDirection

    35 mm

    Mesh> 35mm

    b. Mesh Depth at 50 mm; Unit S2

    ActuatorDirection

    Neutral Axis

  • 7/28/2019 Shear Stud Cap in Steel Decks

    19/20

    Total area of mesh and reinforcement = 618 mm2

    Elastic neutral axis = 33.8 mm from the top of the

    slab.

    Resulting Elastic Concrete Moment before cracking

    then becomes 2.11 kNm

    While the Moment of the concrete after cracking is

    6.36 kNm

    Now this clearly shows that for unit S1 the crack

    will also appear, but will require a larger moment to

    cause it. The calculation of the Ultimate Moment

    Capacity was also conducted for further proof.

    Yield stress fy was found to be 448.5 MPa.

    T = Asfy = 618x0.4485 = 277.2 kN

    04.13b'f85.0

    Ta

    c

    == mm

    Unit S2: M=277.2(65-56-(13.04/2))= 0.687 kNm

    Unit S1: M=277.2(65-46-(13.04/2))= 3.459 kNm

    Figure 6.9 Forces actions after cracking.

    This shows that for unit S2 there is not sufficient

    moment generated to withstand the forces acting on

    the slab, while for unit S1 there was sufficient

    moment to withstand the force and generate goodstrength. Figure 6.9 shows the ultimate moment

    actions.

    This mode of failure can be prevented by ensuring

    that the mesh depth is not greater than 35mm fromthe top of the slab.

    6.7 Recommended Changes to the Composite

    Beam Design Procedure.

    6.7.1 Minimum Shear Connection Ratio (ie.

    Partial Composite Action)

    From a comparison of all the provisions it isrealistic to amend the Partial Composite Action

    limit to that given by the Eurocode 4 (Clause6.1.2(2)), to give a more realistic shear connection

    ratio (PSC). The New Zealand provisions state that

    the PSC is taken as a minimum of 50 %, while theEurocode stipulates a minimum value of PSC br

    taken as 40 % up to 10 meters, increasing to 100%at 25 meters.

    6.7.2 Correlation factor for Component

    Capacity Equations.

    This is being presented for completeness although it

    is not intended to make changes to the design

    procedure.

    Table 6.2 shows the influence on shear stud numberdetermination if this is determined by matching

    design capacity of shear stud to design capacity of

    the critical component action, as is done with the

    three international procedures studies. Where thecompression generated within the concrete slab

    governs, adopting this approach would result in areduction of 0.83x the exact number of shear studs

    required by current New Zealand practice. Where

    the tension generated within the steel beam

    governs, adopting this approach would increase the

    number of shear studs required by current NewZealand practice.

    The net result across all application would be a

    benefit in terms of reducing the number of shear

    studs required, however the complexity of changingdesign process outweighs this benefit. It is therefore

    preferable to leave the currant practice of matchingdesign shear stud capacity, incorporating a partial

    strength reduction factor = 1.0 in positive momentregions, to the nominal component capacity in

    order to determine the number of shear studs

    required.

    Canada UK Eurocode

    NewZealand

    Shear

    Stud

    0.8 1/1.25 1/1.25 1.0

    Concrete 0.6 1/1.5 1/1.5 1.25/1.5

    = 0.83

    Steel 0.9 1/1.1 1/1.1 1.25/1.1= 1.13

    Table 6.2. Strength Reduction Factor Comparison.

    7. RECOMMENDATIONS FOR FURTHER

    RESEARCH.

    These are as follows:

    (i) To determine the influence of rib endsupport conditions on suppressing the rib

    rolling failure shown in the secondary

    beam tests, by adding stiffening ribs to the

    test specimens to represent continuity of

    slab beyond an internal secondary beam.(ii) To determine the influence of shear stud

    height/diameter ratio on the load-deflection characteristics and design

    capacity reached (i.e. provide experimental

    data to replace the dotted line AB in

    Figure. 6.1).

    Actuator Direction

    Crack

    a

    T

    Cjd

    Compression

    Block

    Mesh

  • 7/28/2019 Shear Stud Cap in Steel Decks

    20/20

    (iii) To determine the influence of mesh heighton spandrel secondary beam capacity.

    (iv) To determine the splitting capacity of

    spandrel beams and so allow the design

    recommendations of section 6.5 to be

    updated.

    REFERENCES

    Bird, G.D. and Klemick, M.P.; HiBond Design

    Wizard for Composite Design of the HiBond

    Flooring System, Version 1.0; Dimond, Auckland,

    New Zealand, 2002.

    British Standard (BS 5950 (1990)). Structural use

    of steelwork in building, Part 3: Design in

    composite construction, Section 3.1: Code of

    practice for design of simple and continuous

    composite beams, British Standards Institution,London.

    Butterworth, J. (2000). Push-off tests on shear

    studs used with a deep ribbed deck, Auckland

    UniServices Limited, University of Auckland,Report No. 8258.00, (pp. 25).

    Canadian Standard (CSA S16-01: 1984). Limit

    States Design of Steel Structures, CanadianStandard Association, Ontario, Canada.

    Canadian Standard (CSA S16-01: 2001). Limit

    States Design of Steel Structures, Canadian

    Standard Association, Ontario, Canada.

    Clifton, C. (1998). Reminders on good detailingand construction practice", Steel Design andConstruction Bulletin, HERA, No. 42, (pp. 8).

    Clifton, C. (2002). Notes prepared for Composite

    Steel Design and Construction Seminar, HERAReport R4-113, 2002.

    Eurocode 4: ENV 1994-1-1:1994, (1994). Designof Composite Steel and Concrete Structures Parts

    1-1 General Rules and Rules for Buildings, BSI

    Standards, London, pp. 143-148.

    Grant, J., Fisher, J.W. and Slutter, R.G., (1977).

    Composite beams with formed metal deck,Engineering Journal of the American Institute of

    Steel Construction, Vol. 14, 1st

    quarter, (pp. 24-42).

    Hawkins, N.M. and Mitchell, D., (1984). Seismic

    Response of Composite Shear Connections,Journal of Structural Engineering, ASCE, Vol.

    110, No. 9 (pp. 2120-2136).

    Hyland, C., Clifton, C., Butterworth, J,. andStickland, S., (2000). Shear studs in composite

    construction: concepts in determining the shear studdesign shear capacity, Steel Design andConstruction Bulletin, HERA, No.55, (pp. 18-28).

    Hyland, C., Clifton, C., Butterworth, J,. and

    Stickland, S., (2001). Composite Down-Stand

    Steel Beam Behaviour with a Profiled Deep-Deck

    Slab, Proceeding of Australasian StructuralEngineering Conference, 2001.

    Jayas, B. S. and Hosain, M. U. (1988). Behaviour

    of headed stud in composite beams: push-out tests,Canadian Journal of Civil Engineering, Vol. 15,

    No. 2, (pp. 240-253).

    Jayas, B. S. and Hosain, M. U. (1989). Behaviourof headed stud in composite beams: full-size tests,Canadian Journal of Civil Engineering, Vol. 16,

    No. 2, (pp. 712-724).

    Johnson, R. P. and Anderson, D. (1993).Designers Handbook to Eurocode 4 part

    1.1:Design of Composite Steel and Concrete

    Structures. Thomas Telford, London.

    Lin, Y., Butterworth, J., and Ingham, J. (2001).

    Capacity of Shear Studs Embedded in Lightweight

    polystyrene Concrete Diaphragms, School of

    Engineering, Civil and Resource Engineering,

    University of Auckland, Report No. 607, December2001.

    New Zealand Standard (NZS 3101: Part 2:1995).Concrete Structures Standard Part1 The Design

    of Concrete Structures, Standards New Zealand,

    Wellington, pp. 209-212.

    New Zealand Standard (NZS 3404: Part 1:1997).

    Chapter 13, Design of Composite Members and

    Structures, Standards New Zealand, Wellington.

    Oehlers, D. J. and Bradford, M. A. (1995).Composite Steel and Concrete Structural Members,Elsevier Science Ltd, Oxford, U.K.

    Ollgaard, J. G., Slutter, R. G., and Fisher, J.W.(1971). Shear strength of stud connections in

    lightweight and normal-density concrete,Engineering Journal, American Institute of Steel

    Construction, Vol. 8, (pp. 55-640.

    Slutter, R. G. and Driscoll, G. C. (1965). Flexural

    strengths of steel concrete composite beams,

    Proc. ASCE, J. structural Div., Vol. 91, No. ST2,

    April 1965, pp. 55-64.

    Zaki, R.J. (2003) Shear Stud Capacity in Profiled

    Steel Decks, MEngSt, Project Report, University

    of Auckland, September 2003.