Upload
aarigon
View
220
Download
0
Embed Size (px)
Citation preview
7/28/2019 Shear Stud Cap in Steel Decks
1/20
SHEAR STUD CAPACITY IN PROFILED STEELDECKS
RAED J. ZAKI is theAssistant Structural Engineer
at HERA. He obtained his
BE at the University of
Baghdad, Iraq and his
Masters at the University of
Auckland, New Zealand. He
is currently working on the
application of steel semi-
rigid joints in a damage
avoidance seismic system
and on improved design
provisions for shear studs in composite floor
systems.
JOHN BUTTERWORTHis Deputy Head,
Department of Civil and
EnvironmentalEngineering, University of
Auckland. His research
interests include behaviour
of steel structures,
earthquake engineering,
passive seismic protection,
structural dynamics, thin-
walled metal sections,
composites, structural
stability and large scale dynamic testing of bridges
and buildings.
G. CHARLES CLIFTONheads the Structural
Division of HERA (the
New Zealand Heavy
Engineering Research
Association). His role there
is to promote the proper
and effective use of
structural steel in New
Zealand. His principal
activities are research,
development of design
guidance and technicalpromotion. He runs HERAs fire and seismic
research programme, which is aimed at improving
the safety and cost-effectiveness of structural steel
building performance in the high risk but infrequent
events of severe fire and severs earthquake. He is a
Fellow of the Institution of Professional Engineers
New Zealand and of the New Zealand Society for
Earthquake Engineering.
ABSTRACT
The New Zealand design procedure for composite
beams incorporates provisions for headed, welded
shear stud design shear capacity developed forNorth American standards in the 1970s, modified
with a partial strength reduction factor incorporated
in 1992. Following New Zealand and international
tests which showed shortcomings with these
equations, the topic of composite beam design
using shear studs and trapezoidal decking was re-
evaluated in 2003 and a series of experimental tests
undertaken to determine the adequacy of proposed
new provisions.
This paper covers the following: the changes made,
the previous reports on over-estimating the stud
capacity, the testing of eleven shear stud push-
through specimens and the results of these tests.
Also included are constructional issues such as stud
positioning, the effect of decking edge in primary
beams and the influence of the self weight of the
slab on the transverse bending moment acting on
the beam and its effect on the shear studs. The
results of these tests have allowed us to make
recommendations for shear stud capacity, which
more accurately reflect the failure modes that
occurred, and to incorporate these into revisions to
the composite beam design procedure for beams
supporting concrete slabs on profiled steel decks.
Raed J. Zaki
ohn Butterworth
G. Charles Clifton
7/28/2019 Shear Stud Cap in Steel Decks
2/20
1. INTRODUCTION
The use of composite steel beams with profiled
steel decking and in-situ concrete floors has
increased in recent years in New Zealand and
around the world. This increased interest led to a
critical review of current design procedures in
(NZS 3404:1997) arising from concerns that theseprovisions overestimate the strength of shear studs
in profiled steel decks. A number of studies, (Lin,
et. al., 2001), (Jayas and Hosain, 1988 & 1989),
have shown that many building codes over-estimate
the predicted ultimate shear stud capacity, in
comparison with the observed shear stud capacity.
This has led to updating of standards; for example
the latest (CSA S16-01: 2001) has been revised to
correct this error.
This paper presents an overview of research
recently undertaken (Zaki, et. al., 2003) into the
adequacy of current New Zealand design provisions
for composite beams supporting profiled steel
decks. Following a detailed comparison of the
overall New Zealand composite design procedure
(NZS 3404:1997) with that from the United
Kingdom (BS 5950(1990)), Europe (Eurocode 4:
ENV 1994-1-1:1994), and Canada (CSA
S16:2001), recommendations for changes to the
design provisions and to the equations for
determining the capacity of headed, welded shear
studs have been made. The latter were basedinitially on a review of the international standards
mentioned above and an experimental testing
programme was undertaken.
Figure 2.1. Concepts of composite construction
(Oehlers and Bradford 1995).
That programme has led to further recommended
changes to the shear stud capacity equations. The
end result has been minor changes to the composite
beam design provisions and a revision to the
equations for determining shear stud capacity. The
overall effect will be more accurate determination
of the number of shear studs needed in a composite
beam. Further areas of required research have also
been identified.
This paper firstly reviews, in section 2, the concepts
involved in composite action. This includes the
strength of shear connectors in solid slabs and in
profiled slabs, covering the various failure modesidentified in the literature.
While one of the main drivers behind this research
was concern over the design capacity of shear studs
as predicted by (NZS 3404:1997), it is important to
note that the calculated shear strength of a welded
stud is only one of the factors that determines the
shear stud numbers and positions required in a
composite beam. The first stage of the research
therefore involved a comparative calculation study
of the design requirements for a range of steel
beams designed to New Zealand, British, European
and Canadian practice. Section 3 presents details of
this work. The conclusions from this research are
presented in section 7, followed by the references.
2. CONCEPTS OF COMPOSITE
CONSTRUCTION
2.1 Composite Steel-Concrete Sections:
Composite construction is based upon connecting a
concrete slab to a steel beam so that the twoelements act as one. By placing the steel beam in
tension, the high tensile strength of the beam can be
fully used, and the possibility of buckling of thin
steel members can be reduced. Likewise, by placing
concrete slabs in compression, the disadvantage of
weak concrete tensile strength can be avoided and
the advantage of good compression strength/cost
fully utilised. Also, concrete slabs have good sound
and fire insulation properties. A common form of
construction is to use a steel beam to support the
slab, as shown in figure. 2.1(a) and (b). It has been
found that by bonding the steel beam to the
steel/concrete interface
strain distribution
composite beam
A
(a)
reinforced-concrete slab
A
(c)composite slab
steel decking or profiled sheet
composite beam
steel beam
(b)
A-A
B C B
C
concrete
B
cold formed ribs
weff
x
x
(a) Full composite beam
beff
Profiled, cold - formed steeldecking.
(a) Full composite beam-strain distribution.
7/28/2019 Shear Stud Cap in Steel Decks
3/20
concrete slab by shear connectors, the flexural
strength and stiffness of the beam can be at leastdoubled (Oehlers and Bradford, 1995). This in turn
leads to an increase in the span to depth ratio that
can be used.
Figure 2.1 (a) shows the strain distribution
associated with full interaction between the steelbeam and the concrete slab. In this instance, there is
no interface slip between them. In practise, a
limited degree of interface slip is usually allowed
and incorporated into the design; this is known as
partial composite action.
Another type of composite structure is formed
when profiled steel decking is used as a permanent
formwork for a concrete slab and is designed to act
integrally with the concrete so that the two
components act as one, as shown in figure 2.1 (c).
Figure 2.2 Composite beam with profiled steel
decking.
The most commonly used composite section is the
one that connects the concrete slab with the steel
beam by welding connectors between them to
achieve composite action, as shown in figure 2.2.
The connector is welded through the troughs of the
profiled decking to the flange of the steel beam
(Oehlers and Bradford, 1995). The ribs of the
profiled decking, through which the interaction
Figure 2.3 Shear stud and transfer of connector
force (Oehlers and Bradford 1995)
between the steel decking and the concrete is
achieved, can be placed either parallel, or
transverse to the steel element. New Zealand is one
of the very few countries to have all-weather stud
welding capability, which elevates the economic
viability of headed studs when compared with other
anchor types as it allows these to be welded through
the deck or directly onto the beam even in wetweather. The study reported herein focuses on this
type of composite construction and specifically on
the connector between steel beam and concrete slab
known as the headed, welded shear stud (hereafter
referred to as a shear stud).
2.2 Shear Stud.
The shear stud, as shown in figure 2.3 (a), is the
most commonly used shear connector in composite
construction. The shank and the weld-collar
adjacent to the steel flange are designed to resist the
longitudinal shear force, whereas the head is
designed to resist the tensile force that is normal to
the steel/concrete interface and to engage the
concrete. The shank diameter of headed studs
ranges from 10mm to 22mm. The most commonly
used is the 19mm diameter. The length of headed
studs before welding varies from 55mm to 250mm.
After welding the stud length will have decreased
by 3mm to 11mm, depending on the stud diameter
and the stud application, i.e. welding through
decking burns off some 2-4mm more than cleanbeam welding (Clifton, 1998).
Oehlers and Bradford (1995) noted that shear studs
are simply steel dowels embedded in a concrete
medium. As the concrete slab tries to slip relative to
the beam, the stud imposes a very high
concentrated force, which is transferred from the
dowel action of the stud into the concrete, as
illustrated in figure 2.3(b). The resistance of a stud
to this dowel action is known as the dowel strength,
and this strength is specified in the New Zealand.
Standard (NZS 3404:1997) as the nominal shear
capacity of connectors. The dispersing of this
force into the concrete element can induce tensile
cracking particularly when the connector is also
(c) plan view of slab
showing crack formation
Theight
(a) stud
diameter
(b) dowel action
C
embedment
cracking
weld collar
shank
headsteel dowel
steel element
concrete element
ripping
C
T
shear splitting
steel
concrete
Transversecracking
Splitting
Longitudinal
(a) Ribs Parallel
(b) Ribs Transverse
Composite Slab
7/28/2019 Shear Stud Cap in Steel Decks
4/20
resisting separation at the steel/concrete interface of
the composite beam, which in turn is caused bytransverse cracking, shear and longitudinal splitting
actions. Figure 2.3 (b) shows the tensile cracks that
are also known as embedment cracks, and figure
2.3 (c) shows the dispersal of the dowel action
inducing a longitudinal splitting crack.
These forms of tensile failure of the slab can affect
both the dowel strength and ductility of the shear
connection. With the absence of reinforcing bars
crossing the planes of cracking, the strength of the
dowel reduces immediately after cracking occurs
and the slip capacity is also reduced. On the other
hand, the presence of reinforcement across a crack
plane makes failure more ductile and even allows
increases in stud shear resistance after cracking.
2.3 Mechanism of dowel action.
Figure 2.4(a), from (Oehlers and Bradford, 1995),
demonstrates the transfer of longitudinal shear by
dowel action of shear studs. That figure shows the
resulting mechanism where the stud is forced to the
right when the steel beam moves to the right,
causing the stud to bear on the concrete to the right
of the stud. For the dowel action to work, the
concrete adjacent to the bearing zone has to
withstand compressive stresses up to seven times
the cylinder strength, fc, which is only achieved by
the triaxial restraint imposed on the region by thesteel element, the stud and the surrounding
concrete.
The resultant force in the bearing zone in figure
2.4(a) is F, the centroid of which occurs at an
eccentricity, e, from the steel/concrete interface.
There is horizontal equilibrium between the force F
and the shear force in the steel element and, to
maintain the rotational equilibrium, a moment is
induced at the base of the stud. Therefore, the steel
stud must resist both flexural and shear forces,
Figure 2.4 Dowel mechanism (Oehlers and
Bradford 1995)
which are the cause of high tensile stresses in the
steel failure zone shown in figure 2.4 (c). Due to
these forces the concrete can crush in the bearing
zone and the steel can fracture in the steel failure
zone, therefore the mechanism of dowel failure is
governed by the interaction between the steel and
concrete failure zones. This can be best described
by considering the equivalent dowel mechanism infigure 2.4 (b). As shown in figure 2.4 (b), the dowel
behaviour can be considered to be a steel beam
resting on a concrete medium (Oehlers and
Bradford, 1995), where section a-a at the midspan
of the steel beam in figure 2.4(b) is equivalent to
section a-a at the steel/concrete interface in figure
2.4(a).
Consider the distribution of pressure at the
steel/concrete interface in (b), for a constant applied
force 2F and for different configurations of the
material properties. When the steel modulus Esapproaches infinity, the pressure at the interface can
be considered uniform and hence the resultant force
F in one shear span will act at an eccentricity e=h/2.
The section at midspan has therefore to resist a
shear force F and a moment Fh/2, and the dowel
strength of the stud is determined at this section.
Conversely, when Es approaches zero, the steel
beam can be visualized as a layer of paper such that
the resultant interface force in one shear span is
now almost in line with the applied force, so that e
tends to zero. Therefore, the midspan of the beamnow only resists a shear force F. It can therefore be
seen that as Es increases relative to the concrete
modulus Ec, shear stud capacity reduces because
the flexural component Fe at midspan increases.
On the other hand decreasing Ec is equal to
increasing Es, by increasing e which in turn
increases the flexural component Fe therefore
reduces the shear stud capacity. Therefore, the
shear stud capacity is proportional to the modular
ratio parameter Es/Ec, no matter what the shape or
size of the steel dowel.
(b) equivalent dowel mechanism
mid-span
steel beam Es,fu
(a) dowel mechanism
FFe
a ae
cracktip
concrete medium
Ec,fc
shear stud Es,fu
F
2F
F1h F
(c) dowel mechanism with weld collar
Fe1
concrete medium
Ec,fc
dh
a a
F
e
e
steel failure
zone
e2F2
concrete
bearing zone
dsh
weld collar
h co
h st
7/28/2019 Shear Stud Cap in Steel Decks
5/20
Since the studs are welded into the steel element
and specifically in the flange of the steel beam, aweld collar with a diameter of about 1.3 times the
shank diameter dsh and a height of about 0.3 dsh,as
shown in Figure. 2.4 (c), is formed. This collar
increases the shear stud capacity by increasing the
bearing surface at the stud/concrete interface, which
in turn reduces the stresses in the concrete for agiven force F. It also increases the shear stud
capacity by raising the steel failure zone so that it
occurs at the weld-collar/shank interface. Raising
that zone will subject the zone to a portion F2 of the
total shear force F. The weld collar also reduces the
flexural stresses at the failure zone since the
eccentricity e2 of F2 in (c) is less than the
eccentricity e of F in (a).
2.4. Strength of Shear Stud Connectors.
2.4.1 Introduction.
Since the stud is embedded in concrete, the shear
stud capacity is dependent on the properties of the
concrete slab in addition to the properties of the
steel stud. If the concrete in the bearing zone splits
or crushes, it will cause the base of the stud to
move forward, while the head of the stud remains
in the previous position. This will lead to a larger
slip at the steel beam/concrete slab interface than
that caused only by the deformation of the stud.
This failure may also lead to rotation of the stud,whichwill generate flexural rotation actions and anadditional axial tensile force in the stud. The
magnitude of this axial tensile force increases as the
rotation of the stud increases, tending to pull the
stud out of the concrete, according to (Hyland, et.
al., 2000). The strength of the concrete that resists
stud pullout is called the embedment strength of the
shear stud, while the strength of the concrete that
resists local splitting is known as Vsplit.
If the shear stud doesnt fail in a push-through test
by pulling out of the concrete (i.e. by embedment
failure, in which the stud pulls out of the concrete
along with a cone of surrounding concrete), then it
will fail either through concrete crushing/stud
fracture or through longitudinal splitting. The first
case is governed by the dowel strength of the stud
in uncracked concrete and this is described in
section 2.4.2. The second case is covered in section
2.4.3.
2.4.2 Dowel Strength of Shear Studs in
Uncracked Concrete
Ollgaard, et. al. (1971) pioneered research on the
dowel strength of shear stud connectors, and
identified the important parameters that control the
dowel strength. Using statistical analysis, they
derived an equation to determine the mean dowel
strength of shear stud connectors in push off
specimens, in which the concrete slab had not failed
prematurely through splitting, shear or embedment.
This equation for the dowel strength as dictated by
concrete crushing, Dmax, is given by:
44.0c
3.0cshmax EfA83.1D = (2.1)
where the units are in N and mm, Ash is the cross-
sectional area of the stud shank and Ec is theYoung's modulus of elasticity of the concrete,
which is given by equation 2.2a
c5.1
c f043.0E = (2.2a)
However, New Zealand Standard (NZS 3101:1995)
gives another expression for Ec
( )5.1
cc2300
6900f3320E
+= (2.2b)
where Ec and cf are in N/mm, and is the density
of the concrete in kg/m3. There is not much
difference between these two expressions,
In adapting equation 2.1 to design use, the
exponents were changed to make the equation
dimensionally correct and simpler, although this led
to a loss of accuracy. The altered equation is
cc
2sc
ccscmax Ef8
dEfA50.0D
== (2.3)
Certain types of stud welding procedure produce
very small or no weld collars, and it would beunsafe to use equation 2.3 directly to determine
their strengths. It was therefore suggested that theshear strength given by equation 2.3 should be used
in conjunction with a reduction factor when the
mean height of the weld collar is less than d sh/5(Oehlers and Bradford, 1995). The reduction factor
Rco is given by
sc
coco
d3
h5
3
2R += (2.4)
where hco is the mean height of the weld collar, anddsc is the shank diameter of the stud.
Equation 2.3 was adopted by (NZS 3404:1997) forcalculating the nominal shear capacity of headed
studs, along with a steel profile reduction factordc,as determined by (Slutter and Discoll, 1965). That
factor related to the reduction in stud strength in a
ribbed slab. Including dc, as specified in section13.3.2 of the standard, this gives:
7/28/2019 Shear Stud Cap in Steel Decks
6/20
dcscuccscdcr AfEfA5.0q = (2.5)
where qr is the nominal shear capacity, and Asc is
the cross-section area of the stud shank which is
equivalent to Ash in equation 2.3. dc is the deckingreduction factor, fu is the minimum tensile strength
of the stud, which is equal to 415 MPa for studs
manufactured to AS 1443 grades 1010 to 1020 orASTM A108 grades C1010 to C1020. A strength
reduction factor (sc)is used to obtain the designcapacity of headed studs, which is equal to 0.8 for
studs situated in positive moment regions and 0.6for studs situated in negative moment regions.
The expression fuAsc in the second half of equation
2.5 represents shear stud failure, i.e. due to steel
failure in the zone shown in figure 2.4 (c). As
described below, such steel failure is principally an
ultimate shear failure and as such is over-estimatedby the expression fuAsc. This was fortuitouslyrectified through the incorporation of the partial
strength reduction factor of 0.8, introduced into the1992 edition of NZS 3404. However, in the case of
shear stud failure, that 0.8 should be part of the
equation itself.
Amendment No. 1 (2001) for Clauses 13.3.2.1 and
13.3.2.2 stated changes to be made on equation 2.5
by multiplying the reduction factor (sc) by (1/0.8)and (qr) by (0.8), as shown in equation 2.6. This
brings the factor (0.8) directly into the equation for
determining shear stud nominal capacity, which
provides better agreement with experimental resultsissued in (Hyland, et. al., 2000) and makes the
embedment equations;
dcscuccscdcr Af8.0EfA4.0q = (2.6)
In (Clifton, 2002), another recommendation to
replace equation 13.3.2.1 of (NZS 3404:1997),
shown here in equation 2.6, by:
scuccscdcr Af8.0EfA5.0q = (2.7)
This more correctly represents the dowel strength
of a stud in solid concrete, with the left-hand side ofthe inequality representing concrete crushing and
the right hand side shear failure, of the steel stud atthe top of the weld collar.
For ribbed slabs, it has been noted (Slutter and
Driscoll, 1965) that the shear stud shear capacity is
reduced, with the reduction dependent on the
orientation of the ribs. This reduction factor has
been established experimentally, example equation
2.8 for ribs perpendicular to the steel beam, (Grant,
et. al., 1977), which has been adopted by (NZS3404:1997).
=
rc
r
rc
sc
rc
dch
b1
h
h
n
85.0(2.8)
where nrc is the number of studs in a rib, hsc is the
total height of the stud, hrc is the height of the rib
and br is the mean width of the rib. However, thereduction factor given in draft Eurocode 4 (Johnson
and Anderson, 1993) is more conservative, using
0.7 as a reduction factor instead of 0.85
=
rc
r
rc
sc
rc
dch
b1
h
h
n
7.0(2.9)
Equations 2.8 and 2.9 are presented as representing
the reduced dowel capacity of the shear studs. They
are experimentally determined on the premise that
the concrete does not undergo longitudinal splittingat the base. However, review of the pictures from
the Canadian push-off tests (Jayas and Hosain,
1988) indicate that splitting was the likely limiting
mode of failure for their tests. It is therefore
considered likely by the authors that the Canadianreduction equations represent a splitting-induced
loss of shear stud capacity due to the profiled natureof the concrete slab. The equation for primary beam
application-which is not presented herein- is alsobased on a test configuration that is not
representative of that used in practice.
Given that splitting strength can often govern the
shear stud capacity, the background to this is nowgiven.
2.4.3 Splitting Strength of Concrete.
a. Primary Beam.
Splitting of the concrete happens when the high,concentrated dowel stress formed by the shear stud
is dispersed laterally into the concrete element, as
shown in figure 2.3(c). This dispersion isrepresented by the arrows marked as C and, to
maintain equilibrium transverse tensile stresses are
induced in the concrete, represented as T. When
these transverse tensile stresses exceed the splitting
tensile strength of the concrete, fcb, longitudinalcracks will form in the concrete prism in the
bearing zone along the line of the shear connectors.
The splitting tensile strength of the concrete fcb isobtained from cylinder split tests, as given by the
following equation:
ccb 'f5.0f = (2.10)
A detailed background to the shear splitting
provisions is given in section 11.3 of (Oehlers and
Bradford, 1995). The relevant equation for the
7/28/2019 Shear Stud Cap in Steel Decks
7/20
nominal concrete splitting resistance of a haunch ofconcrete of width bce is given by:
+=
c
a
2
c
a
cbasc
d
cbeqce
split
h
h
h
h1
fhd6.0
k
fhb6.0V (2.12)
where:
bce = concrete effective haunch width,
ha = 1.8dsc, effective stud bearing height. (2.13)
fc = characteristic concrete cylinder compressionstrength (MPa).
dsc = diameter of welded, headed shear stud (mm).
Vsplit = nominal splitting capacity (N).
kd =
2
ce
sc
b
d1
1
, lateral force parameter. (2.14)
hc = effective haunch height for splitting = min
(4.5ha, to).
The following dimensional constraints are requiredfor equation 2.12 to be valid:
bc 3dsc (2.15)hc 3ha = 5.4dsc (2.16)
hsc hc (2.17)
where:
bc = actual width of insitu concrete into which the
shear stud is embedded (mm)
hsc = height of shear stud after installation (mm)
In addition, especially for individual concrete ribs
containing studs, hsc 4.5ha = 8.1dsc is highly
desirable, as this places the head of the stud, whichacts as the anchor for preventing vertical slip of the
stud within the concrete, outside of the region ofhigh compression bearing stress where splitting
initiates. This has benefits in increasing the post-
splitting shear capacity, as given by (Oehlers andBradford, 1995).
b. Secondary Beam.
Splitting failure in the secondary beam
configurations, ribs transverse to the beam, has
been represented by some researchers as concretepullout failure. (Hawkins and Mitchell, 1984)
proposed the following equation:
ccc A'f45.0V = (2.18)
where:
Vc = shear capacity due to concrete pull-out failure(N).
fc = concrete compressive strength (MPa).Ac = area of concrete pull out failure surface (mm
2).
Jayas and Hosain (1988) made further researchbased on this equation for 38 and 76mm decks,where they found out that instead of a fixed value
of 0.45, separate coefficients should be used for the38 and 76mm decks.
However, in our push-off tests on the secondary
beams, the governing failure mode for thesecondary beam studs was a splitting failure mode,
as shown by the classic longitudinal splitting crack
developing in the concrete slab (see section 6.2).
This has been approached through the use of
equation 2.12, obtaining Vsplit experimentally and
then back calculating to obtain the effective haunchwidth, for the secondary beam, bce,sb.
3. COMPARATIVE CALCULATION PRIOR
TO EXPERIMENTAL TESTING
3.1 Introduction and Scope.
When designing a composite beam, many factors
govern the selection of steel beam size and the
number of shear studs required. These factors maymean that a significant change in shear stud design
shear capacity may not make much difference to thenumber of shear studs required for a given beam
span, configuration and loading.
The purpose of the comparative calculations was to
determine the number of shear studs required for arange of typical primary and secondary beams
designed in accordance with the strengthrequirements of new Zealand, Canadian, British
and European standards. The range of parametersused in this study are given in Table 3.1.
Each beam was designed to meet all the strengthand serviceability requirements of current New
Zealand practise (NZS 3404:1997) and (Clifton,2002). The software HiBond Design Wizard, which
covers use of the 55mm high trapezoidal deckingprofile used in the study, based on (NZS
3404:1997), was used to achieve this.
Having undertaken these designs and determined
the number of shear studs required, the number of
shear studs required for the same beam size andapplied loads to the requirements of the current
Canadian Standard, British Standard and European
Standard were then determined.
The results of these comparisons were then
tabulated in order to compare the current NewZealand requirements with those of three major
international composite standards. This was done in
order to give an indication as to the combined effect
of the many parameters influencing the number ofstuds required on the design solution and to see
what influence any change in shear stud design
7/28/2019 Shear Stud Cap in Steel Decks
8/20
shear capacity would have against currentinternational best practice.
Parameter
Live Loads 3.5 kPa & 5 kPa
Beam Span 8 m & 15 m
Propping No
Precambered NoPartial Shear
Connection
As stated in the respective
Standard
Slab Span 2.8 m
Thickness 120 mm
Deck Type 55 mm trapezoidal profile.
Stud Height 100 mm
Stud Diameter 19 mm
Stud fu 415 MPa
Concrete fc 25 MPa
Table 3.1 Parameters used in the Study.
Section 3.2 presents the New Zealand requirements
for determining the ultimate limit state capacity of asteel beam and the number of shear studs required.
Section 3.3 presents an overview of the strength
design requirements of the other Standards used,
highlighting the differences between these and the(NZS 3404:1997) requirements.
Section 3.4 gives some of the comparative results,first in terms of shear stud design capacity and
secondly in terms of the number of studs requiredin each beam size. Full details are in (Zaki, 2003).
Following this work initial recommendation were
proposed for the shear stud design shear capacityand also for the partial shear connection limits, inorder to keep the net changes to as-built details to a
minimum. The initial recommendations arising atthe end of the comparative calculations are given in
section 3.5.
3.2 New Zealand Provision for Calculation of the
Composite Ultimate Limit State Design Moment
Capacity, Mrc
This involves the following general steps:1. Calculation of the factored design loads and
design actions (moment and shear).
2. Calculating the maximum axial compressionand tension capacity of the various composite
section components, known as componentcapacities.
3. Calculating the shear stud capacity based on theorientation of decking and number of studs per
set.
4. Determining the percentage of compositeaction (PSC) to use.
5. Calculation of the plastic neutral axis andcomposite section properties.
6. Calculation of the nominal composite moment
capacity.7. Multiplying by the global strength reduction
factor to give the design composite momentcapacity.
The full details of this procedure are given in
section 2.2 of (Clifton, 2002).
3.3 Design for Strength to Chosen International
Standards.
These international standards all follow the same
general design procedure, with certain differences
based on their specific development. These
differences to the New Zealand requirements are
given in section 3.3.1 to 3.3.3:
One significant difference between all three
international standards and New Zealand practice is
the use of global strength reduction factors in New
Zealand and the partial strength reduction factors inthe three international standards.
In New Zealand, the design shear capacity of the
shear stud (which does incorporate a partial
strength reduction factor, although this is 1.0 forstuds in positive moment regions) is matched to the
nominal component capacity when determining thenumber of shear studs required. The nominal
moment capacity is determined and converted todesign moment capacity through the use of a global
strength reduction factor.
In the three international standards, the nominal
capacity of the shear studs and internal componentsis converted to the design capacity through the use
of a partial strength reduction factor, which ismaterial specific. (Typical values, from Canadian
practice, are 0.8, 0.6, and 0.9 for the shear stud,concrete and steel beam components respectively).
The design capacity of shear stud is matched to the
design component capacity when determining the
number of shear studs required. The design moment
capacity of the composite section is then
determined directly.
This has important implications when determining
the number of shear studs required by eachprocedure, as discussed in sections 3.4 and 3.5.
3.3.1 Canadian Code (CSA S16-01: 2001).
The first difference is the load factors where (1.25)
is used for the dead load and (1.5) is for the live
load (Clause 7.2.4). This is the same as for(AS/NZS 1170.1:2002) and is not a critical
difference. The minimum shear connection ratio,
7/28/2019 Shear Stud Cap in Steel Decks
9/20
(PSCmin), allowed is 40% and for the componentcapacity there is a factor of (0.6) added to thenominal concrete capacity in compression (Nccc)
(Clause 17.9.3) and a factor of (0.9) for the nominaltensile steel capacity (Ntsc) (Clause 17.9.3). Finally,
the shear stud capacity for the secondary beam iscalculated according to the following equations:
uccscr Q'fA35.0q = 76mm decking. (3.1)
uccscr Q'fA61.0q = 38mm decking. (3.2)
where:
qr= shear stud capacity.
sc = factor that depends on the concrete type.(Clause 17.7.1). For normal weight concrete,
positive moment action it is 0.8.
Ac = area of concrete pullout surface (cone).
Qu = Ultimate shear capacity, which is the
following equation.
ccscscu E'fA5.0Q = (3.3)
While the primary beam equation is:
uscscc'cscscr fAEfA5.0q = (3.4)
3.3.2 British Standard (BS 5950:Part3:Section
3.1:1990).
The BS 5950:Part 3 differences with New Zealand
practice are as follows. First the load factors are(1.4) used for the dead load and (1.6) for the live
load. The minimum shear connection ratio (PSCmin)
is taken from Clause 5.5.2 where up to 10m, PSCminis 40%, while for 16m and above it is 100%. For
the spans between 10 to 16m, the followingrelationship between PSC and the span must be
satisfied:
( )4.0PSCbut
10
6LPSC
(3.5)
where:
PSC = Partial Composite Action.L = span in meters.
As for the component capacity, the concrete
compression stress is based on (0.45 fcu) fordetermining the design concrete capacity in
compression (Nccc) (Clause B.2.1). To convert thecharacteristic cube strength of concrete (fcu) to
cylinder strength (fc) a factor of (0.8) is used. Asfor the design tensile steel capacity (Ntsc) a factor of
(1/1.1) is used (Clause B.2.1). Finally, the designshear stud capacity is calculated according to the
following equation for both primary and secondarybeams, from Clause 5.4.3:
kQ8.0Q kp = (3.6)
where:
Qp = Shear Stud Design Capacity.
Qk = Characteristic resistance of the shearconnector, determined directly from experimental
testing and read from a table.0.8 = strength reduction factor.
k = reduction factor = 1.0 for both secondary andprimary beam configurations using 55mm
trapezoidal decking.
3.3.3Eurocode 4 (DD ENV 1994-1-1: 1994).
The Eurocode also has similar differences to the
British Standard. The load factors used are the same
as the British (1.4) for dead load and (1.6) live load,
while the shear connection ratio (PSC) is given byClause 6.1.2(2). Up to 10m, PSCmin is taken as
40%, while for 25m and above its taken as 100%.
For the spans between 10 to 25m the followingrelationship between PSC and span must be
satisfied:
L04.0PSC (3.7)
Partial strength reduction factors of (1/1.5) are used
on the calculation of design concrete capacity incompression (Nccc) (Clause 2.3.3.2(1)) and (1/1.1)
for the nominal tensile steel capacity (Ntsc) (Clause
2.3.3.2(1)). The shear stud capacity is given by the
minimum of the following equations for both
primary and secondary beams, from Clause 6.3.2.1:
v
2sc
u1r 4
d
f8.0kq
= (3.8)
v
cc2sc2r
E'fd29.0kq
= (3.9)
where:dsc = diameter of shear connector.
k= constant
3.3.4 Comparative results.
According to (Lin, et. al., 2001) the New Zealand
Standard clearly overestimated the shear studcapacity, as shown in Figure.3.1, where the
difference between the New Zealand Standard
(NZS 3404:1997), the Canadian Standard (CSAS16-01:2001, added by the author) and test results
from (Lin et. al., 2001) are clearly demonstrated,for 30 MPa concrete.
The Canadians recognised the unconservative
nature of their (CSA S16-01: 1984) shear stud
capacity equation for secondary beam
configurations, which prompted (Jayas and Hosain,
7/28/2019 Shear Stud Cap in Steel Decks
10/20
1988) to undertake research on the shear studcapacity. In (Jayas and Hosain, 1988) they
proposed the changes to the shear stud capacity
equation for secondary beams from that given forprimary beams (equation 3.4) to the new equation
3.1 and 3.2. This was followed by a full size test,details of which are published in (Jayas and Hosain,
1989). These changes were implemented in theCanadian Code (CSA S16-01: 2001), in Clause
17.7.2.3. As can be seen from Figure 3.1, these
equations predicted much lower shear studcapacities than the (NZS 3404:1997) provisions,
leading to the potential requirement for more studs
on a given beam.
The results of the comparative calculations are
presented in (Zaki, 2003) with details of 2 cases
given in Tables 3.1 and 3.2 below. These show the
difference between the various standards for deck
and strength reduction factors, shear stud capacity,number of studs required for the given beam and
shear connection ratio used. The designation
numbers 8/10/3.5 mean that the secondary beam
length was 10 m, primary beam length 8 m and theload acting on the tributary area 3.5 kPa.
Figure 3.1. Shear force-slip history for fc= 30 Mpa
(taken from Figure 5.13-unit 120/N30/19R/12F/02
(Lin, Y., et. al., (2001) with addition by author).
In Table 3.1.a, even though the New Zealand
determination for the primary beam shear studcapacity is higher than the rest, the number of studs
used is less than the number of studs required by
the British and Eurocode, as the PSC% used islower in this instance. Table 3.1.b shows that,
although the New Zealand procedure gives the
greatest shear stud capacity for this secondarybeam; the estimated number of studs is nearly
similar to the other standards. This is largely
determined by practical considerations of studspacing in a secondary beam supporting a profiled
steel deck. Looking at table 3.2.a, the New Zealand
shear stud capacity is still higher than the rest, but
the number of studs is higher, as it took a 100%PSC to make the primary beam work. Table 3.2.b
still has a high capacity, but the PSC is lower than
the British and Eurocode, as they are governed byClause 5.5.2 and clause 6.1.2(2) respectively intheir respective standards, (BS 5950:Part3: Section
3.1:1990) and (DD ENV 1994-1-1: 1994). Thesestate that the PSC is taken as a minimum of 40% till
10m increasing to 100% at 16m and 25mrespectively. Minimum PSC ratio is typically a
governing factor for secondary beam stud numbers.
These comparisons show that research to improve
the New Zealand composite design provisionsshould not just be limited to shear stud capacity but
should address the following:
1. The minimum value of PSC required.
2. Whether factors should be added to the
calculation of Nccc and Ntsc to be consistent
with the approach used by the other standards
that use partial material strength reduction
factors to match design shear stud capacity todesign internal action.
3.4.Initial Recommendation
At the conclusion to the comparative studies, the
recommendations on all these considerations
proposed were as follows:
1. For shear stud nominal shear capacity insecondary beams, use the new Canadian
equations equations 3.1, 3.2 withinterpolation as required and equation 3.3. Use
sc = 1.0 as for New Zealand practice.2. For shear stud nominal shear capacity in
primary beams, use equation 2.7 and determine
the potential for rib splitting from experimentaltesting.
3. For limits on PSC, change to the Eurocode
provision.4. Do not make changes to the calculation of
component capacities and the matching ofshear stud design capacity to component
nominal capacity.
The next stage of this project involved an
experimental testing programme to determine shear
stud nominal and design shear capacity when used
in a 55 mm deep trapezoidal deck concrete slab in a
primary and in a secondary beam configuration.
0
30
60
90
120
150
0 2 4 6 8 10 12 14 16 18 20
Mean slip (mm)
Shearforce/stud
(kN)
123 kN (NZS 3404)
83 kN (80% of max)
104 kN (max)
73.2 (CSA S16-01)
128 kN (Eq 2.6 )
58 kN (splitting)
7/28/2019 Shear Stud Cap in Steel Decks
11/20
Code Deck R.F. Strength R.F. Capacity No of Studs PSC%
NZ 1 1 94.1 42 70
Canada 1 0.8 89.5 28 75
UK 1 0.8 76 49 100
Eurocode 1 0.8 66.2 56 100
Table 3.1.a. Primary Beam 8/10/3.5.
Code Deck R.F. Strength R.F. Capacity No of Studs Practical No Studs* PSC%
NZ 1 1 94.1 24 34 50
Canada 0.54 0.8 68.5 24 34 40
UK 1 0.8 76 23 34 42
Eurocode 1 0.8 66.2 26 34 42
* Practical number of studs is dictated by 1 stud per deck rib.
Table 3.1.b. Secondary Beam 8/10/3.5
Code Deck R.F. Strength R.F. Capacity No of Studs PSC%
NZ 1 1 94.1 59 100
Canada 1 0.8 89.5 29 80
UK 1 0.8 76 39 80
Eurocode 1 0.8 66.2 51 90
Table 3.2.a. Primary Beam 8/15/5.
Code Deck R.F. Strength R.F. Capacity No of Studs Practical No Studs PSC%
NZ 1 1 94.1 42 49 50
Canada 0.54 0.8 68.5 28 49 40
UK 1 0.8 76 61 49 90
Eurocode 1 0.8 66.2 47 49 60
Table 3.2.b. Secondary Beam 8/15/5.
4. SHEAR STUD TEST SET-UP
4.1. Introduction
Because of the complexity of composite action, ashas already been discussed in sections 2.3 and 2.4,
the strength and ductility of shear studs are always
determined experimentally. The details associatedwith the shear stud testing conducted at the
University of Auckland are reported in this section.
The test set-up adopted that previously used by(Butterworth, 2000), with changes made to the
dimensions of the test units, the shape of the corbel,
and the position of the test units on the test rig. Theshear force was applied by blocking one side of the
test unit and adding a push force on the other side.The push force and the reaction force were
positioned collinear with the steel-slab interface,
such that the position of the test unit on the test righad no influence on test results.
The associated details of the test set-up including
test rig, test units, instrumentation, loading
procedure, and corbel design are discussed insections 4.2 to 4.7.
4.2. Shear Stud Testing Rig
The test rig with mounted unit is shown in Figure.
4.1. The frame had three components; the base
frame, head frame and foot frame. The baseframe was bolted to the strong floor of the test hall.
A 1000 kN jack was horizontally bolted to thehead frame. Centre lines of the push force and the
reaction force were regulated by steel bearings,which were positioned collinear with the steel-slab
interface and the horizontal stiffener in the head
and foot frames.
Test units were laid on packers with the slabpositioned on top and the steel section positioned
underneath, representing the real situation.
Thickness of the packers was carefully adjusted tomake the steel-slab interface collinear with the the
centre line of the bearings (line of thrust). The steel
corbel of the test units was positioned close to jack
and the foot frame restrained the concrete corbel.
7/28/2019 Shear Stud Cap in Steel Decks
12/20
Figure 4.1. Test rig with mounted test unit
(Butterworth 2000)
Slide rollers were placed between the packer and
the lower surface of the steel beam, in order for the
slab to freely slide during testing.
4.3 Shear Stud Test Units
4.3.1 General
The push specimens are referred to here as shear
stud test units. The test unit was composed of three
main components steel beam, composite slab and
studs. A typical shear stud test unit is shown in
figure. 4.2, 4.3 and 4.4, for both secondary andprimary beams, with each test unit having small
changes from that shown
The design of shear stud test units adopted in thisresearch closely emulated the design used
previously (Butterworth, 2000), although therewere some changes, these being:
1. As a conventional profiled steel decking wasadopted in this study, the total thickness of the
slab was much less than that previously tested,so studs with a length complying with (NZS
3404:1997) Clause 13.3.2.2.1 (d)-ie hsc hr +
40 mm were required. In this case hsc 95mmwas required.
2. There was no concrete haunch over the steelbeam, which in previous testing had a width
the same as the steel beam top flange.
3. Especially for the secondary beam, stud
spacing was controlled by the decking profile.
4. Because of the reduced slab thickness, the
section of the corbel became more critical, sothe corbel required redesign.
5. Nominal mesh reinforcement complying with
(NZS 3404:1997) was used.
4.3.2 List of Shear Stud Test Units
All test units used in this study are listed in Table
4.1. Key results are presented in section 5, with full
details in (Zaki, 2003).
S is for the secondary beams and P is for theprimary beams. All the secondary beam slabs were
1105mm by 1000mm with 120mm depth while the
primary beams were 1240 mm by 1000 mm with
120mm depth no matter how many studs were
tested.
For the secondary beams, Units S1, S2 and S3 are
identical in the number of studs and concrete
strength, while S4 has the same number of studs but
different concrete strength. S5 has double thenumber of studs at the staggered position, while
S6 has the same number of studs as the first 4 with
a concrete strength of 25 MPa but the studs
positioned in the unfavourable position.
For the primary beams P2, P3 and P5 are identical
while P1 is the same but with different concretestrength and finally, P4 has double the number of
studs at double the spacing compared to P2, P3 andP4. These differences were intended to generate a
good representation of shear stud capacity and test
the influence of key parameters, but not change toomany variables to give meaningful results. Theshear connection devices used in this study wereheaded studs with a shank diameter of 19 mm and a
before-weld length of 106mm, clean beam and 110mm through deck. These give an installed length of
99-102mm in each instance.
4.4 Loading procedure
The test protocol was based on the Eurocode 4
(1994) recommendation:
1. Load the test unit to 40% of the expectednominal capacity (failure load) of the stud
group.2. Cycle the load 25 times between 5% and 40%
of the expected nominal capacity.
3. Continue monotonic loading from 40%, such
that 100% of the expected normal capacity isreached in under 15 minutes.
4. Measure longitudinal interface slip
continuously during loading, at least until theload has dropped to 20% below maximum.
80 mm packers
310UC158-HD bolts to strong floor
610UB101295
"foot" frame bearing
610UB101loading plate
"head" frame
horizontal stiffer
bearingload cell
1000 kN jack
2410
7/28/2019 Shear Stud Cap in Steel Decks
13/20
5. Measure transverse separation between thesteel beam and the composite slab close to thegroup of shear studs.
Summary Details of Test Units
No. Code Slab
Dimension
fc No of
Studs
Comments
1 S1 1105x1000x120
25 3 Favourable
2 S2 1105x1000x
120
25 3 Favourable
3 S3 1105x1000x
120
25 3 Favourable
4 S4 1105x1000x
120
30 3 Favourable
5 S5 1105x1000x
120
25 6 Double
Staggered
6 S6 1105x1000x
120
25 3 Unfavourable
7 P1 1240x1000x120
30 4 Single Row
8 P2 1240x1000x120
25 4 Single Row
9 P3 1240x1000x
120
25 4 Single Row
10 P4 1240x1000x120
25 4 Double Rowat Double the
Spacing
11 P5 1240x1000x120
25 4 Single Row
Table 4.1 Shear Stud Test Units.
Figure 4.2 Unit 2 ready for concrete casting.
Figure 4.3 Unit P2 ready for concrete casting.
Figure 4.4 Test Unit S1 ready for testing.
5. SHEAR STUD TEST RESULTS
Reporting of the final shear force-slip history
adopted the format shown in figure 5.1, while
figure 5.2 is from the test results of unit S4.
Figure 5.1 Typical shear force-slip history
diagram.
Figure 5.2 Unit S4 test results.
The following observations were recorded during
testing of the units. For the secondary beams, thecracks formed transverse to the beam especially at
the first and third trough. The crack adjacent to the
third trough typically was the first crack to form butdid not affect the results. The longitudinal crack,
which is also shown in figure 5.3, typically formedat or near the peak shear stud strength achieved, it
also shows an example of the crack formationtypical for a secondary beam. Delamination of the
slab also occurred, figure 5.4, as well as an
interesting phenomenon named the biting
Phenomenon of the decking into the steel beam,
see figure 5.5. Another interesting aspect of testingwas the wedging of the concrete between the
0
10
20
30
40
50
60
70
80
90
100
110
120
0 2 4 6 8 10 12
Mean Slip (mm)
Shearforce/stud
(kN)
100.21 kN (NZS 3404)
86.6 kN (4.1)
106 kN (max) and L1
84.4 kN (80% of max)L2
L3
Mean slip (mm)
Shearforce/stud
(kN)
Starting from end of first 25 cycles
(qr)n (NZS 3404) (=1.0)
Revised qr
Q max (kN)
80 % of max
7/28/2019 Shear Stud Cap in Steel Decks
14/20
shear stud and the decking, see figure 5.6. Theseobservations were common for all secondary beamtest units.
As for the primary beam, longitudinal cracks
parallel to the beam occurred with curving of theslab due to the splitting of the concrete pushing
against the stud. Figure 5.7 demonstrates thecurving while figure 5.8 shows the typical
longitudinal cracks. Refer to (Zaki, 2003), Chapter
6 for detailed observations of the test units.
Figure 5.3 Secondary beam cracks.
Figure 5.4 Delamination of the slab.
Figure 5.5 Biting Phenomenon.
Figure 5.6 Wedging of the concrete.
Figure 5.7 Curving of the slab in the PrimaryBeam.
Figure. 5.8 Primary Beam cracks.
6. SHEAR STUD TEST RESULTS-
DISCUSSION
6.1. Introduction.
This section discusses the shear stud failure modes
and gives final recommendations for shear studcapacity and composite design provisions.
6.2 Failure Mode.
The main modes of failure described in theliterature are concrete pull out failure (stud
embedment failure), concrete crushing failure,shear stud fracture, and concrete splitting failure.
Of these, the major cause of failure in this series oftests was concrete splitting failure, with a case of
concrete crushing and splitting (Unit P4) and two
cases of a new mode of failure, which we arecalling Rolling Failure. This principally affected
7/28/2019 Shear Stud Cap in Steel Decks
15/20
unit S2, which had Rib Rolling Failure and unitP3, which failed due to a construction defect. Thefollowing section talks about the reason why
splitting and not cone pullout failure was the maincause of failure, even though the concrete cone
shape was present in nearly all the units tested.
6.2.1. Why Cone Pull Out Failure Was Not theMain Failure Mode.
Our initial recommendations and calculations used
to develop the test specimens were based on the
Canadian study by (Jayas and Hosain, 1988 &
1989) for the secondary beam, which in turn basedtheir equations on the reported embedment
failure. For the primary beams, initial
recommendations were based upon the longitudinal
splitting concept from (Oehlers and Bradford,
1995). However, embedment failure was not the
observed failure mode for any of the specimenstested. Therefore a new set of recommendations has
to be made, to better represent the failure mode that
occurred in this series of tests. Embedment failure
is the form of failure that always has a concretecone shape surrounding the shear studs where the
concrete around the cone gets separated from the
slab causing a drop in strength. It is not
accompanied by a longitudinal splitting crack. In
the tests conducted, although the cone shape waspresent in all the secondary beam units after
dissecting the unit, it was not the observed failuremode that limited the stud shear strength. As
previously reported, that was longitudinal splittingin all cases except for units S2 and P3 which failed
prematurely and unit P4 which failed by combined
crushing and splitting.
Further support for this can be seen from a study ofthe parameters that govern embedment strength.
According to (Oehlers and Bradford, 1995), theembedment strength is dependent on the ratio of the
stud height to the stud diameter (see figure 6.1)
while the strength can be derived from thefollowing equation.
( )beammaxhemb
DKD = (6.1)
Where, Demb is the shear strength that allows
variation in shear embedment strength, Kh can be
derived from line A-B-C in figure 6.1 and(Dmax)beam can be derived from equation 6.2.
Equation 6.2 represents the strength of a shear stud
in a solid concrete slab. It is also the original
equation that (NZS 3404:1997) Equation 13.3.2.1 is
derived from, as it incorporates both the concretecrushing and shear stud fracture resistance into one
equation. It is determined from a curve fit of testdata on push-off tests in solid slabs, with allowance
made for the test rig setup on the capacity. Details
Figure 6.1 Shear Embedment Strength Relationship
to find Kh (Oehlers and Bradford, 1995).
are given in section (2.4.6.3) of (Oehlers and
Bradford, 1995):
( )4.0
s
c35.0c
65.0uscbeammax E
EffA
n
1.13.4D
= (6.2)
where n is the total number of studs in the test
sample. Using the values from experimental tests
including the actual measured material properties,
the Shear Embedment Strength is calculated and isshown in figures. 6.2 and 6.3 for the secondary and
the primary beams, respectively.
The values of the shear embedment strength (Demb)means that, if no other form of failure occurs before
Demb is reached, then embedment failure will limit
the available strength. However, with these studs,slab crushing and shear stud fracture would occur
before embedment failure. In fact (Dmax)beam ,which
incorporates both the concrete crushing and shearstud fracture, clearly was also greater than the testresults, demonstrating that the failure mode was notthe concrete crushing or fracture of the studs at the
maximum stud strength. Therefore, according to the
Figure 6.2 Comparison between the test results and
the embedment, solid concrete failure modes for the
secondary beams.
results in Chapter 6 in (Zaki, 2003) and the
comparison shown above in figures 6.2 and 6.3
neither did shear embedment, concrete crushing or
0
10
20
30
40
50
60
70
80
90
100
110
120
130
140
0 1 2 3 4 5 6 7 8 9 10 11 12
Mean Displacement (mm)
Shearforce/stud
(kN)
(Dmax)beam = 123 kN
Demb = 135.3kN
7/28/2019 Shear Stud Cap in Steel Decks
16/20
Figure 6.3 Comparison between the test results and
the embedment, solid concrete failure modes for the
primary beams.
stud fracturing initiate the failure, but longitudinal
splitting did. It should be noted that stud fracture
was observed in units S6 and P4, however this didnot occur until well after the peak load was reached
and so was not the limiting factor in terms of stud
design capacity. These results show that revision to
(NZS 3404:1997) Equation 13.3.2.1 is needed.
6.3 Proposed Revision of NZS 3404 Cl 13.3.2.1
As mentioned in Section 2.4.3, equation 13.3.2.1 in
(NZS 3404:1997) has been amended in 2001 fromthe old format of:
dcscuccscdcr Af)Ef(A5.0q = (6.3)
Into:
dcscuccscdcr Af8.0)Ef(A4.0q = (6.4)
where the first part is for concrete crushing while
the second is for shear stud fracture. According toequation 6.3, from which this simplified equation is
derived, the present equation 6.4 underestimates thetrue value of the concrete crushing. It is
recommended that the equation 6.5, initiallyproposed by (Lin, et. al., 2001) as his equation 2.15,
and referenced in (Clifton, 2002), be used:
dcscuccscdcr Af8.0)Ef(A5.0q = (6.5)
This equation gives a value that is consistent withthe test results and with the original equation putforth by (Oehlers and Bradford, 1995), equation
6.2. Given that this is for a solid slab, dc=1.0 andthis term can be omitted giving equation 6.6 as the
proposed replacement to NZS 3404 Equation13.3.2.1:
scuccscr Af8.0)Ef(A5.0q = (6.6)
Comparing equations 6.4, and 6.6 with 6.2 we getthe following results, using the actual material
properties of the test:
Ec = 24.8 GPa Asc = 283.4 mm2
fu = 516 MPa fc = 24.3 MPa
Eq. 6.4 qr= 88 kN 117 kN
Eq. 6.6 qr= 110 kN 117 kNEquation 6.2 (Dmax)beam = 112 kN
It is clear that equation 6.6 shows closer results toequation 6.2 than equation 6.4. Therefore, it is
recommended that the present equation 13.3.2.1 in
(NZS 3404:1997) should be amended to equation
6.6, for welded studs in a solid concrete slab.
6.4 Making Allowance for Concrete Splitting in
Interior Beams.
The experimental tests showed that concrete
longitudinal splitting failure governed all tests
involving a single row of studs, either in a straightline or staggered. The equation for calculating thesplitting strength, Vsh, of a stud within a concrete
rib of effective width, bce, is given by (Oehlers and
Bradford, 1995). Equation 2.12, which can betransformed into equation 6.8:
+
=
c
2
c
sc
ce
sc
cecscsplit
h
8.1
h
d8.11
b
d1
1
b'fd54.0V
(6.8)
In this equation, bce is the effective width, dsc is the
stud diameter, and hc the effective haunch height forsplitting, taken as the minimum of (5.4dsc,to), whereto is the slab height.
In this instance, the actual splitting shear strength
has been determined by experimental testing, using
the process described on page 28, equation 55.26 of
(Hyland, C., et. al. 2001).
That equation is used to back-calculate and find the
effective width, bce, for the interior secondary andprimary beam configurations.
For the secondary beam, this results in the effective
width using the results from our test. Resulting in
the effective width being 440mm, for the presenttest conditions of the slab height being greater or
equal to 120mm, stud height greater or equal to 4xthe stud diameter and stud diameter of 16 to 22mm.
This effective width happens to be close to four
times the stud height used in the tests. (Lin, et. al.
2001) recorded that the concrete cone shape slope
angle was around 24 to 29, while the slope anglefor this test with the effective width of 440 mm was
0
10
20
3040
50
60
70
80
90
100
110
120
130
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
Mean Slip (mm)
S
hearforce/stud
(kN)
P2
P4
P5
Demb = 125.4kN
(Dmax)beam = 114 kN
7/28/2019 Shear Stud Cap in Steel Decks
17/20
24.4. This indicated that there may be arelationship between effective rib width and studheight. Therefore, a recommendation future testing
is to find if such a relationship between the stud
height and effective rib width exists and itsinfluence on the shear stud capacity.
Taking the effective width to be 440mm tocalculate the longitudinal splitting capacity, for the
studs in the favourable position, another factor isrecommended to be added to this equation to make
it consistent with the test results. This factor is the
stud-positioning factor (sp)taken as:
Favourable = 1.0
Unfavourable = 0.94
Double staggered = 0.84
This factor is the position of the stud in the
secondary beam, whether it is in the favourable,
unfavourable or double staggered.
Therefore, the recommended splitting equation tobe used for shear stud capacity estimation in the
secondary beam configuration is:
+
=
c
2
c
sc
ce
sc
cecscspsplit
h
8.1
h
d8.11
b
d1
1
b'fd54.0V
(6.9)
The following values and limits are required withthis equation:
bce = 440 mmto 120 mm
hsc 95 mmdsc from 16 mm to 22 mm.
hsc/dsc 4.32
Profile is 55mm trapezoidal deck. Where, bce =effective width to use for interior secondary beam
(ie runs over decking).
For the primary beam, splitting was clearly themain cause of failure for all single rows of studs.
Therefore the recommended equation 6.8 is also
used for the primary beam, back-calculating again
to find the effective rib width. This is also 440mmfor the present test conditions of the slab heightbeing greater or equal to 120mm, stud height of
greater or equal to 4 stud diameters, stud diameterof 16 to 22mm, and the deck fastened onto the
beam flange within 10mm at the flange edge.
Figure 6.4 demonstrates that edge distance. Thatequation is applicable to a single row of studs.
It was noted in unit P1, which had 30 MPa concrete
instead of 25 MPa, that the strength was 98 kN
which was 1kN more than the equivalent specimenusing 25 MPa concrete. The unit S4, which was thesecondary beam with 30 MPa strength, was 106 kN
which was approximately the same as the predictedvalue from equation 6.9. This difference in
strength could be due to the different 30 MPa
Figure 6.4 Edge distance of decking on Primary
Beam.
concrete batches used that were hand mixed, and
might have had different compressive strengthsfrom the cylinder test values. It is an aspect for
which future testing is recommended.
Unit P4, with the double row of studs at doublespacing, clearly had a combination of crushing and
splitting failure, as seen in figure. 6.5. The splitting
crack is clearly seen, but is deflected by the stud,
also the crushing of the concrete was also present.
This is also consistent with the parameterscontrolling splitting, which show that a double stud
row is not as susceptible to splitting is a single studrow.
Therefore, for unit P4 which had double the studs at
double the spacing, equation 6.6 is to be used to
better represent the failure mode and it also givesthe best estimate for the shear stud capacity. Where
equation 6.6 for crushing was 110 kN while our testresult was 104 kN, therefore equation 6.6 is slightly
Figure 6.5 Crushing and splitting failure in unit P4.
overestimating the value, which can be from the
minimal splitting cracks that did occur but were
deflected by the stud. A Double Stud safety
factor of (0.9) is recommended until future tests are
conducted to find the actual strength and whether afactor is needed or not.
10 mm
7/28/2019 Shear Stud Cap in Steel Decks
18/20
6.5 Extending Concrete Splitting Provision to
Spandrel Beams
6.5.1 Secondary Beam
For the spandrel secondary beam, it is
recommended to use equation 6.8 but taking theeffective width as:
ofce bbb += (6.10)
This is likely to be conservative but to an unknown
extent. Because the decking is not continuous over
the beam, its role in confining the concrete withinthe splitting zone of the stud (see figure. 2.4 (a))
will be limited and is ignored in this
recommendation. Also, using the post-splitting
reinforcement shown below is recommended:
Figure 6.6 Secondary Spandrel Beam.
The DH12 @ 300 mm was calculated using thepost splitting provisions of (Oehlers and Bradford,1995). Finally, (NZS 3404:1997), Cl. 13.4.1.3(3)
states that if the decking runs across the spandrel by
greater or equal to 550mm then the spandrel beamis to be treated as an internal secondary beam. Thatis consistent with the experimental tests.
6.5.2. Primary Beam
Similarly with the primary spandrel beam, excepttaking the effective width as follows:
oferiorint,ce
ce b2
b
2
bb ++= (6.11)
Also, use of the post-splitting reinforcement as
shown below is recommended:
Figure 6.7 Primary Spandrel Beam.
The DH12 @ 300 mm was calculated using the
post splitting equation 2.19.
6.6 Suppression of Rib Rolling Fracture
Unit S2 had what is called Rib Rolling Fracture
which is when the mesh depth is greater than theintended designed depth, setting the mesh
reinforcement below the tension zone in the slab,
causing the slab to tilt resulting in premature failure
of the unit. It is called the Rib Rolling Fracture
because the action of the forces in the slab cause the
slab to roll caused by the rolling moment
forces acting in the slab. This is demonstrated in
figure 6.8.
Figure 6.8 Rolling Fracture
To explain this failure mathematically, the concrete
elastic moment and the crack moment were
calculated for both unit S1 and S2 to give a
comparison between the two failure modes.
First, for unit S2 it had the following
characteristics: the transverse crack that caused the
failure L5 occurred at a shear force/stud of 58 kN.
The mesh depth at the crack was 50mm, making the
centre of the reinforcement to the top of the slab
height 56mm. Basing the calculations on that we
get the following:
Total area of mesh and reinforcement = 618mm2
Elastic neutral axis = 34.75mm from the top of the
slab.
Resulting Elastic Concrete Moment before cracking
is thus 2.23kNm
While the post-splitting moment, calculated in
accordance with figure 6.9, using the conventional
reinforced concrete theory, is 3.953 kNm
This indicate that the concrete will develop a crack,which actually happened, but when the result of this
unit is compared to unit S1 which had the following
characteristics, the transverse crack that caused the
failure L4 occurred at a shear force/stud of 92 kN.
The mesh depth at the crack was 40 mm making the
centre of the reinforcement to the top of the slab
height 46 mm. Basing the calculations on that we
get the following:
DH 12 @ 300 mm
bobf
50
DH12
bce,interior/2 bobf/2
DH 12 @ 300 mm
DH12
< 220 mm
a. Mesh Depth at 35 mm; Unit S1
.
ActuatorDirection
35 mm
Mesh> 35mm
b. Mesh Depth at 50 mm; Unit S2
ActuatorDirection
Neutral Axis
7/28/2019 Shear Stud Cap in Steel Decks
19/20
Total area of mesh and reinforcement = 618 mm2
Elastic neutral axis = 33.8 mm from the top of the
slab.
Resulting Elastic Concrete Moment before cracking
then becomes 2.11 kNm
While the Moment of the concrete after cracking is
6.36 kNm
Now this clearly shows that for unit S1 the crack
will also appear, but will require a larger moment to
cause it. The calculation of the Ultimate Moment
Capacity was also conducted for further proof.
Yield stress fy was found to be 448.5 MPa.
T = Asfy = 618x0.4485 = 277.2 kN
04.13b'f85.0
Ta
c
== mm
Unit S2: M=277.2(65-56-(13.04/2))= 0.687 kNm
Unit S1: M=277.2(65-46-(13.04/2))= 3.459 kNm
Figure 6.9 Forces actions after cracking.
This shows that for unit S2 there is not sufficient
moment generated to withstand the forces acting on
the slab, while for unit S1 there was sufficient
moment to withstand the force and generate goodstrength. Figure 6.9 shows the ultimate moment
actions.
This mode of failure can be prevented by ensuring
that the mesh depth is not greater than 35mm fromthe top of the slab.
6.7 Recommended Changes to the Composite
Beam Design Procedure.
6.7.1 Minimum Shear Connection Ratio (ie.
Partial Composite Action)
From a comparison of all the provisions it isrealistic to amend the Partial Composite Action
limit to that given by the Eurocode 4 (Clause6.1.2(2)), to give a more realistic shear connection
ratio (PSC). The New Zealand provisions state that
the PSC is taken as a minimum of 50 %, while theEurocode stipulates a minimum value of PSC br
taken as 40 % up to 10 meters, increasing to 100%at 25 meters.
6.7.2 Correlation factor for Component
Capacity Equations.
This is being presented for completeness although it
is not intended to make changes to the design
procedure.
Table 6.2 shows the influence on shear stud numberdetermination if this is determined by matching
design capacity of shear stud to design capacity of
the critical component action, as is done with the
three international procedures studies. Where thecompression generated within the concrete slab
governs, adopting this approach would result in areduction of 0.83x the exact number of shear studs
required by current New Zealand practice. Where
the tension generated within the steel beam
governs, adopting this approach would increase the
number of shear studs required by current NewZealand practice.
The net result across all application would be a
benefit in terms of reducing the number of shear
studs required, however the complexity of changingdesign process outweighs this benefit. It is therefore
preferable to leave the currant practice of matchingdesign shear stud capacity, incorporating a partial
strength reduction factor = 1.0 in positive momentregions, to the nominal component capacity in
order to determine the number of shear studs
required.
Canada UK Eurocode
NewZealand
Shear
Stud
0.8 1/1.25 1/1.25 1.0
Concrete 0.6 1/1.5 1/1.5 1.25/1.5
= 0.83
Steel 0.9 1/1.1 1/1.1 1.25/1.1= 1.13
Table 6.2. Strength Reduction Factor Comparison.
7. RECOMMENDATIONS FOR FURTHER
RESEARCH.
These are as follows:
(i) To determine the influence of rib endsupport conditions on suppressing the rib
rolling failure shown in the secondary
beam tests, by adding stiffening ribs to the
test specimens to represent continuity of
slab beyond an internal secondary beam.(ii) To determine the influence of shear stud
height/diameter ratio on the load-deflection characteristics and design
capacity reached (i.e. provide experimental
data to replace the dotted line AB in
Figure. 6.1).
Actuator Direction
Crack
a
T
Cjd
Compression
Block
Mesh
7/28/2019 Shear Stud Cap in Steel Decks
20/20
(iii) To determine the influence of mesh heighton spandrel secondary beam capacity.
(iv) To determine the splitting capacity of
spandrel beams and so allow the design
recommendations of section 6.5 to be
updated.
REFERENCES
Bird, G.D. and Klemick, M.P.; HiBond Design
Wizard for Composite Design of the HiBond
Flooring System, Version 1.0; Dimond, Auckland,
New Zealand, 2002.
British Standard (BS 5950 (1990)). Structural use
of steelwork in building, Part 3: Design in
composite construction, Section 3.1: Code of
practice for design of simple and continuous
composite beams, British Standards Institution,London.
Butterworth, J. (2000). Push-off tests on shear
studs used with a deep ribbed deck, Auckland
UniServices Limited, University of Auckland,Report No. 8258.00, (pp. 25).
Canadian Standard (CSA S16-01: 1984). Limit
States Design of Steel Structures, CanadianStandard Association, Ontario, Canada.
Canadian Standard (CSA S16-01: 2001). Limit
States Design of Steel Structures, Canadian
Standard Association, Ontario, Canada.
Clifton, C. (1998). Reminders on good detailingand construction practice", Steel Design andConstruction Bulletin, HERA, No. 42, (pp. 8).
Clifton, C. (2002). Notes prepared for Composite
Steel Design and Construction Seminar, HERAReport R4-113, 2002.
Eurocode 4: ENV 1994-1-1:1994, (1994). Designof Composite Steel and Concrete Structures Parts
1-1 General Rules and Rules for Buildings, BSI
Standards, London, pp. 143-148.
Grant, J., Fisher, J.W. and Slutter, R.G., (1977).
Composite beams with formed metal deck,Engineering Journal of the American Institute of
Steel Construction, Vol. 14, 1st
quarter, (pp. 24-42).
Hawkins, N.M. and Mitchell, D., (1984). Seismic
Response of Composite Shear Connections,Journal of Structural Engineering, ASCE, Vol.
110, No. 9 (pp. 2120-2136).
Hyland, C., Clifton, C., Butterworth, J,. andStickland, S., (2000). Shear studs in composite
construction: concepts in determining the shear studdesign shear capacity, Steel Design andConstruction Bulletin, HERA, No.55, (pp. 18-28).
Hyland, C., Clifton, C., Butterworth, J,. and
Stickland, S., (2001). Composite Down-Stand
Steel Beam Behaviour with a Profiled Deep-Deck
Slab, Proceeding of Australasian StructuralEngineering Conference, 2001.
Jayas, B. S. and Hosain, M. U. (1988). Behaviour
of headed stud in composite beams: push-out tests,Canadian Journal of Civil Engineering, Vol. 15,
No. 2, (pp. 240-253).
Jayas, B. S. and Hosain, M. U. (1989). Behaviourof headed stud in composite beams: full-size tests,Canadian Journal of Civil Engineering, Vol. 16,
No. 2, (pp. 712-724).
Johnson, R. P. and Anderson, D. (1993).Designers Handbook to Eurocode 4 part
1.1:Design of Composite Steel and Concrete
Structures. Thomas Telford, London.
Lin, Y., Butterworth, J., and Ingham, J. (2001).
Capacity of Shear Studs Embedded in Lightweight
polystyrene Concrete Diaphragms, School of
Engineering, Civil and Resource Engineering,
University of Auckland, Report No. 607, December2001.
New Zealand Standard (NZS 3101: Part 2:1995).Concrete Structures Standard Part1 The Design
of Concrete Structures, Standards New Zealand,
Wellington, pp. 209-212.
New Zealand Standard (NZS 3404: Part 1:1997).
Chapter 13, Design of Composite Members and
Structures, Standards New Zealand, Wellington.
Oehlers, D. J. and Bradford, M. A. (1995).Composite Steel and Concrete Structural Members,Elsevier Science Ltd, Oxford, U.K.
Ollgaard, J. G., Slutter, R. G., and Fisher, J.W.(1971). Shear strength of stud connections in
lightweight and normal-density concrete,Engineering Journal, American Institute of Steel
Construction, Vol. 8, (pp. 55-640.
Slutter, R. G. and Driscoll, G. C. (1965). Flexural
strengths of steel concrete composite beams,
Proc. ASCE, J. structural Div., Vol. 91, No. ST2,
April 1965, pp. 55-64.
Zaki, R.J. (2003) Shear Stud Capacity in Profiled
Steel Decks, MEngSt, Project Report, University
of Auckland, September 2003.