Page 1 of 26 Signature of the tenderer
under seal of the firm
SOUTH EASTERN COALFIELDS LIMITED
NIT No.34/OT/SECL-KUSMUNDA/Civil & P. Way/PKG-II/2015
Dated 17.7.2015
Tender document for Earthwork in Railway formation,
Construction of bridges, blanketing, P. Way Linking Works
including supply of P. Way fittings & track Ballast, PSC Sleepers
and Points & crossings in connection with construction of railway
infrastructure for providing railway siding at Kusmunda project
for dispatch of washed and raw coal(PACKAGE-II)
PART – 2
REVISED FINANCIAL BID
SCHEDULE (BILL) OF QUANTITIES
(PERCENTAGE RATE CONTRACT)
Issued to (Name of Tenderer):________________________________________
Address of tenderer:_________________________________________________
Signature of officer issuing the documents___________________
Designation _______________________________
Date of Issue___________________
(A Govt. of India Enterprise)
Regional Project Office, KOLKATA
56 C R Avenue, 2nd floor, Kolkata – 700 012
e.mail : [email protected]
Phone No: (033) 22367118/7146/7162/7143(Fax)
Page 2 of 26 Signature of the tenderer
under seal of the firm
PART – 2
REVISED FINANCIAL BID
SCHEDULE (BILL) OF QUANTITIES
PERCENTAGE RATE CONTRACT
Name of work: Earthwork in Railway formation, Construction of bridges,
blanketing, P. Way Linking Works including supply of P. Way fittings & track
Ballast, PSC Sleepers and Points & crossings in connection with construction of
railway infrastructure for providing railway siding at Kusmunda project for
dispatch of washed and raw coal (PACKAGE-II).
POINT TO BE NOTED WHILE QUOTING PERCENTAGE RATE
1. The time allowed for completion will be 24 (Twenty four) months from
the date of start which is define in schedule-F under clause 5.1a of clause
of contract.
2. Where tender has been invited on percentage rate basis, percentages on
the estimated cost (whether above or below) are to be quoted for
schedule.
Page 3 of 26 Signature of the tenderer
under seal of the firm
PART –2
FINANCIAL BID (REVISED) SCHEDULE (BILL) OF QUANTITIES
(PERCENTAGE RATE TENDER)
ABSTRACT OF COST
(PERCENTAGE TO BE QUOTED BY THE BIDDER)
Part-A
SCHEDULE DESCRIPTION TOTAL ESTIMATED COST (IN
RUPEES)
Schedule-1 Earth work in Railway formation Rs. 257635882.00
Schedule-2 Minor Bridges work Rs. 173672978.00
Schedule-3 Construction of ROB(3x 24m+ 1x18m Composite Girder) with ancillary work
Rs. 136831629.00
Schedule-4 Drain, Retaining wall/Toe wall, Path way and dismantling items etc.
Rs. 110007651.00
TOTAL ESTIMATED COST
OF PART-A (RUPEES) Rs. 678148140.00
PERCENTAGE ABOVE (+)
OR BELOW (-) OF TOTAL ESTIMATED COST OF
PART-A AS QUOTED
PERCENTAGE IN
FIGURES
PERCENTAGE IN WORDS
TOTAL QUOTED COST OF
PART-A BASED ON PERCENTAGE QUOTED (+)
OR (-) (RUPEES)
AMOUNT IN FIGURES
(RUPEES)
AMOUNT IN WORDS (RUPEES)
LESS REBATE ( %) IF
ANY (IN FIGURES) LESS REBATE ( %) IF
ANY (IN WORDS)
NET QUOTED COST OF PART-A
* Strike out which is not applicable i) SIGNATURE OF AUTHORISED SIGNATORY OF TENDERER
ii) NAME OF SIGNATORY
iii) NAME AND SEAL OF TENDERER iv) DATE
v) PLACE
Note:
TENDERERS ARE REQUESTED TO QUOTE THEIR RATE IN THIS PAGE ONLY AND NOT IN SCHEDULES, BASIC
RATES HAS BEEN SHOWN IN SCHEDULES FOR GUIDENCE
Page 4 of 26 Signature of the tenderer
under seal of the firm
Part-B
SCHEDULE DESCRIPTION TOTAL ESTIMATED COST (IN RUPEES)
Schedule-1 P-Way works Rs. 176694780.00
Schedule-2 Supply of PSC Sleepers Rs. 139037677.00
Schedule-3 Supply of P-Way Fittings Rs. 24956453.00
Schedule-4 Supply of Point & Crossing Rs. 51690280.00
TOTAL ESTIMATED COST
OF PART-B (RUPEES) Rs. 392379190.00
PERCENTAGE ABOVE (+) OR BELOW (-) OF TOTAL
ESTIMATED COST OF PART-B AS QUOTED
PERCENTAGE IN FIGURES
PERCENTAGE IN
WORDS
TOTAL QUOTED COST OF PART-B BASED ON
PERCENTAGE QUOTED (+) OR (-) (RUPEES)
AMOUNT IN FIGURES (RUPEES)
AMOUNT IN WORDS
(RUPEES)
LESS REBATE ( %) IF ANY (IN FIGURES)
LESS REBATE ( %) IF ANY (IN WORDS)
NET QUOTED COST OF
PART-B
NET QUOTED COST OF PART-A+ PART-B
Rs.
* Strike out which is not applicable
i) SIGNATURE OF AUTHORISED
SIGNATORY OF TENDERER
vi) NAME OF SIGNATORY
vii) NAME AND SEAL OF TENDERER
viii) DATE
ix) PLACE
Note:
TENDERERS ARE REQUESTED TO QUOTE THEIR RATE IN THIS PAGE ONLY AND NOT IN SCHEDULES, BASIC
RATES HAS BEEN SHOWN IN SCHEDULES FOR GUIDENCE
Page 5 of 26 Signature of the tenderer
under seal of the firm
Name of work: Earthwork in Railway formation, Construction of bridges, blanketing, P. Way Linking
Works including supply of P. Way fittings & track Ballast, PSC Sleepers and Points & crossings in
connection with construction of railway infrastructure for providing railway siding at Kusmunda
project for dispatch of washed and raw coal (PACKAGE-II).
NIT No.34/OT/SECL-KUSMUNDA/Civil & P. Way/PKG-II/2015 Dated 17.7.2015
SCHEDULE (BILL) OF QUANTITIES (Revised)
PACKAGE-II
Part-A
Schedule-1 (Earth work in Railway formation)
Sl
No.
Description of Item Unit Qty Estimated
Rate (Rs)
Estimated
Amount (Rs)
1 Earthwork in cutting (classified) in formation,
trolley refuges, side drains, level crossing
approaches, platforms, catch water drains,
diversion of nallah & finishing to required
dimension and slopes to obtain a neat
appearance to standard profile inclusive of all
labour, machine & materials and removing &
leading all cut spoils within a lead upto 4 Km
from cutting edge or for filling in
embankment with all leads within the section
limit, lifts, ascent, descent, loading,
unloading, all taxes/royalty, clearance of site
and all incidental charges, bailing & pumping
out water, if required, etc. complete as per
directions of the Engineer-in-Charge. The
work is to be executed as per latest /
updated edition of "Guidelines for Earthwork
in Railway Projects" issued by RDSO,
Lucknow. Cut trees shall be property of SECL
and to be deposited in the client godown
unless specified otherwise in the Special
Conditions of Contract
Note: (i)All useable earth arising from cuts
spoils shall be led into bank formation and
useable spoils shall be dumped /stack. (ii) all
hard rock/and boulders not fit for filling will
be stacked by the contractor and will be
property of the SECL.
a) In all conditions and classifications of soil
except rock
cum 710170.00 180.00 127830600.00
b) Soft rock not requiring blasting in all
conditions
cum 62000.00 305.75 18956500.00
Page 6 of 26 Signature of the tenderer
under seal of the firm
Sl
No.
Description of Item Unit Qty Estimated
Rate (Rs)
Estimated
Amount (Rs)
1A Removal of excavating overburden (including
drilling in all kinds of strata/over burden),
mechanical transfer into tippers,
transportation and unloading the excavated
materials & silt, dumping, dozing,
scraping/removal of bands , maintenance of
haul road, water sprinkling and spreading of
materials at the site shown and as per
directive of the Engineer-in-charge .The
above rate inclusive of finishing to required
dimension and slopes to obtain a neat
appearance to standard profile ,all labour,
machine & materials and removing & leading
all cut spoils within a lead upto 2.650 Km
from cutting edge with all lifts, ascent,
descent, loading, unloading,all taxes/royalty,
clearance of site and all incidental charges
etc.
NOTE: Please refer proforma-4 as attached
in the tender documents.
cum 812000.00 65.75 53389000.00
2 Earthwork in filling in embankment, guide
bunds, around buried type abutments, bridge
gaps, trolley refuges, rain bunds, if provided,
platforms etc. with earth excavated from
outside the SECL land boundary entirely
arranged by the contractor at his own cost
as per RDSO's latest guidelines and
specifications and special condition of
contract including all leads, royalty, lifts,
ascents, descents, crossing of nallahs or any
other obstructions. The rates shall include all
dressing of bank to final profile, demarcation
and setting out of profile, site clearance,
removing of shrubs, roots of vegetations
growth, heavy grass, benching of existing
slope of old bank, all handling/re-handling,
taxes, octroi and royalty etc. as a complete
job. Cut trees shall be property of SECL and
to be deposited in the client godown unless
specified otherwise in the Special Conditions
of Contract.
cum 3000.00 272.23 816690.00
Page 7 of 26 Signature of the tenderer
under seal of the firm
Sl
No.
Description of Item Unit Qty Estimated
Rate (Rs)
Estimated
Amount (Rs)
3 Extra for mechanical compaction of earth
and blanketing material filled in embankment
with contractor’s rollers of suitable capacity,
type and size to achieve specified density as
per specification, testing as per IS codes
including cost of water, T&P, consumable
material and all labour as a complete job. The
work is to be executed as per Latest edition
of "Guidelines for Earthwork in Railway
Projects" issued by RDSO, Lucknow.
cum 111250.00 19.29 2146012.50
4 Supplying, laying and spreading blanketing
materials (Natural or Mechanically prepared
as per GE-1 or G.E.IRS-2) over new / old
embankment / cutting in layers of 30cm in
loose state to make the embankment of
designed profile as per specifications. The
rate is inclusive of initial site clearance,
cutting of shrubs, removal of roots of
vegetation growth & heavy grass, surfacing &
leveling to give required slope, benching, if
required on existing bank slope, dressing and
finishing of bank, all lead & lift, ascent,
descent, crossing of nallahs / other
obstructions, spreading the material and final
dressing of slopes and top surface as per
specified camber using contractor’s own
machinery, equipment, T&P, labour etc. as a
complete job.
cum 108250.00 477.16 51652570.00
5 Turfing / planting, including all lead & lift and
watering as required until properly rooted
with. Note - Initially payment of only 40% will
be made. Balance 60% will be paid only after
3 months of maintenance period : Turfing
with sods, 10cm thick and 20cm square
closely laid
100
Sqm
3850.00 7627.50 293658.75
Sub total of schedule-1
255085031.25
Add 1% labour welfare cess
2550850.31
Total amount of Schedule-1
257635881.56
Say Rs
257635882.00
Page 8 of 26 Signature of the tenderer
under seal of the firm
Schedule-2 (Minor Bridges work)
Sl
No.
Description of Item Unit Qty Estimated
Rate (Rs)
Estimated
Amount (Rs)
1 Earthwork in excavation for foundations and
floors of the bridges, retaining walls etc.
including setting out, dressing of sides,
ramming of bottom, getting out the excavated
material, back filling in layers with approved
material and consolidation of the layers by
ramming and watering etc. including all lift,
disposal of surplus soil upto a lead of 300m, all
types of shoring and strutting with all labour
and material complete as per drawing and
technical specification as directed by Engineer
in charge
a)All kinds of soils
cum 10165.00 257.76 2620130.40
b)Ordinary rock
cum 1235.00 288.75 356606.25
2 Supplying, spreading and filling coarse sand
(no cohesive materials to be used) of approved
quality including watering and ramming in
foundation, plinth, behind the abutment, wing
wall, retaining wall in layers not exceeding
150mm thick including its compaction as per
direction of Engineer-in-charge. The rate
includes all lead, lift, ascent, descent, crossing
of Railway line etc. complete with contractor’s
labour, materials, tools and plant.
cum 3475.00 1094.11 3802032.25
3 Providing and laying in position machine
mixed, machine vibrated and machine batched
Design Mix Cement Concrete M35 grade (Cast
in-Situ) in bottom/top slab, side walls, toe wall
and sumps haunch filling head walls or any
other component using 20mm graded crushed
stone aggregate and coarse sand of approved
quality of cast in-situ RCC box of size upto 5m
(bigger inside dimension) including finishing,
Admixtures in recommended proportions (as
per IS:9103), if approved in Mix design, to
accelerate, retard setting of concrete, improve
workability without impairing strength and
durability, complete as per drawings and
technical specifications as directed by Engineer
in charge. Rate includes cost of cement and
providing thermocol at expansion joint but
excludes cost of reinforcement and shuttering,
which will be paid in seperate items.
cum 6170.00 5681.47 35054669.90
Page 9 of 26 Signature of the tenderer
under seal of the firm
Sl
No.
Description of Item Unit Qty Estimated
Rate (Rs)
Estimated
Amount (Rs)
4 Providing and laying in position machine
mixed, machine vibrated and machine batched
Design Mix Mass Cement Concrete M-20 grade
(cast in-situ) using 20mm graded crushed
stone aggregate and coarse sand of approved
quality in Drop and curtain wall and alike
structures below bed level, including the cost
of centring, shuttering and finishing complete
as per drawings and technical specifications as
directed by Engineer. Payment for The rate
includes cost of cement and also providing
thermocol at expansion joint but excluding
cost of reinforcement which will be paid in
seperate items.
cum 1600.00 5028.77 8046032.00
5 Centring and shuttering including strutting,
propping etc. and removal of form for :
a) RCC Foundation
Sqm 2650.00 162.94 431791.00
b) Abutment, pier, wing walls and return walls
Sqm 1632.00 278.77 454952.64
c) In Bottom/top slab, side walls, toe wall and
sumps haunch filling head walls or any other
component
Sqm 10257.00 278.77 2859343.89
6 Supplying reinforcement for R.C.C. work
including straightening, cutting, bending,
placing in position and binding all complete -
Thermo-Mechanically Treated bars Kg 968735.00 70.85 68634874.75
7 Providing and laying pitching with stone
boulders weighing not less than 35kg each
with the voids filled with cement sand mortar
1:4 on slopes laid over prepared filter media
including boulder apron laid dry in front of toe
of embankment complete as per drawing and
Technical specifications (filter media to be paid
separately under the relevant item)
cum 410.00 2102.00 861820.00
8 Providing and laying of filter media consisting
of granular materials of GW, GP, SW groups as
per IS:1498-1970 in required profile behind
boulder filling of abutments, wing walls /
return walls etc. above bed level with all
labour and material complete job as per
drawing and technical specification of RDSO
Guidelines.
cum 22580.00 2079.76 46960980.80
Page 10 of 26 Signature of the tenderer
under seal of the firm
Sl
No.
Description of Item Unit Qty Estimated
Rate (Rs)
Estimated
Amount (Rs)
9 Providing weep holes by making suitable
opening or drilling in existing Brick Masonry /
Plain / Reinforced Concrete abutment, wing
wall/return wall with 100 mm dia AC pipe,
extending through the full width of the
structure complete.
metre 298.00 372.82 111100.36
10 Supplying and providing Boulder Backing
behind wing wall, return wall, retaining wall
with hand packed boulders & cobbles with
smaller size boulders toward the back
including all lead, lift, labour & other incidental
charges as complete work in all respect. cum
1884.00 933.71 1759109.64
Sub total of schedule-2
171953443.88
Add 1% labour wellfare cess
1719534.44
Total amount of schedule-2
173672978.32
Say Rs
173672978.00
Schedule-3 Construction of ROB(3x 24m+ 1x18m Composite Girder) with ancillary work
Sl
No.
Description of Item Unit Qty Estimated
Rate (Rs)
Estimated
Amount (Rs)
1 Earthwork in excavation for foundation of
structures, RE wall and protection works in all
types of soil including ordinary rock and
marshy soil for all depth, including disposal of
surplus materials with all lifts and leads upto
1000 m complete as per drawings, Technical
Specifications Section 300, 2900 and as
directed by Engineer.
Cum 675.00 124.90 84307.50
2 Providing and laying in position Plain Cement
Concrete of M-15 Grade in levelling course
below open foundations, pile caps, approach
slabs, RE wall, in inspection ladders, annular
filling around foundation in rock and below
concrete wearing coat including centering and
shuttering complete as per drawings and
Technical Specifications Sections 1500 and
1700 and as directed by Engineer.
Cum 50.00 5422.48 271124.00
Page 11 of 26 Signature of the tenderer
under seal of the firm
Sl
No.
Description of Item Unit Qty Estimated
Rate (Rs)
Estimated
Amount (Rs)
3 Providing and laying in position Reinforced
Cement Concrete of M-35 grade in bored cast
in situ concrete piles including boring of piling,
but excluding cost of routine load test, cost of
reinforcement steel complete as per drawings
and Technical Specifications Sections
1100,1700 and IRC 78-2000 and as directed by
Engineer: For 1200 mm diameter piles in soil,
bouldary strata and soft rock.
Rm 630.00 14592.91 9193533.30
4 Providing and laying Reinfored cement
concrete of M-40 Grade in Deck Slab & End
girder including centering and shuttering but
excluding the cost of reinforcement all
complete as per drawing and Technical
Specifications Sections 1500, 1700, 2300 and
as directed by Engineer.
Cum 370.00 8468.41 3133311.70
5 Supplying reinforcement for R.C.C. work
including straightening, cutting, bending,
placing in position and binding all complete :
Thermo-Mechanically Treated bars
Kg 309815.00 70.85 21950392.75
6 Conducting vertical load testing of a single pile
upto following capacity in accordance with
IS:2911(Part-IV) including installation of
loading platform and preparation of pile head
or construction of test cap and dismantling of
test cap after test etc. with all labour ,
material, tool & plants, equipment, machinery,
etc complete as per drawing and specification,
as directed by the Engineer.
(a) Intial load test up to pile capacity 300 MT. Nos 1.00 90260.92 90260.92
(b) Routine load test up to pile capacity 300
MT.
Nos 2.00 83599.10 167198.20
7 Conducting lateral load testing of a single pile
upto following capacity in accordance with
"IS:2911(Part-IV) for determining safe
allowable lateral load of pile " with all labour,
material, tool & plants, equipment, machinery,
etc complete as per drawing and specification
as directed by the Engineer: Piles with lateral
load capacity above 20 tonnes.
Nos 1.00 57071.81 57071.81
8 Providing and laying in position Reinforced
Cement Concrete of M-35 grade in pile caps
including centering and shuttering but
excluding cost of reinforcement all complete
as per drawing and Technical Specifications
Sections 1100, 1500 and 1700 and as directed
by Engineer.
Cum 440.00 6812.83 2997645.20
Page 12 of 26 Signature of the tenderer
under seal of the firm
Sl
No.
Description of Item Unit Qty Estimated
Rate (Rs)
Estimated
Amount (Rs)
9 Providing and laying in position concrete in
Reinforced/Plain Cement Concrete of M-35
grade in pier, pier cap,
pedestals,cantilever/counterfort abutment,
abutment cap,dirt wall,splayed wing wall, box
return, cantilever return, screen wall, median
wall, curtain wall, cut-off wall, inspection
ladders, box cell structures, seismic restrainer
etc. including centering and shuttering but
excluding cost of reinforcement all complete
as per drawings and Technical Specifications
Sections 1500, 1700 and 2200 and as directed
by Engineer.
Cum 320.00 7679.04 2457292.80
10 Providing and laying in position 65mm thick
wearing coat consisting of 40mm thick
bituminous concrete overlaid wih a 25 mm
thick layer of mastic asphalt over deck slab
after applying prime coat complete as per
drawings and Technical Specifications Sections
500 and 2700 and as directed by Engineer
Sqm 1345.21 1288.26 1732982.81
11 Supplying,fitting and fixing in position true to
line and level POT-PTFE bearing consisting of a
metal piston supported by a disc or
unreinforced elastomer confined within a
metal cylinder, sealing rings, dust seals, PTFE
surface sliding against stainless steel mating
surface, complete assembly to be of cast steel
/ fabricated structural steel, metal and
elastomer elements complete as per IS 2062,
is: 1030, AISI: 304, AISI: 316, IS:6911, BS:3784,
IS: 3400, IS:226, BS- 5400, Bridge code and as
per drawing and approved Technical
Specifications.The design of the bearings shall
be submitted by the manufacturers/contractor
and got approved from Railway before
fixing.Test report of the bearings should be got
approved before the materials are lifted from
the manufacturer premises, Payment is based
on 250 MT capacity of Bearing : POT-PTFE
Bearing
MT
Bearing
Capacity
5585.80 576.26 3218873.11
12 Providing and fixing in position Expantion
Joints under supervision of manufacturer
specialist complete as per drawings and
Technical Specifications Section 2600 and as
directed by Engineer : Strip seal type capable
of taking 40mm movement
Rm 71.00 28434.18 2018826.93
Page 13 of 26 Signature of the tenderer
under seal of the firm
Sl
No.
Description of Item Unit Qty Estimated
Rate (Rs)
Estimated
Amount (Rs)
13 Proving and fixing in position drainage spouts
(Diameter of GI pipe in the assembly should be
150mm dia & length 5m) complete as per
drawings and Technical Specifications Clause
2705 and as directed by Engineer.
Nos 106.00 4797.30 508513.27
14 Providing and fixing in position with clamps
100 mm dia CPVC/GI downtake and runner
pipe including joining with drainage spout
pipe, providing couplers, bends etc. complete
as per drawings and as directed by Engineer.
Rm 270.00 2971.68 802353.90
15 Providing and fixing in position MS pipe railing
including MS plate holder to be fixed with
vehicular/high containment crash barrier as
per drawing and directed by Engineer.
Rm 220.00 3664.81 806257.10
16 Reinforced cement concrete M-35 grade
approach slab including reinforement and
formwork complete as per drawing and
Technical specification.
Cum 40.00 14105.61 564224.20
17 Providing and laying in position Reinforced
Cement Concrete of Grade M-40 in Safety
Kerb, Friction Slab, crash barrier/ high
containment crash barrier as per drawing
excluding cost of reinforcement, including
centering and shuttering ,bituminous fibre
board and premoulded joint filler at expansion
joints/ gap locations but MS pipe railing all
complete as per drawing and Technical
Specifications Sections 1500, 1600, 1700 and
2700 and as directed by Engineer-in- charge.
Cum 360.00 8104.25 2917530.00
18 Providing and fixing in positon 20 mm thick
bitumen impregnated fibre board conforming
to IS 1838 including cost of Primer, sealing
compound in expansion joints.
Rm 30.00 228.39 6851.78
19 Construction of Reinforced Earth Structures
(RES) together with the construction of
earthwork in layers, assembly & erection of
reinforcing element & placement of facial
panels/ block and all associated components
complete as per approved drawings and
Technical Specification 3100 and as directed by
Engineer
Page 14 of 26 Signature of the tenderer
under seal of the firm
Sl
No.
Description of Item Unit Qty Estimated
Rate (Rs)
Estimated
Amount (Rs)
a) Providing and erecting precast concrete
facial panels including untensioned
reinforcement, soil reinforcing element (
GeoStrap and other accessories like
connectors, non woven geotextile, lifting
anchores etc. foundation pad ,all accessories
and consumables and components including
drainage system, ground improvement,
capping beam, if required complete.
Sqm 2170.00 4429.97 9613040.33
b)Earhwork including excavation, backfilling,
grading and compaction with selected backfill
soil (φ ≥ 30 and U ≥ 1.8) meeting approved
design parameters in layers in soil reinforced
zone complete.
Cum 11940.00 1872.40 22356426.15
c)600 mm thick filter media behind Concrete
facia panel.
Cum 1300.00 2496.53 3245489.00
20 Providing and Constructing Granular Sub- base
(GSB) with Grading I of Table 400-1 , with
crushed aggregates by mix in place method
complete as per drawing and Technical
specifications clause 401.
Cum 315.00 2149.73 677165.34
21 Constructing Wet Mix Macadam (WMM) base
complete as per drawing and Technical
Specifications Clause 406.
Cum 305.00 2395.49 730624.45
22 Providing and applying prime coat with
bitumen emulsion grade (SS-1) over granular
surface complete as per Technical
specifications clause 502 : @ 6.0 kg to 9.0
kg/10 sqm
Sqm 1045.00 35.79 37395.33
23 Providing and applying tack coat with bitumen
emulsion grade (RS-1) over prepared surface
all complete as per Technical specifications
clause 503 : @ 2.0 kg to 2.5 kg/10 sqm over
bituminous surface
Sqm 1045.00 12.63 13198.35
24 Proving and laying Dense Bituminous
Macadam (DBM) course using bitumen of VG-
30 grade, complete as per drawing and
Technical Specifications Clause 505.
Cum 70.00 11185.44 782981.06
25 Providing and laying bituminous concrete (BC)
wearing course using bitumen of VG-30 grade,
complete as per drawings and technical
specifications clause 508.
Cum 42.00 12787.35 537068.65
Page 15 of 26 Signature of the tenderer
under seal of the firm
Sl
No.
Description of Item Unit Qty Estimated
Rate (Rs)
Estimated
Amount (Rs)
26 Providing and laying close graded premix
surfacing / mixed seal surfacing wearing course
using bitumen of VG-30 grade, complete as per
drawings and technical specifications clause 510
Sqm 1045.00 235.76 246369.20
27 Supplying of all types of structural steel
conforming to IS : 2062-2006 of Grade Fe 250B0 ,
fabrication, assembling, errection/slewing/end
launching of steel girders ( not requiring traffic
block) of span upto 36m (c/c of bearing) on sub-
structure including provision of trolley refuges, if
required, complete as per approved drawing
including one coat of Zinc chrome primer to IS-
104 and one coat of Zinc chrome Red Oxide to
IS:2074 & painting as per IRC specifications on all
members ,( Detailed fabrication and erection
drawings & launching methodology will be
prepared and got approved by the contractor
from Consultant). Rate includes fabrication of all
the types of battens, bracings, ties ,stiffners,
packing, diaphragms, shop rivets/welding, T&F
bolts, drifts, shop welds, templates, jigs, fixtures,
back up supports, accessories, transporting
various components from fabrication shop to site
, including loading, unloading , lift and taxes
comlete.Assembly of girders' on drift/bolts, field
riveting /welding, assembling of temporary
support for side slewing , raising of girders to the
bed block level , providing sliding arrangements
and slewing the girder in position , lowering of
girder on bearings and bed plates, grouting holes
in the bed block for fixing of HD bolts/anchore
pins of bed plates, all temporary
arrangements.Load testing may be done as per
IRC:24.The bearing sets to be provided with the
girders will be paid separately as per relevant
item separately.
Payment Schedule
a)Material at site-40%
b) Fabrication at site - 15%
c) Erection/launching-20%
d) Completion including painting and finishing-
25%.
MT 360.00 122940.42 44258551.20
Sub total = 135476860.33
Sub total of Schedule-3 135476860.33
Add 1% for labour wellfare cess= 1354768.603
Total amount of Schedule-3 136831628.94
Say Rs 136831629.00
Page 16 of 26 Signature of the tenderer
under seal of the firm
Schedule-4 (Drain,Retaining wall/Toe wall,Path way and dismantling items etc.)
Sl
No.
Description of Item Unit Qty Estimated
Rate (Rs)
Estimated
Amount (Rs)
1 Earth work in excavation as per approved
drawings and dumping at embankment site or
spoil heap, within SECL Land boundary ,including
50 m lead and 1.5 m lift, the shall be measured
from the centre of gravity of excavation to centre
of gravity of spoil heap: the lift to be measured
from natural ground level and paid for in layers of
1.5 m each, including incidental works, as per
specifications- in
a) All kinds of Soils cum 28799.00 119.00 3427081.00
b) Ordanary rock ( Not requiring blasting) cum 2880.00 358.92 1033689.60
2 Providing and laying in position cement concrete
of M 20 Grade including cost of cement but
excluding cost of centering and shuttering, as per
direction of Engineering- in -charge:
a) All works up to Plinth level
cum 16453.00 5028.77 82738352.81
b) All work above Plinth Level in Retaining
wall/toe walls, walls(of any thickness) etc
cum 2050.00 5406.00 11082300.00
3 Centreing and shuttering including strutting,
proping etc.and removal of form work for:
a) Foundations, Footings, bases of columns sqm 61000.00 163.42 9968620.00
b) Retaining walls, return walls, walls(any
thickness)
sqm 830.00 278.80 231404.00
4 Filling,watering and ramming earth in 15 cm
layers in floors and foundations with surplus earth
from foundations including 50m lead and 1.5 m
lift.
cum 6000.00 26.46 158760.00
5 Demolishing plain cement concrete including
disposal of material within 50m lead
1:2:4 or richer mix with max. 20 mm coarse
aggregate
cum 50.00 605.19 30259.50
6 Demolishing brick work including stacking of
serviceable material and disposal of unserviceable
material within 50m lead
In cement mortar cum 225.00 510.97 114968.25
Page 17 of 26 Signature of the tenderer
under seal of the firm
Sl
No.
Description of Item Unit Qty Estimated
Rate (Rs)
Estimated
Amount (Rs)
7 Dismantling roofing including ridges, hips valleys
and gutters etc. and stacking the material within
50m lead
G.I. sheet sqm 275.00 44.62 12270.50
8 Dismantling steel work in single sections including
dismembering & stacking within 50m lead in
R.S. joists./ Rails Kg 1500.00 0.86 1290.00
Channels, angles, tees and flats/ rounds or any
other rolled shape
Kg 900.00 0.63 567.00
9 Dismantling steel work and trusses upto 10m span
and 5m height in built up sections in angles, tees,
flats and channels including all gusset plates,
bolts, nuts, cutting rivets, welding etc. including
dismembering and stacking within 50m lead
Kg 2750.00 1.5 4125.00
10 Demolishing R.C.C. work including cutting and
stacking of steel bars and disposal of
unserviceable material within 50m lead. (Extra
payment for scraping, cleaning and straightening
of bars to be made separately)
cum 130.00 882.91 114778.30
Sub total of schedule-4 108918465.96
Add 1% labour wellfare cess 1089184.66
Total amount of schedule-4 110007650.62
Say Rs 110007651.00
Total of Part -A ( Sch.1+ Sch. 2+ Sch 3+Sch 4) = Rs.
678148140.00
Page 18 of 26 Signature of the tenderer
under seal of the firm
Part-B
Schedule-1 (P-Way works)
Sl
No.
Description of Item
Unit Qty Estimated
Rate (Rs)
Estimated
Amount (Rs)
1 Laying, B.G.straight or curve P.Way following rail
section (single rail) and concrete sleeper1660 nos
(M+8) density with standard fittings ensuring
correct spacing of sleepers, fixing & tightening of
Fish bolts & nuts and maintaining proper guage,
alignment, level (both cross & longitudinal),
expansion gap at rail joints, super elevation where
necessary and wih one initial through packing.
The rate should be inclusive of dekinking of rails
as required, cutting of rails as required on
straight and curve track for squaring of joints,
drilling holes on web of rail square to rail surface
by using proper template for fish plated joints,
champhering of drilled holes, greasing and oiling
of fish plates & fish bolts and nuts and at fishing
zone of the rail ends including supply of grease oil
etc. Sleeper spacing, versine, superelevation etc
shall also be marked by the contrctor wih white
paint at his own cost. The work has to be carried
out as laid down in IRPWM and as per direction of
the Engineer-in-Charge at site. The unit of track
metre consists both sides rails, sleepers and all
other fittings required thereof :
With 60 Kg. rails .
Tr.m 21250.00 434.50 9233125.00
2 Through packing of any kind of sleepers with
stone ballast to maintain correct alignment cross
and longitudinal level as required for maintaining
track gauge, versine, superelevation etc. on both
straight and curve track laid with contractor's
tools and labour inclusive of all charges as per
IRPWM and as directed by Engineer-in-charge.
i) First through packing of track (M+8) Density of
sleepers
Tr.m 21250.00 67.51 1434587.50
ii) 2nd through packing of track (M+8) Density of
sleepers
Tr.m 21250.00 56.25 1195312.50
iii) 3rd through packing of track (M+8) Density of
sleepers
Tr.m 21250.00 56.25 1195312.50
iv) 4th through packing of track (M+8) Density of
sleepers
Tr.m 21250.00 56.25 1195312.50
Page 19 of 26 Signature of the tenderer
under seal of the firm
Sl
No.
Description of Item Unit Qty Estimated
Rate (Rs)
Estimated
Amount (Rs)
3 Supply and delivery of locally available machine
Crushed ballast of 50 mm size clean angular, hard
and durable track Ballast as per Specification and
stacking the same on the cess of formation or toe
of the bank or at suitable place as directed by
Engineer-in-charge at site. The rate include all
cost of lead, lift, royalty, sales tax & other tax and
duties and all other incidential charges complete
as applicable. Tools, plants and screens of
approved mesh & dimensions required for
inspection and passing at the time of
measurement are to be arranged by the
contractor. The rate also includes levelling of
ground, if necessary, where the ballast are to be
stacked. Note: 90% payment shall be released on
the net quantity accepted and balance 10% shall
be released after spreading.
cum 53150 2,100.00 111615000.00
4 Handling, lifting and leading of ballast from stacks
with lead of 100m, which have been duly
measured and spreading ballast on formation,
Track & turnouts to ensure uniform and compact
ballast cushion under the sleepers desired ballast
profile. Spreading of ballast should be as per
specified line and level and maintaining approved
profile as provided in the technical specifications.
Spreading of ballast on formation will be done
only after supply is completed for a particular
stretch as decided by Engineer in charge and
ballast stacks have been released for spreading.
cum 53150 173.66 9230029.00
5 For every additional lead of ballast for 50 m or
part thereof beyond initial lead lead of 100m.
cum 10630 49.62 527460.60
6 Trolleying new rails, PSC sleepers from the
Client/RITES Site store to the site of work by
contractors transport/diplorry upto a distance of
1 km including handling, loading, unloading of
materials with all lead, lift, crossing road/ rly.
tracks etc complete.
MT 15500 613.77 9513435.00
7 Trolleying new rails, PSC sleepers for every addl.
½ km by contractors transport/diplorry
MT 7750 83.39 646272.50
Page 20 of 26 Signature of the tenderer
under seal of the firm
Sl
No.
Description of Item Unit Qty Estimated
Rate (Rs)
Estimated
Amount (Rs)
8 Flash butt welding of 52/60 kg(90UTS/72 UTS)
IRS-T-12-96 880 grade new rail joints in yard or
track as directed by the engineer in charge at site
with contractors mobile flash butt welding
plant,freight ,consumeables, labour and all
ancilary works as per the manual for flash butt
welding of rail 2012 (with latest correction slip)
including ultrasonic testing of welded joints using
contractors USFD testing machine.The rate
includes supply of skilled /artisan staff like
welder,moulder,chipper,lutter,aligner,striker/ham
mar man and adequate numbers of semiskilled,
unskilled labours and supplying fuel etc as
required for the work
Each
joint
2530 7,000.00 17710000.00
9 Drilling holes 28mm/32mm dia. (as directed by
Engineer at site) in rails (New/SH) for fish bolts
inside/outside track.
i) 52 kg/90 R (New/SH) rails section each 50 95.63 4781.50
ii) 60 kg(New/SH) rails section each 50 101.25 5062.50
10 Cutting rails (New/SH) rails section inside/outside
track.
i) 52 kg/90 R (New/SH) rails section each 100 114.76 11476.00
ii)60 kg(New/SH) rails section each 100 121.50 12150.00
11 Manufacturing and fixing of check rails for L-xing
as per RDSO drg. no. T-4215 by Machine cut of
52 /60kg rails of required size . Drilling holes on
web by drilling machine as per requirement.
Fixing the check rail to inner side of both the
running rails of L-Xing with the help of C.I. Bracket
bolts and nuts and plate screw at an intervals as
directed by engineer-in-charge maintaining
proper check rail clearance and fixing them on
each concrete sleeper. (Rails will be provided by
RITES/employer free of cost).
metre 500 1194.49 597245.00
12 Fabrication, manufacturing and supply of glued
insulated joint of following rail section as per
RDSO drg no. provided with 2 nos. X 3.25 m long
rail and joining by 1 m long fish plates & upto
date atl. & conforming to IRS specification
including cost of all supplied materials required
thereof i.e. the cost of rails, fish plates, fish bolts
& nuts complete in all respect.
i) With 60 kg/m (UIC) 1st quality rails to RDSO Drg.
No. T-5843 (G3L type) (Without supply of rails)
each 200 21475.86 4295172.00
Page 21 of 26 Signature of the tenderer
under seal of the firm
Sl
No.
Description of Item Unit Qty Estimated
Rate (Rs)
Estimated
Amount (Rs)
13 Assembling, linking and laying in position
B.G.Standard 60 kg/52 kg turn-outs on P.S.C.
sleepers including approach & exit PSC sleeper
portion to correct alignment & gauge.This
includes switches lead rails, stock rails both
straight and curve, crossing with 60 kg/52 kg rails
and standard fittings ensuring correct spacing of
sleepers fixing & tightening of Fish bolts & nuts
and maintaining proper guage, expansion gap at
rail joints and with one initial through packing.
The rate should be inclusive of dekinking of rails
as required, bending stock rails, cutting of rails to
required standard size and drilling holes on web
of rails square to rail surface by using proper
template (for fixing fishplates, distance block,
stretcher bars), greasing and oiling of fish plates &
fish bolts and nuts and at fishing zone of the rail
ends including supply of grease, oil etc. complete
in all respects. The rate should also be inclusive of
carrying rails, sleepers, switches, crossings,
fittings & fastenings with all lead, lift, ascent,
descent crossing Road/Rly line if necessary from
Client/RITES Store Depot to Site of work within a
distance of 1 km. Sleeper spacing shall also be
marked by the contractor with white/yellow paint
at his own cost. The work has to be carried out as
laid down in IRPWM and as per direction of the
Engineer-in-Charge at site.
ii) 1 in 12 Turnout Set 14.00 102647.08 1437059.12
i) 1 in 8½ Turnout/Sym. split Set 31.00 76985.31 2386544.61
iii) 1 in 8½ Derailing switch Set 4.00 27372.55 109490.20
14 Through packing of 1 in 12 Turn-out on any kind
of sleepers with stone ballast to maintain correct
alignment cross and longitudinal level as required
for maintaining track gauge, versine,
superelevation etc. on both straight and curve
track laid with contractor's tools and labour
inclusive of all charges as per IRPWM and as
directed by Engineer-in-charge.
i) First Through packing set 14 9896.1 138545.40
ii) 2nd Through packing set 14 8913.19 124784.66
iii) 3rd Through packing set 14 7930.29 111024.06
iv) 4th Through packing set 14 7930.29 111024.06
Page 22 of 26 Signature of the tenderer
under seal of the firm
Sl
No.
Description of Item Unit Qty Estimated
Rate (Rs)
Estimated
Amount (Rs)
15 Through packing of 1 in 8½ Turn-out/Sym. split on
any kind of sleepers with stone ballast to maintain
correct alignment cross and longitudinal level as
required for maintaining track gauge, versine,
superelevation etc. on both straight and curve
track laid with contractor's tools and labour
inclusive of all charges as per IRPWM and as
directed by Engineer-in-charge. (Note: Length of
turnout will be considered from stock rail joint to
the rail joint after 4th exit sleeper)
i) First Through packing set 31 7275.02 225525.62
ii) 2nd Through packing set 31 6292.11 195055.41
iii) 3rd Through packing set 31 5964.48 184898.88
iv) 4th Through packing set 31 5964.48 184898.88
16 Through packing of 1 in 8½ Derailing switch on
any kind of sleepers with stone ballast to maintain
correct alignment cross and longitudinal level as
required for maintaining track gauge, versine,
superelevation etc. on both straight and curve
track laid with contractor's tools and labour
inclusive of all charges as per IRPWM and as
directed by Engineer-in-charge.
i) First Through packing set 4 2425.01 9700.04
ii) 2nd Through packing set 4 2097.37 8389.48
iii) 3rd Through packing set 4 1988.16 7952.64
iv) 4th Through packing set 4 1988.16 7952.64
17 Supply & Fixing Hand lever box including pull over
rod with switches for operation of points.
each
set
49.00 10101.66 494981.34
18 Making and fixing in position cement concrete (1:
2:4) fouling mark as per enclosed drawing with
proper painting and lettering as per directives of
Engineer-in-charge of the work.The rate is
inclusive of all materials like cement ,stone
aggregate,sand,and paints etc with all incidental
works required for fixing in position complete in
all respect.
each 45.00 2614.13 117635.85
Page 23 of 26 Signature of the tenderer
under seal of the firm
Sl
No.
Description of Item Unit Qty Estimated
Rate (Rs)
Estimated
Amount (Rs)
19 Making and fixing in position cement concrete
(1:2:4) Kilometer/curve/gradient pillar as per
enclosed drawing with proper painting and
lettering as per directives of Engineer-in-
charge of the work.The rate is inclusive of all
materials like cement ,stone
aggregate,sand,and paints etc,earth work in
excavation and all incidental works required
for fixing in position complete in all respects.
each 50.00 3013.95 150697.50
20 Construction of RCC buffer as per RITES'
drawing including supply of
reinforcement,cement,buffer,wooden
sleepers(2.75mx0.30mx0.20m) bolts and
nuts,washersand all other materials.The rate
should also include painting of buffers wooden
sleepers with approved quality red paints.The
rate should also inclusive of digging of
eoundation trenches ,shuttering and form of
finishing with all leads,lift,
ascent,decent etc complete.
each 2.00 258716.13 517432.26
Sub total of schedule-1 174945326.75
Add 1% labour wellfare cess 1749453.27
Total amount of schedule-1 176694780.02
Say Rs 176694780.00
Schedule -2 (Supply of PSC Sleepers)
Sl
No. Description of Item Unit
Qty Estimated
Rate (Rs)
Estimated
Amount (Rs)
1 Supply ofMonoblock prestressed concrete
sleepers to suit B. G.60Kg for straight track
vide RDSO Drg. No. T-2496/T-39(with latest
alteration if any)
Each 38346 3,004.41 115207105.86
2 Supply of Monoblock prestressed concrete
sleepers for curve with RDSO Drg No. T-4186
Each 697 3,081.61 2147884.23
3 Supply of BG prestressed cocrete Sleepers
(category I) for 1 IN 12 Turn out including
approach and exit sleepers as per Turnout
assembly RDSO drg. No. T-4218 with upto date
alt. and confirming to IRS specifications.
set 14 5,80,866.80 8132135.20
Page 24 of 26 Signature of the tenderer
under seal of the firm
Sl
No.
Description of Item Unit Qty Estimated
Rate (Rs)
Estimated
Amount (Rs)
4 Supply of BG PSC Sleepers (category I) for 1 in 8.5
Turn out including approach and exit sleepers as
per Turnout assembly RDSO drg. No. T-4865 with
upto date alt. and confirming to IRS specifications.
set 31 3,70,978.20 11500324.20
5 Supply of BG prestressed cocrete Sleepers
(category I) for 1 in 8.5 derailing switch including
approach and exit sleepers as per Turnout
assembly RDSO drg. No. T-6068 with upto date
alt. and confirming to IRS specifications.
set 4 1,68,404.33 673617.32
Sub total of schedule-2 137661066.81
Add 1% labour
wellfare cess
1376610.67
Total amount of
schedule-2
139037677.47
Say Rs 139037677.00
Schedule -3 (Supply of P-Way Fittings)
Sl
No.
Description of Item Unit Qty Estimated
Rate (Rs)
Estimated
Amount (Rs)
1 Supply of Elastic Rail Clip RDSO Drg. No.T-3701
protected by anticorrosive paint)
Each 156173 87.71 13698699.08
2 Supply of Elastic Rail Clip 'J-clip'confirming to
RDSOT-4158
Each 2278 89.26 203338.61
3 Supply of Grooved Rubber sole plates for 60 Kg
layouts RDSO Drg. No.T-3711
Each 78086 30.79 2403900.94
4 Supply of 60 Kg Metal Liner RDSO Drg. No.T-3740 Each 47789 27.69 1323339.54
5 Supply of End cut Metal Liner 60Kg RDSO Drg. No.
T-3740
Each 3880 27.69 107442.24
6 Supply of GFN liner 60 kg RDSO Drg No.T-3706
(upto date alt.) confirming to IRS specification for
use of mark III flat toe ERC (Drg. No. T-3701)
Each 10400 21.55 224094.00
7 Supply of End cut GFN RDSO drg. No. T-3706 Each 3492 21.55 75243.87
Page 25 of 26 Signature of the tenderer
under seal of the firm
Sl
No.
Description of Item Unit Qty Estimated
Rate (Rs)
Estimated
Amount (Rs)
8 Supply of Fish Bolts and nuts(25x140) RDSO Drg.
No. T-1899 Alt2
Each 5741 96.96 556668.89
9 Supply of Combination fish plate 60x52kg RDSO
DRG. No.-T-696,T-697,T-698 & T-699 confirming
IRS -T-6
Set 25 13,987.62 349690.51
10 Supply of Fish Bolts and nuts(25x140) &
(25x190)RDSO Drg. No. T-1899 Alt2 & T-11514,IRS
T-23
Each
set
250 214.96 53740.00
11 Supply of 60 Kg juggle fish plate RDSO Drg. No. T-
4016 with clamps Drg. No. T-4017 &4017/1
including one bolt Drg. No. T-11524, One set
comprises og two fish plate and four clamps of
each type and 4 bolts
Set 100 8,155.60 815559.62
12 Supply of 60 Kg Fish plate 610mm long Drg no T-
1898 & IRS Specification (Note: 1 Pair=2 nos.
fishpaltes)
Pair 1359 2,985.26 4056964.20
13 Supply of Fittings for check rail
i) C.I Bracket RDSO Drg. No. T-4917, Conforming
to IS 210-1962 Grade (20) & IRS -T-10
Each 700 609.37 426562.05
ii) Distance Bracket RDSO Drg. No. T-4785,
Conforming to IS 210-1962 Grade (20) & IRS -T-10
Each 700 83.10 58167.20
iii) Bolts & nuts (22mmx110mm) including single
coil spring washer Drg. No. T-11550 IRS T-10
Each 700 81.56 57092.04
iv) Plate screw RDSO Drg no. T-3913 conforming
to IRS T-16
Each 1400 64.63 90484.03
v) M.S. Packing plate Drg. No. T-4320 with upto
date alt conforming IRS -T -10
Each 700 169.27 118492.47
14 Supply of Switch clamp(Male& Female)RDSO drg
no. T-858 to 858/1
Set 20 4,494.00 89880.00
Sub total of schedule-3 24709359.26
Add 1% labour welfare cess 247093.59
Total amount of schedule-3 24956452.85
Say Rs 24956453.00
Page 26 of 26 Signature of the tenderer
under seal of the firm
Schedule -4 (Supply of Point & Crossing)
Sl
No.
Description of Item Unit Qty Estimated
Rate (Rs)
Estimated
Amount (Rs)
1 B.G. 1 in 12 Points & Xings with 60 kg (IRS-T-
12) 90 UTS 1st quality rails on PSC sleeper
layout as per RDSO Drg. No. T-4218, T-4219
& T-4220 with CMS Crossings, all fittings &
fastenings, 2 pair of 1m long fish plates,
bolts & nuts, Lead rails, standard fish
plates(610mm long) and fish bolts & nuts
complete but exclusive of PSC sleepers.
Set 14 13,71,242.18 19197390.52
2 B.G. 1 in 8.1/2 Points & Xings with 60 kg (IRS-
T-12) 90 UTS 1st quality rails on PSC sleeper
layout as per RDSO Drg. No. T-4865, T-4866
& T-4867 with CMS Crossings, all fittings &
fastenings, 2 pair of 1m long fish plates,
bolts & nuts, Lead rails, standard fish
plates(610mm long) and fish bolts & nuts
complete but exclusive of PSC sleepers.
Set 31 9,90,780.90 30714207.90
3 B.G. 1 in 8.1/2 Derailing switch with 60 kg
(IRS-T-12) 90 UTS 1st quality rails on PSC
sleeper layout as per RDSO Drg. No. T-6068,
with all fittings & fastenings, bolts & nuts,
Lead rails, standard fish plates(610mm long)
and fish bolts & nuts complete but exclusive
of PSC sleepers
Set 4 316724.27 1266897.08
Sub total of schedule-4 51178495.50
Add 1% labour welfare cess 511784.96
Total of Schedule - 4 51690280.46
Say Rs. 51690280.00
Total of Part -B ( Sch.1+ Sch. 2+ Sch 3+Sch 4) = Rs. 392379190.00
Total of Part -A & Part-B = Rs. 1070527330.00