SOW_ZTE WiFi Project
1
01.PROJECT SCOPE
1.1The solution shall deliver necessary and sufficient hardware, software, and professional services
for the complete solution implementation integrating with the existing network within the agreedproject period
1.2The solution shall accommodate the existing network capacity & architectural requirements while
ensuring required redundancy.
1.3The solution shall deliver necessary long term support and maintenance for the implemented
solution.
1.4The solution shall be extensible on to the commercial Wi-Fi network so that the customers enjoys
a better coverage both domestic and commercial areas.
1.5Supplier shall implement the solution in turnkey basis.
1.6Supplier shall implement the finalized proposal as contracted for the proposed project
deliverables.
1.7
The Supplier shall study the existing service delivery architecture and design the proposal
accordingly, which may cover under professional services of the project.
1.8Supplier shall implement the entire solution while seamlessly integrating and interworking with
existing network elements without disturbing the prevailing services.
1.9
Supplier shall provide necessary and sufficient test equipment and any other resources required
for carrying out test procedures successfully at own cost without any additional cost to ZTEl.
1.10
The solution shall be plan and design in such a way that it shall not introduce any changes to
the exiting service architectures
1.11 All the equipment shall be installed in Indoor environment.
1.12 Following category of Implementation models are willing to serve from the Wi-Fi.
Category A:Small size (Single AP) Installation
Category B:Medium size (2-16 APs) Installation
Category C:Large size (17 above Aps) Installation
Category D:IBS size (1-10 above Aps) Installation
7/26/2019 Sow Zte Wifi Project v1.1
2/8
SOW_ZTE WiFi Project
2
1.12.1 Category A:Small size Installation
Single Access Point (AP) installation scenario is categorized as Small size Installation and it shall
consists with relevant power arrangement, Installation & testing with material transportation
including all required materials supply except of Wi-Fi routers, Switches, Diplexers & Access Point
(AP)s. All required Wi-Fi routers, Switches, Diplexers & Access Point (AP)s will be given by ZTE and
the product brand will be Cisco.
Item Description UnitDefined
QtysRemark
Transportation & Mobilization
from warehouse to siteSite
1 AccessPoint
Bidder shall collect the equipment from
warehouse. Customer will present for the
acceptance after installation, Commissioning and
integration of the equipment. After got the
acceptance from the customer bidder shall
submit an as built drawing for each and every
site.
Installation PcsCommissioning & Integration Pcs
Service check & Acceptance Pcs
Supply & Installation of 13A
Plug basePcs 2
Bidder shall supply and install relevant 13A plug
base with sunk box in accepted brand (All
accepted product details are attached). If the
Access Point (AP)s / Router power cord length is
not enough, shall be extended by 1.5mm2 two
core power cable. All the power cables shall be
separated with data cables and properly covered
with PVC conduit, casing & flexible.
Installation of CAT5/CAT6
cablem 20
Data cables shall be laid securely. Shall be laid
through PVC conduit/casing, PVC flexible. All the
covering materials shall be fixed properly with
self-tapping screws.
1.12.2 Category B:Medium size Installation
Access Point (AP) installation is not limited to one number and not exceeding Sixteen numbers, such
scenario is categorized as Medium size Installation and it shall consists with relevant power
arrangement, Installation & testing with material transportation including all required materials
supply except of Wi-Fi routers, Switches, Diplexers & Access Point (AP)s. All required Wi-Fi routers,
Switches, Diplexers & Access Point (AP)s will be given by ZTE and the product brand will be Cisco.
Bidder shall perform the Technical site survey (Referred as TSS hereafter ) and shall be submitted
the Technical Site Survey Report (Referred as TSSR hereafter) with relevant drawings and designs.
7/26/2019 Sow Zte Wifi Project v1.1
3/8
SOW_ZTE WiFi Project
3
Item Description UnitDefined
QtysRemark
Transportation & Mobilization
from warehouse to siteSite
3 Access
Points
Bidder should collect the equipment from
warehouse. Customer will present for the
acceptance after installation, Commissioning and
integration of the equipment. After got theacceptance from the customer bidder should
submit an as built drawing for each and every
site.
Installation Pcs
Commissioning & Integration Pcs
Service check & Acceptance Pcs
Supply & Installation of 13A
Plug basePcs 4
Bidder should supply and install relevant 13A
plug base with sunk box in accepted brand (All
accepted product details are attached). If the
Access Point (AP)s / Router power cord length is
not enough, should be extended by 1.5mm2two
core power cable. All the power cables should be
separated with data cables and properly covered
with PVC conduit, casing & flexible.
Installation of CAT5/CAT6
cablem 150
Data cables should be laid securely. Should be
laid through PVC conduit/casing, PVC flexible. All
the covering materials should be fixed properly
with self-tapping screws.
1.12.3 Category C:Large size Installation
Access Point (AP) installation is not limited to sixteen number and exceeding the quantity, such
scenario is categorized as Large size Installation and it shall consists with relevant power
arrangement, Installation & testing with material transportation including all required materials
supply except of Wi-Fi routers, Switches, Diplexers & Access Point (AP)s. All required Wi-Fi routers,
Switches, Diplexers & Access Point (AP)s will be given by ZTE and the product brand will be Cisco.
Bidder shall perform the TSS and shall be submitted the TSSR with relevant drawings and designs.
Item Description UnitDefined
QtysRemark
Transportation & Mobilization
from warehouse to site
Site
30
Access
Points
Bidder should collect the equipment from
warehouse. Customer will present for the
acceptance after installation, Commissioning and
integration of the equipment. After got the
acceptance from the customer bidder should
submit an as built drawing for each and every
site.
Installation Pcs
Commissioning & Integration Pcs
Service check & Acceptance Pcs
Supply & Installation of 13A
Plug basePcs 34
Bidder should supply and install relevant 13A
plug base with sunk box in accepted brand (All
accepted product details are attached). If the
Access Point (AP)s / Router power cord length is
not enough, should be extended by 1.5mm2two
core power cable. All the power cables should be
separated with data cables and properly covered
with PVC conduit, casing & flexible.
7/26/2019 Sow Zte Wifi Project v1.1
4/8
SOW_ZTE WiFi Project
4
Installation of CAT5/CAT6
cablem 1500
Data cables should be laid securely. Should be
laid through PVC conduit/casing, PVC flexible. All
the covering materials should be fixed properly
with self-tapping screws.
Installation of Optical Fibers m 200
Data cables should be laid securely. Should be
laid through PVC conduit/casing, PVC flexible. Allthe covering materials should be fixed properly
with self-tapping screws.
1.12.4 Category D:IBS size Installation
Access Point (AP) installation is in IBS sites , such scenario is categorized as IBS size Installation and
it shall consists with relevant power arrangement, Installation & testing with material transportationincluding all required materials supply except of Wi-Fi routers, Switches, Diplexers & Access Point
(AP)s. All required Wi-Fi routers, Switches, Diplexers & Access Point (AP)s will be given by ZTE and
the product brand will be Cisco. Bidder shall perform the TSS and shall be submitted the TSSR with
relevant drawings and designs.
Item Description UnitDefined
QtysRemark
Transportation & Mobilization
from warehouse to site Site10
Access
Points
Bidder should collect the equipment from
warehouse. Customer will present for theacceptance after installation, Commissioning and
integration of the equipment. After got the
acceptance from the customer bidder should
submit an as built drawing for each and every
site.
Installation Pcs
Commissioning & Integration Pcs
Service check & Acceptance Pcs
Supply & Installation of 13A
Plug basePcs 12
Bidder should supply and install relevant 13A
plug base with sunk box in accepted brand (All
accepted product details are attached). If the
Access Point (AP)s / Router power cord length is
not enough, should be extended by 1.5mm2two
core power cable. All the power cables should beseparated with data cables and properly covered
with PVC conduit, casing & flexible.
Installation of CAT5/CAT6
cablem 500
Data cables should be laid securely. Should be
laid through PVC conduit/casing, PVC flexible. All
the covering materials should be fixed properly
with self-tapping screws.
Installation of Optical Fibers m 150
Data cables should be laid securely. Should be
laid through PVC conduit/casing, PVC flexible. All
the covering materials should be fixed properly
with self-tapping screws.
7/26/2019 Sow Zte Wifi Project v1.1
5/8
SOW_ZTE WiFi Project
5
02.
ACCEPTED MATERIALS AND BRANDS
No Material Brand
1 13A Plug base (Square type) with Sunk box Orange/Clipsal
2 1.5 mm2Power cable (3 core) Kelani/ACL
3 2.5 mm2Power cable (3 Core) Kelani/ACL
4 CAT5/CAT6 cable 3M
5 PVC Pipe S-Lon/Anton
6 PVC Casing S-Lon/Anton
7 PVC Flexible S-Lon/Anton
8 Self-Tapping Screw NA
9 Roll Plugs NA
10 Cantilever Shelf 19"X2UX400mm Easy Link
11 Cantilever Shelf 19"X5UX400mm Easy Link
12 Cantilever Shelf 19"X12UX400mm Easy Link
13 1.5 mm2Power cable (2 core) Kelani/ACL
14 Bonding Tape 3M
15 Insulation Tape 3M
16 Metal cover Amano
03.
COVERING AND SEALING
3.1
All the cable paths, both power and data should be properly covered and
sealed with PVC (Water Pipes) and PVC fittings.
3.2PVC flexible shall be used for the bends and other relevant places to lay
the cables.
3.3Bonding tapes and insulation tapes (3M Type) shall be used to cover all
the joints and connectors.
3.4Bidder shall cover the cable path and keep them on the ceiling or inside
the ducts and should not be visible to consumers.
3.5All the cable paths should be tight properly with self-tapping screws and
should be rigidly fixed.
3.6Any special situation bidder shall supply and install GI pipes and GI
flexible to cover the Optical fiber cables (Only if cable lay in outdoor
premises) and can be claimed under AWR category.
3.7Any special situation if the customer requested to cover the cable path
lay along the outdoor walls should supply and install Amano ducts and
can be claimed under AWR category.
7/26/2019 Sow Zte Wifi Project v1.1
6/8
SOW_ZTE WiFi Project
6
04.
EARTHING
4.1
Bidder shall earth the installed router or switch to the nearest ECB by
using 25mm2copper green cable.
4.2Bidder shall earth the laid GI pipes to the common earth ring (Only if
available) by using 25mm2copper green cable.
4.3
Bidder shall properly interconnect GI pipes with 25mm2 copper yellow
green cable.
4.4
Customer will arrange to complete the earthing of outdoor GI pipes
(Only if not available a common earthing system) and it shall be
completed together with the Wi-Fi site installation without any interrupt
to the site implementation, integration and commission.
05.POWER SUPPLY TO SWITH, ROUTER OR ACCESS POINT
5.1
Bidder shall supply and install 13A square type plug base with sunk box
to get the AC power for installed switches, routers or installed access
points.
5.2 If the Access Point (AP)s / Router power cord length is not enough,
bidder shall extend the power cable of the equipment by 1.5mm2 two
core power cable.
5.3All the power cables should be separated with data cables and properly
covered with PVC conduit, casing & flexible and shall be fixed rigidly.
06.
SERVICE TEST PROCEDURE
6.1Bidder shall complete the walk test after commission the Wi-Fi network
and shall be submitted a document to the customer
6.2Bidder shall be able to test and confirm the working condition of all
installed equipment and mentioned coverage in the approved design
drawing in the TSSR.
6.3Bidder shall be able to test and identify any coverage issue and submit a
report to customer.
6.4
Bidder shall be able to enhance the coverage area of the Wi-Fi network
with new design in addition to first installation and that shall be claimed
7/26/2019 Sow Zte Wifi Project v1.1
7/8
SOW_ZTE WiFi Project
7
under AWR. The design document shall be given by the customer.
07.ACCEPTANCE TEST PROCEDURE
7.1
Bidder shall be completed the Pre-PAT once installation completed and
after the Pre-PAT bidder shall be able to integrate and commission the
Wi-Fi network.
7.2Customer shall be presented for the acceptance test once after
commissioned the Wi-Fi network and it will be followed the accepted
document format attached in Annex 01.
7.3Once customer confirmed the Acceptance document, bidder should
submit the As Built Drawing (Referred as ABD hereafter) and it will befollowed the document format attached in Annex 02.
08.TERMS AND CONDITIONS
8.1 Bidder can apply an additional work request for each and every
additional quantity of materials beyond the defined work package
8.2 AWR should be identified during the TSS and must get the prior approval
from the customer before attend to work
8.3 Bidder Shall be taken the confirmation for each and every AWR work
done from the Customer by the time of acceptance test
7/26/2019 Sow Zte Wifi Project v1.1
8/8
SOW_ZTE WiFi Project
8
09.LIST OF ADDITIONAL WORK REQUEST ITEMS
SN Line item Unit
1 Engineering technical site survey site
2 Telecom equipment installation design site
3Transportation & Mobilization from warehouse
to site (Colombo)Site
4Transportation & Mobilization from warehouse
to site (Other)Site
5Transportation & Mobilization from warehouse
to site (North & East)Site
6 Supply & Installation of Bonding tape Pcs
7 Supply & Installation of Insulation tapes Pcs
8 Supply & Installation of CAT 5/CAT 6 cable m
9Supply & Installation of PVC casing with fixing
materialsm
10Supply & Installation of PVC pipe with fixing
materialsm
11 Fiber cable laying through PVC conduits/Casing m
12Supply & installation of GI pipe with fixing
materialsm
13 Supply & installation of 25mm2
copper yellowgreen cable
m
14Supply & Installation of 1.5mm
2two core power
cablem
15 Supply & Installation of 1.2mm2power cable m
16 Supply & Installation of 2.5mm2power cable m
17Supply & Installation of Cantilever Shelf
19"X2UX400mmPcs
18Supply & Installation of Cantilever Shelf
19"X5UX400mmPcs
19 Supply & Installation of Cantilever Shelf19"X12UX400mm
Pcs
20 Supply & Installation of Amano ducts m
21 Supply and installation of ECB Pcs