    SOW_ZTE WiFi Project

    1

    01.PROJECT SCOPE

    1.1The solution shall deliver necessary and sufficient hardware, software, and professional services

    for the complete solution implementation integrating with the existing network within the agreedproject period

    1.2The solution shall accommodate the existing network capacity & architectural requirements while

    ensuring required redundancy.

    1.3The solution shall deliver necessary long term support and maintenance for the implemented

    solution.

    1.4The solution shall be extensible on to the commercial Wi-Fi network so that the customers enjoys

    a better coverage both domestic and commercial areas.

    1.5Supplier shall implement the solution in turnkey basis.

    1.6Supplier shall implement the finalized proposal as contracted for the proposed project

    deliverables.

    1.7

    The Supplier shall study the existing service delivery architecture and design the proposal

    accordingly, which may cover under professional services of the project.

    1.8Supplier shall implement the entire solution while seamlessly integrating and interworking with

    existing network elements without disturbing the prevailing services.

    1.9

    Supplier shall provide necessary and sufficient test equipment and any other resources required

    for carrying out test procedures successfully at own cost without any additional cost to ZTEl.

    1.10

    The solution shall be plan and design in such a way that it shall not introduce any changes to

    the exiting service architectures

    1.11 All the equipment shall be installed in Indoor environment.

    1.12 Following category of Implementation models are willing to serve from the Wi-Fi.

    Category A:Small size (Single AP) Installation

    Category B:Medium size (2-16 APs) Installation

    Category C:Large size (17 above Aps) Installation

    Category D:IBS size (1-10 above Aps) Installation

  • 7/26/2019 Sow Zte Wifi Project v1.1

    2/8

    SOW_ZTE WiFi Project

    2

    1.12.1 Category A:Small size Installation

    Single Access Point (AP) installation scenario is categorized as Small size Installation and it shall

    consists with relevant power arrangement, Installation & testing with material transportation

    including all required materials supply except of Wi-Fi routers, Switches, Diplexers & Access Point

    (AP)s. All required Wi-Fi routers, Switches, Diplexers & Access Point (AP)s will be given by ZTE and

    the product brand will be Cisco.

    Item Description UnitDefined

    QtysRemark

    Transportation & Mobilization

    from warehouse to siteSite

    1 AccessPoint

    Bidder shall collect the equipment from

    warehouse. Customer will present for the

    acceptance after installation, Commissioning and

    integration of the equipment. After got the

    acceptance from the customer bidder shall

    submit an as built drawing for each and every

    site.

    Installation PcsCommissioning & Integration Pcs

    Service check & Acceptance Pcs

    Supply & Installation of 13A

    Plug basePcs 2

    Bidder shall supply and install relevant 13A plug

    base with sunk box in accepted brand (All

    accepted product details are attached). If the

    Access Point (AP)s / Router power cord length is

    not enough, shall be extended by 1.5mm2 two

    core power cable. All the power cables shall be

    separated with data cables and properly covered

    with PVC conduit, casing & flexible.

    Installation of CAT5/CAT6

    cablem 20

    Data cables shall be laid securely. Shall be laid

    through PVC conduit/casing, PVC flexible. All the

    covering materials shall be fixed properly with

    self-tapping screws.

    1.12.2 Category B:Medium size Installation

    Access Point (AP) installation is not limited to one number and not exceeding Sixteen numbers, such

    scenario is categorized as Medium size Installation and it shall consists with relevant power

    arrangement, Installation & testing with material transportation including all required materials

    supply except of Wi-Fi routers, Switches, Diplexers & Access Point (AP)s. All required Wi-Fi routers,

    Switches, Diplexers & Access Point (AP)s will be given by ZTE and the product brand will be Cisco.

    Bidder shall perform the Technical site survey (Referred as TSS hereafter ) and shall be submitted

    the Technical Site Survey Report (Referred as TSSR hereafter) with relevant drawings and designs.

  • 7/26/2019 Sow Zte Wifi Project v1.1

    3/8

    SOW_ZTE WiFi Project

    3

    Item Description UnitDefined

    QtysRemark

    Transportation & Mobilization

    from warehouse to siteSite

    3 Access

    Points

    Bidder should collect the equipment from

    warehouse. Customer will present for the

    acceptance after installation, Commissioning and

    integration of the equipment. After got theacceptance from the customer bidder should

    submit an as built drawing for each and every

    site.

    Installation Pcs

    Commissioning & Integration Pcs

    Service check & Acceptance Pcs

    Supply & Installation of 13A

    Plug basePcs 4

    Bidder should supply and install relevant 13A

    plug base with sunk box in accepted brand (All

    accepted product details are attached). If the

    Access Point (AP)s / Router power cord length is

    not enough, should be extended by 1.5mm2two

    core power cable. All the power cables should be

    separated with data cables and properly covered

    with PVC conduit, casing & flexible.

    Installation of CAT5/CAT6

    cablem 150

    Data cables should be laid securely. Should be

    laid through PVC conduit/casing, PVC flexible. All

    the covering materials should be fixed properly

    with self-tapping screws.

    1.12.3 Category C:Large size Installation

    Access Point (AP) installation is not limited to sixteen number and exceeding the quantity, such

    scenario is categorized as Large size Installation and it shall consists with relevant power

    arrangement, Installation & testing with material transportation including all required materials

    supply except of Wi-Fi routers, Switches, Diplexers & Access Point (AP)s. All required Wi-Fi routers,

    Switches, Diplexers & Access Point (AP)s will be given by ZTE and the product brand will be Cisco.

    Bidder shall perform the TSS and shall be submitted the TSSR with relevant drawings and designs.

    Item Description UnitDefined

    QtysRemark

    Transportation & Mobilization

    from warehouse to site

    Site

    30

    Access

    Points

    Bidder should collect the equipment from

    warehouse. Customer will present for the

    acceptance after installation, Commissioning and

    integration of the equipment. After got the

    acceptance from the customer bidder should

    submit an as built drawing for each and every

    site.

    Installation Pcs

    Commissioning & Integration Pcs

    Service check & Acceptance Pcs

    Supply & Installation of 13A

    Plug basePcs 34

    Bidder should supply and install relevant 13A

    plug base with sunk box in accepted brand (All

    accepted product details are attached). If the

    Access Point (AP)s / Router power cord length is

    not enough, should be extended by 1.5mm2two

    core power cable. All the power cables should be

    separated with data cables and properly covered

    with PVC conduit, casing & flexible.

  • 7/26/2019 Sow Zte Wifi Project v1.1

    4/8

    SOW_ZTE WiFi Project

    4

    Installation of CAT5/CAT6

    cablem 1500

    Data cables should be laid securely. Should be

    laid through PVC conduit/casing, PVC flexible. All

    the covering materials should be fixed properly

    with self-tapping screws.

    Installation of Optical Fibers m 200

    Data cables should be laid securely. Should be

    laid through PVC conduit/casing, PVC flexible. Allthe covering materials should be fixed properly

    with self-tapping screws.

    1.12.4 Category D:IBS size Installation

    Access Point (AP) installation is in IBS sites , such scenario is categorized as IBS size Installation and

    it shall consists with relevant power arrangement, Installation & testing with material transportationincluding all required materials supply except of Wi-Fi routers, Switches, Diplexers & Access Point

    (AP)s. All required Wi-Fi routers, Switches, Diplexers & Access Point (AP)s will be given by ZTE and

    the product brand will be Cisco. Bidder shall perform the TSS and shall be submitted the TSSR with

    relevant drawings and designs.

    Item Description UnitDefined

    QtysRemark

    Transportation & Mobilization

    from warehouse to site Site10

    Access

    Points

    Bidder should collect the equipment from

    warehouse. Customer will present for theacceptance after installation, Commissioning and

    integration of the equipment. After got the

    acceptance from the customer bidder should

    submit an as built drawing for each and every

    site.

    Installation Pcs

    Commissioning & Integration Pcs

    Service check & Acceptance Pcs

    Supply & Installation of 13A

    Plug basePcs 12

    Bidder should supply and install relevant 13A

    plug base with sunk box in accepted brand (All

    accepted product details are attached). If the

    Access Point (AP)s / Router power cord length is

    not enough, should be extended by 1.5mm2two

    core power cable. All the power cables should beseparated with data cables and properly covered

    with PVC conduit, casing & flexible.

    Installation of CAT5/CAT6

    cablem 500

    Data cables should be laid securely. Should be

    laid through PVC conduit/casing, PVC flexible. All

    the covering materials should be fixed properly

    with self-tapping screws.

    Installation of Optical Fibers m 150

    Data cables should be laid securely. Should be

    laid through PVC conduit/casing, PVC flexible. All

    the covering materials should be fixed properly

    with self-tapping screws.

  • 7/26/2019 Sow Zte Wifi Project v1.1

    5/8

    SOW_ZTE WiFi Project

    5

    02.

    ACCEPTED MATERIALS AND BRANDS

    No Material Brand

    1 13A Plug base (Square type) with Sunk box Orange/Clipsal

    2 1.5 mm2Power cable (3 core) Kelani/ACL

    3 2.5 mm2Power cable (3 Core) Kelani/ACL

    4 CAT5/CAT6 cable 3M

    5 PVC Pipe S-Lon/Anton

    6 PVC Casing S-Lon/Anton

    7 PVC Flexible S-Lon/Anton

    8 Self-Tapping Screw NA

    9 Roll Plugs NA

    10 Cantilever Shelf 19"X2UX400mm Easy Link

    11 Cantilever Shelf 19"X5UX400mm Easy Link

    12 Cantilever Shelf 19"X12UX400mm Easy Link

    13 1.5 mm2Power cable (2 core) Kelani/ACL

    14 Bonding Tape 3M

    15 Insulation Tape 3M

    16 Metal cover Amano

    03.

    COVERING AND SEALING

    3.1

    All the cable paths, both power and data should be properly covered and

    sealed with PVC (Water Pipes) and PVC fittings.

    3.2PVC flexible shall be used for the bends and other relevant places to lay

    the cables.

    3.3Bonding tapes and insulation tapes (3M Type) shall be used to cover all

    the joints and connectors.

    3.4Bidder shall cover the cable path and keep them on the ceiling or inside

    the ducts and should not be visible to consumers.

    3.5All the cable paths should be tight properly with self-tapping screws and

    should be rigidly fixed.

    3.6Any special situation bidder shall supply and install GI pipes and GI

    flexible to cover the Optical fiber cables (Only if cable lay in outdoor

    premises) and can be claimed under AWR category.

    3.7Any special situation if the customer requested to cover the cable path

    lay along the outdoor walls should supply and install Amano ducts and

    can be claimed under AWR category.

  • 7/26/2019 Sow Zte Wifi Project v1.1

    6/8

    SOW_ZTE WiFi Project

    6

    04.

    EARTHING

    4.1

    Bidder shall earth the installed router or switch to the nearest ECB by

    using 25mm2copper green cable.

    4.2Bidder shall earth the laid GI pipes to the common earth ring (Only if

    available) by using 25mm2copper green cable.

    4.3

    Bidder shall properly interconnect GI pipes with 25mm2 copper yellow

    green cable.

    4.4

    Customer will arrange to complete the earthing of outdoor GI pipes

    (Only if not available a common earthing system) and it shall be

    completed together with the Wi-Fi site installation without any interrupt

    to the site implementation, integration and commission.

    05.POWER SUPPLY TO SWITH, ROUTER OR ACCESS POINT

    5.1

    Bidder shall supply and install 13A square type plug base with sunk box

    to get the AC power for installed switches, routers or installed access

    points.

    5.2 If the Access Point (AP)s / Router power cord length is not enough,

    bidder shall extend the power cable of the equipment by 1.5mm2 two

    core power cable.

    5.3All the power cables should be separated with data cables and properly

    covered with PVC conduit, casing & flexible and shall be fixed rigidly.

    06.

    SERVICE TEST PROCEDURE

    6.1Bidder shall complete the walk test after commission the Wi-Fi network

    and shall be submitted a document to the customer

    6.2Bidder shall be able to test and confirm the working condition of all

    installed equipment and mentioned coverage in the approved design

    drawing in the TSSR.

    6.3Bidder shall be able to test and identify any coverage issue and submit a

    report to customer.

    6.4

    Bidder shall be able to enhance the coverage area of the Wi-Fi network

    with new design in addition to first installation and that shall be claimed

  • 7/26/2019 Sow Zte Wifi Project v1.1

    7/8

    SOW_ZTE WiFi Project

    7

    under AWR. The design document shall be given by the customer.

    07.ACCEPTANCE TEST PROCEDURE

    7.1

    Bidder shall be completed the Pre-PAT once installation completed and

    after the Pre-PAT bidder shall be able to integrate and commission the

    Wi-Fi network.

    7.2Customer shall be presented for the acceptance test once after

    commissioned the Wi-Fi network and it will be followed the accepted

    document format attached in Annex 01.

    7.3Once customer confirmed the Acceptance document, bidder should

    submit the As Built Drawing (Referred as ABD hereafter) and it will befollowed the document format attached in Annex 02.

    08.TERMS AND CONDITIONS

    8.1 Bidder can apply an additional work request for each and every

    additional quantity of materials beyond the defined work package

    8.2 AWR should be identified during the TSS and must get the prior approval

    from the customer before attend to work

    8.3 Bidder Shall be taken the confirmation for each and every AWR work

    done from the Customer by the time of acceptance test

  • 7/26/2019 Sow Zte Wifi Project v1.1

    8/8

    SOW_ZTE WiFi Project

    8

    09.LIST OF ADDITIONAL WORK REQUEST ITEMS

    SN Line item Unit

    1 Engineering technical site survey site

    2 Telecom equipment installation design site

    3Transportation & Mobilization from warehouse

    to site (Colombo)Site

    4Transportation & Mobilization from warehouse

    to site (Other)Site

    5Transportation & Mobilization from warehouse

    to site (North & East)Site

    6 Supply & Installation of Bonding tape Pcs

    7 Supply & Installation of Insulation tapes Pcs

    8 Supply & Installation of CAT 5/CAT 6 cable m

    9Supply & Installation of PVC casing with fixing

    materialsm

    10Supply & Installation of PVC pipe with fixing

    materialsm

    11 Fiber cable laying through PVC conduits/Casing m

    12Supply & installation of GI pipe with fixing

    materialsm

    13 Supply & installation of 25mm2

    copper yellowgreen cable

    m

    14Supply & Installation of 1.5mm

    2two core power

    cablem

    15 Supply & Installation of 1.2mm2power cable m

    16 Supply & Installation of 2.5mm2power cable m

    17Supply & Installation of Cantilever Shelf

    19"X2UX400mmPcs

    18Supply & Installation of Cantilever Shelf

    19"X5UX400mmPcs

    19 Supply & Installation of Cantilever Shelf19"X12UX400mm

    Pcs

    20 Supply & Installation of Amano ducts m

    21 Supply and installation of ECB Pcs