SPREMEMBE V NOVEM PRIROČNIKU ZA IZVAJANJE PROJEKTOV TMIS 2009 SANJA MILINOVIĆ 23. 10. 2009

SPREMEMBE V NOVEM PRIROČNIKU ZA IZVAJANJE PROJEKTOV TMIS 2009

  • Upload
    jaron

  • View
    56

  • Download
    0

Embed Size (px)

DESCRIPTION

SPREMEMBE V NOVEM PRIROČNIKU ZA IZVAJANJE PROJEKTOV TMIS 2009. SANJA MILINOVIĆ 23. 10. 2009. 1. TRETJA NAPOTITEV RTA – ČL. 2.2. NOVA GEOGRAFSKA PODROČJA NAPOTITVE: 12 DČ IZ PETE ŠIRITVE DRŽAVE KANDIDATKE DRŽAVE POTENCIALNE KANDIDATKE JUŽNA SREDOZEMSKA REGIJA NOVE NEODVISNE DRŽAVE. - PowerPoint PPT Presentation

Citation preview

Page 1: SPREMEMBE V NOVEM PRIROČNIKU ZA IZVAJANJE PROJEKTOV TMIS 2009

SPREMEMBE V NOVEM PRIROČNIKU ZA IZVAJANJE PROJEKTOV TMIS 2009

SANJA MILINOVIĆ23. 10. 2009

Page 2: SPREMEMBE V NOVEM PRIROČNIKU ZA IZVAJANJE PROJEKTOV TMIS 2009

1. TRETJA NAPOTITEV RTA – ČL. 2.2.

NOVA GEOGRAFSKA PODROČJA NAPOTITVE:

1. 12 DČ IZ PETE ŠIRITVE2. DRŽAVE KANDIDATKE3. DRŽAVE POTENCIALNE KANDIDATKE4. JUŽNA SREDOZEMSKA REGIJA5. NOVE NEODVISNE DRŽAVE

Page 3: SPREMEMBE V NOVEM PRIROČNIKU ZA IZVAJANJE PROJEKTOV TMIS 2009

2. POTRDITEV TWINNING POGODB ENPI – ČL. 3.9.2

• POTRDITEV TWINNING POGODB V PROJEKTIH FINANCIRANIH IZ ENPI DELEGIRANA MAROKU, TUNIZIJI, JORDANIJI, EGIPTU IN UKRAJINI

Page 4: SPREMEMBE V NOVEM PRIROČNIKU ZA IZVAJANJE PROJEKTOV TMIS 2009

3. NOVA TERMINOLOGIJA – ČL. 4.2 IN PRILOGA 2

• TRAJANJE PROJEKTA (“LEGAL DURATION”) DEFINIRANO KOT “EXECUTION PERIOD”, PREJ “IMPLEMENTATION PERIOD OF THE PROJECT”

• “IMPLEMENTATION PERIOD OF THE ACTION (WP)”, PREJ DURATION OF THE WP

• ŠE VEDNO PA VELJA, DA SE PROJEKT ZAKLJUČI 3 MESECE PO KONCU IZVAJANJA WP

Page 5: SPREMEMBE V NOVEM PRIROČNIKU ZA IZVAJANJE PROJEKTOV TMIS 2009

4. POTNI STROŠKI JAVNIH USLUŽBENCEV DRŽAV PREJEMNIC POMOČI

• ČL. 5.7.2: NOVOST ZA TWINNING PROJEKTE V OKVIRU IPA: DRŽAVA PREJEMNICA POMOČI JE DOLŽNA KRITI POTNE STROŠKE SVOJIH USLUŽBENCEV IZ PRESTOLNICE V DČ ALI MED DČ, TA VLOŽEK SE ŠTEJE KOT SOFINANCIRANJE

Page 6: SPREMEMBE V NOVEM PRIROČNIKU ZA IZVAJANJE PROJEKTOV TMIS 2009

5. DVIG ZGORNJE MEJE ZA DOBAVO STORITEV

• ČL. 7.6: Z OBSTOJEČIH 5.000 EUR NA 10.000 EUR PO PRORAČUNSKI POSTAVKI

Page 7: SPREMEMBE V NOVEM PRIROČNIKU ZA IZVAJANJE PROJEKTOV TMIS 2009

6. TWINNING REVIEW MISSIONS – ČL. 9.2.2

• NOV INSTITUT• 6 DO 12 MESECEV PO KONCU IZVAJANJA

TWINNING PROJEKTA• CILJI: OCENA TRAJNOSTI REZULTATOV,

“LESSONS LEARNED” IN ŠIRJENJE DOBRIH PRAKS

• MISIJA TRAJA NAJVEČ EN TEDEN (3-5 DEL.DNI)• FINANCIRANJE PREKO TAIEX

Page 8: SPREMEMBE V NOVEM PRIROČNIKU ZA IZVAJANJE PROJEKTOV TMIS 2009

6. TWINNING REVIEW MISSIONS

• TWINNING REVIEW EXPERT (TRE) – STROKOVNJAK DČ, KI NI BILA NE VODILNI NE SODELUJOČI PARTNER V OCENJEVANEM TWINNINGU

• TRE PRIPRAVI POROČILO V SODELOVANJU S “CORE GROUP” (VODJA PROJEKTA IN RTA DČ IN DRŽAVE PREJEMNICE, “TASK MANAGER” NA DELEGACIJI EK ZADOLŽEN ZA OCENJEVANI PROJEKT)

Page 9: SPREMEMBE V NOVEM PRIROČNIKU ZA IZVAJANJE PROJEKTOV TMIS 2009

7. DVIG ZGORNJE MEJE STROŠKOV ZA RAZPOZNAVNOST – ČL. 9.4

• 5.000 EUR ZA PROJEKTE DO 1 MIO EUR IN 10.000 EUR ZA PROJEKTE NAD 1 MIO EUR

Page 10: SPREMEMBE V NOVEM PRIROČNIKU ZA IZVAJANJE PROJEKTOV TMIS 2009

8. PRILOGA 6 – MODEL EXPENDITURE VERIFICATION REPORT

• TEMELJITA PRENOVA PRILOGE 6 V SKLADU Z SPREMENJENIM PRAG-om (PRACTICAL GUIDE TO CONTRACT PROCEDURES FOR EC EXTERNAL ACTIONS ) DECEMBER 2008

Page 11: SPREMEMBE V NOVEM PRIROČNIKU ZA IZVAJANJE PROJEKTOV TMIS 2009

9. POROČILO O IZBIRI (SELECTION FACT SHEET) PRILOGA C7

• SPREMENJEN VZOREC POROČILA ZA PROJEKTE V OKVIRU IPA

• DODANA NOVA OCENA: DELOMA USTREZEN (“PARTLY ADEQUATE”)

• PREJ: “ADEQUATE” IN “NON ADEQUATE”

Page 12: SPREMEMBE V NOVEM PRIROČNIKU ZA IZVAJANJE PROJEKTOV TMIS 2009

10. PRILOGE C12, C13 IN C14

• UPOŠTEVAJOČ ŽELJE TWINNING PARTNERJEV JE EK V NOVI PRIROČNIK DODALA PRILOGE ZA SPREMNA PISMA IN ADDENDUME TER NAVODILA ZA NJIHOVO SESTAVO