Stakeholder Analysis Process Using Cognitive Mapping

19th ISPE International Conference on Concurrent Engineering – CE2012, Trier

(Germany), Sept 3 – 7

Brenda C. Lopez Villafranca - ITA

PhD. Geilson Loureiro - INPE

Page 2: Stakeholder Analysis Process Using Cognitive Mapping€¦ · 4.2 Construct Cognitive Maps 2.0 Construct Cognitive Maps -Context - List of Stakeholders - List of scenarios (if applicable)

Summary

1. Introduction

2. Stakeholder Analysis

3. Cognitive Maps

4. Stakeholder Analysis Process Using Cognitive Mapping

5. Advantages and Disadvantages

6. Conclusions

2

Page 3: Stakeholder Analysis Process Using Cognitive Mapping€¦ · 4.2 Construct Cognitive Maps 2.0 Construct Cognitive Maps -Context - List of Stakeholders - List of scenarios (if applicable)

1. Introduction

The stakeholder needs, most of the time are subjective, unclear, or even contradictory and must be translated into stakeholder requirements. The stakeholder requirements describe the problem supposed to be solved by the system of interest.

The cognitive maps aim to deal with subjective information and problem structuring, both capabilities needed by the stakeholder analysis.

3

Page 4: Stakeholder Analysis Process Using Cognitive Mapping€¦ · 4.2 Construct Cognitive Maps 2.0 Construct Cognitive Maps -Context - List of Stakeholders - List of scenarios (if applicable)

2. Stakeholder Analysis

• A Stakeholder is any person or organization that affects or can be affected by the system of interest.

• The Stakeholder Analysis refers to the study of how the stakeholders understand a specific problem, their point of view about it and their relation to it.

4

Page 5: Stakeholder Analysis Process Using Cognitive Mapping€¦ · 4.2 Construct Cognitive Maps 2.0 Construct Cognitive Maps -Context - List of Stakeholders - List of scenarios (if applicable)

2. Stakeholder Analysis

How to understand the stakeholders’ problem:

• Understanding the way they perceive it;

• Understanding how they structure it; and

• Reaching the real needs.

It does not mean that it is the correct way to represent the problem or even, if it is the real problem that should be analyzed; but this information must be elicited to get any conclusion.

5

Page 6: Stakeholder Analysis Process Using Cognitive Mapping€¦ · 4.2 Construct Cognitive Maps 2.0 Construct Cognitive Maps -Context - List of Stakeholders - List of scenarios (if applicable)

3. Cognitive Map

• Represents the mental model of an individual or group of individuals.

• Helps to structure complex situations with subjective information, and assumptions.

• Helps on the clarification of mental models and evokes reflection and analysis of the information exposed verbally, textually and graphically through the construction of the cognitive map process.

6

Page 7: Stakeholder Analysis Process Using Cognitive Mapping€¦ · 4.2 Construct Cognitive Maps 2.0 Construct Cognitive Maps -Context - List of Stakeholders - List of scenarios (if applicable)

4. Stakeholder Analysis Using Cognitive Maps

• The main purpose is to get to the root need through the continuous questioning to the stakeholder with generic WH questions, and specially the question Why?

• The process is iterative by nature

• Guide the thinking and reflection, changing several times the mental model of the stakeholder.

7

Page 8: Stakeholder Analysis Process Using Cognitive Mapping€¦ · 4.2 Construct Cognitive Maps 2.0 Construct Cognitive Maps -Context - List of Stakeholders - List of scenarios (if applicable)

8

4. Stakeholder Analysis Using Cognitive Maps

The stakeholders listens to the questions of the Systems Engineer.

The stakeholder reflects about the problem and brings a mental model about it.

The stakeholder expresses his mental model. As the verbal description arises, the reflection of the speech makes the stakeholder to feed the original mental model.

The systems engineer creates a mental model or perception of the problem.

The systems engineer represents the information as a cognitive map.

The stakeholder views and reflects about the graphic representation of his point of view of the problem, which takes him into reflection to create a new mental model about the situation under review

Page 9: Stakeholder Analysis Process Using Cognitive Mapping€¦ · 4.2 Construct Cognitive Maps 2.0 Construct Cognitive Maps -Context - List of Stakeholders - List of scenarios (if applicable)

9

4. Stakeholder Analysis Using Cognitive Maps

I. Stakeholder

Analysis Process -Need statement -Existing documents -Unofficial information

-Structured problem description - Relevant information for stakeholder requirements derivation

-Needs -MoE’s -Constraints -Assumptions -Etc.

-Rationale form the relevant information - Balanced understanding of the problem among the stakeholders involved and the requirements engineer

- Stakeholder’s validation

-Interaction with stakeholders -Cognitive Mapping tool -Analysis -Two requirements engineers

Input Output

Mechanisms & Resources

Control

STAKEHOLDER ANALYSIS PROCESS- IDEF0

Page 10: Stakeholder Analysis Process Using Cognitive Mapping€¦ · 4.2 Construct Cognitive Maps 2.0 Construct Cognitive Maps -Context - List of Stakeholders - List of scenarios (if applicable)

10

4. Stakeholder Analysis Using Cognitive Maps

1.0 Analyse the

Context

2.0 Construct Cognitive

Maps 3.0

Analyse Cognitive

Maps 4.0 Analyse the

Problem

Page 11: Stakeholder Analysis Process Using Cognitive Mapping€¦ · 4.2 Construct Cognitive Maps 2.0 Construct Cognitive Maps -Context - List of Stakeholders - List of scenarios (if applicable)

11

4.1 Analyze the Context

1.0

Analyze the Context -Need statement -Existing documents - Unofficial information

- Context - List of stakeholders - List of scenarios (if applicable) - Trigger question

- Stakeholder’s validation

- Interview - Research - Analysis - 2 system engineers

Input Output

Mechanisms & Resources

Control

STAKEHOLDER ANALYSIS PROCESS- IDEF0

Page 12: Stakeholder Analysis Process Using Cognitive Mapping€¦ · 4.2 Construct Cognitive Maps 2.0 Construct Cognitive Maps -Context - List of Stakeholders - List of scenarios (if applicable)

12

4.2 Construct Cognitive Maps

2.0

Construct Cognitive Maps

-Context - List of Stakeholders - List of scenarios (if applicable) - Trigger questions

- Elicited information - Individual maps validated

- Stakeholder’s validation

- Proposed Cognitive mapping tool - Cognitive Mapping software - Analysis - 2 system engineers

Input Output

Mechanisms & Resources

Control

STAKEHOLDER ANALYSIS PROCESS- IDEF0

Page 13: Stakeholder Analysis Process Using Cognitive Mapping€¦ · 4.2 Construct Cognitive Maps 2.0 Construct Cognitive Maps -Context - List of Stakeholders - List of scenarios (if applicable)

13

4.3 Analyze Cognitive Maps

3.0

Analyze Cognitive Maps - Elicited information

- Individual maps validated

- Integrated and validated map - Structured problem

- Stakeholder’s validation

- Proposed Cognitive mapping tool - Cognitive Mapping software - Analysis - 2 system engineers

Input Output

Mechanisms & Resources

Control

STAKEHOLDER ANALYSIS PROCESS- IDEF0

Page 14: Stakeholder Analysis Process Using Cognitive Mapping€¦ · 4.2 Construct Cognitive Maps 2.0 Construct Cognitive Maps -Context - List of Stakeholders - List of scenarios (if applicable)

14

4.3 Analyze Cognitive Maps

Capacity of Current Transmission Programming

Electrical Interface

Cluster

Output - Integrated and validated map - Structured problem

Page 15: Stakeholder Analysis Process Using Cognitive Mapping€¦ · 4.2 Construct Cognitive Maps 2.0 Construct Cognitive Maps -Context - List of Stakeholders - List of scenarios (if applicable)

15

4.4 Analyze the problem

4.0

Analyze the Problem - Integrated and validated map

- Structured problem

- Problem description - Relevant information (needs, MoE’s, constraints, assumptions, desires, etc. - Rationale - Balanced understanding among stakeholders and system engineers

- Stakeholder’s validation

- Analysis - 2 system engineers

Input Output

Mechanisms & Resources

Control

STAKEHOLDER ANALYSIS PROCESS- IDEF0

Page 16: Stakeholder Analysis Process Using Cognitive Mapping€¦ · 4.2 Construct Cognitive Maps 2.0 Construct Cognitive Maps -Context - List of Stakeholders - List of scenarios (if applicable)

16

4.4 Analyze the problem

Rationale Output - Problem description - Relevant information (needs, MoE’s, constraints, assumptions, desires, etc. - Rationale - Balanced understanding among stakeholders and system engineers

Real need

Page 17: Stakeholder Analysis Process Using Cognitive Mapping€¦ · 4.2 Construct Cognitive Maps 2.0 Construct Cognitive Maps -Context - List of Stakeholders - List of scenarios (if applicable)

Advantages

• Knowledge genertion

• Leveled knowledge

• Exhaustiveness

• Rationale capture

Disadvantages

• Trigger questions

• Several maps to integrate

• Lack of elicitation completeness

17

5. Advantages and Disadvantages

Page 18: Stakeholder Analysis Process Using Cognitive Mapping€¦ · 4.2 Construct Cognitive Maps 2.0 Construct Cognitive Maps -Context - List of Stakeholders - List of scenarios (if applicable)

6. Conclusions

The advantages proposed are worth enough to consider the cognitive mapping technique as part of the stakeholder analysis process.

The critical issues to obtain a succeeded analysis are:

• the complete involvement of the stakeholders.

• the previous contextualization on the problem for the systems engineer.

18

Page 19: Stakeholder Analysis Process Using Cognitive Mapping€¦ · 4.2 Construct Cognitive Maps 2.0 Construct Cognitive Maps -Context - List of Stakeholders - List of scenarios (if applicable)

Acknowledgements: