10
State Estimator (SE) and Simultaneous Feasibility Test (SFT) Status Report Steve Myers Manager of System Operations

State Estimator (SE) and Simultaneous Feasibility Test (SFT) Status Report

Embed Size (px)

DESCRIPTION

State Estimator (SE) and Simultaneous Feasibility Test (SFT) Status Report. Steve Myers Manager of System Operations. State Estimator. Progress Total difference between generation & load reduced from 10’s of 1000’s at first to 50 MW mismatch - PowerPoint PPT Presentation

Citation preview

Page 1: State Estimator (SE) and Simultaneous Feasibility Test (SFT) Status Report

State Estimator (SE)and

Simultaneous Feasibility Test (SFT)Status Report

Steve MyersManager of System Operations

Page 2: State Estimator (SE) and Simultaneous Feasibility Test (SFT) Status Report

State Estimator

Progress• Total difference between generation & load

reduced from 10’s of 1000’s at first to <500 MW

• Approximately 25 buses >50 MW mismatch

• 90% observability (75% with measurements)

Page 3: State Estimator (SE) and Simultaneous Feasibility Test (SFT) Status Report

Uses of the State Estimator

Identifying data problems Identifying model problems Monitoring of locations w/o SCADA (by

System Operators) Creating a case for Contingency

Analysis• Normally successful at least once per day

Page 4: State Estimator (SE) and Simultaneous Feasibility Test (SFT) Status Report

SE Plan

Continue to incrementally improve Continue to reduce mismatches With Engineer’s attention, use in Day-

Ahead analysis Train System Operators Ultimately – SE will run CA in RT

sequence

Page 5: State Estimator (SE) and Simultaneous Feasibility Test (SFT) Status Report

SE Plan

Needs• Data Response from QSE’s and Private

Networks• Unit Status – QSE

• Private Network Issues to Correct• Net Gen sent as one unit

• Loads not modeled

• Data required by ERCOT Operating Guides Section 8

Page 6: State Estimator (SE) and Simultaneous Feasibility Test (SFT) Status Report

Simultaneous Feasibility Test (SFT)

Calculates “Shift Factors” used in Congestion Management

Progress• Attempted use in December '02

• Bugs that had not shown up in test mode

• Waiting on fixes from vendor

• Once offline testing complete, will test again in production

Page 7: State Estimator (SE) and Simultaneous Feasibility Test (SFT) Status Report

SFT Plan

Use in Day-Ahead• Initially peak hour• Limited contingencies

Use in Hours Ahead• Initially test mode• Limited contingencies• Limited iterations with SPD

Page 8: State Estimator (SE) and Simultaneous Feasibility Test (SFT) Status Report

Next Steps

Contingency Analysis will run in the Real-Time sequence and upon demand

SE and SFT will run for each BES deployment

ERCOT expects its systems to be ready By April 1

Page 9: State Estimator (SE) and Simultaneous Feasibility Test (SFT) Status Report

What Do We Gain?

More accurate analyses – closer to RT Greatly improved pro-active CM Much more accurate “Shift Factors” Potentially less OOM deployments

Page 10: State Estimator (SE) and Simultaneous Feasibility Test (SFT) Status Report