Upload
jameson-gardner
View
19
Download
2
Embed Size (px)
DESCRIPTION
State Estimator (SE) and Simultaneous Feasibility Test (SFT) Status Report. Steve Myers Manager of System Operations. State Estimator. Progress Total difference between generation & load reduced from 10’s of 1000’s at first to 50 MW mismatch - PowerPoint PPT Presentation
Citation preview
State Estimator (SE)and
Simultaneous Feasibility Test (SFT)Status Report
Steve MyersManager of System Operations
State Estimator
Progress• Total difference between generation & load
reduced from 10’s of 1000’s at first to <500 MW
• Approximately 25 buses >50 MW mismatch
• 90% observability (75% with measurements)
Uses of the State Estimator
Identifying data problems Identifying model problems Monitoring of locations w/o SCADA (by
System Operators) Creating a case for Contingency
Analysis• Normally successful at least once per day
SE Plan
Continue to incrementally improve Continue to reduce mismatches With Engineer’s attention, use in Day-
Ahead analysis Train System Operators Ultimately – SE will run CA in RT
sequence
SE Plan
Needs• Data Response from QSE’s and Private
Networks• Unit Status – QSE
• Private Network Issues to Correct• Net Gen sent as one unit
• Loads not modeled
• Data required by ERCOT Operating Guides Section 8
Simultaneous Feasibility Test (SFT)
Calculates “Shift Factors” used in Congestion Management
Progress• Attempted use in December '02
• Bugs that had not shown up in test mode
• Waiting on fixes from vendor
• Once offline testing complete, will test again in production
SFT Plan
Use in Day-Ahead• Initially peak hour• Limited contingencies
Use in Hours Ahead• Initially test mode• Limited contingencies• Limited iterations with SPD
Next Steps
Contingency Analysis will run in the Real-Time sequence and upon demand
SE and SFT will run for each BES deployment
ERCOT expects its systems to be ready By April 1
What Do We Gain?
More accurate analyses – closer to RT Greatly improved pro-active CM Much more accurate “Shift Factors” Potentially less OOM deployments