Status of the Transfer of CRYRING to FAIR
Status of the Transfer of CRYRING to FAIR
MSL, 2 February 2009
Håkan DanaredHåkan Danared
•March 2008: Letter from FLAIR collaboration to FAIR and Swedish Research Council that FLAIR accepts CRYRING as the LSR.
• June 2008: Discussion between MSL and the Swedish Research Council, where it is agreed that MSL will obtain 30 MSEK to cover the costs of keeping the ring at MSL though 2010, make the necessary modifications, and transfer it to FAIR.
•February 2009: No contract yet between MSL and Swedish Research Council, mainly because of unclear rules about how FAIR is to accept in-kind contributions to experiments (my interpretation). Nevertheless MSL has started to spend the money.
Developments during 2008-2009Non-Technical
Developments during 2008-2009Non-Technical
•Start of writing of Technical Design Report. Contains documentation of existing hardware, design of new systems, ...
Developments during 2008-2009Technical
Developments during 2008-2009Technical
•CAD engineer hired to transfer CRYRING drawings on paper and in 2d Autocad to 3d CAD (Solid Edge).
•Septum magnet and supply (Földi 2 kA, 28 V) given to the project from TSL.
•Dag Reistad (retired from TSL) hired to prepare acquisition of kicker magnets with supplies.
•Contacts with Imtech-Vonk for transfer of magnet power converters to FAIR, will visit Angela and GSI on Thursday to discuss technical details.
Zero:th order specifications for LSR
• Current: 2.8 kA• Voltage: 22 kV• Rise/fall time: 200 ns• Stability: 1 %• Max pulse length: ?
Kicker MagnetsKicker Magnets
GSI specifications
For single-turn extraction, field strength 0.10 T, fall time (injection)/rise time (extraction) less than particle revolution time.
Dag Reistad visited
• CERN• GSI• Puls-Plasma-Technik
Danfysik coming to MSL next week
Contacts with Friatec, ScandiNova, ...
TimelineTimeline
Technical Design Report: Ready summer 2009 (optimistically)
Design of injection and extraction: Until April 2009
Manufacturing (in-house, commercial): Until December 2009
Installations and tests: Spring 2010
Disassembly and transfer: Completed by 31 December 2010
Minor work possible after 2010, such as preparation of new ion-source platform