Upload
allyson-johnson
View
214
Download
0
Embed Size (px)
DESCRIPTION
asdfadfvathhee123
Citation preview
SECURITY AND DIVERSIFICATION
OF SUPPLIES WITH THE TWIN
PRIORITIES OF IMPROVING SAFETY
AND ENVIRONMENTAL IMPACT
AGENDA
1.General presentation
2.Site location: connections to Belgium and French gas systems
3.Developing EPC strategy
4.Use of the cooling water discharged from Gravelines nuclear power
plant
5. Improving safety by demonstrating tanks ability to support overfilling
6. Improving safety by using state of the art sea protection
7.Erection status to date
I LNG Tech – S. Ringot I 04 décembre 2012 2
General presentation
1
I LNG Tech – S. Ringot I 04 décembre 2012 3
TERMINAL MAIN CHARACTERISTICS
4
Commercial capacity Storage (m3) Jetty Emission flow rate
13 bcm/y (# 9.2 mtpa) 3 tanks of 190,000 m3
570,000 m3 total 1 0 – 1,9 Mm3/h
Ship sizes:
75,000 – 270,000 m3
Re-gasification technology
ORVs using cooling water discharged
from the nearby nuclear power plant
GRTgaz (French grid)
Fluxys (Belgian grid)
flare 53 ha plateform
I LNG Tech – S. Ringot I 04 décembre 2012 4
DUNKERQUE LNG STRUCTURATION
Dunkerque LNG : EDF subsidiary
Fluxys
• Belgium gas TSO
• Zeebrugge LNG terminal operator
Total
• Main Oil & Gas player
Gaz Opale
• Dunkerque LNG & Fluxys subsidiary
• Dedicated to terminal operation
3 Bcma
10 %
Disponibles
Contrats de réservation de capacité
25% 65%
Pacte d’actionnaires
2 Bcma 8 Bcma
I LNG Tech – S. Ringot I 04 décembre 2012 5
• Dunkerque LNG participates with partners in INNOCOLD, Institute of Low-Temperature Technology, for : • Research topics (materials, industrial safety, process efficiency)
• Training in cold technologies
• Test facility development
I LNG Tech – S. Ringot I 04 décembre 2012 6
Site location : connections to Belgium
and French gas systems
2
I LNG Tech – S. Ringot I 04 décembre 2012 7
CONNECTION OF DUNKERQUE LNG TERMINAL TO FRANCE
• Has triggered 1,2 G€ investment on the
French gas network to connect the terminal
and reinforce the transmission system,
allowing to send out 520 GWh/d (13 bcma)
• GRTgaz is thus laying down a 170 km
pipeline with a diameter of 1200 mm
• The natural gas will not be odorized after
measuring and before being piped into the
transmission system
• For the first time in France,
a no odorized pipeline: a first step towards a
wider no odorized gas transmission system in
France ?
8
GRTgaz
I LNG Tech – S. Ringot I 04 décembre 2012 8
CONNECTION OF DUNKERQUE LNG TERMINAL TO BELGIUM
• Dunkerque LNG pushed GRTgaz and Fluxys
Belgium to extend the pipeline to Belgium and
thus create a direct connection of the terminal to
Belgium
• In an European first, a new concept: a single
Fluxys contract for cross-border capacity
between Dunkirk terminal and the Belgian
system
9
• GRTgaz and Fluxys Belgium will lay down a nearly 100 km pipeline offering thus a 8 bcma capacity
from France into the Belgian system on a firm basis
• The new capacity is expected to be ready for use by late 2015, to coincide with the commissioning of
the LNG terminal in Dunkirk
Dunkerque LNG terminal offers through a direct connection to 2 major markets,
a gateway to supply gas to NW Europe
I LNG Tech – S. Ringot I 04 décembre 2012 9
Developping EPC strategy
3
I LNG Tech – S. Ringot I 04 décembre 2012 10
EPC STRATEGY
• Reach a cost « As Low As Possible » is a common goal for all
project developers
• Classical EPCC contracts « all in one », despite some real
avantages, suffers
• A limitation of competition (number of Tanks manufacturers / number of
engineering compagnies)
• Mixing very different activities within only one contract (severability,
liabilities)
• A « huge » amount, among wich any claims seems « so little »
• Dunkerque LNG choice was to split on three homogenous
contracts : • Process, throught an engineering compagny :
• Tanks, throught a consortium :
• Tunnel, also throught a consortium :
I LNG Tech – S. Ringot I 04 décembre 2012 11
TSLNG
INDUSTRIAL ORGANISATION
Dunkerque LNG GPMD
GRT gaz Département
Grands Projets
COFIVA : EDF Ingénierie
SOGREGAZ,…
Lo
t 3 : G
C C
ôtie
r
Lot 1
: Pré
para
tion
Lo
t 2 : D
rag
ag
e
Lo
t 4 : M
esu
res C
om
p.
MO
E : L
ot «
Pro
ce
ss »
– T
S L
NG
Lo
t « R
ése
rvo
irs »
– E
P-B
Y
Lo
t « T
un
ne
l » –
BR
S
Po
se
tub
es
Fo
urn
iture
tub
es
Centre
d’ingénierie
GRTgaz
ARCADIS
Maîtrise
d’ouvrage
Maîtrise
d’œuvre
Réalisation
Réseaux Terminal méthanier Installations portuaires
I LNG Tech – S. Ringot I 04 décembre 2012 12
Use of the cooling water discharged from
Gravelines nuclear power plant
4
I LNG Tech – S. Ringot I 04 décembre 2012 13
Reach a « 0 CHG » emission goal
• Zero CHG terminal was a major objective of Dunkerque project
since the begining
• First decision was to collect every emission of LNG and gas to
flare systems • TSV and PSV on every lines
• ORV and Tanks (hight flow-rate) are collected throught a specific system
• Second challenge was to face the sea-water temperature in
winter (-4°C as a minimum) : • Dual system (ORV / SCV et ORV / sea-water heater) has been designed
• A tunnel solution, from Western to Eastern part of harbour, associated
with ORV, has been designed
• Economical comparison has been carried out
• TUNNEL (5km) was the optimum solution
• Tender result has confirmed this choice
I LNG Tech – S. Ringot I 04 décembre 2012 14
OVERVIEW OF TUNNEL
I LNG Tech – S. Ringot I 04 décembre 2012 15
FULLY BORED IN FLANDER CLAY
Terminal platform
(+10 m CMG)
Tunnel (-40 m CMG)
Exhaust pit (Ø 16m)
CNPE pits
I LNG Tech – S. Ringot I 04 décembre 2012 16
GRAVELINES POWER : WATER INTAKE
Sea-water
intake (during
unit
maintenance)
inlet pits
EXHAUST PIT : D-WALL OVER 65 METER DEPTH
• Main challenge was the verticality, with a requested deviation
of less than 260 mm at -65 m from top.
• The result is better than
110 mm
• Including for the part
digged in clay (30 m)
I LNG Tech – S. Ringot I 04 décembre 2012 18
EXHAUST PIT : D-WALL OVER 65 METER DEPTH
• Waterstop CWS welding technique was used at -55m (first of a
kind)
I LNG Tech – S. Ringot I 04 décembre 2012 19
Improving safety by demonstrating tanks ability to
support overfilling
5
I LNG Tech – S. Ringot I 04 décembre 2012 20
TANK ABILITY TO SUPPORT OVERFILLING
• French regulation request that the consequences of « any
danger that cannot be demonstrated as impossible » must be
studied in detail
• Despite all the safety barriers, an overfilling cannot be
qualified of « impossible »
• Tank design has been slightly modified to take into account
this accidental case
• This has been achieved by designing a frangible dome roof • The roof is set to fail at a predetermined over pressure,
• The slab and wall are set to remain structurally able to hold the liquid
I LNG Tech – S. Ringot I 04 décembre 2012 21
SEQUENCE OF EVENTS
t=0: start of overfilling
From 0 to 40 s after start of overfilling:
Total evaporation of LNG in contact with the
warmer elements of the annular space
Internal gas pressure increases quickly
dome frangibility happens at 757 mbarg (safe
margin / operation : 2.5 x design pressure)
I LNG Tech – S. Ringot I 04 décembre 2012 22
DESCRIPTION OF HOW IS TANK FRANGIBILITY ACHIEVED (1/4)
Overview of dome roof structure arrangement
I LNG Tech – S. Ringot I 04 décembre 2012 23
DESCRIPTION OF HOW IS TANK FRANGIBILITY ACHIEVED (2/4)
Welds failure happens first
I LNG Tech – S. Ringot I 04 décembre 2012 24
DESCRIPTION OF HOW IS TANK FRANGIBILITY ACHIEVED (3/4)
Welds failure leads to large displacement
P2 = 757 mbarg weld failure
Tension redistributed in rebars
Rebar plastification; large rebar deformation
Separation dome / rafter
I LNG Tech – S. Ringot I 04 décembre 2012 25
DESCRIPTION OF HOW IS TANK FRANGIBILITY ACHIEVED (4/4)
P2 = 757 mbarg weld failure
Tension redistributed in rebars
Rebar plastification; large rebar deformation
Separation dome / rafter
Cracking of dome
Gas flow => overpressure evacuated
Large displacements leads to dome cracking
I LNG Tech – S. Ringot I 04 décembre 2012 26
Improving safety by using state of the art
sea protection
6
I LNG Tech – S. Ringot I 04 décembre 2012 27
STATE OF THE ART SEA PROTECTION
• During the 1990’s, and beginning of 2000’s, several bad
weather conditions leads to industrial damage in France
• LNG Terminal took into account sea-water protection from the
early design, regarding : • Static level of plateform,
• Wave protection.
• Static protection was achieved with a plateform level of +10 m
CMG (Gravelines Coastal Level), including some provision for
climate change
• Methodology for wave protection is not define nor requested
by regulation or standard.
I LNG Tech – S. Ringot I 04 décembre 2012 28
DEFINITION OF PROJECT CRITERIA
• Criteria for dike design : • Stability for W100 / L100 (stands for 100 years return period)
• Limited (less than 5%) disorders for W100 / L1000
• No overtopping for W10 / L10 (stands for 10 years return period)
• Additionnal protection (sea walls) have been designed to
obtain a level of protection defined per : • a wave climate of W100 / L100
• a protection level :
• LNG pipes : no over-topping
• Gangways… : < 3 l/s/ml
• Roads : 10-50 l/s/ml
• Protection efficiency has been checked under W100 / L1000 wave
climate.
I LNG Tech – S. Ringot I 04 décembre 2012 29
SPECIFICATION FOR SEA PROTECTION
I LNG Tech – S. Ringot I 04 décembre 2012 30
RESULTS
DIKE
I LNG Tech – S. Ringot I 04 décembre 2012 31
Erection Status to date
7
I LNG Tech – S. Ringot I 04 décembre 2012 32
DUNKERQUE WESTERN HARBOUR
I LNG Tech – S. Ringot I 04 décembre 2012 33
21 octobre 2007
I LNG Tech – S. Ringot I 04 décembre 2012 34
16 septembre 2011
I LNG Tech – S. Ringot I 04 décembre 2012 35
9 décembre 2011
I LNG Tech – S. Ringot I 04 décembre 2012 36
20 avril 2012
I LNG Tech – S. Ringot I 04 décembre 2012 37
25 mai 2012
I LNG Tech – S. Ringot I 04 décembre 2012 38
24 août 2012
I LNG Tech – S. Ringot I 04 décembre 2012 39
27 septembre 2012
I LNG Tech – S. Ringot I 04 décembre 2012 40
TERMINAL
MÉTHANIER
DE DUNKERQUE
THANKS FOR YOUR KIND
ATTENTION