    Emergency Response Program Maban Field OfficeMaban County, Upper Nile State, South Sudan

    Semi-Permanent Classroom ProjectTechnical Scope of Works: Construction Works

    OBJECTIVE

    The key objectives is to construct 6m x 16m classroom blocks located at Dorro Refugee camp in

    Maban city that will improve learning space environment for children and school administration.

    STATEMENT OF WORK AND DESCRIPTION OF DELIVERABLES

    A. GENERAL CONDITIONS

    The sub-contractor shall provide the following:

    The Sub-contractor shall provide all technical staff, skilled and unskilled labor, tools and execute

    the construction works to be done and as described in the subcontract, and to execute this worksafely, timely, professionally and economically. The Sub-contractors responsibilities shall

    include:

    1. The Sub-contractor shall execute and complete the Works in accordance with the Drawingsprovided by Save the Children subcontract and with Save the Children Construction Teams

    instructions, and shall remedy all defects in the Works.

    2. The Sub-contractor shall be responsible for the adequacy, stability and safety of all Siteoperations and of all methods of construction. Except to the extent specified in the

    subcontract, the Sub-contractor shall be responsible for all sub-contractors Documents,

    Temporary Works, and shall not otherwise be responsible for the design or specification of thePermanent Works.

    3. The Sub-contractor shall take all necessary measures to control dust and mud and stormwater

    from the operations, and to prevent spillage of excavated materials on public and private roads

    and facilities4. The Contractor shall employ the best practical means to minimize noise and vibration

    produced by the operations

    5. Disbursement Schedule: There will be no advance paid for mobilization.

    B. SPECIFICATIONS FOR SEMI-PERMANENRT CLASSROOMS CONSTRUCTION

    SUBPROJECT DESCRIPTION

    The Semi-Permanent Classrooms of 6m width and 16m length and of height as shown in the

    drawings shall be constructed for this subproject and shall be at the following locations in Dorro

    Refugee camp, as stipulated in the drawings:

    Nur School,

    Unity School

    1

  • 7/28/2019 Technical Scope of Works for Classroom Construction Works

    2/4

    Emergency Response Program Maban Field OfficeMaban County, Upper Nile State, South Sudan

    Jamhur School

    Dares Salem School

    The proposed improvements will include:

    All necessary demolition works and removal of debris, etc. created by said works

    The diversion of flow and bailing out of water

    Excavation of foundation

    Plain cement concrete and reinforced concrete works as specified in this scope of works

    and subproject drawings

    Cement masonry works as specified in this scope of work and subproject drawings

    Construction of Semi-Permanent Classrooms as specified in the drawings

    1. MOBILIZATION AND DEMOBILISATION

    1.1 Mobilization

    This work consists of moving personnel, tools and equipment to the subproject site and

    performing all preparatory work necessary before starting construction. The cost of mobilizationis included in the BOQ and shall include movement of tools, equipment and personnel to the site

    and shall include (but not necessarily be limited to):

    a) Provision of any required access and detour roads, within and outside the construction site;b) Provision of transportation for all personnel and tools as necessary.

    1.2 Demobilization

    Payment for demobilization shall be compensation in full for the costs of removing tools,equipment, facilities, and personnel from the site and shall include (but not necessarily be limited

    to):

    a) Transportation of any temporary plant from the site;b) Dismantling, demolishing, and removing of all temporary facilities on the site;

    c) Restoration of all construction site areas to a satisfactory condition;

    d) Cleaning up the site.

    The cost of demobilization is specified in the BOQ and must be completed to the satisfaction of

    the Save the Children Construction Team. This item shall be payable only in respect of the wholeof the Works and shall not apply in cases of sectional completion.

    2

  • 7/28/2019 Technical Scope of Works for Classroom Construction Works

    3/4

    Emergency Response Program Maban Field OfficeMaban County, Upper Nile State, South Sudan

    2. SITE CLEARANCE, SETTING OUT ALLIGNMENTS, EARTHWORKS

    2.1 SITE CLEARANCE

    The site clearance shall cover all the operations required in full, as instructed by the Save the

    Children Construction Team, for clearing the site and its surroundings, including providinglabour, tools, equipments and incidentals necessary to complete the work. It will also include

    handling, salvaging, piling or stacking or collecting and disposing off cleared materials.

    2.2 SETTING OUT

    After the site clearance operations have been carried out, the Sub-contractor shall do all setting

    out required including the limits of excavation set to true levels, lines, curves, slopes, grades and

    sections, etc. as shown on the drawings or as directed by the Save the Children Construction

    Team.

    3. EARTHWORKS

    Earthworks shall include excavation and backfilling works.

    3.1 EXCAVATION WORKS

    Excavation works shall include the careful removal of all the materials of whatever nature and

    whether dry or wet, exactly in accordance with the lines, levels, grades, curves and dimensionsetc. shown on the drawings or as directed by the Save the Children Construction Team, taking

    exact widths and levels of the lowest step of the foundations, footing, basement, etc. and the sides

    shall be left plumb where the nature of soil permits it.

    3.2 BACKFILLING WORKS

    Backfilling works shall include the filling in of foundations, trenches, etc. with selected materials

    from the excavation as instructed by Save the Children Construction Team. Selected material

    filling shall be free from roots, debris or any other foreign matter. All clods of selected material

    shall be broken or removed. Where the excavated material is mostly rock, the boulders shall bebroken into pieces not bigger than 15 cm in size in any direction, and shall be mixed with fine

    materials and fill the voids as far as possible. The approved material for filling shall be approved

    by Save the Children Construction Team before the Sub-contractor can fill the specified areas.

    4. CONSTRUCTION

    The Sub-contractor, as instructed by the Save the Children Construction Team, shall implement

    all construction works. Construction works shall include the following activities:

    Production of snadcrete blocks

    Construction/installation of necessary formworks

    Pouring of mass concrete footings

    3

  • 7/28/2019 Technical Scope of Works for Classroom Construction Works

    4/4

    Emergency Response Program Maban Field OfficeMaban County, Upper Nile State, South Sudan

    Pouring and ramming and compaction of marram floors

    Fabrication and setting of reinforcement steel bars

    Laying of masonry block foundation walls and columns

    Anti-termiting of all necessary timber materials

    Fabrication and installation of timber roofing frames

    Installation of CI roofing sheets

    Any necessary painting works

    All defects works associated with construction

    Any other required construction activities as instructed by the Save the Children

    Construction Team

    5. VISITING AND TESTING

    Routine site visits covering inspection and testing shall be carried out by Save the Children

    Construction Team to test the quality of workmanship for compliance with the requirements of

    drawing and technical scope of works. If required by Save the Children Construction Team, testspecimen shall be provided by the Sub-contractor at his expense if required at locations selected

    by the Save the Children Construction Team.

    6. MEASUREMENT AND PAYMENT

    The unit of measurement for all works shall be units specified in the subcontract drawings.

    Payments shall be made as agreed in the subcontract payment conditions and schedule. TheSubcontractor shall submit all payment requests to the Save the Children Construction Team for

    verifications and certifications, and subsequent submission to the Save the Children Maban officeTeam Leader for approval and subsequent payments.

    4