Semi-Permanent Classroom ProjectTechnical Scope of Works: Construction Works
OBJECTIVE
The key objectives is to construct 6m x 16m classroom blocks located at Dorro Refugee camp in
Maban city that will improve learning space environment for children and school administration.
STATEMENT OF WORK AND DESCRIPTION OF DELIVERABLES
A. GENERAL CONDITIONS
The sub-contractor shall provide the following:
The Sub-contractor shall provide all technical staff, skilled and unskilled labor, tools and execute
the construction works to be done and as described in the subcontract, and to execute this worksafely, timely, professionally and economically. The Sub-contractors responsibilities shall
include:
1. The Sub-contractor shall execute and complete the Works in accordance with the Drawingsprovided by Save the Children subcontract and with Save the Children Construction Teams
instructions, and shall remedy all defects in the Works.
2. The Sub-contractor shall be responsible for the adequacy, stability and safety of all Siteoperations and of all methods of construction. Except to the extent specified in the
subcontract, the Sub-contractor shall be responsible for all sub-contractors Documents,
Temporary Works, and shall not otherwise be responsible for the design or specification of thePermanent Works.
3. The Sub-contractor shall take all necessary measures to control dust and mud and stormwater
from the operations, and to prevent spillage of excavated materials on public and private roads
and facilities4. The Contractor shall employ the best practical means to minimize noise and vibration
produced by the operations
5. Disbursement Schedule: There will be no advance paid for mobilization.
B. SPECIFICATIONS FOR SEMI-PERMANENRT CLASSROOMS CONSTRUCTION
SUBPROJECT DESCRIPTION
The Semi-Permanent Classrooms of 6m width and 16m length and of height as shown in the
drawings shall be constructed for this subproject and shall be at the following locations in Dorro
Refugee camp, as stipulated in the drawings:
Nur School,
Unity School
1
7/28/2019 Technical Scope of Works for Classroom Construction Works
2/4
Emergency Response Program Maban Field OfficeMaban County, Upper Nile State, South Sudan
Jamhur School
Dares Salem School
The proposed improvements will include:
All necessary demolition works and removal of debris, etc. created by said works
The diversion of flow and bailing out of water
Excavation of foundation
Plain cement concrete and reinforced concrete works as specified in this scope of works
and subproject drawings
Cement masonry works as specified in this scope of work and subproject drawings
Construction of Semi-Permanent Classrooms as specified in the drawings
1. MOBILIZATION AND DEMOBILISATION
1.1 Mobilization
This work consists of moving personnel, tools and equipment to the subproject site and
performing all preparatory work necessary before starting construction. The cost of mobilizationis included in the BOQ and shall include movement of tools, equipment and personnel to the site
and shall include (but not necessarily be limited to):
a) Provision of any required access and detour roads, within and outside the construction site;b) Provision of transportation for all personnel and tools as necessary.
1.2 Demobilization
Payment for demobilization shall be compensation in full for the costs of removing tools,equipment, facilities, and personnel from the site and shall include (but not necessarily be limited
to):
a) Transportation of any temporary plant from the site;b) Dismantling, demolishing, and removing of all temporary facilities on the site;
c) Restoration of all construction site areas to a satisfactory condition;
d) Cleaning up the site.
The cost of demobilization is specified in the BOQ and must be completed to the satisfaction of
the Save the Children Construction Team. This item shall be payable only in respect of the wholeof the Works and shall not apply in cases of sectional completion.
2
7/28/2019 Technical Scope of Works for Classroom Construction Works
3/4
Emergency Response Program Maban Field OfficeMaban County, Upper Nile State, South Sudan
2. SITE CLEARANCE, SETTING OUT ALLIGNMENTS, EARTHWORKS
2.1 SITE CLEARANCE
The site clearance shall cover all the operations required in full, as instructed by the Save the
Children Construction Team, for clearing the site and its surroundings, including providinglabour, tools, equipments and incidentals necessary to complete the work. It will also include
handling, salvaging, piling or stacking or collecting and disposing off cleared materials.
2.2 SETTING OUT
After the site clearance operations have been carried out, the Sub-contractor shall do all setting
out required including the limits of excavation set to true levels, lines, curves, slopes, grades and
sections, etc. as shown on the drawings or as directed by the Save the Children Construction
Team.
3. EARTHWORKS
Earthworks shall include excavation and backfilling works.
3.1 EXCAVATION WORKS
Excavation works shall include the careful removal of all the materials of whatever nature and
whether dry or wet, exactly in accordance with the lines, levels, grades, curves and dimensionsetc. shown on the drawings or as directed by the Save the Children Construction Team, taking
exact widths and levels of the lowest step of the foundations, footing, basement, etc. and the sides
shall be left plumb where the nature of soil permits it.
3.2 BACKFILLING WORKS
Backfilling works shall include the filling in of foundations, trenches, etc. with selected materials
from the excavation as instructed by Save the Children Construction Team. Selected material
filling shall be free from roots, debris or any other foreign matter. All clods of selected material
shall be broken or removed. Where the excavated material is mostly rock, the boulders shall bebroken into pieces not bigger than 15 cm in size in any direction, and shall be mixed with fine
materials and fill the voids as far as possible. The approved material for filling shall be approved
by Save the Children Construction Team before the Sub-contractor can fill the specified areas.
4. CONSTRUCTION
The Sub-contractor, as instructed by the Save the Children Construction Team, shall implement
all construction works. Construction works shall include the following activities:
Production of snadcrete blocks
Construction/installation of necessary formworks
Pouring of mass concrete footings
3
7/28/2019 Technical Scope of Works for Classroom Construction Works
4/4
Emergency Response Program Maban Field OfficeMaban County, Upper Nile State, South Sudan
Pouring and ramming and compaction of marram floors
Fabrication and setting of reinforcement steel bars
Laying of masonry block foundation walls and columns
Anti-termiting of all necessary timber materials
Fabrication and installation of timber roofing frames
Installation of CI roofing sheets
Any necessary painting works
All defects works associated with construction
Any other required construction activities as instructed by the Save the Children
Construction Team
5. VISITING AND TESTING
Routine site visits covering inspection and testing shall be carried out by Save the Children
Construction Team to test the quality of workmanship for compliance with the requirements of
drawing and technical scope of works. If required by Save the Children Construction Team, testspecimen shall be provided by the Sub-contractor at his expense if required at locations selected
by the Save the Children Construction Team.
6. MEASUREMENT AND PAYMENT
The unit of measurement for all works shall be units specified in the subcontract drawings.
Payments shall be made as agreed in the subcontract payment conditions and schedule. TheSubcontractor shall submit all payment requests to the Save the Children Construction Team for
verifications and certifications, and subsequent submission to the Save the Children Maban officeTeam Leader for approval and subsequent payments.