87
COMPANY: HOANG LONG JOC TGT FIELD DEVELOPMENT PROJECT PROVISION OF TRANSPORTATION AND INSTALLATION FOR WHP-H5 TOPSIDE AND PIPELINES EPCI CONTRACTOR: PTSC MECHANICAL & CONSTRUCTION COMPANY LIMITED T&I CONTRACTOR: PTSC OFFSHORE SERVICES JSC INSTALLATION SUBCONTRACTOR: TL OFFSHORE SDN.BHD LOAD OUT PROCEDURE Document No.: TGT-POS-S-H05-CA-0003 TLO/PTSC POS PTSC M&C HLJOC REV. NO. DATE PREPARED BY TLO APPROVED BY TLO APPROVED BY PTSC POS APPROVED APPROVED NAME SIGN DATE NAME SIGN DATE NAME SIGN DATE NAME SIGN DATE NAME SIGN DATE A0 DVL DVL PMT B0 11.5.15 DVL DVL PMT

TGT POS S H05 CA 0003 H5 Spools Loadout Procedure_B0

Embed Size (px)

DESCRIPTION

Loadout Procedure

Citation preview

  • COMPANY: HOANG LONG JOC

    TGT FIELD DEVELOPMENT PROJECT

    PROVISION OF TRANSPORTATION AND INSTALLATION

    FOR WHP-H5 TOPSIDE AND PIPELINES EPCI CONTRACTOR: PTSC MECHANICAL & CONSTRUCTION

    COMPANY LIMITED T&I CONTRACTOR: PTSC OFFSHORE SERVICES JSC

    INSTALLATION SUBCONTRACTOR: TL OFFSHORE SDN.BHD

    LOAD OUT PROCEDURE

    Document No.: TGT-POS-S-H05-CA-0003

    TLO/PTSC POS PTSC M&C HLJOC

    REV.

    NO. DATE

    PREPARED BY TLO APPROVED BY TLO APPROVED BY PTSC POS APPROVED APPROVED

    NAME SIGN DATE NAME SIGN DATE NAME SIGN DATE NAME SIGN DATE NAME SIGN DATE

    A0 DVL DVL PMT

    B0 11.5.15 DVL DVL PMT

  • HLJOC/PTSC M&C PTSC POS/ TLO

    TGT FIELD DEVELOPMENT PROJECT

    PROVISION OF TRANSPORTATION AND INSTALLATION FOR WHP-H5 TOPSIDE AND PIPELINES

    Document No.:

    TGT-POS-S-H05-CA-0003 LOAD OUT PROCEDURE Page 2 of 10

    Revision No.: B0 Date: 09 May 15

    Contents

    1. INTRODUCTION ...................................................................................................................................................... 3

    1.1. PROJECT DESCRIPTION ....................................................................................................................................... 3

    1.2. DEFINITIONS ............................................................................................................................................................ 5

    1.3. ABBREVIATIONS ..................................................................................................................................................... 5

    1.4. REFERENCE DOCUMENTS ................................................................................................................................... 5

    1.5. SCOPE OF DOCUMENT ......................................................................................................................................... 7

    2. LOAD OUT PROCEDURE ....................................................................................................................................... 8

    2.1. SPOOLS DATA .......................................................................................................................................................... 8

    2.2. PROCEDURE ............................................................................................................................................................. 8

    3. APPENDIX ................................................................................................................................................................. 9

    3.1. LIFTING ANALYSIS ................................................................................................................................................ 9

    3.2. DRAWINGS .............................................................................................................................................................. 10

  • HLJOC/PTSC M&C PTSC POS/ TLO

    TGT FIELD DEVELOPMENT PROJECT

    PROVISION OF TRANSPORTATION AND INSTALLATION FOR WHP-H5 TOPSIDE AND PIPELINES

    Document No.:

    TGT-POS-S-H05-CA-0003 LOAD OUT PROCEDURE Page 3 of 10

    Revision No.: B0 Date: 09 May 15

    1. INTRODUCTION

    1.1. Project Description

    The Te Giac Trang (TGT or White Rhinoceros) Field is located in the northern part of Block 16

    1, in the Cuu Long Basin offshore Vietnam, it is about 100km southeast of Vung Tau shore

    base, 20km northwest of the Bach Ho Field and 35km west of the Rang Dong Field.

    Figure 1.1: TGT Field Location Map

    TGT Field is divided into H1, H2, H3, H4 and H5 fault blocks. Hoang Long Joint Operating

    Company (HLJOC) has commenced production from TGT Oil Field since 2011. Currently, the

    field facilities of the TGT Field are summarized as follows:

    A 16 slot H1-WHP is located in a water depth of 43.0 m (LAT) over the H1.1, H1.2 and

    H2 areas;

    A 16 slot H4-WHP is located in a water depth of 44.77 m (LAT) and middle of the H4

    and H3N area;

    A leased FPSO Armada TGT1 is located approximately 2 km southeast of H1-WHP, in a

    water depth of 43.4 m (LAT);

    A PLEM and connect subsea pipelines including 4x10 multiphase flow lines, a 10

    water injection flow line and a 8 Gas-lift gas flow line between the H1-WHP and the

    FPSO;

    A 16 multiphase pipeline, a 8 water injection pipeline, a 6 gas-lift pipeline connecting

    H4-WHP to H1-WHP with a length of 7km each;

  • HLJOC/PTSC M&C PTSC POS/ TLO

    TGT FIELD DEVELOPMENT PROJECT

    PROVISION OF TRANSPORTATION AND INSTALLATION FOR WHP-H5 TOPSIDE AND PIPELINES

    Document No.:

    TGT-POS-S-H05-CA-0003 LOAD OUT PROCEDURE Page 4 of 10

    Revision No.: B0 Date: 09 May 15

    An SSIV and a 8 subsea gas export pipeline from the PLEM to the tie-in point with the

    12 Gas collection pipeline which is installed and operated by PetroVietnam Gas (PV

    Gas);

    The WHPs are normally unattended installations with independent power and control

    systems;

    There will be no processing on the WHPs, i.e. full well streams transferred to the FPSO

    Armada TGT1 for processing, storing and export;

    Oil export via by shuttle tanker.

    Well stream fluids from H4-WHP are transported to H1-WHP via an infield pipeline, and then

    commingled with well stream fluids from H1-WHP. Additionally, well stream fluids from Hai

    Su Trang (HST) / Hai Su Den (HSD) Fields, Block 15-2/01, adjacent to Block 16-1 is also tied-

    in H1-WHP. The commingled well stream fluids are sent to the FPSO for processing via four

    multiphase 10 flow lines. A leased FPSO Armada TGT1 provides all processing facilities,

    utilities and storage for export oil. The produced gas (less fuel gas) is exported to shore via 8

    subsea gas export pipeline and the newly installed 12 Gas collection pipeline tied in to

    existing STV-RD-BH pipeline. Injection water is supplied from the FPSO via a 10 carbon

    steel pipeline. The Gas-lift gas is also supplied from FPSO via an 8 carbon steel pipeline.

    Gas lift and water injection for HST/HSD Fields are also provided from FPSO via a gas lift and

    a water injection pipelines.

    The H5 project is an upstream project which includes a well head platform H5 and infield

    pipeline system. One insulated 12 NPS pipeline is to transport well stream fluid from well

    head platform H5 to H1 Riser Base for commingling with H1 fluids and onwards to FPSO for

    stabilization and exporting, one 8 NPS pipeline is to transport water injection from well head

    platform H4 to H5 for reservoir pressure maintenance and one 6 NPS pipeline is to transport

    lift gas from H4 to H5 for gas lift application. It is preferred by COMPANY for subsea tie in

    for water injection at tie in spools adjacent to H4 platform.

    An overview of the Te Giac Trang Field Lay-out is shown in the Figure 1.2:

  • HLJOC/PTSC M&C PTSC POS/ TLO

    TGT FIELD DEVELOPMENT PROJECT

    PROVISION OF TRANSPORTATION AND INSTALLATION FOR WHP-H5 TOPSIDE AND PIPELINES

    Document No.:

    TGT-POS-S-H05-CA-0003 LOAD OUT PROCEDURE Page 5 of 10

    Revision No.: B0 Date: 09 May 15

    Figure 1.2: Te Giac Trang Field Lay-out

    1.2. Definitions

    Company Hoang Long Joint Operating Company (HLJOC)

    Contractor PTSC Offshore Services Joint Stock Co. (PTSC POS)

    1.3. Abbreviations

    API RP-2A-WSD Recommended Practice for Planning, Designing, and Constructing

    Fixed Offshore Platforms Working Stress Design

    ASTM-ASD Manual of Steel Construction Allowable Stress Design, 9th Edition,

    Jun 1989

    1.4. Reference Documents

    COMPANY DOCUMENTS

    No. Documents No. Rev Document Title

    1 TGT-N-H05-DW-1002 0 General Note & Drawing Index

    2 TGT-N-H05-DW-1003 0 TGT Field Layout Drawing

    3 TGT-N-H05-DW-1004 0 Platform Approach Drawing At H4-WHP

    4 TGT-N-H05-DW-1005 0 Platform Approach Drawing At H5-WHP

    5 TGT-N-H05-DW-1006 0 Platform Approach Drawing At H1-WHP

  • HLJOC/PTSC M&C PTSC POS/ TLO

    TGT FIELD DEVELOPMENT PROJECT

    PROVISION OF TRANSPORTATION AND INSTALLATION FOR WHP-H5 TOPSIDE AND PIPELINES

    Document No.:

    TGT-POS-S-H05-CA-0003 LOAD OUT PROCEDURE Page 6 of 10

    Revision No.: B0 Date: 09 May 15

    6 TGT-N-H05-DW-1010 0 Route Alignment Sheets - 12-Inch Production

    Pipeline No. 3

    7 TGT-N-H05-DW-1011 0 Route Alignment Sheets - 8-Inch Production Pipeline

    No. 2

    8 TGT-N-H05-DW-1012 0 Route Alignment Sheets - 6-Inch Production Pipeline

    No. 1

    9 TGT-N-H05-DW-1013 0 Inch Production Pipeline -Tie-In Spool General

    Arrangement at H5-WHP

    10 TGT-N-H05-DW-1014 0 12-Inch Production Pipeline -Tie-In Spool General

    Arrangement at H1-WHP

    11 TGT-N-H05-DW-1015 0 8-Inch Water Injection Pipeline Tie-In Spool General

    Arrangement at H4-WHP

    12 TGT-N-H05-DW-1016 0 8-Inch Water Injection Pipeline Tie-In Spool General

    Arrangement at H5-WHP

    13 TGT-N-H05-DW-1017 0 6-Inch Gas Lift Pipeline Tie-In Spool General

    Arrangement at H4-WHP

    14 TGT-N-H05-DW-1018 0 6-Inch Gas Lift Pipeline Tie-In Spool General

    Arrangement at H5-WHP

    15 TGT-N-H05-DW-1036 0 Flange Protector Details Drawing for 12 inches

    Production Flanges

    16 TGT-N-H05-DW-1051 0 Coating Cutback and Field Joint Coating Details

    Drawing

    17 TGT-S-H05-BOD-0001 0 H05 WHP Topsides Structural Basis of Design

  • HLJOC/PTSC M&C PTSC POS/ TLO

    TGT FIELD DEVELOPMENT PROJECT

    PROVISION OF TRANSPORTATION AND INSTALLATION FOR WHP-H5 TOPSIDE AND PIPELINES

    Document No.:

    TGT-POS-S-H05-CA-0003 LOAD OUT PROCEDURE Page 7 of 10

    Revision No.: B0 Date: 09 May 15

    CONSTRUCTOR DOCUMENT

    No. Documents No. Rev Document Title

    1 POS-H5-S-LA-SP-001 A Lifting Arrangement 01 For 12 Spool At H5

    2 POS-H5-S-LA-SP-002 A Lifting Arrangement 02 For 10 Spool At H1

    3 POS-H5-S-LA-SP-003 A Lifting Arrangement 03 For 8 Spool At H4

    4 POS-H5-S-LA-SP-004 A Lifting Arrangement 04 For 8 Spool At H4

    5 POS-H5-S-LA-SP-005 A Lifting Arrangement 05 For 8 Spool At H5

    6 POS-H5-S-LA-SP-006 A Lifting Arrangement 06 For 6 Spool At H4

    7 POS-H5-S-LA-SP-007 A Lifting Arrangement 07 For 6 Spool At H4

    8 POS-H5-S-LA-SP-008 A Lifting Arrangement 08 For 6 Spool At H5

    `

    MWS DOCUMENTS

    No. Documents No. Rev Document Title

    1 Load out 1 LOCG-GEN-Guideline-001

    1.5. Scope of Document

    The purpose of this document is to detail the step by step procedure for load out spools from

    site to vessel at PVC MS port. Total have 21 main part and some ben part of spool need load

    out, the parts have long smaller than 15 m no need check by software. Appendix 1 will details

    parts of spools.

    PART OF SPOOLS

    No. Descriptions Refer Drawing No.

    1 12 inch spool at H5 TGT-N-H05-DW-1014_0, POS-H5-S-LA-SP-001_A

    2 10 inch spool at H1 TGT-N-H05-DW-1014_0, POS-H5-S-LA-SP-002_A

    3 8 inch spool at H4 TGT-N-H05-DW-1015_0, POS-H5-S-LA-SP-003_A

    4 8 inch spool at H4 TGT-N-H05-DW-1015_0, POS-H5-S-LA-SP-004_A

    5 8 inch spool at H5 TGT-N-H05-DW-1016_0, POS-H5-S-LA-SP-005_A

  • HLJOC/PTSC M&C PTSC POS/ TLO

    TGT FIELD DEVELOPMENT PROJECT

    PROVISION OF TRANSPORTATION AND INSTALLATION FOR WHP-H5 TOPSIDE AND PIPELINES

    Document No.:

    TGT-POS-S-H05-CA-0003 LOAD OUT PROCEDURE Page 8 of 10

    Revision No.: B0 Date: 09 May 15

    PART OF SPOOLS

    No. Descriptions Refer Drawing No.

    6 6 inch spool at H4 TGT-N-H05-DW-1017_0, POS-H5-S-LA-SP-006_A

    7 6 inch spool at H4 TGT-N-H05-DW-1017_0, POS-H5-S-LA-SP-007_A

    8 6 inch spool at H5 TGT-N-H05-DW-1018_0, POS-H5-S-LA-SP-008_A

    2. LOAD OUT PROCEDURE

    2.1. Spools data

    Spools data were descripted details at Company documents. They include pipe 12 inch, 10

    inch, 8 inch, 6 inch with vary in long, vary in weight... Maximum weight (estimate 21 metric

    tons) is 12 inch spool at H5 platform.

    2.2. Procedure

    The spools fabrication will be done at site (PVC MS port) and will be loaded out to vessel by

    crane. Load out sequence for one spool table as below, other spools same it.

    STEP BY STEP

    No. Task Description Document

    Refer

    Rev

    1 Prepare lift area

    To clear all the equipment, cables, gas racks,

    lighting posts, materials near lifting area and

    in the way of the cranes.

    Double check lifting gear to make sure that they

    fully inspected according to the specification/

    code/ standard.

    Setting up working radius as per drawings

    Way of crane shall be marking exactly

    2 Lift spools from site to vessel by crane All document of

    company &

    Lastest

    3 Put spools to final design location at vessel by crane

  • HLJOC/PTSC M&C PTSC POS/ TLO

    TGT FIELD DEVELOPMENT PROJECT

    PROVISION OF TRANSPORTATION AND INSTALLATION FOR WHP-H5 TOPSIDE AND PIPELINES

    Document No.:

    TGT-POS-S-H05-CA-0003 LOAD OUT PROCEDURE Page 9 of 10

    Revision No.: B0 Date: 09 May 15

    4 Release lifting gear before lashing all spools for

    transportation

    constructor

    3. APPENDIX

    3.1. Lifting Analysis

  • HLJOC/PTSC M&C PTSC POS/ TLO

    TGT FIELD DEVELOPMENT PROJECT

    PROVISION OF TRANSPORTATION AND INSTALLATION FOR WHP-H5 TOPSIDE AND PIPELINES

    Document No.:

    TGT-POS-S-H05-CA-0003 SPOOLS LIFTING ANALYSIS Page 2 of 54

    Revision No.: B0 Date: 09 May 15

    Contents

    1. INTRODUCTION ...................................................................................................................................................... 3

    1.1. PROJECT DESCRIPTION ....................................................................................................................................... 3

    1.2. DEFINITIONS ............................................................................................................................................................ 5

    1.3. ABBREVIATIONS ..................................................................................................................................................... 5

    1.4. REFERENCE DOCUMENTS ................................................................................................................................... 5

    1.5. SCOPE OF DOCUMENT ......................................................................................................................................... 7

    2. ANALYSIS PROCEDURE AND ASSUMPTIONS ................................................................................................. 8

    2.1. PROCEDURE ............................................................................................................................................................. 8

    2.2. MODELING AND LOAD INPUT ............................................................................................................................ 8

    2.3. ANALYSIS LOADING CONDITIONS ................................................................................................................... 8

    2.4. DESIGN CODES, STANDARD AND SPECIFICATIONS .................................................................................... 8

    3. BASIS LOAD CASE AND COMBINATIONS ........................................................................................................ 9

    3.1 GRAVITY LOAD .............................................................................................................................................................. 9 3.2 DYNAMIC AMPLIFICATION FACTOR (DAF) ................................................................................................................... 11 3.3 SPOOLS LIFTING ANALYSIS FOR LOAD OUT CONDITION .................................................................................................. 11 3.4 LOAD COMBINATION MATRIX ...................................................................................................................................... 15

    4. ANALYSIS RESULTS ............................................................................................................................................. 16

    APPENDIX ........................................................................................................................................................................ 18

    APPENDIX 1: SACS MODEL INPUT FILE ...................................................................................................................... 19 APPENDIX 1.1: 12 SPOOL AT H5 MODEL ................................................................................................................... 20 APPENDIX 1.2: 10 SPOOL AT H1 MODEL ................................................................................................................... 24 APPENDIX 1.3: 8 SPOOL AT H4 MODEL ..................................................................................................................... 27 APPENDIX 1.4: 8 SPOOL AT H4 MODEL ..................................................................................................................... 30 APPENDIX 1.5: 8 SPOOL AT H5 MODEL ..................................................................................................................... 33 APPENDIX 1.6: 6 SPOOL AT H4 MODEL ..................................................................................................................... 37 APPENDIX 1.7: 6 SPOOL AT H4 MODEL ..................................................................................................................... 40 APPENDIX 1.8: 6 SPOOL AT H5 MODEL ..................................................................................................................... 43 APPENDIX 2: SACS OUTPUT FILE ................................................................................................................................. 46 APPENDIX 2.1: UC OF 12 SPOOL AT H5 ...................................................................................................................... 47 APPENDIX 2.2: UC OF 10 SPOOL AT H1 ...................................................................................................................... 48 APPENDIX 2.3: UC OF 8 SPOOL AT H4 ........................................................................................................................ 49 APPENDIX 2.4: UC OF 8 SPOOL AT H4 ........................................................................................................................ 50 APPENDIX 2.5: UC OF 8 SPOOL AT H5 ........................................................................................................................ 51 APPENDIX 2.6: UC OF 6 SPOOL AT H4 ........................................................................................................................ 52 APPENDIX 2.7: UC OF 6 SPOOL AT H4 ........................................................................................................................ 53 APPENDIX 2.8: UC OF 6 SPOOL AT H5 ........................................................................................................................ 54

  • HLJOC/PTSC M&C PTSC POS/ TLO

    TGT FIELD DEVELOPMENT PROJECT

    PROVISION OF TRANSPORTATION AND INSTALLATION FOR WHP-H5 TOPSIDE AND PIPELINES

    Document No.:

    TGT-POS-S-H05-CA-0003 SPOOLS LIFTING ANALYSIS Page 3 of 54

    Revision No.: B0 Date: 09 May 15

    1. INTRODUCTION

    1.1. Project Description

    The Te Giac Trang (TGT or White Rhinoceros) Field is located in the northern part of Block 16

    1, in the Cuu Long Basin offshore Vietnam, it is about 100km southeast of Vung Tau shore

    base, 20km northwest of the Bach Ho Field and 35km west of the Rang Dong Field.

    Figure 1.1: TGT Field Location Map

    TGT Field is divided into H1, H2, H3, H4 and H5 fault blocks. Hoang Long Joint Operating

    Company (HLJOC) has commenced production from TGT Oil Field since 2011. Currently, the

    field facilities of the TGT Field are summarized as follows:

    A 16 slot H1-WHP is located in a water depth of 43.0 m (LAT) over the H1.1, H1.2 and

    H2 areas;

    A 16 slot H4-WHP is located in a water depth of 44.77 m (LAT) and middle of the H4

    and H3N area;

    A leased FPSO Armada TGT1 is located approximately 2 km southeast of H1-WHP, in a

    water depth of 43.4 m (LAT);

    A PLEM and connect subsea pipelines including 4x10 multiphase flow lines, a 10

    water injection flow line and a 8 Gas-lift gas flow line between the H1-WHP and the

    FPSO;

    A 16 multiphase pipeline, a 8 water injection pipeline, a 6 gas-lift pipeline connecting

    H4-WHP to H1-WHP with a length of 7km each;

  • HLJOC/PTSC M&C PTSC POS/ TLO

    TGT FIELD DEVELOPMENT PROJECT

    PROVISION OF TRANSPORTATION AND INSTALLATION FOR WHP-H5 TOPSIDE AND PIPELINES

    Document No.:

    TGT-POS-S-H05-CA-0003 SPOOLS LIFTING ANALYSIS Page 4 of 54

    Revision No.: B0 Date: 09 May 15

    An SSIV and a 8 subsea gas export pipeline from the PLEM to the tie-in point with the

    12 Gas collection pipeline which is installed and operated by PetroVietnam Gas (PV

    Gas);

    The WHPs are normally unattended installations with independent power and control

    systems;

    There will be no processing on the WHPs, i.e. full well streams transferred to the FPSO

    Armada TGT1 for processing, storing and export;

    Oil export via by shuttle tanker.

    Well stream fluids from H4-WHP are transported to H1-WHP via an infield pipeline, and then

    commingled with well stream fluids from H1-WHP. Additionally, well stream fluids from Hai

    Su Trang (HST) / Hai Su Den (HSD) Fields, Block 15-2/01, adjacent to Block 16-1 is also tied-

    in H1-WHP. The commingled well stream fluids are sent to the FPSO for processing via four

    multiphase 10 flow lines. A leased FPSO Armada TGT1 provides all processing facilities,

    utilities and storage for export oil. The produced gas (less fuel gas) is exported to shore via 8

    subsea gas export pipeline and the newly installed 12 Gas collection pipeline tied in to

    existing STV-RD-BH pipeline. Injection water is supplied from the FPSO via a 10 carbon

    steel pipeline. The Gas-lift gas is also supplied from FPSO via an 8 carbon steel pipeline.

    Gas lift and water injection for HST/HSD Fields are also provided from FPSO via a gas lift and

    a water injection pipelines.

    The H5 project is an upstream project which includes a well head platform H5 and infield

    pipeline system. One insulated 12 NPS pipeline is to transport well stream fluid from well

    head platform H5 to H1 Riser Base for commingling with H1 fluids and onwards to FPSO for

    stabilization and exporting, one 8 NPS pipeline is to transport water injection from well head

    platform H4 to H5 for reservoir pressure maintenance and one 6 NPS pipeline is to transport

    lift gas from H4 to H5 for gas lift application. It is preferred by COMPANY for subsea tie in

    for water injection at tie in spools adjacent to H4 platform.

    An overview of the Te Giac Trang Field Lay-out is shown in the Figure 1.2:

  • HLJOC/PTSC M&C PTSC POS/ TLO

    TGT FIELD DEVELOPMENT PROJECT

    PROVISION OF TRANSPORTATION AND INSTALLATION FOR WHP-H5 TOPSIDE AND PIPELINES

    Document No.:

    TGT-POS-S-H05-CA-0003 SPOOLS LIFTING ANALYSIS Page 5 of 54

    Revision No.: B0 Date: 09 May 15

    Figure 1.2: Te Giac Trang Field Lay-out

    1.2. Definitions

    Company Hoang Long Joint Operating Company (HLJOC)

    Contractor PTSC Offshore Services Joint Stock Co. (PTSC POS)

    1.3. Abbreviations

    API RP-2A-WSD Recommended Practice for Planning, Designing, and Constructing

    Fixed Offshore Platforms Working Stress Design

    ASTM-ASD Manual of Steel Construction Allowable Stress Design, 9th Edition,

    Jun 1989

    1.4. Reference Documents

    COMPANY DOCUMENTS

    No. Documents No. Rev Document Title

    1 TGT-N-H05-DW-1002 0 General Note & Drawing Index

    2 TGT-N-H05-DW-1003 0 TGT Field Layout Drawing

    3 TGT-N-H05-DW-1004 0 Platform Approach Drawing At H4-WHP

    4 TGT-N-H05-DW-1005 0 Platform Approach Drawing At H5-WHP

    5 TGT-N-H05-DW-1006 0 Platform Approach Drawing At H1-WHP

  • HLJOC/PTSC M&C PTSC POS/ TLO

    TGT FIELD DEVELOPMENT PROJECT

    PROVISION OF TRANSPORTATION AND INSTALLATION FOR WHP-H5 TOPSIDE AND PIPELINES

    Document No.:

    TGT-POS-S-H05-CA-0003 SPOOLS LIFTING ANALYSIS Page 6 of 54

    Revision No.: B0 Date: 09 May 15

    6 TGT-N-H05-DW-1010 0 Route Alignment Sheets - 12-Inch Production

    Pipeline No. 3

    7 TGT-N-H05-DW-1011 0 Route Alignment Sheets - 8-Inch Production Pipeline

    No. 2

    8 TGT-N-H05-DW-1012 0 Route Alignment Sheets - 6-Inch Production Pipeline

    No. 1

    9 TGT-N-H05-DW-1013 0 Inch Production Pipeline -Tie-In Spool General

    Arrangement at H5-WHP

    10 TGT-N-H05-DW-1014 0 12-Inch Production Pipeline -Tie-In Spool General

    Arrangement at H1-WHP

    11 TGT-N-H05-DW-1015 0 8-Inch Water Injection Pipeline Tie-In Spool General

    Arrangement at H4-WHP

    12 TGT-N-H05-DW-1016 0 8-Inch Water Injection Pipeline Tie-In Spool General

    Arrangement at H5-WHP

    13 TGT-N-H05-DW-1017 0 6-Inch Gas Lift Pipeline Tie-In Spool General

    Arrangement at H4-WHP

    14 TGT-N-H05-DW-1018 0 6-Inch Gas Lift Pipeline Tie-In Spool General

    Arrangement at H5-WHP

    15 TGT-N-H05-DW-1036 0 Flange Protector Details Drawing for 12 inches

    Production Flanges

    16 TGT-N-H05-DW-1051 0 Coating Cutback and Field Joint Coating Details

    Drawing

    17 TGT-S-H05-BOD-0001 0 H05 WHP Topsides Structural Basis of Design

  • HLJOC/PTSC M&C PTSC POS/ TLO

    TGT FIELD DEVELOPMENT PROJECT

    PROVISION OF TRANSPORTATION AND INSTALLATION FOR WHP-H5 TOPSIDE AND PIPELINES

    Document No.:

    TGT-POS-S-H05-CA-0003 SPOOLS LIFTING ANALYSIS Page 7 of 54

    Revision No.: B0 Date: 09 May 15

    CONSTRUCTOR DOCUMENTS

    No. Document No. Rev. Document Title

    1 POS-H5-S-LA-SP-001 B0 Lifting Arrangement 01 For 12 Spool At H5

    2 POS-H5-S-LA-SP-002 B0 Lifting Arrangement 02 For 10 Spool At H1

    3 POS-H5-S-LA-SP-003 B0 Lifting Arrangement 03 For 8 Spool At H4

    4 POS-H5-S-LA-SP-004 B0 Lifting Arrangement 04 For 8 Spool At H4

    5 POS-H5-S-LA-SP-005 B0 Lifting Arrangement 05 For 8 Spool At H5

    6 POS-H5-S-LA-SP-006 B0 Lifting Arrangement 06 For 6 Spool At H4

    7 POS-H5-S-LA-SP-007 B0 Lifting Arrangement 07 For 6 Spool At H4

    8 POS-H5-S-LA-SP-008 B0 Lifting Arrangement 08 For 6 Spool At H5

    1.5. Scope of Document

    This report documents the lifting analysis for the details engineering design of TGT-H5

    Topside and Pipeline T&I. The following lifting calculations were performed for part of

    Spools with long dimension more than 15m. With part of Spools smaller than 15m no need

    recheck by SACS Software.

    PART OF SPOOLS

    No. Descriptions Referent Drawings No.

    1 12 inch spool at H5 TGT-N-H05-DW-1014, POS-H5-S-LA-SP-001.

    2 10 inch spool at H1 TGT-N-H05-DW-1014, POS-H5-S-LA-SP-002.

    3 8 inch spool at H4 TGT-N-H05-DW-1015, POS-H5-S-LA-SP-003.

    4 8 inch spool at H4 TGT-N-H05-DW-1015, POS-H5-S-LA-SP-004.

    5 8 inch spool at H5 TGT-N-H05-DW-1016, POS-H5-S-LA-SP-005.

    6 6 inch spool at H4 TGT-N-H05-DW-1017, POS-H5-S-LA-SP-006.

    7 6 inch spool at H4 TGT-N-H05-DW-1017, POS-H5-S-LA-SP-007.

    8 6 inch spool at H5 TGT-N-H05-DW-1018, POS-H5-S-LA-SP-008.

  • HLJOC/PTSC M&C PTSC POS/ TLO

    TGT FIELD DEVELOPMENT PROJECT

    PROVISION OF TRANSPORTATION AND INSTALLATION FOR WHP-H5 TOPSIDE AND PIPELINES

    Document No.:

    TGT-POS-S-H05-CA-0003 SPOOLS LIFTING ANALYSIS Page 8 of 54

    Revision No.: B0 Date: 09 May 15

    2. ANALYSIS PROCEDURE AND ASSUMPTIONS

    2.1. Procedure

    The analysis was carried out based on the following steps:

    Structural model and simulation of structural behavior.

    Loads and simulation of load effects.

    Load combinations.

    Joint and member checks in accordance with relevant design codes.

    The software used for the analysis is SACS Program Version 5.6.

    2.2. Modeling and Load input

    The SACS models used for Spools lifting analysis is molded by SACS software. The model

    thus consists of the following main components:

    Part of spool 12, 10, 8, 6 at H5, H4, H1 Well Head Platform.

    A hook point shall be created above the COG, with the longest sling making a minimum 60

    degrees sling angle to horizontal plane.

    2.3. Analysis Loading Conditions

    Two one loading conditions are considered for the analysis, as follows:

    1) One hook analysis, connected to padeye (with DAF of 2.00 for members)

    2) One hook analysis, not connected to padeye (with DAF of 1.35 for members)

    to differentiate results between different DAF.

    2.4. Design Codes, Standard and Specifications

    The structure is designed to satisfy the Working Stress Design (WSD) requirements and is

    performed in accordance with the following:

    No. Document No. Document Title

    1 API RP-2A-WSD, 21

    st Edition,

    Dec 2000

    Recommended Practice for Planning,

    Designing, and Constructing Fixed Offshore

    Platforms Working Stress Design

    2 AISC Manual of Steel

    Construction Allowable Stress

    Design, 9th Edition, Jun 1989

    Specification for Structural Steel Building

    Allowable Stress Design and Plastic Design

  • HLJOC/PTSC M&C PTSC POS/ TLO

    TGT FIELD DEVELOPMENT PROJECT

    PROVISION OF TRANSPORTATION AND INSTALLATION FOR WHP-H5 TOPSIDE AND PIPELINES

    Document No.:

    TGT-POS-S-H05-CA-0003 SPOOLS LIFTING ANALYSIS Page 9 of 54

    Revision No.: B0 Date: 09 May 15

    3. BASIS LOAD CASE AND COMBINATIONS

    3.1 Gravity Load

    Basic gravity load cases for part of Spools analysis are tabulated in table below. Rigging load is

    adopted from the drawings POS-H5-S-LA-SP-001, POS-H5-S-LA-SP-002, POS-H5-S-LA-SP-

    003, POS-H5-S-LA-SP-004, POS-H5-S-LA-SP-005, POS-H5-S-LA-SP-006, POS-H5-S-LA-

    SP-007, POS-H5-S-LA-SP-008.

    Table 3.1: Gravity Load Cases of a part spool 12 at H5

    No. LC Description Fz (kN) Contingency Fz (kN)

    1

    1 Computer Generated Self-weight -67.11 1.15 -77.81

    2 Appurtenances -102.34 1.15 -117.69

    3 Rigging Weight -2.50 1.00 -2.50

    Subtotal -197.4

    Table 3.2: Gravity Load Cases of a part spool 10 at H1

    No. LC Description Fz (kN) Contingency Fz (kN)

    2

    1 Computer Generated Self-weight -52.20 1.15 -60.03

    2 Appurtenances -9.85 1.15 -11.31

    3 Rigging Weight -2.00 1.00 -2.00

    Subtotal -73.36

    Table 3.3: Gravity Load Cases of a part spool 8 at H4

    No. LC Description Fz (kN) Contingency Fz (kN)

    3

    1 Computer Generated Self-weight -37.30 1.15 -42.91

    2 Appurtenances -24.88 1.15 -28.61

    3 Rigging Weight -2.00 1.00 -2.00

    Subtotal -73.51

  • HLJOC/PTSC M&C PTSC POS/ TLO

    TGT FIELD DEVELOPMENT PROJECT

    PROVISION OF TRANSPORTATION AND INSTALLATION FOR WHP-H5 TOPSIDE AND PIPELINES

    Document No.:

    TGT-POS-S-H05-CA-0003 SPOOLS LIFTING ANALYSIS Page 10 of 54

    Revision No.: B0 Date: 09 May 15

    Table 3.4: Gravity Load Cases of a part spool 8 at H4

    No. LC Description Fz (kN) Contingency Fz (kN)

    4

    1 Computer Generated Self-weight -34.71 1.15 -39.92

    2 Appurtenances -16.90 1.15 -19.44

    3 Rigging Weight -2.00 1.00 -2.00

    Subtotal -61.36

    Table 3.5: Gravity Load Cases of a part spool 8 at H5

    No. LC Description Fz (kN) Contingency Fz (kN)

    5

    1 Computer Generated Self-weight -60.17 1.15 -69.20

    2 Appurtenances -40.11 1.15 -46.15

    3 Rigging Weight -2.00 1.00 -2.00

    Subtotal -117.32

    Table 3.6: Gravity Load Cases of a part spool 6 at H4

    No. LC Description Fz (kN) Contingency Fz (kN)

    6

    1 Computer Generated Self-weight -25.59 1.15 -29.43

    2 Appurtenances -23.31 1.15 -26.81

    3 Rigging Weight -2.00 1.00 -2.00

    Subtotal -58.23

    Table 3.7: Gravity Load Cases of a part spool 6 at H4

    No. LC Description Fz (kN) Contingency Fz (kN)

    7

    1 Computer Generated Self-weight -27.87 1.15 -32.05

    2 Appurtenances -26.61 1.15 -30.60

    3 Rigging Weight -2.00 1.00 -2.00

    Subtotal -64.66

  • HLJOC/PTSC M&C PTSC POS/ TLO

    TGT FIELD DEVELOPMENT PROJECT

    PROVISION OF TRANSPORTATION AND INSTALLATION FOR WHP-H5 TOPSIDE AND PIPELINES

    Document No.:

    TGT-POS-S-H05-CA-0003 SPOOLS LIFTING ANALYSIS Page 11 of 54

    Revision No.: B0 Date: 09 May 15

    Table 3.8: Gravity Load Cases of a part spool 6 at H5

    No. LC Description Fz (kN) Contingency Fz (kN)

    8

    1 Computer Generated Self-weight -30.34 1.15 -34.89

    2 Appurtenances -22.97 1.15 -26.42

    3 Rigging Weight -2.00 1.00 -2.00

    Subtotal -63.31

    3.2 Dynamic Amplification Factor (DAF)

    Dynamic amplification factor (DAF) of 1.35 and 2.00 shall be applied to the factored lift

    weight. Structural members attached directly to the pad eye will be designed against DAF of

    2.00 while other structural members will only be checked against DAF of 1.35.

    3.3 Spools lifting analysis for load out condition

    The lifting analysis for spools was has two slings lifting arrangement will be used. Appendix 1

    is detailed SACS input file. The lifting analysis model is showed follow figure.

    Figure 3.1: 12 Spool At H5 Lift Configuration

  • HLJOC/PTSC M&C PTSC POS/ TLO

    TGT FIELD DEVELOPMENT PROJECT

    PROVISION OF TRANSPORTATION AND INSTALLATION FOR WHP-H5 TOPSIDE AND PIPELINES

    Document No.:

    TGT-POS-S-H05-CA-0003 SPOOLS LIFTING ANALYSIS Page 12 of 54

    Revision No.: B0 Date: 09 May 15

    Figure 3.2: 10 Spool At H1 Lift Configuration

    Figure 3.3: 8 Spool At H4 Lift Configuration

  • HLJOC/PTSC M&C PTSC POS/ TLO

    TGT FIELD DEVELOPMENT PROJECT

    PROVISION OF TRANSPORTATION AND INSTALLATION FOR WHP-H5 TOPSIDE AND PIPELINES

    Document No.:

    TGT-POS-S-H05-CA-0003 SPOOLS LIFTING ANALYSIS Page 13 of 54

    Revision No.: B0 Date: 09 May 15

    Figure 3.4: 8 Spool At H4 Lift Configuration

    Figure 3.5: 8 Spool At H5 Lift Configuration

  • HLJOC/PTSC M&C PTSC POS/ TLO

    TGT FIELD DEVELOPMENT PROJECT

    PROVISION OF TRANSPORTATION AND INSTALLATION FOR WHP-H5 TOPSIDE AND PIPELINES

    Document No.:

    TGT-POS-S-H05-CA-0003 SPOOLS LIFTING ANALYSIS Page 14 of 54

    Revision No.: B0 Date: 09 May 15

    Figure 3.6: 6 Spool At H4 Lift Configuration

    Figure 3.7: 6 Spool At H4 Lift Configuration

  • HLJOC/PTSC M&C PTSC POS/ TLO

    TGT FIELD DEVELOPMENT PROJECT

    PROVISION OF TRANSPORTATION AND INSTALLATION FOR WHP-H5 TOPSIDE AND PIPELINES

    Document No.:

    TGT-POS-S-H05-CA-0003 SPOOLS LIFTING ANALYSIS Page 15 of 54

    Revision No.: B0 Date: 09 May 15

    Figure 3.8: 6 Spool At H5 Lift Configuration

    3.4 Load Combination Matrix

    Table 3.3: Load Combination for Lifting Analysis

    Basic Load Case Load Combinations for Lifting Analysis

    BC 1.35 2.00

    1 Computer Generated Self-weight 1.150 1.5525 2.300

    2 Appurtenances Weight 1.150 1.5525 2.300

    3 Rigging Weight 1.000 1.3500 2.000

  • HLJOC/PTSC M&C PTSC POS/ TLO

    TGT FIELD DEVELOPMENT PROJECT

    PROVISION OF TRANSPORTATION AND INSTALLATION FOR WHP-H5 TOPSIDE AND PIPELINES

    Document No.:

    TGT-POS-S-H05-CA-0003 SPOOLS LIFTING ANALYSIS Page 16 of 54

    Revision No.: B0 Date: 09 May 15

    4. ANALYSIS RESULTS

    The analysis results indicate that the spools structure is adequately designed for onshore. Unity

    checks (UC) for all members are below 1.00. A summary of results are given in Table 4.1; 4.2;

    4.3; 4.4; see Appendix 2 for more details.

    Table 4.1: Maximum Sling Forces

    No. Description Sling Member LOAD CASE

    BC (kN) DAF 1.35 (kN) DAF 2.00 (kN)

    1 12 spool at H5 0017-SL01 60.2 81.3 120.4

    0016-SL02 49.6 67.0 99.2

    2 10 spool at H1 SL01-HOOK 41.6 56.2 83.2

    0004-SL01 24.8 33.5 49.6

    3 8 spool at H4 SL01-HOOK 42.6 57.5 85.2

    0008-SL01 26.2 35.4 52.4

    4 8 spool at H4 SL01-HOOK 37.9 51.2 75.8

    0014-SL01 18.5 25.0 37.0

    5 8 spool at H5 SL02-HOOK 72.1 97.3 144.2

    0013-SL02 34.6 46.7 69.2

    6 6 spool at H4 SL01-HOOK 35.4 47.8 70.8

    SL08-SL01 21.0 28.4 42.0

    7 6 spool at H4 SL01-HOOK 38.2 51.6 76.4

    0009-SL02 29.1 39.3 58.2

    8 6 spool at H5 SL02-HOOK 37.3 50.4 74.6

    SL02-SL07 18.2 24.6 36.4

    Table 4.2: Maximum Joint Unity Check Of Spool

    No. Description Member No. Description Group Member Max. UC

    Load Case UC

    1 12 spool at H5 0004-0005 323.9 x 20.6 324 2.00 0.08

    0002-0010 323.9 x 20.6 324 2.00 0.08

    2 10 spool at H1 0000-1005 273.1 x 20.6 273 2.00 0.06

    0000-1007 273.1 x 20.6 273 2.00 0.05

    3 8 spool at H4 0001-0008 219.1 x 20.6 219 2.00 0.04

    0002-0003 219.1 x 20.6 219 2.00 0.03

    4 8 spool at H4 0003-0004 219.1 x 20.6 219 2.00 0.05

    0004-0005 219.1 x 20.6 219 2.00 0.05

    5 8 spool at H5 0004-0005 219.1 x 20.6 219 2.00 0.10

    0005-0006 219.1 x 20.6 219 2.00 0.10

    6 6 spool at H4 0003-SL08 168.3 x 12.7 168 2.00 0.23

  • HLJOC/PTSC M&C PTSC POS/ TLO

    TGT FIELD DEVELOPMENT PROJECT

    PROVISION OF TRANSPORTATION AND INSTALLATION FOR WHP-H5 TOPSIDE AND PIPELINES

    Document No.:

    TGT-POS-S-H05-CA-0003 SPOOLS LIFTING ANALYSIS Page 17 of 54

    Revision No.: B0 Date: 09 May 15

    No. Description Member No. Description Group Member Max. UC

    Load Case UC

    0002-SL06 168.3 x 12.7 168 2.00 0.12

    7 6 spool at H4 0002-0009 168.3 x 12.7 168 2.00 0.26

    0003-SL06 168.3 x 12.7 168 2.00 0.21

    8 6 spool at H5 0006-SL07 168.3 x 12.7 168 2.00 0.10

    0006-0007 168.3 x 12.7 168 2.00 0.09

  • HLJOC/PTSC M&C PTSC POS/ TLO

    TGT FIELD DEVELOPMENT PROJECT

    PROVISION OF TRANSPORTATION AND INSTALLATION FOR WHP-H5 TOPSIDE AND PIPELINES

    Document No.:

    TGT-POS-S-H05-CA-0003 SPOOLS LIFTING ANALYSIS Page 18 of 54

    Revision No.: B0 Date: 09 May 15

    APPENDIX

  • HLJOC/PTSC M&C PTSC POS/ TLO

    TGT FIELD DEVELOPMENT PROJECT

    PROVISION OF TRANSPORTATION AND INSTALLATION FOR WHP-H5 TOPSIDE AND PIPELINES

    Document No.:

    TGT-POS-S-H05-CA-0003 SPOOLS LIFTING ANALYSIS Page 19 of 54

    Revision No.: B0 Date: 09 May 15

    APPENDIX 1: SACS MODEL INPUT FILE

    (27 pages)

  • HLJOC/PTSC M&C PTSC POS/ TLO

    TGT FIELD DEVELOPMENT PROJECT

    PROVISION OF TRANSPORTATION AND INSTALLATION FOR WHP-H5 TOPSIDE AND PIPELINES

    Document No.:

    TGT-POS-S-H05-CA-0003 SPOOLS LIFTING ANALYSIS Page 20 of 54

    Revision No.: B0 Date: 09 May 15

    APPENDIX 1.1: 12 SPOOL AT H5 MODEL

    (04 pages)

  • HLJOC/PTSC M&C PTSC POS/ TLO

    TGT FIELD DEVELOPMENT PROJECT

    PROVISION OF TRANSPORTATION AND INSTALLATION FOR WHP-H5 TOPSIDE AND PIPELINES

    Document No.:

    TGT-POS-S-H05-CA-0003 SPOOLS LIFTING ANALYSIS Page 21 of 54

    Revision No.: B0 Date: 09 May 15

    LDOPT NF+Z1.0250007.850000 GLOBMN CMB

    ****************************************************************************

    ******************TE GIAC TRANG FILED DEVELOPMENT PROJECT*******************

    **************PROVISION OF TRANSPORTATION AND INSTALLATION FOR**************

    ***********************WHP-H5 TOPSIDE AND PIPELINES*************************

    ****************************************************************************

    OPTIONS MN 1 1

    SECT

    SECT 323.9 TUB 32.3902.060

    GRUP

    GRUP 324 323.9 20.008.000450.0 1 1.001.00 0.500 7.8500

    GRUP SLI 5.000 2.490 20.008.00024.80 1 1.001.00 0.500 7.8500

    GRUP SPR 16.830 1.270 20.008.00024.80 1 1.001.00 0.500 7.8500

    MEMBER

    MEMBER 00000001 324

    MEMBER 00010002 324

    MEMBER 00020003 324

    MEMBER 00030004 324

    MEMBER 00040005 324

    MEMBER 00050006 324

    MEMBER 00060017 324

    MEMBER 00070008 324

    MEMBER 00080018 324

    MEMBER 00090010 324

    MEMBER 00110013 324

    MEMBER 00120007 324

    MEMBER 00130012 324

    MEMBER 00140011 324

    MEMBER 00150016 324

    MEMBER 00160009 324

    MEMBER 00170014 324

    MEMBER 00180019 324

    MEMBER 00190015 324

    MEMBER 0002SL01 SLI T

    MEMBER 0005SL01 SLI T

    MEMBER 0016SL02 SLI T

    MEMBER 0017SL01 SLI T

    MEMBER 0018SL02 SLI T

    JOINT

    JOINT 0000 -13. 10. 1. -1.100 73.000 15.800

    JOINT 0001 -11. 10. 1.-74.600 73.000 15.800

    JOINT 0002 -9. 10. 0.-52.900 73.000 -7.000

    JOINT 0003 -8. 10. 0.-12.500 73.000 -7.000 110000

    JOINT 0003 10.000 10.000 ELASTI

    JOINT 0004 -3. 10. 0.-63.000 73.000 -7.000

    JOINT 0005 -1. 10. 0.-41.001 73.000 -7.000

    JOINT 0006 0. 7. 0.-66.977 96.745 -7.000

    JOINT 0007 2. -2. 0. 19.277-71.569 -7.000 110000

    JOINT 0007 10.000 10.000 ELASTI

    JOINT 0008 2. -3. 0. 46.711-73.957 -7.000

    JOINT 0009 5. -14. 0. 32.965-42.271 -7.000 110000

    JOINT 0009 10.000 10.000 ELASTI

    JOINT 0010 5. -15. 0. 64.981-61.756 -7.000

    JOINT 0011 0. 2. 0. 76.150 62.588 -7.000 110000

    JOINT 0011 10.000 10.000 ELASTI

    JOINT 0012 1. 1. 0. 2.032 65.995 -7.000

  • HLJOC/PTSC M&C PTSC POS/ TLO

    TGT FIELD DEVELOPMENT PROJECT

    PROVISION OF TRANSPORTATION AND INSTALLATION FOR WHP-H5 TOPSIDE AND PIPELINES

    Document No.:

    TGT-POS-S-H05-CA-0003 SPOOLS LIFTING ANALYSIS Page 22 of 54

    Revision No.: B0 Date: 09 May 15

    JOINT 0013 0. 2. 0. 89.091 14.291 -7.000

    JOINT 0014 0. 3. 0. 63.209 10.884 -7.000

    JOINT 0015 4. -11. 0. 63.084-81.471 -7.000

    JOINT 0016 4. -13. 0. 98.025-11.871 -7.000

    JOINT 0017 0. 4. 0. 37.328 7.477 -7.000

    JOINT 0018 2. -4. 0. 72.593-70.550 -7.000

    JOINT 0019 2. -5. 0. 98.475-67.142 -7.000

    JOINT SL01 -2. 6. 9.-91.527 69.735 FIXED

    JOINT SL02 2. -8. 9. 99.912-27.741 FIXED

    LOAD

    LOADCN 1

    LOADLB1 COMPUTER GENERATED SELFWEIGHT

    DEAD

    DEAD -Z M

    LOADCN 2

    LOAD Z 00000001 -0.1200 -0.1200 GLOB UNIF 3PUF

    LOAD Z 00010002 -0.1200 -0.1200 GLOB UNIF 3PUF

    LOAD Z 00020003 -0.1200 -0.1200 GLOB UNIF 3PUF

    LOAD Z 00030004 -0.1200 -0.1200 GLOB UNIF 3PUF

    LOAD Z 00040005 -0.1200 -0.1200 GLOB UNIF 3PUF

    LOAD Z 00050006 -0.1200 -0.1200 GLOB UNIF 3PUF

    LOAD Z 00070008 -0.1200 -0.1200 GLOB UNIF 3PUF

    LOAD Z 00090010 -0.1200 -0.1200 GLOB UNIF 3PUF

    LOAD Z 00030004 -3.3100 -3.3100 GLOB UNIF CONCRETE

    LOAD 0010 -4.7700 GLOB JOIN FLANGE

    LOAD 0000 -4.7700 GLOB JOIN FLANGE

    LOAD Z 00120007 -0.1200 -0.1200 GLOB UNIF 3PUF

    LOAD Z 00120007 -3.3100 -3.3100 GLOB UNIF CONCRETE

    LOAD Z 00110013 -0.1200 -0.1200 GLOB UNIF 3PUF

    LOAD Z 00110013 -3.3100 -3.3100 GLOB UNIF CONCRETE

    LOAD Z 00130012 -0.1200 -0.1200 GLOB UNIF 3PUF

    LOAD Z 00130012 -3.3100 -3.3100 GLOB UNIF CONCRETE

    LOAD Z 00140011 -0.1200 -0.1200 GLOB UNIF 3PUF

    LOAD Z 00140011 -3.3100 -3.3100 GLOB UNIF CONCRETE

    LOAD Z 00150016 -0.1200 -0.1200 GLOB UNIF 3PUF

    LOAD Z 00150016 -3.3100 -3.3100 GLOB UNIF CONCRETE

    LOAD Z 00160009 -0.1200 -0.1200 GLOB UNIF 3PUF

    LOAD Z 00160009 -3.3100 -3.3100 GLOB UNIF CONCRETE

    LOAD Z 00060017 -0.1200 -0.1200 GLOB UNIF 3PUF

    LOAD Z 00060017 -3.3100 -3.3100 GLOB UNIF CONCRETE

    LOAD Z 00170014 -0.1200 -0.1200 GLOB UNIF 3PUF

    LOAD Z 00170014 -3.3100 -3.3100 GLOB UNIF CONCRETE

    LOAD Z 00080018 -0.1200 -0.1200 GLOB UNIF 3PUF

    LOAD Z 00080018 -3.3100 -3.3100 GLOB UNIF CONCRETE

    LOAD Z 00180019 -0.1200 -0.1200 GLOB UNIF 3PUF

    LOAD Z 00180019 -3.3100 -3.3100 GLOB UNIF CONCRETE

    LOAD Z 00190015 -0.1200 -0.1200 GLOB UNIF 3PUF

    LOAD Z 00190015 -3.3100 -3.3100 GLOB UNIF CONCRETE

    LOADCN 3

    LOAD 0002 -0.5000 GLOB JOIN RIGGING

    LOAD 0005 -0.5000 GLOB JOIN RIGGING

    LOAD 0017 -0.5000 GLOB JOIN RIGGING

    LOAD 0018 -0.5000 GLOB JOIN RIGGING

    LOAD 0016 -0.5000 GLOB JOIN RIGGING

    LCOMB

    LCOMB BC 11.1500 21.1500 3 1.

  • HLJOC/PTSC M&C PTSC POS/ TLO

    TGT FIELD DEVELOPMENT PROJECT

    PROVISION OF TRANSPORTATION AND INSTALLATION FOR WHP-H5 TOPSIDE AND PIPELINES

    Document No.:

    TGT-POS-S-H05-CA-0003 SPOOLS LIFTING ANALYSIS Page 23 of 54

    Revision No.: B0 Date: 09 May 15

    LCOMB 1.35 BC 1.3500

    LCOMB 2.00 BC 2.0000

    END

  • HLJOC/PTSC M&C PTSC POS/ TLO

    TGT FIELD DEVELOPMENT PROJECT

    PROVISION OF TRANSPORTATION AND INSTALLATION FOR WHP-H5 TOPSIDE AND PIPELINES

    Document No.:

    TGT-POS-S-H05-CA-0003 SPOOLS LIFTING ANALYSIS Page 24 of 54

    Revision No.: B0 Date: 09 May 15

    APPENDIX 1.2: 10 SPOOL AT H1 MODEL

    (03 pages)

  • HLJOC/PTSC M&C PTSC POS/ TLO

    TGT FIELD DEVELOPMENT PROJECT

    PROVISION OF TRANSPORTATION AND INSTALLATION FOR WHP-H5 TOPSIDE AND PIPELINES

    Document No.:

    TGT-POS-S-H05-CA-0003 SPOOLS LIFTING ANALYSIS Page 25 of 54

    Revision No.: B0 Date: 09 May 15

    LDOPT NF+Z1.0250007.850000 GLOBMN CMB

    ****************************************************************************

    ******************TE GIAC TRANG FILED DEVELOPMENT PROJECT*******************

    **************PROVISION OF TRANSPORTATION AND INSTALLATION FOR**************

    ***********************WHP-H5 TOPSIDE AND PIPELINES*************************

    ****************************************************************************

    OPTIONS MN 1 1

    SECT

    SECT 273 TUB 27.3102.060

    GRUP

    GRUP 273 273 20.008.000450.0 1 1.001.00 0.500 7.8490

    GRUP SLI 5.000 2.490 20.008.00024.80 1 1.001.00 0.500 7.8500

    GRUP SPR 16.830 1.270 20.008.00024.80 1 1.001.00 0.500 7.8500

    MEMBER

    MEMBER 00001005 273

    MEMBER 00021006 273

    MEMBER 00040003 273

    MEMBER 00040005 273

    MEMBER 10050004 273

    MEMBER 10061007 273

    MEMBER 10070000 273

    MEMBER 0004SL01 SLI T

    MEMBER 1005SL01 SLI T

    MEMBER 1006SL02 SLI T

    MEMBER 1007SL02 SLI T

    MEMBER SL01HOOK SLI T

    MEMBER SL02HOOK SLI T

    MEMBER COG SL01 SPR

    MEMBER 1003SL02 SPR

    MEMBER SL011002 SPR

    MEMBER SL02COG SPR

    JOINT

    JOINT COG 6. 2. 11. 53.000 96.000

    JOINT 0000 0. 0. 0.

    JOINT 0002 0. 11. 0. 97.100

    JOINT 0003 18. 0. 0. 7.330

    JOINT 0004 14. 0. 0. 84.530 110000

    JOINT 0004 10.000 10.000 ELASTI

    JOINT 0005 13. 0. 1. 29.430 6.700

    JOINT 1002 9. 1. 11. 37.542 92.436

    JOINT 1003 3. 3. 11. 68.465 99.564

    JOINT 1005 8. 0. 0. 84.530 110000

    JOINT 1005 10.000 10.000 ELASTI

    JOINT 1006 0. 8. 0. 50.000 110000

    JOINT 1006 10.000 10.000 ELASTI

    JOINT 1007 0. 1. 0. 50.000 110000

    JOINT 1007 10.000 10.000 ELASTI

    JOINT HOOK 6. 2. 16. 53.000 96.000 50.000 FIXED

    JOINT SL01 9. 2. 11. 15.930 0.302 110000

    JOINT SL02 3. 3. 11. 90.079 91.698 110000

    LOAD

    LOADCN 1

    LOADLB1 COMPUTER GENERATED SELFWEIGHT

    DEAD

    DEAD -Z M

    LOADCN 2

  • HLJOC/PTSC M&C PTSC POS/ TLO

    TGT FIELD DEVELOPMENT PROJECT

    PROVISION OF TRANSPORTATION AND INSTALLATION FOR WHP-H5 TOPSIDE AND PIPELINES

    Document No.:

    TGT-POS-S-H05-CA-0003 SPOOLS LIFTING ANALYSIS Page 26 of 54

    Revision No.: B0 Date: 09 May 15

    LOAD 0002 -4.7670 GLOB JOIN FLANGE

    LOAD 0003 -4.7670 GLOB JOIN FLANGE

    LOAD Z 00040003 -0.0100 -0.0100 GLOB UNIF 3PUF

    LOAD Z 00040005 -0.0100 -0.0100 GLOB UNIF 3PUF

    LOAD Z 00001005 -0.0100 -0.0100 GLOB UNIF 3PUF

    LOAD Z 10050004 -0.0100 -0.0100 GLOB UNIF 3PUF

    LOAD Z 00021006 -0.0100 -0.0100 GLOB UNIF 3PUF

    LOAD Z 10061007 -0.0100 -0.0100 GLOB UNIF 3PUF

    LOAD Z 10070000 -0.0100 -0.0100 GLOB UNIF 3PUF

    LOADCN 3

    LOAD 1007 -0.5000 GLOB JOIN RIGGING

    LOAD 1006 -0.5000 GLOB JOIN RIGGING

    LOAD 1005 -0.5000 GLOB JOIN RIGGING

    LOAD 0004 -0.5000 GLOB JOIN RIGGING

    LCOMB

    LCOMB BC 11.1500 21.1500 3 1.

    LCOMB 1.35 BC 1.3500

    LCOMB 2.00 BC 2.0000

    END

  • HLJOC/PTSC M&C PTSC POS/ TLO

    TGT FIELD DEVELOPMENT PROJECT

    PROVISION OF TRANSPORTATION AND INSTALLATION FOR WHP-H5 TOPSIDE AND PIPELINES

    Document No.:

    TGT-POS-S-H05-CA-0003 SPOOLS LIFTING ANALYSIS Page 27 of 54

    Revision No.: B0 Date: 09 May 15

    APPENDIX 1.3: 8 SPOOL AT H4 MODEL

    (03 pages)

  • HLJOC/PTSC M&C PTSC POS/ TLO

    TGT FIELD DEVELOPMENT PROJECT

    PROVISION OF TRANSPORTATION AND INSTALLATION FOR WHP-H5 TOPSIDE AND PIPELINES

    Document No.:

    TGT-POS-S-H05-CA-0003 SPOOLS LIFTING ANALYSIS Page 28 of 54

    Revision No.: B0 Date: 09 May 15

    LDOPT NF+Z1.0250007.850000 GLOBMN CMB

    ****************************************************************************

    ******************TE GIAC TRANG FILED DEVELOPMENT PROJECT*******************

    **************PROVISION OF TRANSPORTATION AND INSTALLATION FOR**************

    ***********************WHP-H5 TOPSIDE AND PIPELINES*************************

    ****************************************************************************

    OPTIONS MN 1 1

    SECT

    SECT 219.1 TUB 21.9102.060

    GRUP

    GRUP 219 219.1 20.008.000450.0 1 1.001.00 0.500 7.8490

    GRUP SLI 5.000 2.490 20.008.00024.80 1 1.001.00 0.500 7.8500

    GRUP SPR 16.830 1.270 20.008.00024.80 1 1.001.00 0.500 7.8500

    MEMBER

    MEMBER 00010008 219

    MEMBER 00020003 219

    MEMBER 00030006 219

    MEMBER 00040005 219

    MEMBER 00050002 219

    MEMBER 00060007 219

    MEMBER 00070010 219

    MEMBER 00080009 219

    MEMBER 00090000 219

    MEMBER 00100001 219

    MEMBER 0001SL01 SLI T

    MEMBER 0003SL02 SLI T

    MEMBER 0005SL02 SLI T

    MEMBER 0008SL01 SLI T

    MEMBER SL01HOOK SLI T

    MEMBER SL02HOOK SLI T

    MEMBER COG SL01 SPR

    MEMBER SL01SL03 SPR

    MEMBER SL02COG SPR

    MEMBER SL04SL02 SPR

    JOINT

    JOINT COG 14. 0. 6. 69.000-13.000

    JOINT 0000 26. 0. 1. 88.601 49.500

    JOINT 0001 19. 0. 0. 7.000 110000

    JOINT 0001 100.000100.000 ELASTI

    JOINT 0002 6. 0. 0. 84.200

    JOINT 0003 9. 0. 0. 22.950 110000

    JOINT 0003 100.000100.000 ELASTI

    JOINT 0004 0. 0. 0. -0.001

    JOINT 0005 2. 0. 0. 6.700 110000

    JOINT 0005 100.000100.000 ELASTI

    JOINT 0006 11. 0. 0. 61.700

    JOINT 0007 13. 0. 0. 42.000

    JOINT 0008 24. 0. 0. 72.000 110000

    JOINT 0008 100.000100.000 ELASTI

    JOINT 0009 26. 0. 0. 33.201

    JOINT 0010 16. 0. 0. 24.500

    JOINT HOOK 14. 0. 10. 69.000-13.000 90.000 FIXED

    JOINT SL01 17. 0. 6. 48.800-13.000 110000

    JOINT SL02 11. 0. 6. 89.200-13.000 110000

    JOINT SL03 17. 0. 6. 71.800-13.000

    JOINT SL04 11. 0. 6. 66.200-13.000

  • HLJOC/PTSC M&C PTSC POS/ TLO

    TGT FIELD DEVELOPMENT PROJECT

    PROVISION OF TRANSPORTATION AND INSTALLATION FOR WHP-H5 TOPSIDE AND PIPELINES

    Document No.:

    TGT-POS-S-H05-CA-0003 SPOOLS LIFTING ANALYSIS Page 29 of 54

    Revision No.: B0 Date: 09 May 15

    LOAD

    LOADCN 1

    LOADLB1 COMPUTER GENERATED SELFWEIGHT

    DEAD

    DEAD -Z M

    LOADCN 2

    LOAD Z 00040005 -0.0070 -0.0070 GLOB UNIF 3PUF

    LOAD Z 00060007 -0.0070 -0.0070 GLOB UNIF 3PUF

    LOAD Z 00080009 -0.0070 -0.0070 GLOB UNIF 3PUF

    LOAD Z 00000009 -0.0070 -0.0070 GLOB UNIF 3PUF

    LOAD 0000 -3.8300 GLOB JOIN FLANGE

    LOAD Z 00010008 -0.0070 -0.0070 GLOB UNIF 3PUF

    LOAD Z 00010008 -1.0000 -1.0000 GLOB UNIF CONCRETE

    LOAD Z 00050002 -0.0070 -0.0070 GLOB UNIF 3PUF

    LOAD Z 00050002 -1.0000 -1.0000 GLOB UNIF CONCRETE

    LOAD Z 00020003 -0.0070 -0.0070 GLOB UNIF 3PUF

    LOAD Z 00020003 -1.0000 -1.0000 GLOB UNIF CONCRETE

    LOAD Z 00030006 -0.0070 -0.0070 GLOB UNIF 3PUF

    LOAD Z 00030006 -1.0000 -1.0000 GLOB UNIF CONCRETE

    LOAD Z 00070010 -0.0070 -0.0070 GLOB UNIF 3PUF

    LOAD Z 00070010 -1.0000 -1.0000 GLOB UNIF CONCRETE

    LOAD Z 00100001 -0.0070 -0.0070 GLOB UNIF 3PUF

    LOAD Z 00100001 -1.0000 -1.0000 GLOB UNIF CONCRETE

    LOADCN 3

    LOAD 0005 -0.5000 GLOB JOIN RIGGING

    LOAD 0003 -0.5000 GLOB JOIN RIGGING

    LOAD 0001 -0.5000 GLOB JOIN RIGGING

    LOAD 0008 -0.5000 GLOB JOIN RIGGING

    LCOMB

    LCOMB BC 1 1.15002 1.15003 1.0000

    LCOMB 1.35 BC 1.3500

    LCOMB 2.00 BC 2.0000

    END

  • HLJOC/PTSC M&C PTSC POS/ TLO

    TGT FIELD DEVELOPMENT PROJECT

    PROVISION OF TRANSPORTATION AND INSTALLATION FOR WHP-H5 TOPSIDE AND PIPELINES

    Document No.:

    TGT-POS-S-H05-CA-0003 SPOOLS LIFTING ANALYSIS Page 30 of 54

    Revision No.: B0 Date: 09 May 15

    APPENDIX 1.4: 8 SPOOL AT H4 MODEL

    (03 pages)

  • HLJOC/PTSC M&C PTSC POS/ TLO

    TGT FIELD DEVELOPMENT PROJECT

    PROVISION OF TRANSPORTATION AND INSTALLATION FOR WHP-H5 TOPSIDE AND PIPELINES

    Document No.:

    TGT-POS-S-H05-CA-0003 SPOOLS LIFTING ANALYSIS Page 31 of 54

    Revision No.: B0 Date: 09 May 15

    LDOPT NF+Z1.0250007.850000 GLOBMN CMB

    ****************************************************************************

    ******************TE GIAC TRANG FILED DEVELOPMENT PROJECT*******************

    **************PROVISION OF TRANSPORTATION AND INSTALLATION FOR**************

    ***********************WHP-H5 TOPSIDE AND PIPELINES*************************

    ****************************************************************************

    OPTIONS MN 1 1

    SECT

    SECT 219.1 TUB 21.9102.060

    GRUP

    GRUP 291 219.1 20.008.000450.0 1 1.001.00 0.500 7.8490

    GRUP SLI 5.000 2.490 20.008.00024.80 1 1.001.00 0.500 7.8500

    GRUP SPR 16.830 1.270 20.008.00024.80 1 1.001.00 0.500 7.8500

    MEMBER

    MEMBER 00000002 291

    MEMBER 00010003 291

    MEMBER 00020014 291

    MEMBER 00030004 291

    MEMBER 00040005 291

    MEMBER 00050006 291

    MEMBER 00050013 291

    MEMBER 00070001 291

    MEMBER 00110009 291

    MEMBER 00120015 291

    MEMBER 00130012 291

    MEMBER 00140007 291

    MEMBER 00150011 291

    MEMBER 0002SL01 SLI T

    MEMBER 0013SL02 SLI T

    MEMBER 0014SL01 SLI T

    MEMBER 0015SL02 SLI T

    MEMBER SL01HOOK SLI T

    MEMBER SL02HOOK SLI T

    MEMBER COG SL02 SPR

    MEMBER 0010SL01 SPR

    MEMBER SL01COG SPR

    MEMBER SL020008 SPR

    JOINT

    JOINT COG 0. 0. 6.

    JOINT 0000 -7. -2. 0.-81.000-75.000

    JOINT 0001 0. -2. 0. 93.900-75.000

    JOINT 0002 -7. -2. 0.-12.800-75.000 110000

    JOINT 0002 10.000 10.000 ELASTI

    JOINT 0003 1. -2. 0. 93.900-75.000

    JOINT 0004 3. -2. 0. 88.500-75.000

    JOINT 0005 3. 0. 0. 88.500 51.700

    JOINT 0006 6. 0. 1. 93.600 51.700 5.000

    JOINT 0007 0. -2. 0. -6.100-75.000

    JOINT 0008 2. 2. 6. 14.112 14.112

    JOINT 0009 3. 8. 0. 88.500 58.200

    JOINT 0010 -2. -2. 6.-14.112-14.112

    JOINT 0011 3. 7. 0. 88.500 58.200

    JOINT 0012 3. 2. 0. 88.500 51.700

    JOINT 0013 3. 1. 0. 88.500 51.700 110000

    JOINT 0013 10.000 10.000 ELASTI

    JOINT 0014 -1. -2. 0. -6.100-75.000 110000

  • HLJOC/PTSC M&C PTSC POS/ TLO

    TGT FIELD DEVELOPMENT PROJECT

    PROVISION OF TRANSPORTATION AND INSTALLATION FOR WHP-H5 TOPSIDE AND PIPELINES

    Document No.:

    TGT-POS-S-H05-CA-0003 SPOOLS LIFTING ANALYSIS Page 32 of 54

    Revision No.: B0 Date: 09 May 15

    JOINT 0014 10.000 10.000 ELASTI

    JOINT 0015 3. 6. 0. 88.500 58.200 110000

    JOINT 0015 10.000 10.000 ELASTI

    JOINT HOOK 0. 0. 10. 50.000 FIXED

    JOINT SL01 -1. -1. 6.-97.849-97.848 110000

    JOINT SL02 1. 1. 6. 97.849 97.848 110000

    LOAD

    LOADCN 1

    LOADLB1 COMPUTER GENERATED SELFWEIGHT

    DEAD

    DEAD -Z M

    LOADCN 2

    LOAD Z 00000002 -0.0070 -0.0070 GLOB UNIF 3PUF

    LOAD Z 00030004 -0.0070 -0.0070 GLOB UNIF 3PUF

    LOAD Z 00040005 -0.0070 -0.0070 GLOB UNIF 3PUF

    LOAD Z 00050006 -0.0070 -0.0070 GLOB UNIF 3PUF

    LOAD 0000 -3.8260 GLOB JOIN CONCRETE

    LOAD 0009 -3.8260 GLOB JOIN CONCRETE

    LOAD Z 00110009 -0.0070 -0.0070 GLOB UNIF 3PUF

    LOAD Z 00010003 -0.0070 -0.0070 GLOB UNIF 3PUF

    LOAD Z 00010003 -1.0000 -1.0000 GLOB UNIF CONCRETE

    LOAD Z 00070001 -0.0070 -0.0070 GLOB UNIF 3PUF

    LOAD Z 00070001 -1.0000 -1.0000 GLOB UNIF CONCRETE

    LOAD Z 00050013 -0.0070 -0.0070 GLOB UNIF 3PUF

    LOAD Z 00130012 -0.0070 -0.0070 GLOB UNIF 3PUF

    LOAD Z 00020014 -0.0070 -0.0070 GLOB UNIF 3PUF

    LOAD Z 00020014 -1.0000 -1.0000 GLOB UNIF CONCRETE

    LOAD Z 00140007 -0.0070 -0.0070 GLOB UNIF 3PUF

    LOAD Z 00140007 -1.0000 -1.0000 GLOB UNIF CONCRETE

    LOAD Z 00120015 -0.0070 -0.0070 GLOB UNIF 3PUF

    LOAD Z 00150011 -0.0070 -0.0070 GLOB UNIF 3PUF

    LOADCN 3

    LOAD 0002 -0.5000 GLOB JOIN RIGGING

    LOAD 0014 -0.5000 GLOB JOIN RIGGING

    LOAD 0013 -0.5000 GLOB JOIN RIGGING

    LOAD 0015 -0.5000 GLOB JOIN RIGGING

    LCOMB

    LCOMB BC 11.1500 21.1500 3 1.

    LCOMB 1.35 BC 1.3500

    LCOMB 2.00 BC 2.0000

    END

  • HLJOC/PTSC M&C PTSC POS/ TLO

    TGT FIELD DEVELOPMENT PROJECT

    PROVISION OF TRANSPORTATION AND INSTALLATION FOR WHP-H5 TOPSIDE AND PIPELINES

    Document No.:

    TGT-POS-S-H05-CA-0003 SPOOLS LIFTING ANALYSIS Page 33 of 54

    Revision No.: B0 Date: 09 May 15

    APPENDIX 1.5: 8 SPOOL AT H5 MODEL

    (04 pages)

  • HLJOC/PTSC M&C PTSC POS/ TLO

    TGT FIELD DEVELOPMENT PROJECT

    PROVISION OF TRANSPORTATION AND INSTALLATION FOR WHP-H5 TOPSIDE AND PIPELINES

    Document No.:

    TGT-POS-S-H05-CA-0003 SPOOLS LIFTING ANALYSIS Page 34 of 54

    Revision No.: B0 Date: 09 May 15

    LDOPT NF+Z1.0250007.850000 GLOBMN CMB

    ****************************************************************************

    ******************TE GIAC TRANG FILED DEVELOPMENT PROJECT*******************

    **************PROVISION OF TRANSPORTATION AND INSTALLATION FOR**************

    ***********************WHP-H5 TOPSIDE AND PIPELINES*************************

    ****************************************************************************

    OPTIONS MN 1 1

    SECT

    SECT 219.1 TUB 21.9102.060

    GRUP

    GRUP 291 219.1 20.008.000450.0 1 1.001.00 0.500 7.8490

    GRUP SLI 5.000 2.490 20.008.00024.80 1 1.001.00 0.500 7.8500

    GRUP SPR 16.830 1.270 20.008.00024.80 1 1.001.00 0.500 7.8500

    MEMBER

    MEMBER 00000001 291

    MEMBER 00010002 291

    MEMBER 00020003 291

    MEMBER 00030020 291

    MEMBER 00040005 291

    MEMBER 00050006 291

    MEMBER 00060019 291

    MEMBER 00080007 291

    MEMBER 00090013 291

    MEMBER 00100009 291

    MEMBER 00110016 291

    MEMBER 00120017 291

    MEMBER 00130012 291

    MEMBER 00140004 291

    MEMBER 00150014 291

    MEMBER 00160007 291

    MEMBER 00170008 291

    MEMBER 00180015 291

    MEMBER 00190011 291

    MEMBER 00200021 291

    MEMBER 00210018 291

    MEMBER 0002SL01 SLI T

    MEMBER 0004SL01 SLI T

    MEMBER 0013SL02 SLI T

    MEMBER 0016SL02 SLI T

    MEMBER SL01HOOK SLI T

    MEMBER SL02HOOK SLI T

    MEMBER COG SL01 SPR

    MEMBER SL01SL03 SPR

    MEMBER SL02COG SPR

    MEMBER SL04SL02 SPR

    JOINT

    JOINT COG 0. 0. 19. -1.000-10.000

    JOINT 0000 -15. 8. 1.-51.400 89.000 29.200

    JOINT 0001 -14. 8. 1.-38.900 89.000 29.200

    JOINT 0002 -11. 8. 0.-95.900 89.000 110000

    JOINT 0002 10.000 10.000 ELASTI

    JOINT 0003 -10. 8. 0.-51.900 89.000

    JOINT 0004 0. 8. 0.-96.600 89.000 110000

    JOINT 0004 10.000 10.000 ELASTI

    JOINT 0005 0. 8. 0. 72.999 89.000

    JOINT 0006 1. 6. 0. 28.026 83.644

  • HLJOC/PTSC M&C PTSC POS/ TLO

    TGT FIELD DEVELOPMENT PROJECT

    PROVISION OF TRANSPORTATION AND INSTALLATION FOR WHP-H5 TOPSIDE AND PIPELINES

    Document No.:

    TGT-POS-S-H05-CA-0003 SPOOLS LIFTING ANALYSIS Page 35 of 54

    Revision No.: B0 Date: 09 May 15

    JOINT 0007 4. -4. 0. 20.491 -7.852

    JOINT 0008 4. -4. 0. 41.455-86.092

    JOINT 0009 7. -15. 0. 33.921-77.588

    JOINT 0010 7. -16. 0. 63.970-89.732

    JOINT 0011 2. 1. 0. 74.259 37.896

    JOINT 0012 5. -10. 0. 87.688-31.840

    JOINT 0013 6. -13. 0. 60.805 -4.714 110000

    JOINT 0013 10.000 10.000 ELASTI

    JOINT 0014 -1. 8. 0.-96.600 89.000

    JOINT 0015 -2. 8. 0.-96.600 89.000

    JOINT 0016 3. -1. 0. 47.375-34.978 110000

    JOINT 0016 10.000 10.000 ELASTI

    JOINT 0017 5. -7. 0. 14.572-58.966

    JOINT 0018 -3. 8. 0.-96.600 89.000

    JOINT 0019 2. 4. 0. 1.143 10.770

    JOINT 0020 -9. 8. 0.-51.900 89.000

    JOINT 0021 -8. 8. 0.-51.900 89.000

    JOINT HOOK 0. 0. 24. 1.000-10.000 5.000 FIXED

    JOINT SL01 -1. 2. 18.-19.249 43.585 99.832 110000

    JOINT SL02 1. -2. 19. 17.256-63.586 0.168 110000

    JOINT SL03 -1. 2. 18.-28.970 64.429 99.819