Upload
doandiep
View
215
Download
0
Embed Size (px)
Citation preview
Page 1 of 54
MINUTES OF THE 305th MEETING OF THE STATE LEVEL EXPERT APPRAISAL
COMMITTEE HELD ON 14/09/2016 AT COMMITTEE ROOM, GUJARAT
POLLUTION CONTROL BOARD, GANDHINAGAR.
The 305th meeting of the State Level Expert Appraisal Committee (SEAC) was held on 14th September 2016 at Committee Room, Gujarat Pollution Control Board, Gandhinagar. Following members attended the meeting:
1.Shri T.P. Singh, Chairman, SEAC.
2.Shri V.C.Soni,Vice Chairman, SEAC
3.Dr. Mayuri Pandya, Member, SEAC
4.Dr. V.K.Jain,Member,SEAC
5.Shri R.J.Shah, Member, SEAC
Following officers from the Geology and Mining Department attended the meeting:
1. Shri R.R.Bukhari,Royalty Inspector, Dist: Tapi
2. Shri Mann Chaudhry, Geological Assistant, Dist:Kutch
3. Shri M.B.Shah, Royalty Inspector, Dist: Chota Udepur
Sr. District Ordinary Clay
Marble River bed
Sand
Black trap
China Clay
Quartz Chalk Total
1 Ahmedabad 1 - - - - - - 1
2 Banaskantha -- 3 - - - - - 3
3 Chotaudepur - - 3 - - - - 3 4 Kheda - - - 1 - - - 1
5 Mehsana - - - - 2 - - 2
6 Panchmahal - - - - - 1 -- 1
7 Porbandar - - - - - - 1 1
8 Sabarkantha - - - - 1 - - 1
9 Tapi - - 6 - - - - 6
1 3 9 1 3 1 1 19
All the above proposals of minor minerals which have been received by the
Committee through the project proponent were taken up in the meeting.
1. ORDINARY CLAY MINING PROJECT,DIST: AHMEDABAD
Page 2 of 54
Sr. no.
Proposal No. Project Name
S NO Vill, Taluka
District
Hectare
Rate of mining
Nearest Habitation
Proposed Use
1 SIA/GJ/MIN/ 57547/2016
Simran Bricks
332,336,337,338,339
Vill: Chiyada, Ta:Bavla
Ahmedabad
-06-70-30 Existing
1500 MTPM
Kerala: 1.59 km
Construction
Shri Rashidkhan Pathan, Project proponent represented the above proposal before
the committee. He mentioned that above proposal does not include blasting and
mineral will be removed through open cast mining. Proposal does not involve
intersection of ground water table. It was presented that arrangement of water
sprinkling will be done during excavation and loading of mineral for transportation.
No protected areas/Reserve Forest/Sanctuary exist within 10 Km radius of the
proposed lease. Depth of mining will be restricted to 2 meter. PP informed that
Mining plan is submitted to the office of geology and Mining department, Ahmedabad
for approval. A copy of mining plan is submitted along with application. Project
details submitted by the geologist shows there is no applicability of cluster situation
to the above lease. The above proposal was categorized as B2 as per the amended
EIA Notification 2016.
After discussion and detailed scrutiny of the above proposals, considering the
mitigation measures proposed by the lease holder, the committee unanimously
decided to recommend above proposal for grant of environmental clearance to
SEIAA with stipulation of standard conditions for Sand mining as approved in 232nd
SEAC meeting held on 15th April 2015 with specific conditions mentioned in Office
Memorandum of MoEF&CC, New Delhi dated 24th June 2013 for ordinary earth as
under
1. The activity associated with borrowing/excavation of ‘brick earth’ and ‘ordinary earth’ for
purpose of brick manufacturing, construction of roads, embankments etc. shall not involve
blasting.
2. The borrowing/excavation activity shall be restricted to a maximum depth of 2m below
general ground level at the site.
3. The borrowing/excavation activity shall be restricted to 2 m above the ground water table at
the site.
4. The borrowing/excavation activity shall not alter the natural drainage pattern of the area.
5. The borrowed/excavated pit shall be restored by the project proponent for useful
purpose(s).
6. Appropriate fencing all around the borrowed/excavated pit shall be made to prevent any
mishap.
Page 3 of 54
7. Measures shall be taken to prevent dust emission by covering of borrowed/excavated earth
during transportation.
8. Safeguards shall be adopted against health risks on account of breeding of vectors in the
water bodies created due to borrowing/excavation of earth.
9. Workers / labourers shall be provided with facilities for drinking water and sanitation.
10. A berm shall be left from the boundary of adjoining field having a width equal to at least half
the depth depth of proposed excavation.
11. A minimum distance of 15 m from any civil structure shall be kept from the periphery of any
excavation area.
2. MARBLE STONE MINING PROJECT,DIST: BANASKANTHA
Sr. no.
Proposal No. Project Name
S NO Vill, Taluka
Hectare Rate of mining
Nearest Habitation
Proposed Use
2 SIA/GJ/MIN/56994/2016
D K Trivedi And Sons
57,58,59/1
Vill:Zarivav Ta:Danta
15-12-41 Ha Existing
5,02,076 MTPA
Ambaji town: 2.5 km
Construction
Shri Sunil Dixit, EIA Consultant, J.M.InfraNet Pvt. Limited along with project
proponent of D.K.Trivedi and Sons remained present before the committee. He
informed that aforementioned proposal is existing. No blasting is required as marble
blocks will be excavated by drill machine. Undertaking is submitted by the
aforementioned lease holder that waste generated during cutting of marble will not
be thrown outside the lease area.He further mentioned that nearest residence from
the above lease is located more than 500 meters.It was also noticed that the above
project does not involve intersection of ground water table. It was presented that
arrangement of water sprinkling will be done during cutting for control of fugitive
emission.
It is mentioned that the above proposal falls within 5 km radius from the interstate
border of Rajasthan however as per the amended notification of MOEF&CC, New
Delhi dated 15/01/2016 and 01/07/2016, general conditions are not applicable to the
aforementioned proposal. PP further informed that above proposal is accorded
before 09/09/2013 and hence there is no applicability of cluster situation.
The above proposal was categorized as B2 as per the amended EIA Notification
2016.
PP mentioned that environmental management plan, approved mining plan are
submitted and all the conditions mentioned therein will be followed. No court case is
pending against the project
Page 4 of 54
After discussion and detailed scrutiny of the above proposal, considering the
mitigation measures proposed by the lease holder, the committee unanimously
decided to recommend above proposal for grant of environmental clearance to
SEIAA with stipulation of standard conditions for Non-Sand mining as approved in
232nd SEAC meeting held on 15th April 2015.
3. MARBLE STONE MINING PROJECT,DIST: BANASKANTHA
Sr. no.
Proposal No. Project Name
S NO Vill, Taluka
Hectare Rate of mining
Nearest Habitation
Proposed Use
3 SIA/GJ/MIN/57029/2016
Ambaji Minerals
9 Vill: Khokharbilli Ta:Danta
9-10 Ha Existing
2,00,200 MTPA
Ambaji town: 3.5 km
Construction
Shri Sunil Dixit, EIA Consultant, J.M.InfraNet Pvt. Limited along with project
proponent of Ambaji Minerals Shri C.S.Mehta remained present before the
committee. He informed that aforementioned proposal is existing. No blasting is
required as marble blocks will be excavated by drill machine. Undertaking is
submitted by the aforementioned lease holder that waste generated during cutting of
marble will not be thrown outside the lease area.He further mentioned that nearest
residence from the above lease is located more than 500 meters.It was also noticed
that the above project does not involve intersection of ground water table. It was
presented that arrangement of water sprinkling will be done during cutting for control
of fugitive emission.
It is mentioned that the above proposal falls within 5 km radius from the interstate
border of Rajasthan however as per the amended notification of MOEF&CC, New
Delhi dated 15/01/2016 and 01/07/2016, general conditions are not applicable to the
aforementioned proposal. PP further informed that above proposal is accorded
before 09/09/2013 and hence there is no applicability of cluster situation.
PP mentioned that environmental management plan, approved mining plan are
submitted and all the conditions mentioned therein will be followed. No court case is
pending against the project.The above proposal was categorized as B2 as per the
amended EIA Notification 2016.
After discussion and detailed scrutiny of the above proposals, considering the
mitigation measures proposed by the lease holder, the committee unanimously
decided to recommend above proposal for grant of environmental clearance to
SEIAA with stipulation of standard conditions for Non-Sand mining as approved in
232nd SEAC meeting held on 15th April 2015.
4. MARBLE STONE MINING PROJECT,DIST: BANASKANTHA
Sr. no.
Proposal No. Project Name
S NO Vill, Taluka
Hectare Rate of mining
Nearest Habitation
Proposed Use
4 SIA/GJ/MIN/ Vipul 62 Vill: 10-00 Ha 9,90,920 Ambaji Constructio
Page 5 of 54
57038/2016 Marble Koteshwar Ta:Danta
Existing MTPA town: 2.5 km
n
Shri Sunil Dixit, EIA Consultant, J.M.InfraNet Pvt. Limited along with project
proponent Shri Gopal Modi of Vipul marble remained present before the committee.
He informed that aforementioned proposal is existing. No blasting is required as
marble blocks will be excavated by drill machine. Undertaking is submitted by the
aforementioned lease holder that waste generated during cutting of marble will not
be thrown outside the lease area. He further mentioned that nearest residence from
the above lease is located more than 500 meters. It was also noticed that the above
project does not involve intersection of ground water table. It was presented that
arrangement of water sprinkling will be done during cutting for control of fugitive
emission.
It is mentioned that the above proposal falls within 5 km radius from the interstate
border of Rajasthan however as per the amended notification of MOEF&CC, New
Delhi dated 15/01/2016 and 01/07/2016, general conditions are not applicable to the
aforementioned proposal. PP further informed that all the above proposal is
accorded before 09/09/2013 and hence there is no applicability of cluster situation.
PP mentioned that environmental management plan, mining plan (under approval of
office of the geology and Mining, Banaskantha) are submitted and all the conditions
mentioned therein will be followed. No court case is pending against the projectThe
above proposal was categorized as B2 as per the amended EIA Notification 2016.
After discussion and detailed scrutiny of the above proposals, considering the
mitigation measures proposed by the lease holder, the committee unanimously
decided to recommend above proposal for grant of environmental clearance to
SEIAA with stipulation of standard conditions for Non-Sand mining as approved in
232nd SEAC meeting held on 15th April 2015.
5. SAND MINING PROJECT,DIST: CHHOTAUDEPUR
Sr. No.
Proposal No. Project Name
Sr. No. Village/Taluka /Dist.
Area in Hectare
Rate of Mining
Name of River
Distance of Nearest habitation
Proposed Use
5 SIA/GJ/MIN/ 57433/2016
Dineshbhai Shantilal Oad
lagu S NO: 381,394,395,396, Vill:Ratanpur, Ta:Jetpurpavi,Dist:Chotaudepur
06-39-52 New
96,500 MTPA
Orsang Sithol:0.98 km
Construction
Shri M. B.Shah, Royalty Inspector, Dist: Chotaudepur represented above proposal
before the committee. He informed that there is no bridge piers / water intake wells /
irrigation structures within 500 m distance from boundary of above lease area. He
explained that sand excavation will be done up to maximum 3 m depth or water
level, whichever is less. Water sprinkling will be done during loading of material. All
Page 6 of 54
the transportation vehicles are proposed to be covered to avoid fugitive emission of
fine particles. PP informed that setback distance of 20 meter will be maintained from
the river bank to prevent bank erosion.
PP further mentioned that copies of approved mining plan, environment
management plan (EMP), prefeasibility report, and details regarding non applicability
of cluster formation for homogeneous minerals are submitted.The above proposal
was categorized as B2 as per the amended EIA Notification 2016.
Considering the anticipated impacts of mining and mitigation measures proposed by
the lease holder,committee unanimously decided to recommend the proposal for
grant of environmental clearance to SEIAA with stipulation of standard conditions for
Sand mining as approved in 232nd SEAC meeting held on 15thApril 2015 with
compliance of all the conditions mentioned in Sustainable sand mining management
guidelines 2016 of MOEF&CC, New Delhi.
6. SAND MINING PROJECT,DIST: CHHOTAUDEPUR
Sr. No.
Proposal No. Project Name Sr. No. Village/Taluka /Dist.
Area in Hectare
Rate of Mining
Name of River
Distance of Nearest habitation
6 SIA/GJ/MIN/56446/2016
Shri Somaji
Naraji
Vanzara
Adjacent to S O: 284 A, Vill:Jabugam, Ta: Jetpurpavi,
10.00 Existing
52000 MTPM
Orsang Jabugam:2.5 km
Shri M. B.Shah, Royalty Inspector, Dist: Chotaudepur represented above proposal
before the committee. He informed that there is no bridge piers / water intake wells /
irrigation structures within 500 m distance from boundary of above lease area. He
explained that sand excavation will be done up to maximum 3 m depth or water
level, whichever is less. Water sprinkling will be done during loading of material. All
the transportation vehicles are proposed to be covered to avoid fugitive emission of
fine particles. PP informed that setback distance of 20 meter will be maintained from
the river bank to prevent bank erosion.
PP further mentioned that copies of mining plan (submitted for approval to office of
geology and Mining,Dist:Chiotaudepur), environment management plan (EMP),
prefeasibility report, and details regarding non applicability of cluster formation for
homogeneous minerals are submitted.
Committee asked Royalty Inspector, Dist: Chotaudepur regarding status of district
survey report (DSR) prepared for sand mining to which he informed that it is yet not
prepared. Committee asked royalty insoetor to prepare district survey report at the
earliest as per the amendment of EIA Notification of MOEF&CC dated 15/01/2016.
Page 7 of 54
The above proposal was categorized as B2 as per the amended EIA Notification
2016.
After deliberation and considering the anticipated impacts of mining and mitigation
measures proposed by the lease holder, committee unanimously decided to
recommend the proposal for grant of environmental clearance to SEIAA with
stipulation of standard conditions for Sand mining as approved in 232nd SEAC
meeting held on 15thApril 2015 with compliance of all the conditions mentioned in
Sustainable sand mining management guidelines 2016 of MOEF&CC, New Delhi.
7. SAND MINING PROJECT,DIST: CHHOTAUDEPUR
Sr. No.
Proposal No. Project Name Sr. No. Village/Taluka /Dist.
Area in Hectare
Rate of Mining
Name of River
Distance of Nearest habitation
7 SIA/GJ/MIN/50791/2016
Shri Sardarji
Naraji
Vanzara
Adjacent to S O: 21,25 to 29, Vill: Alhadpura, Ta: sankheda,
10.00 Existing
47000 MTPM
Orsang Dhokaliya:0.60 km
Shri M. B.Shah, Royalty Inspector, Dist: Chotaudepur represented above proposal
before the committee. He informed that there is no bridge piers / water intake wells /
irrigation structures within 500 m distance from boundary of above lease area. He
explained that sand excavation will be done up to maximum 3 m depth or water
level, whichever is less. Water sprinkling will be done during loading of material. All
the transportation vehicles are proposed to be covered to avoid fugitive emission of
fine particles. PP informed that setback distance of 20 meter will be maintained from
the river bank to prevent bank erosion.
PP further mentioned that copies of mining plan (submitted for approval to office of
geology and Mining,Dist:Chiotaudepur), environment management plan (EMP),
prefeasibility report, and details regarding non applicability of cluster formation for
homogeneous minerals are submitted. The above proposal was categorized as B2
as per the amended EIA Notification 2016.
After deliberation and considering the anticipated impacts of mining and mitigation
measures proposed by the lease holder, committee unanimously decided to
recommend the proposal for grant of environmental clearance to SEIAA with
stipulation of standard conditions for Sand mining as approved in 232nd SEAC
meeting held on 15thApril 2015 with compliance of all the conditions mentioned in
Sustainable sand mining management guidelines 2016 of MOEF&CC, New Delhi.
8. BLACK TRAP MINING PROJECT,DIST: KHEDA
Page 8 of 54
Sr. No.
Proposal No. Project Name Sr. No. Village/Taluka /Dist.
Area in Hectare
Rate of Mining
Distance of Nearest habitation
8 SIA/GJ/MIN/16743/2016
J.J. Patel Infrastructure
& Engineering Private
Limited
362 paiki Vill: Danadara Ta:Kapadwanj Dist:Kheda
39.86.79 Ha. Existing since 2008
1,50,000 MTPM MTPM
Danadara: 2.28 km
The above proposal is amalgamation of seven leases and it is sanctioned by the
office of geology and mining, Dist; Kheda vide letter no: AGK/QL/Ekatrikaran/227
dated 5 February 2014.
Project proponent applied for EC in prescribed Form 1 along with other necessary
documents. The proposal was scheduled during SEAC meeting held on 20/05/2015.
During meeting, as lease area is greater than 25 Hectare, committee unanimously
decided to categorize the proposal under B1 category and stipulated TOR for
preparation of EIA covering 10 km area of study in periphery of the aforementioned
lease.
PP conducted public hearing on 10/06/2016 and submitted final EIA report on
20/07/2016.
During SEAC meeting, committee referred the minute of meeting of public hearing
proceedings and asked point-wise clarification committed by the project proponent.
Committee noted that some of the points are not addressed properly by the Project
proponent. Hence before appraising the project, committee asked PP to resubmit
reply addressing each of the point raised by the public during public hearing and
decided that upon submission of the details, proposal will be considered in one of the
upcoming SEAC meeting.
9 & 10. CHINA CLAY MINING PROJECT,DIST: MEHSANA
9. SIA/GJ/MIN/16704/2016 Amrapali Chinaclay Mining & Development Corporation
41-42-00
Mehsana Chinaclay
10 SIA/GJ/MIN/16706/2016 Oriental Prospecting Company
26-50-68
Mehsana Chinaclay
Project proponents /Geologist /RQP remained absent to represent the above
proposals before the committee. Hence, it was decided to defer the above proposals
in one of the up coming SEAC meeting for consideration.
11. QUARTZ MINING PROJECT,DIST: PANCHMAHAL
11
SIA/GJ/MIN/42089/2016 Shri Roshanali Mohmedali
5-91-86 Panchmahal Quartz
Page 9 of 54
Valikarimwala
Project proponent /Geologist /RQP remained absent to represent the above proposal
before the committee. Hence, it was decided to defer the above proposal in one of
the up coming SEAC meeting for consideration.
12. CHALK MINING PROJECT, DIST: PORBANDAR
Sr.
no.
Proposal No. Project
Name
S NO Address Hectare Rate
of
mining
Nearest
Habitati
on
Proposed
use
12 SIA/GJ/MIN/53169/2016
Shree Ashok H. Thanki
7/P and 9/P
Vill:
Virpur,
Ta:Ranavav,
Dist:Porban
dar
18.3040
Ha
Existing (Govt.
waste
land)
2350
MTP
A
Virpur:
1 km Filler in rubber,paints and ingredient in putty
During SEAC meeting held on 01/06/2016,Project proponent represented that application for EC is made on 10/05/2016.Project proponent has submitted approved mining plan. He informed the committee that mining will be a shallow and not obstructing surface run off and there will be no diversion of surface run off. There will be no creation of waste dump in present mining. Stone after lavigation will be back filled in mined out pits and levelled. Chalk will be excavated manually by pick axes and JCB excavators. As there is negligible soil cover, soil contamination will not be there. The overburden i.e. topsoil, generated will be used to back fill mined out pit. The open voids will be properly barricaded to prevent casualty. Waste will be temporary stored near to levigation site and after completion of operation, the reject or waste will be dumped into mined out area. All the trucks will be covered to prevent fugitive emission. Regular water sprinkling on haulage roads will be carried out during transportation of material by water sprinklers. Water requirement of 10.0 KLD for the proposed project activity will be met by water tankers supply from nearby village source. Tube well outside the lease area will provide the water for drinking purposes. Accumulated rainwater in mined out pits will be used for sprinkling on haul roads for dust suppression and mineral levigation. There will be no intersection of ground water table as mining depth is maintained above water table. The fencing will be provided surrounding to the mined out pits to prevent casualty. The above proposal was categorized as B2 as per the amended EIA Notification
2016.After presentation, committee asked Project proponent to submit the details
regarding formation of cluster of homogenous mineral. During meeting, committee
noted that the lease is issued to PP on 21/05/1993 and hence vide amendment in
EIA Notification dated 01/07/2016, applicability of cluster does not exist for the above
proposal.
After deliberation and considering the anticipated impacts of mining and mitigation
measures proposed by the lease holder, committee unanimously decided to
recommend the proposal for grant of environmental clearance to SEIAA with
Page 10 of 54
stipulation of standard conditions for Non Sand mining as approved in 232nd SEAC
meeting held on 15thApril 2015 with compliance of all the commitments, conditions
mentioned in approved mining plan.
13. CHINA CLAY MINING PROJECT,DIST: SABARKANTHA
Sr.No. Proposal No. Project Name District Hectare
13 SIA/GJ/MIN/52393/2016 Unific Enterprise Sabarkantha 16-53-00
For the above proposal, Project proponent /Geologist /RQP remained absent to
represent the above proposal before the committee. Hence, it was decided to defer
the proposal in one of the up coming SEAC meeting for consideration.
14. RIVER BED SAND MINING PROJECT,DIST: TAPI
Sr. No.
Proposal No. Project Name S NO Vill,Taluka Hectare Rate of mining
Name of River
Nearest Habitation
Proposal use
14 SIA/GJ/MIN/58713/2016
Alpeshkumar Babubhai Panchal
Tapi river patt, opp.survey No: 01 to 09
Vill:Chorgav Ta:Nizar Dist:Tapi
10.00 Ha New
62,500 MTPM
Tapi Chorgav: 0.6 km
Construction
Shri R.R.Bukhari, Royalty Inspector, office of Geology and MIning, Dist:Tap and Shri
Alpeshkumar B. Panchal, Project Proponent (PP)remained present to represent
above proposal before the committee. Royalty inspectorinformed that there is no
bridge piers / water intake wells / irrigation structures within 500 m distance from
boundary of above lease area. He explained that sand excavation will be done up to
maximum 3 m depth or water level, whichever is less. Water sprinkling will be done
during loading of material. All the transportation vehicles are proposed to be covered
to avoid fugitive emission of fine particles. PP informed that setback distance of 10
meter will be maintained from the river bank to prevent bank erosion.
PP further mentioned that copies of approved mining plan, prefeasibility report
including mitigation measures to curb pollution and details regarding non applicability
of cluster formation for homogeneous minerals.
In project details, Asst. geologist has validated that there is no instream mining and
lease area remains dry except during monsoon season
Committee asked Royalty Inspector, Dist: Tapi regarding status of district survey
report (DSR) prepared for sand mining to which he informed that it is yet not
prepared. Committee asked royalty inspector to prepare district survey report at the
earliest as per the amendment of EIA Notification of MOEF&CC dated
15/01/2016The above proposal was categorized as B2 as per the amended EIA
Notification 2016.
Page 11 of 54
Considering the anticipated impacts of mining and mitigation measures proposed by
the lease holder, committee unanimously decided to recommend the proposal for
grant of environmental clearance to SEIAA with stipulation of standard conditions for
Sand mining as approved in 232nd SEAC meeting held on 15thApril 2015 with
compliance of all the conditions mentioned in Sustainable sand mining management
guidelines 2016 of MOEF&CC, New Delhi.
15. RIVER BED SAND MINING PROJECT,DIST: TAPI
Sr. No.
Proposal No. Project Name S NO Vill,Taluka Hectare Rate of mining
Name of River
Nearest Habitation
Proposal use
15 SIA/GJ/MIN/58446/2016
Alpeshkumar Babubhai Panchal
Tapi river bed at survey No: 08 to 15
Vill:Bahupura Ta:Nizar Dist:Tapi
10.00 Ha New
62,500 MTPM
Tapi Bahupura : 2.80 km
Construction
Shri R.R.Bukhari, Royalty Inspector, office of Geology and MIning, Dist:Tap and Shri
Alpeshkumar B. Panchal, Project Proponent (PP)remained present to represent
above proposal before the committee. Royalty inspector informed that there is no
bridge piers / water intake wells / irrigation structures within 500 m distance from
boundary of above lease area. He explained that sand excavation will be done up to
maximum 3 m depth or water level, whichever is less. Water sprinkling will be done
during loading of material. All the transportation vehicles are proposed to be covered
to avoid fugitive emission of fine particles. PP informed that setback distance of 10
meter will be maintained from the river bank to prevent bank erosion.
PP further mentioned that copies of approved mining plan, prefeasibility report
including mitigation measures to curb pollution and details regarding non applicability
of cluster formation for homogeneous minerals.
In project details, Asst. geologist has validated that there is no instream mining and
lease area remains dry except during monsoon season
The above proposal was categorized as B2 as per the amended EIA Notification
2016.Considering the anticipated impacts of mining and mitigation measures
proposed by the lease holder, committee unanimously decided to recommend the
proposal for grant of environmental clearance to SEIAA with stipulation of standard
conditions for Sand mining as approved in 232nd SEAC meeting held on 15thApril
2015 with compliance of all the conditions mentioned in Sustainable sand mining
management guidelines 2016 of MOEF&CC, New Delhi.
16. RIVER BED SAND MINING PROJECT,DIST: TAPI
Sr. No.
Proposal No. Project Name
S NO Vill,Taluka Hectare Rate of mining
Name of River
Nearest Habitatio
Proposal use
Page 12 of 54
n
16 SIA/GJ/MIN/ 58452/2016
Alpeshkumar Babubhai Panchal
Tapi river patt paiki at adjoining S NO: 144 to 152
Vill:Kothali Ta:Nizar Dist:Tapi
08-70 Ha New
54,400 MTPM
Tapi Kothali : 2.50 km
Construction
Shri R.R.Bukhari, Royalty Inspector, office of Geology and MIning, Dist:Tap and Shri
Alpeshkumar B. Panchal, Project Proponent (PP)remained present to represent
above proposal before the committee. Royalty inspector informed that there is no
bridge piers / water intake wells / irrigation structures within 500 m distance from
boundary of above lease area. He explained that sand excavation will be done up to
maximum 3 m depth or water level, whichever is less. Water sprinkling will be done
during loading of material. All the transportation vehicles are proposed to be covered
to avoid fugitive emission of fine particles. PP informed that setback distance of 10
meter will be maintained from the river bank to prevent bank erosion.
PP further mentioned that copies of approved mining plan, prefeasibility report
including mitigation measures to curb pollution and details regarding non applicability
of cluster formation for homogeneous minerals validated by the Asst. geologist are
submitted.
In project details, Asst. geologist has validated that there is no instream mining and
lease area remains dry except during monsoon season
Considering the anticipated impacts of mining and mitigation measures proposed by
the lease holder, committee unanimously decided to recommend the proposal for
grant of environmental clearance to SEIAA with stipulation of standard conditions for
Sand mining as approved in 232nd SEAC meeting held on 15thApril 2015 with
compliance of all the conditions mentioned in Sustainable sand mining management
guidelines 2016 of MOEF&CC, New Delhi.
17. & 20. RIVER BED SAND MINING PROJECT,DIST: TAPI
Sr. No.
Proposal No. Project Name S NO Vill,Taluka Hectare Rate of mining
Name of River
Nearest Habitation
Proposal use
17 & 20
SIA/GJ/MIN/58451/2016 & SIA/GJ/MIN/57395/2016
Alpeshkumar Babubhai Panchal
Tapi river patt paiki opp to S NO: 5 & 6
Vill:Ashravaa Ta:Kakrmunda Dist:Tapi
10-00 Ha New
62,500 MTPM
Tapi Ashravaa : 0.80 km
Construction
Shri R.R.Bukhari, Royalty Inspector, office of Geology and MIning, Dist:Tapi and Shri
Alpeshkumar B. Panchal, Project Proponent (PP) remained present to represent
above proposals before the committee. Royalty inspector informed that proposal
Nos: SIA/GJ/MIN/58451/2016 and SIA/GJ/MIN/57395/2016 are identical. He further
informed that there is no bridge piers / water intake wells / irrigation structures within
Page 13 of 54
500 m distance from boundary of above lease area. He explained that sand
excavation will be done up to maximum 3 m depth or water level, whichever is less.
Water sprinkling will be done during loading of material. All the transportation
vehicles are proposed to be covered to avoid fugitive emission of fine particles. PP
informed that setback distance of 10 meter will be maintained from the river bank to
prevent bank erosion.
PP further mentioned that copies of approved mining plan, prefeasibility report
including mitigation measures to curb pollution and details regarding non applicability
of cluster formation for homogeneous minerals validated by the Asst. geologist are
submitted.
In project details, Asst. geologist has validated that there is no instream mining and
lease area remains dry except during monsoon season
The above proposal was categorized as B2 as per the amended EIA Notification
2016. Considering the anticipated impacts of mining and mitigation measures
proposed by the lease holder, committee unanimously decided to recommend the
proposal for grant of environmental clearance to SEIAA with stipulation of standard
conditions for Sand mining as approved in 232nd SEAC meeting held on 15thApril
2015 with compliance of all the conditions mentioned in Sustainable sand mining
management guidelines 2016 of MOEF&CC, New Delhi.
18. RIVER BED SAND MINING PROJECT,DIST: TAPI
Sr. No.
Proposal No. Project Name
S NO Vill, Taluka
Hectare Rate of mining
Name of River
Nearest Habitation
Proposal use
18. SIA/GJ/MIN/58449/2016
Alpeshkumar Babubhai Panchal
Tapi river patt paiki at adjoining to S NO:27,28,51,54
Vill:Gorasa Ta:Kukarmunda Dist:Tapi
09-66-92 Ha New
60,400 MTPM
Tapi Gorasa:0.70 km
Construction
Shri R.R.Bukhari, Royalty Inspector, office of Geology and MIning, Dist:Tap and Shri
Alpeshkumar B. Panchal, Project Proponent (PP)remained present to represent
above proposal before the committee. Royalty inspector informed that there is no
bridge piers / water intake wells / irrigation structures within 500 m distance from
boundary of above lease area. He explained that sand excavation will be done up to
maximum 3 m depth or water level, whichever is less. Water sprinkling will be done
during loading of material. All the transportation vehicles are proposed to be covered
to avoid fugitive emission of fine particles. PP informed that setback distance of 10
meter will be maintained from the river bank to prevent bank erosion.
PP further mentioned that copies of approved mining plan, prefeasibility report
including mitigation measures to curb pollution and details regarding non applicability
Page 14 of 54
of cluster formation for homogeneous minerals validated by the Asst. geologist are
submitted.
In project details, Asst. geologist has validated that there is no instream mining and
lease area remains dry except during monsoon season
The above proposal was categorized as B2 as per the amended EIA Notification
2016.
Considering the anticipated impacts of mining and mitigation measures proposed by
the lease holder, committee unanimously decided to recommend the proposal for
grant of environmental clearance to SEIAA with stipulation of standard conditions for
Sand mining as approved in 232nd SEAC meeting held on 15thApril 2015 with
compliance of all the conditions mentioned in Sustainable sand mining management
guidelines 2016 of MOEF&CC, New Delhi.
19. RIVER BED SAND MINING PROJECT,DIST: TAPI
Sr. No.
Proposal No. Project Name
S NO Vill, Taluka
Hectare Rate of mining
Name of River
Nearest Habitation
Proposal use
19 SIA/GJ/MIN/48663/2016
Dhruv Stone Quarry
Opp S NO: 192, Block: A
Vill: Chinchoda Ta: Nizar
06-00 Ha
4,93,200 MTPA
Tapi Chinchoda:1.30 km
Construction
Shri R.R.Bukhari, Royalty Inspector, office of Geology and MIning, Dist:Tapi
informed that there is no bridge piers / water intake wells / irrigation structures within
500 m distance from boundary of above lease area. He explained that sand
excavation will be done up to maximum 3 m depth or water level, whichever is less.
Water sprinkling will be done during loading of material. All the transportation
vehicles are proposed to be covered to avoid fugitive emission of fine particles. PP
informed that setback distance of 10 meter will be maintained from the river bank to
prevent bank erosion. PP further mentioned that copy of mining plan is submitted to
the office of the geology and Mining, dist: Tapi for approval. Also copy of
prefeasibility report including mitigation measures to curb pollution and details
regarding non applicability of cluster formation for homogeneous minerals validated
by the Asst. geologist are submitted.
PP mentioned that district collector has cancelled their lease and they are going for
appeal PP requested committee to defer their EC application to upcoming meeting.
After deliberation, committee decided to defer the proposal in one of the upcoming
SEAC meeting and asked PP to submit ownership of the aforementioned quarry
lease.
PROPOSALS OF MAJOR MINERALS
1. Ranavav Limestone Mine (Lease area: 12.14 Ha), S NO: 78/5, Near
Village: Ranavav, Ta: Ranavav, Dist: Porbandar.
Page 15 of 54
The project proponent has applied for their new limestone mine located at above mentioned address. The mine lease area is 12.14 Ha and proposed rate of mining is 1,28,000 MTPA. Technical presentation was made by the PP. During presentation, it was noted by the committee that proposed lease area falls within 5 km of Barda wildlife sanctuary. Referring Notification of MOEF dated 25 June 2014, it was observed by the committee that since above proposal is located within 5 KM distance from Barda Wildlife Sanctuary, general conditions are applicable and therefore the above project falls under category A and is not coming under the purview of SEAC.Being category A project, Committee advised project proponent to approach Environmental Appraisal Committee at MOEF&CC, New Delhi for obtaining Environmental Clearance.
2. Ranavav Limestone Mine (Lease area: 12.14 Ha), S NO: 78/5, Near
Village: Ranavav, Ta: Ranavav, Dist: Porbandar.
The project proponent has applied for their new limestone mine located at above mentioned address. The mine lease area is 11.33 Ha and proposed rate of mining is 1,20,000 MTPA. Technical presentation was made by the PP. During presentation, it was noted by the committee that proposed lease area falls within 5 km of Barda wildlife sanctuary. Referring Notification of MOEF dated 25 June 2014, it was observed by the committee that since above proposal is located within 5 KM distance from Barda Wildlife Sanctuary, general conditions are applicable and therefore the above project falls under category A and is not coming under the purview of SEAC. Being category A project, Committee advised project proponent to approach Environmental Appraisal Committee at MOEF&CC, New Delhi for obtaining Environmental Clearance.
3. Limestone Mine of Shree Babhubhai Kalabhai Vaja (Lease area: 01.00
Ha), S NO: 397 paiki,Village: Khorasa, Ta: Malia-Hatina, Dist: Junagadh.
Sr.
no.
Proposal No. Project Name S NO Vill,Taluka Hectare Rate of
mining
Nearest
Habitation
1 SIA/GJ/MIN
/16707/2016
Ranavav
Limestone
Mine
78/5 Vill:Ranavav
Ta:Ranavav
12-14 1,28,000
MTPA
Ranavav: 2
km
Sr.
no.
Proposal No. Project Name S NO Vill,Taluka Hectare Rate of
mining
Nearest
Habitation
2 SIA/GJ/MIN /16774/2016
Ranavav Limestone
Mine
78/5 Vill:Ranavav Ta:Ranavav
11-33 1,20,000 MTPA
Ranavav: 2 km
Page 16 of 54
During meeting for the above proposal no: SIA/GJ/MIN/33799/2016, PP submitted a
letter for withdrawal of EC application. Committee acknowledged the request of PP
and unanimously decided to close the proposal and delist from pending application
list of SEAC.
4. Dari Limestone Mine ( Lease Area: 6.4734 Ha), S NO: 523/P,Village: Dari,
Ta:Veraval, Dist: Gir Somnath.( Proposal NO: SIA/GJ/MIN/34003/2016).
During SEAC meeting held on 01/06/2016, the above proposal was scheduled for appraisal. Addtional details were sought during the meeting.PP submitted the additional details and proposal was scheduled for appraisal.
During presentation, details of production for the years 2000-2001 to 2014-15 is
submitted. Committee noticed that lease area of the proposal is greater than 5
hectare and production of Limestone (Major Mineral) is taken without obtaining prior
environmental clearance as per the EIA Notification 2006. Hence Committee found
that the project proponent has violated the provisions of EIA Notification-2006 by
carrying out mining activity/ starting the production activity without obtaining prior EC.
After deliberation,, committee decided not to consider the project at this stage.
Further it was decided to inform Gujarat Pollution Control Board to initiate credible
action on the violation by invoking powers under Section 19 of the Environment
(Protection) Act, 1986 for taking necessary legal action under Section 15 of the Act.
5. Limestone Mine of Shree Rudabhai Devshibhai Vadher (Lease area:
01.00 Ha), S NO: 397 paiki,Village: Khorasa, Ta: Malia-Hatina, Dist:
Junagadh.
Sr. no.
Proposal No. Project Name S NO Vill,Taluka Hectare Rate of mining
Nearest Habitation
3 SIA/GJ/MIN
/33799/2016
Limestone
Mine of
Shree Babhubhai
Kalabhai
Vaja
397 Vill:Khorasa
Ta:Malia-
Hatina
01-00
Ha
1,00,000
MTPA
Khorasa:
1.40 m
Sr.
no.
Proposal No. Project Name S NO Vill,Taluka Hectare Rate of
mining
Nearest
Habitation
4 SIA/GJ/MIN /34003/2016
Dari Limestone Mine
S NO: 523/P
Village: Dari, Ta:Veraval
6.47.34 Ha
60,000 MTPA
Dari:0.80 km
Page 17 of 54
During meeting for the above proposal no: SIA/GJ/MIN/34720/2015, PP submitted a
letter for withdrawal of EC application. Committee acknowledged the request of PP
and unanimously decided to close the proposal and delist from pending application
list of SEAC.
6. Vasai Limestone of Kherajbha Karubha Ker(Limestone Lease Area: 4.90.00 Ha),
S NO: 424/P,Village: Vasai, Ta: Okhanmandal,Dist: devbhumi Dwarka (Proposal
NO:SIA/GJ/MIN/57031/2016).
The project proponent has applied for their existing Limestone mine located at S NO: 424/P, Vill: Vasai, Ta: Okhanmandal, Dist: Devbhumi dwarka. The limestone mine lease area is 04.90.00 Ha and proposed rate of mining is 11,120 MTPA. Mining process include manual open cast semi mechanized mining. The proposal falls in project / activity no. 1(a) of the Schedule of the EIA Notification, 2006 and as the lease area is less than 50 Hectares, it falls under category B. The technical presentation of the project included detailed lease status, details of mining method, google image of site, Environmental setting of the project, Mining details, water requirements, Environment management plan with impacts and its mitigation measures etc. After detailed deliberation, considering the scale of project, it was categorized as B2. Project proponent was asked to submit additional information as below for further ppraisal of the project:
1. Project site specific details such as distance of the project site from the nearest (1) Village (2)Water Body : River / Creek / Nallah / Lake / Pond / Reservoir / Canal (3) National Highway(4) State Highway (5) Railway line (6) Heritage site (7) National Park / Wild Life Sanctuary /Reserve Forest / Protected Forest. A map indicating the aerial distance of the lease area from these entities.
Sr. no.
Proposal No. Project Name S NO Vill,Taluka Hectare Rate of mining
Nearest Habitation
5 SIA/GJ/MIN
/34720/2015
Limestone
Mine of
Shree Rudabhai
Devsinhbhai
Vadher
397
Paik
Vill:Khorasa
Ta:Malia-
Hatina
01-00
Ha
1,00,000
MTPA
Khorasa:
1.40 km
Sr.
no.
Proposal No. Project Name S NO Vill,Taluka Hectare Rate of
mining
Nearest
Habitation
6 SIA/GJ/MIN /57031/2016
Vasai Limestone of
Kherajbha
Karubha Ker
S NO:
424/P
Village: Vasai, Ta:Okhanmandal
4.90.00 11,120 MTPA
Vasai: 1.60km
Page 18 of 54
2. Copies of all requisite permissions including online acceptance letter for your proposal, permissions from District Collector, Commissioner, Geology & Mining, Indian Bureau of Mines, GPCB,Copy of valid renewed lease and / or lease renewal status from department of Industries and Mine, Government of Gujarat etc.
3. Year-wise production details since 2004 with monthwise production details for the year 2016 including current status of mining operation duly validated by the district geologist.
4. Land use plan of the mine lease area should be prepared to encompass pre-operational, operational and post operational phases.
5. Approved mining plan including progressive mine closure plan including details of cluster for homogeneous mineral within 500 meter radius of the lease boundary and details of EC status of each lease included in a cluster.
6. One complete season baseline ambient air quality data (except monsoon) to be given along with the dates of monitoring. The parameters to be covered shall be in accordance with the revised National Ambient Air Quality Standards as well as project specific parameters. Locations of the monitoring stations should be so decided so as to take into consideration the pre-dominant downwind direction, population zone and sensitive receptors. There should be at least one monitoring station in the upwind direction. There should be at least one monitoring station in the pre dominant downwind direction at a location where maximum ground level concentration is likely to occur.
7. Details of peripheral drains to arrest the inflow of surface runoff in the quarry area and garland drains for arresting run off from the overburden / reject dumps. Specific measures to ensure that contaminated runoff from mine terrain will not lead to the rivers / natural drains / adjoining farms, in any case.
8. Technical justification for no requirement of blasting. Notarized undertaking stating that no blasting shall be carried out for entire period of mining.
9. Impact due to fugitive emissions including that because of transportation activities and the mitigation measures thereof need to be elaborated.
10. Dust suppression measures & control measures at worker level & proposed PPE to workers.
11. Detailed overburden and mine rejects management plan.
12. Detailed write up and drawing of mine closure plan. Water reservoirs to be constructed after closure of mine should be in proper shape and having proper fencing.
13. Details on back filling system of the exhausted mine. Details on compaction of back filling layer.
14. The reclamation plan, post mine land use and progressive green belt development plan along with year wise financial outlay shall be included.
Page 19 of 54
15. The water requirement for the project along with the source and availability as well as necessary permissions from the competent authority for drawl of groundwater, if any. Justification for water consumption with regard to domestic consumption, plantation and dust suppression use keeping rate of mining and vehicles movements per day in a view.
16. Details of the water conservation measures proposed to be adopted in the project should be highlighted.
17. Information on site elevation, working depth, ground water table should be provided. Based on actual monitored data, it may clearly be shown whether working will intersect groundwater.
18. Check list of flora and fauna in the study area and impacts of the project on the same along with mitigation measures.
19. Occupational health impact of the project especially during manual operations in the work area and the mitigation measures proposed along with the commitment of the project proponent for implementation of the mitigation measures.
20. Plan for periodic medical examination of the mine workers.
21. Details of the basic amenities, infrastructure facilities, PPEs etc. to be provided to the mine workers.
22. Detailed Mitigation Plan and the Environmental Management Plan with respect to all likely impacts of the project activities. Total capital cost and recurring cost/annum earmarked for environment pollution control measures.
23. An action plan showing list of the activities along with the fund allocation shall be submitted based on the socio-economic profile of the surrounding villages and need base field assessment.
24. Details regarding existing green belt development activity carried out during past years. A detailed future greenbelt development plan including type of species, number of trees, budgetary allocation, etc.
25. Details of fencing, tree plantation done in the existing mined area.
26. Any litigation pending against the project and / or any direction / order passed by any Court of Law against the project, if so, details thereof.
27. (a) Does the company have a well laid down Environment Policy approved by its Board of Directors? If so, it may be detailed. (b). Does the Environment Policy prescribe for standard operating process / procedures to bring into focus any infringement / deviation / violation of the environmental or forest norms / conditions ? If so, it may be detailed.
28. What is the hierarchical system or administrative order of the company to deal with the environmental issues and for ensuring compliance with the EC conditions. Details of this system may be given.
29. Does the company have a system of reporting of non compliances / violations of environmental norms to the Board of Directors of the company and / or
Page 20 of 54
shareholders or stakeholders at large? This reporting mechanism should be detailed.
The project shall be appraised after submission of above cited additional details.
7. Vavarda Limestone Mining Lease Area( 4.0469) of Nirma Limited,( Lease Area:
4.0469 Ha), S NO: 111 (P),Village: Vavarada, Ta: Una, Dist: Gir Somnath
(Proposal NO:SIA/GJ/MIN/56588/2016).
The project proponent has applied for their existing Limestone mine located at S NO: 111 (P), Vill: Vavarda, Ta: Una, Dist: Gir Somnath. The limestone mine lease area is 04.04.69 Ha and proposed rate of mining is 10,625 MTPA. Mining process include manual open cast semi mechanized mining. The proposal falls in project / activity no. 1(a) of the Schedule of the EIA Notification, 2006 and as the lease area is less than 50 Hectares, it falls under category B. The technical presentation of the project included detailed lease status, details of mining method, google image of site, Plantation programme, Environmental setting of the project, Mining details, water requirements, Environment management plan with impacts and its mitigation measures etc. After detailed deliberation, considering the scale of project, it was categorized as B2. Project proponent was asked to submit additional information as below for further appraisal of the project:
1. Project site specific details such as distance of the project site from the nearest (1) Village (2)Water Body : River / Creek / Nallah / Lake / Pond / Reservoir / Canal (3) National Highway(4) State Highway (5) Railway line (6) Heritage site (7) National Park / Wild Life Sanctuary /Reserve Forest / Protected Forest. A map indicating the aerial distance of the lease area from these entities.
2. Copies of all requisite permissions including permissions from District Collector, Commissioner, Geology & Mining, Indian Bureau of Mines, GPCB, Copy of valid renewed lease and / or lease renewal status from department of Industries and Mine, Government of Gujarat etc.
3. Year-wise production details since 2002 with monthwise production details for the year 2016 including current status of mining operation duly validated by the district geologist.
Sr.
no.
Proposal No. Project
Name
S NO Vill,
Taluka
Hectare Rate of
mining
Nearest
Habitation
7 SIA/GJ/MIN
/56588/2016
Vavarda
Limestone Mining
Lease Area(
4.0469) of Nirma
Limited
S NO:
111 (P)
Village:
Vavarada, Ta: Una
4.04.69
Ha
10,625
MTPA
Vavarda:
7.5 km
Page 21 of 54
4. Land use plan of the mine lease area should be prepared to encompass pre-operational, operational and post operational phases.
5. Approved mining plan including progressive mine closure plan including details of cluster for homogeneous mineral within 500 meter radius of the lease boundary and details of EC status of each lease included in a cluster.
6. One complete season baseline ambient air quality data (except monsoon) to be given along with the dates of monitoring. The parameters to be covered shall be in accordance with the revised National Ambient Air Quality Standards as well as project specific parameters. Locations of the monitoring stations should be so decided so as to take into consideration the pre-dominant downwind direction, population zone and sensitive receptors. There should be at least one monitoring station in the upwind direction. There should be at least one monitoring station in the pre dominant downwind direction at a location where maximum ground level concentration is likely to occur.
7. Details of peripheral drains to arrest the inflow of surface runoff in the quarry area and garland drains for arresting run off from the overburden / reject dumps. Specific measures to ensure that contaminated runoff from mine terrain will not lead to the rivers / natural drains / adjoining farms, in any case.
8. Technical justification for no requirement of blasting. Notarized undertaking stating that no blasting shall be carried out for entire period of mining.
9. Impact due to fugitive emissions including that because of transportation activities and the mitigation measures thereof need to be elaborated.
10. Dust suppression measures & control measures at worker level & proposed PPE to workers.
11. Detailed overburden and mine rejects management plan.
12. Detailed write up and drawing of mine closure plan. Water reservoirs to be constructed after closure of mine should be in proper shape and having proper fencing.
13. Details on back filling system of the exhausted mine. Details on compaction of back filling layer.
14. The reclamation plan, post mine land use and progressive green belt development plan along with year wise financial outlay shall be included.
15. The water requirement for the project along with the source and availability as well as necessary permissions from the competent authority for drawl of groundwater, if any. Justification for water consumption with regard to domestic consumption, plantation and dust suppression use keeping rate of mining and vehicles movements per day in a view.
16. Details of the water conservation measures proposed to be adopted in the project should be highlighted.
Page 22 of 54
17. Information on site elevation, working depth, ground water table should be provided. Based on actual monitored data, it may clearly be shown whether working will intersect groundwater.
18. Check list of flora and fauna in the study area and impacts of the project on the same along with mitigation measures.
19. Occupational health impact of the project especially during manual operations in the work area and the mitigation measures proposed along with the commitment of the project proponent for implementation of the mitigation measures.
20. Plan for periodic medical examination of the mine workers.
21. Details of the basic amenities, infrastructure facilities, PPEs etc. to be provided to the mine workers.
22. Detailed Mitigation Plan and the Environmental Management Plan with respect to all likely impacts of the project activities. Total capital cost and recurring cost/annum earmarked for environment pollution control measures.
23. An action plan showing list of the activities along with the fund allocation shall be submitted based on the socio-economic profile of the surrounding villages and need base field assessment.
24. Details regarding existing green belt development activity carried out during past years. A detailed future greenbelt development plan including type of species, number of trees, budgetary allocation, etc.
25. Details of fencing, tree plantation done in the existing mined area.
26. Any litigation pending against the project and / or any direction / order passed by any Court of Law against the project, if so, details thereof.
27. (a) Does the company have a well laid down Environment Policy approved by its Board of Directors? If so, it may be detailed. (b). Does the Environment Policy prescribe for standard operating process / procedures to bring into focus any infringement / deviation / violation of the environmental or forest norms / conditions ? If so, it may be detailed.
28. What is the hierarchical system or administrative order of the company to deal with the environmental issues and for ensuring compliance with the EC conditions. Details of this system may be given.
29. Does the company have a system of reporting of non compliances / violations of environmental norms to the Board of Directors of the company and / or shareholders or stakeholders at large? This reporting mechanism should be detailed.
The project shall be appraised after submission of above cited additional details.
8. Ankoli Limestone Mining Lease Area (4.56.00) of Nirma Limited,( Lease Area:
4.56.00 Ha), S NO: 1 (P),Village: Ankolali, Ta: Gir-Gadhada Dist: Gir Somnath
(Proposal NO:SIA/GJ/MIN/56589/2016).
Page 23 of 54
The project proponent has applied for their existing Limestone mine located at S NO: 1(P), Vill: Ankolali, Ta: Gir-Gadhada, Dist: Gir Somnath. The limestone mine lease area is 04.56.00 Ha and proposed rate of mining is 37,500 MTPA. Mining process include manual open cast semi mechanized mining. The proposal falls in project / activity no. 1(a) of the Schedule of the EIA Notification, 2006 and as the lease area is less than 50 Hectares, it falls under category B. The technical presentation of the project included detailed lease status, details of mining method, google image of site, Plantation programme, Environmental setting of the project, Mining details, water requirements, Environment management plan with impacts and its mitigation measures etc. After detailed deliberation, considering the scale of project, it was categorized as B2. Project proponent was asked to submit additional information as below for further appraisal of the project:
1. Project site specific details such as distance of the project site from the nearest (1) Village (2)Water Body : River / Creek / Nallah / Lake / Pond / Reservoir / Canal (3) National Highway(4) State Highway (5) Railway line (6) Heritage site (7) National Park / Wild Life Sanctuary /Reserve Forest / Protected Forest. A map indicating the aerial distance of the lease area from these entities.
2. Copies of all requisite permissions including permissions from District Collector, Commissioner, Geology & Mining, Indian Bureau of Mines, GPCB, Copy of valid renewed lease and / or lease renewal status from department of Industries and Mine, Government of Gujarat etc.
3. Year-wise production details since 2002 with month-wise production details for the year 2016 including current status of mining operation duly validated by the district geologist.
4. Land use plan of the mine lease area should be prepared to encompass pre-operational, operational and post operational phases.
5. Approved mining plan including progressive mine closure plan including details of cluster for homogeneous mineral within 500 meter radius of the lease boundary and details of EC status of each lease included in a cluster.
6. One complete season baseline ambient air quality data (except monsoon) to be given along with the dates of monitoring. The parameters to be covered
Sr.
no.
Proposal No. Project
Name
S NO Vill,
Taluka
Hectare Rate of
mining
Nearest
Habitation
8 SIA/GJ/MIN
/56589/2016
Ankoli
Limestone Mining
Lease Area
(4.56.00) of Nirma
Limited
1(P) Village:
Ankolali, Ta: Gir-
Gadhada
04.56.00
Ha
37,500
MTPA
Gir-
Gadhada: 9 km
Page 24 of 54
shall be in accordance with the revised National Ambient Air Quality Standards as well as project specific parameters. Locations of the monitoring stations should be so decided so as to take into consideration the pre-dominant downwind direction, population zone and sensitive receptors. There should be at least one monitoring station in the upwind direction. There should be at least one monitoring station in the pre dominant downwind direction at a location where maximum ground level concentration is likely to occur.
7. Details of peripheral drains to arrest the inflow of surface runoff in the quarry area and garland drains for arresting run off from the overburden / reject dumps. Specific measures to ensure that contaminated runoff from mine terrain will not lead to the rivers / natural drains / adjoining farms, in any case.
8. Technical justification for no requirement of blasting. Notarized undertaking stating that no blasting shall be carried out for entire period of mining.
9. Impact due to fugitive emissions including that because of transportation activities and the mitigation measures thereof need to be elaborated.
10. Dust suppression measures & control measures at worker level & proposed PPE to workers.
11. Detailed overburden and mine rejects management plan.
12. Detailed write up and drawing of mine closure plan. Water reservoirs to be constructed after closure of mine should be in proper shape and having proper fencing.
13. Details on back filling system of the exhausted mine. Details on compaction of back filling layer.
14. The reclamation plan, post mine land use and progressive green belt development plan along with year wise financial outlay shall be included.
15. The water requirement for the project along with the source and availability as well as necessary permissions from the competent authority for drawl of groundwater, if any. Justification for water consumption with regard to domestic consumption, plantation and dust suppression use keeping rate of mining and vehicles movements per day in a view.
16. Details of the water conservation measures proposed to be adopted in the project should be highlighted.
17. Information on site elevation, working depth, ground water table should be provided. Based on actual monitored data, it may clearly be shown whether working will intersect groundwater.
18. Check list of flora and fauna in the study area and impacts of the project on the same along with mitigation measures.
19. Occupational health impact of the project especially during manual operations in the work area and the mitigation measures proposed along with the
Page 25 of 54
commitment of the project proponent for implementation of the mitigation measures.
20. Plan for periodic medical examination of the mine workers.
21. Details of the basic amenities, infrastructure facilities, PPEs etc. to be provided to the mine workers.
22. Detailed Mitigation Plan and the Environmental Management Plan with respect to all likely impacts of the project activities. Total capital cost and recurring cost/annum earmarked for environment pollution control measures.
23. An action plan showing list of the activities along with the fund allocation shall be submitted based on the socio-economic profile of the surrounding villages and need base field assessment.
24. Details regarding existing green belt development activity carried out during past years. A detailed future greenbelt development plan including type of species, number of trees, budgetary allocation, etc.
25. Details of fencing, tree plantation done in the existing mined area.
26. Any litigation pending against the project and / or any direction / order passed by any Court of Law against the project, if so, details thereof.
27. (a) Does the company have a well laid down Environment Policy approved by its Board of Directors? If so, it may be detailed. (b). Does the Environment Policy prescribe for standard operating process / procedures to bring into focus any infringement / deviation / violation of the environmental or forest norms / conditions ? If so, it may be detailed.
28. What is the hierarchical system or administrative order of the company to deal with the environmental issues and for ensuring compliance with the EC conditions. Details of this system may be given.
29. Does the company have a system of reporting of non compliances / violations of environmental norms to the Board of Directors of the company and / or shareholders or stakeholders at large? This reporting mechanism should be detailed.
The project shall be appraised after submission of above cited additional details.
9. Somnath Hydrated Lime and Chemical Indutries Pvt. Limited,(15.1352
Ha), S.No.42/1/P, Vill:Kherali,Ta: Veraval, Dist: Gir Somnath.(Proposal
NO: SIA/GJ/MIN/48072/2016).
During SEAC meeting held on 01/06/2016, above proposal was scheduled.After technical presentation, committee asked additional information after categorising the above proposal under B2. Committee noted that reply of additional information is not yet submitted by the project proponent and hence decided to ask PP to submit additional information till 30 September 2016 for further consideration of EC application.
Page 26 of 54
10. Ajotha Limestone Mine (Lease Area: 2.000 Ha), S NO: 389,Village:
Ajotha,Ta:Veraval,Dist:GirSomnath.(ProposalNO:SIA/GJ/MIN/33988/2016).
During During SEAC meeting held on 01/06/2016, above proposal was scheduled for appraisal. During meeting it was informed that it is an existing limestone mine located at S NO: 389,Village: Ajotha, Ta:Veraval, Dist: Gir Somnath. The mine lease area is 02.0000 Ha and proposed rate of mining is 46,300 MTPA.The proposed mining scheme envisages exploitation of minerals by manual method without deep hole drilling & blasting. The proposal falls in project / activity no. 1(a) of the Schedule of the EIA Notification, 2006 and as the lease area is less than 50 Hectares, it falls under category B. The proposal falls in project / activity no. 1(a) of the Schedule of the EIA Notification, 2006 and as the lease area is less than 50 Hectares, it falls under category B. The technical presentation of the project included detailed lease status, details of mining method, google image of site & its surrounding, land use plan, dust suppression measures at site, details of overburden and reject management plan etc. After detailed deliberation, considering the scale of project, it was categorized as B2 and additional information was sought. PP submitted the additional information and accordingly proposal was appraised. Mining lease for mineral limestone for area of 2.00 ha. of Survey No. 389, village: Ajotha, Taluka: Veraval, Dist. Gir somnath was granted to Arjanbhai Khimabhai Rathod. The mining operations were commenced from 05.12.1979.Lessee has applied for renewal on 8.09.1998. The first renewal was from 08.10.1999 to 07.10.2019.PP submitted application for EC on 15.02.2016.Lease area is Govt. waste land & total lease area is free from forest land.The limestone deposit is exposed to surface without any top soil & overburden. Mining will be carried out through opencast method. The transportation of limestone from mines to the chemical & cement industries is done through the covered trucks. The blasting requirement will be met by drilling & blasting of small diameter shallow depth holes. There is one mining pit within the mine. The broad mining parameters being adopted at the times are (1)The proposed mining scheme envisages exploitation of minerals by manual without deep hole drilling & blasting. However, Jack hammer drilling & blasting may be performed whenever required. & if required it should be through trained persons (2)Transportation within mining area is carried out by truck and transportation of limestone to factory head or elsewhere is carried by trucks. Limestone in the lease area is exposed to surface without any soil and overburden cover. Hence waste generation will be nil in the mine area. Nearest distances of various entities from the proposed mine lease are as under: (1)Village: Ajotha (1.2 Km).(2)Arabian Sea (around 6.45 km)(3) National Highway: Somnath-Una Hwy – 0.30 km (4)State Highway: Somnath-
Sr. no. Proposal
No.
Project
Name
S
NO
Vill,Taluka Hectar
e
Rate of
mining
Nearest
Habitation
10 SIA/GJ/
MIN /33988/
2016
Ajotha
Limestone Mine
S
NO: 389
Village:
Ajotha, Ta:Veraval,
2.00.0
0 Ha
46,300
MTPA
Ajotha: 1.2
km
Page 27 of 54
Una Hwy – 0.30 km (5)Railway line: Somnath (around 7.6 km) (6)Heritage site: No Heritage site listed by archaeological dept. falls within 10 km from mine boundary.(7)Nearest Wild Life Sanctuary Sasan-Gir is around 24.0 km.Lessee has applied for renewal on 28.09.1998. The first renewal was from 08.10.1999 to 07.10.2019. Details of production is as under:
Period Production(MT)
2004-05 20127.43
2005-06 18134.08
2006-07 17673.15
2007-08 16522.21
2008-09 14951.37
2009-10 6649.67
2010-11 10390.12
2011-12 4569.92
2012-13 18119.44
2013-14 11220.53
2014-15 11939.06
2015-16 10090.87
Land use plan of the mine lease area is as under: Sr. No. Particulars Present land use
area (ha.) Land use area at the end of
proposed scheme (ha.)
1 Area under mining 0.8320 0
2 Storage for top soil 0 0
3 Overburden/ Dump 0 0
4 Mineral storage 0 0
5 Infrastructure 0.02 0.022
6 Roads 0.04 0.044
7 Greenbelt 0.1 0.1
8 Total used area 0 0.066
9 Remaining unused
area
1.108 0.20
Page 28 of 54
10 Abundant mine
(Water harvesting
pond)
-- 1.668
Total 2.00 2.00
Mining plan including progressive mining closure plan approved by IMB is submitted by the PP. There are no other homogenous minerals mines within 500 meter radius from the lease boundary hence no possibility of formation of cluster.A garland drain and earthen bunds will be provided to avoid any inflow of surface water into the mine pit or runoff from mine.Jack hammer will be adopted to avoid drilling & blasting. Dust will be generated from transportation and sizing which will be minimized by taking preventive measures by sprinkling of water at mining area & mine road. Dust masks will be provided to all workers for precaution. Limestone in the lease area is exposed to surface without any soil and overburden cover. Hence waste generation will be nil in the mine area. However, the undersized which is generated during mining stored on pit bottom and will be taken out before end of mining.Mined out pit will be used as water reservoirs after closure of mine and having proper fencing, security arrangement & stabilized bund. There is no O/B or waste material available in the lease. Therefore, backfilling of pit is not possible. The mined out area will be developed as water collection pond to store rain water and covered by wire fencing. The area is devoid of sufficient quantum of overburden to reclaim the mined out voids. Therefore, backfilling of pit is not possible. The mined out area will be developed as water collection pond to store rain water. A protecting barbed fencing will be provided to prevent entry of men & animals. Water consumption will be 2 KLPD ( Domestic: 500 litre/day, Green belt: 1000 litre/day, Dust suppression: 500 litre/day)and will be brought through tankers. Used pit will be used as water reservoirs after closure of mine and having proper fencing. Proposed mining will not intersect the water table.PP informed that medical examination is undertaken every six months for every workers. Around 0.20 Lakhs recurring cost/annum earmarked for environment pollution control measures mainly for greenbelt development & occupational health.PP informed that there is no litigation pending against the proposed mining lease.Company will develop reporting systems of non-compliances/ violations of environmental norms to the Lessee.
After presentation, committee noted that copy of renewed lease/lease renewal status from department of Industries and Mine. Government of Gujarat is not submitted which was sought earlier. A discrepancy for national highway and state highway is also observed as both the highways are mentioned as Somnath-Una highway located at 300 meter from the proposed lease. Committee also asked PP to submit month-wise details of production for the year 2016. An undertaking regarding blasting is also sought by the committee. After deliberation, committee asked PP to submit aforementioned details within 30 days so as to consider the above proposal in one of the upcoming SEAC meeting expeditiously.
Page 29 of 54
11. VASAI LIMESTONE AND MARL MINES OF RAJESH SHARDULBHA KER, S NO:
129,VILL:VASAI,TA: OKHAMANDAL,DIST:DEVBHUMIDWARKA( Lease Area:
4.2467 Ha), S NO: 129,Village: Vasai,Ta:Okhamandal,Dist: Devbhumidwarka.
(ProposalNO:SIA/GJ/MIN/50609/2016).
Sr.
No.
Proposal No. Project Name Lease Area Rate of
Mining
11 SIA/GJ/MIN/50609/2016 VASAI LIMESTONE AND MARL MINES OF RAJESH SHARDULBHA KER, S NO: 129,VILL:VASAI,TA: OKHAMANDAL,DIST:DEVBHUMIDWARKA
4.2467 Ha Existing
Limestone: 30,000
MTPA and
Marl: 73780 MTPA
During SEAC meeting held on 30/04/2016,the aforementioned proposal was
appraised and committee sought additional information.PP submitted the details of
additional information on 08/07/2016.
The details of environmental entities from the proposed lease area is as under:
1 Nearest Village is Lalsinghpur 1.75 KM
2 Water body, River, Creek, Nallah, Lake, Pond, Reservoir, Canal,
Arabian Sea Cost – 4.5 KM
3 National Highway 8 E 120 KM
4 State Highway No. 25 2.75 KM
5 Railway Line 3 KM
6 Heritage Site (Dwarkadhish Jagat Temple) 7.5 KM
8 National Park/Wild Life Sanctuary/ Reserve Forest/ Protected Forest- Barda Wild Life Sanctuary
15 KM (Marine
PP has submitted copies of the Mining deed and approved Mining Plan. The mining is shallow and not obstructing surface run off and there is no diversion of surface run off, it will take its own natural flow. There is no creation of waste dump in present mining. Crawl Mounted rock breakers will be deployed for direct breaking of insitu Limestone into desired size of limestone boulders. The underlying marl bed is soft and freeable in nature and will be excavated by excavator’s bucket. Hence no blasting will be required. Provision of spraying water to reduce dust emission. As there is negligible soil cover, possibilities of contamination of soil do not exist.The overburden i.e. topsoil, generated is covered on back filled into the pits after operation.The open voids will be properly barricaded to prevent accidental fall.Care will be taken during manual transportation of soil during backfilling. The proposed mining area has negligible soil cover of 0.3 to 0.6m thickness. It will backfilled in the mined out pits. Plantation on the backfilled overburden/soil to be prevent soil erosion possibility. Drinking water will be procured from private tanker.Sewage generated will be disposed off in soak pits.No blasting will take place hence no Fly Rocks will be generated.Mineral rejects are negligible and back filled and levelled in mined out pits.Transportation of material from site, vehicles passing on kuccha and pucca roads will create fugitive air emission Regular water spraying on haulage roads during transportation of material by water sprinklers.All vehicles will be covered to prevent fugitive emission.Regular maintenance of vehicle will be made to prevent noise pollution.Pit generated after extraction of mineral will be refilled with post
Page 30 of 54
mining waste material. Top soil will be spread on the pit for agriculture purpose. Plant species, which are indigenous, fast growing, spreading root, broad leaf base etc, will be selected for plantation.PP has submitted environmental management plan.Marl is hydroscopic mineral and wet at the time of excavation. It will be ensured that the Marl bed is wet at the time of excavation, if not, water will be sprinkled on the Marl bed prior to excavation so that dust is supressed at the time of excavation. At the time of insitu breaking of limestone bed, water will be sprinkled to arrest dust emission. Water will be sprayed on haul roads of before vehicular movement on it. First Aid kit will be provided for the workers .Proper training for handling the particular job to every worker will be given. The personal protective equipment such as DGMS approved dust masks, helmets, gloves, respirators etc. shall be provided to the workers depending upon the nature of the work they involved. At the end of the mines the mined out pits are proposed to convert into water reservoirs.Water requirement of 06.0 KLD for the proposed project activity will be met by water tankers supply from nearby village source. Tube well outside the lease area will provide the water for drinking purposes. General elevation at lease area is 10 M from MSL. Working depth is up to 6 meters.Depth of Ground water table is 30 m (Pre-Monsoon) to 910m (Post-Monsoon) below the general ground level & hence mining will not intersect groundwater. No endanger spices of flora and fauna found in the lease area.PP mentioned that they will plant 250 trees area in the area available nearby the lease. Fencing will be provided surrounding to the excavated pit. There is no litigation pending against the project in any court of law. PP has submitted details of production for the years 2007-2008 to 2016-2017 for lime stone and Marl. No production of marl is made since Janauary 2016 and no production is taken from lime stone since March 2016. PP has applied for EC on 11/04/2016.
Considering the above project details, committee unanimously decided to
recommend the above proposal for grant of environmental clearance to SEIAA with
stipulation of following specific conditions.
1. Project proponent shall comply all the measures, conditions suggested in the approved mining plan and environment management plan (EMP) in a letter and spirit.
2. Project proponent shall comply all the conditions mentioned in “The Companies (Corporate Social Responsibility Policy) Rules, 2014 and its amendments from time to time vide notification of ministry of corporate affairs dated 27th February, 2014 in a letter and spirit.
12. NAVDRA LIMESTONE MINE,(APPLICANT:HARDASBHAI KARSHANBHAI
AMBALIYA), S NO: 80(P),VILL: NAVDRA,TA:KALYANPUR,DIST:DEVBHUMI
DWARKA, GUJARAT. (PROPOSALNO:SIA/GJ/MIN/30482/2015).
Sr. No.
Proposal No.
Project Name Lease Area Rate of Mining
12 SIA/GJ/M
IN/30482/
2015
NavdraLimestoneMine,(Applicant:Hard
asbhai Karshanbhai Ambaliya), S NO:
80(P),,Vill:Navdra,Ta:Kalyanpur,Dist:Devbhumi Dwarka,Gujarat
5.00 Ha
New
20,400 MTPA
Page 31 of 54
During SEAC meeting held on 30/04/2016, aforementioned proposal was scheduled
for appraisal. After presentation, committee sought additional information considering
proposal under B2 category. Mining lease is accorded to the PP on 16th February
1999 for 20 years.
Additional information was submitted by the PP on 06/09/2016.
The Mining Lease was granted over an area of 5.00 ha in Village – Navdra, Taluka-
Kalyanpur, and Dist-Devbhumi Dwarka; in favor of Shri Hardas Karsan Ambaliya
vide Govt. order no. MCR/1595-1967 CHH dated 24- 06-1998 and executed on
16.02.1999 for a period of 20 years. The proposed rate of production is 20,400
Tonnes per annum of Limestone. The estimated project cost is Rs.12 Lacs. The
expected life of mine is 14 years.The mining plan was approved by Indian Bureau of
Mines (IBM) Udaipur, vide their Letter no. 682 (23) MP- 763/1997 MCCM (N) UDP
dated 24.11.1997 for fresh grant of Lease. The mining scheme with progressive
closer plan is approved by Indian Bureau of Mines (IBM) Udaipur, vide their Letter
no. 682 (23)(763)/1997-MCCM (N) UDP Dated 29.04.2015.Project site specific
details are given in table below:
S. No. Entities Specifics Distance Direction
1 Village Navdra 2 km South-East
2 Water body: River/nalla/lake/pond/Reservoir Arabian Sea 1.2 km West
3 National Highway NA NA NA
4 State Highway SH-6 3 km East
5 Railway Line Bhatia R.S. 15 km North-East
6 Heritage site NA NA NA
7 National Park/Wildlife Sanctuary/RF/PF NA NA NA
Land-use pattern is mentioned as under:
SI. No.
Particulars Present land use pattern(ha)
End of the fifth years(ha)
Conceptual land use pattern(ha)
1. Area under mining 1.3388 1.5938 3.9762 (reclaimed as water reservoir)
2. Storage soil 0 0 0
3. OB dump 0 0 0
4. Mineral storage 0.0120 0.0120 0
5. Infrastructure 0.0050 0.0050 0
6. Green belt 0.0100 0.0500 0.1500
7. Road 0.0100 0.0100 0
8. Township area 0 0 0
9. Railway 0 0 0
Page 32 of 54
10. Tailing pond 0 0 0
11. Effluent treatment plant
0 0 0
12. Mineral separation plant
0 0 0
13. Sub grade 0 0 0
14. Undisturbed 3.6292 3.3292 0.8738
Total 5.00 5.00 5.00
PP informed that lease area is considered as gently sloping so it is not an erosion
prone area.There is no permanent overburden/ reject dumps in the lease area. This
is a limestone mine and there is no contaminated runoff from the mine terrain. There
are no surface water bodies also in the vicinity of the lease area and hence the
proposed mining will not affect surface water bodies.
Noise at the mine is due to mechanized mining operations and truck
transportation activities. The noise generated by the mining activity dissipates within
the mine. There is no regular blasting and also the villages are located far off from
the mine workings. Hence the impact of blasting on the surrounding villages will be
minimal.
Use of Personal Protection Equipments (PPE) like dust masks, ear plugs etc. will be
provided to the mine workers. Rock breaker will be used for breaking over size
boulders in order to reduce dust and noise generation, which otherwise would be
generated due to secondary blasting.
Regular water sprinkling on haul roads & loading points will be carried out.
Development of green belt/plantation around the lease boundary, roads, dumps will
be made. Ambient Air Quality Monitoring is proposed to be conducted on regularly
basis to assess the quality of ambient air. All the haul roads will be kept properly
graded and maintained with sufficient width. The vehicles deployed for material
transportation will be spillage proof to avoid or minimize the spillage of the
material during transportation. In any case, the transportation links are to be
inspected at least twice daily to clear accidental spillage, if any.For the proposed
mining scheme, it is suggested that the waste generated during scheme period will
be stacked at pit floor, no overburden is generated during mine scheme period, no
external dumps will be developed due to mining, and hence the problem of disposal
of waste will not be there. Mined out pit cannot be backfilled to original ground level
therefore mined out land will be used as a water reservoir. An area of 3.9762 ha of
mined out area will be converted into water reservoir with proper fencing. The
working will go by semi-mechanized opencast method of mining.
Page 33 of 54
Water for domestic and operations is required to be 5.80 KLD. It is proposed to
obtain water for drinking from nearby villages. Necessary permission from Village
Panchayat is obtained.
The proposed working of the mine is very much above the water table and hence it
will not intersect the ground water table.
Surface water management shall be adopted within and outside lease area to ensure
that run off from the mining area does not adversely affect nearby water bodies or
natural water streams. During monsoon, adequate arrangements will be made to
ensure that water drains out naturally. PP informed that there is no litigation pending
against this project.
After technical presentation committee asked PP to submit following details and
decided to consider the proposal in one of the upcoming SEAC meeting.
1. Month-wise production details for the years 2014, 2015 and 2016 with current
operational status of mining lease.
SUBMISSION OF REPLY FOR ADDITIONAL DETAILS SOUGHT
1. SAND MINING PROJECT,DIST: CHHOTAUDEPUR
Sr. no.
Proposal No. Project Name S NO Vill,Taluka Hectare Rate of mining
Name of River
Nearest Habitation
Proposal use
1 SIA/GJ/MIN/35660/2015
Sanjaybhai Buddhisagarbhai Solanki
23,24,25 ne lagu
Kadila/ Sankheda
6-63-68 Existing
40,000 MTPM
Orsang Kadila 1.00 km
Construction
During SEAC meeting held on 30/04/2016,Shri Mehul Shah, Royalty Inspector, Dist:
Chotaudepur informed that there is no bridge piers / water intake wells / irrigation
structures within 500 m distance from boundary of above lease area. He explained
that sand excavation will be done up to maximum 3 m depth or water level,
whichever is less. Water sprinkling will be done during loading of material. All the
transportation vehicles are proposed to be covered to avoid fugitive emission of fine
particles. Minimum setback distance of 10 meter shall be maintained from the river
bank to prevent bank erosion.
After presentation, committee asked geologist to submit approved mining plan,
environment management plan (EMP) and details regarding formation of cluster for
homogeneous minerals within 500 meter radius from the outer periphery of the lease
area.
Page 34 of 54
On 5/08/2016, PP submitted mining plan under approval of office of Geology and
Mining department, Chotaudepur and Environmental Management Plan (EMP). PP
submitted copy of order of Appellate authority, Department of Geology and Mining
sanctioning lease area which was granted earlier on 24/10/2008 and accordingly
informed that as per the notification of MOEF&CC dated 01/07/2016, sanctioned
lease does not attract cluster provision.
Considering the mitigation measures proposed by the lease holder, committee
unanimously decided to recommend the proposal for grant of environmental
clearance to SEIAA with stipulation of standard conditions for Sand mining as
approved in 232nd SEAC meeting held on 15thApril 2015 with compliance of all the
conditions mentioned in Sustainable sand mining management guidelines 2016 of
MOEF&CC, New Delhi.
Letter of Shri Natubha Jadeja,At :Lifra,Ta: Mundra,Dist: Kutch dated 10-05-
2016 regarding reviewing of EC accorded to the following quarry Leases:
Sr.No. Project Name Hectare Sr.No. Village Taluka/District 1 Jadeja Rajendrasinh
Svaraiji 01-00-00 S.No.141P Lifra Mundra/Kutch
2 Pir Swarupaiji Khengarji
04-90-00 S.No.141P Lifra Mundra/Kutch
3 Jadeja Desrathsinh Khanji
02-00-00 S.No.141P Lifra Mundra/Kutch
Aforementioned proposals were considered during SEAC meeting held on 28/11/2014 and Environmental clearances were accorded in the SEIAA meeting held on 27/02/2015. A letter of Shri Natubha Jadeja, At :Lifra, Ta: Mundra, Dist: Kutch dated 10/05/2016 requesting to review EC accorded to the above proposals was received by SEIAA which was forwarded to SEAC on 19/08/2016. With reference to the letter of Shri Natubha Jadeja, project proponents, geological assistant, Dist:Kutch were called before the SEAC. In a view of the letter of Shri Natubha Jadeja, committee was informed regarding inspection carried out by GPCB for all the aforementioned lease areas. According to the Inspection report of GPCB dated 07/07/2016 , It is noted by the committee that one check dam exists in upstream of the above mentioned lease areas at a distance of 50 meter where accumulation of water is observed and another check dam exists
Page 35 of 54
in the downstream of the proposed lease areas at a distance of 100 meters. It is also mentioned in the report that there is possibility of damage to the check dam structures when aforementioned lease starts functioning that includes blasting and excavation. Project proponents were asked to mention their stand in this regard by the committee to which PP mentioned that they have not started mining activities. Committee asked geological assistant to mention distance criteria to grant quarry lease specifically for the check dams according to the procedure adopted by the office of geology and Mining department which was not satisfactorily replied. After deliberation, prior to decide for the above mining leases, committee unanimously decided :
(1) To invite senior official of geology and mining department to opine regarding the prevailing criteria for distance of check dams for grant of lease that includes blasting
(2) To ask irrigation department of the district to opine for above mentioned leases in the vicinity of the check dams.
EC AMENDMENT PROPOSALS
(1) Black trap Mining Project, Dist.: Tapi
Sr No.
Name of applicant
Lease Area (H-A-M)
Survey No:
Village Taluka Dist: Rate of mining
Distance
of the
nearest
village
1 Shree Kailash Stone Quarry
03-00-00 Block No: 59/p2, S NO: 227
Sonarpada
Songadh Tapi 4780 MTPM
Sonarpada: 2.2 km
Environmental Clearance for the above proposal was issued on 25/03/2015 vide
letter No. SEIAA/GUJ/EC/1(a)/146/2015. Project proponent has submitted an
application on 11/08/2016 for correction of rate of mining mentioned in the EC.
Project proponent has mentioned that in an application comprising Form 1,it is
mentioned that rate of mining is 90,000 MTPA whereas in EC, rate of mining
mentioned is 4780 MTPM.
Referring to the application made in Form I by the applicant, committee noticed that
typographical error has inadvertently been made. After deliberation, committee
Page 36 of 54
decided to recommend amendment in Environmental Clearance to SEIAA issued on
25/03/2015 vide letter No. SEIAA/GUJ/EC/1(a)/146/2015 for correction in rate of
mining as below.
Sr No.
Name of applicant
Lease Area (H-A-M)
Survey No:
Village Taluka Dist: Rate of mining
Distance
of the
nearest
village
1 Shree Kailash Stone Quarry
03-00-00 Block No: 59/p2, S NO: 227
Sonarpada
Songadh Tapi 90,000 MTPA
Sonarpada: 2.2 km
(2). Black trap Mining Project, Dist.: Tapi
Sr No.
Name of applicant
Lease Area (H-A-M)
Survey No:
Village Taluka Dist: Rate of mining
2 Shree Kailash Stone Quarry
04-75-00 New
S. No: 227, Block NO: 59/p2
Sonarpada
Songadh Tapi 4780 MTPM
Environmental Clearance for the above proposal was issued on 23/06/2015 vide
letter No. SEIAA/GUJ/EC/1(a)/2486/2015. Project proponent has submitted an
application on 11/08/2016 for correction of rate of mining mentioned in the EC.
Project proponent has mentioned that in an application comprising Form 1,it is
mentioned that rate of mining is 1,00,000 MTPA whereas in EC, rate of mining
mentioned is 4780 MTPM.
Referring to the application made in Form I by the applicant, committee noticed that
typographical error has inadvertently been made in rate of mining as well as lease
area. After deliberation, committee decided to recommend amendment in
Environmental Clearance to SEIAA issued on 23/06/2015 vide letter No.
SEIAA/GUJ/EC/1(a)/2486/2015 for correction in rate of mining and lease area as
below.
Sr Name of Lease Area Survey Village Taluka Dist: Rate of
Page 37 of 54
No. applicant (H-A-M) No: mining
2 Shree Kailash Stone Quarry
03-75-00
S. No: 227, Block NO: 59/p2
Sonarpada
Songadh Tapi 1,00,000 MTPA
(3). Black trap Mining Project, Dist.: Tapi
Sr No.
Name of applicant
Lease Area (H-A-M)
Survey No:
Village Taluka Dist: Rate of mining
Distance of nearest village
3 Sujan Mineral Industries
03-65-75 B NO:73
Vaghpani
Vyara Tapi 3900 MTPM
Vaghpani: 600 m
Environmental Clearance for the above proposal was issued on 25/03/2015 vide
letter No. SEIAA/GUJ/EC/1(a)/159/2015. Project proponent has submitted an
application on 11/08/2016 for correction of rate of mining mentioned in the EC.
Project proponent has mentioned that in an application comprising Form 1,it is
mentioned that rate of mining is 5,75,000 MTPA whereas in EC, rate of mining
mentioned is 3900 MTPM.
Referring to the application made in Form I by the applicant, committee noticed that
typographical error has inadvertently been made in rate of mining.
After deliberation, committee decided to recommend amendment in Environmental
Clearance to SEIAA issued on 25/03/2015 vide letter No.
SEIAA/GUJ/EC/1(a)/159/2015 for correction in rate of mining as below.
Sr No.
Name of applicant
Lease Area (H-A-M)
Survey No:
Village Taluka Dist: Rate of mining
Distance of nearest village
3 Sujan Mineral Industries
03-65-75 B NO:73
Vaghpani
Vyara Tapi 5,75,000 MTPA
Vaghpani: 600 m
4). Black trap Mining Project, Dist.: Tapi
Sr No.
Name of applicant
Lease Area (H-A-M)
Survey No:
Village Taluka Dist: Rate of mining
Distance of nearest village
4 Swastik Stone Quarry
04-27-06 Block No: 88/p1, S NO:
Kumkuva
Songadh Tapi 9584 MTPM
Kumkuva: 2.5 km
Page 38 of 54
92 & 89/p3,96
Environmental Clearance for the above proposal was issued on 25/03/2015 vide
letter No. SEIAA/GUJ/EC/1(a)/156/2015. Project proponent has submitted an
application on 11/08/2016 for correction of rate of mining mentioned in the EC.
Project proponent has mentioned that in an application comprising Form 1,it is
mentioned that rate of mining is 1,30,000 MTPA whereas in EC, rate of mining
mentioned is 9584 MTPM.
Referring to the application made in Form I by the applicant, committee noticed that
typographical error has inadvertently been made in rate of mining.
After deliberation, committee decided to recommend amendment in Environmental
Clearance to SEIAA issued on 25/03/2015 vide letter No.
SEIAA/GUJ/EC/1(a)/156/2015 for correction in rate of mining as below.
Sr No.
Name of applicant
Lease Area (H-A-M)
Survey No:
Village Taluka Dist: Rate of mining
Distance of nearest village
4 Swastik Stone Quarry
04-27-06 (Existing:02-27-06) (Proposed New:02-00-00)
Block No: 88/p1, S NO: 92 & 89/p3,96
Kumkuva
Songadh Tapi For Existing lease: 1,30,000 MTPA For Proposed New lease:1,00,000 MTPA)
Kumkuva: 2.5 km
The meeting was concluded with thanks to the chair and members.
1. Shri T.P. Singh, Chairman, SEAC.
Page 39 of 54
2. Shri V.C.Soni,Vice Chairman, SEAC
3. Dr. Mayuri Pandya, Member, SEAC
4. Dr. V.K.jain,Member, SEAC.
5. Shri R.J.Shah, Member, SEAC
Page 40 of 54
Minutes of the 305th meeting of the State Level Expert Appraisal Committee held on
14/09/2016 at Committee Room, Gujarat Pollution Control Board, Gandhinagar.
The 305th meeting of the State Level Expert Appraisal Committee (SEAC) was held on 14th
September, 2016 at Committee Room, Gujarat Pollution Control Board, Gandhinagar. Following
members attended the meeting:
1. Shri T. P. Singh, Chairman, SEAC.
2. Shri V. C. Soni, Vice Chairman, SEAC.
3. Dr. V. K. Jain, Member, SEAC
4. Dr. Mayuri Pandya, Member, SEAC
5. Shri R J Shah, Member, SEAC.
The agenda of TOR/Scoping/Category 8 (a) cases & EC amendment cases was taken up. One (1)
case of TOR/Scoping/Category 8 (a) and two (two) cases of Appraisal was taken up. The applicants
made presentations on the activities to be carried out along with other details furnished in the Form-1 /
Form-1A, EIA report and other reports.
1. SIA/GJ/IND2/10624/2016 M/s: Nebula Pharma LLP,
Survey no. 60, Vill. Ankhol, Ta. Kadi, Dist. Mehsana
Screening & Scoping
Project / Activity No.: 5(f)
M/s: Nebula Pharma LLP (herein after Project Proponent – PP) has submitted application vide their
proposal no. SIA/GJ/IND2/10624/2016 dated 26/03/2016.
Project proponent was called for presentation on 04/05/2016.
As per amendment to EIA Notification, 2006 vide SO 1599 (E) dated 25.06.2014, small units are
categorized as Category “B” projects. Small units are defined as with water consumption less than 25
M3/day; Fuel consumption less than 25 TPD; and not covered in the category of MAH units as per the
Management, Storage, Import of Hazardous Chemical Rules (MSIHC Rules), 1989. During
presentation, PP informed that water consumption is 19.2 KL/day. Fuel consumption is 2 MT/day and
Chemicals to be used are not covered in MAH category. Hence, this project falls under Category B of
project activity 5(f) as per the EIA Notification 2006.
While discussing about the treatability of the waste water to be generated from the proposed products,
PP informed that the entire quantity of effluent will be evaporated after primary treatment. However, PP
could not reply satisfactorily regarding characteristics of the effluent stream and VOC management
during w/w treatment. Committee desired to know about the exact quality and quantity of the waste
water and its treatability. Committee observed that at present there is no common facility available for
waste water treatment in the vicinity of the proposed site. Committee also discussed about the
proposed evaporation system and its efficacy. Considering the above facts, it was unanimously decided
to consider the project for TOR/Scoping only after satisfactory submission of the following:
Revised proposal with sound environmental management system including (i) Product wise quality &
quantity of waste water to be generated.(ii) Technical details of ETP & Evaporation system.
Project status: New
Project / Activity Details:
Page 41 of 54
This is a new unit proposes the manufacturing of Synthetic organic chemicals (Bulk Drugs) as tabulated
below:
Sr.
no.
Product Name Quantity
MT/Month
1. Propyl Paraben 25
2. Methyl Paraben 50
3. Sodium Propyl Paraben 50
4. Sodium Methyl Paraben 100
Total 225
The project falls under Category B of project activity 5(f) as per the EIA Notification 2006.
The project proponent has applied for manufacturing of API drugs. A plot of 12486 sq. m area has been
acquired for this new project. Unit has proposed 4120.38 sq. m of green belt development. Total cost of the
project is Rs. 2 Crores. Total fresh water consumption for the proposed project will be 19.2 KL/day which
will be sourced from Bore well. Source of waste water generation is mainly from process, water treatment &
utilities. Total industrial waste water generation will be 8.4 KL/day, which will be sent to common facility
(Spray dryer unit) namely M/s: Chhatral Environment Management System Pvt. Ltd., (CEMSPL) Chhatral
after primary treatment. Domestic waste water (0.8 KL/day) discharged into soak pit through septic tank.
Unit has proposed one Boiler (cap.: 1 TPH) and one HAG in which Agro waste briquettes (10 MT/Month &
40 MT/Month respectively) will be used as fuel. Multi Cyclone separator followed by Bag filter is proposed as
APCM. Two spray dryers (200 Kg/hr each) and one spin flash dryer is proposed. Cyclone separator followed
by water scrubber and bag filter will be facilitated as APCM with Spray dryer and Spin splash dryer
respectively. One DG set (75 KVA) is proposed as stand-by facility. No process gaseous emission is
envisaged. Hazardous waste generated from the manufacturing activity will be ETP sludge & Evaporation
residue (3 MT/Month), Discarded containers/liners (0.2 MT/Month) and Used oil (200 Lit./Yr.)
Observations & Discussions:
Technical presentation made during the meeting by project proponent. While discussing about the waste
water management, PP informed that the common spray dryer facility of CEMSPL will be operative within 2-
3 months and entire quantity of waste water will be sent to CEMSPL through dedicated tankers. Committee
noted that there is no process gas emission from the proposed project. During meeting Project proponent
has requested to consider the project as B2 category project. Looking to the small scale of the project and
low pollution potential, the request was considered and the project was categorized as B2 and the additional
information was sought for appraisal of the project.
1. Land Possession Documents of the proposed site. NA permission letter from concern authority.
2. Demarcation of proposed project activities in lay out plan.
3. Exact details about infrastructural facilities, plant machineries etc. required for the proposed project.
4. Details of surrounding industrial units within 2 km radius with details like Name and address of the unit,
type and nature of industrial activity etc.
5. Project site specific details such as aerial distance of the project site from the nearest (1) Village-
Nearest residential area N(2) Water Body: Creek / Nallah / Lake / Pond / Reservoir / Canal (3) National
Highway (4) State Highway (5) Railway line (6) Heritage site (7) Aanganwadi/School/College/Institute
etc. and likely impact on them due to the proposed project along with the mitigation measures proposed
Page 42 of 54
to minimize the likely impact. Give satellite image of 2 km radius.
6. Ensure that there is no National Park / Wild Life Sanctuary/Eco Sensitive area etc. Within 10 km radius
of the proposed project.
7. Legal Undertaking stating that unit is complying the three conditions [i.e. water consumption less than
25 M3/day; Fuel consumption less than 25 TPD; and not covered in the category of MAH units as per
the Management, Storage, Import of Hazardous Chemical Rules (MSIHC Rules), 1989] as per the
amendment to EIA Notification, 2006 vide SO 1599 (E) dated 25.06.2014.
8. Layout plan of the factory premises. Provision of separate entry & exit and adequate margin all round
the periphery for unobstructed easy movement of the emergency vehicle / fire tenders without reversing
back. Mark the same in the plant layout.
9. Proposed monthly production of each product and product wise monthly consumption of each raw
material.
10. Chemical name of each proposed product to be manufactured. Details on end use of each product.
Manufacturing process along with chemical reactions, mass balance for each product.
11. Water balance diagram (including reuse-recycle, if any) along with qualitative and quantitative analysis
of each waste stream to be generated from the manufacturing process of each product to be
manufactured along with mass balance.
12. Stream wise qualitative & quantitative analysis of each waste stream (including process water, cooling
tower blow down, boiler blow down, washing effluent etc.) to be generated. Give segregation scheme at
source. Characteristics of untreated and treated wastewater. A detailed effluent treat ability study vis-à-
vis the adequacy and efficacy of the treatment facilities proposed for the wastewater to be generated.
The characteristic on which treatability is based shall also be stated.
13. Details of the ETP units including its capacity, size of each unit, retention time and other technical
parameters. Details regarding provision of online continuous pH meter, TOC analyser and flow meter at
the final outlet of the ETP.
14. Membership of Common Environmental Infrastructure facility i.e. Common spray dryer CEMSPL.
15. Plans for management and disposal of waste streams to be generated from spillage, leakages, vessel
washing, used container washing etc. Measures proposed for preventing effluent discharge during
unforeseen circumstances.
16. Specific details of (i) Process gas emission from each unit process with its quantification, (ii) Air
pollution Control Measures proposed for process gas emission, (iii) Adequacy of the air pollution control
measures for process gas emission, measures to achieve the GPCB norms (iv) Details of the utilities
required (v) Type and quantity of fuel to be used for each utility (vi) Flue gas emission rate from each
utility (vii) Air Pollution Control Measures proposed to each of the utility along with its adequacy (viii)
List the sources of fugitive emission along with its quantification and proposed measures to control it.
17. Specific details of fugitive emission from the unit along with its quantification and proposed measures to
control it along with measures proposed to monitor VOC within work area. Details of ventilation system
proposed in the work area. Measures proposed to keep the work area environment as per the norms of
GFR.
18. Details of measures proposed for noise pollution abatement & its monitoring.
19. Details of management of the hazardous wastes to be generated from the project stating detail of
Page 43 of 54
storage area for each type of waste, its handling and its disposal. How the manual handling of the
hazardous wastes will be minimized?
20. Methodology of de-contamination and disposal of discarded containers and its record keeping.
21. Measures proposed to be taken for the work area ambient air quality monitoring as per Gujarat
Factories Rules.
22. A detailed EMP including the protection and mitigation measures for preventing impacts on human
health and environment as well as detailed monitoring plan with respect to various parameters and
responsible head for the environmental management cell and environmental management cell
proposed for implementation and monitoring of EMP.
23. Detailed socio-economic development measures including community welfare program most useful in
the project area for the overall improvement of the environment.
24. A detailed Green Belt Development Program including annual budget, types & number of trees to be
planted, area under green belt development [with map]; along with commitment of the management to
carry out the tree plantation activities outside the premises at appropriate places in the Industrial estate
and elsewhere.
25. Details of hazardous characteristics and toxicity of raw materials and products to be handled and the
control measures proposed to ensure safety and avoid the human health impacts. This shall include the
details of Antidotes also.
26. Details of quantity of each hazardous chemical to be stored, Material of Construction of major
hazardous chemical storage tanks, threshold storage quantity as per schedules of the Manufacture,
Storage & Import of Hazardous Chemicals Rules of major hazardous chemicals. How the manual
handling of the hazardous chemicals will be minimized?
27. Details of the separate isolated storage area for chemicals. Details of fire extinguishers, flame proof
electrical fittings, DCP extinguishers and other safety measures proposed.
28. Specific safety details / provisions for various hazardous chemicals and detailed fire control plan for
flammable substances.
29. Details of possibilities of occupational health hazards from the proposed manufacturing activities and
proposed measures to prevent them.
30. Detailed risk assessment report including prediction of the worst-case scenario and maximum credible
accident scenario along with damage distances and preparedness plan to combat such situation and
risk mitigation measures. Vulnerable zone demarcation.
31. Submit checklist in the form of Do’s & Don’ts of preventive maintenance, strengthening of HSE, mfg
utility staff for safety related measures.
32. A tabular chart with index for point-wise compliance of above details.
The project shall be appraised on satisfactory submission of the above.
19. SIA/GJ/IND2/16818/2015 M/s: Hindusthan Speciality Chemicals Ltd.,
Plot No:830, GIDC-Jhagadia, Dist.: Bharuch. EC amendment
Project / Activity No.: 5(f)
M/s: Hindusthan Speciality Chemicals Ltd. (herein after Project Proponent – PP) has submitted
application vide online application no. SIA/GJ/IND2/16818/2015 dated 22/07/2016 for EC
Page 44 of 54
amendment.
Project status: Existing
Project / Activity Details:
This is an existing Specialty Chemical manufacturing unit which was accorded Environmental Clearance
vide letter no. SEIAA/GUJ/EC/5(f)/3570/2015 dated 22/09/2015. Environmental Clearance was granted with
a condition to use HSD – 0.602 MTPH shall be used as a fuel in the proposed Boiler - 02. The project
proponent requested for amendment in Environmental Clearance order dated 22/09/2015 with respect to the
change in fuel from HSD to FO or NG for the proposed Steam Boiler. In addition to this, PP also requested
to add one Thermic Fluid Heater (Cap. 4 Lac K cal/hr) with fuel consumption HSD – 44 Kg/hr.
The request was considered during the meeting and it was presented that the EC was granted for HSD as
fuel for Boiler. Now, they intend to change fuel as FO or NGfor their boiler. PP informed that FO price have
dropped drastically in the last one year and there is no change in HSD price. Upon asking regarding detailed
justification for price difference and justification for installation of new TFH, project proponent could not reply
satisfactorily. After detailed discussion on the matter, It was decided to further appraise the project only after
submission of the following:
1. Detailed justification for (1) proposed change in fuel along with the authentic documents and (2)
Justification for installation of new TFH which was not listed in the existing Environmental clearance.
2. Specific details on (i) Type, quantity and quality (CV, Sulphur content, Ash content, etc,) of coal to be
used (iii) Flue gas emission details (iv) Air pollution Control Measures along with its adequacy to
achieve the GPCB Norms. (v) List the sources of fugitive emission from the unit along with its
quantification and proposed measures to control it.
3. Base line status of ambient air quality and its comparison with ambient air quality results mentioned in
previous EIA Report for assessing change in ambient air quality.
4. Prediction of likely impacts on ambient air quality due to change of fuel (Type and quantity) by use of
modeling. Air quality modeling to be carried out considering the worst case scenario partial and
complete failure of the APCM. The details of model used and input parameters used for modeling
should be provided. The air quality contours may be shown on location map clearly indicating the
location of sensitive receptors, if any, and the habitation. The wind rose showing pre-dominant wind
direction should also be indicated on the map.
5. A detailed EMP including the protection and mitigation measures for the impacts on human health and
environment due to this proposed change as well as detailed monitoring plan.
3. SIA/GJ/IND2/16896/2015 M/s: Eshyasi Pharma Ltd.
S.No.590-A and 592-A, Luna, Padra, Vadodara EC amendment
Project / Activity no.: 5(f)
M/s: Eshyasi Pharma Ltd. (herein after Project Proponent – PP) has submitted application vide online application no. SIA/GJ/IND2/16896/2016 dated 22/07/2016 for EC amendment.
Project status: Existing
Project / Activity Details:
This is an existing Bulk drug manufacturing unit which was accorded Environmental Clearance vide letter no.
SEIAA/GUJ/EC/5(f)/316/2016 dated 10/05/2016. Environmental Clearance was granted with a condition to
maintain Zero Liquid Discharge (ZLD).
Page 45 of 54
The project proponent requested for amendment in Environmental Clearance order dated 10/05/2016 with
respect to the change in mode of disposal of waste water.
The request was considered during the meeting and it was presented that the EC was granted to maintain
Zero Liquid Discharge (ZLD) by means of primary treatment followed by Evaporator.
Now, project proponent proposed to change in mode of disposal by sending waste water to CETP of M/s:
Enviro Infrastructure Co. Ltd. [EICL]. Upon asking about the justification for proposed change in mode of
disposal, PP informed that they required EC amendment due to recent policy of GPCB regarding waste
water disposal into common facility for the Padra region. Unit has obtained membership certificate of M/s:
EICL with discharge quantity 1 KL/day. PP has furnished a CTE rejection order dated 01/09/2016 issued by
GPCB.
The committee was satisfied with the clarification given by the project proponent and decided to forward the
proposal to SEIAA for the grant of amendment in environment clearance by replacing the Specific condition
no. 5, 6 and Water condition no. 7, 12, 13, 14, 15, 16 & 17 of Environmental Clearance vide letter no.
SEIAA/GUJ/EC/5(f)/316/2016 dated 10/05/2016 as below and with rest of conditions same as prescribed in
the said Environmental Clearance dated 10/05/2016.
Specific Condition no. 5
Entire quantity of effluent to be generated from the proposed production shall be completely sent to CETP of
M/s: Enviro Infrastructure Co. Ltd.[EICL] and shall not be discharge within or outside the premises, in any
case.
Specific Condition no.6
Unit shall provide buffer water storage tank of adequate capacity for storage of treated waste water before
sending to CETP.
Water Condition no.7
Total water consumption for the proposed project shall not exceed 4 KL/day and it will be sourced from the
Bore well. Necessary permission from the CGWA shall be obtained for withdrawal of ground water.
Water Condition no.12
Waste water generated from the manufacturing process (0.5 KL/day) shall be passed through solvent
stripper after neutralization. Generated mixed solvent (0.1 KL/day) shall be sold out to authorized re-refiners
and remaining effluent (0.4 KL/day) shall be sent to CETP M/s: Enviro Infrastructure Co. Ltd.[EICL] along
with washing & utility waste water (0.65 KL/day).
Water Condition no.13
The stripped effluent (0.4 KL/day) shall be mixed with the washings and utility streams and after passing
through distillation unit entire effluent (0.9 KL/day) shall be sent to CETP M/s: Enviro Infrastructure Co.
Ltd.[EICL].
Water Condition no.14
The unit shall continuously strive to reduce, recycle and reuse the treated effluent.
Water Condition no.15
Unit shall obtain membership certificate for minimum 1 KL/day from the CETP of M/s: Enviro Infrastructure
Co. Ltd.[EICL]. Waste water shall be sent to CETP through dedicated tankers only.
Water Condition no.16
The unit shall provide adequate effluent treatment plant (ETP) & Stripping column and primary treated
effluent conforming CETP inlet norms shall be sent to CETP.
Page 46 of 54
Water Condition no.17
Proper logbook of ETP and Stripping column operation, effluent sent to CETP etc. shall be maintained and
furnished to the GPCB from time to time
Meeting ended with thanks to the Chair and the Members.
--------------------------------
Minutes approved by:
1. Shri T. P. Singh, Chairman, SEAC.
2. Shri V. C. Soni, Vice Chairman, SEAC.
3. Dr. V. K. Jain, Member, SEAC
4. Dr. Mayuri Pandya, Member, SEAC
5. Shri R J Shah, Member, SEAC.
Page 47 of 54
Minutes of the 305th meeting of the State Level Expert Appraisal Committee held on
14/09/2016 at Committee Room, Gujarat Pollution Control Board, Gandhinagar.
The 305th meeting of the State Level Expert Appraisal Committee (SEAC) was held on 14th
September, 2016 at Committee Room, Gujarat Pollution Control Board, Gandhinagar. Following
members attended the meeting:
1. Shri T. P. Singh, Chairman, SEAC.
2. Shri V. C. Soni, Vice Chairman, SEAC.
3. Dr. V. K. Jain, Member, SEAC
4. Dr. Mayuri Pandya, Member, SEAC
5. Shri R J Shah, Member, SEAC.
The agenda of TOR/Scoping/Category 8 (a) cases & EC amendment cases was taken up. One (1)
case of TOR/Scoping/Category 8 (a) and two (two) cases of Appraisal was taken up. The applicants
made presentations on the activities to be carried out along with other details furnished in the Form-1 /
Form-1A, EIA report and other reports.
1. SIA/GJ/IND2/10624/2016 M/s: Nebula Pharma LLP,
Survey no. 60, Vill. Ankhol, Ta. Kadi, Dist. Mehsana
Screening & Scoping
Project / Activity No.: 5(f)
M/s: Nebula Pharma LLP (herein after Project Proponent – PP) has submitted application vide
their proposal no. SIA/GJ/IND2/10624/2016 dated 26/03/2016.
Project proponent was called for presentation on 04/05/2016.
As per amendment to EIA Notification, 2006 vide SO 1599 (E) dated 25.06.2014, small units
are categorized as Category “B” projects. Small units are defined as with water consumption
less than 25 M3/day; Fuel consumption less than 25 TPD; and not covered in the category of
MAH units as per the Management, Storage, Import of Hazardous Chemical Rules (MSIHC
Rules), 1989. During presentation, PP informed that water consumption is 19.2 KL/day. Fuel
consumption is 2 MT/day and Chemicals to be used are not covered in MAH category. Hence,
this project falls under Category B of project activity 5(f) as per the EIA Notification 2006.
While discussing about the treatability of the waste water to be generated from the proposed
products, PP informed that the entire quantity of effluent will be evaporated after primary
treatment. However, PP could not reply satisfactorily regarding characteristics of the effluent
stream and VOC management during w/w treatment. Committee desired to know about the
exact quality and quantity of the waste water and its treatability. Committee observed that at
present there is no common facility available for waste water treatment in the vicinity of the
proposed site. Committee also discussed about the proposed evaporation system and its
efficacy. Considering the above facts, it was unanimously decided to consider the project for
TOR/Scoping only after satisfactory submission of the following:
Revised proposal with sound environmental management system including (i) Product wise
quality & quantity of waste water to be generated.(ii) Technical details of ETP & Evaporation
system.
Page 48 of 54
Project status: New
Project / Activity Details:
This is a new unit proposes the manufacturing of Synthetic organic chemicals (Bulk Drugs) as
tabulated below:
Sr.
no.
Product Name Quantity
MT/Month
1. Propyl Paraben 25
2. Methyl Paraben 50
3. Sodium Propyl Paraben 50
4. Sodium Methyl Paraben 100
Total 225
The project falls under Category B of project activity 5(f) as per the EIA Notification 2006.
The project proponent has applied for manufacturing of API drugs. A plot of 12486 sq. m area has
been acquired for this new project. Unit has proposed 4120.38 sq. m of green belt development.
Total cost of the project is Rs. 2 Crores. Total fresh water consumption for the proposed project
will be 19.2 KL/day which will be sourced from Bore well. Source of waste water generation is
mainly from process, water treatment & utilities. Total industrial waste water generation will be 8.4
KL/day, which will be sent to common facility (Spray dryer unit) namely M/s: Chhatral Environment
Management System Pvt. Ltd., (CEMSPL) Chhatral after primary treatment. Domestic waste water
(0.8 KL/day) discharged into soak pit through septic tank. Unit has proposed one Boiler (cap.: 1
TPH) and one HAG in which Agro waste briquettes (10 MT/Month & 40 MT/Month respectively)
will be used as fuel. Multi Cyclone separator followed by Bag filter is proposed as APCM. Two
spray dryers (200 Kg/hr each) and one spin flash dryer is proposed. Cyclone separator followed
by water scrubber and bag filter will be facilitated as APCM with Spray dryer and Spin splash dryer
respectively. One DG set (75 KVA) is proposed as stand-by facility. No process gaseous emission
is envisaged. Hazardous waste generated from the manufacturing activity will be ETP sludge &
Evaporation residue (3 MT/Month), Discarded containers/liners (0.2 MT/Month) and Used oil (200
Lit./Yr.)
Observations & Discussions:
Technical presentation made during the meeting by project proponent. While discussing about the
waste water management, PP informed that the common spray dryer facility of CEMSPL will be
operative within 2-3 months and entire quantity of waste water will be sent to CEMSPL through
dedicated tankers. Committee noted that there is no process gas emission from the proposed
project. During meeting Project proponent has requested to consider the project as B2 category
project. Looking to the small scale of the project and low pollution potential, the request was
considered and the project was categorized as B2 and the additional information was sought for
appraisal of the project.
33. Land Possession Documents of the proposed site. NA permission letter from concern
authority.
34. Demarcation of proposed project activities in lay out plan.
Page 49 of 54
35. Exact details about infrastructural facilities, plant machineries etc. required for the proposed
project.
36. Details of surrounding industrial units within 2 km radius with details like Name and address of
the unit, type and nature of industrial activity etc.
37. Project site specific details such as aerial distance of the project site from the nearest (1)
Village-Nearest residential area N(2) Water Body: Creek / Nallah / Lake / Pond / Reservoir /
Canal (3) National Highway (4) State Highway (5) Railway line (6) Heritage site (7)
Aanganwadi/School/College/Institute etc. and likely impact on them due to the proposed
project along with the mitigation measures proposed to minimize the likely impact. Give
satellite image of 2 km radius.
38. Ensure that there is no National Park / Wild Life Sanctuary/Eco Sensitive area etc. Within 10
km radius of the proposed project.
39. Legal Undertaking stating that unit is complying the three conditions [i.e. water consumption
less than 25 M3/day; Fuel consumption less than 25 TPD; and not covered in the category of
MAH units as per the Management, Storage, Import of Hazardous Chemical Rules (MSIHC
Rules), 1989] as per the amendment to EIA Notification, 2006 vide SO 1599 (E) dated
25.06.2014.
40. Layout plan of the factory premises. Provision of separate entry & exit and adequate margin
all round the periphery for unobstructed easy movement of the emergency vehicle / fire
tenders without reversing back. Mark the same in the plant layout.
41. Proposed monthly production of each product and product wise monthly consumption of each
raw material.
42. Chemical name of each proposed product to be manufactured. Details on end use of each
product. Manufacturing process along with chemical reactions, mass balance for each
product.
43. Water balance diagram (including reuse-recycle, if any) along with qualitative and quantitative
analysis of each waste stream to be generated from the manufacturing process of each
product to be manufactured along with mass balance.
44. Stream wise qualitative & quantitative analysis of each waste stream (including process
water, cooling tower blow down, boiler blow down, washing effluent etc.) to be generated.
Give segregation scheme at source. Characteristics of untreated and treated wastewater. A
detailed effluent treat ability study vis-à-vis the adequacy and efficacy of the treatment
facilities proposed for the wastewater to be generated. The characteristic on which treatability
is based shall also be stated.
45. Details of the ETP units including its capacity, size of each unit, retention time and other
technical parameters. Details regarding provision of online continuous pH meter, TOC
analyser and flow meter at the final outlet of the ETP.
46. Membership of Common Environmental Infrastructure facility i.e. Common spray dryer
CEMSPL.
47. Plans for management and disposal of waste streams to be generated from spillage,
leakages, vessel washing, used container washing etc. Measures proposed for preventing
Page 50 of 54
effluent discharge during unforeseen circumstances.
48. Specific details of (i) Process gas emission from each unit process with its quantification, (ii)
Air pollution Control Measures proposed for process gas emission, (iii) Adequacy of the air
pollution control measures for process gas emission, measures to achieve the GPCB norms
(iv) Details of the utilities required (v) Type and quantity of fuel to be used for each utility (vi)
Flue gas emission rate from each utility (vii) Air Pollution Control Measures proposed to each
of the utility along with its adequacy (viii) List the sources of fugitive emission along with its
quantification and proposed measures to control it.
49. Specific details of fugitive emission from the unit along with its quantification and proposed
measures to control it along with measures proposed to monitor VOC within work area.
Details of ventilation system proposed in the work area. Measures proposed to keep the work
area environment as per the norms of GFR.
50. Details of measures proposed for noise pollution abatement & its monitoring.
51. Details of management of the hazardous wastes to be generated from the project stating
detail of storage area for each type of waste, its handling and its disposal. How the manual
handling of the hazardous wastes will be minimized?
52. Methodology of de-contamination and disposal of discarded containers and its record
keeping.
53. Measures proposed to be taken for the work area ambient air quality monitoring as per
Gujarat Factories Rules.
54. A detailed EMP including the protection and mitigation measures for preventing impacts on
human health and environment as well as detailed monitoring plan with respect to various
parameters and responsible head for the environmental management cell and environmental
management cell proposed for implementation and monitoring of EMP.
55. Detailed socio-economic development measures including community welfare program most
useful in the project area for the overall improvement of the environment.
56. A detailed Green Belt Development Program including annual budget, types & number of
trees to be planted, area under green belt development [with map]; along with commitment of
the management to carry out the tree plantation activities outside the premises at appropriate
places in the Industrial estate and elsewhere.
57. Details of hazardous characteristics and toxicity of raw materials and products to be handled
and the control measures proposed to ensure safety and avoid the human health impacts.
This shall include the details of Antidotes also.
58. Details of quantity of each hazardous chemical to be stored, Material of Construction of major
hazardous chemical storage tanks, threshold storage quantity as per schedules of the
Manufacture, Storage & Import of Hazardous Chemicals Rules of major hazardous chemicals.
How the manual handling of the hazardous chemicals will be minimized?
59. Details of the separate isolated storage area for chemicals. Details of fire extinguishers, flame
proof electrical fittings, DCP extinguishers and other safety measures proposed.
60. Specific safety details / provisions for various hazardous chemicals and detailed fire control
plan for flammable substances.
Page 51 of 54
61. Details of possibilities of occupational health hazards from the proposed manufacturing
activities and proposed measures to prevent them.
62. Detailed risk assessment report including prediction of the worst-case scenario and maximum
credible accident scenario along with damage distances and preparedness plan to combat
such situation and risk mitigation measures. Vulnerable zone demarcation.
63. Submit checklist in the form of Do’s & Don’ts of preventive maintenance, strengthening of
HSE, mfg utility staff for safety related measures.
64. A tabular chart with index for point-wise compliance of above details.
The project shall be appraised on satisfactory submission of the above.
19. SIA/GJ/IND2/16818/2015 M/s: Hindusthan Speciality Chemicals Ltd.,
Plot No:830, GIDC-Jhagadia, Dist.: Bharuch. EC amendment
Project / Activity No.: 5(f)
M/s: Hindusthan Speciality Chemicals Ltd. (herein after Project Proponent – PP) has
submitted application vide online application no. SIA/GJ/IND2/16818/2015 dated 22/07/2016 for EC amendment.
Project status: Existing
Project / Activity Details:
This is an existing Specialty Chemical manufacturing unit which was accorded Environmental
Clearance vide letter no. SEIAA/GUJ/EC/5(f)/3570/2015 dated 22/09/2015. Environmental
Clearance was granted with a condition to use HSD – 0.602 MTPH shall be used as a fuel in the
proposed Boiler - 02. The project proponent requested for amendment in Environmental
Clearance order dated 22/09/2015 with respect to the change in fuel from HSD to FO or NG for
the proposed Steam Boiler. In addition to this, PP also requested to add one Thermic Fluid Heater
(Cap. 4 Lac K cal/hr) with fuel consumption HSD – 44 Kg/hr.
The request was considered during the meeting and it was presented that the EC was granted for
HSD as fuel for Boiler. Now, they intend to change fuel as FO or NGfor their boiler. PP informed
that FO price have dropped drastically in the last one year and there is no change in HSD price.
Upon asking regarding detailed justification for price difference and justification for installation of
new TFH, project proponent could not reply satisfactorily. After detailed discussion on the matter,
It was decided to further appraise the project only after submission of the following:
6. Detailed justification for (1) proposed change in fuel along with the authentic documents and
(2) Justification for installation of new TFH which was not listed in the existing Environmental
clearance.
7. Specific details on (i) Type, quantity and quality (CV, Sulphur content, Ash content, etc,) of
coal to be used (iii) Flue gas emission details (iv) Air pollution Control Measures along with its
adequacy to achieve the GPCB Norms. (v) List the sources of fugitive emission from the unit
along with its quantification and proposed measures to control it.
8. Base line status of ambient air quality and its comparison with ambient air quality results
mentioned in previous EIA Report for assessing change in ambient air quality.
9. Prediction of likely impacts on ambient air quality due to change of fuel (Type and quantity) by
use of modeling. Air quality modeling to be carried out considering the worst case scenario
Page 52 of 54
partial and complete failure of the APCM. The details of model used and input parameters
used for modeling should be provided. The air quality contours may be shown on location map
clearly indicating the location of sensitive receptors, if any, and the habitation. The wind rose
showing pre-dominant wind direction should also be indicated on the map.
10. A detailed EMP including the protection and mitigation measures for the impacts on human
health and environment due to this proposed change as well as detailed monitoring plan.
3. SIA/GJ/IND2/16896/2015 M/s: Eshyasi Pharma Ltd.
S.No.590-A and 592-A, Luna, Padra, Vadodara EC amendment
Project / Activity no.: 5(f)
M/s: Eshyasi Pharma Ltd. (herein after Project Proponent – PP) has submitted application vide online application no. SIA/GJ/IND2/16896/2016 dated 22/07/2016 for EC amendment.
Project status: Existing
Project / Activity Details:
This is an existing Bulk drug manufacturing unit which was accorded Environmental Clearance
vide letter no. SEIAA/GUJ/EC/5(f)/316/2016 dated 10/05/2016. Environmental Clearance was
granted with a condition to maintain Zero Liquid Discharge (ZLD).
The project proponent requested for amendment in Environmental Clearance order dated
10/05/2016 with respect to the change in mode of disposal of waste water.
The request was considered during the meeting and it was presented that the EC was granted to
maintain Zero Liquid Discharge (ZLD) by means of primary treatment followed by Evaporator.
Now, project proponent proposed to change in mode of disposal by sending waste water to CETP
of M/s: Enviro Infrastructure Co. Ltd. [EICL]. Upon asking about the justification for proposed
change in mode of disposal, PP informed that they required EC amendment due to recent policy
of GPCB regarding waste water disposal into common facility for the Padra region. Unit has
obtained membership certificate of M/s: EICL with discharge quantity 1 KL/day. PP has furnished
a CTE rejection order dated 01/09/2016 issued by GPCB.
The committee was satisfied with the clarification given by the project proponent and decided to
forward the proposal to SEIAA for the grant of amendment in environment clearance by replacing
the Specific condition no. 5, 6 and Water condition no. 7, 12, 13, 14, 15, 16 & 17 of Environmental
Clearance vide letter no. SEIAA/GUJ/EC/5(f)/316/2016 dated 10/05/2016 as below and with rest
of conditions same as prescribed in the said Environmental Clearance dated 10/05/2016.
Specific Condition no. 5
Entire quantity of effluent to be generated from the proposed production shall be completely sent
to CETP of M/s: Enviro Infrastructure Co. Ltd.[EICL] and shall not be discharge within or outside
the premises, in any case.
Specific Condition no.6
Unit shall provide buffer water storage tank of adequate capacity for storage of treated waste
water before sending to CETP.
Water Condition no.7
Total water consumption for the proposed project shall not exceed 4 KL/day and it will be sourced
Page 53 of 54
from the Bore well. Necessary permission from the CGWA shall be obtained for withdrawal of
ground water.
Water Condition no.12
Waste water generated from the manufacturing process (0.5 KL/day) shall be passed through
solvent stripper after neutralization. Generated mixed solvent (0.1 KL/day) shall be sold out to
authorized re-refiners and remaining effluent (0.4 KL/day) shall be sent to CETP M/s: Enviro
Infrastructure Co. Ltd.[EICL] along with washing & utility waste water (0.65 KL/day).
Water Condition no.13
The stripped effluent (0.4 KL/day) shall be mixed with the washings and utility streams and after
passing through distillation unit entire effluent (0.9 KL/day) shall be sent to CETP M/s: Enviro
Infrastructure Co. Ltd.[EICL].
Water Condition no.14
The unit shall continuously strive to reduce, recycle and reuse the treated effluent.
Water Condition no.15
Unit shall obtain membership certificate for minimum 1 KL/day from the CETP of M/s: Enviro
Infrastructure Co. Ltd.[EICL]. Waste water shall be sent to CETP through dedicated tankers only.
Water Condition no.16
The unit shall provide adequate effluent treatment plant (ETP) & Stripping column and primary
treated effluent conforming CETP inlet norms shall be sent to CETP.
Water Condition no.17
Proper logbook of ETP and Stripping column operation, effluent sent to CETP etc. shall be maintained and
furnished to the GPCB from time to time
Meeting ended with thanks to the Chair and the Members.
Minutes approved by:
1. Shri T. P. Singh, Chairman, SEAC.
2. Shri V. C. Soni, Vice Chairman, SEAC.
3. Dr. V. K. Jain, Member, SEAC
4. Dr. Mayuri Pandya, Member, SEAC
5. Shri R J Shah, Member, SEAC.
Page 54 of 54