TheCryopit
Fraser DuncanCryopit Workshop16 August 2011
Underground Campus
Personnel facilities
SNOCavern
Ladder Labs
Cube Hall
Cryopit
SouthDrift
HALOStub
J-Drift
UtilityArea
Fraser Duncan Cryopit Workshop 16 Aug 2011
Cryopit Workshop 16 Aug 2011
Cryopit
Fraser Duncan
SNOLAB, an expansion of the original SNO laboratory, was proposed by the original SNO Canadian universities (Carleton, Guelph, Laurentian, Queen's and UBC) and University of Montreal with Carleton University as the Lead institution.
The project was divided into Phase I (Cube Hall, Ladder Labs, new lab entrance) and Phase II (the Cryopit) to provide a break point to control project cost. The Cryopit, at $16M, was an addition to the initial SNOLAB grant and was funded 50% from federal and 50% from provincial contributions.
It was conceived as a hall that could readily be isolated from the rest of the underground facility in the case that it contained a large inventory of cryogens or other substances that could displace significant volumes of air.
Excavation began in 2007 and was completed in 2008. Was brought to a clean room state in March 2011.
Third largest cavity after the SNO Cavern and Cube Hall (about 1/3 the size of the SNO Cavern).
Cryopit Workshop 16 Aug 2011
History
Fraser Duncan
Cryopit Workshop 16 Aug 2011Fraser Duncan
BAR (Bottom Access Drift)
Cryopit
Bottom AccessRamp Airlock
STAC(StagingAreaCryopit)
Cube Hall
TAC(Top AccessCryopit)
J-Drift
Notches forPressureBulkheads
Cryopit Workshop 16 Aug 2011Fraser Duncan
Limited “As Built”Surveys have beenDone
The CryopitThe Cryopit
Cryopit
STAC (Staging Area Cryopit)
STAC (Staging Area Cryopit)
Cryopit Utility Drift(J-2 Drift)
TAC (Top Access Cryopit)
Bottom AccessDrift
Bottom AccessRampAirlock
The Cyropit is designed to be operated at a higher air pressure than the surrounding areas to force dust out. The air is recirculated through HEPA filters.
Particulate measurements are done on a regular basis. With no work being done in the Cryopit, achieving much better than the class 2000 goal.
Cryopit Workshop 16 Aug 2011
Cleanliness
Fraser Duncan
Present:
Ventilation: Nominally 5 air changes/hr through HEPA filtered, cooled air.
Fire Water and Chilled Water (also available for process equipment).
Future:
Power: Design is for a 400 A service at 600 V phase with a Motor Control Centre located south of the Cryopit.
Communications: Tie in to existing fibre network.
Fire Detection: Detection and alarming contract issued and should be complete by year end.
Plumbing: Industrial Water, Ultra Pure Water, Forced Drain, Compressed Air.
Cryopit Workshop 16 Aug 2011
Services
Fraser Duncan
Safe venting in the case of cryogenic boil off or other release of inert gas.
1200 ft (370m) run from Cryopit to sealed exhaust raise.
Possibly install pressure bulkheads around the cryopit.
Need to coordinate with other experiments also planning to use vent raise.
MC Collab Mtg Yale 19-21 July 2011
Exhaust Venting
Fraser Duncan
Cryopit Workshop 16 Aug 2011Fraser Duncan
Cryopit Configuration Options
Cryopit Workshop 16 Aug 2011Fraser Duncan
Option: Stand Alone Tank
Cryopit Workshop 16 Aug 2011Fraser Duncan
Option: Spray on Liner
Cryopit Workshop 16 Aug 2011Fraser Duncan
Option: Small Tank and Deck
The Cryopit has been a 3,900 m3 class 2000 clean room since May 2011. Beneficial occupancy could occur Jan 2011 with completion of fire detection. Electrical infrastructure would also need to be installed.
Could deploy a short term experiment almost immediately by constructing a small tank and deck.
Fully exploiting the cavity would (likely) require design and installation of large deck and liner/tank.
Cryopit Workshop 16 Aug 2011
Summary
Fraser Duncan
End