Upload
others
View
0
Download
0
Embed Size (px)
Citation preview
I LDJ R
12-071
The Preparatory Survey on
the Project for Introduction of Clean Energy by Solar Electricity Generation System
in Georgia
FINAL REPORT
MARCH 2012
JAPAN INTERNATIONAL COOPERATION AGENCY
ORIENTAL CONSULTANTS CO., LTD.
MINISTRY OF ECONOMY AND SUSTAINABLE DEVELOPMENT OF GEORGIA THE GOVERNMENT OF GEORGIA
The Preparatory Survey on
the Project for Introduction of Clean Energy by Solar Electricity Generation System
in Georgia
FINAL REPORT
MARCH 2012
JAPAN INTERNATIONAL COOPERATION AGENCY
ORIENTAL CONSULTANTS CO., LTD.
MINISTRY OF ECONOMY AND SUSTAINABLE DEVELOPMENT OF GEORGIA THE GOVERNMENT OF GEORGIA
SUMMARY
SUMMARY
1. Outline of the Country
Georgia is located at the north end of Western Asia and east of the Black Sea. Georgia is bordered
on the north by Russia, on the south by Turkey and Armenia and on the east by Azerbaijan. With
these geographical features, Georgia has played a significant role in transportation between
Europe and Asia in the past. Georgia has 69.7 thousand km2 of area and 4.2 million of population.
Georgia is one of the former USSR countries and attained independence in 1991. The capital city
of Georgia is Tbilisi.
Georgia has two different climates, one west and the other east of Surami Mountain, which is in
the middle of the country. The west side is a subtropical area. With the Black Sea on its west, the
area is blessed with rainfall and fertile land. Throughout the year the area is relatively warm,
daytime temperature usually reaches 30 degrees Celsius in summer and 10-15 degrees Celsius in
winter. Whereas, the east side, where the capital city of Tbilisi is located, is dry and categorized as
a continental climate. The temperature depends on the elevation. Daytime temperature reaches
30-35 degrees Celsius in summer and average hours of sunshine is more than eight hours a day
from June to August. Whereas, daytime temperature is usually 0-10 degrees Celsius in winter but
can reach -10 degrees Celsius at night. Total annual period of daylight in Georgia is more than
2,000 hours and that of Tokyo is 1,800-1,900 hours. The northern mountainous parts are relatively
cool and it snows occasionally.
Its population of 4.2 million is composed of Georgian (83.8%), Azerbaijanian (6.5%), Armenian
(5.7%), Russian (1.5%) and Ossetian (0.9%). The capital city of Tbilisi has a population of
approximately 1.2 million people.
GDP of Georgia is 10.7 billion US dollars and GDP per capita is 2,450.3 US dollars. Inflation rate
was 10% in 2008 but stopped its rapid increase and recorded 1.7% in 2009. Recently the economy
of Georgia has been experiencing contraction because of the armed conflicts with Russia in
August 2008 and recent economic crisis. Georgia has exported and imported power to/from
neighboring countries. Georgia has particularly turned to import it from Turkey in winter.
2. Background and Outline of the Project
In terms of both energy policy and security guarantees, energy sector reform has been an
important task in Georgia. That is due to a growing need for commitment to international
standards and its situation such that Georgia has to turn to neighboring countries for almost all of
the fuel for thermal power generation. In fact, there was a temporary stop of natural gas supply
due to pipe line damage in 2006. In response to this accident, Georgia has made and declared its
plan for energy independence.
1
Recognizing the physical, human, and social disasters brought by ecosystem destruction and
meteorological disasters due to climate change, Georgia sees climate change as one of its top
priority agendas. Georgia ratified the United Nations Framework Convention on Climate
Change (UNFCCC) in 1994 and Kyoto Protocol as one of the Non-Annex I countries in 1999.
Later it established the National Research Center to start policies on the climate change in 1996.
In January, 2003, the National Agency on Climate Change (NACC)which belonged to the
Ministry of Environment of Georgia was designated as a Designated National Authority (DNA)
of Georgia which handles clean development mechanism (CDM). Then the Ministry of
Environmental Protection and Natural Resources of Georgia (currently the Ministry of
Environmental Protection of Georgia) became a new DNA in January 2005.
In terms of climate change, it is intended to elaborate a National Adaptation Plan of Action
(NAPA), which was formulated in 2009. In the plan were held up three policies of 1) Taking
effort against climate change, 2) Utilizing CDM scheme and 3) Improvement of public awareness
to the climate change. As for the energy section, it’s aimed to pursue utilizing renewable
energies (hydro power, wind power, solar power, geothermal power and biomass).
Japan has established a new financial mechanism of “Cool Earth Partnership” in order to help
developing countries both in reduction of green house gases and economic development. As a
part of this mechanism, Grant Aid for the Environment Program was introduced to provide
financial support and capacity development.
With this background, the purpose of this project is to introduce a grid connected PV system. In
addition, related equipment and materials will be procured and technical assistance for the
operation and maintenance will be provided.
3. Study Results and Project Contents
Four candidate sites were initially requested as installation locations of the PV system by Georgia.
Each candidate site and the purpose of electric power are as follows.
Requested candidate site (initial)
Priority Level
Candidate Site Name Generation Capacity
Installation Location & Area Use of Generated Power
1 Ministry of Environmental Protection and Natural Resources
Approx. 177kW
Roof, walls, and entrance area (Approx. 4,700 sq m)
Ministry building
2 Tsuerovani refugee camp Approx. 777kW
Unoccupied land in the camp (Approx. 22,500 sq m)
Houses and facilities in the camp
3 Ilia State University Approx. 70kW Unoccupied land in the
university campus (Approx. 2,350 sq m)
University campus
4 Tbilisi No. 199 school Approx. 60kW Schoolhouse roof top (Approx. 2,100 sq m)
School premises including dormitory
The site selection was implemented according to the following six criteria.
2
Security of the facilities
Sustainability of the facilities
Grid connectivity
Capability of operation and maintenance for the PV system
Sun shadow effect
Showcase effect of the PV system
Comprehensive evaluation of each location according to the criteria, are as follows.
(1) Ministry of Environmental Protection and Natural Resources
Since the Ministry of Environmental Protection and Natural Resources (hereafter referred to as
“MoEPNR”) is in charge of acting as contact Ministry concerning the Clean Development
Mechanism (CDM) as of 2009 and promoting clean energy, it’s expected that introduction of the
PV system to MoEPNR would be appealing to the public. Also due to a main road and traffic
in front of MoEPNR, the PV system will be seen by a large number of people, which is what we
call the showcase effect. At MoEPNR, sustainability of the facilities and interconnectivity are
ensured. In addition, capability of operation and maintenance can also be provided by
technical assistance (soft component). However, the deterioration of the ministry building has
to be taken into account in selecting an installation site. Furthermore, due to shadow which
would be cast by surrounding buildings, it’s estimated that generation efficiency would be lower
than the other candidate sites.
(2) Tserovani Refugee Camp
Even though the installation site will not be affected by shadow, and it can be ensured that
enough generation capacity and interconnection will be easy, the site is located away from the
highway and showcase effect is expected to be low. Furthermore, there are also problems in
continuity, safety, and operation and maintenance, which are intrinsic to refugee camps.
(3) Ilia State University
Appealing to and enlightening of the students regarding the PV systems is expected as well as a
showcase effect because of the installation location facing the main road. As the installation
site is located in the university campus, facility safety, continuity and interconnectivity are
assured. There will be no problems in operation and maintenance if technical assistance (soft
component) is provided.
(4) Tbilisi No.199 School
Appealing to and enlightening of the students regarding the PV system can be expected but the
schoolhouse is too old to be safe for installing the equipment unless a great deal of repairing is
carried out. There is some concern about the capability for operation and maintenance.
As a result of discussions between Georgia and Japan, MoEPNR and Ilia State University were
3
selected as candidate sites. The reasons are: Tserovani Refugee Camp has problems in continuity
and safety and Tbilisi No.199 School does not have enough space for the installation.
Despite what was described above, MoEPNR was removed from the list of candidate sites since
the Georgian government restructured its government ministries and agencies in February 2011,
and an additional candidate site of Tbilisi International Airport (hereinafter referred to as TIA)
was added as shown below.
Requested candidate site (Additional)
Candidate Site Name Power Generation Capacity Installation Location & Area Use of Generated Power
Tbilisi International Airport
Approx. 200kW In the Parking Space (Approx. 4,100sq m)
Terminal building
Comprehensive evaluation of TIA according to the criteria is as follow.
(5) TIA
TIA is the largest airport in Georgia and a gateway for more than 820,000 tourists a year. It’s
expected that introduction of the PV system to the airport would be appealing to the public and
promote clean energy. The PV system will be installed in front of the terminal building, the
system is expected to be seen by a large number of people. At the Airport, sustainability of the
facilities and interconnectivity are ensured as well as capability of operation and maintenance
by existing technical staff for operation and maintenance. In addition, operation and
maintenance will be enhanced by technical assistance (soft component). However, the
installation space for the PV system is limited to the green zone in the Parking area because it is
impossible to decrease Parking space. Furthermore, influence of the existing facilities has to
be studied in the construction work.
As a result of a comprehensive consideration, TIA and Ilia State University were chosen as
project sites of this project.
The responsible agency for the project is the Ministry of Economy and Sustainable Development
of Georgia. The implementing agencies are United Airports Georgia (hereinafter referred to as
UAG) and Ilia State University respectively at TIA and Ilia State University. Tbilisi Electricity
Network (TELASI) will take charge of the practical and technical parts of the project including
authorization for power receiving and distribution, technical support and coordination. Georgia
has no precedents in reverse power flow, power selling or setting up related regulations or
institutions. Therefore, the PV system without reverse power flow is proposed, however, Georgia
plans to conduct reverse power flow by itself in the future when appropriate regulations and
institutions are set up. Therefore, equipment procurement and technical assistance related to
reverser power flow are included in the project.
4
Outline of the Grant Aid Program
Equipment procurement for PV system
Equipment Use of power generated Needs
Grid connected PV system
Generated power is supplied to facilities by a grid connected PV system
Promotion of renewable energy is needed out of concern for the ecosystem disruption in consequence of climate change and increasing physical, human and social damage due to meteorological disaster.
Technical Assistance for grid-connected PV system (Soft Component)
Technical assistance
Training on basic technical knowledge of PV system and on the operation and maintenance thereof including inspection and troubleshooting.
To address the lack of technical knowledge for operation and management of PV systems, because it has not been introduced in Georgia up to now.
Outline of the PV system at TIA
Responsible agency Ministry of Economy and Sustainable Development of Georgia
Implementing agency United Airports of Georgia
Location TIA (Parking and Open Space)
Location environment International Airport Parking in capital city of Tbilisi
Owner of the land United Airports of Georgia
Licensing United Airports of Georgia
Power-generating capacity Approximately 310kW
Estimated annual power generation Approximately 329,000kWh
Area of installation Approximately 4,100sq m
Use of power generated Electric power in the terminal building
Reduction of CO2 emission 182.594t/year
Perspective at TIA
5
Outline of the PV system at Ilia State University
Responsible agency Ministry of Economy and Sustainable Development of Georgia
Implementing agency Ilia State University
Location Ilia State University premises
Location environment Center of the capital city of Tbilisi
Owner of the land Ilia State University
Licensing Ilia State University
Power-generating capacity Approximately 37kW
Estimated annual power generation Approximately 32,000kWh
Area of installation Approximately 420sq m
Use of power generated Electric power in university campus
Reduction of CO2 emission 17.76t/year
Perspective at Ilia State University
6
Equipment Specification Plan for TIA
Item Specification Qty Uses
PV module Mono or Poly-crystalline Cell not less than 310kW
1 set To transform solar light to electricity.
Supporting structure for PV
modules
1 set To fix the PV modules on the frame structure and concrete foundation
Rotation operation control
panel
DC electromagnetic contactor, changing-over switch, yearly timer and others Ingress Protection: not less than IP20
1 set Four out of five power conditioners will operate in rotation
Power conditioners
Rated capacity: not less than 310kW (including step-up transformers) More than five sets (including one back-up) are to be combined and synchronized power conversion efficiency: not less than 90%Output harmonic: less or equal to 5% in total, less or equal to 3% each Output power factor: not less than 0.95 Protective relay: Over Voltage Relay (OVR) Under Voltage Relay (UVR) Over Frequency Relay (OFR) Under Frequency Relay (UFR) Detection of islanding operation (Passive
and active) Manual operation start-up Ingress Protection: not less than IP20
1 set To convert direct current power generated by the PV modules to alternating current power To control power, voltage and frequency in relation to the PV system
Junction Box
Direct current switchgear, surge protection device, power back-flow prevention device, terminal block and etc. Ingress Protection: not less than IP53
1 set To collect direct current generated by the PV system and connect it to the power conditioner
Grid Connecting Board
Alternating current switchgear and etc. Ingress Protection: not less than IP20
1 set To collect the alternating current output from power conditioner and connect it to the electric substation
Power Factor Improvement
Static Capacitor Board
Rating: 3P 3W 380V 50Hz Main circuit breaker: MCCB Capacitor: equivalent to 400kVA Series reactor: equivalent to 24kVA (L=6%) Automatic power factor control Ingress Protection: not less than IP20
1 set To improve the power factor of receiving points
Data Management
and Monitoring Systems
Personal computer LCD (15 inch or more) Data sensing instruments Signal transmitter UPS (Capacity of 10 minutes or more) Color printer (Size: up to A3) Software for data monitoring Software for external large display
1 set To track the amount of power generated, input/output voltage from/to power conditioners, solar radiation, air temperature etc. as well as to record and display them in the specified format to be set To operate the indoor type large display
Pyranometer 1 set To observe solar radiation Meteorological observation instruments
Thermometer 1 set To observe air temperature
Large display Size: not less than 100-inch (Liquid crystal, PDP or LED)
1 set To indicate power generated and meteorological data etc. for showcases
Infrared thermograph camera 1 set Instrument to measure the temperature of the PV module surface
Maintenance equipment
Insulation tester (Megger) 1 set Instrument to measure insulation of cables and devices
7
Item Specification Qty Uses
Digital circuit tester 1 set Instrument to measure voltage, current and impedance of cables and devices
Electrical Detector (for medium, AC/DC low voltage)
1 each Devices to check presence of voltage
Insulated rubber gloves 1 pair To avoid an electric shock
Insulated Rubber boots 1 pair To avoid an electric shock
Equipment Specification Plan for Ilia State University
Item Specification Qty Uses
PV module Mono or Poly-crystalline Cell not less than 37kW
1 set To transform solar light to electricity.
Supporting structure for PV
modules
1 set
To fix the PV modules on the frame structure
Power conditioners
Rated capacity: not less than 37kW (including step-up transformers) More than four sets are combined and synchronized power conversion efficiency: not less than 90% Output harmonic: less or equal to 5% in total, less or equal to 3% each Output power factor: not less than 0.95 Protective relay: Over Voltage Relay (OVR) Under Voltage Relay (UVR) Over Frequency Relay (OFR) Under Frequency Relay (UFR) Detection of islanding operation (Passive
and active) Manual operation start-up Ingress Protection: not less than IP20
1 set
To convert direct current power generated by the PV modules to alternating current power To control power, voltage and frequency in relation to the PV system
Junction Box
Direct current switchgear, surge protection device, power back-flow prevention device, terminal block and etc. Ingress Protection: not less than IP53
1 set
To collect direct current generated by the PV system and connect it to the power conditioner
Grid Connecting Board
Alternating current switchgear and etc. Ingress Protection: not less than IP20 1 set
To collect the alternating current output from power conditioner and connect it to the electric substation
Electric substation
Receiving voltage: 3-phase 3-wire 6 kV50Hz Main circuit breaker: VCB3P630A Transformer: 250 kVA 3-phase 3-wire 4W380/220V Protective relay: OVGR, OCR, RPR, PT Ingress Protection: not less than IP53
1 set
To interconnect the PV system with the grid.Protection relays are built in the system
Data management and
monitoring systems
Personal computer LCD (15 inch or more) Data sensing instruments Signal transmitter UPS (Capacity of 10 minutes or more) Color printer (Size: up to A3 ) Software for data monitoring Software for external large display
1 set
To track the amount of power generated, input/output voltage from/to power conditioners, solar radiation, air temperature etc. as well as to record and display them in the specified format to be set
8
Item Specification Qty Uses
Data management and
monitoring systems for education
Personal computer LCD (15 inch or more) UPS (Capacity of 10 minutes or more) Color printer (Size: up to A3 )
1 set
To educate students
Pyranometer 1 set To observe solar radiation Meteorological observation instruments
Thermometer 1 set To observe air temperature
Large display Size: not less than 60- inch (Liquid crystal, PDP or LED)
1 set To indicate power generated and meteorological data etc. for showcases
Infrared thermograph camera 1 set
Instrument to measure the temperature of the PV module surface
Insulation tester (Megger) 1 set
Instrument to measure insulation of cables and devices
Digital circuit tester 1 set
Instrument to measure voltage, current and impedance of cables and devices
Electrical Detector (for medium, AC/DC low voltage)
1 eachDevices to check presence of voltage
Insulated rubber gloves 1 pair To avoid an electric shock
Maintenance equipment
Insulated Rubber boots 1 pair To avoid an electric shock
4. Implementation Schedule
Total project implementation period will be 14 months, which consists of 4 months for detailed
design and tender process, 9 months for procurement and 1.5 months for the soft component.
5. Project Effect
The table below shows expected direct/indirect effects expected to be brought by the project.
Present situation and problems
Countermeasure by the project
Direct Effects Indirect Effect/Degree of
improvement
1 Georgia is insufficient in ability and funds to pursue both Green house gas (GHG) reduction and economic development
2 Georgia aims at energy independence because most of the fuel for thermal power generation is imported
1 Introduction of the grid connected PV system
2 Soft Component (Technical assistance) for operation and maintenance of the above said system
1 Annual reduction of 200 (t-CO2/year) in green house gas (GHG) emission
2 Showcase effects that the PV systems will be shown to 820 thousand persons and 6.55 million vehicles annually
1 Contribution to the upper level plan and promotion of dissemination and expansion of PV systems in Georgia
2 Contribution to the research and development of renewable energy and fostering of related industries in Georgia
6. Recommendations
(1) Issues to be addressed by the recipient country and recommendations
To attain the long term effects brought by the project, the following items shall be taken into
account after implementation of the project.
9
10
Georgia has aggressively promoted installation of renewable energy such as solar thermal and
wind power. Under such situation, it is essentially important to use the PV system of the project as
a jump start to promote PV power generation. Therefore, it is highly recommended that a policy
for introduction of renewable energy such as preferential taxation, subsidy, Feed-in Tariffs (FIT)
or Renewable Portfolio Standard (RPS) is formulated as quickly as possible.
(2) Technical cooperation and tie-up with other donors
Technical and economic assistance by Japan, international organizations and other developed
countries is essential for dissemination of PV power generation such as installation of PV systems
for residential buildings, work places and offices and establishment of PV power plants by private
companies. Therefore, in addition to technical assistance by Japanese private companies and
other possible bodies through international organizations such as PV panel manufacturers,
Institutionalization of grid connected PV systems including reverse power flow, high
performance and large scale battery systems, Smart Grids and so on, financial assistance is also
necessary.
CONTENTS
Summary
Contents
Location Map/Perspective
List of Figures & Tables
Abbreviations
Page
Chapter 1 Background of the Project 1-1 Background of the Request ................................................................................................ 1-1
1-2 Outline of the Request........................................................................................................ 1-1
1-3 Natural Conditions ............................................................................................................. 1-2
1-4 Social and Environmental Considerations ......................................................................... 1-3
Chapter 2 Contents of the Project 2-1 Basic Concept of the Project .............................................................................................. 2-1
2-1-1 Overall Goal and Project Objectives ............................................................................... 2-1
2-1-2 Outline of the Project ...................................................................................................... 2-2
2-2 Outline Design of the Requested Japanese Assistance....................................................... 2-2
2-2-1 Design Policy .................................................................................................................. 2-2
2-2-1-1 Basic Policy ........................................................................................................... 2-2
2-2-1-2 Policy for Natural Conditions ................................................................................ 2-7
2-2-1-3 Policy Related to Socio-Economic Conditions...................................................... 2-9
2-2-1-4 Construction/Procurement Affairs, Special Situations and Commercial
Customs ............................................................................................................... 2-10
2-2-1-5 Policy for Utilizing Local Companies ................................................................. 2-11
2-2-1-6 Policy for Operation and Maintenance ................................................................ 2-11
2-2-1-7 Policy for Equipment and Frame Structure Grade............................................... 2-11
2-2-1-8 Policy for Installation/Procurement Methods ...................................................... 2-12
2-2-1-9 Policy for Installation and Construction .............................................................. 2-13
2-2-2 Basic Plan (Construction Plan / Equipment Plan)......................................................... 2-13
2-2-2-1 Overall Plan ......................................................................................................... 2-13
2-2-2-2 Equipment Plan.................................................................................................... 2-26
2-2-2-3 Frame Structure Plan............................................................................................ 2-29
2-2-3 Outline of the Design Drawings.................................................................................... 2-38
2-2-4 Implementation Plan ..................................................................................................... 2-50
2-2-4-1 Implementation Policy ......................................................................................... 2-50
2-2-4-2 Implementation Conditions.................................................................................. 2-52
2-2-4-3 Scope of Works .................................................................................................... 2-52
2-2-4-4 Consultant Supervision ........................................................................................ 2-53
2-2-4-5 Quality Control Plan ............................................................................................ 2-53
2-2-4-6 Procurement Plan ................................................................................................. 2-56
2-2-4-7 Operational Guidance Plan .................................................................................. 2-58
2-2-4-8 Soft Component (Technical Assistance) Plan ...................................................... 2-59
2-2-4-9 Implementation Schedule..................................................................................... 2-62
2-3 Obligations of Recipient Country .................................................................................... 2-63
2-4 Project Operation Plan ..................................................................................................... 2-64
2-4-1 Operation and Maintenance Plan .................................................................................. 2-64
2-5 Project Cost Estimation.................................................................................................... 2-65
2-5-1 Initial Cost Estimation................................................................................................... 2-65
2-5-2 Operation and Maintenance Cost .................................................................................. 2-65
Chapter 3 Project Evaluation and Recommendations 3-1 Project Effect...................................................................................................................... 3-1
3-2 Recommendations .............................................................................................................. 3-2
3-2-1 Issues to be addressed by the recipient country and recommendations .......................... 3-2
3-2-2 Technical cooperation and tie-up with other donors ....................................................... 3-2
[Appendices]
1. Member List of the Study Team
2. Study Schedule
3. List of Parties Concerned in the Recipient Country
4. Minutes of Discussion
5. Soft Component (Technical Assistance) Plan
6. Simulation of Annual/Monthly Power Generation
7. Solar Panel Reflection Simulation
8. Reference
N
GEORGIA
Tbilisi
1,000km0
Tbilisi International Airport
Ilia State University
0 3km
N
Location Map
Perspective, Tbilisi International Airport
The Preparatory Survey on the Project for Introduction of Clean Energy by Solar Electricity Generation System in Georgia
Perspective, Ilia State University
LIST OF FIGURES Page
Figure 2-1 Observed data (Solar Radiation and Temperature in Tbilisi Area in 2000) ......2-7 Figure 2-2 Monthly Average Solar Radiation and Air Temperature in Tbilisi (NASA).......2-8 Figure 2-3 Outline of the PV system ...................................................................................2-13 Figure 2-4 Perspective at TIA (Parking and Open Space)..................................................2-21 Figure 2-5 Perspective at Ilia State University ..................................................................2-22 Figure 2-6 TIA Frame Layout Plan .....................................................................................2-32 Figure 2-7 Ilia State University Frame Structure Layout Plan ........................................2-33 Figure 2-8 TIA Frame Structure Section Plan (Parking) ...................................................2-34 Figure 2-9 TIA Supporting Structure Section Plan (Open Space) .....................................2-34 Figure 2-10 Ilia State University Frame Structure Section Plan ........................................2-35 Figure 2-11 Project Implementation Scheme........................................................................2-50
LIST OF TABLES
Page
Table 1-1 Natural Conditions in Tbilisi (2006-2008 Average) ............................................1-3 Table 2-1 Outline of the Project ...........................................................................................2-2 Table 2-2 Requested candidate sites (initial) ......................................................................2-3 Table 2-3 Requested candidate site (Additional).................................................................2-4 Table 2-4 Items to be observed...........................................................................................2-15 Table 2-5 Maintenance Equipment....................................................................................2-16 Table 2-6 Schedule of Protection Relays............................................................................2-19 Table 2-7 System Outline at TIA .......................................................................................2-21 Table 2-8 Outline at Ilia State University.........................................................................2-22 Table 2-9 Equipment Specifications Plan for TIA.............................................................2-26 Table 2-10 Equipment Specification Plan for Ilia State University...................................2-27 Table 2-11 Scope of Works by the Project and Georgian Side ............................................2-52 Table 2-12 Initial Operational Guidance for the PV system ..............................................2-59 Table 2-13 Soft Component Schedule ..................................................................................2-62 Table 2-14 Implementation Schedule ..................................................................................2-62 Table 2-15 Maintenance Cost for the Project (TIA) ............................................................2-68 Table 2-16 Maintenance Cost for the Project (Ilia State University).................................2-68
ABBREVIATIONS
Abbreviation Original Word
C CC Climate Change
CDM Clean Development Mechanism
D DNA Designated National Authority
E EBRD European Bank for Reconstruction and Development
EIA Environmental Impact Assessment
EIB European Investment Bank
FIT Feed in Tariff
G GHG Greenhouse Gas
K KfW Kreditanstalt fur Wiederaufbau
G GEF Global Environmental Facility
GOGC Georgian Oil and Gas Corporation
I ISU Ilia State University
L LEPL Legal Entity of Public Law
M MAD Maximum Admissible Discharge Limit
M MoE Ministry of Energy and Natural Resources of Georgia
MoESD Ministry of Economy and Sustainable Development of Georgia
MoEPNR Ministry of Environmental Protection and Natural Resources of Georgia
MoEP Ministry of Environmental Protection of Georgia
MoIA Ministry of Internal Affairs of Georgia
MoF Ministry of Finance of Georgia
MoFA Ministry of Foreign Affairs of Georgia
MCGF Millennium Challenge Georgia Fund
NASA National Aeronautic and Space Administration
NOAA National Oceanic and Atmospheric Administration
P PV Photovoltaic
R RPS Renewable Portfolio Standard
T TAV TAV
TELASI Tbilisi Electricity Network
TPP Thermal Power Plant
U UAG United Airports Georgia
UNDP United Nation Development Plan
UNFCCC United Nations Framework Convention on Climate Change
UPS Uninterrupted Power Supply
USAID United Sates Agency for International Development
W WB World Bank
CHAPTER 1
BACKGROUND OF THE PROJECT
Chapter 1 Background of the Project
1-1 Background of the Request
The Government of Japan (hereinafter referred to as “GoJ”) established the Cool Earth Partnership
in the address made by the then Prime minister Fukuda of Japan during the World Economic
Forum held in Davos, Switzerland in January 2008 as a new financial mechanism for developing
countries that are aiming to achieve both emission reduction and economic growth, and that are
suffering severe adverse impacts as a result of climate change. Through this, a new scheme of grant
aid, the “Grant Aid for the Environment and Climate Change Program” (hereinafter referred to as
GAEC) (2008) was also created by GoJ for insufficiently funded and less capable developing
countries willing to take actions for climate change.
As one of the co-benefit cooperation projects, JICA aims to utilize Japanese advanced technology
in clean energies including renewable ones. As a result, it was decided to conduct GAEC using the
solar photovoltaic (hereinafter referred to as “PV”) system for the member countries of the Cool
Earth Partnership.
Because of these backgrounds, GoJ was asked for installation of a PV system as GAEC by Georgia,
which has a policy to develop renewable energy to mitigate negative impacts on the environment
and is experiencing rapidly increasing electricity demand, and in response, the implementation of
the preparatory survey under JICA was approved by the Ministry of Foreign Affairs of Japan.
1-2 Outline of the Request
Outlines of the requests at the times of the application for GAEC, the project formulation and
outline design of the preparatory survey are as follows.
(1) Request at the time of application for GAEC
GAEC for installation of a grid connected PV system and technical assistance for the
operation and maintenance thereof was requested by Georgia in April 2009. The Ministry of
Environmental Protection and Natural Resources of Georgia (MoEPNR), Tserovani Refugee
Camp, Ilia State University and Tbilisi No. 199 school were proposed by Georgia as
candidate sites for this project. The generating capacities at each site are approx. 177kW at
MoEPNR site, approx. 777kW at Tserovani Refugee Camp site, approx. 70kW at Ilia State
University site and approx. 60kW at Tbilisi No. 199 school site.
In this preparatory survey, as a first step, project formulation including narrowing down the
candidate sites, was implemented. As a second step, through site survey, the conceptual
design, the project cost estimation and drawing up of the draft tender documents were
conducted.
1-1
(2) Request at the time of project formulation in the preparatory survey
At the time of project formulation in the preparatory survey in September 2009, the
candidate sites were evaluated in terms of showcase effect, security of the facilities,
sustainability of the facilities, grid connectivity, capability of operation and maintenance of
the PV system and sun shadow effects. As a result, MoEPNR and Ilia State University were
selected as project sites.
(3) Request at the time of outline design in the preparatory survey
At the time of outline design in the preparatory survey in November 2010, the JICA study
team explained to the Georgian side that MoEPNR and Ilia State University were selected as
project sites and this was approved by the Georgian side. Afterward, further feasible studies,
detailed designs and cost estimations were conducted. Meanwhile, MoEPNR had a drastic
institutional reform and it is no longer possible to install the PV system at the MoEPNR site.
As a new candidate site, Tbilisi International Airport (hereinafter referred as to TIA) was
added in June 2011. As a result of an additional survey, TIA and Ilia State University were
selected as new project sites. The detailed survey results are as follows.
1) TIA
TIA site not only plays a leading role for clean energy in Georgia, but also will be seen by a
large number of people (showcase effects). In addition, sustainability of facilities and grid
connectivity will be ensured. It is expected that technical assistance (soft component) of this
project will contribute to development of necessary operation and maintenance ability. The
concern about the TIA site is that the installation area is limited to the green zone in the
parking area, so construction work should be done so that there is no effect on existing
facilities.
2) Ilia State University
Because Ilia State University faces a heavy-trafficked road, it will have show case effects not
only to students but for the general public. Security of facilities, sustainability of facilities
and grid connectivity will be ensured. In addition, it is expected that technical assistance
(soft component) of this project will contribute to development of necessary operation and
maintenance ability.
1-3 Natural Conditions
Georgia has two different climates, one west and the other east of Surami Mountain, which is
in the middle of the country. The west side is a subtropical area. With the Black Sea on its
west, the area is blessed with rainfalls and fertile land. Through a year the area is relatively
warm, daytime temperature usually reaches 30 degrees Celsius in summer and 10-15 degrees
Celsius in winter. Whereas, the east side, where the capital city of Tbilisi is located, is dry
and categorized as a continental climate. The temperature depends on the elevation. Daytime
1-2
temperature reaches 30-35 degrees Celsius in summer and average day length is more than
eight hours a day from June to August. Whereas, daytime temperature is usually 0-10
degrees Celsius in winter but can reach -10 degrees Celsius at night. Total annual hours of
daylight in Georgia is more than 2,000 hours and that of Tokyo is 1,800-1,900 hours. The
northern mountainous parts are relatively cool and it snows occasionally.
Table 1-1 Natural Conditions in Tbilisi (2006-2008 Average)
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Average(or Total)
Average Max. Daily Temperature (deg C)
4.8 8.5 14.9 18.7 23.2 28.8 30.8 34.4 27.2 20.6 12.5 7.3 19.3
Average Min. Daily Temperature (deg C)
-2,1 -0.4 4.8 8.4 12.4 17.5 19.4 21.0 16.7 11.8 4.5 0.3 9.5
Average Temperature (deg C)
0.6 3.2 9.0 12.7 17.4 22.5 24.5 27.1 21.2 15.4 7.7 3.0 13.7
Average Humidity (%) 76 73 66 70 73 72 67 65 75 78 83 81 73
Rainfall (mm/month) 25 10 26 78 78 57 54 19 35 41 35 18 476
No. of Sunny Days 2 3 2 1 3 4 6 5 4 2 2 4 38
Hours of Sunshine (Hour/Day)
2.8 4.6 4.4 4.4 7.1 8.5 8.2 8.7 6.4 4.5 3.6 3.3 2,021
Whether Bureau
1-4 Social and Environmental Considerations
In Georgia, the following documents should be followed to obtain an environmental permit.
September 1, 2005 N154 Resolution of Georgia on Rules and Conditions of Issuing of
Environmental Permit;
Georgian law on“Environmental Protection”
Georgian Law on “Atmospheric Air Protection”
Georgian Law on Water
17 September 1996 #130 Order of MoEPNR of Georgia
Georgia ratified the United Nations Framework Convention on Climate Change (UNFCCC) in
1994 and the Kyoto Protocol as one of the Non-Annex I countries in 1999. Later it established the
National Research Center to start implementing policies on climate change in 1996. In January,
2003, the National Agency on Climate Change (NACC), which belonged to the Ministry of
Environment of Georgia was designated as a Designated National Authority (DNA) of Georgia,
which handles the clean development mechanism (CDM). Then the Ministry of Environmental
Protection and Natural Resources of Georgia (currently the Ministry of Environmental Protection
of Georgia) became a new DNA in January 2005.
The PV system of the project is less than 500kW and will not produce significant negative
environmental impacts. As a result of consideration in accordance with the JICA EIA guideline,
this PV system is categorized as “Category C” and an environmental review can be skipped after
screening.
1-3
CHAPTER 2
CONTENTS OF THE PROJECT
Chapter 2 Contents of the Project
2-1 Basic Concept of the Project
2-1-1 Overall Goal and Project Objectives
Recognizing the physical, human, and social disasters brought by ecosystem destruction and
meteorological disasters due to climate change, Georgia sees climate change as one of its top
priority agendas. Georgia ratified the United Nations Framework Convention on Climate Change
(UNFCCC) in 1994 and the Kyoto Protocol as one of the Non-Annex I countries in 1999. Later it
established the National Research Center to start implementing policies on the climate change in
1996. In January, 2003, the National Agency on Climate Change (NACC), which belonged to the
Ministry of Environment of Georgia was designated as a Designated National Authority (DNA) of
Georgia, which handles clean development mechanism (CDM). Then the Ministry of
Environmental Protection and Natural Resources of Georgia (currently the Ministry of
Environmental Protection of Georgia) became a new DNA in January 2005.
Hydropower (Approx. 90%) and thermal power (Approx. 10%) are the main power generation
contributors in Georgia. According to statistics, annual power generation in 2010 is from base load
plants (6,525.4GWh), seasonal plants (2,842.3GWh) and thermal power plants (678.6GWh).
In terms of both energy policy and security guarantees, energy sector reform has been an important
task in Georgia. That is due to the growing need for commitment to international standards and its
situation such that Georgia has to turn to neighboring countries for almost all of the fuel for thermal
power generation. In fact, there was a temporary stop of natural gas supply due to pipe line damage
in 2006. In response to this accident, Georgia has made and declared its plan for energy
independence.
This project, as a pilot project, is about introducing a grid connected PV system (hereinafter
referred to as PV system) aiming at contribution to both reduction in greenhouse gas emission and
stable energy supply.
(1) Upper Level Plan
In terms of climate change, it is intended to elaborate a National Adaptation Plan of Action
(NAPA), which was formulated in 2009. In the plan were held up three policies of 1)
Making an effort against climate change, 2) Utilizing a CDM scheme and 3) Improvement of
public awareness regarding the climate change. As for the energy section, it’s aimed to
pursue utilizing renewable energies (hydro power, wind power, solar power, geothermal
power and biomass).
(2) Project Purposes
Japan has established a new financial mechanism for a “Cool Earth Partnership” in order to
help developing countries both in reduction of green house gases and economic development.
2-1
As a part of this mechanism, a Grant Aid for the Environment Program was introduced to
provide financial support and capacity development.
With this background, the purpose of this project is to introduce the PV system. Main effects
which this project will bring are promotion of renewable energy usage, reduction in
greenhouse gas emission and improvement of public awareness of climate change by the
showcase effect.
2-1-2 Outline of the Project
To accomplish the above goal, equipment and materials for the PV system will be procured and
technical assistance for the operation and maintenance will be provided.
Table 2-1 Outline of the Project
Equipment procurement for PV system
Equipment Use of power generated Needs
Grid-connected PV system
Generated power is supplied to facilities by a grid connected PV system
Promotion of renewable energy is needed out of concern about ecosystem disruption in consequence of climate change and increasing physical, human and social damage due to meteorological disaster.
Technical Assistance for grid-connected PV system (Soft Component)
Technical assistance
Training on basic technical knowledge of PV systems and on the operation and maintenance thereof including inspection and troubleshooting.
To address the lack of technical knowledge for operation and management of PV systems, because it has hardly been introduced in Georgia up to now.
2-2 Outline Design of the Requested Japanese Assistance
2-2-1 Design Policy
2-2-1-1 Basic Policy
(1) Scope of Cooperation
The project will provide a PV system in which Japanese technology and know-how can be
utilized. These can also assure a showcase effect of the PV system and sustainable operation
and maintenance. Georgia has no experience in grid connected PV systems, reverse power
flow, or buying electric power from independent power producers. In addition, Tbilisi
Electricity Network (hereafter referred to as “TELASI”) considers implementing reverse
power flow when institutional conditions are cleared after completion of this project.
Therefore, a grid connected PV system without reverse power flow will be provided. As the
Georgian government is willing to introduce a reverse power flow system, this project also
covers equipment procurement and technical assistance related to reverse power flow.
2-2
(2) Site Selection
Four candidate sites were initially requested as installation locations of the PV system by
Georgia. Each candidate site and the use of generated power are as follows.
Table 2-2 Requested candidate sites (initial)
Priority Level
Candidate Site Name Generation Capacity
Installation Location & Area Use of Generated
Power
1 Ministry of Environmental
Protection and Natural Resources
Approx. 177kW
Roof, walls, and entrance area (Approx. 4,700sq m)
Ministry building
2 Tserovani Refugee Camp
Approx. 777kW
Unoccupied land in the camp (Approx. 22,500 sq m)
Houses and facilities in the
camp
3 Ilia State University Approx. 70kW
Unoccupied land in the university campus
(Approx. 2,350sq m)
University campus
4 Tbilisi No.199 school Approx. 60kW
Schoolhouse roof top (Approx. 2,100 sq m)
School premises including dormitory
The site selection was implemented according to the following six criteria.
Security of the facilities
Sustainability of the facilities
Grid connectivity
Capability of operation and maintenance for the PV system
Sun shadow effect
Showcase effect of the PV system
Comprehensive evaluations for each location according to the criteria, are as follows.
1) Ministry of Environmental Protection and Natural Resources
Since the Ministry of Environmental Protection and Natural Resources (hereafter referred to
as “MoEPNR”) is in charge of acting as contact Ministry concerning Clean Development
Mechanism (CDM) as of 2009 and promoting clean energy, it’s expected that introduction of
the PV system to MoEPNR would be appealing to the public. Also due to a main road and
heavy traffic in front of MoEPNR, the PV system will be seen by a large number of people,
which is what we call the showcase effect. At MoEPNR, sustainability of the facilities and
interconnectivity are ensured. In addition, capability of operation and maintenance can also
be provided by technical assistance (soft component). However, the deterioration of the
ministry building has to be taken into account in selecting an installation site. Furthermore,
due to shadow which would be cast by surrounding buildings, it’s estimated that generation
efficiency would be lower than the other candidate sites.
2) Tserovani Refugee Settlement
Even though the installation site will not be affected by shadow, and it can be ensured that
2-3
enough generation capacity and interconnection will be easy, the site is located away from
the highway and showcase effect is expected to be low. Furthermore, there are also
problems in continuity, safety, and operation and maintenance, which are intrinsic to refugee
camps.
3) Ilia State University
Appealing to and enlightening of the students regarding the PV system is expected as well as
a showcase effect because of the installation location facing the main road. As the
installation site is located in the university campus, facility safety, continuity and
interconnectivity are assured. There will be no problems in operation and maintenance if
technical assistance (soft component) is provided.
4) Tbilisi No.199 School
Appealing to and enlightening of the students regarding the PV system can be expected but
the schoolhouse is too old to install the equipment to be safe unless a great deal of repairing
is carried out. There is some concern about capability of operation and maintenance.
As a result of discussions between Georgia and Japan, MoEPNR and Ilia State University
were selected as candidate sites. The reasons are: Tserovani Refugee Camp has critical
problems in continuity and safety and Tbilisi No.199 School does not have enough space for
the installation.
Despite what was described above, MoEPNR was removed from the list of candidate sites
since the Georgian government restructured its government ministries and agencies in
February 2011, and an additional candidate site of Tbilisi International Airport (hereinafter
referred to as TIA) was added and information about the site is shown below.
Table 2-3 Requested candidate site (Additional)
Candidate Site Name
Power Generation Capacity
Installation Location & Area Use of Generated Power
Tbilisi International Airport
Approx. 200kW In the Parking Space (Approx. 4,100sq m)
In the terminal building
Comprehensive evaluation of TIA according to the criteria is as follow.
5) TIA
TIA is the largest airport in Georgia and a gateway for more than 820,000 passengers a year.
It’s expected that introduction of the PV system to the airport would be appealing to the
public and promote clean energy. As the PV system will be installed in front of the terminal
building, the system is expected to be seen by a large number of people. At the Airport,
sustainability of the facilities and interconnectivity are ensured as well as capability of
operation and maintenance by existing technical staff for operation and maintenance. In
addition, operation and maintenance will be enhanced by technical assistance (soft
2-4
component). However, installation space for the PV system in the parking lot is limited to
the green zone because it is impossible to decrease the Parking space. Furthermore,
influence of the existing facilities has to be studied in the construction work.
As a result of a comprehensive consideration, TIA and Ilia State University were chosen as
project sites for this project.
(3) Required Space and Capacity of the PV System
The study of this project on space and capacity at TIA and Ilia State University was based on
the following conditions;
There should be as little shadow effect of trees, surrounding buildings, etc. on the panel
as possible in order to maximize generation efficiency
There should not be structural problems when installing the PV modules
There should not be reflection which causes negative effects on neighbors or airplanes
There should not be shadow effects of PV modules on neighboring facilities
Reverse power flow should be avoided even when power usage is small, for example
weekends, by effective power usage because reverse power flow is out of the scope of
this project
Direction and tilting angle of PV modules should be set so as to attain high generation
efficiency.
Based on the above conditions, the results of the study are as follows.
1) TIA
TIA and the terminal building are operated by a Turkish company under contract with the
Georgian government, which is a BOT (Build-Operate-Transfer) financing project for 20
years. All incomes of this pay car park are used for operation and maintenance of the whole
airport facilities. Therefore, the plan was made to build a supporting structure above the
existing green zone and open space so as not to interfere with the current parking space. As a
result, generation efficiency including the shadow effect of approximately 98% and
generation capacity of about 310kW will be achieved. It’s also estimated that this amounts
to approximately 38% of the total estimated power consumption capacity (800kW).
2) Ilia State University
The original request was to install the PV system on unoccupied land in the campus with a
generation capacity of 70kW. However, it was affected by shadow of a university building
on the southern side and if set high enough to avoid the effect it would cause a shadow effect
to a university building on the north side. So, the plan was made to install it on the west side
where the shadow effect is minimal. Therefore, the generation capacity was 37kW and
generation efficiency including the shadow effect is 83%. It’s estimated that this amounts to
approximately 18% of the total estimated power consumption capacity (200kW).
2-5
(4) Overall Design Concepts
The outline design of the project is based on the following concepts.
1) In consideration of the fact that there has been no precedent of reverse power flow to
the grid or electric power selling coupled with absence of relevant institutions
regarding PV systems in Georgia, the project will provide necessary equipment for the
PV systems without reverse power flow.
2) Reverse Power Relays (not necessary when allowing reverse power flow) and technical
assistance for reverse power flow will be included in the plan, as Georgia intends to
utilize reverse power flow once the conditions allow.
3) As for interconnection, an equipment plan should be drafted in accordance with
technical requirements to Japanese interconnection standards so as not to bring
negative effects on distribution power quality and to ensure safety.
4) It is required to install protection devices that include over voltage ground relays and
reverse power relays. The power factor at the receiving point is estimated to be
approximately 80% because there is no power factor correction capacitor. Therefore,
capacitors in the electrical substation to comply with the requirements of the Grid-
Interconnection Code will be installed to improve the power factor to 95%.
a) TIA
The existing terminal building was built in 2007 and electrical substation facilities have
an extra space to install the above said protection devices. So, the plan was made to
install necessary devices into the existing substation.
b) Ilia State University
The existing substation has no space for installing protection devices and no substation
protection devices such as transformers. So, the plan was made that this should be
replaced by a new substation fully equipped with above said equipment.
1) The PV system and existing power distribution systems will be connected at the low
voltage side of the transformer of the above substation.
2) For an interconnection system without reverse power flow, the system should be
designed to effectively utilize the PV generated power when the facility side power
consumption is low.
3) The supporting structure should be completely independent from the existing building
and be installed where the shadow effect from this new supporting structure to existing
buildings is low.
2-6
2-2-1-2 Policy for Natural Conditions
(1) Altitude
The altitude of the project site where the procured equipment will be installed and then
operated is approximately 400m above the sea level. Therefore, all equipment is designed
with manufactures’ standard specifications for altitude and pressure.
(2) Solar Radiation and Air Temperature
As shown in Figure 2-1, the average clear day solar radiation observed in the site survey is
1.77 kWh/sq m/d, which is above NASA’s December average of 1.74 kWh/sq m/d, however,
the average monthly value is presumed to be almost identical. Based on the above data, the
annual power generation by the PV system at the two sites will be calculated adopting
NASA data and reflecting the result of the shadow effect simulation.
As NASA average temperature data in Figure 2-2 shows, temperature varies annually from -
4 deg C to +20 deg C, which is within the usual solar panel operating temperature condition
of “-20 deg C to +45 deg C” and will not decrease the output due to the panel surface
temperature rise. Further, judging from the usual operating temperature condition of -10 deg
C to +40 deg C for power conditioners, the main item in the system, the planned equipment
of the standard specification can be applicable and so no special considerations will be given.
Solar Radiation (kWh//d) in Tbilisi
1.72
1.82
1.66
1.68
1.7
1.72
1.74
1.76
1.78
1.8
1.82
1.84
2nd Dec 15th Dec
Figure 2-1 Observed data (Solar Radiation and Temperature in Tbilisi Area in 2000)
2-7
2.08
2.87
3.8
4.7
5.58
6.3
1.74
2.16
5.95
5.15
3.11
4.23
1.42
-2.25
2.88
9.27
14.8
19.520.3
16.9
12.6
8.17
-3.26-3.44
0
1
2
3
4
5
6
7
1月 2月 3月 4月 5月 6月 7月 8月 9月 10月 11月 12月
-5
0
5
10
15
20
25
日射量(kWh//d)
月平均気温()
Daily Solar Radiation
Monthly averageAir Temperature
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Daily SolarRadiation
(kWh//d)
Monthlyaverage AirTemperature
()
※annual average daily solar
radiation:3.97kWh/m2/d
annual average airtemperature:8.14
Figure 2-2 Monthly Average Solar Radiation and Air Temperature in Tbilisi (NASA)1
(3) Seismic Load
Although some earthquakes have been recorded in Georgia (2.9-6.0 magnitude earthquakes
occurred 39 times in 2009), there is no record of any building destruction or damage by an
earthquake in Tbilisi.
The design strength of the supporting frame for the PV modules and support bolts is
calculated assuming the fixed load (panel, structure weight) as the long-term load and the
heaviest of either the fixed load plus wind load, the fixed load plus seismic load, or the fixed
load plus snow load as the short-term load.
(4) Wind
According to NASA data for the past 22 years, the average wind speed in Tbilisi is 5.5m/sec.
(10m above ground level). At Ilia State University, however, blasts of concentrated wind
caused by surrounding buildings may bring serious effects. In wind-resistant design,
considering the strength of airflow, design wind velocity for the calculation shall be assumed
to be 30 meters per second for the wind load calculation, supporting the frame and anchor
bolts for the foundation, and foundation of the PV module. Further, consideration is given to
the fact that the planned site is located in the inland area of Tbilisi. Tbilisi belongs to
“ground roughness class Ⅲ” in the Building Standards Act of Japan. The design speed
pressure of 1,120N/sq m will be adopted based on the wind load calculation method
specified in the Building Standards Act of Japan. In contrast, at the project site for TIA,
design wind velocity for the calculation shall be assumed to be 40 meters per second, which
1 Source: NASA, Tbilisi (Lat.41.7, Long.45.0) Note: Mean daily solar radiation is shown for a horizontal
surface (kWh/sq m/d).
2-8
is pursuant to the design standard for the existing terminal building, and the design speed
pressure of 1,348N/sq m will be adopted.
(5) Snowfall
The maximum amount of snowfall of 170 millimeters was recorded in the past in Tbilisi.
Therefore, 300 millimeters shall be adopted as assumptive maximum amount of snowfall and
600 N/sq m shall be adopted as the snow load.
(6) Rainfall
According to the Meteorological Office’s data, the annual rain fall in Tbilisi is 450mm to
500mm, which is less than one-third of Tokyo’s. Adequate cleaning effect on the PV
modules will be assured, so special measures for water exposure of outdoor electric
equipment will not be considered.
(7) Lightning
In Tbilisi, thunder clouds are usually observed seven times a year mainly between November
and March, but no lightning damage has been reported. However, in recent years in many
countries trouble with electronic equipment, computers, etc. have become a big problem. By
direct strikes and induced lightning, abnormal current and voltage enter electronic equipment
through power and telephone lines, etc. to cause trouble. For this reason, for power
conditioners, measurement monitors and large displays, measures will be taken to block
abnormal current and voltage effects through the existing power and telephone lines, etc. and
to ensure a steady power supply.
(8) Salt Damage
The proposed sites are located in an inland area about 240km from the Black Sea in linear
distance and about 290km from the Caspian Sea, and no salt damage by sea breeze etc. has
been reported. As standard specifications are applicable to the planned equipment, no
special measures will be taken.
2-2-1-3 Policy Related to Socio-Economic Conditions
So far Georgia has put a high national priority on economic development rather than on an
effort to reduce greenhouse gasses (GHG) emission, not leaving sufficient funds for
improvement of infrastructures or policies for renewable energy utilization. Therefore, it’s
necessary to raise public awareness for introducing renewable energy and the showcase
effect has to be considered to promote renewable energy in Georgia in the planning and
design stage.
2-9
2-2-1-4 Construction/Procurement Affairs, Special Situations and Commercial Customs
(1) Permits and Approvals and Laws Related to the Implementation of the Project
Within this project, installation works for foundations, supporting frames and equipment and
electric works will be conducted. In Georgia, the labor law governs employment contracts,
gender consideration, working hours, break time, wages, working rules, working
environment and so on. Therefore, this law should be applied to installation works of this
project. Building standards law and related laws in Georgia should be referred to and design
documents are subject to be checked by the local government prior to submission. Also
environmental preservation regulated by parliamentary resolutions, laws, ministerial order
and so on in Georgia should be conformed to.
(2) Applicable Technical Guidelines, Regulations and Standards
The design, manufacture and installation of devices, equipment and materials to be procured
under this project are to conform to international and Japanese standards issued by the
following organizations.
IEC Standards (IEC61215, IEC61646, IEC61730-1 and IEC61730-2)
Japanese Industrial Standards (JIS)
The Standard of Japan Electric Manufacturer’s Association (JEM)
Japan Electromechanical Committee (JEC)
Japanese Cable Maker’s Association Standards (JCS)
Guideline on interconnection system technology requirements for power quality (Japan)
Grid-Interconnection Code, Japan Electric Association (JEAC)
Electricity Business Act (Japan)
Electric Installation Engineering Standards (Japan)
(3) Permit Approval for the Works
According to the Georgian regulations, permit approval by the jurisdictional Municipality shall
be needed for the works. The basic design drawings for the supporting structure and application
documents will be reviewed as an extension work at each site and it will take two weeks.
(4) Design Standards to be Complied with for the Works
In Georgia, the building code is in the process of being clarified and currently refers to the
design standards of the USSR and international standards such as AASHTO, ANSI, BS and
so on. As for safety standards, Japanese standards will be applied to the works.
It’s expected to conduct civil, architectural, electrical and communication facility works
related to the PV system and its accessories. All the plans and designs are based on the
Japanese specifications and standards while still referring to the guidelines of Georgian civil,
construction, electrical, and mechanical work and so on.
2-10
2-2-1-5 Policy for Utilizing Local Companies
This is the first time for Georgia to install a PV system of this scale and local companies
have no experiences with the installation of a PV system like this project. It is absolutely
necessary to provide training and guidance to local companies by experts; thus, Japanese
companies, which will be the suppliers for this project will supervise the entire installation
work and provide training and instruction to local companies. It is planed to utilize the local
companies for the civil/construction work, transportation of equipment and materials in
Georgia etc, which can be executed by local companies.
2-2-1-6 Policy for Operation and Maintenance
TIA and Ilia State University will have the first experience to install a PV system under this
project.
For the introduction of the PV system, the operation and maintenance will be carried out by
3 staff members in the existing management department of United Airports of Georgia
(hereinafter referred to as UAG) and 5 staff members in the existing management department
of TAV Urban Georgia LLC (hereinafter referred to as TAV) in the case of TIA, and by a 10
staff members of a new organization under the direct control of the president in the case of
Ilia State University.
One 6th grade2 electric engineer at TIA and one 6th grade and two 5th grade engineers at Ilia
State University will undertake managing duty. They have enough knowledge and skills for
electric equipment in normal buildings but do not have technical knowledge regarding the
PV system that is to be provided by the project.
Therefore, sufficient training for the operation and maintenance of the newly introduced
equipment shall be provided. The trainings are to be conducted by the manufacturer in
charge of the installation’s initial operation guidance and the consultant’s soft component.
2-2-1-7 Policy for Equipment and Frame Structure Grade
For the project to be successful, the equipment and supporting structure must be of general
versatility, toughness, and good cost performance.
In the TIA Parking, the PV modules should be installed at the height of 4m to ensure safe
parking space under the PV modules.
In the TIA Open Space, due to the wide installation space, the PV modules can be installed
on the ground.
2 Electrical engineers are rated by experience years after graduation from electrical school and the scope of works which
electrical engineers can handle is ruled and limited by the rating. The rating grades range from the 1st to the top 6th.
2-11
At Ilia State University, the PV modules should be installed at the height of 2.5m to ensure
safety in the limited installation space.
Under the above conditions, it’s important to choose appropriate equipment. The equipment
should also be easily operated and maintained and experimentally proved.
There are many kinds of PV cells which compose PV modules, such as mono-crystalline
silicon, poly-crystalline silicon, Thin-film amorphous silicon, chemical compounds and
hybrid types. All these different types of PV modules have their own characteristics of power
generation ratio, temperature-maximum output, and voltage-current performance and so on.
In accord with the above requirements and capability of the PV cells, the type of PV cells for
the project are selected from crystalline silicon and amorphous silicon types which have
proven long-term good performance, in consideration of the required minimum generation
capacity, installation space and shadow effects at each installation site.
Furthermore, anti-reflection materials will be selected in consideration of reflection effects
on neighboring facilities and airplanes.
2-2-1-8 Policy for Installation/Procurement Methods
(1) Construction Method
The foundations and columns for the supporting structure will be reinforced concrete and
steel. In addition, local construction methods shall be adopted in this project.
(2) Procurement Method
Procurement of the equipment and materials for the Project are to be implemented with
consideration of the following:
1) Connection between the PV modules, support structures, power conditioners,
measuring and data management and monitoring systems and so on must be
guaranteed to function as an integrated system.
2) Establishment of an appropriate support structure for operation and maintenance of the
system is essential because this is the first introduction of the PV system in Georgia.
3) The Project shall be implemented within a limited time in accordance with the
guidelines for the Japanese grant aid scheme.
4) Since major equipment for the Project such as PV modules and power conditioners are
to be procured from Japanese manufacturers, competitiveness among those
manufacturers in the tender has to be secured.
5) Prevailing construction materials and other materials such as electric and
telecommunication cables etc. to be used for the installation of equipment and common
construction materials are to be procured in Georgia in order to reduce the project cost.
2-12
(3) Construction Schedule
Under the basic policy of the package contract for procurement and construction, fair
competition, in addition to economic efficiency and work efficiency shall be secured. The
work schedule management for construction of equipment and supporting structures shall be
paid the most attention and the work schedule shall be determined as short as practical.
2-2-1-9 Policy for Installation and Construction
Top priority shall be placed on securing the safety of users, tourists, employees, visitors, students,
and faculty, in addition to protecting existing facilities. Moreover, an appropriate plan for
installation and construction shall be established so as to minimize the influence of noise and
vibration to neighborhood facilities.
2-2-2 Basic Plan (Construction Plan / Equipment Plan)
2-2-2-1 Overall Plan
As the result of studies based on the Japanese interconnection standard regarding the effect to the
grid by the Project, it is confirmed that the introduction of the PV system of this Project will be
technically feasible.
(1) Study of the Equipment plan
As a result of studies and discussions with the Georgian side and analysis in Japan regarding
equipment for the PV system in this project, the planned PV system will be composed of a
grid connected PV system, data management and monitoring system, and other devices
described below.
Grid② Power Conditioners
① PV Modules
④Meteorological Observation Instruments
AC
③ Substation
⑤ Large Display④ Monitoring PC
DC
Power Generated,Meteorological Data etc.
Facilities (Lighting, Air conditioner etc.)
Figure 2-3 Outline of the PV system
2-13
1) PV Modules
There are many kinds of PV cells which compose PV modules, such as mono-crystalline
silicon, poly-crystalline silicon, thin-film amorphous silicon, chemical compounds and
hybrid types. All these different types of PV modules have their own characteristics of power
generation efficiency, temperature-maximum output, and voltage-current performance and
so on. PV cells for this project are selected from crystalline silicon which has proven long-
term good performance, in consideration of the required minimum power generated capacity,
area available for installing the PV modules and shadow effects at each installation site.
2) Power Conditioners
According to the maximum power demand data at both installation sites and planned
generation capacity, the power generation may exceed the power consumption during
minimum power demand periods.
Operation of reverse power flow is out of the scope of this project and the system has to
avoid reverse power flow when surplus power is generated. Therefore, the planned power
conditioners need to control output of generated power. This will also decrease the risk of
system shutdown in case of trouble.
3) Electric Substation
The PV system will be interconnected to the distribution grid on the lower voltage side of
this substation equipment. An Over Voltage Ground Relay (OVGR) has to be installed for
interconnection of the PV system to the grid. In addition, a Reverse Power Relay (RPR) has
to be installed to avoid reverse power flow.
a) TIA
OVGR and RPR will be installed in the existing substation. There is sufficient space for
installing these protective relays in the existing substation of the terminal building.
In order to install the new protective relays, power supply has to be stopped. Therefore,
power stop time has to be as short as possible.
From the substation to the main distribution boards located in the terminal building,
electric power is distributed by two lines. So it is possible to stop power supply of one
line to install the protective relays while the other line provides power. By rotation of this
process, a blackout may be avoided.
b) Ilia State University
The existing substation equipment at the site does not have sufficient space in itself for
installing the OVGR and RPR. In addition, the existing substation is not equipped with
basic protective relays such as a transformer. Therefore, this project will replace the
existing substation with necessary protective relays at Ilia State University.
2-14
During the substation renewal period, power stop time has to be as short as possible.
Therefore the new substation will be equipped close to the existing one so that cable
reconnecting work from the existing substation to the new one can be completed easily.
This cable reconnecting work is to be borne by the Georgian side.
4) Data Management and Monitoring Systems
Data management and monitoring systems consist of a personal computer, meteorological
observation instruments such as pyranometer and thermometer, along with data detectors and
signal transmitters. The systems enable tracking of the amount of power generation,
input/output voltage from/to power conditioners, solar radiation, air temperature etc. The
system also records and displays these data in the specified format to be set. In addition to
monitoring the performance of the PV system, these systems display an alarm in case of
system abnormality which will be stored in memory.
The data measuring equipment monitors and collects information using devices specified in
subparagraph i), under the conditions specified in the subparagraph ii), regarding the data
specified in the subparagraph iii)
At Ilia State University, one measurement monitor will be installed for educational purposes
in addition to the one for operation and maintenance.
1. Components of the Data Management and Monitoring System (at Each Site)
Personal Computer : 1 unit
Pyranometer : 1 unit
Thermometer : 1 unit
Data detector and signal converter : 1 lot
2. Measuring period, Calculation Period and Data Storage Period
Measuring Period 6 seconds
Calculation Period Approx. 6 seconds
Data storage period 1 minute or 1 hour
3. Items to be Observed
Items to be observed are as follows.
Table 2-4 Items to be observed
Observation Items Measuring points Data storage
Solar radiation 1 Yes
Air Temperature 1 Yes
Input voltage to power conditioners (TIA) 5 or more for each Yes
Input voltage to power conditioners (Ilia State University) 4 or more for each Yes
Output voltage from power conditioners (TIA) 5 or more for each Yes
Output voltage from power conditioners (Ilia State University) 4 or more for each Yes
Amount of power generated by the PV system 5 Yes
Power Factor 1 Yes
Frequency 1 Yes
2-15
5) Large Display
A large display is planned to be installed at the arrival hall of the terminal building of TIA,
and in the cafeteria of Ilia State University. This displays an outline of the PV system, the
amount of power generation (present, daily, monthly and annually) and meteorological data
(air temperature and solar radiation). The main purpose of the large display is to introduce
the PV system and indicate its environmental effects to users, passengers, and staff of TIA as
well as students and staff of Ilia State University. Data monitored on the large display can be
set or edited by the Data Management and Monitoring Systems.
6) Maintenance Equipment
For proper maintenance of the PV system and the substation, the maintenance equipment is
planned as follows.
Table 2-5 Maintenance Equipment
Items Qty
Thermo graphic camera 1 unit
Insulation tester (Megger) 1 unit
Digital Circuit Tester 1 unit
Clamp meter 1 unit
Electric Detector (for 6kV) 1 unit
Electric Detector (for AC/DC 400V) 1 unit
Insulated Rubber Gloves 1 pair
Insulated Rubber Boots 1 pair
7) Spare Parts and Consumables
Two percent (2%) of the total amount of the PV modules is planned as spare parts.
(2) System Design
The design condition of this system is as follows.
1) Meteorological Condition
Meteorological conditions for planning and designing the Project shall be in compliance with
the “2-2-1-2 Policy for Natural Conditions” and the engineering practice in Georgia shall
also be taken into consideration. (Refer to the following data).
1. Air Temperature
Annual average 19.3 deg C
Maximum in the past 40.3 deg C
Minimum in the past -16.3 deg C
Average in summer 18.9 deg C
Average in winter -3.0 deg C
Design temperature -20 deg C to 45 deg C
2-16
2. Air Humidity 53 to 82% (annual average 69.5%)
3. Wind pressure 1,120 N/sq m (for Ilia State University), 1,348 N/sq m (for TIA)
4. Rainfall Intensity 131mm/hour
5. Snow load 600 N/sq m
2) Condition for Electrical Requirements
1. Medium voltage power supply
6 kV 50Hz 3-phase 3-wire non-grounded
2. Low voltage power supply
Voltage and system 380V/220V 3-phase 4-wire system (TN-C)
Frequency 50Hz
Steady voltage fluctuation %±4
Frequency fluctuation %±0.02
3. Design conditions for the electrical equipment
Since the above-mentioned power supply condition indicates a steady fluctuation
range, the electrical equipment of the PV system adheres to the following design
conditions that reflect transient fluctuation range,
Voltage fluctuation %±10 Steady fluctuation
Instantaneous voltage fluctuation ±15%
Frequency fluctuation %±3 Steady fluctuation
Instantaneous frequency fluctuation %± 5
3) System Requirements for the PV System
1. PV cells convert sunlight to direct current power and feed it to power conditioners.
2. The power conditioners convert this direct current into the alternating current that shall be synchronized with the voltage, frequency and phase of the grid. The alternating current from the power conditioners is distributed to the electrical load in the premises
3. If the power generated by the PV system exceeds the power demand of the premises, the power conditioners will control the output power in order to not reverse the surplus power to the grid.
4. The power conditioners are provided with protective functions that shut-off the connection between the grid and itself in case of its own faults or failures of the grid.
5. The data management and monitoring systems monitor the performance of the PV system and record the operating data.
6. The system shall be manually operated in time of a disaster if the commercial grid stops.
7. At TIA, power conditioners including the back up power conditioner will operate in rotation
8. At TIA, there is an existing backup generator so this generator and the PV system should not operate simultaneously.
2-17
4) Operation of the Power Conditioners
1. The power conditioners continually monitor the performance of the PV modules and start automatically when the output voltage of the PV modules reaches a set value.
2. Power conditioners automatically stop if either output voltage or power generated by the PV modules drops below a set value.
3. In principle, the PV system distributes generated power in the daytime only. The PV system automatically stops power distribution in case of a shortage of sunlight.
4. When operation of the PV system recovers, the power conditioners restart automatically after a specified period of delay time in order to avoid excessive run/stop cycling.
5. In case the alternating system connected to the PV system has an accident or the power conditioners themselves break down, the PV system is automatically shutdown and disconnects from the alternating system immediately.
6. In case an accident occurs in the grid, the PV system shuts down. When the grid recovers, the PV system restarts automatically after confirmation.
7. Before surplus power is generated, the power conditioners regulate output power so as to not reverse it to the grid.
8. If the commercial grid stops in time of disaster, the PV system is started up manually and independently to provide power to certain loads
9. The power conditioner should stop automatically when the backup generator starts its operation
5) Protection Measures for the PV System
In Georgia, no standards or guidelines relating to grid-connected PV systems have been
prepared. Therefore, the protection relays for the PV system are planned in accordance with
the “Guideline on interconnection system technology requirements for power quality” and
the “Grid-interconnection Code” in Japan. Types, number of phases and installation
locations are as shown in Table 2-6.
2-18
Table 2-6 Schedule of Protection Relays
Type of Protective relay No. of Phases Installation Location
Over Voltage Grounding Relay (OVGR) Operating voltage setting range: 2 to 30% (5-step preset value or more) Operating time setting range: 0.1 to 10 seconds (5-step preset value or more)
Zero phase Circuit
Reverse Power Relay (RPR) Operating power setting range: 0.25 to 10% 5-step preset value or more ) Operating time setting range: 0.1 to 10 seconds (5-step preset value or more )
1 phase
Voltage Relay (VR) Operating power setting range: 10 to 300V 5-step preset value or more ) Operating re-setting value range: 5 to 30% (TIA)
1 phase
Power receiving panel in the electric substation
or LV switchgear
Over Voltage Relay (OVR) Operating voltage setting range: 105-110-115-120% of rated voltage Operating time setting range: 0.5-1.0-1.5-2.0seconds
1 phase
Under Voltage Relay (UVR) Operating voltage setting range: 95-90-85-80% of rated voltage Functional Period: 0.5-1.0-1.5-2.0seconds
3 phases
Over Frequency Relay (OFR) Operating frequency setting range: 100.3-100.5-101-102% of rated frequency Operating time setting range: 0.5-1.0-1.5-2.0seconds
1 phase
Under Frequency Relay (UFR) Operating frequency setting range: 99.7-99.5-99-98% of rated frequency Operating time setting range: 0.5-1.0-1.5-2.0seconds
1 phase
Detection of islanding operation (Passive or active) Operating setting range: 3-5-7-9 Rad. Operating time setting range: 0.35-0.7-1.5-3.0seconds
-
Power conditioner
6) Grounding Works
The TN-C method in the IEC standard has been the local power distribution standard. A
grounding conductor is commonly used with the neutral conductor of the receiving
transformer and each piece of electrical equipment.
In this project, a substation including a neutral grounded transformer will be renewed at Ilia
State University. Therefore, the resistance value of the earth work for the substation should
be kept equal to or less than the existing one.
The power conditioner, supporting structure for PV modules, junction box, grid connecting
board and other devices of the PV system will be earthed. According to the Electrical
Facilities Engineering standards in Japan, these grounding works are classified as Class C
(grounding resistance value of 10 Ohms or less). Therefore, the grounding resistance value
of 10Ω or less will be applied to the system of this project and also grounding electrodes will
be independently embedded.
2-19
7) Security Plan
TIA is secured on a steady basis by the current security systems and there might be no need
for additional security measures for the TIA. Ilia State University will install security
cameras which monitor the PV system in this project. The power conditioner in Ilia State
University will be provided in a lockable outdoor type enclosure (the same type of enclosure
as the one of the outdoor substation).
(3) Construction Plan
Construction Plan for frames for the PV modules is as follows:
1) TIA
Frame structures for the PV system will be installed in the existing green area in the parking
lot (hereinafter referred as to Parking). This area was chosen because the shadow from the
terminal building should not reach this area. Also safety of the current parking spaces and
advertising panels, and showcase effect were taken into account. Some PV modules will be
installed in an open space at the parking side (hereinafter referred as to Open Space). During
construction work and operation and maintenance, safety has to be taken into account
because the Parking is always in service during its construction and operation.
2) Ilia State University
Considering effective land use and showcase effect, frame structures for the PV modules will
be constructed along the main road in front of Ilia State University.
(4) System Outline of the PV System
The outlines of the PV systems of TIA (Parking and Open Space) and Ilia State University
were planned based on the equipment plan, system requirements and construction plan for
the frames as follows.
2-20
Table 2-7 System Outline at TIA
Responsible agency Ministry of Economy and Sustainable Development of Georgia
Implementing agency United Airports of Georgia
Location TIA (Parking and Open Space)
Location environment International Airport Parking in capital city of Tbilisi
Owner of the land United Airports of Georgia
Licensing United Airports of Georgia
Power-generating capacity Approximately 310kW
Estimated amount of annual power generation
Approximately 329,000kWh3
Area of installation Approximately 4,100sq m
Use of power generated Electric power in the terminal building
Reduction of CO2 emission 182.594t/year4
Figure 2-4 Perspective at TIA (Parking and Open Space)
3 Estimated annual power generation: 329,000kWh
Parking: 210kW×3.97kWh/sq m/d×365d×Slope Coefficient 1.057×Insolation Coefficient 0.977×Integrated Design Coefficient 0.7=219,000kWh
Open Space: 100kW×3.97kWh/sq m/d×365d×Slope Coefficient 1.093×Insolation Coefficient 1.0×Integrated Design Coefficient 0.7=110,000kWh
4 Reduction of CO2 emission: 329,000kWh×Emission Coefficient 0.555/1,000=182.59t
2-21
Table 2-8 Outline at Ilia State University
Responsible agency Ministry of Economy and Sustainable Development of Georgia
Implementing agency Ilia State University
Location Ilia State University premises
Location environment Center of the capital city of Tbilisi
Owner of the land Ilia State University
Licensing Ilia State University
Power-generating capacity Approximately 37kW
Estimated amount of annual power generation
Approximately 32,000kWh5
Area of installation Approximately 420sq m
Use of power generated Electric power in university campus
Reduction of CO2 emission 17.76t/year6
Figure 2-5 Perspective at Ilia State University
5 Estimated annual power generation:
37kW×3.97kWh/sq m/d×365d×Slope Coefficient 1.052×Insolation Coefficient 0.83×Integrated Design Coefficient 0.7=32,000kWh
6 Reduction of CO2 emission: 32,000kWh×Emission Coefficient 0.555/1,000=17.76t
2-22
(5) Estimated Electricity Generation by the PV Systems
The estimated annual power generation and reduction of CO2 emission are calculated as
follows;
1) TIA
1. Estimated Annual Power Generation
Parking
Annual power generation (kWh/year)
= PV module capacity (kW) × Average solar radiation (kWh/sq m/d) × 365(d)
× Slope Coefficient × Radiation Coefficient × Integrated Design Coefficient
= 210kW × 3.97kWh/sq m/d × 365d × 1.057 × 0.977 × 0.7
= 219,000kWh/year
Open Space
Annual power generation (kWh/year)
= PV module capacity (kW) × Average solar radiation (kWh/sq m/d) × 365(d)
× Slope Coefficient × Radiation Coefficient × Integrated Design Coefficient
= 100kW × 3.97kWh/sq m/d × 365d × 1.093 × 1.0 × 0.7
= 110,000kWh/year
Total
= 219,000kWh/year+ 110,000kWh/year=329,000kWh/yea
2. Estimated annual reduction of CO2 emission
Annual reduction of CO2 emission (ton/year)
= Annual power generation (kWh/year) × Emission Coefficient
= 329,000kWh/year × 0.555/1,000
= 182.59ton/year
3. Calculation Base
Average solar radiation : 3.97kWh/sq m/d (From Figure 2-2)
Slope Coefficient : Coefficient of specific direction and tilting angle against the
horizontal solar radiation
Radiation Coefficient : Appendix 6, Solar Radiation Simulation
Total Coefficient : 0.7
*Total Coefficient is quoted from “Guideline of the
introduction to the PV power generation, NEDO in 2000”
Emission Coefficient : 0.555kg- CO2/kWh
* Emission Coefficient is quoted from guideline of the
Ministry of the Environment, Government of Japan.
2-23
2) Ilia State University
1. Estimated Annual Power Generation
Annual Power Generation (kWh/year)
= PV module capacity (kW) × Average solar radiation (kWh/sq m/d) × 365(d) ×
Slope Coefficient × Radiation Coefficient × Integrated Design Coefficient
= 37kW × 3.97kWh/sq m/d × 365d × 1.052 × 0.83 × 0.7
= 32,000kWh/year
2. Estimated Annual Reduction of CO2 Emission
Annual Reduction of CO2 Emission (ton/year)
= Annual Power Generation (kWh/year) × Emission Coefficient
= 32,000kWh/year × 0.555/1,000
= 17.76ton/year
3. Calculation Base
The same as above.
(6) Impact of Interconnection of the PV System
1) TIA
The electric power is supplied to the site by two 6 kV distribution lines in underground
cables from TELASI Airport substation which is located 3.0 km from the site. These two
distribution lines with 185sqmm cable conductor size are dedicated to the site, so there will
be no voltage effects to low-voltage consumers around the area by the PV system connecting
to the grid.
2) Ilia State University
The electricity is provided to the Ilia State University through a 6kV underground cable from
BAGEB substation which is located 1.5km away, the cable size 50sqmm from the site.
Voltage of general low voltage consumers adjacent to the site is as mentioned below.
1. PV System without Reverse Power Flow
The total connected load is estimated to be 200kW, which is much higher than the PV
electricity capacity of 37 kW, therefore no reverse power flow is presumed. The
voltage of general low-voltage consumers adjacent to the site will be 218 V under the
conditions below, which is within the target value range (212V to 228V) of TELASI.
PV electricity capacity: 37 kW
Ratio of distribution transformer: 6.3kV/400-230V
Power factor: 0.6 lag
Improved power factor: 0.85
2. PV System with Reverse Power Flow
The voltage of general low-voltage consumers adjacent to the site can be calculated as
2-24
219V under conditions below. This value is within the target value range (212V to
228V) of TELASI.
Power demand in Ilia State University drops to 27kW
Generating capacity is 37kW
Other conditions are equal to the case i)
(7) Direction and Tilting Angle of PV Modules
1) TIA
Theoretically the most efficient power generation direction of PV modules is direct south
and tilting angle is 30 degrees. Therefore PV modules in the Open Space will be installed to
direct south with 30 degrees. Meanwhile, the PV modules in Parking can not be set toward
direct south. In this case south west (133 degrees) is the most efficient of all the feasible
directions. Tilting angle of 25 degrees is chosen because it maximizes generating efficiency
given this direction. In addition, the PV modules will be affected by shadow from the
southern terminal building. Therefore the PV modules will be installed at a distance of 40
meters from the building. This limits the decrease in generation capacity by shadow to
approximately 3% in Parking and 1.5% in total.
2) Ilia State University
The direction of the PV module is set almost toward direct south (89 degrees) considering
the existing building condition and area border. The tilting angle is set at 10 degrees taking
into account the installation area and shadow from its own building. The decrease in
generation capacity amounts to 4% compared with the one by the best title of 30 degrees. In
addition, the PV modules are subject to be affected by shadow from the southern and
northern buildings of the university and the western building with a height of 56 meters,
(under construction) and that amounts to 17% of the total generation capacity.
(8) Reflection of Solar Light from PV Modules
1) TIA
As a result of the study on PV module direction and tilting angle, there is a possibility that
reflection from the PV modules in Parking during the spring to autumn season will affect
drivers on the road south-west of the panel. During the summer season there is also a risk of
reflection affecting pilots in airplanes landing from the north-west route. Therefore, anti-
reflective PV modules will be employed for the site.
2) Ilia State University
As a result of the study on the PV module direction and tilting angle, reflection from the PV
module during the spring to autumn season may affect drivers on the road south-west.
Therefore, anti-reflective PV modules will be employed for the site.
2-25
2-2-2-2 Equipment Plan
Specifications for the equipment to be provided for project based on consideration and analysis
described “2-2-2-1 Overall Plan” are shown in Table 2-9 and Table 2-10.
Table 2-9 Equipment Specifications Plan for TIA
Item Specification Qty Uses
PV module Mono or Poly-crystalline Cell not less than 310kW
1 set To transform solar light to electricity.
Supporting structure for PV
modules 1 set
To fix the PV modules on the frame structure and concrete foundation
Rotation operation control
panel
DC electromagnetic contactor, changing-over switch, yearly timer and others Ingress Protection: not less than IP20
1 set Four out of five power conditioners will operate in rotation
Power conditioners
Rated capacity: not less than 310kW (including step-up transformers) More than five sets (including
one back-up) are combined and synchronized power conversion efficiency: not less than 90% Output harmonic: less or equal to %5 in total, less or equal to 3%
each Output power factor: not less than 0.95 Protective relay: Over Voltage Relay (OVR) Under Voltage Relay (UVR) Over Frequency Relay (OFR) Under Frequency Relay (UFR) Detection of islanding
operation (Passive and active) Manual operation start-up Ingress Protection: not less than IP20
1 set
To convert direct current power generated by the PV modules to alternating current power To control power, voltage and frequency in relation to the PV system
Junction Box
Direct current switchgear, surge protection device, power back-flow prevention device, terminal block and etc. Ingress Protection: not less than IP53
1 set To collect direct current generated by the PV system and connect it to the power conditioner
Grid Connecting Board
Alternative current switchgear and etc. Ingress Protection: not less than IP20
1 set To collect the alternating current output from power conditioner and connect it to the electric substation
Power Factor Improvement
Static Capacitor Board
Rating: 3P 3W 380V 50Hz Main circuit breaker: MCCB Capacitor: equivalent to 400kVA Series reactor: equivalent to 24kVA (L=6%) Automatic power factor control Ingress Protection: not less than IP20
1 set To improve the power factor of receiving points
2-26
Item Specification Qty Uses
Data Management and
Monitoring Systems
Personal computer LCD ( 15 inch ) or more Data sensing instruments Signal transmitter UPS ( Capacity of 10 minutes or
)more Color printer (Size: up to A3) Software for data monitoring Software for large display
1 set
To track the amount of power generated, input/output voltage from/to power conditioners, solar radiation, air temperature etc. as well as to record and display them in the specified format to be set To operate the indoor type large display
Pyranometer 1 set To observe solar radiation Meteorological observation instruments Thermometer 1 set To observe air temperature
Large display Size: not less than 100-inch (Liquid crystal, PDP or LED)
1 set To indicate power generated and meteorological data etc. for showcases
Infrared thermograph camera 1 set Instrument to measure the temperature of the PV module surface
Insulation tester (Megger) 1 set Instrument to measure insulation of cables and devices
Digital circuit tester 1 set Instrument to measure voltage, current and impedance of cables and devices
Electrical Detector (for medium, AC/DC low voltage)
1 each Devices to check presence of voltage
Insulated rubber gloves 1 pair To avoid an electric shock
Maintenance equipment
Insulated Rubber boots 1 pair To avoid an electric shock
Table 2-10 Equipment Specification Plan for Ilia State University
Item Specification Qty Uses
PV module Mono or Poly-crystalline Cell not less than 37kW
1 set To transform solar light to electricity.
Supporting structure for PV
modules 1 set To fix the PV modules on the frame structure
Power conditioners
Rated capacity: not less than 37kW (including step-up transformers) More than four sets are combined and synchronized power conversion efficiency: not less than 90% Output harmonic: less or equal to 5% in total, less or equal to 3% each Output power factor: not less than 0.95 Protective relay: Over Voltage Relay (OVR) Under Voltage Relay (UVR) Over Frequency Relay (OFR) Under Frequency Relay (UFR) Detection of islanding
operation (Passive and active) Manual operation start-up Ingress Protection: not less than IP20
1 set
To convert direct current power generated by the PV modules to alternating current power To control power, voltage and frequency in relation to the PV system
2-27
Item Specification Qty Uses
Junction Box
Direct current switchgear, surge protection device, power back-flow prevention device, terminal block and etc. Ingress Protection: not less than IP53
1 set To collect direct current generated by the PV system and connect it to the power conditioner
Grid Connecting Board
Alternating current switchgear and etc. Ingress Protection: not less than IP20
1 set To collect the alternating current output from power conditioner and connect it to the electric substation
Electric substation
Receiving voltage: 3-phase 3-wire 6 kV50Hz Main circuit breaker: VCB3P630A Transformer: 250 kVA 3-phase 3-wire 4W380/220V Protective relay: OVGR, OCR, RPR, PT Ingress Protection: not less than IP53
1 set To interconnect the PV system with the grid. Protection relays are built in the system
Data management and
monitoring systems
Personal computer LCD (15 inch or more) Data sensing instruments Signal transmitter UPS (Capacity of 10 minutes or
more) Color printer (Size: up to A3 ) Software for data monitoring Software for external large display
1 set
To track the amount of power generated, input/output voltage from/to power conditioners, solar radiation, air temperature etc. as well as to record and display them in the specified format to be set
Data management and
monitoring systems for education
Personal computer LCD (15 inch or more) UPS (Capacity of 10 minutes or
more) Color printer (Size: up to A3 )
1 set To educate students
Pyranometer 1 set To observe solar radiation Meteorological observation instruments Thermometer 1 set To observe air temperature
Large display Size: not less than 60- inch (Liquid crystal, PDP or LED)
1 set To indicate power generated and meteorological data etc. for showcases
Infrared thermograph camera 1 set Instrument to measure the temperature of the PV module surface
Insulation tester (Megger) 1 set Instrument to measure insulation of cables and devices
Digital circuit tester 1 set Instrument to measure voltage, current and impedance of cables and devices
Electrical Detector (for medium, AC/DC low voltage)
1 each Devices to check presence of voltage
Insulated rubber gloves 1 pair To avoid an electric shock
Maintenance equipment
Insulated Rubber boots 1 pair To avoid an electric shock
2-28
2-2-2-3 Frame Structure Plan
Design policies for the structural frames to support the PV modules are as follows:
(1) Site Plan
1) TIA
Parking space in front of TIA Terminal Building as a main gateway is capable of holding
330 cars and an arrival and departure point for public transport by trains, buses and taxis as
well as to connect between the airport and city center. Therefore the showcase effect has to
be considered and effective land use is also important and some area under the PV modules
will be used safely as pedestrian walkways and a parking lot. Under these basic policies, the
installation location was selected considering shadow effect brought by the southern terminal
building. PV modules will also be installed in the Open Space at the parking side.
2) Ilia State University
Showcase effect has to be considered as a high priority because the installation site, Ilia State
University, is located close to the city center and faces a heavy trafficked main road.
Effective land use is also taken into account and area under the PV modules, currently used
as green space, will be utilized as pedestrian walkways and green space. Under these basic
policies, the installation location was selected considering shadow effect brought by the
existing university building.
(2) Basic Plan
1) TIA
In the Parking area, the frame structure will be installed in the central green zone in
Parking, avoiding the shadow effect brought by the southern terminal building and
interferences with underground installation in the northern green zone. In particular,
safety and parking capacity were given the most importance in the planning.
Furthermore, some space for maintenance of outdoor lights and PV modules will be
installed keeping away from each lamp post.
As for the structure, columns should be steel, which is general in Georgia. Spread
foundations (independent footings) will be adopted for the foundation structure based
on the field study.
Re-bar spread foundations (independent footings) will be adopted for the basement of
the foundation structure
Lighting fixtures and their electric supply for night time will be installed.
In the Open Space, the PV modules will be installed on the ground because the area is
wide enough and will not be affected by sunshade
2-29
2) Ilia State University
The frame structure is to be designed so that natural light and ventilation in the existing
building as well as the installation area are ensured. Therefore, the PV modules should
not be set close to each other and column capitals of the frame structure should be
connected with joists for effective use of space while taking into account power
generating efficiency.
As for the structures, columns should be reinforced concrete, which is general in
Georgia.
Spread foundations (independent footings) will be adopted for the foundation structure.
Large displays for monitoring the PV generating system and measuring equipment for
educational purposes are to be installed. In addition, an existing sub-station shall be
replaced.
(3) Layout Plan
1) TIA
a) Parking
Parking space is sometimes not adequate at peak hour. Therefore, for avoiding
interference with the current parking spaces, a structurally independent frame
structure will be constructed above the green zone on which the PV modules are
planned to be installed.
Due to shadow effect brought by the terminal building in the southern green zone
and the many existing advertising panels and manholes in the northern green zone,
the frame structure is planned to be constructed in the central green zone in the
Parking area.
Area for columns and foundation structures for the frame structure is limited and
the foundation structure must be kept away from existing underground facilities and
structures.
Attention should be paid for preserving the existing green zone, ensuring
illuminance into the existing parking and not interfering with advertising panels in
the limited area.
Lightning and ventilation under the frame structure will be considered. Safety of the
supporting structure has priority in planning.
b) Open Space
Low-height concrete foundations will be prepared and the PV modules and
supporting structures will be installed on them because the area is wide enough.
The PV modules should be set far enough apart from each other so that there should
be no shadow effects because the tilting angle of PV modules is 30 degrees
2-30
2) Ilia State University
Due to the deterioration and unsound structure of the building of Ilia State University,
a structurally independent frame structure will be constructed and the PV modules are
planned to be installed on it, instead of on the roof or wall of the building.
Colonnades will be installed along the main road on which the PV modules are
planned to be installed to avoid any negative effect on the roads and Parking lot in the
compound.
Utilization of the area under the frame structure will be assured considering lightning
and ventilation.
The layout plans for frames (Figure 2-6 and Figure 2-7) are shown below.
2-31
0 10 20 30 40 50 m
N
Tbilisi City
Existing Lamp Post
Terminal Building
DepartureGate
ArrivalGate
Figure 2-6 TIA Frame Layout Plan
2-32
0 5 10 15 20 25 m
Five-Story Building
Four-Story Building
AdjacementBuilding
N
Figure 2-7 Ilia State University Frame Structure Layout Plan
(4) Section Plan
1) TIA
In the Parking area, the PV modules are to be set an average of 5.1m from the ground in
height, at a slope of 25 degrees. Based on the utilization plan in Georgia, the lowest height
under joists for the frame structure is to be 4.0m. Meanwhile existing underground
installations shall be carefully protected. In the Open Space, the PV modules will be set to
direct south and installed on the ground.
2-33
Figure 2-8 TIA Frame Structure Section Plan (Parking)
Figure 2-9 TIA Supporting Structure Section Plan (Open Space)
2) Ilia State University
The PV modules are to be installed from 2.8m to 4.0m in height, beyond people’s reach, to
ensure safety at the entrance of the parking lot.
2-34
Figure 2-10 Ilia State University Frame Structure Section Plan
(5) Structure Plan
1) Design Policy
The structural design for the project shall be formulated after a full review of the existing site
conditions. In principle, the structure form shall be designed in consideration of the
deflection in the long-term load, the vibration, and so on. It also shall have satisfactory safety
at the time of the short-term load (earthquakes or wind load) without degradation of the
strength of the building. Furthermore, simple construction methods and durable structural
form shall be adopted.
2) Structural Design Standard
As for structural design, Georgian standard law shall be conformed to basically. If necessary,
the structural design standard of the Architectural Institute of Japan shall be referred to for
analysis methods and structure designs. Though it’s already confirmed that local mill
certificates meet the requirements of various material standards such as JIS, ASTM, BS and
so on, in general JIS shall be conformed to in the structural design.
3) Construction Method
As for the construction method, reinforced concrete structures and steel structures are
adopted, which are popular and economical in Georgia.
4) Seismic Design
As for seismic design criteria, the base shear coefficient adopted for the superstructure shall
be Co=0.2 (the Building Standards Law of Japan). The wind load can affect the structure in
either an upward or downward direction. Therefore, whichever is greater shall be adopted for
the structural calculation.
2-35
5) Wind Resistant Design
Due to wind load from the upward and downward direction, the structural design condition
of wind velocity of 30m/sec shall be adopted for the bearing force of the PV modules and
strength calculation of the supporting structure, foundation and its anchor bolts. In addition,
the design wind pressure of 1,120 N/sq m is adopted in accordance with the calculation
method of wind load defined by the Japanese Building Code, considering that the project site
is located inland and belongs to “Ground roughness classification 3.” However, complying
with a request to meet the design standard for the terminal building, wind velocity of
40m/sec and design wind pressure of 1,348 N/sq m shall be adopted for TIA.
6) Snow Resistant Design
Since 170mm maximum snow fall has been recorded in Tbilisi area, snow load of 600 N/sq
m is to be adopted under the assumption that maximum snow fall is presumed to be 300mm.
7) Material
Reinforcing bar Round steel bar φ6~φ9
Deformed bar SD295A D10~D16
Deformed bar SD345 D20~D25
Structural steel Molded steel, Steel plate SS400, SSC400
(6) Utilities Plan
1) Mechanical works
a) Water Supply and Drainage System
The annual rainfall of 450mm~500mm, which is less than one third of that in Japan, is
expected to clean dust off of the PV modules. In addition, a water supply system in the
existing building is also available. Therefore, a water supply system for cleaning will not
be installed.
b) Air-conditioning System
The existing LV Switchgear room at TIA is already equipped with ventilation systems,
which are adequate for the apparatus such as the power conditioner or capacitor board.
Therefore, there is no need for additional air-conditioning or ventilation systems.
At Ilia State University, the power conditioners will be installed in purpose-built boxes,
the box shall be air-conditioned and air-tight in order to prevent dust and sand entering
from outside.
(7) Electrical works
1) Power Supply System
The incoming switchgear at TIA was installed four years ago and has enough space for
2-36
installing the protective relays necessary for the PV system. Therefore, the new protective
relays shall be installed to the existing incoming switchgear. Signal cables from these
protective relays to the power conditioner will be installed on the existing cable tray in the
trench installed under the Parking.
At Ilia State University, there is not enough space for installing necessary protective relays in
the existing electric substation, therefore the existing electric substation shall be replaced
with a new substation for the protective relays. The new electric substation will be located
next to the existing one and capacity of the transformer will be the same because the electric
loads are identical. Due to renewal of the electric substation, the existing middle voltage (3-
phase 3-wire 6kV) lead-in cable will be connected to the new electric substation. In addition,
a low voltage main cable will be connected between the new electric substation and the
existing main distribution board. The distribution system of the low voltage main cable will
be 3-phase 4-wire 380V/22V.
2) Emergency Power Equipment
UPS (Uninterrupted Power Supply System) are to be installed to the computers, monitoring
system and so on which need special care for voltage fluctuation and instantaneous power
failure.
3) Lighting System
At the TIA site, the PV modules will block the light from the existing pole lights, and it is
assumed that the illumination under the PV modules at night will be darker than the present
condition. Therefore, in consideration of the safety and to prevent crime, the present
brightness shall be ensured.
At Ilia State University site, the lighting system shall ensure necessary brightness under the
PV panels for pedestrians and drivers at night.
Taking into account the maintenance and running cost, LED will be adopted as an illuminant.
The lighting system will be automatically controlled by timer and photo-switch. The
distribution system for the lighting system and outlets will be single phase 2-wire 220V.
4) Wiring Design
At the TIA site, power distribution cables (from the PV modules to the power conditioner)
shall be installed on the existing cable tray in the trench installed under the Parking
At Ilia State University site, power distribution cables (from the power conditioners to the
electric substation) shall be installed in the existing university buildings.
2-37
2-38
2-2-3 Outline of the Design Drawings
The following is an outline of the basic design drawings of the PV system, equipment layout and
supporting structure etc, for both project sites planned based on “2-2-2-2 Equipment plan”.
TIA PV-01-A PV System Outline
PV-02-A PV Module Installation Plan, Equipment Installation Plan
PV-03-A PV System Diagram
A-01-A Installation Plan
A-02-A Plan
A-03-A Section and Elevation
Ilia State University PV-01-U PV System Outline
PV-02-U PV Module Installation Plan, Equipment Installation Plan
PV-03-U PV System Diagram
A-01-U Installation Plan
A-02-U Plan, Section and Elevation
ORIENTAL CONSULTANTS CO., LTD.Mar. 2012
PV SYSTEM OUTLINENONE PV-01-A
K. YAMAZAKIH. KATO
THE PROJECT FOR INTRODUCTION OF CLEAN ENERGY BY SOLAR ELECTRICITY GENERATION SYSTEM
TBILISHI INTERNATIONAL AIRPORT-GEORGIA
(TIA)
2-39
6b 7a
Z
Y
X
7b6c6a5b5a
K
J
I
H
G
F
E
D
C
B
A
K
J
I
H
G
F
E
D
C
B
A
01 02 03 04 05 06 07 08 09 10 11 12
01 02 03 04 05 06 07 08 09 10 11 12
BUSNO PARKING
NO PARKING
NO
PA
RK
ING
NO
PA
RK
ING
NO
PA
RK
ING
NO
PA
RK
ING
NO
PA
RK
ING
NO
PA
RK
ING
NO
PA
RK
ING
NO
PA
RK
ING
PV-02-A
K. YAMAZAKIH. KATO
Mar. 2012
1/1000 PV SYSTEM LAYOUTTHE PROJECT FOR INTRODUCTION OF CLEAN ENERGY BY SOLAR ELECTRICITY GENERATION SYSTEM
TBILISHI INTERNATIONAL AIRPORT-GEORGIA ORIENTAL CONSULTANTS CO., LTD.
MO
DM
LD
PCSSC ROC
(TIA)
18000
8000
12000
18700
30‹
GCB
2-40
ORIENTAL CONSULTANTS CO., LTD.Mar. 2012
PV SYSTEM DIAGRAMNONE PV-03-A
K. YAMAZAKIH. KATO
THE PROJECT FOR INTRODUCTION OF CLEAN ENERGY BY SOLAR ELECTRICITY GENERATION SYSTEM
TBILISHI INTERNATIONAL AIRPORT-GEORGIA
(TIA)
2-41
2-42
2-43
2-44
2-45
2-46
2-47
2-48
2-49
2-2-4 Implementation Plan
2-2-4-1 Implementation Policy
(1) Basic Points
1) Implementation Scheme
This Project shall be implemented according to the implementation scheme of the
organizations concerned illustrated in
Figure 2-11 and in accordance with the implementation procedures of the grant aid of Japan
for Environment and Climate Change (hereinafter referred to as “GAEC”).
Government of Japan
JICA G/A
E/N
Supervision of Implementation
Contract
Japanese Consultant
Contract
Supplier
United Airports of Georgia Ilia State University
Consultative Committee
Ministry of Economy and Sustainable Development of Georgia
Procurement Agency
(Government of Georgia) (Government of Japan)
Procurement & Construction Supervision
Figure 2-11 Project Implementation Scheme
2) Exchange of Notes (E/N)
The contents of GAEC shall be decided by the exchange of notes (E/N) to be signed between
Georgia and the Government of Japan. Project objectives, implementation schedule, terms
and conditions, amount of grant and so on shall be enumerated in the E/N based on the
confirmation.
3) Details of Procedures
Details of procedures on procurement and services under GAEC will be agreed between the
authorities of the two governments concerned at the time of the signing of the Grant
Agreement (hereinafter referred to as “G/A”).
Essential points to be agreed are outlined as follows:
2-50
i) The purpose and budget of the project
ii) Period of the project
iii) Application of the Procurement Guidelines:
At the procurement of products or services stage, “The Procurement Guidelines of
Japan's Grant Aid for the Environment and Climate Programme” shall be applied
iv) The scope of works by the Recipient Country
4) The Procurement Agency
The procurement agency shall be in charge of a series of procurement procedures, such as
tender, contracts with consultants and suppliers in terms of construction and procurement,
financial management of the project including payment, progress management etc. in
accordance with the contract with the recipient country. Technical parts of the tender
documents and supervision for construction and procurement are included in the scope of
works by consultants for the project.
(2) Utilization of Local Transportation Company
This project is located in Tbilisi urban area. The transportation routes are between Japan and
the port of Batumi in Georgia and between the port of Batumi and Tbilisi urban area. It
would be appropriate to employ a Japanese transportation company for the transportation
between Japan and the port of Batumi in Georgia to provide smooth and reliable equipment
shipping to maintain the project schedule. On the other hand, between the port of Batumi and
Tbilisi urban area, it would be effective to utilize local transportation companies under the
supervision of the Japanese transportation company in order to achieve project installation
work within the intended time period and with required quality because they are familiar
with the local transportation situation.
(3) Utilization of Local Firms for Equipment Installation
Local companies (including local contractors) have no experience, sufficient knowledge or
abilities to install PV systems of the size to be procured by the project. Thus, a Japanese
firm shall be the prime contractor of the project and oversee the entire installation work. It
would be possible to carry out economical and high quality installation work by using local
firms if they have been provided with appropriate training and guidance under the
supervision of the prime contractor.
(4) Utilization of Local Consultants
Although there are some local consultants in Georgia capable of providing architectural and
civil engineering services, there are no such local consultants that have sufficient knowledge
of PV systems or that can conduct the consulting service impartially. In general, it is
evaluated that local consultants including architecture and civil engineering fields don’t have
enough experience to become a prime consultant to handle a large scale project such as
2-51
foreign assistance projects. For this reason, local consultants will be utilized as the sub-
consultants of the Japanese consultant for the project and transfer of technologies will be
provided to them through project implementation.
2-2-4-2 Implementation Conditions
As mentioned above in 2-2-1-9 Policy for Installation and Construction, installation and
construction work shall be conducted in operation of airport and school. Therefore, the safety of
tourists, employees, students and faculty shall be secured.
Local firms don’t have experience, sufficient knowledge or abilities required for the project. Thus,
unpacking of equipment, construction of the supporting structures and installation work are to be
conducted by local firms after training by the Japanese PV system engineer. Adjustment of
equipment, trial operation, and initial operation guidance for the PV systems are to be conducted by
the Japanese PV system engineers.
2-2-4-3 Scope of Works
The Scope of works by the Georgian side is shown in the Table 2-11.
Table 2-11 Scope of Works by the Project and Georgian Side
No. Components To be covered by
the project To be covered by
Georgian Side
1 Space for the installation of equipment and materials 2 Indoor space for the installation of equipment and materials 3 Space for construction materials 4 Connecting leading-in cable to the new substation 5 Cost of equipment and construction materials 6 Cost of packing and shipping equipment and construction materials
7 Cost of domestic transportation of equipment and construction materials
8 Cost of delivering, installing and adjusting equipment 9 Cost of soft components 10 Tax exemption 11 Miscellaneous help for Japanese personnel
12 Establish a bank account in a certain bank in Japan under the name of the government of Georgia and issue of authority to pay to the bank
13 Space for temporary storage of equipment and construction materials and approach road during implementation period
14 Site office during implementation period 15 Cutting branches of existing trees (Ilia State University) 16 Removal of existing walls and revetment (Ilia State University) 17 Installation of security camera (Ilia State University) 18 Reconnection of the existing incoming cables between substation and
existing main switchboard (Ilia State University)
19 Protection devices in the existing electric substation 20 Signal cables between the protection devices and power conditioner
(TIA)
2-52
2-2-4-4 Consultant Supervision
The Japanese consultant will engage in the supervision and procurement for the project pursuant to
the following policies.
The PV system is composed of two components; the PV system and the data management
and monitoring system. Thus, the consultants should make sure that technical specifications
cover interface parts of these systems.
The consultants will supervise the installation and construction works at both sites so as to
enable the said works to be completed within the specified time schedule by monitoring the
work progress as necessary.
The Consultant will monitor the progress of technology transfer to be provided by the
supplier/contractor so that the staff of the Implementing Agency may be able to acquire
reasonable know-how about the installation, adjustment and testing of the equipment.
The Consultant will collect security related information and will share the same with the
supplier/contractor to assure the safety of their staff and personnel.
Under these policies, as part of the supervision work of the consultant for this Project, the
consultant will station one management engineer at the project site and another expert engineer will
be dispatched in accordance with the progress of the installation and construction works. In Japan,
during manufacturing or before shipping the equipment, the consultant will witness the testing and
inspection of equipment and materials at manufacturer’s plants during manufacturing to confirm
that the equipment and materials meet the specifications. The consultant will engage in the
following supervision work;
Confirmation and approval of manufacturing drawings, and necessary documents for
equipment and materials
Attending factory tests
Supervising the progress and safety control of the supplier
Attending equipment installation, adjustment and trial-run
Approval of acceptance test procedures and plans
Attending the acceptance testing (final inspection) and issuing of completion certificates.
Executing technical assistance (Soft Component)
Preparation of monthly and completion reports to be submitted to the related organizations.
2-2-4-5 Quality Control Plan
(1) Inspection and Acceptance Test Implementation Plan (equipment work)
1) Basic policy
During the period of manufacturing of the equipment, the Consultant shall review all shop
drawings for the equipment and installation and construction works to be submitted by the
2-53
contractor in terms of conformity with the contract documents and technical specifications
and shall give necessary approvals.
And further, during the period of the installation and construction works, the consultant will
check the statement of methodology including implementation structure, installation and
construction schedules, sequence of installation and construction, and so on and provide the
approvals.
2) Quality Inspection by the Consultant
As for the quality inspection for the equipment, the following inspections and acceptance
tests shall be conducted
a) Factory Inspection
Prior to the shipment of the equipment out of the factory, each and all equipment are to be
inspected as to their conformity with required specifications and performance tests for the
systems are also to be conducted.
b) Collation Inspection prior to Shipment
Though quantities of the principal equipment shall be confirmed at the time of the factory
inspection, quantities of all equipment are also to be confirmed during collation
inspection prior to shipment to be conducted by a third party inspection agency. Place of
inspection is the manufacturer’s packing warehouse.
c) Acceptance Test and Handover
After completion of guidance on operation, counterparts of the Project with the presence
of the consultant, will verify required efficiency/performance and function. Acceptance
testing is to be conducted by operating the actual PV systems.
After completion of the acceptance tests, results of the tests are to be confirmed among
the counterparts, the consultant and the contractor. Then, the Project will be handed over
to the Implementation Agency.
(2) Quality Control Plan (construction work)
1) Basic Policy
At the time of preparation of the proposed tender documents, the outline design drawings are
to be prepared after reviewing construction details using local materials and widely adopted
local construction methods giving consideration to the construction situation in Georgia and
the maintenance cost. As for the technical specifications, reference is made to Georgian
Standard, Japanese Architectural Standard Specification (JASS), Japan Industrial Standard
(JIS), British Standard (BS), and American Society for Testing and Materials (ASTM) and
so on in order to secure high quality of the construction and installation works.
2-54
During the construction period, the consultant will check of all the submittals from the
contractor such as the supporting structures construction plans, the construction schedules,
and shop drawings in terms of conformity of such submittals with the contract documents
and technical specifications, and provide necessary approvals.
2) Quality Inspection by the Consultant
On site, the consultant will review and/or examine the statement of methodology and
material sample in terms of conformity of the construction materials and construction quality
with the relevant technical specifications and give necessary approvals prior to the
commencement of each category of the construction work. After the commencement of each
category of the construction work, the consultant will conduct inspections as necessary in
accordance with check sheets highlighting important check points prepared based on the
approved statement of methodology.
Although all construction materials used for the project can be procured locally, random
inspection is to be conducted as necessary in order to secure the required quality in addition
to obtaining manufacturer’s warranties.
a) Earth Work and Foundation Work
Since the extent of the area for construction of the concrete foundation for installation of
the PV modules is quite large, appropriate work plans and curing plans are to be prepared
with consideration of earth excavation, curing of excavated surfaces, placing of concrete,
backfilling and compaction and so on.
b) Re-bar Work
The consultant will confirm the mill certificates prepared by the manufacturer and
submitted by the contractor. At the same time, the consultant also will conduct random
inspections of the reinforcing steel bars regarding the yield strength in terms of
conformity with the relevant technical specifications.
The consultant will review the shop drawings and inspect re-bar arrangement regarding
joints, anchorage, quantities, concrete coverage, and so on for each element of reinforced
concrete structures.
c) Concrete Work
There are several ready mixed concrete plants in Tbilisi where the project will be
implemented. They are located at a distance of within one hour by delivery truck from
the project site and the daily production capacity, the materials storage condition and the
quality control in production are acceptable. The items of inspections and their
methodologies for quality control of concrete, which shall be conducted by the contractor
with the presence of the consultant, are described as follows:
2-55
1. Materials for concrete Material Item to be inspected Method of inspection
Cement Hydration heat Dissolution heat
Grading Sieve analysis
Absolute dry specific gravity Specific gravity and water absorption test
Sand/ Gravel/ Crushed Stone
Alkali aggregate reaction Alkali-reactive test
Water Organic impurities etc. Water quality test
2. Trial mix for ready-mixed concrete Item to be inspected Method of inspection
Compressive strength Compression test machine
Slump Slump cone
Concrete humidity Hygrometer
Air content Manometer
Chloride volume Measuring instrument for salt
3. Inspection before casting concrete Item to be inspected Method of inspection
Time taken for mixing and casting concrete Review log book / stop watch
Slump Slump cone
Concrete temperature Thermometer
Air contents Manometer / Air pressure gauge
Chloride volume Chloride test paper
4. Inspection of completed concrete work Item to be inspected Method of inspection
Compressive strength for structural concrete Schmidt hammer
Accuracy / precision (plumb) Plum bob, measuring tape
Accuracy / precision (floor slab levelness) Auto level, measuring tape
Finish Visual inspection
2-2-4-6 Procurement Plan
(1) Suppliers of Equipment and Materials
The major items to be procured under the project are shown below,
Principal Equipment;
PV Modules
Power Conditioner (Inc. insulated transformers or step up transformers)
Rotation Operation Control Panel
Non-principal Equipment;
Junction Box
Grid Connecting Board
Main Isolation Switch
LV switchgear
2-56
Electric Substation including transformer
Power Conditioner Outer Case
PV Distribution Board for Islanded Operation
Distribution Board for Outdoor Light
Grounding Terminal Board
Large Display
Data Management and Monitoring Systems (Personal Computer: Including data
processing software)
Meteorological observation Instruments (Pyranometer, Thermometer)
Frame Structure
Power cables
Control cables
Piping Materials
Handholes
Grounding materials
Maintenance equipment
Construction materials for installation/construction including concrete materials
Cables, cement, aggregate, reinforcing steel bars, mold forms and so on which fulfill the
international standards are widely spread through local markets and are available. As for the
procurement from overseas, the equipment is to be procured from Japan as explained in
Section 2-2-1-8 (2)
(2) Procurement Plan
The procurement contract shall include responsibility for design, manufacture, coating,
factory testing and inspection, packing, transportation, installation, testing by the suppliers,
acceptance inspection pursuant to the specification of equipment prepared by the consultant,
and delivery after fully confirming the operation by site tests and inspection. The suppliers
will obtain approval for inland transportation and installation, prepare necessary materials
for work at each site, and fully discuss with the executing agency.
(3) Transportation Plan
1) Equipment and Materials to be Procured in Georgia
As for equipment and materials to be procured in Georgia (mostly construction materials for
equipment installation and architectural works), the contractor/supplier shall purchase them
from local firms and deliver them to each project site.
2) Equipment and Materials to be Procured in Japan
Equipment and materials to be procured in Japan are to be shipped from the port of
Yokohama to the port of Batumi and carried on trucks from the port of Batumi to each
2-57
project site. The port of Batumi is one of the best operated ports and deals with 75% of the
domestic port products. The delivery from the port of Batumi to each project site generally
takes ten hours on trucks without trouble or difficulty.
3) Classification of Equipment Transportation
As for the inland transportation in Tbilisi, trailer or container trucks are adopted for delivery
of equipment and materials. Considering the procurement of local trucks and transportation
route, only 20 feet containers which are less than 23 tons in total weight are to be adopted.
2-2-4-7 Operational Guidance Plan
As the grid connected PV systems planned in this project are to be introduced for the first time for
UAG, TAV, Ilia State University and TELASI staff, it is indispensable to provide guidance on
initial operation in order to realize sustainable operation of the PV systems. The initial operation
guidance plan for the project is as follows.
(1) Contents of Initial Operation Guidance
The initial operation guidance will be given to the operation and maintenance staff by the
engineers who have been engaged in the installation work for the PV system which consist
of the PV modules, junction boxes, grid connecting board and the power conditioners which
are the main components of the PV system, along with the data management and monitoring
systems, the large display, the meteorological observation instruments and the distribution
board which are supplementary equipment. The contents and methods of the initial
operation guidance are as shown in Table 2-12 below.
2-58
Table 2-12 Initial Operational Guidance for the PV system
Content Guidance Method
To provide guidance on visual inspection items for the PV modules, confirmation of module connections, and measurement of grounding resistance.
To provide guidance on visual inspection items for the junction box, grid connecting board, rotation operation control panel and LV switchgear for PV system, confirmation of their connection with the PV modules and the power conditioners, confirmation of insulation resistance, open voltage, polarity, etc.
To provide guidance on visual inspection items for the junction box, grid connecting board, rotation operation control panel, LV switchgear for PV system, confirmation of their connection with relay terminal boxes and substation equipment, confirmation of insulation resistance and phase rotation, method of measurement of grounding resistance, etc.
To provide guidance on visual inspection items for substation equipment, confirmation of connection with power conditioners, and main incoming cable, insulation resistance, grounding resistance, phase rotation, etc.
To provide guidance on protection switching gears and relays to be equipped with the power conditioners and substation equipment, confirmation of their functions and method of setting.
To provide guidance on method of operation and shut-off, and method of measurement such as voltage of power to be generated and received.
To provide guidance on connection between the personal computer (PC) and the power conditioners, the large display, and operation of the data management and monitoring systems and the large display.
To provide guidance on connection of the watt-hour meter and reading quantity of power being generated, power demand and quantity of power being sold through the grid.
To provide guidance on visual inspection items for meteorology observation instruments, confirmation of their connection, and collection and handling the data.
Initial Operation: To explain equipment operation and provide guidance including on-the-job training for equipment handling and operation by using the operation manuals and to confirm trainees’ learning level i.e. proficiency.
(2) Implementation Plan
After installing, setting and trial operation for the PV system at both sites, the initial
operation guidance is to be conducted for two weeks at the each site by one Japanese
engineer and one local engineer who will be engaged in related works.
2-2-4-8 Soft Component (Technical Assistance) Plan
(1) Necessity of the Soft-Component Works (Technical Assistance)
UAG, TAV, Ilia State University and TELASI will be operating and maintaining a PV
system for the first time. Therefore, it is necessary for operation and management staff to
understand the basic principles and operation procedures of the PV system. Furthermore, the
work flow, which consists of collection, compilation, analysis and recording with respect to
power generating and meteorological data, must be formulated.
It is indispensable to communicate and collaborate with TELASI in order to ensure secure,
stable and safe operation of the PV system which is connected to the grid owned by TELASI.
Therefore, participation in the soft component from TELASI is essential.
2-59
Accordingly, the JICA study team proposed implementation of a soft component covering all
aspects of the above items, aiming at smooth and sustainable operation of the PV system.
(2) Goals of the Soft Component
Goals of the soft component are as follows;
The trainees obtain the ability to appropriately operate and maintain the PV system
The trainees obtain the ability to operate the interconnection system to the grid
including the countermeasures to address system troubles
The trainees obtain the ability to utilize the power generating and meteorological data
(3) Target Group (Trainees) of the Soft Component No. Target group (trainees) Items No. of trainees
1 UAG PV system maintenance staff
All items above 3
2 TAV PV system maintenance staff
All items above 5
3 Ilia State University PV system maintenance staff
All items above 10
4 TELASI Electricity distribution manager and distribution transformer maintenance staff
All items above 10
Total 28
(4) Contents of the Soft Component
The contents of the Soft Component Training Program consist of three groups as follows: a)
Operation and maintenance method of the PV system, b) Operation and maintenance of the
interconnection system to the grid, and c) Utilization of power generating and meteorological
data from the PV system.
1. Operation and Maintenance of the PV System
Contents
1) Technical guidance on basic theory and structure of the PV system
2) Technical guidance on the functions and features of the main equipment such as
the PV modules, connection boxes, the power conditioners and so on.
3) Technical guidance on troubleshooting of the PV system
4) Technical guidance on daily and periodic inspection for the PV system
5) Technical guidance on earth and insulation measurements for the PV system
6) Technical guidance on replacement of equipment for the PV system
7) Guidance on financial plans for operation and maintenance for the PV system
Training method
Lectures on outline of PV system, its components and work-flow using relevant
manuals
2-60
On-the-job training on PV system operation using the actual devices of the
project.
2. Operation and Maintenance of the Interconnection to the Grid
Contents
1) Technical guidance on equipment configuration of the substation which is the
connection point to the grid
2) Technical guidance on the functions and features of the circuit breakers,
protection equipment, transformers, and measurement equipment
3) Troubleshooting of the interconnection system to the grid
4) Technical guidance on daily and periodic inspection of the interconnection
system to grid
5) Technical guidance on earth and insulation measurements for the interconnection
system to the grid
6) Technical guidance on replacement of equipment for the interconnection system
7) Technical guidance on setting and operation for reverse power flow and self-
sustained operation
Training method
Lectures on functions and properties of the electric substation using relevant
devices
Lectures on device trouble shooting, contact system, and work flow with
relevant materials
On-the-job training on the electric substation and PV system with relevant
materials
3. Utilization of Power Generation and Meteorological Data from the PV System
Contents
1) Technical guidance on configuration of measurement equipment for power
generating
2) Technical guidance on configuration, function and features of the meteorological
measurement equipment
3) Technical guidance on data collecting and handling methods in relation to power
generating and meteorological data
4) Technical guidance on analysis and evaluation skill for power generating and
meteorological data
5) Technical guidance on public relations activity for the large display showing
graph of power generating and meteorological data
6) Technical guidance on replacement of equipment for PV systems
2-61
Training method
Lectures on functions and properties of Data Management and Monitoring
Systems with relevant devices
Lectures and on-the-job training on data processing, analytical methods, work-
flow using relevant materials and Data Management and Monitoring Systems.
(5) Soft Component Schedule
Implementation schedule of the soft component is as shown in Table 2-13. The trainees will
be divided into three groups of “UAG and TAV”, “Ilia State University” and “TELASI” for
efficiency of the soft component.
Table 2-13 Soft Component Schedule
First Month Second Month Third Month
Preparation in Japan 0.4MM
Training in Georgia 1.0MM
Report Writing in Japan 0.1MM
2-2-4-9 Implementation Schedule
The most rational implementation schedule for the procurement and installation work of the
project is as shown below. Total project implementation period will be 14 months, which
includes 4 months for detailed design and tender process, 9 months for procurement and 1.5
months for the soft component.
Table 2-14 Implementation Schedule
1 2 3 4 5 6 7 8 9 10 11 12 13 14
1 2 3 4 5 6 7 8 9 10 11 12 13 14
Transportation
Installation Frame Structure
Procurem
ent/InstallationS
oft Com
ponent
4 months in total
1.5 months
9.0 months
Manufacturing
Work in Japan
Tender
Design
Ilia State University
TIA
Site Survey
2-62
2-3 Obligations of Recipient Country
Upon the implementation of this Project as a grant aid from Japan, Georgia shall be responsible for
those items indicated in Table 2-11. Both the governments of Japan and Georgia have confirmed
the needs for taking the following measures.
(1) Undertakings to Be Borne by Georgian Side
1) Tax Exemption
The Georgian Authority will exempt customs duties, domestic taxes and other charges for
Japanese nationals entering into the recipient country to procure and install equipment and
materials based on the procurement contract of the Project and to implement various
activities. The Georgian Authority will also facilitate prompt processing of customs
clearance of procured equipment and materials, and exempt import duties and VAT for such
equipment and materials.
2) Convenience Provision
To accord Japanese nationals, whose services may be required in connection with the supply
of the products and the services under the verified contract, such conveniences as may be
necessary for their entry into Georgia and stay therein for the performance of their work.
3) Banking Arrangement (B/A), Authorization to Pay (A/P)
The Georgian Authority will open a bank account in its name at a Japanese bank and issue
Authorization to Pay (A/P) to the bank. Based on the Banking Arrangement (B/A), the
Georgian side should bear advising commissions of an Authorization to Pay (A/P) and
payment commissions to the Bank.
(2) Works by the Georgian Side
1) Cutting branches of existing trees.
At Ilia State University site, there exist trees. These tree branches should be cut off in order
to ensure efficient power generation by the PV system.
2) Removal of Existing Walls and Revetment
At Ilia State University site, there exist walls and a revetment. These walls should be
removed. The existing meter box should be capped after removal of the walls.
3) Reconnection of existing incoming cables
At Ilia State University site, a new electric substation with protective relays will be installed
next to the existing electric substation. The new electric substation will replace the existing
one. Therefore, a lead-in cable (three-phase three-wire system 6kV) drawn in to the existing
electric substation should be repositioned and connected to the new transformer.
2-63
Three sets of middle-voltage cables from Bagebi electric power substation are embedded in
the space where the new electric substation will be installed. These cables should also be
repositioned and connected to the new transformer
4) Installation of Security Cameras
Additional security cameras will be installed in addition to the existing security system at the
university.
2-4 Project Operation Plan
2-4-1 Operation and Maintenance Plan
The operation and maintenance structure and inspection, cleaning and maintenance items for the
PV system are as follows.
(1) Operation and Maintenance Structure
TIA: 8 Staff (including 3 O&M staff from UAG and 5 O&M staff from TAV)
Ilia State University: 10 Staff (including present O&M staff, “6” grade in local standard, and
two “5” grade electricians)
(2) The PV System Inspection Items
The main items of regular inspection and cleaning (once a month or more) are as follows.
These items are to be managed mainly by engineers and conducted by technical staff.
Visual inspection and cleaning: the PV modules, the connection box, the power
conditioners, etc.
Other work: Cleaning, etc.
The main items of periodic inspection (twice a year or more) are as follows. These items are
to be managed mainly by engineers and conducted by technical staff.
Visual and finger touch inspection: the PV modules, the connection box, the power
conditioner, etc.
Insulation resistance measuring: the connection box, the power conditioner, the
switchgear, cables, etc.
Open voltage test: the relay terminal box
2-64
2-5 Project Cost Estimation
2-5-1 Initial Cost Estimation
Items estimated for initial cost are as follows;
(1) Cutting branches of existing trees
(2) Removal of existing walls and revetment
(3) Reconnection of existing incoming cables
(4) Installation of security camera(s)
2-5-2 Operation and Maintenance Cost
The PV system for the project consists of the PV modules, the power conditioners, the
meteorological observation instruments, the data management and monitoring systems, the large
display, substation equipment, etc. Since all items except for the substation equipment are newly
installed, items for operation and maintenance cost are as follow:
Reduction of electricity cost by power generated by the PV system
Electricity cost for the data management and monitoring system, the large display, etc.
Labor cost for cleaning of the PV modules
Personal expense for operation and maintenance staff for the PV system
Consumable materials cost
(1) Reduction of Electricity Cost by PV Power Generation
1) TIA
Annual generated energy is estimated to be 329,000kWh, equivalent to annual electric cost
reduction of 47,700 Lari.
Power Purchase Reduction (Lari) = PV Power Generation(kWh)×Power Price (Lari/kWh)
= 329,000 kWh×0.145 Lari/kWh
= 47,700 Lari
2) Ilia State University
The annual generated energy is estimated to be 32,000kWh, equivalent to annual electric
cost reduction of 4,640 Lari.
Power Purchase Reduction (Lari) = PV Power Generation(kWh)×Power Price (Lari/kWh)
= 32,000 kWh×0.145 Lari/kWh
= 4,640 Lari
2-65
(2) Electricity Cost for the Data Management and Monitoring System, Large Display, etc.
1) TIA
Electricity cost of 3,140 Lari will be required annually for operating one set of data
management and monitoring systems and one set of large display (100 inch), and lighting
including entrance section.
Data management and monitoring systems
Power Purchase (Lari) = Power Price (Lari/kWh)×Power Consumption(kW)×hours of
use(h/day)×days a year(days/year)×set
= 0.145Lari/kWh×0.5 kW×24 h/day×365 day/year×1
= 635 Lari
Large Display (100 inches)
Power Purchase (Lari) = Power Price (Lari/kWh)×Power Consumption (kW)×hours of
use(h/day)×days a year(days/year)×set
= 0.145Lari/kWh×1.5 kW×24 h/day×365 day/year×1
= 1,905 Lari
Lighting
Power Purchase(Lari) = Power Price(Lari/kWh)×Power Consumption(kW)×hours of
use(h/day)×days a year(days/year)×set
= 0.145Lari/kWh×0.05 kW×12 h/day×365 day/year×19
= 603 Lari
Total Electricity Cost
Total Power Purchase (Lari) = 635 Lari + 1,905 Lari + 603 Lari
≒ 3,140 Lari
2) Ilia State University
Electricity cost of 2,660 Lari will be required annually for operating two sets of data
management and monitoring systems (one for education) and one set of large display (60
inch).
Data management and monitoring systems
Power Purchase (Lari) = Power Price (Lari/kWh)×Power Consumption(kW)×hours of
use(h/day)×days a year(days/year)×set
= 0.145Lari/kWh×0.5 kW×24 h/day×365 day/year×1
=635 Lari
Data management and monitoring systems for education
Power Purchase (Lari) = Power Price (Lari/kWh)×Power Consumption(kW)×hours of
use(h/day)×days a year(days/year)×set
2-66
= 0.145Lari/kWh×0.5 kW×8 h/day×250 day/year×1
= 145 Lari
Large Display(100 inches)
Power Purchase (Lari) = Power Price (Lari/kWh)×Power Consumption(kW)×hours of
use(h/day)×days a year(days/year)×set
= 0.145Lari/kWh×10.9kW×8 h/day×250 day/year×1
= 261 Lari
Lighting
Power Purchase (Lari) = Power Price (Lari/kWh)×Power Consumption(kW)×hours of
use(h/day)×days a year(days/year)×set
= 0.145Lari/kWh×0.05 kW×10 h/day×365 day/year×32
= 847 Lari
Total Electricity Cost
Total Power Purchase (Lari)=635 Lari +145Lari+261 Lari + 847 Lari
≒ 1,880 Lari
(3) Labor Cost for Cleaning of the PV Modules
1) TIA
Labor cost of 3,940 Lari is estimated to be required annually for cleaning the PV modules
(310kW) once a month.
Labor Cost (Lari) = Staff (person/time)×Times (times/year)×Cost per person(Lari/person)
= 6 person/time×12 times/year×54.8 Lari/person
≒ 3,940 Lari
2) Ilia State University
Labor cost of 660 Lari is estimated to be required annually for cleaning the PV modules
(37kW) once a month.
Labor Cost (Lari) = Staff (person/time)×Times(times/year)×Cost per person (Lari/person)
= 1 person/time×12 times/year×54.8 Lari/person
≒ 660 Lari
(4) Personal Expense for Operation and Maintenance Staff for the PV System
At both TIA and Ilia State University sites, maintenance is necessary not only for the PV
system but also for overall existing facility equipment. Three full-time staff members are
presumed to be necessary for each.
At present, five full-time employees work at TIA, and three at Ilia State University, so no
additional staff is required.
2-67
(5) Consumable Materials Cost
The data management and monitoring system measurement includes the ink jet printer. The
ink cartridge will have to be replaced twice a year. One printer will be for TIA and two for
Ilia State University. The annual cost will be 70 Lari and 140 Lari respectively.
The maintenance costs mentioned above are summarized in Table 2-15 and Table 2-16.
Table 2-15 Maintenance Cost for the Project (TIA) (Unit: Lari)
Item Annual Cost % against
expenditure in 2010Expense item and expenditure in
2010
Reduction of electricity cost by PV power generation
-47,700 -6.32% Power consumption cost 754,701
Electricity cost for the data management and monitoring system, the large display, etc.
3,140 0.42% Power consumption cost 754,701
Labor cost for regular PV module cleaning
3,940 - -
Personnel expense for operation and maintenance staff for PV system
0 -
-
Consumable materials cost 70 - -
Total -40,550 -5.37% Total expenditure 754,701
Note: 1 Georgian Lari = 48 JPY
As for TIA, the current budget can cover the operation and maintenance cost due to
reduction in power purchase by PV power generation.
Table 2-16 Maintenance Cost for the Project (Ilia State University) (Unit: Lari)
Item Annual
Cost % against
expenditure in 2008Expense item and expenditure in 2008
Reduction of electricity cost by PV power generation
-4,640 -17.39% Power consumption cost 26,680
Electricity cost for the data management and monitoring system, the large display, etc.
2,660 7.05% Power consumption cost 26,680
Labor cost for regular PV module cleaning
660 2.5% Maintenance cost 26,000
Personnel expense for operation and maintenance staff for PV system
0 0% Maintenance cost 26,000
Consumable materials cost 140 0.5% Maintenance cost 26,000
Total -1,190 -3.72% Total expenditure 52,680
Note: 1 Georgian Lari = 48 JPY
As for Ilia State University, the current budget can cover the operation and maintenance cost
due to reduction in power purchase by PV power generation.
2-68
CHAPTER 3
PROJECT EVALUATION AND RECOMMENDATIONS
Chapter 3 Project Evaluation and Recommendations
3-1 Project Effect
(1) Expected Effect
The following “Table 3-1” shows the specific effects (results) expected to be achieved by the
implementation of the project.
Table 3-1 Project Effect
Present situation and problems
Countermeasure by the project
Direct Effects Indirect Effect/Degree of
improvement
1 Georgia is insufficient in ability and funds to pursue both Green house gas (GHG) reduction and economic development
2 Georgia aims at energy independence because most of the fuel for thermal power generation is imported
1 Introduction of the grid connected PV system
2 Soft Component (Technical assistance) for operation and maintenance of the above said system
1 Annual reduction of 200 (t-CO2/year) in green house gas (GHG) emission
2 Showcase effects that the PV systems will be shown to 820 thousand persons and 6.55 million vehicles annually
1 Contribution to the upper level plan and promotion of dissemination and expansion of PV system in Georgia
2 Contribution to the research and development of renewable energy and fostering of related industries in Georgia
(2) Showcase effect
1) TIA
TIA is located approximately 20km east of the center of Tbilisi city. The showcase effect is
expected to be high because the PV system will be seen by passengers (more than 8 hundred
thousand per year). The increase rate goes up every year and it hit 17% in 2010. In addition,
the showcase effect is expected not only for passengers but for drivers, neighbors and airport
staff. Therefore, a high showcase effect is expected.
2) Ilia State University
The showcase effect at Ilia State University is also expected to be high because the PV
system will be seen by passengers, students (Approx. 8,000) and academic staff (Approx.
300). In addition, a heavy trafficked road (Three lanes each way, six lanes in total) in front of
the university will contribute to the showcase effect (a total of 6.55 million vehicles
annually). There are main facilities such as a stadium, parks and shopping malls around it so
the showcase effect is expected for a lot of neighboring citizens too.
(3) Reduction of CO2 emission
By introducing the PV system, reduction of CO2 emission of 200t will be achieved (182.5t at
TIA and 17.7t at Ilia State University) which is equivalent to the CO2 absorbing ability of
14,300 cedar trees and 67,000 liters of petroleum oil saving
3-1
Table 3-2 Reduction of CO2 Emission
Project Site (PV capacity)
Power Generation (kWh/year)
CO2 Reduction (kg-CO2/year)
CO2 Absorption by Cedar Trees
(trees/year)
Petroleum Saving (Bunker C)
(l/year)
TIA (310kW)
329,000 182,590 13,042 61,271
Ilia State University (37kW)
32,000 17,760 1,268 5,959
Total (347kW)
361,000 200,350 (Approx.200 t-CO2/year)
14,310 (Approx. 14,300)
67,230 (Approx.62,000l/year)
CO2 Reduction (kg-CO2/year)= Annual power generation (kWh/year) × Emission Coefficient(0.555(kg-CO2/kWh))1 CO2 Absorption by Cedar Trees (trees/year)=CO2 Reduction(kg-CO2/year) /CO2 Absorption by a cedar tree(14kg-CO2/tree) Petroleum Saving (Bunker C)= CO2 Reduction (kg-CO2/year)/ Emission Coefficient(2.98(kg-CO2/l)
2
The PV system in this project will enhance environmental consciousness and is expected to
promote renewable energy in Georgia. The PV system will also enable reverse power flow
by interconnection to the grid in the future. This eventually will contribute to reduction of
green house gases and promote international climate change policies as a part of “Cool Earth
Partnership”.
3-2 Recommendations
3-2-1 Issues to be addressed by the recipient country and recommendations
To attain the long term effects brought by the project, the following items shall be taken into
account after implementation of the project.
Georgia has aggressively promoted installation of renewable energy such as solar thermal and wind
power. Under such situation, it is essentially important to use the PV system of the project as a
jump start to promote PV power generation. Therefore, it is highly recommended that a policy for
introduction of renewable energy such as preferential taxation, subsidy, Feed-in Tariffs (FIT) or
Renewable Portfolio Standard (RPS) is formulated as quickly as possible.
3-2-2 Technical cooperation and tie-up with other donors
Technical and economic assistance by Japan, international organizations and other developed
countries is essential for dissemination of PV power generation such as installation of PV systems
for residential buildings, work places and offices and establishment of PV power plants by private
companies. Therefore, in addition to technical assistance by Japanese private companies and other
possible bodies through international organizations such as PV panel manufacturers,
Institutionalization of grid connected PV systems including reverse power flow, high performance
and large scale battery systems, Smart Grids and so on, financial assistance is also necessary.
1 Ministry of Environment of Japan 2 Ministry of Environment of Japan
3-2