43
Document of The World Bank Report No: ICR1984 IMPLEMENTATION COMPLETION AND RESULTS REPORT (IDA-H2970) ON A Grant IN THE AMOUNT OF SDR 13.7 MILLION (US$ 20.4 MILLION EQUIVALENT) TO THE ISLAMIC REPUBLIC OF AFGHANISTAN FOR A CIVIL SERVICE REFORM PROJECT January 25, 2012 Governance and Public Sector Afghanistan South Asia Region Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized

The World Bank Report No: ICR1984 IMPLEMENTATION ... · PDF fileIMPLEMENTATION COMPLETION AND RESULTS REPORT (IDA-H2970 ... 04/02/2007 Restructuring ... Consistency and transparency

  • Upload
    vuliem

  • View
    216

  • Download
    2

Embed Size (px)

Citation preview

Document of

The World Bank

Report No: ICR1984

IMPLEMENTATION COMPLETION AND RESULTS REPORT

(IDA-H2970)

ON A

Grant

IN THE AMOUNT OF SDR 13.7 MILLION

(US$ 20.4 MILLION EQUIVALENT)

TO THE

ISLAMIC REPUBLIC OF AFGHANISTAN

FOR A

CIVIL SERVICE REFORM PROJECT

January 25, 2012

Governance and Public Sector

Afghanistan

South Asia Region

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

CURRENCY EQUIVALENTS

Currency Unit = Afghani (Afn)

US$ 1.00 = Afn 48.6

FISCAL YEAR: March 20- March 21

ABBREVIATIONS AND ACRONYMS

ARS Administrative Reform Secretariat MPW Ministry of Public Works

ARTF Afghanistan Reconstruction Trust Fund MRRD Ministry of Rural Rehabilitation

and Development

CBR Capacity Building for Results Facility MTCA Ministry of Transport and Civil

Aviation

CSMD Civil Services Management Directorate MTR Mid-Term Review

CSRP Civil Service Reform Project PAD Project Appraisal Document

GoA Government of the Islamic Republic of

Afghanistan PAR Public Administration Reform

HRM Human Resource Management PARD Public Administration Reform

Department

HRMD Human Resource Management

Directorate PCD Program Coordination

Department

I-ANDS Interim Afghanistan National

Development Strategy

P&G Pay and Grading

IARCSC Independent Administrative Reform and

Civil Service Commission PDOs Project Development Objectives

IAB Independent Appointments Board PMU Project Management Unit

ICR Implementation Completion and Results

Report

PRR Priority Reform and Restructuring

IDA International Development Association QAG Quality Assurance Group

ITA International Technical Assistants QALP-2 Second Quality Assessment of the

Lending Portfolio

MAC Ministerial Advisory Committee RIMU Reform Implementation and

Management Unit

MAIL Ministry of Agriculture, Irrigation, and

Livestock PSC Project Steering Committee

M&E Monitoring and Evaluation SMG Senior Management Group

MCP Management Capacity Program TA Technical Assistance

MoF Ministry of Finance

Vice President: Isabel M. Guerrero, SARVP

Country Director: Josephine Bassinette, SACAF

Sector Manager: Antonius Verheijen, SASGP

Project Team Leader: Satyendra Prasad, SASGP

ICR Team Leader: Vikram K. Chand, SASGP

AFGHANISTAN

Civil Service Reform Project

CONTENTS

Data Sheet

A. Basic Information

B. Key Dates

C. Ratings Summary

D. Sector and Theme Codes

E. Bank Staff

F. Results Framework Analysis

G. Ratings of Project Performance in ISRs

H. Restructuring

I. Disbursement Graph

1. Project Context, Development Objectives and Design ............................................... 1

2. Key Factors Affecting Implementation and Outcomes .............................................. 6

3. Assessment of Outcomes .......................................................................................... 11

4. Assessment of Risk to Development Outcome ......................................................... 15

5. Assessment of Bank and Borrower Performance ..................................................... 16

6. Lessons Learned ....................................................................................................... 19

7. Comments on Issues Raised by Borrower/Implementing Agencies/Partners .......... 20

Annex 1. Project Costs and Financing .......................................................................... 22

Annex 2. Outputs by Component ................................................................................. 23

Annex 3. Bank Lending and Implementation Support/Supervision Processes ............ 27

Annex 4. Summary of Borrower's ICR and/or Comments on Draft ICR ..................... 29

Annex 5. List of Supporting Documents ...................................................................... 31

MAP

A. Basic Information

Country: Afghanistan Project Name: AF: Civil Service

Reform Project

Project ID: P097030 L/C/TF Number(s): IDA-H2970

ICR Date: 01/25/2012 ICR Type: Core ICR

Lending Instrument: TAL Borrower: GOVERNMENT OF

AFGHANISTAN

Original Total

Commitment: XDR 13.50M Disbursed Amount: XDR 9.53M

Revised Amount: XDR 13.50M

Environmental Category: C

Implementing Agencies:

Independent Administrative Reform and Civil Service Commission (IARCSC)

Cofinanciers and Other External Partners:

B. Key Dates

Process Date Process Original Date Revised / Actual

Date(s)

Concept Review: 10/18/2005 Effectiveness: 07/11/2007 07/11/2007

Appraisal: 04/02/2007 Restructuring(s): 11/06/2009

Approval: 05/29/2007 Mid-term Review: 07/08/2010 10/14/2010

Closing: 07/31/2011 07/31/2011

C. Ratings Summary

C.1 Performance Rating by ICR

Outcomes: Moderately Unsatisfactory

Risk to Development Outcome: High

Bank Performance: Moderately Unsatisfactory

Borrower Performance: Moderately Unsatisfactory

C.2 Detailed Ratings of Bank and Borrower Performance (by ICR)

Bank Ratings Borrower Ratings

Quality at Entry: Moderately

Unsatisfactory Government:

Moderately

Unsatisfactory

Quality of Supervision: Moderately

Unsatisfactory

Implementing

Agency/Agencies:

Moderately

Unsatisfactory

Overall Bank

Performance:

Moderately

Unsatisfactory Overall Borrower

Performance:

Moderately

Unsatisfactory

C.3 Quality at Entry and Implementation Performance Indicators

Implementation

Performance Indicators

QAG Assessments

(if any) Rating

Potential Problem Project

at any time (Yes/No): No

Quality at Entry

(QEA):

Moderately

Unsatisfactory

Problem Project at any

time (Yes/No): Yes

Quality of

Supervision (QSA): Moderately Satisfactory

DO rating before

Closing/Inactive status:

Moderately

Unsatisfactory

D. Sector and Theme Codes

Original Actual

Sector Code (as % of total Bank financing)

Central government administration 90 90

Sub-national government administration 10 10

Theme Code (as % of total Bank financing)

Administrative and civil service reform 100 100

E. Bank Staff

Positions At ICR At Approval

Vice President: Isabel M. Guerrero Praful C. Patel

Country Director: Anthony Cholst Alastair J. McKechnie

Sector Manager: Antonius Verheijen Ijaz Nabi

Project Team Leader: Satyendra Prasad Anne Tully

ICR Team Leader: Vikram K. Chand

ICR Primary Author: Vikram K. Chand

F. Results Framework Analysis

Project Development Objectives (from Project Appraisal Document) Across the time frame of the project, (by 2011), a significant proportion of key

ministries/agencies will be performing their functions to an acceptable level and can be

held accountable for the use of public resources

Revised Project Development Objectives (as approved by original approving authority)

Upon restructuring of the project in November 2009, the PDO was modified as follows:

Across the timeframe of the project (by July 2011) more accountable and transparent

practices in the management of civil service will be introduced in selected ministries.

(a) PDO Indicator(s)

Indicator Baseline Value

Original Target

Values (from

approval

documents)

Formally

Revised

Target

Values

Actual Value

Achieved at

Completion or

Target Years

Indicator 1 : By Project Closing Date, 100 percent of civil service posts will be re-graded

according to the provisions of the Civil Servants Law & related regulations

Value

quantitative or

Qualitative)

0% 100% 87%

Date achieved 09/01/2007 07/31/2011 07/31/2011

Comments

(incl. %

achievement)

A total of 325,499 out of 375,000 positions re-graded. Re-gradation Major

ministries completed.

Indicator 2 : By Project Closing Date, 100 percent of civil service appointments being made

on a merit basis following the Civil Servants Law and related regulations

Value

quantitative or

Qualitative)

0% 100% 80%

Date achieved 09/01/2007 07/31/2011 07/31/2011

Comments

(incl. %

achievement)

Ministries/agencies refer a large portion of grade 1-2 appointments to the

Independent Appointments Board (IAB) on the basis of merit. However in many

ministries it is evident that significant numbers of grade 1-2 posts are not civil

service posts.

Indicator 3 :

By Project Closing Date, regulations and procedures for key HR actions,

including recruitment, promotion, disciplinary actions, retrenchment/severance,

and code of conduct have been adopted, in accord

Value

quantitative or

Qualitative)

Civil Servants Law has

been enacted but

preparation of key

implementing regulations

is lagging.

The regulatory

framework for

civil service

management is

complete and

consistently

applied

(confirmed by

regular HR

audits).

HR laws and

regulations in place.

Civil Servants Law

is under revision.

Performance

appraisal process

needs to be

strengthened. HR

compliance

monitoring needs to

be strengthened.

Date achieved 09/01/2007 07/31/2011 07/31/2011

Comments

(incl. %

achievement)

(b) Intermediate Outcome Indicator(s)

Indicator Baseline Value

Original Target

Values (from

approval

documents)

Formally

Revised

Target Values

Actual Value

Achieved at

Completion or

Target Years

Indicator 1 : Number of restructured and functional HR Departments in Line Ministries.

Value

(quantitative

or Qualitative)

0 5 5

Date achieved 09/01/2007 07/31/2011 07/31/2011

Comments

(incl. %

achievement)

Functionality improvements evident in five ministries, MoF, MRRD, MAIL,

MoPW and MoTCA. Capacity built for P&G implementation and compliance to

HR policies and regulations.

Indicator 2 : Number of ministries that have implemented P&G reform

Value

(quantitative

or Qualitative)

0 40 25

Date achieved 09/01/2009 07/31/2011 07/31/2011

Comments

(incl. %

achievement)

25 ministries/agencies have completed the pay and grading process, P&G in one

ministry is suspended and six are in progress. 17 ministries/agencies are yet to

start the process.

Indicator 3 : Quality and consistency of HR procedures within ministries against clearly set

standards.

Value

(quantitative

or Qualitative)

Civil Servants Law

gazetted. Preparation of

key implementing

regulations lagging.

Early compliance

monitoring

activities started.

Too early to

monitor

developments.

Date achieved 09/09/2007 07/31/2011

Comments

(incl. %

achievement)

Indicator 4 : Consistency and transparency of the recruitment process and perception of

integrity in it.

Value

(quantitative

or Qualitative)

While civil servants law

legally requires merit

based recruitment

procedures, WB

vulnerability assessment

of the IAB confirms that

recruitment and other HR

decisions continue to be

adversely affected by

entho-centric politics and

patronage.

Merit based

appointments have

increased.

Adherence to Civil

Service laws and

regulations.

However, in many

ministries/agencies

significant number

of grade 1-2 posts

are not civil service

posts and

recruitment of these

are carried out

through donor top-

ups

Date achieved 09/01/2007 07/31/2011

Comments

(incl. %

achievement)

G. Ratings of Project Performance in ISRs

No. Date ISR

Archived DO IP

Actual

Disbursements

(USD millions)

1 01/22/2008 Satisfactory Satisfactory 0.00

2 08/07/2008 Moderately Satisfactory Moderately Satisfactory 0.60

3 03/20/2009 Moderately

Unsatisfactory

Moderately

Unsatisfactory 1.52

4 10/30/2009 Unsatisfactory Moderately

Unsatisfactory 3.60

5 12/15/2009 Unsatisfactory Moderately

Unsatisfactory 4.80

6 12/17/2010 Moderately

Unsatisfactory

Moderately

Unsatisfactory 11.07

H. Restructuring (if any)

Restructuring

Date(s)

Board

Approved

PDO Change

ISR Ratings at

Restructuring

Amount

Disbursed at

Restructuring

in USD

millions

Reason for Restructuring &

Key Changes Made DO IP

11/06/2009 Y U MU 3.60

The project operates in an

exceptionally challenging

environment and a number of

risks identified in the original

project document have

materialized despite efforts to

mitigate them. The restructuring

is undertaken to align the PDO

with a more feasible set of

outcomes that can be achieved

in the remaining

implementation period. There

continue to be reasonable

prospects for achieving

significant results from a more

focused, less ambitious agenda

so that suspending the project

would not be advisable.

If PDO and/or Key Outcome Targets were formally revised (approved by the original approving

body) enter ratings below:

Outcome Ratings

Against Original PDO/Targets

Against Formally Revised PDO/Targets

Overall (weighted) rating Moderately Unsatisfactory

I. Disbursement Profile

.

1

1. Project Context, Development Objectives and Design

1.1 Context at Appraisal

Building an effective state - that can provide security and services to the people, while protecting

their rights - has been at the heart of the reconstruction effort in Afghanistan. At the end of 2001,

after nearly a quarter century of wars and civil strife the political system had largely collapsed.

While many of the formal structures and some of the traditional practices of public administration

remained in place, they lacked the human, financial and physical resources to do their job,

particularly in a modem context. The new government faced enormous challenges in restoring

security, taking charge of running the country, building consensus across various political

factions and rebuilding the very limited capacity of the state.

Despite this, progress had been made in restoring institutions of governance and laying the basis

for a strong economic recovery. A new Constitution was adopted in January 2004 and Afghans

actively participated in elections for their first democratically elected President in December 2004.

Elections for the Wolesi Jirgu (lower house of the National Assembly) and for provincial councils

took place in September 2005. Female turnout in both elections was around 40 percent of the total

electorate and more than a quarter of Wolesi Jirgu members were female. The inauguration of the

National Assembly in December 2005 marked the formal conclusion of the Bonn political

transition process.

Afghanistan‟s economy had recovered strongly from a state of collapse at the end of the Taliban

rule. The real value of non-opium Gross Domestic Product (GDP) increased by 29 percent in

2002/03, 16 percent in 2003/04, 8 percent in 2004/05, and 14 percent in 2005/06. This solid

performance was supported by the government‟s sound macroeconomic policies. Afghanistan had

successfully completed all quarterly reviews under the IMF Staff-Monitored Program and the first

review of the Poverty Reduction and Growth Facility (PRGF) program. Monetary policy was

restrained, relying on fiscal discipline and a no-overdraft rule that prohibited Central Bank

financing of the deficit. Inflation was decelerating with year-on-year inflation declining to 5.2

percent in September 2006 (compared to 16 percent in 2004/05).

Despite this economic recovery and sound macroeconomic policies, progress in development

remained tenuous across the country. Security problems continued to be encountered almost

daily. Sustaining gains in development outcomes, particularly in health and education, remained a

challenge given the inability of government and donor agencies to access various communities.

The opium economy, accounting for around a quarter of total GDP, was still Afghanistan‟s

leading economic activity, and a key contributor to insecurity, promoting corruption, capture, and

violence.

1.2 Government Public Administration Reform Framework

The Government‟s Public Administration Reform (PAR) Framework, as reflected in

Afghanistan‟s Interim National Development Strategy (I-ANDS), had as its goal the

establishment of strong state institutions at the central and sub-national level, capable of

achieving improvements in the delivery of services. The PAR Framework flowed from the I-

ANDs which envisioned a well functioning and affordable administration that was small and

focused on core functions. Key elements of the framework included:

Establishing a well-performing, merit-based civil service;

2

Strengthening the structure of Government, especially line ministries and sub-national

administration

Building institutions of public accountability.

In addition under the Afghanistan Compact, the government agreed to specific benchmarks for

public administration reform including inter alia:

The rationalization and restructuring of Government to ensure a fiscally sustainable

public administration.

Strengthening the civil service commission and putting in place a transparent mechanism

for the selection of senior civil servants, members of the judiciary, and provincial

governors.

Strengthening performance management at all levels of the system

1.3 Rationale for IDA’s Involvement in Public Administration

Public administration reform was essential to rebuilding the state, institutionalizing improved

governance and combating corruption. Without a medium term strategy to build core capacities in

line ministries, Afghanistan would most certainly remain dependent on international technical

assistance and/or donor funds. The project was complemented by a program of analytical work

focusing on sub-national governance and institutions of accountability, developing an

implementation plan for civil service reform to meet compact benchmarks, and assistance

towards the formulation of an anti-corruption strategy. The Bank had extensive experience in

promoting public administration reform in Afghanistan through a series of development policy

credit/grants intended to bolster reforms.

In addition, the Management Capacity Program (MCP), an initiative funded by the Afghanistan

Reconstruction Trust Fund (ARTF) administered by the Bank supported the induction of Afghan

consultants into civil service positions. Given its experience in public administration reform –

and the importance of the area for Afghanistan – the rationale for Bank involvement was a strong.

1.4 Original Project Development Objectives (PDO) and Key Indicators (as approved)

The original development objective for this project stated that “across the time frame of the

project, (by 2011), a significant proportion of service delivery ministries will be performing their

functions to an acceptable level and can be held accountable for the use of public resources. This

will have resulted from core ministries having been reorganized according to functions and civil

servants being managed according to clear rules and procedures.”

Key indicators of the progress in meeting the development objective included at the outset:

The number of service delivery ministries reporting on progress toward achieving their

sectoral objectives, and the use of resources for those purposes.

The proportion of civil service appointments based on merit, and the rigor of the merit-

based appointments process.

The consistency of the application of the Civil Service Law and regulations to the

management of civil servants.

The extent to which Independent Administrative Reform and Civil Service Commission

(IARCSC) was able to coordinate donor support for civil service reform, as well as

3

monitor and report on progress regarding the implementation of the approved civil

service reform plan.

1.5 Revised PDO (as approved by original approving authority) and Key Indicators,

and reasons / justification

The development objective for the project was revised to state that “across the timeframe of the

project (by July 2011) more accountable and transparent practices in the management of the civil

service will be introduced in selected ministries.”

Key indicators to assess progress towards this revised PDO by the project closing date included:

100% of civil service posts will be re-graded according to the provisions of the civil

service law and related regulations

100% of civil service appointments will be made on a merit-basis following the civil

servants law and related regulations.

Regulations and procedures for key human resource (HR) actions, including recruitment,

promotion, disciplinary actions, retrenchment, severance, and code of conduct have been

adopted in accordance with the civil servants law and applied consistently across the

human resources departments of participating line ministries.

Reasons for Restructuring

The primary reason for restructuring was corrective. Government commitment at all

levels to the comprehensive public administration reform agenda originally supported by

the project had weakened since project approval. The political environment had become

more challenging with attention being absorbed by the deteriorating security and

economic situation. Many line ministries did not consider strategic planning and

organizational reform a priority. Fragmented responsibilities within Independent

Administrative Reform and Civil Service Commission (IARCSC), and weak coordination

and communication, both internally and externally, impaired its ability to manage the

project effectively.

Consequently, progress targets for the first project year were almost entirely missed, and

only limited progress was made in the second year. Progress in the preparation and

enactment of key civil service regulations lagged. The roll out of the Pay and Grading

reform started with almost a one year delay, and the focus was largely on achieving

quantitative targets with little regard to quality. While legally required, implementation of

merit-based procedures continued to be a challenge in a public sector environment still

characterized by patronage and ethnically-based politics. While some modest changes to

the organizational structures of ministries were achieved as part of the roll out of the new

pay and grading policy, IARCSC support to line ministries with regard to strategic

planning and more substantial organizational reforms was not effective. As a result, it

became clear that the project would not achieve the impact on ministry performance and

service delivery in selected line ministries set out in the original PDO.

Restructuring was intended to recalibrate the project's development objectives to focus on

more attainable priorities, adjust the project's scope to focus on areas with stronger

government ownership; and strengthen implementation arrangements within the

IARCSC.

4

1.6 Main Beneficiaries

The main beneficiaries of the project were expected to be (i) the Government of Afghanistan and

(ii) the Independent Administrative Reform and Civil Service Commission (IARCSC).

(i) Government of Afghanistan: The government was expected to benefit by putting in place a

new pay and grading system designed to improve transparency, attract talent to the civil service,

and shift from a civil service that historically rewarded seniority to one that supported

performance. In addition, the project sought to improve the working of the Afghan civil service

by creating a system for merit-based recruitment, creating a universally applicable framework of

laws, rules, and regulations for the civil service as a whole, and improving the functioning of

ministries through organizational restructuring and better human resource management.

(ii) The IARCSC: The IARCSC was expected to benefit by receiving technical assistance to

improve the capacity of several of its units, particularly the Human Resource Policy Department,

the Public Administration Reform Department (PARD), and the Administrative Reform

Secretariat (ARS). In addition, the project was expected to improve the capacity of the

Independent Appointments Board to implement merit-based recruitment, particularly for senior

civil servants, and strengthen the working of the Appeals Board.

1.7 Original Components (as approved)

Component One: Organizational Reforms within Core Ministries ($8.4 million)

Activities under this component were intended to result in a number of core ministries being able

to perform their functions more effectively, and with greater transparency in the use of resources.

This rubric consisted of two sub-components: (i) Line Ministry Reorganization and (ii)

strengthening the IARCSC as a facilitating and coordinating agency for civil service reform.

Sub-component (i) was intended to provide technical assistance, training and limited equipment

support to core ministries to support their reorganization efforts. Work under this sub-component

aimed to improve the ability of line ministries to develop their own work programs; justify their

use of public resources to Cabinet and Parliament more effectively; put in place strategic plans

with clear deliverables and the ability to monitor them; continue with organizational

restructuring; apply new human resource procedures and policies across ministries including

transitioning to a new pay grade structure and merit-based recruitment; and build donor support to

address critical funding gaps. Each ministry was expected to set up a Reform Implementation

Management Unit (RIMU) to lead its restructuring. It was expected that four to five ministries

would be supported under the project based on such factors as their financial importance, role in

service delivery, and level of commitment to reform. (Estimated Cost $7.Im)

Sub-component (ii) was designed to support technical assistance and capacity building for the

IARCSC to facilitate and coordinate reforms across line ministries, and ensure consistency. The

Public Administration Reform Department of the IARCSC was the nodal point within the

IARCSC for this sub-component. (Estimated cost $1.3m)

Component Two: Implementation of Merit-based Human Resource Management Reforms in

Government ($8.7 million).

This component was designed to support the establishment and implementation of merit-based

HR policies and practices. Assistance was to be provided through three sub components: (i)

Establishing and extending HR policies and practices to line ministries: This sub-component

5

focused on preparing regulations and procedures under the civil service law and applying them

across ministries. Technical assistance was to be provided to ministries to create human resource

departments, along with training and mentoring for HR staff and mangers. Assistance was to be

provided to the Human Resources Policy Department of the IARCSC to carry out the program.

(Estimated Cost $3.5m) (ii) Strengthening appointments procedures: This involved implementing

an action plan for merit-based recruitment and better monitoring of appointments at junior levels

through the Independent Appointments Board (IAB). This sub-component also sought to

strengthen the Appeals Board to ensure effective resolution of complaints including those likely

to arise from pay and grading reforms. (Estimated Cost $1.4m) (iii) Implementing the

government’s pay and grading reform in line with fiscal parameters and ministry implementation

readiness: This sub-component was supposed to involve undertaking a sustained communications

plan to build understanding of the new reforms in pay and grading; re-grading positions onto a

new eight grade structure; and developing procedures and guidance for such re-grading as well as

monitoring its quality. (Estimated Cost $3.8m)

Component Three: Oversight and Monitoring of the Public Administration Program ($3.3

million).

This component was supposed to support the IARCSC in carrying out its stewardship role under

the Civil Service Law to “lead, regulate, formulate and implement structure policies of the public

administration system” (Article 5). As a result of support provided under the project, the

government through the IARCSC was expected to develop a fully funded, regularly monitored

and well coordinated and communicated civil service reform program.

Assistance under this rubric was divided into sub-components: (i) Program Coordination and

Management: Assistance under this sub-component was designed to enable the Program

Coordination Department (PCD) of the IARCSC to take charge of coordinating donor

investments in the area of public administration reform. PCD was expected to develop the

capacity to ensure coordination across technical assistance providers as well as adherence to grant

agreements, identify bottlenecks in implementation and suggest solutions. (Estimated Cost

$1.6m). (ii) Monitoring and Evaluation, and Communication: This sub-component aimed to

strengthen capacity to monitor the outcomes of civil service reform effort as well as improve

reporting. Assistance was to be provided to the Administrative Reform Secretariat (ARS) of the

IARCSC to periodically monitor and evaluate progress on civil service reforms, draw out lessons,

and identify areas for change. The project sought to support ARS in guiding line ministries in

establishing clear monitoring indicators. Assistance was also intended to focus developing a clear

communication strategy and outreach program to policy-makers and other stakeholders in the

area of civil service reform. (Estimated Cost $1.7m)

1.8 Revised Components

Component One: Strengthening Human Resource Management Capacity in Core Ministries

($8.73 million)

Initially, this component focused on efforts to substantially restructure selected ministries through

the creation of Reform Implementation Management Units (RIMUs) within those ministries

supported by the project. After restructuring, this component was limited to supporting human

resource management (HRM) functions in five line ministries. In addition, this component sought

to intensify training to help internalize basic foundation concepts and practices of human

resources management needed to build new human resources management units.

6

Component Two: Implementation of Merit-Based Human Resource Management Reforms in

Government ($9.54 million)

The original activities planned for this component remained viable, although some modification

was needed to accommodate actual progress being made in the development of the HRM units in

line ministries. In addition, this component now sought to focus more on developing personnel

registries and human resource information systems with the aim of better monitoring

employment, strengthening internal and external controls on payroll systems and mitigating risks

of employment-related fraud, including ghost workers and absenteeism.

Component Three: Project Management and Support Services ($2.13 million)

This component was reengineered to strengthen IARCSC governance, coordination and

management of the project, rather than supporting the communication, coordination, and

monitoring efforts for the government‟s wider PAR agenda, as envisaged originally.

2. Key Factors Affecting Implementation and Outcomes

2.1 Project Preparation, Design and Quality at Entry

The project suffered from flaws at entry. A perusal of the Project Appraisal Document (PAD)

reveals a conspicuous lack of analysis of the political economy issues that might have been

expected to influence project implementation. The restructured project also displays a lack of

attention to the political, social, and economic dynamics that could affect project performance. A

separate review of the project by the Quality Assurance Group (QAG) of the World Bank in

2010 (the Second Quality Assessment of the Lending Portfolio (QALP -2) makes the same point.

In fact, project documents reveal a highly technocratic perspective poorly adjusted to the Afghan

context. In addition, while work was done separately to cost the impact of the new pay and

grading program on wages and pensions, these find little mention in the PAD or other documents.

Nor was any assessment carried out of the capacity of the Independent Administrative Reform

and Civil Service Commission (IARCSC) to oversee the project competently. Broader analytical

work on public administration reform challenges in Afghanistan was undertaken, including a

large report, but this analysis was only weakly linked to the design of the project, as reflected in

the PAD and the restructuring documents. A deeper understanding of the political economy

dynamics affecting the project‟s environment – and capacity constraints -- might have translated

into a more sober set of initial project development objectives.

The design of the project was problematic. Key counterparts claimed that the IARCSC was not

properly consulted in the initial design of the project. As a result, the project lacked ownership

within the IARCSC at the outset. On the other hand, Bank team leaders stated that they had

consulted adequately with the IARCSC, suggesting a difference of perception on the

effectiveness of consultation, such as it was. The project‟s objectives were too ambitious and

broad to be effectively implemented (or monitored) by the IARCSC. Its three major components,

and seven sub-components, were confusing in nature and overlapping in content. The original

design of the project envisaged that each component would be implemented by a different unit of

the IARCSC (i.e., the Public Administration Reform Department took charge of the pay and

grading exercise, the Human Resource Policy Department was placed in charge of framing HR

regulations, the Administrative Reform Secretariat was tasked with oversight, monitoring, and

communication). As a result, implementation of the project was splintered across these various

IARCSC units. The Project Management Unit (PMU) was vested with little real authority;

coordination responsibility was vested instead in the Program Coordination Department (PCD) of

7

the IARCSC, which had little capacity at the time. A high-level project steering committee was

supposed to exercise general oversight, but this committee quickly became moribund.

The PAD refers to key documents including the Interim-Afghanistan National Development

Strategy (I-ANDS) and the Afghanistan Compact that emphasize the importance of the civil

service reform agenda for development in the country. These documents do suggest at least some

level of political ownership for the broader goals being pursued by the project. On the other hand,

the lack of proper consultation with the IARCSC during project preparation may have

undermined ownership by the project‟s implementing agency.

The analysis of risk was superficial. The ability of the IARCSC to implement the project

satisfactorily was overestimated. The risk that policy-makers could be compelled to shift their

focus away from civil service reform to larger issues relating to the country‟s security and

economic environment was not properly understood at the time of project formulation. The

project‟s mitigation strategy for identified risks betrays some naiveté: Rules-based procedures are

seen as an antidote to weak political commitment, which in turn limits the possibility that such

rules-based procedures would succeed in the first instance.

The considerable speed with which the project was prepared given the demands of the

government and the desire of Bank management to support this area may have contributed to the

flaws in project preparation and design. A Quality Enhancement Review (QER) prior to

appraisal was held but, as the QAG report states, “its impact on important issues such institutional

capacity and project scope was minimal since none of its recommendations was taken into

consideration.”

A better project design at entry might have consisted of the following elements: a more realistic

and scaled down PDO; fewer components and sub-components; a clear point of control and

coordination in the form of an empowered PMU or other mechanism; fewer, but more salient,

monitoring indicators; and provision for intensive implementation support.

Quality of Project Design at Entry Rating by QAG: Moderately Unsatisfactory

2.2 Implementation

The project quickly became a victim of bureaucratic operational bottlenecks within the IARCSC,

which might have been avoided had the project had a single locus of control. In order to

coordinate the program across the three components, a project steering committee was created

consisting of the major players in the IARCSC. Initially the steering committee met on a

quarterly basis to resolve problems raised by consultants and gave the project a strategic thrust;

later the committee became inactive and implementation of the project became balkanized across

different units of the IARCSC, particularly those of the Civil Services Management Department

(CSMD). Communication among these units was poor, resulting in a lack of coordination, weak

monitoring, and missed opportunities for learning across components.

Meanwhile, the PMU was powerless: the processing of consultant contracts and payment

authorizations was done by the Administration and Finance Department of the IARCSC, which

was responsible for performing this function for several projects, not just the CSRP, and lacked

sufficient staff to do so efficiently. This, in turn, resulted in long delays in project

implementation. To make matters worse, the PMU was without a project manager for several

months and operated with a skeleton staff, functioning more as a post office among the units of

the IARCSC and the Finance and Administration Department.

8

This situation in turn contributed to weak contract management. The team leaders of the

consultant firms hired under the project complained that they lacked access to their counterparts

in the IARCSC, resulting in inadequate communication, feedback, and monitoring. One

consultant stated that he was left mostly unsupervised by IARCSC staff. The problem of contract

management was compounded by the fact that attracting qualified consultants to Afghanistan was

not an easy task. Several commission officials lamented the poor quality of some international

consultants and the difficulty of retaining those who were more effective for any length of time.

This rapid turnover of international consultants was particularly apparent in the Reform

Management Implementation Units (RIMUS) initially created to drive the reform process in line

ministries. Difficulties in recruiting a qualified consulting firm led to the cancelation of one

component of the original project relating to the oversight and monitoring of the government‟s

public administration reform effort. Another consulting firm, working on the development of HR

procedures and policies, was terminated during the course of the project. The hiring of consulting

firms took inordinately long time. Indeed none of the three consulting firms chosen to execute the

project were in place until a year after the project became effective on July 11, 2007.

Consequently, agreed results for the first year of the project were entirely missed and only 14.5%

of the total grant amount of $20.4 million had been disbursed at mid-term (about $2.95 million).

Disbursement did improve significantly later but the project still closed with some six million

dollars unutilized, raising serious questions about whether the absorptive capacity of the IARCSC

was properly assessed at the outset.

As the security environment in Afghanistan deteriorated, civil service reform as an issue was

displaced by larger concerns. The IARCSC thus may have felt that it lacked the political

influence to push reform across line ministries. The result was that line ministries tended to

collaborate with the reform program in areas that suited them, such as pay and grading, which

involved a significant pay hike for all civil servants, rather than organizational restructuring,

which could alienate vested interests or involve some measure of pain. Not surprisingly, the

project as a whole fared poorly with respect to serious functional re-organization, while the pay

and grading exercise encountered much less resistance from line ministries. It is not clear how

well the IARCSC was able to articulate and communicate its key objectives to line ministries.

The Bank contributed to some of these implementation difficulties: The project had no less than

four task managers in the four years of its existence, contributing to the sense of confusion,

disruption of continuity, weak accountability, and poor management that affected the project in

general. These issues will be discussed in the section on Bank performance.

The project sought to address some of these problems at the time of restructuring. The project

steering committee was reactivated; a new project manager appointed to lead a PMU with more

staff and resources at his command; and full control over the project given the Director-General

of the Civil Services Management Department to address the problem of poor coordination and

lack of accountability that had characterized project governance in the first two years of its

existence. The positive effects of these changes, however, were limited by the fact that

restructuring came too late in November 2009.

QAG Ratings: Implementation Progress (Unsatisfactory), Supervision (Moderately Satisfactory)

The QAG review noted that the even after restructuring, the project was unlikely to achieve its

scaled-down objectives given the lack of champions for civil service reform and low government

interest, as well as the operational difficulties experienced by the project. With respect to

supervision, the QAG review questioned the appropriateness of restructuring given the

9

unlikelihood that this would help realize the project‟s new development objective. It noted that

the Bank had identified problems in a timely fashion, but expressed concerns about sustainability

over the medium term.

2.3 Monitoring and Evaluation (M&E) Design, Implementation and Utilization

The monitoring and evaluation framework for the project was weak. The initial results

framework prior to restructuring had too many result indicators to be tracked effectively. Both

the initial and the revised result indicators focused entirely on quantitative measures, rather than

indicators to measure the actual quality of the initiatives implemented by the project. While a

large number of posts were re-graded and mapped onto the new eight point pay scale, there is

little evidence to actually judge the quality of the process of crafting job descriptions, evaluating

posts, and creating consistent patterns for pay and grading across ministries. This is not to say

that the quality was poor, only that we do not have any sound basis for arriving at a conclusion

about this based on the quantitative data gathered by the project.

With regard to civil service appointments, the revised results framework simply states that

“100% of civil service appointments will be made on a merit basis following the Civil Servants

Law and related regulations.” The emphasis on compliance with procedure as the criterion for

assessing whether a merit-based appointment was made can be misleading: It is possible to hew

to procedure and yet subvert the goal of making merit-based appointments. Compliance with

procedure is hard to show especially at the lower levels of the civil service (grades 3-8) for which

very little data is forthcoming. It would have been better to have a third party audit appointments

on a sample basis and use this as the key monitoring indicator for merit-based appointments.

The third key indicator relates to the adoption of regulations and procedures for key human

resource actions, particularly recruitment, promotion, disciplinary actions, retrenchment and

severance, as well as the framing of a code of conduct for civil servants. Again, it is relatively

easy to see if these were adopted or not. It is much harder to assess their quality, relevance, and

depth or the degree to which the new regulations have been internalized by civil servants in key

ministries.

The monitoring and evaluation framework for the project thus suffered from three major

limitations: (a) too many indicators hastily put together by a task team that clearly had no idea

how such data would eventually be collected, (b) a neglect of quality as a dimension that needed

to be monitored over time, and (c) a failure to create an independent mechanism for monitoring

that would have given the project a more reliable basis for tracking progress on the project‟s key

qualitative dimensions.

2.4 Safeguard and Fiduciary Compliance

Regular supervision by the Bank team reduced the risk of corruption in the project, a fact noted

by the QAG review. Operational controls were further tightened in the wake of the restructuring

of the project. The mid-term review (MTR) held in September/October, 2010 noted several

procurement-related issues, including frequent revisions in the procurement plan, delay in issuing

no-objection letters by the Bank for hiring consultants under the project, and slow contract

modification procedures. In line with the QAG review, this ICR flags the fact that even after

restructuring, it took some time to modify the contracts of the participating consulting firms

according to the revised objectives of the project, thus possibly blunting the intended impact of

the restructuring exercise.

10

The MTR noted weaknesses in the strength of the internal audit function of the project, a fact that

is not surprising given the relatively low level of capacity in the IARCSC, along with a few other

problems relating to the timely maintenance of the fixed asset register, and delayed reporting.

Overall the project Implementation Status and Results (ISR) report rates the financial

management of the project as „moderately satisfactory‟ (with an „unsatisfactory‟ for internal

audit). This suggests that the IARCSC failed to respond adequately to the concerns raised by the

Bank team regarding internal audit issues.

Procurement also does not appear to have improved much since the MTR: The final ISR rates

procurement for the project as „moderately unsatisfactory‟, citing a host of problems, such as

incomplete and deficient documentation, lack of a proper filing system, poor planning resulting in

delays in hiring key staff, inadequate contract management, and lack of updated information

regarding the status of contracts and the procurement plan in general.

The lack of disbursement was a major problem throughout the project with very little being spent

in the first year and the project closing with a large chunk of its allocation unspent.

2.5 Post-completion Operation/Next Phase

The project has set the right direction for civil service reform in Afghanistan, including the

eventual achievement of a transparent pay and grading system; a more professionally-oriented

civil service recruited on the basis of merit and operating within a framework of clear laws, rules,

and regulations; and a new emphasis on building the capacity of selected line ministries

particularly in the area of human resource management. Yet, the project itself was too small to

make a real dent on the challenges of civil service reform in the country and faced numerous

challenges, particularly a lack of political support, weak capacity in the IARCSC, a mixed

reception by line ministries, inadequate monitoring, and serious implementation problems. It is

therefore too early to say how the new practices sought to be put in place by the project will

evolve over the longer-term unless these obstacles are properly addressed.

The World Bank has approved a much larger, follow on project to improve capacity in the civil

services in Afghanistan. The new project provides some $240 million for efforts designed to

provide salary support for the hiring of senior management group positions in selected ministries

to reinforce common functions, such as human resource management, financial management, and

procurement as well as provide some salary support for technical and professional positions in the

civil service. Ministries selected for such support under the Capacity Building for Results

Facility (CBRF) will have to demonstrate progress on pay and grading, as well as functional

reorganization, among other things. The project seeks to minimize the risk of favoritism by

assigning the selection of staff hired under CBRF to an independent recruiting firm. It also

requires that proposals from ministries be independently evaluated before being presented to the

project steering committee. The project is located in the Ministry of Finance (with IARCSC as a

partner), thereby taking advantage of the power of the purse to push reform forward in line

ministries. An annual independent performance review will take place to provide an objective

assessment of progress, while performance indicators have been better chosen to focus on service

delivery outcomes in departments. The life of the project has been put at five years, instead of the

customary three, providing more time to achieve results in participating ministries. This new

project has the potential to contribute to the process of institution-building in Afghanistan,

assuming a positive enabling environment including political commitment, reasonable security,

greater ownership by line ministries, a cooperative relationship between MoF and IARCSC, and a

willingness to address implementation issues as they arise in a timely fashion.

11

It has been suggested that extending the project, rather than folding its objectives into the CBRF,

might have led to a better outcome. In this view, the restructuring simply did not have the time

given to it to show results. It is difficult to know whether this would have been the case;

therefore this ICR flags the question but does not take a position on it.

3. Assessment of Outcomes

3.1 Relevance of Objectives, Design and Implementation

The objectives of the project – focusing on the strengthening of the civil service in Afghanistan

through organizational restructuring, pay and grading reforms, merit-based appointments and

neutral procedures, and better human resource management – remain strategically relevant at the

time of writing this ICR. The challenge of state-building, with a professionally managed and

motivated civil service at its core, continues to be a pressing one, although it is not clear whether

this goal can accomplished in the context of the country‟s deteriorating security situation, and the

possibility of a draw-down of donor support over time. It is evident that decision-makers have

been compelled to divert much of their attention to addressing security concerns rather than

longer term issues, such as reforming the civil service. With regard to design, it is not apparent

that the goals of this project could have been successfully accomplished through the IARCSC

given its complex internal structure and capacity weaknesses. With regard to implementation, the

project‟s over-reliance on international technical assistants (ITAs) may have undermined the

broader objective of promoting the capacity of key line ministries since ITAs often felt compelled

to take over functions that should have been carried by ministries themselves in an attempt to

deliver results faster. A larger issue is whether one can successfully deliver a project, such as this

one, in a conflict-ridden, low capacity environment, like Afghanistan, as if it were a normal

project subject to the full complement of Bank processes and procedures. A more flexible

approach to project design and implementation, allowing for quick restructuring and calibration

of the results framework in response to shifts in the project‟s operating environment, might have

suited the context in Afghanistan better. The project thus raises questions about how the Bank

should treat projects in trying conditions, such as those prevailing in Afghanistan.

3.2 Achievement of Project Development Objectives

The initial project development objective promised that “across the time frame of the project, (by

2011), a significant proportion of service delivery ministries will be performing their functions to

an acceptable level and can be held accountable for the use of public resources. This will have

resulted from core ministries having been reorganized according to functions and civil servants

being managed according to clear rules and procedures.” This objective was too broad and

overarching to have been achieved by the project, especially given the small resource envelope

promised. In any event, none of the consulting firms that were to execute the project were on

board until almost a year after it became effective, a major delay by any standard of reckoning.

By the project‟s mid-term, only 14.5% of project funds had been disbursed: progress was

particularly weak in the area of organizational restructuring with line ministries showing little

interest, as well as in the area of oversight, monitoring, and communication of the government‟s

PAR program with the Project Coordination Department (PCD) bereft of capacity at the time and

negotiations with consulting firms to execute this component proving unsuccessful. A lack of

clear delineation of roles among different units of the IARCSCalso affected project

implementation.

As a result of this unsatisfactory progress, the project was restructured in November, 2009 with a

more limited project development objective stating the following: across the timeframe of the

12

project (by July 2011) more accountable and transparent practices in the management of the civil

service will be introduced in selected ministries. The remainder of the project post-restructuring

focused primarily on strengthening merit-based human resource practices in government, mainly

pay and grading reforms and merit-based appointments, as well as bolstering human resource

directorates in five line ministries. The third restructured component seeking to direct monitoring

and coordination efforts towards the project itself, rather than the government‟s overall PAR

program never moved forward.

(i) Pay and Grading Reforms

There is no doubt that the government needed to reform its pay and grading structures in order to

introduce a measure of transparency in the management of the civil service, attract more qualified

people into its ranks, and move away from a career civil service with promotions being based on

the principle of seniority towards a position-based system more able to reward performance.

While the project closed with some 325,000 posts having been re-graded, the exercise was flawed

in several key respects. First, the pay and re-grading exercise started late: Initially slated to begin

at the start of the project, pay and re-grading was delayed by a year as it awaited the passage of a

Civil Servants Law to furnish the legal basis for such an initiative. It thus appears that the project

was not ready when it became effective in July, 2007. Second, while ministries were willing to

adopt the new pay and grading scales because this meant a hefty pay hike for civil servants, they

were much less eager to endure the pain of organizational restructuring. As a result, staffing

reviews took place without a transformation of ministry functions and internal organization. This

meant that pay and re-grading was a skin-deep exercise that left ministry structures mostly intact.

Ideally, organizational restructuring should have led to a revised staffing plan followed by pay

and grading; in reality, pay and re-grading was implemented in the absence of organizational

change of any significance. Third, it is almost impossible to judge the quality of job descriptions

and evaluations conducted under the project or their consistency across ministries; the result

indicator for the pay and re-grading exercise is entirely quantitative in nature and there is no data

on its quality.

(ii) Introducing Merit-Based Practices in Government

The project sought to facilitate the development of a uniform set of rules and guidelines affecting

the civil service relating to recruitment, performance appraisal, severance, disciplinary matters

and other issues. Not all of these were adopted directly as a result of the project. The Civil

Servants Law, which became law in June, 2008, was an initiative that fell outside the scope of the

project. It contained many of the legal foundations for HR practices, including pay and re-

grading, appointments to the civil service, performance appraisal, promotions, appeals,

retirements, and disciplinary processes. The final implementation support mission held in July,

2011 noted that recruitment, appraisal, and appeals systems had been established through CSRP

but with only “limited effectiveness” because of a check-list mentality rather than a focus on the

quality of recruitment, providing feedback on appraisals, and taken action on poor performance

reports. One commission official noted that there was a tendency for supervisors to inflate the

performance ratings of their subordinates, undermining the purpose of the exercise.

The Independent Appointments Board and the Appeals Board appear to have made progress in

streamlining their procedures. It is not clear whether this was the result of any direct support

from the CSRP project. The final implementation support mission noted that the consulting firm

hired to work with the two boards provided only “generic” support rather than “specific guidance.”

The contract of the consulting group working with the two Boards, as well as the Human

Resource Policy and Legislation Department, was in fact cancelled because of “highly

unsatisfactory” performance (this according to the final implementation support mission),

suggesting that its contribution was marginal.

13

The Independent Appointments Board (IAB) has introduced some useful reforms including

allowing third parties drawn from civil society and universities to observe selection procedures;

separating short-listing and appointing committees; recording interviews to prevent manipulation;

declaring the successful candidate on the same day as the interview; and establishing a question

bank for written examinations and interviews that is revealed to the panel just before

commencement of the process, as is the position for which the interview is being conducted.

Third party monitoring was a reform supported by the ARTF Incentive program, but not the

project. Some 120,769 civil servants have been appointed as a result of the new pay and re-

grading exercise by July, 2011. Approximately some 12,800 senior civil servants (grades one and

two) have been appointed by the IAB.

While procedures have improved in the Appointments Board, it is difficult to evaluate the extent

to which the problems of patronage, corruption, and nepotism have been tackled. First, we have

no reliable data on the question. Second, all senior appointments have to be routed through the

Council of Ministers before being passed on to the Office of the President for final approval. The

Council of Ministers can delay an appointment for long periods, resulting in frustration for the

candidate, abandonment of the application, re-advertisement, or appeal. Third, the Appointments

Board relies heavily on the criteria laid out in the job descriptions prepared by the ministries; if

these criteria are inadequate or written to favour particular types of candidates (candidates

seeking reappointment through the P&G process would benefit more from a selection criteria

emphasizing prior experience in government than a new applicant from the private sector), there

is little the Board can do about it. Fourth, most appointments are made at lower grades (3-8) by

ministries, provincial governors, and district governors under nominal oversight by the Board.

The project did not monitor whether appointment procedures were being properly followed in

these grades or the extent of political influence or family pressures exerted in the appointments

process by ministers, legislators, and local notables. In any event, the more stringent procedures

applied only to senior appointments made by the IAB. Given the large number of graduates in

Afghanistan produced every year and the lack of private sector opportunities, it is likely that

social pressures to circumvent merit-based employment procedures will remain strong in the

foreseeable future.

The Appeals Board hears complaints from civil servants; approximately seventy percent of these

complaints constitute appeals against decisions by the IAB. Data on appeals is fragmentary, but

the majority of appeals seem to come from ministries based in Kabul. Awareness of the

procedure to file an appeal remains unclear to many civil servants. Fewer reforms appear to have

taken place in the Appeals Board than the IAB and none that can clearly be said to have emerged

from the project.

(iii) Strengthening Human Resource Management in Line Ministries

Initially, the project focused on establishing Reform Implementation Support Units in five

ministries to drive the reform process, including organizational restructuring, preparation of

strategic plans, implementing pay and grading reforms, and bolstering the capacity of human

resource management directorates (HRMDs). RIMUs were overseen by a coordinator (usually an

international consultant) and supported by two or more national consultants. Initially RIMU staff

reported directly to the Deputy Minister of Administration and Finance in the line ministry; later

this was changed to include both the Deputy Minister and HRM Directors in order to make them

more responsive to the ministry HR unit. The argument in favour of using RIMUs to drive

ministry reforms stemmed from the problem of weak capacity. On the other hand, several

ministry staff and commission officials complained that the project had supported the creation of

a parallel structure in ministries that was doing little to build internal capacity and undermining it

14

by taking over core ministry functions. After restructuring, the role of RIMUs was trimmed with

the focus of the project shifting toward building the capacity of HRMDs, particularly with respect

to implementing pay and grading reforms and overseeing critical HR functions, such as

recruitment and performance appraisal. Pay and grading teams chosen by the IARCSC‟s PAR

Department worked closely with HR units in ministries to implement pay and grading reforms;

HR staff received training in a variety of HR functions; and HR units were, in turn, expected to

reach out to ministry staff to explain how the new civil service laws, rules, and guidelines would

work in practice. A decision to appoint HR Directors through the Management Capacity Program

(MCP) on a higher pay scale helped attract more talented people to lead HRMDs.

The project focused on five ministries, including MoF, the Ministry of Transport and Civil

Aviation (MTCA), the Ministry of Agriculture, Irrigation, and Livestock (MAIL), the Ministry of

Rural Rehabilitation and Development (MRRD), and the Ministry of Public Works (MPW). Of

these five, the MoF appeared to have made the most progress in building up its HR capacity: the

HR unit in MoF had an excellent relationship with its RIMU. With RIMU support, the HR unit

in MoF developed some 10 human resource policies for the ministry, put in place an induction

manual for new staff, and completed pay and re-grading for 90% of its positions.

The attempt to strengthen human resource management was marked by certain weaknesses.

RIMUs, for example, were not adequately staffed in terms of numbers and quality, thus

hampering the reform effort. Even when adequately staffed, turnover was high and the continuity

necessary to drive reform was compromised. Capacity within HR directorates was low and staff

constraints significant. The consultants working with RIMUs and HR Directorates more often

than not viewed their support as a one-off exercise, rather than as part of a program of capacity-

building over time. The objectives of the reform process were not clearly communicated to HR

units and ministry staff, resulting in weak ownership and confusion. Because of low capacity in

HRMDs (and a lack of counterparts because of staffing shortages), RIMU consultants were not

able to transfer capacity effectively. Monitoring was also a problem: the project provided little

data on whether HRMDs (and ministries) were complying with new civil service guidelines in

key areas. One consulting group sought to use what it called a „staged capacity building model‟

to evaluate the ability of HRMDs to produce key outputs on their own, but the standards of

quality expected from such outputs were only weakly specified, rendering the exercise much less

meaningful.

3.3 Efficiency

Not applicable – Net Present Value/Economic Rate of Return for the project was not calculated at

the time of appraisal

3.4 Justification of Overall Outcome Rating

While the project‟s objectives were strategically relevant, it is not clear that senior Afghan

officials accorded much priority to civil service reform issues; rather they were preoccupied with

addressing security and economic considerations. The project relied too much on the IARCSC, a

fragmented body with limited capacity, to achieve its objectives. International technical

assistants tended to supplant the core functions of ministries, rather than improving their capacity.

The project lost a year before consulting contracts were put in place, while the rate of

disbursement was very slow right up to project restructuring. As result, the project failed to

achieve its initial project development objective. The initial PDO was so ambitious that even had

the project experienced a faster rate of disbursement, it is unlikely that the PDO could ever have

been achieved in the time frame and limited funds made available under the project. There was a

15

tension between the government‟s desire to achieve system-wide reforms relating to pay and

grading, for example, and the capacity of the IARCSC to implement such changes across

government as well as fiscal constraints.

The revised PDO scaled down what was to be achieved by the project; even so, what was

achieved after restructuring still left much to be desired. One missing dimension was the quality

of the initiatives undertaken by the project. We have little data on quality of the pay and re-

grading exercise, particularly that of job descriptions and evaluations and their consistency across

ministries. The project makes the highly disputable assumption that mere procedural compliance

would be sufficient to translate into a merit-based system of appointment; no serious quality audit

of appointments was carried out and the data on the matter of only procedural compliance was

scanty. The IAB did introduce some welcome reforms in the appointments process for senior

officials but this does not appear to have happened directly as a result of the project. Indeed, one

supervision mission complained about the “highly unsatisfactory” performance of the consulting

firm chosen to work with the IAB, the Appeals Board, and the Human Policy and Legislation

Department, and later cancelled the firm‟s contract. The attempt to restructure human resource

management in five ministries was also beset with problems including overlap between RIMUs

and HR Directorates, weak capacity transfer and staffing gaps, poor communication of reform

objectives by the IARCSC to HR units and within ministries, and hardly any monitoring of how

well HR units and ministries were complying with civil service regulations and guidelines.

Finally, the pay and re-grading exercise occurred without a major overhaul of ministry functions

and structures; this in turn reduced the value of pay and re-grading as a tool for administrative

reforms with new pay-scales and grades being grafted onto existing structures. Even after

restructuring, the project was never able to correct for this basic flaw in the pay and re-grading

exercise and the project closed without any major organizational changes having taken place in

ministries. Donor top-offs undermined the effectiveness of the new pay and grading scales and

contributed to high turn-over rates in RIMUS.

Overall Outcome Rating before Restructuring: Unsatisfactory

Overall Outcome Rating after Restructuring: Moderately Unsatisfactory

Weighted Overall Outcome Rating: Moderately Unsatisfactory

The rating of „moderately unsatisfactory‟ (MU) for the project‟s outcomes is consistent with the

final rating of MU with respect to progress towards achievement of the PDO provided in the last

Implementation Status and Results (ISR) review. It is also a notch better than the rating of

„unsatisfactory‟ with respect to the likelihood of achieving the project‟s overall development

objectives rated by the Quality Assurance Group (QAG).

4. Assessment of Risk to Development Outcome

The development of a professionally managed, merit-based civil service capable of performing

key functions depends on factors that are not easy to predict. Clearly, political ownership will be

needed if this goal is to be realized over time; the Chairman of the IARCSC does not possess

ministerial rank and lacks sustained access to top Afghan leaders. The government has recently

agreed to allow the Chairman to attend Cabinet meetings on a quarterly basis to review the

progress of the civil service agenda in line ministries in the presence of the President. Given the

deteriorating security situation in Afghanistan, however, it is unlikely that the leadership will be

able to focus effectively on the longer term agenda of institution-building in the country,

including the development of the civil service. In the absence of a push to continue reforming the

civil service from the Afghan leadership, line ministries may feel less pressure to press on with

the task of rationalizing their structures and processes. The capacity of the IARCSC (and line

16

ministries) to implement reform remains a problem, despite improvements. Corruption poses a

serious risk to the development of a merit-based civil service especially in light of the burgeoning

opium economy as well as the enormous social pressures on government as the employer of first

resort in a country where alternative private sector sources of employment are scarce. All of

these problems are magnified in provinces where the writ of the central government does not run

and the administrative apparatus, such as it exists, is weak and demoralized. Finally, as the West

whittles down its presence in Afghanistan, donors may lose interest in pumping money into the

country; this, in turn, may translate into a scarcity of resources to pursue public administration

reforms, especially given the country‟s heavy reliance on external sources of support and weak

revenue base.

Risk to Development Outcomes; High

5. Assessment of Bank and Borrower Performance

5.1 Bank Performance

(a) Bank Performance in Ensuring Quality at Entry

Rating: Moderately Unsatisfactory

(b) Quality of Supervision

Rating: Moderately Unsatisfactory

(c) Overall Bank Performance Rating: Moderately Unsatisfactory

Quality at Entry

As noted in Section II, the project had serious weaknesses at entry. The preparation for the

project was inadequate in two respects. There was little attempt to bring political economy

insights to bear on the design of the project. It is also puzzling why the team task did not conduct

a detailed analysis of the capacity of the IARCSC to implement the project effectively beforehand.

A more serious attempt to grapple with the political economy factors affecting the project – and a

more explicit treatment of the capacity issues of the IARCSC – might have resulted in a more

realistic and achievable project development objective. Project documents suffered from a highly

technocratic perspective with inadequate attention paid to the particular context in Afghanistan.

The perception of having been consulted inadequately on the part of the IARCSC was another

problem, which undermined ownership. The project‟s initial objectives were too ambitious to be

implemented or monitored in a low capacity environment, such as the one in Afghanistan. The

structure of the project was such that it became balkanized among the IARCSC different units,

leading to a loss of coherence across the project‟s many components and sub-components. The

failure to create a strong Project Monitoring Unit (PMU) with real authority to steer the project,

along with a confusing multiplicity of result indicators and no mechanism to track them, hobbled

the project from its inception. It should be noted that the PMU was deliberately kept weak to

give the IARCSC‟s units a greater role in project implementation; however, this approach was

unlikely to succeed because of the IARCSC‟s capacity limitations. The project‟s risk framework

and mitigation measures were weak, revealing an over-confidence that was not appropriate. As

the QAG review points out, there seems to have been little attempt to follow up on the

17

recommendations of the QER “to scale down ambitious project scope and guard against the

consequences of the weak implementation capacity of IARCSC.”

On the other hand, the project was prepared in a difficult environment under pressure from both

the government and Bank management.

Quality of Supervision

The Bank team was candid in identifying problems and proactively raising them with the client.

Three key issues that may have affected the quality of supervision bear noting. First, the Bank

team had four task team leaders during the course of the project (on average one per year over the

life of the project) which disrupted the continuity necessary for effective supervision. Second,

while Bank teams were aware of the problems affecting the project as it unfolded and discussed

these with the IARCSC, the project was restructured only in November, 2009, more than two

years after it became effective. The reasons for this delay are unclear give that it would have

become apparent long before then that the project could not meet its development objective.

Indeed, the aide memoire of the supervision mission held in November, 2008 noted serious

problems with project implementation, which it attributed to a combination of a “deteriorating

security environment”, “uncertainties with regard to the authorizing environment of the IARCSC”,

and a decline in “ministry attention on real restructuring” – all of which might have been

expected to compromise timely achievement of the PDO. The Bank team was in fact considering

whether to close the project or proceed towards restructuring; in the end, the latter course was

chosen. The delay in restructuring, however, meant that the project, even in its new scaled-down

form, would have less time to show results. Third, the Bank team was slow in providing critical

no objection letters to the IARCSC to hire consultants under the project and approving contract

amendments (including changes in the terms of reference) with firm consultants pursuant to

restructuring. This meant that legally firm consultants were not obliged to follow the new terms

of reference until formally approved. IARCSC officials stated that they would have benefited

from more frequent supervision missions; the Bank practice of holding supervision missions

every six months was viewed as too infrequent given the difficulties of executing projects in

Afghanistan. They also stated that they would have preferred if supervision missions had relied

more on hard data on project performance obtained through independent monitoring as the basis

for discussion. Finally, it is worth noting that that the quality of consultation with the IARCSC

improved during the restructuring process.

5.2 Borrower Performance

(a) Government Performance Rating: Moderately Unsatisfactory

(b) Implementing Agency or Agencies Performance Rating: Moderately Unsatisfactory

(c) Overall Borrower Performance Rating: Moderately Unsatisfactory

Government Performance

18

The government did signal its ownership of the agenda of civil service reform at first. Both the

Interim Afghanistan National Development Strategy (I-ANDS) and the Afghanistan Compact

emphasized the importance of public administration reform in the creation of viable state. It

launched a Priority Reform and Restructuring (PRR) initiative under which certain departments

were given higher salary packages in exchange for restructuring. Several projects were

commissioned to improve the capacity of the civil service, such as the Management Capacity

Program (MCP). The government passed both a civil service and a civil servants law to create an

overarching legal framework to govern the working of the civil service. On the other hand, the

disbanding of the Ministerial Advisory Committee (MAC) on public administration reform led to

less high-level oversight of the process. The deteriorating security environment, however,

compelled political decision-makers to shift their attention away from the longer-term issues

involved in building an effective civil service to addressing the more immediate threats to the

basis of the nascent state itself. Finally, the government pursued contradictory policies:

permitting a variety of donor-funded salary top offs to officials, while, at the same time, trying to

put in place a relatively uniform pay and grading system across government.

It is hard to assess the degree to which line ministries owned the reforms promoted by the project.

As noted earlier, they embraced the pay and grading reforms, which involved a large pay increase

for civil servants, more easily than the harder organizational reforms sought to be implanted by

the project. As political attention on public administration reform issues waned, line ministries

felt less pressure to move forward on those parts of the agenda that they regarded as difficult.

The capacity of line ministries to implement the reforms supported by the project also varied,

with MoF doing better than some others.

Implementing Agency Performance

The IARCSC lacked the capacity to provide strategic direction to the project; nor was it able to

effectively coordinate and monitor the different initiatives supported by it. The project steering

committee intended to provide high-level oversight and monitoring quickly became inactive.

Responsibility for implementing the project‟s components was scattered among several different

units of the IARCSC, leading to loss of coherence and overall coordination. The Administrative

Reform Secretariat (ARS) was unable to fulfill its responsibility to monitor the project effectively,

making it harder to hold line ministries to account for their performance. The Administration and

Finance Department of the IARCSC also found it difficult to process staffing and payment

decisions in a timely fashion, functions that should normally been performed by the PMU.

Tensions within the Commission over where the locus of control over the project would lie made

it more difficult to implement its objectives successfully.

The IARCSC failed to manage its consultants well. Indeed, the mid-term review (MTR) mission

held in late 2010 noted that “too many IARCSC managers are directing the work program with

the net effect that consultants are not clear whose instructions they should follow.” Consultants

noted that they lacked sustained access to senior counterparts in the IARCSC. They added that

they would have benefited from more intensive supervision and feedback from the IARCSC,

especially senior officials.

One rationale for restructuring was to address these institutional problems. The project steering

committee was reactivated; a new project manager appointed to lead a PMU with more staff and

resources at his command; and full control given the Director-General of the Civil Services

Management Department, thus creating a clear locus of project control and coordination. The

impact of these changes was limited by the fact that restructuring took place late in November,

19

2009, as well as the legal difficulties involved in redrafting the terms of reference of the firms

already chosen to execute the project.

In terms of building ownership, the IARCSC lacked a well designed communication strategy to

convince line ministries to implement the package of reforms supported by the project effectively.

The IARCSC was also unable to create a regular channel of access to high level decision-makers

to maintain a favourable authorizing agenda for public administration reform efforts in

Afghanistan, including the project. This remains a challenge for future operations in this area.

Despite these problems, the implementing agency was able to persevere with pay and grading

reforms (not considering qualitative dimensions) and lay some basis for better human resource

policies and practices especially through the development of HRMDs. The IARCSC‟s capacity

improved over time, particularly through the hiring of more qualified staff, but continued internal

issues and a lack of strategic leadership remained problems.

6. Lessons Learned

(i) Bring political economy analysis to bear on project design: Civil service reforms involve

complex political economy dynamics that need to be understood before initiating a project in such

an area. Key questions that such an analysis should address include the sources of support and

resistance to reform; strategies for sequencing and implementing reforms through time; the

creation of institutional mechanisms to build political ownership for change; and strategies to

galvanize potential winners from the reform process (e.g., users of government services) and

reassure those opposed to change (e.g., avoiding retrenchment). The insights gleaned from such

an analysis should be brought to bear in an explicit fashion on the design of projects through the

PAD and other similar documents.

(ii) Be upfront about the risks of low capacity: It is critical that the design of such projects be

based on a realistic assessment of the capacity of implementing agencies. In the case of the

project under review, no explicit work was done on the capacity of the IARCSC or ministries to

execute its components effectively. It was assumed that such capacity either existed in some

form or could be built up quickly without harming project implementation. Had the extent of the

capacity problem been fully understood from the outset, steps could have been taken to address

the problem by scaling down the PDO, creating an empowered PMU, trimming the components,

and engaging in more intensive implementation support.

(iii) Consult closely with the client when designing a project: There was a perception that the

Bank team did not consult widely enough in the initial design of the project. It is tempting to

design a project in fragile contexts dependent on external aid based on what the team views as

best for the client; however, in practice this can translate into a project that is poorly anchored in

the realities of a country‟s context and deprive the team of the critical local knowledge needed to

structure a successful project.

(iv) Communicate the goals of reform: The project under review lacked a coherent strategy for

communicating the goals of reform to political leaders, line ministries, and other donors. It is

easy to write this off as another example of the IARCSC‟s capacity weaknesses, but there was

nothing to prevent the project for putting in place alternative mechanisms to communicate the

goals of the reform process to build ownership, soothe anxieties among those uncomfortable with

the prospect of change, and influence public discourse about reforms.

20

(v) Be targeted about monitoring: It is important to focus on a few key indicators of progress

that can be reliably tracked over time preferably by an independent means. Such indicators

should capture not just the quantitative dimensions of reform but qualitative ones as well. The

task of monitoring should be driven by the project‟s particular requirements and the feasibility of

data collection in a given setting, rather than the temptation to present an impressive results

matrix to secure easier approval of the project.

(vi) Provide for continuity in task team leadership: The project under review had as many as

four task time leaders in the space of four years, seriously affecting the thread of continuity

needed for proper project implementation and supervision. More attention needs to be given to

the challenge of assuring the continuity of task team and task team leadership in difficult

environments. There is little to be gained by lamenting the rapid turnover of government officials

and consultants when the Bank itself cannot guarantee a modicum of continuity in its own

projects especially in challenging situations.

(vii) Engage in intensive implementation support: In high-conflict countries with rapidly

shifting challenges and capacity constraints, intensive implementation support is crucial for the

success of any project. IARCSC officials noted that they would have benefited from more support

during project implementation. Such field-based support can easily be extended when the Bank

has a functioning country office in place.

(viii) A different approach for projects in difficult contexts? A broader issue is whether it is

possible to successfully deliver a project in a conflict-ridden, low capacity environment, as if it

were a normal project subject to the full array of Bank processes and procedures. A more flexible

approach to project design and implementation that gives project teams some leeway to make

changes in project objectives, components, and result indicators to address problems as they

surface on the ground may yield better outcomes. One could still hold such projects fully

accountable to the fiduciary safeguards common to all Bank projects, but they would no longer

have to operate in a straitjacket that does little to improve project performance and may even

hinder it, particularly in very difficult environments

7. Comments on Issues Raised by Borrower/Implementing Agencies/Partners

(a) Borrower/implementing agencies

We received comments from the Independent Administrative Reforms and Civil Service

Commission (IARCSC) on this ICR. The IARCSC notes that the decision to break-up the project

into three major components was based more on procurement considerations rather than project

design. It is clear that project design should not have been driven by considerations of

simplifying the procurement process but by the larger objectives of the project. The IARCSC

points out that the capacity of the Administration and Finance Department improved over time.

The ICR does note an overall improvement in the capacity of the IARCSC over the life of this

project; however capacity issues remain a problem for the effective implementation of public

administration reforms in the country. The IARCSC points out that the implementation of merit-

based recruitment has experienced difficulties because of the continuing lack of a supportive

administrative culture. This certainly is an issue but some progress has been made in improving

the work of the Independent Appointments Board despite a tough environment. We agree with

the implementing agency that the Bank may not have handled the procurement of consultants for

the oversight and monitoring component of the project well, leading the dropping of this

particular activity. The 'moderately unsatisfactory' rating for project outcomes, as noted by the

IARCSC in its response, is based on both faulty project design at entry as well as problems of

implementation and weak outcomes. We have made some editorial changes in the ICR in

21

response to the comments received by the IARCSC. We fully agree with the IARCSC that the

political, social, and legal context should have been better addressed in the design of this project.

We also agree that the project team should have commissioned a capacity assessment before

embarking on the project.

(b) Cofinanciers N/A

(c) Other partners and stakeholders N/A

22

Annex 1. Project Costs and Financing

(a) Project Cost by Component (in USD Million equivalent)

Components Appraisal Estimate

(USD millions)

Actual/Latest

Estimate (USD

millions)

Percentage of

Appraisal

Building HR Capacity and

Organizational Restructuring in

Line Ministries

8.40 8.73 104

Human Resource Management

Policies and Implementation 8.70 9.54 110

Project management and Support

Services 3.30 2.13 65

Total Baseline Cost 20.4 20.4 100

Physical Contingencies

Price Contingencies

Total Project Costs 20.4 20.4

Front-end fee PPF

Front-end fee IBRD

Total Financing Required 20.4 20.4

(b) Financing

Source of Funds Type of

Cofinancing

Appraisal

Estimate

(USD

millions)

Actual/Late

st Estimate

(USD

millions)

Percentage

of Appraisal

Borrower

IDA Grant 20.40 20.40 100

23

Annex 2. Outputs by Component

Component 1: Strengthening Human Resource Management (HRM) Capacity in Core

Ministries

This component was designed to support strengthening of human resource management functions

in selected line ministries. It was assumed that better functioning HR directorates would facilitate

the implementation of P&G reform. In addition, this component also sought to intensify training

to help internalize basic foundation concepts of practices of human resources management which

are required to build the new and improved human resources management units.

The following table provides the ratio of tashkeel strength of HR directorates to overall tashkeel

for the five ministries which were supported through CSRP. As the table shows, the approved

tashkeel strength of HR directorates after pay and grading reforms is between 1 and 2 percent of

the total tashkeel in these line ministries. This also implies that at least in the five selected

ministries, the structure of HR directorates in line ministries is standardized.

Table 1: Ratio of HR staff relative to Tashkeel

Ministry Tashkeel of HR

Directorates

Current Staff

in HR

Directorates

Total

Tashkeel

HR Tashkeel as % of

Total Tashkeel

MoPW 35 33 3378 1.03

MoF 75 73 7180 1.04

MoTCA 29 29 2104 1.38

MAIL 79 67 9299 1.00

MRRD 26 22 2129 1.22

Specific achievements under this component are summarized below:

Organizational reform interventions completed in 4 ministries including MRRD, MAIL,

MPW and MOT.

HR departments established in 5 ministries (MRRD, MAIL, MPW, MOF, and MOT).

Strategic change management plans have been implemented in 5 ministries

Five HRMDs are established and functional

One general HR training and Coaching Plan has been completed in MAIL and 2

specialized HR Training and Coaching Plans have been completed in MPW and MOT.

Capacity for auditing appointments, appraisals and appeals in 5 line ministries has been

institutionalized within the CSMD.

Specific performance management systems have been put in place and skill transfer

research has been completed.

While these achievements are generally in line with the targets set out at the start of CSRP, it

should be recognized that the emphasis has been on setting up the procedures and processes to

manage HR reforms in line ministries. CSRP, through component 1 has not managed to set up

procedures or transfer sufficient capacity to measure and assess the qualitative depth of reforms.

In addition, evidence from the five selected ministries reveals that the practices institutionalized

24

by CSRP were not effective in maintaining fully functional HR directorates until HR directors for

these ministries were hired through another Bank project, Management Capacity Program (MCP).

Component 2: Implementation of Merit-Based Human Resource Management Reforms in

Government

This component primarily aimed at the provision of technical assistance for i) development of

civil service rules and regulations derived from new Civil Servants and Civil Service Laws; ii)

strengthen the system of merit-based appointments; and, iii) implementing GoA‟s new pay and

grading policy. Subsequent to restructuring, additional effort was made in building up a single

and manageable personnel registries and human resources information system with the aim to

create a basis for monitoring employment, strengthen internal and external controls on payroll

systems and mitigate risks of employment related fraud, including ghost workers and absenteeism.

Basic procedures for recruitment and appraisals have been established through CSRP but these

need to be updated and revised regularly. More transparency and accountability mechanisms

should be included in the recruitment and appraisal procedures. Discussions with the IARCSC

have revealed that the quality of TA provided by implementing consultants (SMEC) was generic.

For the specific context of Afghanistan, it did not provide sufficient guidance on developing a

comprehensive legal framework through which civil service reform can be implemented.

Pay and Grading roll-out consists of the five main stages: (i) Reviewing Ministry/Agency

stuctures; (ii) Evaluation and regrading posts; (iii) Appointing staff (either through transfer or

merit-based appointments); (iv) Payment of salaries; and (v) Monitoring and evaluation. The

P&G teams are able to achieve quantitative targets without external technical assistance. The

original intention was a „light-touch‟ approach to P&G, particularly after it was decided to

partially de-link restructuring from merit-based appointments in 2008. Table 2 presents the status

of P&G implementation for selected ministries/agencies till July 2011. The following measures

were put in place to ensure a reasonable standard to the implementation of P&G:

Readiness Review Manual and Job Description and Job Evaluation Manual periodically

updated based on lessons learned;

Training to P&G teams and ministry HR staff;

Packs given to Ministries/Agencies which include manuals on Civil Servants Law and

Organic Law;

Assessments by Ministries/Agencies of their satisfaction with the work conducted by P&G

teams;

Assessments by HR Unit P&G trainees on the standard of training they received;

Assessments of the knowledge/understanding of the trainees of P&G implementation issues;

Assessments of sample job descriptions completed by P&G team members;

Generic tashkeels for HR Units;

Generic job descriptions;

Weekly review by international consultants of 25 job descriptions and feedback provided to

team members;

Standard formats for P&G implementation plans and final P&G proposals.

25

Table 2: Status of P&G Reform Implementation

Ministry/Agency Restructuring Total Tashkeel Tashkeel Appointed % Appointed

Ministry of Justice Complete 9,004 5,953 66.12

Ministry of Public Health Complete 16,098 3,461 21.50

Ministry of Labour, Social Affairs , Martyrs and Disabled Complete 7,235 1,570 21.70

Ministry of Agriculture, Irrigation and Livestock Complete 9,299 8,075 86.84

IARCSC Complete 473 232 49.05

Ministry of Economy Complete 950 875 92.11

Ministry of Parliamentary Affairs Complete 128 47 36.72

Ministry of Rural Rehabilitation and Development Complete 2,129 1,264 59.37

Independent Directorate of Local Governance Complete 19,971 7,695 38.53

High Officer for Oversight on Anti-Corruption Complete 502 52 10.36

Ministry of Education Complete 222,000 72,341 32.59

Ministry of Finance Complete 7,180 5,191 72.30

Ministry of Public Works Complete 3,378 1,042 30.85

Ministry of Transport Complete 2,104 1,512 71.86

Atomic Energy Commission Complete 125 19 15.20

Ministry of Energy and Water Complete 2,697 1,677 62.18

Ministry of Commerce and Industry Complete 1,168 893 76.46

Ministry of Higher Education Complete 7,100 1,135 15.99

Office of the President Suspended 3,297 66 2.00

Ministry of Urban Development In progress 600 344 57.33

Ministry of Mines In progress 2,405 159 6.61

Ministry of Information and Culture In progress 3,903 2,505 64.18

Upper House of Parliament In progress 1,087 119 10.95

Lower House of Parliament In progress 2,763 119 4.31

Supreme Court In progress 6,542 4,423 67.61

Ministry of Foreign Affairs Not started 1,299 - -

Ministry of Haj and Religious Affairs Not started 7,044 - -

Ministry of Women's Affairs Not started 874 - -

Ministry of Refugees and Repatriation Not started 1,000 - -

Attorney General's Office Not started 4,831 - -

Office of Administrative Affairs Not started 1,206 - -

Science Academy Not started 459 - -

Independent Election Commission Not started 400 - -

Disaster Preparedness Office Not started 329 - -

Central Statistics Office Not started 800 - -

Control and Audit Office Not started 315 - -

Geodesy and Cartography Office Not started 700 - -

Directorate of Nomads Not started 198 - -

National Olympic Committee Not started 360 - -

Afghan National Standards Association Not started 300 - -

Legal Training Centre Not started 27 - -

26

Component 3: Project Management and Support Services

The IARCSC‟s ability to monitor and implement CSRP was designed through the project

management and support services component. This component was reengineered in 2009 to

strengthen project governance, coordination and project management capacity of the IARCSC,

rather than supporting broad reform communication and coordination efforts envisaged under the

original design. The original project design envisaged that project administration be carried out

through a multitude of existing units in the IARCSC. While this was intended to avoid ring

fencing and therefore to provide for more sustainable implementation of the project, in practice

fragmentation of implementation responsibility in the IARCSC has impacted on overall project

performance. Specific issues regarding project management are mentioned below:

Coordination and communication across directorates: The Programme was implemented by

the IARCSC but its implementation was marred by weak and fragmented management. The

different components of the programme were managed by different directorates within the

IARCSC (CSMD, IAB, ARS). Coordination and communication linkages among these

directorates were weak which resulted in bottlenecks in the decision making processes within the

IARCSC.

Capacity: The IARCSC had substantial experience of implementing public sector reform projects

since 2002. These include the first and second Emergency Public Administration Projects (EPAP

and SEPAP) on public administration reforms and projects such as Afghanistan Expatriate

Program (AEP) and Lateral Entry Program (LEP) on civil service capacity building aspects.

However, a thorough assessment of the capacity of the IARCSC to implement CSRP was not

completed prior to the initiation of the project. Therefore a lot of issues with regard to the project

management and implementation such as procurement and financial management issues related to

the consulting firms and co-ordination issues within the IARCSC were not addressed properly.

Utilization of TA by IARCSC: Implementing partners/consultants working with the IARCSC to

implement CSRP were not expected to provide feedback on project design at the policy level and

it was assumed that they would provide technical feedback on issues related to the management

and implementation of the Programme. As a result, many issues that impacted project

performance were resolved only at a very late stage of implementation.

Capacity of the Implementing Consultants: Consultants working with Civil Service

Management Department (CSMD) have helped enhance the capacity of the CSMD in the

technical aspects of implementing P&G and HR reforms. The guidelines, procedures and similar

documents that have been prepared by the consultants are comprehensive for the CSMD staff to

execute reform interventions by themselves to an extent. However counterparts for the

consultants were not identified in a timely manner. Even when counterparts were identified, they

were not permanent positions within the tashkeel, which made it difficult to ensure continuity.

Also, given the delay in recruiting international consultants for specific issues, the CSMD staff

did not receive sufficient training on the specific issues of organizational design and quality

assurance. The consultants deployed in line ministries to support the development of HR

capacities were partially effective. One of the major problems in implementing HR reforms was

the high turnover rate of the RIMU staff and unavailability of qualified replacements for the

mandated work in the line ministries. Also, these consultants did not have the capacity to drive

the reform agenda in the initial phase of project implementation largely due to institutional

constraints that surrounded them as discussed above. It is only with the recruitment of HR

directors through MCP that capacity building concerns began to receive importance within line

ministries.

27

Annex 3. Bank Lending and Implementation Support/Supervision Processes

(a) Task Team members

Names Title Unit Responsibility/

Specialty

Lending

Anne Tully Senior Operations Officer OPCFC TTL

Nagaraju Duthaluri Senior Procurement Specialist SARPS Procurement

Nigel Peter Coulson Senior Public Sector Specialist SASGP Public Sector

Ranjana Mukherjee Senior Public Sector Specialist SASGP Public Sector

Jalpa Patel Consultant SASGP Public Sector

Hossai Mahak Aliffi Team Assistant SASPF Program Assistance

Supervision/ICR

Satyendra Prasad Senior Governance Specialist SASGP TTL

Vikram Chand Senior Public Sector Management

Specialist SASGP TTL (ICRR)

Sebastian Eckardt Economist ECSP4 Public Sector

Deepal Fernando Senior Procurement Specialist ECSO2 Procurement

Asif Ali Senior Procurement Specialist SARPS Procurement

Kenneth O. Okpara Sr Financial Management Specialist SARFM Financial

Management

Asha Narayan Financial Management Specialist SARFM Financial

Management

Zohra Farooq Financial Management Specialist SARFM Financial

Management

Rahimullah Wardak Procurement Specialist SARPS Procurement

Maha Ahmed Consultant SASGP

Public Sector ;

Monitoring and

Evaluation

Jalpa Patel Consultant SASGP Public Sector

Mohammed Edreess Sahak Team Assistant SASEP Program Assistance

Kaushik Sarkar Consultant SASGP Public Sector

28

(b) Staff Time and Cost

Stage of Project Cycle

Staff Time and Cost (Bank Budget Only)

No. of staff weeks USD Thousands (including

travel and consultant costs)

Lending

FY06 18.4 281.84

FY07 38.7 163.06

FY08 0 0.00

Total: 444.90

Supervision/ICR

FY06 0 0.00

FY07 0 0.00

FY08 28.05 165.08

FY09 25.22 149.66

FY10 13.5 82.18

FY11 18.22 160.14

FY12 11.75 69.98

Total: 627.04

29

Annex 4. Summary of Borrower's ICR and/or Comments on Draft ICR

The Independent Administrative Reform and Civil Service Commission (IARCSC) acknowledge

the receipt of the Implementation Completion and Results Report (ICR) on the Civil Service

Reform project (CSRP). The IARCSC is appreciative of the opportunity given to provide its

feedback on the report.

Overall Comments on the ICR

According to IARCSC, this report provides good analytical findings which can be used for

further project design and implementation. This ICR is based on good consultations with all

stakeholders and provides many lessons. The report has noted weaknesses in the M&E and

Administration and Finance (A&F) departments; the project, however, failed to support these

departments. The report did not cover later decisions to address weaknesses in M&E.

The report does not explain clearly the role of the A&F Department in the IARCSC.

Consultations were carried out by the ICR team with the current project manager recruited at the

end of the project, who was not fully aware of the historical background of project

implementation especially during initial financial management of the project and procurement

process. The role of the A&F department was not clearly understood. Financial management,

accounting and contracts management was not the responsibility of the A&F department, as the

IARCSC had a decentralized program management policy. Even during restructuring of the

project, program management was the responsibility of the project manager and the Civil Service

Management Department (CSMD). It was only during the final stages of project implementation

that the A&F department was involved in financial management at length. Although the A&F

department had weaknesses at the beginning of project implementation, the capacity of the

department improved especially after the second supervision mission. This improvement can be

evidenced from the fact that the processing time of invoices fell from three months to 60 days,

and these improvements were also reflected in GRM‟s quarterly completion reports.

The observation regarding the ability of the IARCSC to implement projects satisfactorily has to

be considered in the present context in Afghanistan. The following reasons should be considered

in the context of CSRP:

A proper assessment of the IARCSC‟s capacities was not done before the design

phase.

Numbers of national technical assistants (NTA) available to the IARCSC were

inadequate for proper implementation. The knowledge transfer from the

International Consultants to the NTAs did not take place accordingly.

The report has not grasped the historical development of the project and context in which the

project was designed and implemented. The project was divided into components because of

procurement and administrative considerations rather than programmatic and design ones. This

was not acknowledged in the report. Inappropriate advice on procurement from the World Bank

was another issue, which caused the failure of the oversight and monitoring component of the

project. The World Bank‟s capacity to supervise projects effectively in circumstances such as

Afghanistan has to be enhanced. This could be considered a lesson for subsequent projects if we

want to get better project implementation results.

30

All stakeholders should be realistic in setting the goal for reform interventions as they involve not

only technical, but highly political as well as cultural change processes. Implementing agencies

need to have the right environment and internal capacity to implement these projects. Meanwhile,

the transplantation of concepts and ideas should be avoided and careful study and research on the

feasibility of the socio- political, cultural, economic and administrative potentials should be

undertaken. This project overlooked the need for a supportive political, administrative, and legal

environment for transplantation of reform ideas. The amount of learning that both the IARCSC

and the World Bank gained from this project should be used for future initiatives.

31

Annex 5. List of Supporting Documents

World Bank: Civil Service Reform Project Documents (CSRP P097030)

Implementation Status and Results, (July, 2011)

Final Implementation Support Mission (July, 2011)

Mid-term Review (September/October, 2010)

Aide-Memoire - Supervision (November 2008-March 2009)

Project Paper: Restructuring (November, 2009).

Aide Memoire: Project Supervision and Restructuring Mission (July, 2009)

Project Supervision and Aide Memoire (June-July, 2008)

Aide Memoire: Project Supervision (December, 2007)

Aide-Memoire: Project Launch (July, 2007)

Technical Annex for a Proposed Grant to the Islamic Republic of Afghanistan for a Civil

Service Reform Project (April, 2007).

Aide Memoire: Project Pre-Appraisal (February, 2007)

Consultant Reports: Civil Service Reform Project

GRM International Ltd. Component Completion Report V2: CSRP 600 (June, 2011)

GRM International Ltd. Quarterly Report 5: IARCSC/600 (September-December, 2009)

Public Administration International, Pay and Grading Component: CSRP 602 – Draft

Report (July,

2011).

Public Administration International, Pay and Grading Project: Quarterly Report

(December, 2009).

SMEC, Three Monthly Report Mizan to Qaus 1388: Civil Service Reform

Project/IARCSC 601 (2009)

Other World Bank Documents

Emergency Project Paper – Capacity Building for Results Facility (December, 2011)

(Quality Assessment Group, Quality Assessment of Lending Portfolio (QALP) – Civil

Service Reform Project, Afghanistan (May, 2010)

Afghanistan: Building an Effective State – Priorities for Public Administration Reform

(Washington DC: 2007)

Government of Afghanistan Documents Draft Amendments to Civil Servants Law (n.d.) at

http://www.csmd.gov.af/images/pdfs/laws/csl.pdf

Civil Servants Law (June 2008) at http://www.csmd.gov.af/images/pdfs/laws/csl.pdf

Civil Service Law (2005) at http://www.csmd.gov.af/images/pdfs/laws/csl.pdf

Code of Conduct for Civil Servants (n.d.) at

http://www.csmd.gov.af/images/pdfs/laws/csl.pdf

Personal Affairs Regulation at

http://www.mpil.de/shared/data/pdf/pdf/personal_affairs_regulation.pdf

Interviews Mr. Almoz, Executive Director, Appeals Board, IARCSC.

Mr. Phillip Choudhury, Team Leader, CSRP Component 600.

Mr. Mosa Kamawi, Director, Human Resources, Ministry of Finance, GoA.

32

Mr. Fawad Karmand, Civil Service Reform Project Manager.

Mr. Rahimi, Chairman Appeals Board, IARCSC.

Mr. Mir Javed Sadat, Director-General, Civil Service Management Department, IARCSC.

Mr. Allah Nawaz Safi, Executive Director, Independent Appointments Board (IAB).

Mr. A.E. Sediqi, Director, Legislation and Policies, IARCSC.

Mr. A.W. Sidiqi, Director, Human Resources, Ministry of Transport and Civil Aviation.

GoA.

Ms. Rahela Sidiqui, Senior Advisor, IARCSC.

Mr. Masoud Tokhi, Director, Public Administration Reform Department, IARCSC.

Ms. Ranjana Mukherjee, Sr. Public Sector Management Specialist, the World Bank

(Member of CSRP team).

Comments Received on Draft ICR

Sebastian Eckhardt, former TTL of CSRP

Jalpa Patel, Member of CSRP Team.

Anne Tully, former TTL of CSRP

Tirich MirTirich Mir(7690 m)(7690 m)

D a s h t - I M a r g oD a s h t - I M a r g o

Khyber PassKhyber Pass

P a r o p a m i s u s R a n g e

H i nd

u

Ku

sh

B A D G H I SB A D G H I S¯¯

H E R ATH E R AT¯ G H O RG H O R

FA R A HFA R A H¯

¯ ¯N I M R O ZN I M R O Z K A N D A H A RK A N D A H A R¯

U R U Z G A NU R U Z G A N¯

PA K T I K APA K T I K A¯ ¯

G H A Z N IG H A Z N I

NANGARHARNANGARHAR¯

KABULKABUL¯LAGHMANLAGHMAN

B A G H L A NB A G H L A N¯

KAPISAKAPISA¯ ¯ ¯

SAMANGANSAMANGAN¯

TAKHARTAKHAR BADAKHSHANBADAKHSHAN¯

KUNDUZKUNDUZ¯¯JAWZJANJAWZJAN

FA R YA BFA R YA B¯ ¯

H I L M A N DH I L M A N D

Z A B U LZ A B U L¯

B A L K HB A L K H

SARIPULSARIPUL NURISTANNURISTAN¯ ¯

Meydan ShahrMeydan Shahr¯

BamyanBamyan¯ ¯¯ ¯ ¯CharıkarCharıkar

GardızGardızGhaznıGhaznı

¯ ¯TaloqanTaloqan¯KondozKondoz

¯BaghlanBaghlan¯SamanganSamangan

¯¯

Mazar-eMazar-eSharıfSharıf

¯SheberghanSheberghan

¯ChaghcharanChaghcharan¯HeratHerat

¯FarahFarah

ZaranjZaranj

¯Lashkar GahLashkar Gah¯KandaharKandahar

¯QalatQalat

¯Tarın KowtTarın Kowt

Pol-e ‘AlamPol-e ‘Alam

¯ ¯ ¯JalalabadJalalabad

¯MehtarlamMehtarlam

¯ ¯NuristanNuristan¯ ¯AsadabadAsadabad

SharanSharan

MeymanehMeymaneh

Qal‘eh-ye NowQal‘eh-ye Now

¯ ¯¯Mahmud-e RaqıMahmud-e Raqı¸

FaisabadFaisabad

KABULKABUL¯

WA R D A KWA R D A K

PARWANPARWAN¯KUNARKUNAR

LOGARLOGAR

KOWSTKOWSTKowstKowst

PAKTIAPAKTIA

PANJSH

IR

PANJSH

IRBazarakBazarak

B A D G H I S¯¯

H E R AT¯ G H O R DAY KUNDIDAY KUNDIDAY KUNDI

FA R A H¯

¯ ¯N I M R O Z K A N D A H A R¯

U R U Z G A N¯

PA K T I K A¯ ¯

PAKTIA

G H A Z N I

NANGARHAR¯

KABUL¯LAGHMAN

B A G H L A N¯

KAPISA

PANJSH

IR

¯ ¯ ¯PARWAN¯

SAMANGAN¯

TAKHAR BADAKHSHAN¯

KUNDUZ¯¯JAWZJAN

FA R YA B¯ ¯

H I L M A N D

KOWST

Z A B U L¯

LOGARWA R D A K

KUNAR

B A L K H

SARIPUL

BAMYAN¯ ¯

NURISTAN¯ ¯

Meydan Shahr¯

Bamyan¯ ¯¯ ¯ ¯Charıkar

Bazarak

GardızGhaznı

¯ ¯Taloqan¯Kunduz

¯Baghlan¯Samangan

¯¯

Mazar-eSharıf

¯Sheberghan

¯Chaghcharan

Nili

¯Herat

¯Farah

Zaranj

¯Lashkar Gah¯Kandahar

¯Qalat

¯Tarın Kowt

Pol-e ‘Alam

¯ ¯ ¯Jalalabad

¯Mehtarlam

¯ ¯Nuristan¯ ¯Asadabad

Sharan

Kowst

Meymaneh

Saripul

Qal‘eh-ye Now

¯ ¯¯Mahmud-e Raqı¸

Faisabad

KABUL¯

TURKMENISTAN

UZBEKISTANTAJIKISTAN

TAJIKISTAN

PAKISTAN

PAKISTAN IND

IA

ISLAMICREPUBLICOF IRAN

Gowd-eZereh

Helmand

Helmand

Hamun-eSaberı˛

¯ ¯¯ ¯

Harırud¯ ¯

Morghab¯¯

¯

Pamir

Pyandzh

Indu

s

MurghobAmu Darya

Khas

Farah¯

Harut

¯ ¯

Darya-y

e Qonduz

Tarnak¯

Arghandab

D a s h t - I M a r g o

Khyber Pass

P a r o p a m i s u s R a n g e

H i nd

u

Ku

sh

Tirich Mir(7690 m)

ToMashad

ToMary

ToChardzhev

ToDushanbe

ToKulob˘

ToDushanbe

To Shazud

ToChitral

ToMardan

To Peshawar

ToKohat

ToZhob

ToQuetta

ToQurghonteppa˘

30°N

30°N

35°N

60°E

35°N

75°E

60°E

65°E 70°E

65°E 70°E

AFGHANISTAN

0 50 100

0 50 100 Miles

150 Kilometers

IBRD 33358R1

OC

TOBER 2011

AFGHANISTANPROVINCE CAPITALS

NATIONAL CAPITAL

RIVERS

MAIN ROADS

RAILROADS

PROVINCE BOUNDARIES

INTERNATIONAL BOUNDARIES

This map was produced by the Map Design Unit of The World Bank. The boundaries, colors, denominations and any other informationshown on this map do not imply, on the part of The World BankGroup, any judgment on the legal status of any territory, or anyendorsement or acceptance of such boundaries.