Update on FCPS Construction/Renovation Projects. July 2009. Cassidy Elementary – Renovation. Architect: Tate.Hill.Jacobs: Architects General Contractor: D.W. Wilburn, Inc. Substantial Completion Date:August, 2010 Contract Sum:$9,061,000 Change Orders to Date (1):$3,152.42 - PowerPoint PPT Presentation
Citation preview
Update on FCPS Construction/Renovation Projects
July 2009
July 2009
Cassidy Elementary – Renovation
Architect: Tate.Hill.Jacobs: Architects
General Contractor: D.W. Wilburn, Inc.
Substantial Completion Date: August, 2010 Contract Sum: $9,061,000
Change Orders to Date (1): $3,152.42
Current Phase: 1 (On Schedule)
Estimated Completion: 19%
July 2009
Cassidy Elementary – RenovationRendering of Final Façade
July 2009
Cassidy Elementary – RenovationWork Completed in Last 30 Days:Asphalt removal at Stage Addition complete.Primary electric installed and secondary conduits installed to transformer pad location.Selective interior demolition continuing with removal of walls, ceilings and doors in Phase 1. Mechanical demolition on-going.New Admin. Addition and Music Rm. Addition first floor slab in place.Bearing CMU walls up to first floor height at New Admin. Addition. CMU begun on Music Rm. Addition.Steel columns and beams begun for new Media Center at New Admin. Addition.Door frames installed in new CMU walls at New Admin. Addition.Under-slab plumbing and electrical rough-ins complete in New Admin. and Music Rm. Additions with wall rough-ins continuing with new CMU wall construction. New HVAC delivered to site.
July 2009
Cassidy Elementary – RenovationCurrent Work Effort (July):Storm sewer begun along front of building with new underground retention structures starting.Gas main line to begin between Morton M.S. and Cassidy Elem. with completion prior to start of school. Sanitary sewer work begun with completion prior to start of school.Fire Protection/Water Main work started with completion prior to start of school.Morton M.S. parking lot extension to start with completion prior to start of school.Selective demolition of interior areas to continue as needed for Phase 1 work.Concrete foundation and slab for Stage Addition to start with CMU walls following.Coordination Meeting to be held on site 1½ week prior to start of school with contractors, local fire department officials and FCPS staff to review life safety and emergency egress compliance prior to staff/student occupancy.
July 2009
Cassidy Elementary – RenovationExisting Gym During Demo New Admin Addition
July 2009
New Stage & Music Room Addition
New Media Center Addition
Russell Cave Elementary – Renovation
Architect: Pearson & Peters Architects
General Contractor: Congleton-Hacker
Construction
Substantial Completion Date: August, 2010
Contract Sum: $5,001,150
Change Orders to Date (1): $0
Current Phase: 1 (On Schedule)
Estimated Completion: 16%
July 2009
Russell Cave Elementary – RenovationRendering of Final Façade
July 2009
Russell Cave Elementary – RenovationWork Completed in Last 30 Days:Exterior concrete block walls are being installed.Interior of Kitchen/Cafeteria has been demolished and renovation has begun.Renovation of (4) classrooms on the south side has begun.Concrete slab at the new addition has been poured.Masonry restoration on the exterior of the original building in process.Existing elevator has been upgraded.
Current Work Effort (July):Roof trusses at the new additional will be set.Kitchen/Cafeteria renovation will be completed.Interior work on the new addition and the (4) classrooms on the south side will continue. They are scheduled to be completed in October.Complete new electrical and mechanical systems in Kitchen/Cafeteria.
July 2009
Russell Cave Elementary – RenovationNew Addition New Addition
July 2009
Masonry RestorationInterior of Cafeteria
Arlington Elementary – Renovation
Architect: RossTarrant Architects
General Contractor: W/S Construction
Substantial Completion Date: August, 2010
Contract Sum: $9,920,194
Change Orders: $36,900 (#1--Demo)
Current Phase: 1 (On Schedule)
Estimated Completion: Demo – 100%
July 2009
Arlington Elementary – RenovationRendering of Final Façade
July 2009
Arlington Elementary – RenovationWork Completed in Last 30 Days:Earthwork continuesInterior selective demolition continuesFoundation footers, stem walls and foundation drains are currently being installedSite utilities being brought to the buildingInterior plumbing being installed
Current Work Effort (July):Structural shoring to begin ASAP and subsequent demolition of the remainder of that scope of work to existing to remainMasonry scheduled to begin 7/20
July 2009
Arlington Elementary – RenovationEarthwork Continues Interior Selective Demo
July 2009
Foundation Footers Being Installed
Site Utilities to Building
Bryan Station Middle – Renovation
Architect: Clotfelter-Samokar Architects
General Contractor: Preston Construction Group
Substantial Completion Date: August, 2010
Contract Sum: $10,769,400
Change Orders to Date: $0
Current Phase: 1A (On Schedule)
Estimated Completion: 14%
July 2009
Bryan Station Middle – RenovationRendering of Final Façade
July 2009
Bryan Station Middle – RenovationWork Completed in Last 30 Days:Portable classrooms in placeMajority of demolition work in Phase 1 completeConcrete sidewalk and stairs at rear of building complete
Current Work Effort (July):Contractors preparing sub-grade for new addition and revised bus laneExisting storm drains being replaced with newNew sanitary sewer line being installed to replace old, inadequate “pump-station” type sewer systemKitchen/Cafeteria renovation work progressing rapidly to meet deadlinesOwner installing portable restroom units
July 2009
Bryan Station Middle – RenovationNew Storm Sewer Drains New Sanitary Sewer Line
July 2009
Kitchen/Café Renovation
Portable Restroom Units
Leestown Middle – Renovation
Architect: Lucas/Schwering Architects
General Contractor: D.W. Wilburn, Inc.
Substantial Completion Date: August, 2010
Contract Sum: $11,182,000
Change Orders to Date: $0
Current Phase: 1, 1a, 1b (On Schedule)
Estimated Completion: 12%
July 2009
Leestown Middle – RenovationRendering of Final Façade
July 2009
Leestown Middle – RenovationWork Completed in Last 30 Days:Phase 1demolition and Asbestos abatement efforts on-going.Phase 1 site demolition completeStructural shoring at Cafeteria and in CorridorKitchen foundation walls pouredDemolition of existing kitchen, front entrance and administration suite are complete
Current Work Effort (July):Interior and exterior demolition in Phases 1, 1a & 1b will continuePlumbing, HVAC, electrical demolition on-goingStructural shoring will continue to be erectedFloor slab for the new Kitchen will be pouredElectrical and Plumbing rough-ins to beginMasonry load bearing and erection of new fire walls to startMasonry restoration has begunErection of structural steel to begin
July 2009
Leestown Middle – RenovationFront Entrance Demo Admin Suite Demo
July 2009
Admin Suite Demo Looking From
Courtyard
Existing Kitchen Demo
Lafayette High Stadium – Replacement
Architect: Strand & Associates
General Contractor: Venture One Construction
Substantial Completion Date: June, 2010
Contract Sum: $4,100,000
Change Orders to Date: $0
Current Phase: Phase 1 to begin August 1
July 2009
Lafayette High Stadium – Replacement
Existing Campus
July 2009
Lafayette High Stadium – Replacement
Existing Football Stadium
July 2009
Lafayette High Stadium – Replacement
New Football Stadium
July 2009
Central Bus Garage – Adaptive Reuse
Architect: Lucas/Schwering Architects
General Contractor: James R. Leake & Sons, Inc.
Substantial Completion Date: August, 2009
Contract Sum: $2,782,000
Change Orders to Date (1): $4,346.17
Current Phase: Construction
Estimated Completion: 27%
July 2009
Central Bus Garage – Adaptive ReuseFaçade
July 2009
Central Bus Garage – Adaptive ReuseProposed Floor Plan
July 2009
Central Bus Garage – Adaptive ReuseWork Completed in Last 30 Days:Rock removal continuesExterior concrete continues to be placed, approximately 95% completeElectric standards in parking lot being installedUnder-slab plumbing installed and being testedShoring in place for lift pits Bus exhaust evacuation system in place
Current Work Effort (July):Steel erection for mezzanine to start 7/20Concrete placement at mezzanine to occur 7/24Electrical installation continuesInterior concrete slab placement to continueTrench drain installation to commenceNew parking lot water quality units to be installedParking lot curbs to be placed
July 2009
Central Bus Garage – Adaptive Reuse
July 2009
Install of Sanitary
Sewer LineUnder-slab Plumbing
Under-slab Plumbing
Foundation Wall
for Bus Lift
Tonight’s Agenda ItemsProject Agenda Item
Cassidy Elementary Approval of Third-Party Special Inspection Agreement Cost: $45,200
Arlington Elementary Approval of Third-Party Special Inspection Agreement Cost: $37,345
Bryan Station Middle Approval of Third-Party Special Inspection Agreement Cost: $42,000
Leestown Middle Approval of Third-Party Special Inspection Agreement Cost: $22,500
Lafayette High School Stadium
Approval of Bid, Proposed Contract and Revision to BG-1 Project Application Venture One Construction: $4,100,000 Total Project Cost: $4,616,180
Miles Point Way (Bus Garage)
Approval of Change Order #2 Total Cost: $6,575.94
Russell Cave Elementary Approval of Change Order #2 Total Cost: $11,179.62
Bryan Station Middle Approval of Change Order #1 Total Cost: $9,118.00
July 2009
Tonight’s Agenda Items - continuedProject Agenda Item
Leestown Middle Approval of Change Order #1 Total Cost: $2,874.40
New Elementary at Keithshire
Approval of Schematic Design Documents
July 2009