Upload
others
View
8
Download
0
Embed Size (px)
Citation preview
Update on WAPP Regional Interconnection Project
Update on WAPP Regional Interconnection Project
WAPIC – DAKAR
6 – 9 December, 2010
ContentsContents
Building Blocks for Regional Market
Update on WAPP Priority Project
2
WAPP Power Plant
WAPP Mandate
Information & Coordination Center Outlook
WEB SCADA
Gas Risk Mitigation
Insufficient Insufficient installed/available installed/available
generation capacities in generation capacities in all ECOWAS Member all ECOWAS Member
StatesStates
High volatility in fuel High volatility in fuel prices and inadequate prices and inadequate
tariff levelstariff levels
Supply/Demand Supply/Demand Imbalance characterised Imbalance characterised
by chronic load by chronic load sheddingshedding
ENERGYENERGYENERGYENERGYENERGYENERGYENERGYENERGY
CRISISCRISISCRISISCRISISCRISISCRISISCRISISCRISIS
IN IN IN IN IN IN IN IN
WEST WEST WEST WEST WEST WEST WEST WEST
AFRICAAFRICAAFRICAAFRICAAFRICAAFRICAAFRICAAFRICA
--Development of Development of Development of Development of Development of Development of Development of Development of generation and generation and generation and generation and generation and generation and generation and generation and
interconnection facilitiesinterconnection facilitiesinterconnection facilitiesinterconnection facilitiesinterconnection facilitiesinterconnection facilitiesinterconnection facilitiesinterconnection facilities
--Public Private Public Private Public Private Public Private Public Private Public Private Public Private Public Private PartnershipsPartnershipsPartnershipsPartnershipsPartnershipsPartnershipsPartnershipsPartnerships
--Establishment of a Establishment of a Establishment of a Establishment of a Establishment of a Establishment of a Establishment of a Establishment of a regional electricity regional electricity regional electricity regional electricity regional electricity regional electricity regional electricity regional electricity
marketmarketmarketmarketmarketmarketmarketmarket
--Regional institutional Regional institutional Regional institutional Regional institutional Regional institutional Regional institutional Regional institutional Regional institutional and regulatory and regulatory and regulatory and regulatory and regulatory and regulatory and regulatory and regulatory
frameworkframeworkframeworkframeworkframeworkframeworkframeworkframework
How to Overcome the Energy Deficit in West Africa?
How to Overcome the Energy Deficit in West Africa?
3
Sociétés Membres en 2006 (13#)
Sociétés Membres en 2006 (13#)
ECG
CEBEDG
VRA
SOPIE
Sociétés Membres en 2010 (20#)Sociétés Membres en 2010 (20#)
NIGELECECG
LEC
CEB
EDG
VRA
Essentials of Regional Electricity Essentials of Regional Electricity MarketMarket
WAPPMIS
WAPP Priority Project –Implementation Schedule
9
� WAPP Implementation strategy is based on realising:
� Coastal Transmission Backbone Subprogram (Côte
d’Ivoire, Ghana, Benin/Togo, Nigeria).
� Inter-zonal Transmission Hub Sub-program (Burkina
Faso, OMVS via Mali, Mali via Côte d’Ivoire, LSG via Côte d’Ivoire).
� North-core Transmission Sub-program (Nigeria, Niger, Burkina Faso, Benin).
� OMVG/OMVS Power System Development Subprogram(The Gambia, Guinea, Guinea Bissau, Mali, Senegal)
� Côte d’Ivoire-Liberia-Sierra Leone-Guinea Power System Re-development Subprogram (Côte d’Ivoire, Liberia,
Sierra Leone, Guinea).
� WAPP Strategic Generation Subprogram (Emergency
Power Supply Security Plan).
10
NIGERIA
NIGERSENEGAL
GAMBIA
GUINEABISSAU
GUINEA
MALI
SIERRALEONE
LIBERIA
Implementation Road Map
TOGO
GHANA
CÔTED’IVOIRE
BURKINA FASO
BENIN
Coastal Trans Backbone Sub-program
Inter-Zonal Trans Hub Sub-program
North-core Trans Sub-program
OMVG/OMVS Development Sub-program
CLSG System Redevelopment Sub-program
Coastal Backbone
Northcore
Inter Zonal
OMVG-OMVS
CLSG
NIGERIA
BENIN
TOGO
GHANA
SENEGAL
THEGAMBIA
GUINEABISSAU GUINEA
NIGERMALI
CÔTED’IVOIRE
BURKINA FASO
LIBERIA
SIERRALEONE
Interconnection in service
� 225 kV Bobo Dioulasso – Ouagadougou : OPERATIONAL SINCE DECEMBER 2009
• 330 kV Aboadze (Ghana) – Volta (Ghana); IMPLEMENTATION : 2010
• 330 kV Volta (Ghana) – Lome “C” (Togo) – Sakete (Benin); IMPLEMENTATION : 2013
• 60 MW WAPP Felou Hydropower; IMPLEMENTATION : 2013
• 225 kV Bolgatanga (Ghana) – Ouagadougou (Burkina Faso); PRE-INVESTMENT : 2013
• 147 MW WAPP Adjarala Hydropower – FINANCING REQUIRED : 2014
• 330 kV Birnin Kebbi (Nigeria) - Bembereke (Benin) – Niamey (Niger) – Ouagadougou (Burkina Faso); PRE-INVESTMENT : 2014
NIGERIA
BENIN
TOGO
GHANA
SENEGAL
THEGAMBIA
GUINEABISSAU GUINEA
NIGERMALI
CÔTED’IVOIRE
BURKINA FASO
LIBERIA
SIERRALEONE
Interconnection in service
• Cote d’Ivoire – Liberia – Sierra Leone – Guinea Interconnection Project – PRE-INVESTMENT -FINANCING MOBILISED : 2014
• 330 kV Aboadze (Ghana) – Prestea (Ghana) – Kumasi (Ghana) – Han (Ghana) + Tumu (Ghana) – Han (Ghana) – Wa (Ghana); PRE-INVESTMENT - 2015
• Han (Ghana) – Bobo Dioulasso (Burkina Faso) – Sikasso (Mali) – Bamako (Mali); -FINANCING REQUIRED : 2015
• 330 kV Riviera (Cote d’Ivoire) – Prestea (Ghana) – PRE-INVESTMENT : 2015
• 64 MW WAPP Mount Coffee Hydropower – PRE-INVESTMENT : 2015
NIGERIA
BENIN
TOGO
GHANA
SENEGAL
THEGAMBIA
GUINEABISSAU GUINEA
NIGERMALI
CÔTED’IVOIRE
BURKINA FASO
LIBERIA
SIERRALEONE
Interconnection in service
• Hydropower sites at Kaleta, Sambangalou + 225 kV Interconnection Line - IMPLEMENTATIONFINANCING REQUIRED : 2015
• 225 kV Nzérékoré (Guinea) – Fomi (Guinea – Bamako (Mali); PRE-INVESTMENT - 2016
WAPP Power Plant – Update
Status of Power Supply in ECOWAS:Supply Sources
Status of Power Supply in ECOWAS:Supply Sources
-
10,000
20,000
30,000
40,000
GWh
Benin
Burkin
a Fas
oCote
d'Iv
oireGam
bia
Ghana
Guinea
Guinea
Bis
sau
Liber
ia
Mal
iNig
eria
Seneg
alSie
rra L
eone
Togo
ThermalImport + OthersHydro
Import + Others
5% Hydro31%Thermal
64%
661 688 3,004 1707,773
860 16 16 841
38,370
1,800 56 674-
10,000
20,000
30,000
40,000
50,000
GWh
Benin
Burkin
a Fas
o
Cote d
'Ivoir
e
Gambia
Ghana
Guinea
Guinea
Biss
au
Liber
iaMali
Nigeria
Seneg
al
Sierra
Leon
eTog
o
MetUnmet
Status of Power Supply in ECOWAS:Demand-Supply Balance
Status of Power Supply in ECOWAS:Demand-Supply Balance
Unmet46%
Met54%
17
� Build three (3) regional thermal power plants at strategic locations:
� 450 MW combined cycle plant at Maria Gleta in Benin.
� 400 MW combined cycle plant at Aboadze in Ghana.
� 150 MW combined cycle plant within OMVS region.
WAPP Emergency Power Supply Security PlanWAPP Emergency Power Supply Security Plan
18
� Status:� Authority of ECOWAS Heads of State and Government enacted
fast track implementation of WAPP EPSSP in January 2008;
� Land with free-zone status secured in Benin for 450 MW Maria Gleta;
� Pre-investment studies completed for 450 MW Maria Gleta giving an estimated development cost of about US$700 million;
� Land already identified in Ghana for 400 MW Aboadze and is being secured from Government of Ghana under free-zone status;
� Location of 150 MW plant within OMVS region is being determined;
� Prequalification and Bidding Documents to secure Strategic Partner being finalised;
� Pre-investment studies for WAPP Liquefied Natural Gas Additional Fuel Facility being launched.
WAPP Emergency Power Supply Security Plan (EPSSP)WAPP Emergency Power Supply Security Plan (EPSSP)
GAS RISK MITIGATION PLANGAS RISK MITIGATION PLAN
Natural Gas
WAGP
Floating LNG Vessel
WAPP ICC PROJECTWAPP ICC PROJECT
OSMP Manual
Identified Gaps
Outcome of Gap AnalysisOutcome of Gap Analysis
Capacity Building Operating
Instruction & Procedure
Harmoized protection plan
Upgrade of SCADA/Communi
cation and Substation Equipment
Market Design &Rules
OperationMarket
Bidding Customer Data
Contracts
Billing & Financial Systems
Market Systems ReportsSettlements
Technical Standard and Procedure
Maintenance Coordination
Emergency Procedure
Metering Standards
Reserve Requests
Scheduling & Dispatching
WAPP Database
WAPP Information & Coordination CenterWAPP Information & Coordination Center
WAPP – Information & Coordination
Center
TCN
NIGELEC
CIE
SONABEL
VRA
CEB
SENELEC
EAGB
NAWEC
EDM
LEC
EDG
NPA
WAPP Information & Coordination Center
Control Area Center
National Control Center
Legend
Communication Link
24
Towards the realization of WAPP Electricity Market
Towards the realization of WAPP Electricity Market
Implementationof
OSMP
Implement
identified
gaps
ImplementProposedDesignof ICC
Case StudyWAPP M&E/MIS SystemOn-going
Negotiation stage
Constructthe
WAPP ICCBuilding
PROJECTS AWAITING IMPLEMENTATION
Operation Security &Mitigation
Plan
Gap Analysis
WAPPTariff
Methodology
WAPP M&E/MISSystem
Market Rules&
Market design
Architectural Design ofWAPP ICCBuilding
Web SCADAProject
RE
ALI
ZA
TIO
N O
F W
AP
P E
LEC
TR
ICIT
Y M
AR
KE
T
Feasibility Studies& Basic
Design of ICC
ImplementWeb SCADAsystem
NEXT PHASE
NIGERIA
NIGER
SENEGAL
GUINEA
BISSAUGUINEA
SIERRA
LEONE
MALI
LIBERIA
GAMBIA
Communication Infrastructure (Geographical)
BENIN
TOGO
GHANA
BURKINA
FASO
CÔTE
D’IVOIRE
WAPP Information & Coordination Center
Control Area Center
National Control Center
Legend
Communication Link
KEPCO project was KEPCO project was KEPCO project was KEPCO project was based on realizable communicationbased on realizable communicationbased on realizable communicationbased on realizable communicationLinks in the WAPP Priority ProjectsLinks in the WAPP Priority ProjectsLinks in the WAPP Priority ProjectsLinks in the WAPP Priority Projects
Web SCADA is independent on this Communication
WEB SCADA(Interim and Backup Power Monitoring solution for the operations of WAPP ICC)
WEB SCADA- BENEFITSWEB SCADA- BENEFITS
�Not dependent on completion of interconnection�Back-up WAPP Control Center�No SCADA control center/room associated costs; �Very low capital & operating costs in comparison to other solutions; �Fast to install and easy to maintain and support; �Use of the existing infrastructure of high quality digital communications ;�Flexible and scalable to add project-specific features; �Secure accessibility from anywhere anytime using web browsers;
WAPP WEB SCADA
SENELECWIS
SopieWIS
PHCNWIS
CEBWIS
SonabelWIS
GridcoWIS
WAPP ICC
INTERNETVPN
SOGEMWIS
WAPP ICC BUILDINGWAPP ICC BUILDING
WAPP ICC BuildingWAPP ICC Building
WAPP Information & Coordination CenterPROPOSED DESIGN
THANK YOUTHANK YOU
WEST AFRICAN POWER POOL 06 BP 2907
Cotonou, BeninTel. + 229 21 37 41 95Fax + 229 21 37 41 96E-mail [email protected]