Upload
others
View
1
Download
0
Embed Size (px)
Citation preview
Syncrude Canada Ltd. Mildred Lake Extension Project Volume 1 – Project Description December 2014
Table of Contents
SECTION 5.0 – MINE DESIGN TABLE OF CONTENTS
PAGE
5.0 MINE DESIGN ............................................................................................................... 5-1
5.1 Introduction ......................................................................................................... 5-1
5.2 Mine Design Summary ....................................................................................... 5-1 5.2.1 Mining Technology ............................................................................. 5-4 5.2.2 Geotechnical Design Basis ................................................................ 5-5 5.2.3 Road/Ramp Design ............................................................................ 5-8 5.2.4 Safe Operating Procedures ............................................................. 5-11
5.3 Design Assumptions ......................................................................................... 5-11 5.3.1 Bitumen Production .......................................................................... 5-12 5.3.2 Construction Materials ..................................................................... 5-12
5.4 Mining Equipment ............................................................................................. 5-13
5.5 MLX–W Mine Plan ............................................................................................ 5-14 5.5.1 Preproduction Activities ................................................................... 5-14 5.5.2 Timber and Reclamation Material Salvage ...................................... 5-15 5.5.3 Ore Production ................................................................................. 5-15 5.5.4 Overburden and Interburden ............................................................ 5-17 5.5.5 Mine Status ...................................................................................... 5-18
5.6 MLX–E Mine Plan ............................................................................................. 5-19 5.6.1 Preproduction Activities ................................................................... 5-19 5.6.2 Timber and Reclamation Material Salvage ...................................... 5-19 5.6.3 Ore Production ................................................................................. 5-19 5.6.4 Overburden and Interburden ............................................................ 5-20 5.6.5 Mine Status ...................................................................................... 5-23
Syncrude Canada Ltd. Mildred Lake Extension Project Volume 1 – Project Description December 2014
Table of Contents
TABLE OF CONTENTS (cont)
PAGE
LIST OF TABLES
Table 5.1-1: MLX Project Summary Information ..................................................................... 5-1 Table 5.2-1: Production Schedule .......................................................................................... 5-4 Table 5.2-2: Geotechnical Criteria .......................................................................................... 5-5 Table 5.2-3: Geotechnical Setback Distances ........................................................................ 5-8 Table 5.3-1: MLX Production Summary ............................................................................... 5-12 Table 5.3-2: Construction Material Use Summary ................................................................ 5-13 Table 5.4-1: MLX Project Equipment Profile......................................................................... 5-14 Table 5.5-1: MLX–W Mineable Resource Summary ............................................................ 5-15 Table 5.5-2: MLX–W Overburden/Interburden Volumes ...................................................... 5-17 Table 5.5-3: MLX–W Construction Material Schedule .......................................................... 5-17 Table 5.5-4: MLX–W Overburden/Interburden Placement Schedule ................................... 5-18 Table 5.5-5: MLX–W Development Milestones .................................................................... 5-18 Table 5.6-1: MLX–E Mineable Resource Summary ............................................................. 5-20 Table 5.6-2: MLX–E Overburden/Interburden Volumes ....................................................... 5-20 Table 5.6-3: MLX–E Construction Material Schedule ........................................................... 5-22 Table 5.6-4: MLX–E Overburden/Interburden Placement Schedule .................................... 5-22 Table 5.6-5: MLX–E Development Milestones ..................................................................... 5-23
LIST OF FIGURES
Figure 5.1-1: MLX–W Proposed Site Layout ........................................................................... 5-2 Figure 5.1-2: MLX–E Proposed Site Layout ............................................................................ 5-3 Figure 5.2-1: MLX–W Geotechnical Field Data Sources ......................................................... 5-6 Figure 5.2-2: MLX–E Geotechnical Field Data Sources .......................................................... 5-7 Figure 5.2-3: Permanent Mine Haul Road – Typical Cross-Section ........................................ 5-9 Figure 5.2-4: Temporary Mine Haul Road – Typical Cross-Section ...................................... 5-10 Figure 5.5-1: MLX–W Mining Sequence ................................................................................ 5-16 Figure 5.6-1: MLX–E Mining Sequence ................................................................................. 5-21
Syncrude Canada Ltd. Mildred Lake Extension Project Volume 1 – Project Description December 2014
Page 5-1
5.0 MINE DESIGN
5.1 Introduction
This section provides the mine design basis for the Mildred Lake Extension Project (MLX Project). It includes mine plan principles and assumptions, safe operating procedures, equipment profile, road design assumptions and a description of the ore preparation facilities. Detailed plans specific to the MLX West (MLX–W) and MLX East (MLX–E) mining pits and overburden disposal area (ODAs) follow the summary of common elements. Mineable resource in the MLX Project area is estimated at 117 Mm3 of recoverable bitumen. Development of this resource will extend the duration of mining activity on the Mildred Lake leases by approximately 14 years. For the proposed site layout for MLX–W, see Figure 5.1-1, and for MLX–E, see Figure 5.1-2. For MLX Project summary information, see Table 5.1-1.
Table 5.1-1: MLX Project Summary Information
Project Area MLX–W MLX–E
Mine pit area 1856 ha 769 ha
Bitumen in place (BIP) 101.1 Mm3 35.8 Mm3
Diluted ore grade 10.53 wt% bitumen 9.94 wt% bitumen
Recovered bitumen 87.3 Mm3 30.1 Mm3
Ore 941 MT 349 MT
Waste (excluding soil salvage) 780 Mbcm 159 Mbcm
Waste/Ore ratio 1.8 1.0
TV/BIP cutoff 12:1 12:1
TV/BIP design 14:1 14:1
The objective of the MLX mine design is to maximize recovery of surface mineable resource at Lease 17 and Lease 22. Design objectives are to:
minimize disturbance footprint;
provide reliable and consistent supply of ore to the processing plant;
minimize ore sterilization;
maximize progressive reclamation opportunities; and
support the Life-of-Mine Closure Plan.
5.2 Mine Design Summary
The MLX Project proposes the development of additional mining areas at the Mildred Lake Project site. The MLX mine plan assumes continued use of truck/shovel mining technology, and use of the crushers and ore preparation facilities currently in place at Mildred Lake. The MLX–W pit will be phased-in over four years, starting in 2023. On depletion of North Mine in 2026, the MLX–E pit will be opened up to supplement MLX–W production, maintaining bitumen production rates from Mildred Lake at 184,000 barrels per calendar day. A nominal increase in truck fleet size will be required to accommodate longer haul distances as production transitions and progresses into these new mining areas. For the MLX Project estimated production schedule, see Table 5.2-1.
ú
MacKay River
Dover River
RGE 12 RGE 11 W4
TWP 94
TWP 93
West Access
MacKay River
Bridge
To OPP
DD
A 2
(Cake)
DDA 1(Cake)
IN PITODA
ODA - N
OD
A -
S
Lease 22
Lease 17
448000 450000 452000 454000
632
200
063
24
00
063
26
000
632
800
063
30
000
633
200
06
33
400
063
36
000
LegendOSL Boundary
Operating and ApprovedOil Sands Development
Open Water
Defined Channel
Undefined Channel
Road
Mine Components
Reclamation Material Stockpile
Project Footprint
Facility
Overburden Advance
Mined-out Pit
Cake Placement
Overburden Dyke
Overburden Disposal Area
Mine Dewatering Sump
ú Bridge
±
Projection: UTM Zone 12 NAD83Note: Sources: GeoBase®,Spatial Data Warehouse Ltd., Syncrude.
0.5 0 0.5 1
Kilometres1:60,000
Pa
th:
S:\
Gis
\Pro
ject
s\C
E\S
yncr
ud
e_M
LX
\CE
04
183
_M
LX_
EIA
\Arc
GIS
\Ap
plic
atio
nR
epo
rtF
igur
es\V
ol 1
Sec
tion
05
- M
ine
Pla
n\F
ig05
.01
-01
W G
ene
ral S
ite L
ayo
ut.
mxd
MLX-W Proposed Site Layout
Figure 5.1-1
November 2014
Fig05.01-01 W General Site Layout14-11-03
CF
ANALYST: QA/QC:
DATE:
KW IS EH
MLX Project
Syncrude
PROVIDED BY:
AMEC
FINAL MAPPING BY:
RGE 11 RGE 10 W4
Lease 22
Lease 17
ODA - E
TWP 94
TWP 93
To OPP
East Athabasca
Highway
La SalineNatural
Area
Fort McKay 174
SalineLake
Athabasca
River
Beaver River
Mildred Lake Reservoir
HorseshoeLake
¾¾63
462000 464000 466000 468000
632
200
063
24
000
632
600
063
28
000
633
000
063
32
000
LegendOSL Boundary
Operating and ApprovedOil Sands Development
Indian Reserve
Park/Protected Area
Open Water
Reservoir
Defined Channel
Undefined Channel
Road
Mine Components
Tree Clearing and Grubbing
Reclamation Material Stockpile
Reclamation Soil Salvage
Ore Advance
Project Footprint
Overburden Advance
Mined-out Pit
Overburden Disposal Area
Highway Berm
ú Underpass
±
Projection: UTM Zone 12 NAD83Note: Sources: AB TPR, GeoBase®, Spatial Data Warehouse Ltd., Syncrude.
Pa
th:
S:\
Gis
\Pro
ject
s\C
E\S
yncr
ud
e_M
LX
\CE
04
183
_M
LX_
EIA
\Arc
GIS
\Ap
plic
atio
nR
epo
rtF
igur
es\V
ol 1
Sec
tion
05
- M
ine
Pla
n\F
ig05
.01
-02
E G
en
era
l Site
La
you
t.m
xd
MLX-EProposed Site Layout
Figure 5.1-2
November 2014
Fig05.01-02 E General Site Layout14-11-03
CF
ANALYST: QA/QC:
DATE:
KW IS EH
MLX Project
Syncrude
PROVIDED BY:
AMEC
FINAL MAPPING BY:
0.5 0 0.5 1
Kilometres1:50,000
Syncrude Canada Ltd. Mildred Lake Extension Project Volume 1 – Project Description December 2014
Page 5-4
Table 5.2-1: Production Schedule
Year Ore (Mt)
Overburden (Mt)
MLX–W MLX–E Total MLX–W MLX–E Total
2022 0 0 0 39 0 39
2023 19 0 19 96 0 96
2024 48 0 48 79 0 79
2025 63 0 63 73 0 73
2026 67 0 67 167 43 210
2027 94 26 120 166 28 194
2028 60 60 120 164 28 192
2029 60 60 120 135 61 196
2030 60 60 120 128 53 181
2031 76 44 120 126 41 167
2032 120 0 120 128 0 128
2033 102 18 120 127 32 159
2034 60 60 120 128 47 175
2035 99 21 120 78 4 82
2036 13 0 13 6 0 6
Total 941 349 1,290 1,640 337 1,975
5.2.1 Mining Technology
Shovel/truck mining technology has evolved to become the industry standard for oil sands surface mines because the technology:
has a high availability factor;
is flexible, allowing for rapid redeployment of the fleet to priority areas;
provides a high degree of selective mining capability to limit ore dilution and meet resource conservation expectations;
allows for blending of ores to optimize extraction performance; and
has proven to be cost-effective at the scale associated with oil sands surface mining developments, and suitable for the range of weather conditions experienced in northeastern Alberta.
Continued use of large-scale shovel/truck technology is assumed for excavation and material transport at the MLX Project. Continued use of this technology enables an efficient transfer of equipment used at North Mine, as well as continued use of the ore preparation and extraction facilities currently in place at the Mildred Lake site. Oil sands will be crushed and mixed with hot water at the Mildred Lake ore preparation plant (OPP) and hydraulically transported to the existing extraction facilities for bitumen recovery.
Syncrude Canada Ltd. Mildred Lake Extension Project Volume 1 – Project Description December 2014
Page 5-5
5.2.2 Geotechnical Design Basis
The geotechnical stability of pit walls and ODAs relies on understanding the key subsurface geological features. Generally, the stratigraphic units governing geotechnical design for the project features are the presence and thickness of the Clearwater Formation and Pleistocene deposits. Information for geotechnical analyses and design is derived from the following sources:
geological drill core information;
auger and sonic drilling information;
geotechnical sampling and testing results, and geotechnical information from similar materials found at the Mildred Lake operation; and
geologic model. For the locations of MLX–W geotechnical field data sources, see Figure 5.2-1, and for MLX–E, see Figure 5.2-2. Geotechnical criteria for mining and associated project components were developed based on available information. For a summary of the geotechnical criteria used to develop the mine plan for the MLX Project, see Table 5.2-2.
Table 5.2-2: Geotechnical Criteria
Component Sub-Component MLX–W MLX–E
Pit Walls Minimum safety berm width 10 m 10 m
Oil sands slope 28 degrees (~2H:1V) 42 degrees (~1.1H:1V)
Overburden slope 6H:1V 6H:1V
Overburden Disposal Areas Overall slope 14H:1V 14H:1V
Maximum height 40 m 40 m
Reclamation Stockpiles Overall slope (cover soil) 15H:1V 15H:1V
Overall slope (subsoil) 16.25H:1V 16.25H:1V
Maximum height 40 m 40 m
In-Pit Berms Highway berm slope n/a 6H:1V
Cake berms downstream 8H:1V upstream 6H:1V
n/a
Note: n/a = Not applicable.
For geotechnical setback distances for MLX Project components and existing features adjacent to the proposed development, see Table 5.2-3.
MacKay River
Dover River
RGE 12 RGE 11 W4
TWP 94
TWP 93
MLX-W Pit
ODA-N
ODA-S
444000 446000 448000 450000 452000 454000
632
000
063
22
000
632
400
063
26
000
632
800
063
30
000
63
32
000
633
400
06
33
600
063
38
000
63
40
000
LegendOSL Boundary
Project Footprint
Operating and ApprovedOil Sands Development
Open Water
Defined Channel
Undefined Channel
Road
Geotechnical Points
±
Projection: UTM Zone 12 NAD83Note: Sources: GeoBase®,Spatial Data Warehouse Ltd., Syncrude.
0.75 0 0.75 1.5
Kilometres1:90,000
Pa
th:
S:\
Gis
\Pro
ject
s\C
E\S
yncr
ud
e_M
LX
\CE
04
183
_M
LX_
EIA
\Arc
GIS
\Ap
plic
atio
nR
epo
rtF
igur
es\V
ol 1
Sec
tion
05
- M
ine
Pla
n\F
ig05
.02
-01
W G
eote
ch I
nfo
.mxd
MLX-W Geotechnical Field Data Sources
Figure 5.2-1
October 2014
Fig05.02-01 W Geotech Info14-10-03
FA
ANALYST: QA/QC:
DATE:
KW IS EH
MLX Project
Syncrude
PROVIDED BY:
AMEC
FINAL MAPPING BY:
RGE 11 RGE 10 W4
ODA-E
TWP 94
TWP 93
MLX-E Pit
Mildred Lake Reservoir
East Athabasca
Highway
La SalineNatural
Area
Fort McKay 174
SalineLake
Athabasca
River
Beaver River
HorseshoeLake
462000 464000 466000 468000
632
200
063
24
000
632
600
063
28
000
633
000
063
32
000
LegendOSL Boundary
Project Footprint
Operating and ApprovedOil Sands Development
Indian Reserve
Park/Protected Area
Open Water
Reservoir
Defined Channel
Undefined Channel
Road
Geotechnical Points
±
Projection: UTM Zone 12 NAD83Note: Sources: AB TPR, GeoBase®, Spatial Data Warehouse Ltd., Syncrude.
Pa
th:
S:\
Gis
\Pro
ject
s\C
E\S
yncr
ud
e_M
LX
\CE
04
183
_M
LX_
EIA
\Arc
GIS
\Ap
plic
atio
nR
epo
rtF
igur
es\V
ol 1
Sec
tion
05
- M
ine
Pla
n\F
ig05
.02
-02
E G
eo
tech
Info
.mxd
MLX-EGeotechnical Field Data Sources
Figure 5.2-2
October 2014
Fig05.02-02 E Geotech Info14-10-03
FA
ANALYST: QA/QC:
DATE:
KW IS EH
MLX Project
Syncrude
PROVIDED BY:
AMEC
FINAL MAPPING BY:
0.5 0 0.5 1
Kilometres1:50,000
Syncrude Canada Ltd. Mildred Lake Extension Project Volume 1 – Project Description December 2014
Page 5-8
Table 5.2-3: Geotechnical Setback Distances
Project Area Setback Location Setback Distance
(m) From To
MLX–W Pit (crest) South ODA (toe) 250
North ODA (toe) 250
Reclamation Stockpiles (toe) 250
MLX–E Pit (crest) Mildred Lake Settling Basin (toe) 200
Mildred Lake Reservoir (crest) 200
Geotechnical conditions will be monitored to identify and mitigate areas of potential concern. Final designs for ODAs, stockpiles and pit slopes, including detailed monitoring plans, will be provided before construction, as per Oil Sands Conservation Regulations.
5.2.3 Road/Ramp Design
Components of the mine road system include:
permanent haul roads;
temporary haul roads;
ramps;
safety berms; and
service roads. Permanent and temporary haul roads are designed with a running surface width of 40 m, adequate for two-way haul truck traffic. The finished road surface is crowned at 2% from the centreline. Construction materials for permanent haul roads include a subgrade of interburden, Clearwater overburden or Upper McMurray overburden, followed by a sand sub-base and a cap of pit-run and surfacing gravel, as shown in Figure 5.2-3. Temporary haul roads typically include similar subgrade and capping materials, but exclude the sand sub-base, as shown in Figure 5.2-4. Haul road ramps are designed to a maximum gradient of 8%, to support safe and efficient operation of loaded haul trucks. The cross-sectional design of ramps is generally consistent with those of the affiliated road type. Safety berms are an integral part of the design of both permanent and temporary haul roads. They are generally constructed of sand, till or interburden. Berms are constructed to a minimum of half the height of the tire of the largest haul truck designed to travel on the road. Safety berms will contain breaks every 25 m to facilitate drainage into adjacent ditches. Service roads are required for light vehicle traffic, and are designed fit for purpose.
Figure 5.2-3
Permanent Mine Haul Road -
Typical Cross-SectionMLX ProjectTypical Cross-Section
DATE: PROVIDED BY:
January 2014 AMEC
ANALYST: QA/QC:
JE KW CA IC
FINAL MAPPING BY:
AMEC
Pa
th:
I:\S
yn
cru
de
\00
-CA
D\0
4-W
ork
ing
Dra
win
gs\C
E\F
igure
5.2
-3.d
wg
SCALE HOR. 1:500
VER. 1:250
Figure 5.2-4
Temporary Mine Haul Road -
Typical Cross-SectionMLX ProjectTypical Cross-Section
DATE: PROVIDED BY:
January 2014 AMEC
ANALYST: QA/QC:
JE KW CA IC
FINAL MAPPING BY:
AMEC
Pa
th:
I:\S
yn
cru
de
\00
-CA
D\0
4-W
ork
ing
Dra
win
gs\C
E\F
igure
5.2
-4.d
wg
SCALE HOR. 1:500
VER. 1:250
Syncrude Canada Ltd. Mildred Lake Extension Project Volume 1 – Project Description December 2014
Page 5-11
5.2.4 Safe Operating Procedures
For a discussion on Syncrude’s commitment to safety, see Volume 1, Section 2.10. Safe operating procedures are in place for all aspects of the operation. In all cases, these procedures comply or exceed requirements specified in Alberta Occupational Health and Safety Regulations. The following safety standards will be applied at the MLX Project:
mandatory “Driving in the Mine” training: all personnel driving in the mine areas must have completed this training program;
cell phone use: the use of cell phone, including hands free, is prohibited while operating equipment or driving in the mine;
equipment operation: all equipment will be operated by trained and qualified workers, or under the direct supervision of a competent worker during training;
highwall berms: safety berms must be in place along all highwalls and open faces;
face height: single-bench working face height will not exceed maximum reach of excavation equipment by more than 1.5 m;
face access: walking or parking is not allowed within a distance equivalent to two times the height of the face, except for authorized mining equipment and personnel; and
brake checks: annual brake tests are done on at least 30% of the rubber-tired, self-propelled equipment. All such equipment undergoes brake testing within a three-year period.
Blasting of the mine faces occurs as needed, typically to deal with frozen ground conditions in late winter. Blasting is performed by certified personnel.
5.3 Design Assumptions
The following design principles guided development of the mine plans and production estimates for the MLX mining areas:
location of facilities, infrastructure and ODAs to minimize disturbance footprint and avoid ore sterilization;
mining selectivity of 3 m;
cutoff ore grade of 6 wt% bitumen;
nominal shovel bench height of 15 m, varying from a minimum of 3 m to a maximum of 18 m;
use of multi-benching as required in localized areas;
nominal working bench width of 400 m, with a minimum of 50 m;
cutoff total volume to bitumen in-place ratio of 14:1 in areas where the mining boundary is not constrained by lease boundaries, geotechnical requirements, river offsets or other significant physical features;
Syncrude Canada Ltd. Mildred Lake Extension Project Volume 1 – Project Description December 2014
Page 5-12
minimum setback of 100 m from Athabasca and MacKay River escarpments;
in-situ density of Clearwater and McMurray materials 2.1 t/m3;
swell factor of Clearwater and McMurray materials 10% to 20%;
swell factor of muskeg 30%; and
extraction recovery estimates consistent with those assumed in AER Directive 082: Operating Criteria: Resource Recovery Requirements for Oil Sands Mine and Processing Plant Operations.
5.3.1 Bitumen Production
Bitumen recovery estimates are consistent with those assumed in AER Directive 082. For an estimate of bitumen recovery and produced bitumen from the MLX–W and MLX–E developments, see Table 5.3-1.
Table 5.3-1: MLX Production Summary
Year
MLX–W MLX–E Total
Oil Sands (Mt)
Average Grade (wt%)
Oil Sands (Mt)
Average Grade (wt%)
Oil Sands (Mt)
Average Grade (wt%)
Recovered Bitumen (Mbbls)
2023 19 9.4 0 0.0 19 9.4 9.7
2024 48 10.7 0 0.0 48 10.7 28.3
2025 63 11.3 0 0.0 63 11.3 39.7
2026 67 11.1 0 0.0 67 11.1 41.9
2027 94 10.8 26 9.0 120 10.4 69.0
2028 60 10.4 60 10.3 120 10.4 69.3
2029 60 10.4 60 9.6 120 10.0 65.8
2030 60 10.4 60 9.8 120 10.1 66.9
2031 76 10.7 44 10.0 120 10.4 69.6
2032 120 10.3 0 0.0 120 10.3 69.0
2033 102 9.2 18 9.6 120 9.2 57.6
2034 60 10.4 60 10.2 120 10.3 68.4
2035 99 11.4 21 10.6 120 11.2 75.5
2036 13 10.7 0 0.0 13 10.7 7.9
Total 941 10.5 349 9.9 1,290 10.4 738.6
5.3.2 Construction Materials
To the extent practical, overburden and interburden materials with suitable properties will be used for dyke construction. Clearwater Formation (predominantly Kcw) and McMurray Formation overburden and interburden are typically suitable for construction of high-specification elements of containment dykes. Most materials are acceptable for use in low-specification zones. Overburden and interburden benches will be designed to maximize
Syncrude Canada Ltd. Mildred Lake Extension Project Volume 1 – Project Description December 2014
Page 5-13
availability of material types that meet the geotechnical requirements of planned structures, while maximizing ore recovery. Estimated availability of total construction material is adjusted to reflect weather and operational restrictions. For estimated construction material use for the MLX Project, see Table 5.3-2.
Table 5.3-2: Construction Material Use Summary
Year High Spec. Overburden / Interburden Low Spec. Overburden / Interburden
Available Planned Available Planned1
Mbcm Mbcm Mbcm Mbcm2021 0.0 0.0 0.0 0.0 2022 5.6 0.0 13.7 0.0 2023 14.5 0.0 32.0 0.0 2024 11.8 0.0 26.0 0.0 2025 10.4 3.0 24.7 15.3 2026 26.5 4.7 74.3 34.1 2027 26.6 2.8 66.6 26.3 2028 28.0 2.9 63.8 27.8 2029 26.1 7.5 68.1 39.7 2030 25.4 4.9 61.4 13.2 2031 24.6 3.3 55.5 5.6 2032 20.9 7.7 40.6 45.2 2033 21.0 3.8 55.3 41.1 2034 24.3 0.7 59.3 17.7 2035 11.9 0.0 27.1 0.0 2036 0.9 0.0 1.8 0.0
Total 278.5 41.3 670.2 266.0
Notes: 1 High-specification material not used to meet the requirement of high-specification construction areas is
typically used in low-specification construction zones. Planned low-specification volumes reflect the placement of high-specification material in low-specification areas.
5.4 Mining Equipment
The mining fleet comprises four categories of equipment:
primary equipment – shovels and haul trucks (240 t payload or greater);
major support equipment – dozers, graders, water trucks, excavators, and support haul trucks (100 t payload or less);
minor support equipment – small dozers or excavators; and
auxiliary equipment – light vehicles, service vehicles, welders, generators, compressors, pumps, cranes, forklifts, light towers, and emergency response equipment.
Calculations of primary equipment requirements are based on proposed mining rates and estimated performance metrics such as loading and hauling productivity, haul distance, payload, and mechanical availability. Support and auxiliary equipment fleet estimates are based on both
Syncrude Canada Ltd. Mildred Lake Extension Project Volume 1 – Project Description December 2014
Page 5-14
design considerations and current operating experience. For key equipment required for the MLX development, see Table 5.4-1. Much of this equipment fleet will transition from North Mine to the MLX Project areas over four years.
Table 5.4-1: MLX Project Equipment Profile
Equipment 20
20
2021
2022
2023
2024
2025
2026
2027
2028
2029
2030
2031
2032
2033
2034
2035
2036
Mining Equipment:
Electric cable shovel – 58 yd3 – – – 2 4 5 9 12 11 10 9 9 9 9 9 9 8
Hydraulic shovel – – 3 6 2 1 6 4 2 5 5 5 4 5 5 3 –
Haul truck – 391 t – – – 31 50 62 76 90 108 109 109 109 110 101 91 70 54
Haul truck – 320 t – – – – – – 5 4 – – – – – – – – –
Haul truck – 240 t – – 20 25 - - 25 10 6 6 6 6 6 15 3 – –
Mine Support Equipment:1
Dozer (250 to 800 hp)
Pre-production support equipment
(variable)
1 3 4 4 8 8 8 8 8 8 8 8 8 8
Grader (16H or 24H) 1 1 1 1 2 2 2 2 2 2 2 2 2 2
Loader 1 2 2 2 4 4 4 4 4 4 4 4 4 4
Backhoe 1 2 3 3 5 5 5 5 5 5 5 5 5 5
Scraper 1 1 1 1 2 2 2 2 2 2 2 2 2 2
Cable Reeler 1 1 1 1 2 2 2 2 2 2 2 2 2 2
Cable Tractor 1 1 1 1 2 2 2 2 2 2 2 2 2 2
Water Truck 1 1 2 2 3 3 3 3 3 3 3 3 3 3
Haul Truck (50 t) 1 2 2 2 4 4 4 4 4 4 4 4 4 4
Cake Transport:
Haul truck (cake) – 240 t Cake placement in tailings facilities at North Mine 78 78 78 78 84 87 84
Reclamation Equipment:
Reclamation loader 2 3 2 3 4 6 3 2 4 3 2 2 2 2 2 - -
Haul truck (reclamation) – 100 t
14 20 8 13 26 53 23 15 26 25 12 10 13 11 8 - -
Note: 1 Profile includes support equipment directly associated with mining operation activities; additional support equipment could be
required for other activities and projects.
5.5 MLX–W Mine Plan
Development of the MLX–W resource will require progressive excavation of a mine pit, permanent construction of two out-of-pit ODAs and interim construction of two reclamation material stockpiles (see Figure 5.1-1). Excavation of the mine pit will be followed by progressive infill and reclamation activities.
5.5.1 Preproduction Activities
Site development (preproduction) activities are scheduled to begin in 2018 (five years before bitumen production). Site development includes the following sequence of activities:
bridge and access road construction;
merchantable timber salvage;
clearing and grubbing;
surface drainage;
Syncrude Canada Ltd. Mildred Lake Extension Project Volume 1 – Project Description December 2014
Page 5-15
reclamation material salvage;
overburden removal from opening cut; and
haul road construction. Bridge and access road construction, merchantable timber salvage, clearing and grubbing, surface drainage, and reclamation material salvage activities are scheduled to begin in 2018.
5.5.2 Timber and Reclamation Material Salvage
During steady-state operation, merchantable timber salvage, and clearing and grubbing activities will take place during the winter months, three years ahead of overburden removal. Similarly, reclamation material salvage activities precede overburden stripping activities by one year. For details on timber salvage, clearing and grubbing, and reclamation material salvage, see Volume 1, Section 9.3.
5.5.3 Ore Production
The proposed MLX–W pit is defined by economic limits at the south, west and north of the ore body. To the east, the pit limit is defined by a minimum 100-m setback from the MacKay River escarpment. For the proposed MLX–W pit limit, see Figure 5.1-1. For a summary of mineable resources, see Table 5.5-1.
Table 5.5-1: MLX–W Mineable Resource Summary
Year Ore Grade
Water Content
Solids Fines Recovered Bitumen
Tonnage (Mt)
Volume (Mm3)
wt% wt% wt% wt% of solids
Mbbls
2023 19 9 9.4 5.1 85.5 21.0 10 2024 48 23 10.7 5.1 84.2 19.9 28 2025 63 30 11.3 5.1 83.6 19.8 40 2026 67 32 11. 5.1 83.8 20.7 42 2027 94 45 10.8 5.1 84.1 21.7 57 2028 60 29 10.4 5.1 84.5 24.4 35 2029 60 29 10.4 5.1 84.5 24.3 35 2030 60 29 10.4 5.1 84.5 21.3 35 2031 76 36 10.7 5.1 84.2 22.8 45 2032 120 57 10.3 5.1 84.6 22.6 69 2033 102 49 9.2 5.1 85.7 28.5 48 2034 60 29 10.4 5.1 84.5 21.6 35 2035 99 47 11.4 5.1 83.5 20.0 63 2036 13 6 10.7 5.1 84.2 26.7 8
Total 941 450 10.5 5.1 84.4 22.5 550
Mining will advance northward, with an extension to the west in the latter years of the mining sequence. For an illustration of the mining sequence, based on overburden advances, see Figure 5.5-1. Mining areas are prioritized to meet blending requirements and to meet dyke construction requirements.
ú
MacKay River
Dover River
RGE 12 RGE 11 W4
TWP 94
TWP 93
West Access
Mackay River
Bridge
To OPP
Year 2036
Year 2035
Year 2024
Year 2029
Year 2025
Year 2034
Year 2022
Year 2030
Year 2023
Year 2031
Year 2033
Year 2032
Year 2028
Year 2027
Year 2026
ODA - N
OD
A -
S
Lease 22
Lease 17
448000 450000 452000 454000
632
200
063
24
00
063
26
000
632
800
063
30
000
633
200
06
33
400
063
36
000
LegendOSL Boundary
Operating and ApprovedOil Sands Development
Open Water
Defined Channel
Undefined Channel
Road
Mine Components
Reclamation Material Stockpile
Project Footprint
Facility
Overburden Disposal Area
Mine Dewatering Sump
Mine Advance
Year 2022
Year 2023
Year 2024
Year 2025
Year 2026
Year 2027
Year 2028
Year 2029
Year 2030
Year 2031
Year 2032
Year 2033
Year 2034
Year 2035
Year 2036
ú Bridge
±
Projection: UTM Zone 12 NAD83Note: Sources: GeoBase®,Spatial Data Warehouse Ltd., Syncrude.
0.5 0 0.5 1
Kilometres1:60,000
Pa
th:
S:\
Gis
\Pro
ject
s\C
E\S
yncr
ud
e_M
LX
\CE
04
183
_M
LX_
EIA
\Arc
GIS
\Ap
plic
atio
nR
epo
rtF
igur
es\V
ol 1
Sec
tion
05
- M
ine
Pla
n\F
ig05
.05
-01
W A
nn
ual M
ine
Ad
vanc
e.m
xd
MLX-WMining Sequence
Figure 5.5-1
October 2014
Fig05.05-01 W Annual Mine Advance14-10-03
FA
ANALYST: QA/QC:
DATE:
KW IS EH
MLX Project
Syncrude
PROVIDED BY:
AMEC
FINAL MAPPING BY:
Syncrude Canada Ltd. Mildred Lake Extension Project Volume 1 – Project Description December 2014
Page 5-17
5.5.4 Overburden and Interburden
For a summary of the annual overburden and interburden volumes mined at MLX–W, see Table 5.5-2. For MLX–W overburden and interburden construction material schedule, see Table 5.5-3. For the overburden/interburden placement schedule, see Table 5.5-4.
Table 5.5-2: MLX–W Overburden/Interburden Volumes
Year Overburden Interburden Total Plant Rejects
Mbcm Mbcm Mbcm Mbcm 2022 19 0 19 0.0 2023 38 7 45 0.2 2024 30 8 38 0.4 2025 27 7 34 0.5 2026 67 12 79 0.6 2027 67 12 79 0.8 2028 64 14 78 0.5 2029 59 5 64 0.5 2030 60 1 61 0.5 2031 57 3 60 0.6 2032 54 7 61 1.0 2033 59 2 61 0.8 2034 57 3 61 0.5 2035 27 10 37 0.8 2036 2 1 3 0.1
Total 687 92 780 7.8
Table 5.5-3: MLX–W Construction Material Schedule
Year
Kcw/Marine Oil Sands and Interburden Kc Clays OB1Mbcm Mbcm Mbcm
High Spec Low Spec High Spec Low Spec Low SpecAvailable Planned Available Planned Available Planned Available Planned Available Planned
2022 0.1 0 0.2 0.0 5.5 0.0 12.0 0.0 3.3 0.0 2023 3.1 0 8.6 0.0 11.3 0.0 24.5 0.0 4.1 0.0 2024 2.8 0 8.0 0.0 9.1 0.0 19.6 0.0 2.6 0.0 2025 2.8 0 8.0 2.1 7.6 1.9 14.5 11.0 3.7 3.3 2026 5.4 0 14.5 3.9 19.7 4.7 37.9 23.2 7.1 7.1 2027 5.1 0 13.8 0.0 20.2 2.8 40.9 19.7 6.6 6.6 2028 5.2 0 14.6 3.9 20.2 2.9 40.8 19.3 4.7 4.7 2029 3.0 0 7.5 0.0 18.6 2.9 37.3 28.4 4.4 0.0 2030 2.0 0 4.2 0.0 18.6 0.1 40.1 0.0 4.9 1.5 2031 2.8 0 6.3 0.0 18.4 0.0 39.9 0.7 2.3 0.0 2032 3.1 0 8.4 3.2 17.8 4.3 34.2 33.6 2.3 2.3 2033 2.3 0 4.9 1.5 17.5 3.8 34.2 33.5 6.1 6.1 2034 2.1 0 5.2 4.2 17.8 0.7 37.7 8.0 5.5 5.5 2035 2.5 0 8.2 0.0 9.1 0.0 19.6 0.0 2.1 0.0 2036 0.1 0 0.4 0.0 0.8 0.0 1.6 0.0 0.1 0.0
Notes: Operational and environmental capture rates are applied to total material from the shovel face. Unused high-spec material becomes available for placement in low-spec zones.
Syncrude Canada Ltd. Mildred Lake Extension Project Volume 1 – Project Description December 2014
Page 5-18
Table 5.5-4: MLX–W Overburden/Interburden Placement Schedule
Year Structures Overburden Disposal Areas
Misc.1 Cake Berm 1 Cake Berm 2 ODA-S ODA-N In-Pit
Mbcm Mbcm Mbcm Mbcm Mbcm Mbcm2022 0.0 0.0 19.3 0.0 0.0 0.0 2023 0.0 0.0 46.4 0.0 0.0 0.0 2024 0.0 0.0 37.8 0.0 0.0 0.0 2025 18.3 0.0 1.4 15.4 0.0 0.0 2026 38.8 0.0 0.0 37.9 3.7 0.0 2027 25.5 3.6 0.0 46.5 4.2 0.3 2028 27.1 3.6 0.0 47.7 0.0 0.3 2029 24.4 6.9 0.0 16.7 16.9 0.3 2030 1.6 0.0 0.0 56.3 3.5 0.3 2031 0.0 0.7 0.0 22.3 37.4 0.3 2032 0.0 43.5 0.0 0.0 17.8 0.3 2033 0.0 44.8 0.0 0.0 16.1 0.3 2034 0.0 18.4 0.0 0.0 42.8 0.3 2035 0.0 0.0 0.0 0.0 37.2 0.3 2036 0.0 0.0 0.0 0.0 2.4 0.3
Notes: 1 Overburden for roads, ramps and other site requirements.
Material not used for structures is placed in in-pit or out-of-pit disposal areas.
5.5.5 Mine Status
For MLX–W development milestones, see Table 5.5-5. For status maps showing the MLX–W development from preproduction through to closure, see Volume 1, Section 7.1.
Table 5.5-5: MLX–W Development Milestones Year Development Milestones
Preproduction (2018 to 2022)
Bridge and access road construction. Merchantable timber salvage. Clearing and grubbing. Surface drainage.
Reclamation material salvage. Facilities construction. Opening cut overburden removal and disposal
into ODA-S. Haul road construction.
2023 First ore to OPP. 2024 Clean water diversion channel extension. 2025 Overburden placement ends at ODA-S.
Overburden placement begins at ODA-N. Construction of Cake Berm 1 begins.
2026 – 2027 – 2028 – 2029 – 2030 – 2031 Overburden placement ends at ODA-N.
Construction of Cake Berm 1 is complete. Construction of Cake Berm 2 begins.
2032 – 2033 – 2034 Construction of Cake Berm 2 is complete. 2035 – 2036 Oil sand mining is complete at MLX–W.
Note: – = No significant milestone.
Syncrude Canada Ltd. Mildred Lake Extension Project Volume 1 – Project Description December 2014
Page 5-19
5.6 MLX–E Mine Plan
Development of the MLX–E resource will require progressive excavation of a mine pit, permanent construction of one out-of-pit ODA and interim construction of one reclamation material stockpile (see Figure 5.1-2). Excavation of the mine pit will be followed by infill and reclamation activities.
5.6.1 Preproduction Activities
Site development (preproduction) activities are scheduled to begin in 2022 (five years before start of bitumen production). Site development includes the following sequence of activities:
access road construction including Highway 63 underpass;
merchantable timber salvage;
clearing and grubbing;
surface drainage;
reclamation material salvage;
overburden removal from opening cut; and
haul road construction. Access construction is expected to occur concurrently with early reclamation salvage activities, as access to the MLX–E pit is readily available through existing developments. Haul road access to the MLX–E development includes construction of an underpass to cross Highway 63 (see Figure 5.1-2).
5.6.2 Timber and Reclamation Material Salvage
During steady-state operation, merchantable timber salvage and clearing and grubbing will take place during the winter months, two years ahead of mining. Similarly, reclamation material salvage activities precede overburden stripping activities by one year. For details on timber salvage, clearing and grubbing, and reclamation material salvage, see Volume 1, Section 9.3.
5.6.3 Ore Production
The proposed MLX–E pit is defined by economic limits at the northern and southern extremities. Other constraints include a 100 m setback along the Athabasca River escarpment to the east, and geotechnical offsets of 200 m from both the Mildred Lake Settling Basin and the Mildred Lake Reservoir to the west. For the proposed MLX–E pit limit, see Figure 5.1-2. For a summary of mineable resources, see Table 5.6-1.
Syncrude Canada Ltd. Mildred Lake Extension Project Volume 1 – Project Description December 2014
Page 5-20
Table 5.6-1: MLX–E Mineable Resource Summary
Year Ore Grade
Water Content
Solids Fines Recovered Bitumen
Tonnage (Mt)
Volume (Mm3)
wt% wt% wt% wt%
of solids Mbbls
2027 26 12 9.0 4.6 86.4 28.3 12
2028 60 29 10.3 4.6 85.1 24.2 35
2029 60 29 9.6 4.6 85.8 24.6 31
2030 60 29 9.8 4.6 85.6 29.5 32
2031 44 21 10.0 4.6 85.4 24.6 24
2032 0 0 0.0 0.0 0.0 0.0 0
2033 18 9 9.6 4.6 85.8 27.1 9
2034 60 29 10.2 4.6 85.2 25.0 34
2035 21 10 10.6 4.6 84.8 23.1 12
2036 0 0 0.0 0.0 0.0 0.0 0
Total 349 168 9.9 4.6 85.5 25.8 189
The mining sequence initially proceeds from north to south, mining the eastern portion of the ore body and exposing the footprint of a highway berm to be constructed against the pit wall on the east side of the pit. Once the eastern panel reaches the southern pit boundary, the western panel will be mined from south to north. For an illustration of the mining sequence based on overburden advances, see Figure 5.6-1. There will be limited mining activity at MLX–E during highway relocation activities, estimated to occur in 2032.
5.6.4 Overburden and Interburden
For a summary of annual overburden and interburden volumes mined at MLX–E, see Table 5.6-2. For the MLX–E construction material schedule, see Table 5.6-3, and for the material placement schedule, see Table 5.6-4.
Table 5.6-2: MLX–E Overburden/Interburden Volumes
Year Overburden Interburden Total Plant Rejects
Mbcm Mbcm Mbcm Mbcm
2026 14.3 6.2 20.5 0.0
2027 7.1 6.1 13.2 0.3
2028 1.6 11.5 13.1 0.7
2029 9.2 19.9 29.1 0.7
2030 4.5 20.6 25.1 0.7
2031 5.0 14.4 19.4 0.5
2032 0.0 0.0 0.0 0.0
2033 9.8 5.4 15.2 0.2
2034 3.0 19.2 22.1 0.7
2035 0.0 1.7 1.7 0.2
2036 0.0 0.0 0.0 0.0
Total 54.5 105.0 159.4 4.0
RGE 11 RGE 10 W4
Lease 22
Lease 17
ODA - E
TWP 94
TWP 93
Year 2029
Year 2026
Year 2028
Year 2033
Year 2030
Year 2027
Year 2031Year 2034
To OPP
East Athabasca
Highway
La SalineNatural
Area
Fort McKay 174
SalineLake
Athabasca
River
Beaver River
Mildred LakeReservoir
HorseshoeLake
¾¾63
462000 464000 466000 468000
632
200
063
24
000
632
600
063
28
000
633
000
063
32
000
LegendOSL Boundary
Operating and ApprovedOil Sands Development
Indian Reserve
Park/Protected Area
Open Water
Reservoir
Defined Channel
Undefined Channel
Road
Mine Components
Reclamation Material Stockpile
Project Footprint
Overburden Disposal Area
Mine Advance
Year 2026
Year 2027
Year 2028
Year 2029
Year 2030
Year 2031
Year 2033
Year 2034
±
Projection: UTM Zone 12 NAD83Note: Sources: AB TPR, GeoBase®, Spatial Data Warehouse Ltd., Syncrude.
Pa
th:
S:\
Gis
\Pro
ject
s\C
E\S
yncr
ud
e_M
LX
\CE
04
183
_M
LX_
EIA
\Arc
GIS
\Ap
plic
atio
nR
epo
rtF
igur
es\V
ol 1
Sec
tion
05
- M
ine
Pla
n\F
ig05
.06
-01
E A
nnu
al M
ine
Ad
van
ce.m
xd
MLX-EMining Sequence
Figure 5.6-1
November 2014
Fig05.06-01 E Annual Mine Advance14-11-03
FA
ANALYST: QA/QC:
DATE:
KW IS EH
MLX Project
Syncrude
PROVIDED BY:
AMEC
FINAL MAPPING BY:
0.5 0 0.5 1
Kilometres1:50,000
Syncrude Canada Ltd. Mildred Lake Extension Project Volume 1 – Project Description December 2014
Page 5-22
Table 5.6-3: MLX–E Construction Material Schedule
Year
Kcw/Marine Oil Sands and Interburden
Mbcm
High Spec Low Spec
Available Planned Available Planned
2026 1.4 0.0 5.0 0.0
2027 1.4 0.0 4.9 0.0
2028 2.7 0.0 9.2 0.0
2029 4.6 4.6 11.3 11.3
2030 4.7 4.7 11.7 11.7
2031 3.3 3.3 8.2 4.9
2032 rehandle 3.4 rehandle 6.1
2033 1.2 0.0 4.3 0.0
2034 4.4 0.0 15.3 0.0
2035 0.4 0.0 1.3 0.0
Notes: Operational and environmental capture rates are applied to total material from the shovel face. Unused high-spec material becomes available for placement in low-spec zones. Material not used for structures is placed in in-pit or out-of-pit disposal areas.
Table 5.6-4: MLX–E Overburden/Interburden Placement Schedule
Year Highway Berm ODA-E In-Pit Dump Misc.
Mbcm Mbcm Mbcm Mbcm
2026 0.0 20.5 0.0 0.0
2027 0.0 13.1 0.0 0.2
2028 0.0 13.0 0.0 0.2
2029 15.9 13.0 0.0 0.2
2030 16.5 2.3 6.2 0.2
2031 8.3 0.0 11.0 0.2
2032 9.4 -9.61 0.0 0.2
2033 0.0 0.0 15.1 0.2
2034 0.0 0.0 22.0 0.2
2035 0.0 0.0 1.5 0.2
2036 0.0 0.0 0.0 0.0
Notes: 1 Volume rehandled from ODA-E, placed into highway berm.
Syncrude Canada Ltd. Mildred Lake Extension Project Volume 1 – Project Description December 2014
Page 5-23
5.6.5 Mine Status
For MLX–E development milestones, see Table 5.6-5. For status maps showing the MLX–E development, from preproduction through to closure, see Volume 1, Section 7.2.
Table 5.6-5: MLX–E Development Milestones
Year Development Milestones
Preproduction (2022 to 2026)
Access road construction including Highway 63 underpass. Merchantable timber salvage. Clearing and grubbing. Surface drainage. Reclamation material salvage. Opening cut overburden removal and disposal into ODA-E. Haul road construction.
2027 First ore to OPP.
2028 Addition of clean water diversion system to the south (Horseshoe Lake).
2029 Overburden placement begins in-pit with construction of the Highway Berm.
2030 Overburden placement ends at ODA-E.
2031 –
2032 Construction of Highway Berm is complete; Highway is relocated onto Highway Berm.
2033 –
2034 –
2035 –
2036 Oil sands mining is complete at MLX–E.
Note: – = No significant milestone.