    Weekly Construction Progress Report

    TITAN Contract No. : CAF-583

    LEC Job No. : 511838

    WCPR-01

    Report Period : 2011. 10. 09 ~ 10. 15

    TITAN Project - T

  • 8/2/2019 Weekly Construction Report_2011.10.15

    2/22

    1. Construction Activity Summary

    2. Weather Record

    3. Safety Control Status

    4. Quality Control Status

    5. Construction Progress Summary

    6. Quantitative Construction Progress Status

    7. Three Weeks Construction Schedule

    8. Construction Manpower Status

    9. Material Delivery Status

    10. Pending Matters --> Status of Pending Items

    11. Areas of Concern

    Contents

  • 8/2/2019 Weekly Construction Report_2011.10.15

    3/22

    1. Weekly Construction Activity Summary

    Last Week Due Date Highlight

    **

    **

    Major Activities

    1) Civil

    * Prepare Site ITP for Steel Stucture 13-10-2011

    * Site Visit to Precast Concrete Supplier/Vendor 10-11-2011

    *

    *

    2) Structure

    **

    3) Mechanical

    *

    *

    4) Piping

  • 8/2/2019 Weekly Construction Report_2011.10.15

    4/22

    1. Weekly Construction Activity Summary

    **

    5) Electrical

    *

    *

    6) Instrumentation

    *

    *

    7) Painting / Insulation

    *

    *

  • 8/2/2019 Weekly Construction Report_2011.10.15

    5/22

    Status This Week Highlight

    **

    **

    Major Activities

    1) Civil

    * Prepare Bill of Quantity/Work Volume for Civil Works

    * Prepare & Update Work Breakdown Schedule for Civil Structure Work

    2) Structure

    **

    3) Mechanical

    *

    *

    4) Piping

  • 8/2/2019 Weekly Construction Report_2011.10.15

    6/22

    **

    5) Electrical

    *

    *

    6) Instrumentation

    *

    *

    7) Painting / Insulation

    *

    *

  • 8/2/2019 Weekly Construction Report_2011.10.15

    7/22

    Due Date Status

    Ongoing

    Ongoing

  • 8/2/2019 Weekly Construction Report_2011.10.15

    8/22

  • 8/2/2019 Weekly Construction Report_2011.10.15

    9/22

    2. Weather Record

    Sun Mon Tue Wed Thu

    10/9 10/10 10/11 10/12 10/13

    2.1 Weather Condition

    a. Clear Morning- clear Morning- clear Morning- clear Morning- cloudy

    b. Cloudy Evening-cloudy Evening-cloudy Evening-storm Evening-clear

    c. Rainy * Morning

    * Afternoon

    * Evening

    ** Total (mm)d. Windy

    2.2 Temperature (C) Min - 24o

    C Min - 24o

    C Min - 24o

    C Min - 24o

    C

    a. Highest Max - 32o

    C Max - 32o

    C Max - 32o

    C Max - 32o

    C

    b. Lowest

    2.3 Remarks

    Description

  • 8/2/2019 Weekly Construction Report_2011.10.15

    10/22

    Fri Sat

    10/14 10/15

    Morning- clear Morning- clear

    Evening-storm Evening-storm

    Min - 24o

    C Min - 24o

    C

    Max - 32o

    C Max - 32o

    C

  • 8/2/2019 Weekly Construction Report_2011.10.15

    11/22

    3. Safety Control Status

    3.1. Induction Meeting / Training

    1) Staff/Supervisor MD 4 0 4

    2) Labor 15 0 15

    3.2. Inspection for Construction Equipment

    1) Pass EA 0 0 02) Reject 0 0 0

    3.3. Incident / Accident

    1) Working Hours without LTA HR 960 0 9602) LTA(Lost Time Accident) EA 0 0 03) First-Aid-Case 0 0 0

    UnitPrevious

    (Cumul.)Last Week

    Current

    (Cumul.)

  • 8/2/2019 Weekly Construction Report_2011.10.15

    12/22

    4. Quality Control Status

    1. Inspection Status

    Period CivilSteel

    StructureEquip. Piping Elec/Inst

    Painting/

    InsulationOthers Total Remarks

    Previous (Cumul.) 0 0 0 0 0 0 0 0

    Last Week 0 0 0 0 0 0 0 0

    Current (Cumul.) 0 0 0 0 0 0 0 0

    2. Highlights in Last Week

    1) To Review Construction Specification for Civil and Steel Structural. : 11-10-17

    2) :

    3) :

    4) :

    5) :

  • 8/2/2019 Weekly Construction Report_2011.10.15

    13/22

    5. Summary of Construction Progress

    Project Const.

    Discipline Weight Weight

    % % This WK Cumul. This WK Cumul. This WK Cumul. This WK Cumul.

    1 Temp. Fac. 0.53 3.29 - 100.00 - 100.00 - 0.53 - 0.53

    2 Civil 1.52 9.44 3.00 31.00 - 1.22 0.05 0.47 - 0.02

    3 Stl-Str. 2.64 16.39 2.00 19.00 - - 0.05 0.50 - -

    4 Equipment 1.96 12.17 - - - - - - - -

    5 Piping 6.01 37.31 - - - - - - - -

    6 Electrical 1.90 11.79 1.00 2.00 - - 0.02 0.04 - -

    7 I & C 0.90 5.59 1.00 2.00 - - 0.01 0.02 - -

    8 Paint/Insul. 0.59 3.66 - - - - - - - -

    9 Pre-Comm. 0.06 0.37 - - - - - - - -

    16.11 100.00 0.13 1.56 0.55Total

    Percent Complete Weight Complete

    Plan Actual Plan Actual

  • 8/2/2019 Weekly Construction Report_2011.10.15

    14/22

    6. Quantitative Construction Progress2011. 10. 09 ~ 10. 15

    Previous

    (Cumul.)Last Week

    Current

    (Cumul.)%

    Civil

    Stl-Str.

    Equip.

    Discipl. Work Description UnitTotal

    Q'ty

    Progress

  • 8/2/2019 Weekly Construction Report_2011.10.15

    15/22

    6. Quantitative Construction Progress2011. 10. 09 ~ 10. 15

    Previous

    (Cumul.)Last Week

    Current

    (Cumul.)%

    Discipl. Work Description UnitTotal

    Q'ty

    Progress

    Paint'g

    Insul.

    Total

  • 8/2/2019 Weekly Construction Report_2011.10.15

    16/22

    Project Name : TITAN Project-T * Cut Off Date : * Remaining Days for Completi

    Mon Tue Wed Thu Fri Sat Sun MonStart Finish Unit Plan Act. 10/10 10/11 10/12 10/13 10/14 10/15 10/16 10/17

    Civil -

    1 12/24 1/17 25 m 260 210 81%

    2 1/14 d #VALUE! m 177 8

    3

    4 1/12 1/20 9 EA 96 48 50%

    5 1/16 1/18 3 m 39 -

    6 1/8 1/9 2 m 63 63 100%7 -

    8 -

    9 -

    Piping

    1 1/13 1/20 8 m 177 36 20%

    2 1/8 1/8 1 m 39 39 100%

    3 1/7 1/7 1 m 63 63 100%

    4 1/6 1/6 1 m 39 39 100%

    5 1/6 1/6 1 m 31 31 100%

    Electrical 1/14 1/22 9 m 260 -

    1 1/20 1/26 7 EA 96

    Prog.

    Last Week

    Discipline / Category / Activity

    7. Three(3) Week Schedule

    2011-10-10

    Schedule

    Dur

    Work Volume

    For Example Only

  • 8/2/2019 Weekly Construction Report_2011.10.15

    17/22

    8. Construction Manpower Mobilization Status Unit : Man-Week (M/W)

    Previous

    (Cumul.)Last Week

    Current

    Cumul. (b)

    1 Temp. Fac. 0.0 #DIV/0!

    2 Civil 0.0 #DIV/0!

    3 Stl-Str. 0.0 #DIV/0!

    5 Equipment 0.0 #DIV/0!

    7 Piping 0.0 #DIV/0!

    8 Electrical 0.0 #DIV/0!

    9 I & C 0.0 #DIV/0!

    10 Painting 0.0 #DIV/0!

    11 Insulation 0.0 #DIV/0!

    0.00 0.00 0.00 0.00 #DIV/0!Total

    Original

    Mob. Plan

    (a)

    Discipline

    Actual

    Remarks

    Plan vs.

    Actual :

    (b/a)

    [%]

  • 8/2/2019 Weekly Construction Report_2011.10.15

    18/22

    9. Material Delivery Status

    9.1 Materials Received Last Week

    No. Unit1

    2

    3

    4

    5

    6

    7

    8

    910

    11

    9.2 Materials to be Received This Week

    No. Unit

    1 U/G Piping & Fitting for Project-T 8 Pckg. 2011.10.22 Onhold for C/C

    2

    3

    45

    6

    7

    8

    9

    10

    11

    12

    Q'ty

    Q'ty

    No. P/O No. DescriptionDate of

    Receiving

    Remarks

    No. P/O No. DescriptionDate of

    ReceivingRemarks

  • 8/2/2019 Weekly Construction Report_2011.10.15

    19/22

    9. Material Delivery Status

  • 8/2/2019 Weekly Construction Report_2011.10.15

    20/22

    TITAN Project-T

    Action DueB Date

    ** Fixed Lump-Sum Contract with TITAN* Ex edite TITAN's on Budget Increase PD

    ** LOI to Subcontractors* Ex edite TITAN's Decision on Budget Increase PD

    ** Preparation for Subcontract PCM/PE 14-Oct-11* Index * Main Text* T&C * SOW* BOQ * S ec* Drawings

    ** Project Coordination Procedure_R1* Main Text PD 26-Sep-11* Construction Weekly Re ort (Form) PD 03-Oct-11* Submit to TITAN PE(HO) 07-Oct-11

    **

    ** RFQ/PO Pending Items PO SRD* Field Fab Tanks* Mixer & E ector* Fire-Fighting E t* Gas Detection Sys.

    * E&I Cable/Wire* Pi ing Mat'l (2nd)* Pi ing S ecial Parts (1st)* Butterfly Valve

    10. Status of Pending It

    Cat. Works To Be Done

    Overall/G

    eneral

    Engg

    c

    RFQ B/C TBE Nego14/06/11 23/06/11 19/07/11 22/08/1110/08/11 19/08/11 14/10/1119/09/11 28/09/11 19/10/1127/07/11 24/10/11 03/11/11

    08/09/11 29/09/11

    12/10/11 20/10/11 25/10/11

    12/10/11

  • 8/2/2019 Weekly Construction Report_2011.10.15

    21/22

    As of :

    Prio Status/-rit Forecast

    A

    U * Sent Expediting e-Mail to TITAN on 10-Oct.

    H * Be ready for Approval Processing* Construction Team to review T&C and SOW

    * Updating Details of Const. Matters

    DoneDone

    Done(12-Oct) * Weekly Reporting shall be practiced

    ETA(Site) * Indication of Date : DD-MM-YY

    * Sight Glass, Flexible Hose, etc.* Site Procurement Item

    ems2011-10-15

    Reference / Remarks

  • 8/2/2019 Weekly Construction Report_2011.10.15

    22/22

    11. Areas of Concern

    2011-10-15

    Srl No. Subject Description Remarks

    1 Underground Services

    Underground for BD/OCU at cable trench &

    underground piping clashes with

    Hydrant,Cabinet Hose Reel and Lighting Pole.

    To Contruct New

    Drawing Layout

    2 Incoming MaterialTo revise Inspection Report and pending

    missing Mill. Certificate to be received.Follow -up

    3 U/G Piping Custom ClearanceTo expedite Titan for U/G Piping Custom

    Clearance

    ETA on Saturday

    (10/22)

    4

    5