WEEKLY CONSTRUCTION PROGRESS REPORT Crawford Long Middle School July 1st, 2016 Page 1 of 4 Prepared For: Atlanta Public Schools Prepared By: Austin Nichols Aerial Photo Aerial Photo Aerial Photo Auditorium Stairs/Sidewalk

WEEKLY CONSTRUCTION PROGRESS REPORT Crawford Long … · WEEKLY CONSTRUCTION PROGRESS REPORT Crawford Long Middle School ... WEEKLY CONSTRUCTION PROGRESS REPORT Crawford Long Middle

Embed Size (px)

Citation preview

Page 1: WEEKLY CONSTRUCTION PROGRESS REPORT Crawford Long … · WEEKLY CONSTRUCTION PROGRESS REPORT Crawford Long Middle School ... WEEKLY CONSTRUCTION PROGRESS REPORT Crawford Long Middle

WEEKLY CONSTRUCTION PROGRESS REPORT Crawford Long Middle School July 1st, 2016

Page 1 of 4

Prepared For: Atlanta Public Schools

Prepared By: Austin Nichols

Aerial Photo Aerial Photo

Aerial Photo Auditorium Stairs/Sidewalk

Page 2: WEEKLY CONSTRUCTION PROGRESS REPORT Crawford Long … · WEEKLY CONSTRUCTION PROGRESS REPORT Crawford Long Middle School ... WEEKLY CONSTRUCTION PROGRESS REPORT Crawford Long Middle

WEEKLY CONSTRUCTION PROGRESS REPORT Crawford Long Middle School July 1st, 2016

Page 2 of 4

Chiller Walls Striped Track

‘ New Basketball Goals Gym/Auditorium Demo

Last Week’s Activities:

• Classroom Addition

o Finished installing door hardware

o Finished painting

o Began VCT install

• Auditorium

o Installed restroom fixtures

o Installed stage lights

• Administration Addition

o Installed Sunshade support

o Installed ACT grid

Page 3: WEEKLY CONSTRUCTION PROGRESS REPORT Crawford Long … · WEEKLY CONSTRUCTION PROGRESS REPORT Crawford Long Middle School ... WEEKLY CONSTRUCTION PROGRESS REPORT Crawford Long Middle

WEEKLY CONSTRUCTION PROGRESS REPORT Crawford Long Middle School July 1st, 2016

Page 3 of 4

o MEP grid rough-in

• Administration Renovation

o Finished framing

o Hung ceiling

o Startup HVAC

• Gym Renovation

o Continued MEP rough-in

o Began installing rails

This Week’s Activities:

• Classroom Addition

o Began installing rubber base

o Finished installing VCT

o Finished installing shelves

o Began final cleaning

• Auditorium

o Began prep for sidewalk and steps

o Poured steps and sidewalk

o Demoed wall between auditorium and gym

• Administration Addition

o Finished MEP rough in

• Administration Renovation

o Began hanging drywall

o Finished MEP install

• Gym Renovation

o Continue MEP rough-in

o Continued framing

Next Week’s Activities:

• Classroom Addition

o Begin installing lockers

o Begin installing marker boards

o Begin cleaning

o Continue final cleaning

• Auditorium

o Continue finish paint

o Begin backstage VCT

• Administration Addition

o Begin installing epoxy flooring

Page 4: WEEKLY CONSTRUCTION PROGRESS REPORT Crawford Long … · WEEKLY CONSTRUCTION PROGRESS REPORT Crawford Long Middle School ... WEEKLY CONSTRUCTION PROGRESS REPORT Crawford Long Middle

WEEKLY CONSTRUCTION PROGRESS REPORT Crawford Long Middle School July 1st, 2016

Page 4 of 4

o Begin installing restroom tile

o Finish priming walls

o Overhead ceiling inspection

• Administration Renovation

o Finish prime paint on walls

o Begin wall tile

o Begin epoxy flooring installation

• Gym Renovation

o Finish hanging new basketball goal

o Continue installing waste and vent installation

o Begin MEP overhead rough in new classrooms

Schedule:

• Status: Weather dependent

• Substantial Completion Dates:

o Classroom Addition: July 15, 2016

o Renovations: July 20, 2016

o Administration Addition: July 25, 2016

o Track and Field: September 1, 2016

o Auditorium Addition: September 1, 2016

o Gym Renovation: October 1, 2016

• Final Completion: December 31, 2016

Budget:

• Construction Budget: $15,920,000

• Budget Status: On Budget

• Gross Billed To Date: $10,118,024