West Plumb Lane Project Preliminary Design Public Information Meeting June 4, 2012

West Plumb Lane Project Preliminary Design Public Information Meeting June 4, 2012

Embed Size (px)

Citation preview

Page 1: West Plumb Lane Project Preliminary Design Public Information Meeting June 4, 2012

West Plumb Lane Project Preliminary Design

Public Information MeetingJune 4, 2012

Page 2: West Plumb Lane Project Preliminary Design Public Information Meeting June 4, 2012

Presentation Goals

Review the project history and community outreach process

Present the preferred improvements supported by the community for the Plumb Lane reconstruction project

Provide details on design developmentRequest input on some design elementsAnswer questions and address your concerns

Page 3: West Plumb Lane Project Preliminary Design Public Information Meeting June 4, 2012

Project Limits

Page 4: West Plumb Lane Project Preliminary Design Public Information Meeting June 4, 2012

Public EngagementCommunity Outreach To Date Community Survey 2 Community Workshops One-on-one meetings with residents Meetings with: Councilman Gustin, Councilwoman Zadra, Commissioner

Breternitz, Assemblywoman Benitez-Thompson, Caughlin Ranch HOA, Washoe County West Truckee Meadows CAB, City of Reno Ward 1 NAB

Coordination with City of Reno Community Development and Public Works Coordination with TMWA Media Interviews RTC TAC, CAC and BPAC Reno City Council

Page 5: West Plumb Lane Project Preliminary Design Public Information Meeting June 4, 2012

Community Engagement Results

1. Pavement2. Bike Lanes

3. Multi-use Path

1. Pavement rehabilitation2. Bike lanes

3. Multi-use Path

Presented Three Concepts:

Page 6: West Plumb Lane Project Preliminary Design Public Information Meeting June 4, 2012

Preferred Enhancement:Multi-use Path, Parking One Side

Multi-use Path

Page 7: West Plumb Lane Project Preliminary Design Public Information Meeting June 4, 2012

Design Considerations

Address the needs of the community and provide a safe route for all users

Confine improvements to the existing right-of-way

Address traffic volume and excessive speeds

Evaluate possible safety improvements in the steep, curved section east of Homewood Drive

Maintain existing trees and rural character

Page 8: West Plumb Lane Project Preliminary Design Public Information Meeting June 4, 2012

Existing Conditions

Page 9: West Plumb Lane Project Preliminary Design Public Information Meeting June 4, 2012

Preferred Enhancement:Multi-use Path, Parking One Side

Page 10: West Plumb Lane Project Preliminary Design Public Information Meeting June 4, 2012

N

Multi-use Path, Parking One Side

Page 11: West Plumb Lane Project Preliminary Design Public Information Meeting June 4, 2012

N

Design ConsiderationsLandscaping, mailboxes, fences & parking

Page 12: West Plumb Lane Project Preliminary Design Public Information Meeting June 4, 2012

Design ConsiderationsDrainage Options

With Curb and Gutter, Reduced Landscaping Impact

With Drainage Swale, No Curb and Gutter

8’ 8’

50’ ROW

50’ ROW

Page 13: West Plumb Lane Project Preliminary Design Public Information Meeting June 4, 2012

Design ConsiderationsTraffic Calming and Speed

Plumb Lane Speed Limit Will Remain 25 MPH

Page 14: West Plumb Lane Project Preliminary Design Public Information Meeting June 4, 2012

Design ConsiderationsTMWA

Page 15: West Plumb Lane Project Preliminary Design Public Information Meeting June 4, 2012

Construction Schedule & Costs

$3.5 to $4.5 Million

12 weeks(Fuel Tax)

Item and Descriptio

n

UnitUnit C

ost

1.01 Remove existing and construct composite roadw ay structure section 1 SF

$5.00

2.01 Overexcavate unsuitable materials and replace w /imported aggregate base CY

$20.00

2.02 Overexcavate unsuitable materials and replace w /plantmix bituminous CF

$8.00

3.01 Remove existing and construct PCC sidew alk / median f la

tw ork

SF

$10.00

3.02 Remove existing and construct PCC pedestrian ramp

SF

$15.00

3.04 Remove existing and consturct PCC Type 1 curb and gutter

SF

$25.00

4.01 Install 4" solid yellow linear traff ic

paint pavement markings

LF

$0.25

4.02 Install 4" broken w hite linear traff ic

paint pavement markings

LF

$0.15

4.03 Install 4" solid w hite linear traff ic

paint pavement markings

LF

$0.15

4.04 Install 6" solid w hite linear traff ic

paint pavement markings

LF

$0.35

4.05 Install 8" solid w hite linear traff ic

paint pavement markings

LF

$0.50

4.06 Install 8" dotted w hite linear ptraff ic paint pavement m

arkings

LF

$0.50

4.07 Install 24" thermoplastic stop bar/crossw alk strip

ing

LF

$7.50

4.08 Install 8' thermoplastic "O

NLY" word symbol

EA

$140.00

4.09 Install 6' thermoplastic bike lane symbol and through arro

w

EA

$80.00

4.10 Install thermoplastic yield bar tr

iangle symbol

EA

$39.00

4.11 Install 8' thermoplastic rght tu

rn and left turn arro

w symbol

EA

$90.00

Engineer's

Estimate

It

em

Page 16: West Plumb Lane Project Preliminary Design Public Information Meeting June 4, 2012

How you can help tonight:

Provide your input on comment cards Multi-use path details (concrete color)? Drainage trouble spots? Interest in left turn lanes? Interest in pedestrian crossing? Interest in paved parking adjacent to property? Talk to the project team

We are here to listen to you. Please share your ideas with us!

Thank you!

Page 17: West Plumb Lane Project Preliminary Design Public Information Meeting June 4, 2012

Information Stations

Seven Stations Station 1: McCarran Boulevard to 3510 West

Plumb Lane Station 2: 3510 West Plumb Lane to Carter Drive Station 3: Carter Drive to Suda Way Station 4: Suda Way to Ferris Lane Station 5: City of Reno Station 6: NV Energy Station 7: Design Input

Page 18: West Plumb Lane Project Preliminary Design Public Information Meeting June 4, 2012

Questions?

Contact:Michele Dennis, PE, RTC Project Manager at (775) 335-1861

[email protected]