HEEL MANUFACTURING PROCESS FLO
Prepared by:-Atul
Kaushal
8/3/2019 Wheel Layout
2/14
Rim
Loading
Disc Loading Disc Positioningw.r.t Bolt hole
Rim Positioning
w.r.t Valve Hole
Rim & Disc Pre-
assemblingRim & Disc
Assembly
Welding Spatter
Cleaning
CalibrationROT Inspection
Visual
Inspection
WHEEL MANUFACTURING PROCESSFLOW
8/3/2019 Wheel Layout
3/14
Process:-Rim loading on rim conveyor
Process Objective:-To assemble the rimput rim on the conveyor.
Key points :-
1.Ensure the valve hole must be on downside.
2.Check the astatic defect (scoring
mark ,butt weld defect, valve hole&marking on front side, air leak test punch)
RIM LOADING:-
RIM LOADING
8/3/2019 Wheel Layout
4/14
Process:-Rim position as per drawing
Process Objective:-With help of the valvehole sensor do positioning the valve hole asper drawing.
Key points :-
1.Ensure the valve hole must be down side
2.Valve hole position must be as perdrawing.
RIM POSITIONING:-
RIM POSITIONING
8/3/2019 Wheel Layout
5/14
Process:-Disc loading on disc conveyor
Process Objective:-To assemble the discPut on conveyor.
Key points :-
1.Disc crown area must be on front side oras per picture.
2.Check the astatic defect(scratch/line
mark, bolt hole, vent hole damage)
DISC LOADING:-
DISC LOADING
8/3/2019 Wheel Layout
6/14
Process:-Disc positioning w.r.t to bolt
holeProcess Objective:-With help of bolt holesensor do positioning the disc as per drg.
Key points :-
1.Disc front side area must be on upperside.
DISC POSITIONING:-
DISC POSITIONING W.R.T
BOLT HOLE
8/3/2019 Wheel Layout
7/14
Process:-Disc & Rim pre-assembly
Process Objective:-Feed the disc in rimfor assy.
Key points :-
1.Disc bolt hole & rim valve hole positionmust be as per drawing.
DISC&RIM PRE-ASSEMBLY:-
DISC & RIM PRE-ASSEMBLY
8/3/2019 Wheel Layout
8/14
Process:-Disc & rim press fit operation
Process Objective:-Press the disc & rimwith help of hydraulic press as perdrawing.
Key points :-
1.Check the assy dimension as per spec.
2.Marking position on disc as per drawing,defect free in visual.
DISC&RIM ASSEMBLY:-
RIM & DISC ASSEMBLY
8/3/2019 Wheel Layout
9/14
Process:-MIG welding on wheel
Process Objective:-To joint the disc & rimdo MIG welding on wheel.
Key points :-1.Mig welding position as per drg.
2.Welding length ,weld penetration,porosity, undercut, weld shift to rim & disc
etc.
WELDING:-
WELDING
1
2
3
4
8/3/2019 Wheel Layout
10/14
Process:-Clean the weld spatter on wheel
Process Objective:-With help of chiselclean the all weld spatter.
Key points :-
1.No any spatter on weld & disc.
2.Weld defect porosity, undercut, pin hole,weld crack etc.
SPATTER CLEANING:-
SPATTER CLEANING
8/3/2019 Wheel Layout
11/14
Process:-Calibrate the wheel on
calibration m/cProcess Objective:-With help ofcalibration tool calibrate the wheel
Key points :-
1.Check the 4bolt hole pin must be in atool.
2.Wheel must be clean before thecalibration operation.
3.All 4spacer must be solid & locked.
4.Check the astatic defect (calibrationtool mark, bolt hole damage etc.)
CALIBRATION:-
CALIBRATION
8/3/2019 Wheel Layout
12/14
Process:-Runout checking on ROT m/c.
Process Objective:-Runout checking withhelp of ROT m/c.
Key points :-
1.Wheel front side must be on upper side.
2.Wheel ,roller & fixture must be clean.
3.Check the runout limit as per drawing.
ROT INSPECTION:-
RUN OUT TESTION M/C
8/3/2019 Wheel Layout
13/14
Process:-Wheel final inspection
Process Objective:-Wheel visual inspectionby Quality like dent mark ,mig welddefect, line mark, pin hole,weld crack etc.
Key points :-
1.Ensure the inspector having knowledgeabout Wheel defect( porosity, undercut,weld shift, tool mark etc.)
2.He must be know about MARU-A, safety& critical characteristics of wheel.
WHEEL INSPECTION:-
WHEEL INSPECTION
8/3/2019 Wheel Layout
14/14
THANK YOU