Upload
danny50
View
233
Download
0
Embed Size (px)
Citation preview
8/13/2019 Wip - Mepfs Checklists
1/12
FORM NO. : QAQC WIP 005.4.1
DATE PREPARED : CONTROL NO. :
AREA : ACTUAL INSPECTION DATE/TIME :
GRID LINE :
A.) Pipe Sleeving to Beams1. Materials Used
a. Rebars ( Horizontal )
b. Rebars ( Vertical )
c. Rebars ( Z-Bars )
2. Covering and Tagging
a. Covers @ every Pipe Sleeve
b. Painted Tagging "P" @ cover
3. Pipe to be Used
a. Schedule 20 B.I. Pipe
b. Coated by Primer Paint
B.) Pipe Sleeving to PC-Slab/Wall Casting Bed
1. Materials Used
a. Rebars ( Horizontal Trimmer )
b. Rebars ( Vertical Trimmer Bar )
2. Covering
a. Covering @ every Pipe Sleeve secured with tie wire
3. Layout
a. As per TSP
b. As per Survey Lay-outs
3. Pipe to be Used
a. Series 600 PVC Pipes
b. Size of Sleeve based on Pipes to be Penetrated
REMARKS :
PREPARED BY : INSPECTED BY : APPROVED BY :
LOCATION : NABAS, AKLANPIPE SLEEVINGCHECKLIST
PROJECT : NABAS WIND POWER PROJECT
CHECKLIST N/ANOYES REMARKS
CHECK THAT THE FOLLOWING COMPLY WITH APPROVED SUBMITTALS , FOR CONSTRUCTION DRAWINGS AND TECHNICALSPECIFICATIONS :
NOTE : This form must be submitted to The CQC TEAM (Operations), duly accomplished and signed by the corresponding Contractor's Personnel-in-Charge at least 24 hours before actual INSPECTION.
8/13/2019 Wip - Mepfs Checklists
2/12
FORM NO. : QAQC WIP 005.4.2
DATE PREPARED : CONTROL NO. :
AREA : ACTUAL INSPECTION DATE/TIME :
GRID LINE :
A. Preplanning1. Review design drawing for constructability,
interferences, problems for erection and scheduling.2. Preplan piping installation.3. Perform receiving inspection of piping materials.4. Ensure material is properly stored and maintained.5. Perform periodic material inventories and reorder
required material as necessary.6. Check building areas for possible interferences.7. Check that required piping sleeves and opening are
installed in walls & in floors prior to concrete placement.B. Installation
1. Monitor required field changes in piping systems andobtain req'd eng'g approvals prior to performing the work.
2. Ensure the work is performed per applicable projectprocedures.
3. Ensure that pipe connections do not transmit stress toequipment flanges and nozzles.
4. Ensure that exception reports are properly prepared and
processed.5. Ensure that changes which may result in interferences or
w/c may cause delays are coordinated w/ other disciplines.6. Review other discipline design drawings for possible
interferences and schedule impact.C. Testing
1. Ensure that installed pipe has been released for testing.
2. Ensure that posttest punchlist are completed and thatthe pipe is release for painting & or insulation, as specified.
3. Release the completed system to startup.
REMARKS :
PREPARED BY : INSPECTED BY : APPROVED BY :
NOTE : This form must be submitted to The CQC TEAM (Operations), duly accomplished and signed by the corresponding Contractor's Personnel-in-Charge at least 24 hours before actual INSPECTION.
(Subcon PIC) (PWEI Field Engineer) (PWEI Project Supervisor) (PWEI Project-in-Charge)
LARGE PIPE CHECKLIST
PROJECT : NABAS WIND POWER PROJECT
LOCATION : NABAS, AKLAN
CHECK THAT THE FOLLOWING COMPLY WITH APPROVED SUBMITTALS , FOR CONSTRUCTION DRAWINGS AND TECHNICALSPECIFICATIONS :
CHECKLIST YES NO N/A REMARKS
8/13/2019 Wip - Mepfs Checklists
3/12
FORM NO. : QAQC WIP 005.
DATE PREPARED : CONTROL NO. :
AREA : ACTUAL INSPECTION DATE/TIME :
GRID LINE :
A. Preplanning1. Preplan the piping installation.
2. Determine the small pipe to be field routed.
3. Determine the small pipe to be detailed on field prepared
isometrics.
4. Prepare small pipe layout and isometric drawings.
5. Check building areas for interferences prior to preparation of
isometrics.
6. Perform required receiving inspections.
7. Ensure pipe and pipe fittings are properly marked, identified
and stored.
8. Check that required piping sleeves and openings are
installed in walls floor prior to concrete placement.
9. Monitor drawing changes and ensure they are incorporated
in the fielddrawings.
10. Check that req'd project procedures have been prepared.
11. Review other discipline design drawings for possible
interferences and schedule impacts.
12. Ensure that changes w/c may result in interferences or w/c
may cause delays are coordinated w/ other disciplines.
B. Installations
1.Monitor required field changes in field routed piping systems
and update field drawings accordingly.2. Ensure the work is performed per applicable project
procedures.3. Ensure that pipe connections do not transmit stress to
equipment flanges and nozzles.4. Ensure that exception reports are properly prepared and
processed.5. Ensure that changes which may result in interferences or
w/h may cause delays are coordinated with other disciplines.6. Review other disciplines design drawings for possible
interferences and schedule impacts.
C. Testing
1. Ensure that installed pipe has been released for testing.
2. Ensure that posttest punchlist are completed and that pipe is released for painting and or insulation, as specified.
3. Released the completed system to start - up.
REMARKS :
NOTE : This form must be submitted to The CQC TEAM (Operations), duly accomplished and signed by the corresponding Contractor's Personnel-in-
SMALL PIPE CHECKLIST
PROJECT : NABAS WIND POWER PROJECT
LOCATION : NABAS, AKLAN
CHECK THAT THE FOLLOWING COMPLY WITH APPROVED SUBMITTALS , FOR CONSTRUCTION DRAWINGS AND TECHNICALSPECIFICATIONS :
CHECKLIST YES NO N/A REMARKS
8/13/2019 Wip - Mepfs Checklists
4/12
FORM NO. : QAQC WIP 005.
DATE PREPARED : CONTROL NO. :
AREA : ACTUAL INSPECTION DATE/TIME :
GRID LINE :
A. Storage
1. Maintain surveillance of the storage conditions of the insulation materials.
2. Check that material drawn from storage for application is dry and undamaged.
B. Preplanning
1. Verify that all required hydrostatic and non-destructive testing have been
performed prior to application of insulation.2. Ensure any required surface coating has been applied.
3. Pipe surface is free of moisture prior to application of insulation.
C. Installation
1. Check that correct type and thickness insulation is applied.
2. Check that the support fittings (banding straps, "S" and "J" clips, etc.) are of
the proper material.3. Where a vapor barrier is required, check that it is correctly applied to the proper
thickness and that its integrity is maintained throughout.4. Check that protective metal coverings are applied in a manner that underlying
insulation or vapor barrier is undamaged.5. Ensure that piping or equipment supports do not damage the insulation.
6. To isolate the effects of break-in insulation or vapor barrier, the barrier should
be sealed to the pipe at every fitting and at supports.7. All removable vessels heads and manways should be fitted with removable
insulation.8. When abrasive insulation material such as cellular glass is used on lines or
equipment subject to vibration, the inside surface should be coated to prevent
damage to the lines or equipment.9. When more than one layer is to be applied, check that: (a. All joints of the
previous layer are sealed prior to application of the next layer. b. All joints
between one layer and another are offset.)10. When insulation is beveled or otherwise terminated, the moisture barrier
should be folded over the end of the insulation and sealed.
11. Where insulation abuts flanges which are not to be insulated, the insulation
should be beveled a sufficient distance from the flange to permit removal of flangebolts without damage to insulation.
3. Released the completed system to start - up.
REMARKS :
NOTE : This form must be submitted to The CQC TEAM (Operations), duly accomplished and signed by the corresponding Contractor's Personnel-in-
CHECKLIST
PIPE INSULATIONCHECKLIST
PROJECT : NABAS WIND POWER PROJECT
LOCATION : NABAS, AKLAN
CHECK THAT THE FOLLOWING COMPLY WITH APPROVED SUBMITTALS , FOR CONSTRUCTION DRAWINGS AND TECHNICALSPECIFICATIONS :
YES NO N/A REMARKS
8/13/2019 Wip - Mepfs Checklists
5/12
FORM NO. : QAQC WIP 005.4.5
DATE PREPARED : CONTROL NO. :
AREA : ACTUAL INSPECTION DATE/TIME :
GRID LINE :
A. Preplanning1. Preplan the valve installation.
2. Perform required receiving inspection.3. Check that valves are properly handled, stored and
maintained.4. Check building areas for interference with valves
installation and operation.5. Verify that valves are the correct size, type, and pressure rating and are installed in their correct location and
orientation. (Read the manufacture tags and not thevendors tags to verify valves information.)
6. Perform req'd valves installation in-process inspections.7. Complete valve installation progress reporting.8. Perform periodic valve inventories and initiate field
purchases of valve if necessary.9. Monitor P&ID deviations and obtain required designs
approval for changes.10. Ensure that extra valve stem packing, bonnet gaskets,
pressure seals, plugs, and flange gaskets needed forrepairs are available.
11. Review piping design drawings and vendor valve detailsheets for compatibility including material and end preps.
12. Ensure required operating and setting instructions and
procedures are available.13. Check that operating & setting activities are performed
per applicable instructions, procedures and valve/ operator manufacturer instructions.
14. Ensure that changes which may results in interferenceor which may cause delays are coordinated withother disciplines.
B. Installations1. Ensure that required exception reports are prepared and
processed.2. Verify that required valve operator supports are installed.
3. Make sure measures are taken to protect valve bodiesand internal form heat effect of welding.
C. Testing1. Check valve pressures capacity and ensure it is greater
than the required piping pressure test.
REMARKS :
PREPARED BY : INSPECTED BY : APPROVED BY :
PIPING LINE VALVESCHECKLIST
PROJECT : NABAS WIND POWER PROJECT
LOCATION : NABAS, AKLAN
CHECK THAT THE FOLLOWING COMPLY WITH APPROVED SUBMITTALS , FOR CONSTRUCTION DRAWINGS AND TECHNICALSPECIFICATIONS :
CHECKLIST YES NO N/A REMARKS
NOTE : This form must be submitted to The CQC TEAM (Operations), duly accomplished and signed by the corresponding Contractor's Personnel-in-Charge at least 24 hours before actual INSPECTION.
(Subcon PIC) (PWEI Field Engineer) (PWEI Project Supervisor) (PWEI Project-in-Charge)
8/13/2019 Wip - Mepfs Checklists
6/12
FORM NO. : QAQC WIP 005.4.6
DATE PREPARED : CONTROL NO. :
AREA : ACTUAL INSPECTION DATE/TIME :
GRID LINE :
1. WIRING MATERIALS
a. Type, Color, Brandb. Batch Number c. Quantity
2. CONDUIT SET-UP
a. Embedded, Levels, Alignmentb. Pipe Size, Number, Spacing
3. WIRING INSTALLATIONS
a. Coupling, Conduits, Elbowsb. Clamps, Offsets, Tapes, Wire Color
4. PANEL BOARDS
a. Labelingb. Terminal Sizesc. Cable Ways, Sizes
d. Connections5. WIRING TERMINATION
a. Lightingsb. Power c. Homeruns
6. CLEANLINESS
Pipe Connections, Wires, Tapes, Fixtures, Accessories7. TESTING
a. Branch Circuitb. Groundingc. Zero - Load Protective Devicesd. Ratings
REMARKS :
PREPARED BY : INSPECTED BY : APPROVED BY :
DISTRIBUTION : Subcon Operation QA Document Controller Revision No. 001 (April 2013)
ELECTRICAL
DISTRIBUTION SYSTEMCHECKLIST
PROJECT : NABAS WIND POWER PROJECT
LOCATION : NABAS, AKLAN
CHECK THAT THE FOLLOWING COMPLY WITH APPROVED SUBMITTALS , FOR CONSTRUCTION DRAWINGS AND TECHNICALSPECIFICATIONS :
CHECKLIST YES NO N/A REMARKS
NOTE : This form must be submitted to The CQC TEAM (Operations), duly accomplished and signed by the corresponding Contractor's Personnel-in-Charge at least 24 hours before actual INSPECTION.
(Subcon PIC) (PWEI Field Engineer) (PWEI Project Supervisor) (PWEI Project-in-Charge)
8/13/2019 Wip - Mepfs Checklists
7/12
FORM NO. : QAQC WIP 005.4.7
DATE PREPARED : CONTROL NO. :
AREA : ACTUAL INSPECTION DATE/TIME :
GRID LINE :
1. CIRCUITRY
Location, Number of Points2. WIRING
a. Sizes of Wireb. Brandc. Color d. Type
3. WIRING DISTANCE
Wiring Size4. SPLIICNG
Crimping5. CONNECTION
a. Normal Power b. Emergency Power
6. WIRING INSTALLATIONa. Damagesb. Insulation
7. OTHERS
REMARKS :
PREPARED BY : INSPECTED BY : APPROVED BY :
DISTRIBUTION : Subcon Operation QA Document Controller Revision No. 001 (April 2013)
ELECTRICAL WIRINGSYSTEM FOR HV & LV
CHECKLIST
PROJECT : NABAS WIND POWER PROJECT
LOCATION : NABAS, AKLAN
CHECK THAT THE FOLLOWING COMPLY WITH APPROVED SUBMITTALS , FOR CONSTRUCTION DRAWINGS AND TECHNICALSPECIFICATIONS :
CHECKLIST YES NO N/A REMARKS
NOTE : This form must be submitted to The CQC TEAM (Operations), duly accomplished and signed by the corresponding Contractor's Personnel-in-Charge at least 24 hours before actual INSPECTION.
(Subcon PIC) (PWEI Field Engineer) (PWEI Project Supervisor) (PWEI Project-in-Charge)
8/13/2019 Wip - Mepfs Checklists
8/12
FORM NO. : QAQC WIP 005.4.8
DATE PREPARED : CONTROL NO. :
AREA : ACTUAL INSPECTION DATE/TIME :
GRID LINE :
1. POWER CONDUITS, BOXES & SUPPORTS
a. Wall Rough-insb. Slab rough-insc. Ceiling overhead
2. LIGHTING, CONDUITS, BOXES AND SUPPORTS
a. Wall Rough-insb. Slab rough-insc. Ceiling overhead
3. AUXILIARIES (Wall rough-ins and ceiling overhead)
a. Fire Detectionb. Securityc. CCTVd. BMSe. Telecomf. Lightning Protection
4. CABLE / LADDER TRAY
5. BUS DUCT INSTALLATION
6. RECEPTACLE WIRING
7. LIGHTING WIRING
8. SECURITY DEVICE WIRING
9. FIRE DETECTION / SUPPRESSION WIRING
10. CCTV WIRING (Wall rough-ins and ceiling overhead)
11. BMS WIRING
12. GROUNDING
13. TESTING
14. LIGHT FIXTURE INSTALLATION
15. DUCT BANKS
16. ELECTRICAL PITS
17. COMMUNICATION PITS
REMARKS :
PREPARED BY : INSPECTED BY : APPROVED BY :
DISTRIBUTION : Subcon Operation QA Document Controller Revision No. 001 (April 2013)
ELECTRICAL andAUXILIARIES CHECKLIST
PROJECT : NABAS WIND POWER PROJECT
LOCATION : NABAS, AKLAN
CHECK THAT THE FOLLOWING COMPLY WITH APPROVED SUBMITTALS , FOR CONSTRUCTION DRAWINGS AND TECHNICALSPECIFICATIONS :
CHECKLIST YES NO N/A REMARKS
NOTE : This form must be submitted to The CQC TEAM (Operations), duly accomplished and signed by the corresponding Contractor's Personnel-in-Charge at least 24 hours before actual INSPECTION.
(Subcon PIC) (PWEI Field Engineer) (PWEI Project Supervisor) (PWEI Project-in-Charge)
8/13/2019 Wip - Mepfs Checklists
9/12
FORM NO. : QAQC WIP 005.4.9
DATE PREPARED : CONTROL NO. :
AREA : ACTUAL INSPECTION DATE/TIME :
GRID LINE :
1. GROUND CABLE
a. Type of connection
b. Material typec. Location as per approved drawingd. Wire size
2. LIGHTING ARRESTOR
a. Material typeb. Bracing supportc. Location
3. GROUND PLATES
a. Installationb. Location as per approved drawingc. Material typed. Material size
4. GROUND PIT
a. Ground rod installationb. Location as per approved drawingc. intervalsd. Copper wire diameter e. Connection type
5. EARTH RESISTANCE TEST
Value
REMARKS :
PREPARED BY : INSPECTED BY : APPROVED BY :
DISTRIBUTION : Subcon Operation QA Document Controller Revision No. 001 (April 2013)
Electrical Grounding and
Lightning ProtectionInstallation CHECKLIST
PROJECT : NABAS WIND POWER PROJECT
LOCATION : NABAS, AKLAN
CHECK THAT THE FOLLOWING COMPLY WITH APPROVED SUBMITTALS , FOR CONSTRUCTION DRAWINGS AND TECHNICALSPECIFICATIONS :
CHECKLIST YES NO N/A REMARKS
NOTE : This form must be submitted to The CQC TEAM (Operations), duly accomplished and signed by the corresponding Contractor's Personnel-in-Charge at least 24 hours before actual INSPECTION.
(Subcon PIC) (PWEI Field Engineer) (PWEI Project Supervisor) (PWEI Project-in-Charge)
8/13/2019 Wip - Mepfs Checklists
10/12
FORM NO. : QAQC WIP 005.4.10
DATE PREPARED : CONTROL NO. :
AREA : ACTUAL INSPECTION DATE/TIME :
GRID LINE :
1. MATERIALS
a. Type, Size, Gauge, Brand2. WELDED JOINTS
a. Jointing Materialb. Tested (Ultrasonic)
3. HANGERS
a. Complete/Correct Spacingb. (Painted (Galvanized)c. Sized. Mountinge. Seismic Connection
4. FITTINGS/FIXTURES
a. Type, Size, Brand, Class5. FLANGE
a. Gasketb. Flange Material
6. CORROSION PROTECTION (UNDERGROUND)
a. Materialb. W orkmanship
7. PIPE LAYING
a. Alignment, Elevation8. TESTING
a. Leak Tested
REMARKS :
PREPARED BY : INSPECTED BY : APPROVED BY :
DISTRIBUTION : Subcon Operation QA Document Controller Revision No. 001 (April 2013)
SANITARY and RAINWATER PIPING CHECKLIST
PROJECT : NABAS WIND POWER PROJECT
LOCATION : NABAS, AKLAN
CHECK THAT THE FOLLOWING COMPLY WITH APPROVED SUBMITTALS , FOR CONSTRUCTION DRAWINGS AND TECHNICALSPECIFICATIONS :
CHECKLIST YES NO N/A REMARKS
NOTE : This form must be submitted to The CQC TEAM (Operations), duly accomplished and signed by the corresponding Contractor's Personnel-in-Charge at least 24 hours before actual INSPECTION.
(Subcon PIC) (PWEI Field Engineer) (PWEI Project Supervisor) (PWEI Project-in-Charge)
8/13/2019 Wip - Mepfs Checklists
11/12
FORM NO. : QAQC WIP 005.4.11
DATE PREPARED : CONTROL NO. :
AREA : ACTUAL INSPECTION DATE/TIME :
GRID LINE :
Water Closet Kitchen Faucet FITTINGS:
Shower Set w/ Mixer Floor Drain
Lavatory Sink Bath Tub w/ Drain
Lavatory Faucet Others
Kitchen Sink
1. MATERIALS
a. Type, Size, Gauge, Brand2. WELDED JOINTS
a. Jointing Materialb. Tested (Ultrasonic)
3. HANGERS
a. Complete/Correct Spacingb. (Painted (Galvanized)
c. Sized. Mountinge. Seismic Connection
4. FITTINGS/FIXTURES
a. Type, Size, Brand, Class5. FLANGE
a. Gasketb. Flange Material
6. CORROSION PROTECTION (UNDERGROUND)
a. Materialb. Workmanship
7. PIPE LAYING
a. Alignment, Elevation8. TESTING
a. Leak Testedb. Functionality Test Coducted
REMARKS :
PREPARED BY : INSPECTED BY : APPROVED BY :
DISTRIBUTION : Subcon Operation QA Document Controller Revision No. 001 (April 2013)
NOTE : This form must be submitted to The CQC TEAM (Operations), duly accomplished and signed by the corresponding Contractor's Personnel-in-Charge at least 24 hours before actual INSPECTION.
(Subcon PIC) (PWEI Field Engineer) (PWEI Project Supervisor) (PWEI Project-in-Charge)
FIXTURE
PLUMBING FIXTURES andFITTINGS CHECKLIST
PROJECT : NABAS WIND POWER PROJECT
LOCATION : NABAS, AKLAN
CHECK THAT THE FOLLOWING COMPLY WITH APPROVED SUBMITTALS , FOR CONSTRUCTION DRAWINGS AND TECHNICALSPECIFICATIONS :
CHECKLIST YES NO N/A REMARKS
8/13/2019 Wip - Mepfs Checklists
12/12
FORM NO. : QAQC WIP 005.4.12
DATE PREPARED : CONTROL NO. :
AREA : ACTUAL INSPECTION DATE/TIME :
GRID LINE :
1. MATERIALS
a. Type, Size, Gauge, Class, Brandb. Architectural
2. WELDED JOINTS
a. Welding, Capping, Grindingb. Testing (Ultrasonic)c. Markings
3. HANGERS
a. Complete (Spacing as per drawing)b. Size, Mounting, Seismic Connections
4. FITTINGS
a. Type, Size, Class, Brand5. FLANGE
a. Gasket, Bolt, Interval6. COUPLING
a. Complete, Correct Intervalb. Alignmentc. Brand
7. PIPE LAYING
a. Alignment, Elevation8. SWAY BRACES
a. Spacing9. PAINTING
a. Color b. Tagging
10. FIXTURES
a. Headsb. Line and Grade
11. TESTING
a. Leak Test (Zonal)b. System Testing and Commissioning)
REMARKS :
PREPARED BY : INSPECTED BY : APPROVED BY :
DISTRIBUTION : Subcon Operation QA Document Controller R i i N 001 (A il 2013)
SPRINKLER SYSTEMCHECKLIST
PROJECT : WEST SUPER BLOCK
LOCATION : 28th st., cor. 3rd ave., Crescent Park, West District, Bonifacio, Global City, Taguig
CHECK THAT THE FOLLOWING COMPLY WITH APPROVED SUBMITTALS , FOR CONSTRUCTION DRAWINGS AND TECHNICALSPECIFICATIONS :
CHECKLIST YES NO N/A REMARKS
NOTE : This form must be submitted to The CQC TEAM (Operations), duly accomplished and signed by the corresponding Contractor's Personnel-in-Charge at least 24 hours before actual INSPECTION.
(Subcon PIC) (MDC Field Engineer) (MDC Project Supervisor) (MDC Project-in-Charge)