16
WRAC Issues Workshop Acme Basin B Discharge Project Wellington Community Center January 23, 2006

WRAC Issues Workshop Acme Basin B Discharge Project Wellington Community Center January 23, 2006

  • Upload
    erica

  • View
    21

  • Download
    0

Embed Size (px)

DESCRIPTION

WRAC Issues Workshop Acme Basin B Discharge Project Wellington Community Center January 23, 2006. Everglades Restoration Acceler8 Projects. C-43 (Caloosahatchee River) West Reservoir EAA Reservoir Phase 1 / Boles & Cross Canals EAA Stormwater Treatment Area Expansion - PowerPoint PPT Presentation

Citation preview

Page 1: WRAC Issues Workshop  Acme Basin B Discharge Project  Wellington Community Center January 23, 2006

WRAC Issues Workshop

Acme Basin B Discharge Project

Wellington Community Center

January 23, 2006

Page 2: WRAC Issues Workshop  Acme Basin B Discharge Project  Wellington Community Center January 23, 2006

1. C-43 (Caloosahatchee River) West Reservoir

2. EAA Reservoir Phase 1 / Boles & Cross Canals

3. EAA Stormwater Treatment Area Expansion

4. Picayune Strand (Southern Golden Gate Estates)

5. C-44 (St. Lucie Canal) Reservoir / STA

6. Water Preserve Areas

• Acme Basin B Discharge Project

• Site 1 Impoundment

• C-9 Impoundment

• C-11 Impoundment

• WCA-3A/3B Seepage Management

7. Biscayne Bay Coastal Wetlands Phase 1

8. C-111 Spreader Canal

Everglades Restoration Acceler8 Projects

Page 3: WRAC Issues Workshop  Acme Basin B Discharge Project  Wellington Community Center January 23, 2006

Acme Basin B Discharge Project

Location

Page 4: WRAC Issues Workshop  Acme Basin B Discharge Project  Wellington Community Center January 23, 2006

C-51 CANAL

PUMP #1

PUMP #2

S-319

S-362

WCA-1

LOXAHATCHEE NATIONALWILDLIFE REFUGE

BASIN A

BASIN B

40 72 42 73 44 45SECTION

24

Acme Basin B Discharge Project

Current Conditions

C-1

PUMP #4 PUMP #3 PUMP #6

STA-1E

Southern Blvd.S-155A

S-361

Page 5: WRAC Issues Workshop  Acme Basin B Discharge Project  Wellington Community Center January 23, 2006

89

152

10

0

20

40

60

80

100

120

140

160

180

Acme Pump #1 Acme Pump #2 EFA Requirement

Concentr

atio

n (

ppb)

Flow-Weighted Mean Concentration, WY02 (May 1, 2001 through April 30, 2002)

Source: 2003 Everglades Consolidated Report, Chapter 8B: Everglades Stormwater Program

Acme Basin B Phosphorous Discharges

Acme Basin B Discharge Project The Problem with Current Conditions

Page 6: WRAC Issues Workshop  Acme Basin B Discharge Project  Wellington Community Center January 23, 2006

Requires:

1. Improvements to C-1 canal to increase conveyance capacity and connect the C-1 canal to the C-51 Canal

2. Construction of new pump station AcmePS7 to pump from C-1 canal into C-51 Canal

3. Construction of detention area in Section 24 for temporary offline storage

4. Construction of new pump station AcmePS24 to fill the Section 24 detention area

Acme Basin B Discharge Project

Project Purpose

Acme Pumps #1 and #2 must be shut down on December 31, 2006 to comply with the Everglades Forever Act. Water in Acme Basin B must be re-routed north through Acme Basin A and discharged into the C-51 canal.

Page 7: WRAC Issues Workshop  Acme Basin B Discharge Project  Wellington Community Center January 23, 2006

PUMP #1

PUMP #2

PUMP #4 PUMP #3 PUMP #6S-319

S-362

WCA-1

LOXAHATCHEE NATIONALWILDLIFE REFUGE

40

NEW PUMP #7 (220 cfs)

C-51 CANAL

BASIN A

BASIN B

STA-1E

Southern Blvd.

Acme Basin B Discharge Project

Project Features

C-1

CA

NA

L

SEC 24

NEW PUMP #24 (200 cfs)

PUMP #8

S-361

S-155A

Page 8: WRAC Issues Workshop  Acme Basin B Discharge Project  Wellington Community Center January 23, 2006

• C-1 Canal Improvements

– 3 miles of modified section for 67 to 220 cfs conveyance capacity

– Two 84” culverts at FPL crossing

– Meets DOT setback requirements for Flying Cow Road

• Pump Station AcmePS7

– Connects C-1 to C-51 canal

– 220 cfs (three 110 cfs pumps)

– Diesel

– Includes gravity discharge bay

Acme Basin B Discharge Project

C-1 Canal Improvements and AcmePS7

Page 9: WRAC Issues Workshop  Acme Basin B Discharge Project  Wellington Community Center January 23, 2006

• Section 24

– Converts 365 acres of agricultural land to impoundment with upland areas and tree islands

– Storage of up to 5 feet of water (1,028 ac-ft)

– Two gated culverts (100 cfs each) for inflow/outflow

• Pump Station AcmePS24

– Inflow pump station

– 200 cfs (three 100 cfs pumps)

– Diesel

Acme Basin B Discharge Project

Section 24 and AcmePS24

Page 10: WRAC Issues Workshop  Acme Basin B Discharge Project  Wellington Community Center January 23, 2006
Page 11: WRAC Issues Workshop  Acme Basin B Discharge Project  Wellington Community Center January 23, 2006

Section 24 with additional

recreational components

Page 12: WRAC Issues Workshop  Acme Basin B Discharge Project  Wellington Community Center January 23, 2006

• C-1 canal improvements and pump station AcmePS7– Allows Basin B water to be conveyed to the C-51 canal

and STA-1E

• Section 24 and AcmePS24– Provides temporary offline storage of 1,028 ac-ft of water

• Maintains flood protection in Acme Basin B• Reduces phosphorous load to C-51 canal / STA-1E• Potential water supply

– Provides a buffer between natural and developed areas• Converts 365 acres of agricultural land to upland and open water

habitat

– Provides recreational opportunities• Walking trails, overlooks, equestrian trails

Acme Basin B Discharge Project

Project Benefits

Page 13: WRAC Issues Workshop  Acme Basin B Discharge Project  Wellington Community Center January 23, 2006

• Required C-1 Canal modifications are less than BODR– Modeling indicates that 220 cfs is not needed along entire length – flow incrementally

increases from 67 cfs at Structure #40 to 220 cfs at AcmePS7

• Realignment of Flying Cow Road minimized by using curb & gutter, guardrail, and steeper canal slopes

– Reduces cost

• AcmePS7 was moved 1,000 ft south from C-51 canal to near FPL crossing– Moves pump station away from residences

• AcmePS7 equipped with gravity discharge bay– Reduces cost of operation

• Pump stations will be diesel not electric– To meet District standards

• Section 24 primary purpose changed from passive wetland to detention area– Maintains flood attenuation and level of service locally and in the C-51 Canal

– Temporary storage provides regional benefits

– Reduces phosphorus load to C-51 Canal / STA-1E

• Section 24 seepage canal added– Protects against groundwater mounding

Acme Basin B Discharge Project

Design Modifications After BODR / August 2005 Workshop

Page 14: WRAC Issues Workshop  Acme Basin B Discharge Project  Wellington Community Center January 23, 2006

2004

Timeline – Calendar Years

2005 2006 2007 2008

C-1 Canal and AcmePS7

Section 24 and AcmePS24

Planning and BODR complete Sept 2005

Acme Basin B Discharge Project

Schedule

Design complete February 2006

Procurement complete April 2006

Construction complete Nov 2006

Planning and BODR complete Sept 2005

Design complete March 2006

Procurement complete May 2006

Construction Phase 1 operational Dec 2006

Phase 2 (landscaping, recreational) complete May 2007

Page 15: WRAC Issues Workshop  Acme Basin B Discharge Project  Wellington Community Center January 23, 2006

Acme Basin B Discharge Project

Opinion of Probable Cost

C-1 Canal $1.4M

AcmePS7 $4.2M

Sec 24 $6.3M

AcmePS24 $3.8M

Design and Admin $2.6M

SUBTOTAL $18.3M

Sec 24 Recreation $1.0M*

Sec 24 Real Estate $4.1M

TOTAL $23.4M

* = alternate funding sources

Page 16: WRAC Issues Workshop  Acme Basin B Discharge Project  Wellington Community Center January 23, 2006

PUMP #1

PUMP #2

PUMP #4 PUMP #3 PUMP #6S-319

S-362

WCA-1

LOXAHATCHEE NATIONALWILDLIFE REFUGE

40

NEW PUMP #7 (220 cfs)

C-51 CANAL

BASIN A

BASIN B

STA-1E

Southern Blvd.

Acme Basin B Discharge Project

Questions?

C-1

CA

NA

L

SEC 24

NEW PUMP #24 (200 cfs)

PUMP #8

S-361

S-155A