ID Task
Mode
Task Name Duration Start Finish
0 Residential Construction
152 days Wed 4/27/16
Thu 11/24/16
1 General Conditions 21 days Wed 4/27/16Wed 5/25/16
2 Finalize plans and develop estimate with owner, architect
20 days Wed 4/27/16
Tue 5/24/16
3 Sign contract and notice to proceed
1 day Wed 5/25/16
Wed 5/25/16
4 Apply for Permits
0 days Wed 5/25/16
Wed 5/25/16
5 Secure foundation permit
0 days Wed 5/25/16
Wed 5/25/16
6 Secure framing permit
0 days Wed 5/25/16
Wed 5/25/16
7 Secure electrical permit
0 days Wed 5/25/16
Wed 5/25/16
8 Secure plumbing permit
0 days Wed 5/25/16
Wed 5/25/16
9 Secure HVAC permit
0 days Wed 5/25/16
Wed 5/25/16
General contractor[50%],Architect[50%],Owner[12%],Mortgage lender[12%]
General contractor,Architect,Owner,Mortgage lender
5/25
5/25
5/25
5/25
5/25
5/25
S T M F T S W S T M
Mar 13, '16 Apr 10, '16 May 8, '16 Jun 5, '16 Jul 3, '16
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 1
Project: Residential Constructio
Date: Wed 4/27/16
ID Task
Mode
Task Name Duration Start Finish
10 Secure miscellaneouspermits
0 days Wed 5/25/16
Wed 5/25/16
11 Site Work 3 days Thu 5/26/16 Mon 5/30/16
12 Clear and grub lot
1 day Thu 5/26/16 Thu 5/26/16
13 Install temporary power service
1 day Fri 5/27/16 Fri 5/27/16
14 Install underground utilities
1 day Mon 5/30/16
Mon 5/30/16
15 Foundation 42 days Tue 5/31/16 Wed 7/27/16
16 Excavate for foundations
3 days Tue 5/31/16 Thu 6/2/16
17 Form basement walls
13 days Fri 6/3/16 Tue 6/21/16
18 Place concrete for foundations & basement walls
12 days Wed 6/22/16
Thu 7/7/16
19 Cure basement walls for 7 days
7 days Fri 7/8/16 Mon 7/18/16
20 Strip basement wall forms
2 days Tue 7/19/16 Wed 7/20/16
21 Waterproof/insulatebasement walls
2 days Thu 7/21/16 Fri 7/22/16
5/25
Site excavation contractor
Electric company
Electric contractor,Plumbing contractor
Site excavation contractor
Concrete contractor
Concrete contractor
Concrete contractor
Concrete contractor
S T M F T S W S T M
Mar 13, '16 Apr 10, '16 May 8, '16 Jun 5, '16 Jul 3, '16
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 2
Project: Residential Constructio
Date: Wed 4/27/16
ID Task
Mode
Task Name Duration Start Finish
22 Perform foundation inspection
1 day Mon 7/25/16
Mon 7/25/16
23 Backfill foundation
2 days Tue 7/26/16 Wed 7/27/16
24 Framing 22 days Thu 7/28/16 Fri 8/26/16
25 Install 1st floor joists
2 days Thu 7/28/16 Fri 7/29/16
26 Lay 1st floor decking
2 days Mon 8/1/16 Tue 8/2/16
27 Frame 1st floor walls
4 days Wed 8/3/16 Mon 8/8/16
28 Frame 1st floor corners
1 day Tue 8/9/16 Tue 8/9/16
29 Install 2nd floor joists
2 days Wed 8/10/16
Thu 8/11/16
30 Frame 2nd floor decking
2 days Fri 8/12/16 Mon 8/15/16
31 Frame 2nd floor walls
3 days Tue 8/16/16 Thu 8/18/16
32 Frame 2nd floor corners
2 days Fri 8/19/16 Mon 8/22/16
33 Complete roof framing
3 days Tue 8/23/16 Thu 8/25/16
34 Conduct framinginspection
1 day Fri 8/26/16 Fri 8/26/16
Inspector
Site excavation contractor
Framing contractor
Framing contractor
Framing contractor
Framing contractor
Framing contractor
Framing contractor
Framing contractor
Framing contractor
Framing contractor
Inspector
S T M F T S W S T M
Mar 13, '16 Apr 10, '16 May 8, '16 Jun 5, '16 Jul 3, '16
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 3
Project: Residential Constructio
Date: Wed 4/27/16
ID Task
Mode
Task Name Duration Start Finish
35 Dry In 22 days Fri 8/26/16 Mon 9/26/16
36 Install 1st floor sheathing
3 days Mon 8/29/16
Wed 8/31/16
37 Install 2nd floor sheathing
3 days Thu 9/1/16 Mon 9/5/16
38 Install roof decking
3 days Fri 8/26/16 Tue 8/30/16
39 Install felt, flashing and shingles
3 days Tue 9/13/16 Thu 9/15/16
40 Hang 1st floor exterior doors
1 day Fri 9/16/16 Fri 9/16/16
41 Install 1st floor windows
3 days Mon 9/19/16
Wed 9/21/16
42 Install 2nd floor windows
3 days Thu 9/22/16 Mon 9/26/16
43 Exterior Finishes 19 days Tue 9/27/16 Fri 10/21/16
44 Complete exterior brick
16 days Tue 9/27/16 Tue 10/18/16
45 Complete exterior siding
3 days Wed 10/19/16
Fri 10/21/16
46 Utility Rough-B97Ins and Complete Concrete
21 days Wed 8/31/16
Wed 9/28/16
47 Rough-in plumbing
5 days Tue 9/6/16 Mon 9/12/16
Framing contractor
Framing contractor
Framing contractor
Roofing contractor
Framing contractor
Framing contractor
Framing contractor
Masonry contractor
Plumbing contractor
S T M F T S W S T M
Mar 13, '16 Apr 10, '16 May 8, '16 Jun 5, '16 Jul 3, '16
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 4
Project: Residential Constructio
Date: Wed 4/27/16
ID Task
Mode
Task Name Duration Start Finish
48 Conduct rough-in plumbing inspection
1 day Tue 9/13/16 Tue 9/13/16
49 Place concrete for basement floor
11 days Wed 9/14/16
Wed 9/28/16
50 Rough-in electrical
5 days Tue 9/6/16 Mon 9/12/16
51 Conduct rough-in electrical inspection
1 day Tue 9/13/16 Tue 9/13/16
52 Rough-in HVAC 3 days Wed 9/14/16Fri 9/16/16
53 Conduct rough-in HVAC inspection
1 day Mon 9/19/16
Mon 9/19/16
54 Rough-in communication - phone, cable, computer, alarm
2 days Wed 8/31/16
Thu 9/1/16
55 Interior Finishes 30 days Tue 9/27/16 Mon 11/7/16
56 Insulation 11 days Tue 9/27/16 Tue 10/11/16
57 Place wall insulation - 1st floor
1 day Tue 9/27/16 Tue 9/27/16
Inspector
Concrete contractor
Electric contractor
Inspector
Heating and AC contractor
Inspector
Electric contractor
Insulation contractor
S T M F T S W S T M
Mar 13, '16 Apr 10, '16 May 8, '16 Jun 5, '16 Jul 3, '16
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 5
Project: Residential Constructio
Date: Wed 4/27/16
ID Task
Mode
Task Name Duration Start Finish
58 Place wall insulation - 2nd floor
1 day Wed 9/28/16
Wed 9/28/16
59 Place ceiling insulation - 2nd floor
1 day Mon 10/10/16
Mon 10/10/16
60 Conduct insulation inspection
1 day Tue 10/11/16
Tue 10/11/16
61 Drywall 9 days Wed 9/28/16Mon 10/10/16
62 Install drywall- 1st floor walls
2 days Wed 9/28/16
Thu 9/29/16
63 Install drywall- 1st floor overhead
2 days Fri 9/30/16 Mon 10/3/16
64 Install drywall2nd floor walls
2 days Tue 10/4/16 Wed 10/5/16
65 Install drywall2nd floor overhead
2 days Thu 10/6/16 Fri 10/7/16
66 Tape and float1st floor drywall
1 day Tue 10/4/16 Tue 10/4/16
Insulation contractor
Insulation contractor
Inspector
Drywall contractor
Drywall contractor
Drywall contractor
Drywall contractor
Drywall contractor
S T M F T S W S T M
Mar 13, '16 Apr 10, '16 May 8, '16 Jun 5, '16 Jul 3, '16
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 6
Project: Residential Constructio
Date: Wed 4/27/16
ID Task
Mode
Task Name Duration Start Finish
67 Tape and float2nd floor drywall
1 day Mon 10/10/16
Mon 10/10/16
68 Paint and Wallpaper
17 days Wed 10/5/16
Thu 10/27/16
69 Texture all except entry and kitchen - 1st floor
1 day Wed 10/5/16
Wed 10/5/16
70 Paint all except entry and kitchen - 1st floor
1 day Thu 10/6/16 Thu 10/6/16
71 Hang wallpaper entry and kitchen - 1st floor
1 day Fri 10/7/16 Fri 10/7/16
72 Texture all - 2nd floor
1 day Thu 10/6/16 Thu 10/6/16
73 Paint all - 2nd floor
1 day Fri 10/7/16 Fri 10/7/16
74 Paint exterior siding & trim work
4 days Mon 10/24/16
Thu 10/27/16
75 Cabinets 6 days Mon 10/10/16Mon 10/17/16
Drywall contractor
Painting contractor
Painting contractor
Painting contractor
Painting contractor
Painting contractor
S T M F T S W S T M
Mar 13, '16 Apr 10, '16 May 8, '16 Jun 5, '16 Jul 3, '16
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 7
Project: Residential Constructio
Date: Wed 4/27/16
ID Task
Mode
Task Name Duration Start Finish
76 Install 1st floor - kitchencabinets
2 days Mon 10/10/16
Tue 10/11/16
77 Install 1st floor - master bath and guest cabinets
1 day Wed 10/12/16
Wed 10/12/16
78 Install 2nd floor - hall bath and private bath cabinets
1 day Thu 10/13/16
Thu 10/13/16
79 Install chair rails, crown moldings, trim
2 days Fri 10/14/16 Mon 10/17/16
80 Finish Plumbing 6 days Wed 10/12/16Wed 10/19/16
81 Complete 1st floor - kitchenplumbing
1 day Wed 10/12/16
Wed 10/12/16
82 Complete 1st floor - master bath and guest plumbing
2 days Thu 10/13/16
Fri 10/14/16
Finish carpentry contractor
Finish carpentry contractor
Finish carpentry contractor
Finish carpentry contractor
Plumbing contractor
Plumbing contractor
S T M F T S W S T M
Mar 13, '16 Apr 10, '16 May 8, '16 Jun 5, '16 Jul 3, '16
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 8
Project: Residential Constructio
Date: Wed 4/27/16
ID Task
Mode
Task Name Duration Start Finish
83 Complete 2ndfloor - hall bath and private bath plumbing
2 days Mon 10/17/16
Tue 10/18/16
84 Conduct finishplumbing inspection
1 day Wed 10/19/16
Wed 10/19/16
85 Finish Electrical 3 days Wed 10/19/16Fri 10/21/16
86 Complete 1st floor circuits to service panel
1 day Wed 10/19/16
Wed 10/19/16
87 Complete 2ndfloor circuits to service panel
1 day Thu 10/20/16
Thu 10/20/16
88 Conduct finishelectrical inspection
1 day Fri 10/21/16 Fri 10/21/16
Plumbing contractorS T M F T S W S T M
Mar 13, '16 Apr 10, '16 May 8, '16 Jun 5, '16 Jul 3, '16
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 9
Project: Residential Constructio
Date: Wed 4/27/16
ID Task
Mode
Task Name Duration Start Finish
89 Complete communicationswiring - phone, cable, computer, alarm
2 days Thu 10/20/16
Fri 10/21/16
90 Finish HVAC 3 days Mon 10/24/16Wed 10/26/16
91 Complete 1st floor - zone 1 HVAC
1 day Mon 10/24/16
Mon 10/24/16
92 Complete 2ndfloor - zone 2 HVAC
1 day Tue 10/25/16
Tue 10/25/16
93 Conduct HVAC inspection
1 day Wed 10/26/16
Wed 10/26/16
94 Carpet, Tile and Appliances
8 days Thu 10/27/16
Mon 11/7/16
95 Tile entry, kitchen and baths
3 days Thu 10/27/16
Mon 10/31/16
96 Carpet 1st floor
2 days Tue 11/1/16 Wed 11/2/16
97 Carpet 2nd floor
2 days Thu 11/3/16 Fri 11/4/16
98 Install appliances
1 day Mon 11/7/16
Mon 11/7/16
S T M F T S W S T M
Mar 13, '16 Apr 10, '16 May 8, '16 Jun 5, '16 Jul 3, '16
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 10
Project: Residential Constructio
Date: Wed 4/27/16
ID Task
Mode
Task Name Duration Start Finish
99 Landscaping and Grounds Work
12 days Fri 10/28/16 Mon 11/14/16
100 Pour concrete driveway and sidewalks
2 days Fri 10/28/16 Mon 10/31/16
101 Install backyard fence
2 days Tue 11/8/16 Wed 11/9/16
102 Sod and complete plantings - front yard
2 days Thu 11/10/16
Fri 11/11/16
103 Sod and complete plantings - backyard
1 day Mon 11/14/16
Mon 11/14/16
104 Final Acceptance 8 days Tue 11/15/16Thu 11/24/16
105 Complete final inspection for certificate of occupancy
1 day Tue 11/15/16
Tue 11/15/16
106 Cleanup for occupancy
1 day Wed 11/16/16
Wed 11/16/16
107 Perform final walk-through inspection
1 day Thu 11/17/16
Thu 11/17/16
S T M F T S W S T M
Mar 13, '16 Apr 10, '16 May 8, '16 Jun 5, '16 Jul 3, '16
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 11
Project: Residential Constructio
Date: Wed 4/27/16
ID Task
Mode
Task Name Duration Start Finish
108 Complete punchlist items
5 days Fri 11/18/16 Thu 11/24/16
S T M F T S W S T M
Mar 13, '16 Apr 10, '16 May 8, '16 Jun 5, '16 Jul 3, '16
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 12
Project: Residential Constructio
Date: Wed 4/27/16
General contractor[50%],Architect[50%],Owner[12%],Mortgage lender[12%]
General contractor,Architect,Owner,Mortgage lender
5/25
5/25
5/25
5/25
5/25
5/25
M F T S W S T M F T S W S T M F T S W S
Jul 3, '16 Jul 31, '16 Aug 28, '16 Sep 25, '16 Oct 23, '16 Nov 20, '16 Dec 18, '16 Jan 15, '17
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 13
Project: Residential Constructio
Date: Wed 4/27/16
5/25
Site excavation contractor
Electric company
Electric contractor,Plumbing contractor
Site excavation contractor
Concrete contractor
Concrete contractor
Concrete contractor
Concrete contractor
M F T S W S T M F T S W S T M F T S W S
Jul 3, '16 Jul 31, '16 Aug 28, '16 Sep 25, '16 Oct 23, '16 Nov 20, '16 Dec 18, '16 Jan 15, '17
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 14
Project: Residential Constructio
Date: Wed 4/27/16
Inspector
Site excavation contractor
Framing contractor
Framing contractor
Framing contractor
Framing contractor
Framing contractor
Framing contractor
Framing contractor
Framing contractor
Framing contractor
Inspector
M F T S W S T M F T S W S T M F T S W S
Jul 3, '16 Jul 31, '16 Aug 28, '16 Sep 25, '16 Oct 23, '16 Nov 20, '16 Dec 18, '16 Jan 15, '17
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 15
Project: Residential Constructio
Date: Wed 4/27/16
Framing contractor
Framing contractor
Framing contractor
Roofing contractor
Framing contractor
Framing contractor
Framing contractor
Masonry contractor
Framing contractor
Plumbing contractor
M F T S W S T M F T S W S T M F T S W S
Jul 3, '16 Jul 31, '16 Aug 28, '16 Sep 25, '16 Oct 23, '16 Nov 20, '16 Dec 18, '16 Jan 15, '17
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 16
Project: Residential Constructio
Date: Wed 4/27/16
Inspector
Concrete contractor
Electric contractor
Inspector
Heating and AC contractor
Inspector
Electric contractor
Insulation contractor
M F T S W S T M F T S W S T M F T S W S
Jul 3, '16 Jul 31, '16 Aug 28, '16 Sep 25, '16 Oct 23, '16 Nov 20, '16 Dec 18, '16 Jan 15, '17
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 17
Project: Residential Constructio
Date: Wed 4/27/16
Insulation contractor
Insulation contractor
Inspector
Drywall contractor
Drywall contractor
Drywall contractor
Drywall contractor
Drywall contractor
M F T S W S T M F T S W S T M F T S W S
Jul 3, '16 Jul 31, '16 Aug 28, '16 Sep 25, '16 Oct 23, '16 Nov 20, '16 Dec 18, '16 Jan 15, '17
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 18
Project: Residential Constructio
Date: Wed 4/27/16
Drywall contractor
Painting contractor
Painting contractor
Painting contractor
Painting contractor
Painting contractor
Painting contractor
M F T S W S T M F T S W S T M F T S W S
Jul 3, '16 Jul 31, '16 Aug 28, '16 Sep 25, '16 Oct 23, '16 Nov 20, '16 Dec 18, '16 Jan 15, '17
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 19
Project: Residential Constructio
Date: Wed 4/27/16
Finish carpentry contractor
Finish carpentry contractor
Finish carpentry contractor
Finish carpentry contractor
Plumbing contractor
Plumbing contractor
M F T S W S T M F T S W S T M F T S W S
Jul 3, '16 Jul 31, '16 Aug 28, '16 Sep 25, '16 Oct 23, '16 Nov 20, '16 Dec 18, '16 Jan 15, '17
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 20
Project: Residential Constructio
Date: Wed 4/27/16
Plumbing contractor
Inspector
Electric contractor
Electric contractor
Inspector
M F T S W S T M F T S W S T M F T S W S
Jul 3, '16 Jul 31, '16 Aug 28, '16 Sep 25, '16 Oct 23, '16 Nov 20, '16 Dec 18, '16 Jan 15, '17
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 21
Project: Residential Constructio
Date: Wed 4/27/16
Electric contractor
Heating and AC contractor
Heating and AC contractor
Inspector
Flooring contractor
Flooring contractor
Flooring contractor
Appliance contractor
M F T S W S T M F T S W S T M F T S W S
Jul 3, '16 Jul 31, '16 Aug 28, '16 Sep 25, '16 Oct 23, '16 Nov 20, '16 Dec 18, '16 Jan 15, '17
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 22
Project: Residential Constructio
Date: Wed 4/27/16
Concrete contractor
Fencing contractor
Landscape contractor
Landscape contractor
Inspector
Maid service
Owner
M F T S W S T M F T S W S T M F T S W S
Jul 3, '16 Jul 31, '16 Aug 28, '16 Sep 25, '16 Oct 23, '16 Nov 20, '16 Dec 18, '16 Jan 15, '17
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 23
Project: Residential Constructio
Date: Wed 4/27/16
General contractorM F T S W S T M F T S W S T M F T S W S
Jul 3, '16 Jul 31, '16 Aug 28, '16 Sep 25, '16 Oct 23, '16 Nov 20, '16 Dec 18, '16 Jan 15, '17
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 24
Project: Residential Constructio
Date: Wed 4/27/16