Click here to load reader
Upload
energytrustor
View
1.251
Download
0
Embed Size (px)
Citation preview
Energy Trust New Buildings Allies for Efficiency Chemeketa Community Colleges Path to Net Zero June 4th, 2015
Allies for Efficiency Training Series Organized by the New Buildings program
Focus on high-performance buildings
Continuing Education Credits (AIA and CCB)
Registration priority for New Buildings Trade and Design Allies
Trainings & Education
Upcoming Trainings and Events August 6th Occupant Cx: Learning from
Occupants to Improve Buildings Designs
October 27th Advance Envelope Design
Chemeketa Community Colleges Health Science Complex:
Path to Net Zero PRESENTED BY: Nick Collins PAE Jon Wiener SRG Partnership Jerry Vessello Chemeketa Community College Patrick Rank Lease Crutcher Lewis
Project Overview Passive Strategies Design Process Building It BREAK Lessons Learned & Advice Resources Q&A
Agenda
Summarize the passive cooling, heating, ventilation and lighting strategies utilized in this project
Understand and explain the value of room-level metering data showing energy usage and ambient temperature
Identify technical challenges in the projects design and construction
Learn how to participate in Energy Trust of Oregons new Path to Net Zero offering
Learning Objectives The Why
Project Overview Chemeketa Community
Colleges Health Science Complex
Salem, OR 72,000 sf new construction
$285/sf Path to Net Zero
Saves $47,000/yr
and ESLB, RACI & InSpec
The Team
Salem, OR Health Science Complex
1st Floor Health Science Complex
2nd Floor Health Science Complex
Main Entry
Native American Garden
Lobby/Student Gathering
Faculty Office Suite
0
20
40
60
80
100
120
Tem
pera
ture
(F
)
Daily Temperature Range Salem, Oregon
Climate Willamette Valley Temperature
Summer Design 90F
Average Low
Average High
Winter Design 22F
Jan Feb April May Mar Jun July Aug Sep Oct Nov Dec
Reduce Loads
Night Flush
Added Mass
Comfort Zone
Surface Temperature
78F
Room Temperature
82F
Air Flow 100 FPM
Daylighting
It All Adds Up
Integrated Design
Image courtesy of Lincoln Barbour Photo
Top Lighting
Image courtesy of Lincoln Barbour Photo
Side Lighting & Shaft
Lillis Business School
Mt Angel Abbey
Mt Angel Abbey
Shattuck Hall
Shattuck Hall
10 Years of Refinement
Design Process Ensuring It Will Work
Shading Studies
Glazing Studies
50
55
60
65
70
75
80
85
90
95
0
1,000
2,000
3,000
4,000
5,000
6,000
7,000
F
Btu
h
Window Comparison- Second Floor Classroom (July 1, 2013)
Solarban 60, no shades Solarban 60, shades Solarban 70, shades OAT
50
55
60
65
70
75
80
85
90
95
0
1,000
2,000
3,000
4,000
5,000
6,000
7,000
F
Btu
h
Window Comparison- Second Floor Classroom (July 1, 2013)
Solarban 60, no shades Solarban 60, shades Solarban 70, shades OAT
Glazing Studies
50
55
60
65
70
75
80
85
90
95
0
1,000
2,000
3,000
4,000
5,000
6,000
7,000
F
Btu
h
Window Comparison- Second Floor Classroom (July 1, 2013)
Solarban 60, no shades Solarban 60, shades Solarban 70, shades OAT
Glazing Studies
Daylighting Studies
Chemeketa Health Sciences
Classroom Air Flow Model
Visioning Windows (air inlets)
Interior Wall to
Adjacent Room
Interior Wall to Hallway
Exterior Wall
Classroom 2nd Floor
Air Shaft
Comfort
Design Process
156
81
156 151
16
1
19 14
0
20
40
60
80
100
120
140
160
180
200
Baseline Two MassWalls
2 TurbineVentilators
Thick Slab
Hou
rs P
er Y
ear
Hours Out of Range
Over 88
83-88
Baseline 2nd Floor Classroom
+88F 83F 88F
Design Process
156
81
156 151
16
1
19 14
0
20
40
60
80
100
120
140
160
180
200
Baseline Two MassWalls
2 TurbineVentilators
Thick Slab
Hou
rs P
er Y
ear
Hours Out of Range
Over 88
83-88
Lessons Learned - Mass
5 Slab +88F 83F 88F
Design Process
156
81
156 151
16
1
19 14
0
20
40
60
80
100
120
140
160
180
200
Baseline Two MassWalls
2 TurbineVentilators
Thick Slab
Hou
rs P
er Y
ear
Hours Out of Range
Over 88
83-88151
14
Thick Slab
Thick Slab 7 +88F 83F 88F
Lessons Learned - Mass
Design Process
156
81
156 151
16
1
19 14
0
20
40
60
80
100
120
140
160
180
200
Baseline Two MassWalls
2 TurbineVentilators
Thick Slab
Hou
rs P
er Y
ear
Hours Out of Range
Over 88
83-88
2 Mass Walls +88F 83F 88F
Lessons Learned - Mass
Design Process
156
81
156 151
16
1
19 14
0
20
40
60
80
100
120
140
160
180
200
Baseline Two MassWalls
2 TurbineVentilators
Thick Slab
Hou
rs P
er Y
ear
Hours Out of Range
Over 88
83-88
Lessons Learned - Airflow 3 Turbine Ventilators
1,400 CFM
+88F 83F 88F
Design Process
156
81
156 151
16
1
19 14
0
20
40
60
80
100
120
140
160
180
200
Baseline Two MassWalls
2 TurbineVentilators
Thick Slab
Hou
rs P
er Y
ear
Hours Out of Range
Over 88
83-88156
19
Two Turbine Ventilators
2 Turbine Ventilators 1,000 CFM
+88F 83F 88F
Lessons Learned - Airflow
Design Process
156
81
156 151
16
1
19 14
0
20
40
60
80
100
120
140
160
180
200
Baseline Two MassWalls
2 TurbineVentilators
Thick Slab
Hou
rs P
er Y
ear
Hours Out of Range
Over 88
83-88
Baseline 2nd Floor Classroom
+88F 83F 88F
156 156 151
16 19 14
0
20
40
60
80
100
120
140
160
180
200
Baseline Two MassWalls
2 TurbineVentilators
Thick Slab
Hou
rs P
er Y
ear
Hours Out of Range
Over 88
83-88
Lighting
31
110
6
High Performance
Glass
Design Process
High Performance Glass +88F
83F 88F
156 156 151
16 19 14
0
20
40
60
80
100
120
140
160
180
200
Baseline Two MassWalls
2 TurbineVentilators
Thick Slab
Hou
rs P
er y
ear
Hours Out of Range
Over 88
83-88
Proposed
31
Mass Wall
2 Turbine Ventilators 1,000 CFM
High Performance Glass
High Performance Sage Glass
Design Process
Proposed
+88F 83F 88F
Photovoltaics
Photovoltaics
What It Took To Build How Much Will it Cost?
What It Took To Build How Much Will it Cost?
What It Took To Build Shift in System Costs
Shift in Building System Cost High Performance Envelope
Insulated Composite Panels at Exterior Operable Windows High Performance Glazing Sunshades Electrochromic Skylights
Tunneling Through the Cost Barriers New Materials Insulated Composite Panels
Tunneling Through Cost Barriers New Design Elements Ceiling Reflectors
Tunneling Through Cost Barriers New Design Elements Ceiling Reflectors
Tunneling Through Cost Barriers New Design Elements Electrochromic Glass
Slab Sensors Window Sensors Window Actuators Occupancy Sensors
Tunneling Through Cost Barriers Controls
Tunneling Through Cost Barriers New Design Elements Electrochromic Glass
Finding the Sweet Spot
Q&A Session
BREAK
Lessons Learned & Advice
Verify Performance Modeling Whole Building Actual
Electricity
Heating Water
Gas
Modeled EUI 26.9 Actual EUI 31.9
0.00
0.50
1.00
1.50
2.00
2.50
3.00
3.50
4.00
4.50
5.00
Oct-12 Nov-12 Dec-12 Jan-13 Feb-13 Mar-13 Apr-13 May-13 Jun-13 Jul-13 Aug-13 Sep-13
kBtu
/sf
Health Sciences Addition Modeled and Acutal EUI (2012-2013)
Modeled EUI Actual EUI PV Production
Verify Performance EUI
-
5,000
10,000
15,000
20,000
25,000
30,000
35,000
40,000
Oct-12 Nov-12 Dec-12 Jan-13 Feb-13 Mar-13 Apr-13 May-13 Jun-13 Jul-13 Aug-13 Sep-13
kWh
Electric Usage (2012-2013)
Actual Electric Modeled Electric
Verify Performance Electric Usage
Verify Performance Metering - System
Lighting
Chiller
Domestic Hot Water
Elevators
Other HVAC
Plug Loads
Electricity
Heating Water
Gas
LIGHTING 15%
PLUG LOADS 28%
CHILLER 2% OTHER
HVAC 7%
DOMESTIC HOT
WATER 3%
HEATING WATER 45%
LIGHTING 12%
ELEVATOR 0.4%
PLUG LOADS 20%
CHILLER 2%
OTHER HVAC 15%
DOMESTIC HOT
WATER 6%
HEATING WATER 45%
Verify Performance Metering - System
Modeled Actual
Deep Metering Submetering at the Room Level
Outlet Damper
Air Flow Ceiling Fans
Room Occupancy
Slab Temp Lighting
Ventilation Air Temp
HVAC Heat Recovery Unit
Room Space Temp Plug Loads
Room Heating Load
55
60
65
70
75
80
85
90
95
100
19:0
021
:00
23:0
01:
00:
3:00
:5:
00:
7:00
:9:
00:
11:0
013
:00
15:0
017
:00
19:0
021
:00
23:0
01:
00:
3:00
:5:
00:
7:00
:9:
00:
11:0
013
:00
15:0
017
:00
19:0
021
:00
23:0
01:
00:
3:00
:5:
00:
7:00
:9:
00:
11:0
013
:00
15:0
0
Tem
per
atu
re (
F)
1st Floor Office Actual Temp Compared to Modeled Temp (September 6-9)
Outside Air Temp Modeled Space Temp Actual Space Temp
Results Thermal Comfort
50
55
60
65
70
75
80
85
90
95
100
(F
)
Second Floor Classroom (July 1-3, 2013)
OAT Actual Slab Temp Modeled Slab Temp
July 1 July 2 July 3
Results Mass Slab Temp
50
55
60
65
70
75
80
85
90
95
100
(F
)
Second Floor Classroom (July 1-3, 2013)
OAT Actual Slab Temp Modeled Slab Temp
July 1 July 2 July 3
Results Mass Slab Temp
50
55
60
65
70
75
80
85
90
95
100
(F
)
Second Floor Classroom (July 1-3, 2013)
OAT Actual Slab Temp Modeled Slab Temp
July 1 July 2 July 3
Results Mass Slab Temp
50
55
60
65
70
75
80
85
90
95
100
0
500
1,000
1,500
2,000
2,500
F
CFM
Second Floor Classroom (July 1-3, 2013)
Actual Air Flow Modeled Air Flow OAT
July 1 July 2 July 3
Results Natural Ventilation Flow
Damper Open
50
55
60
65
70
75
80
85
90
95
100
0
500
1,000
1,500
2,000
2,500
F
CFM
Second Floor Classroom (July 1-3, 2013)
Actual Air Flow Modeled Air Flow OAT
July 1 July 2 July 3
Results Natural Ventilation Flow
Damper Open
50
55
60
65
70
75
80
85
90
95
100
0
500
1,000
1,500
2,000
2,500
F
CFM
Second Floor Classroom (July 1-3, 2013)
Actual Air Flow Modeled Air Flow OAT
July 1 July 2 July 3
Results Natural Ventilation Flow
Damper Open
Results Lighting
0.0
0.2
0.4
0.6
0.8
1.0
1.2
W/
sf
Second Floor Classroom (May, 2013)
Occupancy Predicted Lighting Actual Lighting
Results Lighting
0.0
0.2
0.4
0.6
0.8
1.0
1.2
W/
sf
Second Floor Classroom (July 1-3, 2013)
Occupancy Predicted Lighting Actual Lighting
July 1 July 2 July 3
50
55
60
65
70
75
80
85
90
95
100
(F)
Second Floor Classroom (July 1-3, 2013)
OAT Actual Room DBT Modeled Room DBT
July 1 July 2 July 3
Results Space Temperature
50
55
60
65
70
75
80
85
90
95
100
(F)
Second Floor Classroom (July 1-3, 2013)
OAT Actual Room DBT Modeled Room DBT
July 1 July 2 July 3
Results Space Temperature
50
55
60
65
70
75
80
85
90
95
100
(F)
Second Floor Classroom (July 1-3, 2013)
OAT Actual Room DBT Modeled Room DBT
July 1 July 2 July 3
Results Space Temperature
Lessons Learned in Construction
Coordination of New Design Components Jurisdiction Approval Commissioning
Coordination Ductwork, HRVs
Coordination
New Components and Different Planes
Fans Daylight Reflectors Pendant Lights Projectors/AV
Operable Windows Wiring Actuators Clearances Screens
Coordination
Jurisdiction Approval Fire Suppression System
Acoustic Ceilings Impact on Fire Suppression
Jurisdiction Approval Mechanical Service
Commissioning New Players New Challenges
Commissioning
Lessons Learned It Takes LOTS of Studies
Lessons Learned
Buildings are for Teaching Electrochromic glass Noisy actuators KISS (keep it simple/separate)
Client might agree to limitations, but only after design
Lessons Learned
Lessons Learned Manage expectations
Lessons Learned Engage and Train Users
Lessons Learned Engage and Train Users
Lessons Learned Inspire the occupants!
Advice
All of the following are essential: Integrated design Strong leadership Knowledge Persistence / passion Manage expectations Its a paradigm shift!
Lessons Learned Owners Perspective
CM/GC
Get staff buy-in
Always call Elin
Energy impact of custodial
Know the products
Need for heat in AM
Use of LEDs
Solar expertise on board
Create a creative environment
To obtain deep metering data: [email protected] Dashboard: http://live.deckmonitoring.com/?id=Chemeketa_Salem_Campus_Bldg8_Alternate Articles: http://www.hpbmagazine.org/Case-Studies/Chemeketa-Health-Sciences-Complex-Addition-Salem-OR/
Resources
Questions | Comments
Jon Wiener, AIA, LEED AP - Principal [email protected]
Jerry Vessello Project Manager [email protected]
Nick Collins, PE, LEED AP - Principal [email protected]
Patrick Rank Project Manager [email protected]
Path to Net Zero
It all adds up to zero Increased incentives
for early design, technical assistance, installation and post-occupancy
Technical resources and assistance from kick-off through occupancy
Incentives for net-zero certification
Incentives & resources for early design Facilitated kick-off meeting to adopt an EUI
target that aligns with the Architecture 2030 Challenge
Up to $10,000 to offset a design charrette to refine approach and goals using:
EUI targeting tool Shoebox modeling
Construction Document review (required)
Technical assistance & incentives
75 percent of the cost of energy studies, up to $50,000, including:
Early design shoebox modeling CFD analysis Daylighting studies Energy modeling Commissioning design review
Installation incentives
Modeled savings: $0.40/kWh, $1.20/therm
- OR -
Market solutions very best level
Standard and/or special measure incentives
Performance & post-occupancy incentives $0.15/sq ft for
functional testing, up to $40,000
Up to $40,000, or 50 percent of cost of energy metering
Incentives for net-zero certification 50 percent of the cost
of net-zero certification from the International Living Future Institute, ILFI (including application fee)
Thank You Chemeketa Community Colleges Path to Net Zero June 6th, 2015
Slide Number 1Allies for Efficiency Training SeriesTrainings & EducationUpcoming Trainings and EventsSlide Number 5Slide Number 6Slide Number 7Slide Number 8Slide Number 9Slide Number 10Slide Number 11Slide Number 12Slide Number 13Slide Number 14Slide Number 15Slide Number 16Slide Number 17Slide Number 18Slide Number 19Slide Number 20Slide Number 21Slide Number 22Slide Number 23Slide Number 24Slide Number 25Slide Number 26Slide Number 27Slide Number 28Slide Number 29Slide Number 30Slide Number 31Slide Number 32Slide Number 33Slide Number 34Slide Number 35Slide Number 36Slide Number 37Slide Number 38Slide Number 39Slide Number 40Slide Number 41Slide Number 42Slide Number 43Slide Number 44Slide Number 45Slide Number 46Slide Number 47Slide Number 48Slide Number 49Slide Number 50Slide Number 51Slide Number 52Slide Number 53Slide Number 54Slide Number 55Slide Number 56Slide Number 57Slide Number 58Slide Number 59Slide Number 60Slide Number 61Slide Number 62Slide Number 63Slide Number 64Slide Number 65Slide Number 66Slide Number 67Slide Number 69Slide Number 70Slide Number 71Slide Number 72Slide Number 73Slide Number 74Slide Number 75Slide Number 76Slide Number 77Slide Number 78Slide Number 79Slide Number 80Slide Number 81Slide Number 82Slide Number 83Slide Number 84Slide Number 85Slide Number 86Slide Number 87Slide Number 88Slide Number 89Slide Number 91Slide Number 92Slide Number 93Slide Number 94Slide Number 95Slide Number 96Slide Number 97Slide Number 98Slide Number 99Slide Number 100Slide Number 101Slide Number 102Slide Number 103Slide Number 104Slide Number 105Slide Number 106Slide Number 107It all adds up to zeroSlide Number 109Slide Number 110Slide Number 111Slide Number 112Slide Number 113Slide Number 114