Lecture 09 : Project Human Resource Management (1/31)Contents

PMP Lectures Prepared By: Eng. Mohamed ElSaadany

0 . Ro les & Respons ib i l i t i es

1. P lan Human Resou rc e Managemen t

2. Acqu i re P ro jec t Team

3. Deve lop P ro jec t Team

4. Manage P ro jec t Team

Page 2: PMP Preparation - 09 Human Resource Management

PMP Lectures Prepared By: Eng. Mohamed ElSaadany

Sponsor• Initiation: Provide financial resources for the project, determine

requirements and initial scope, giving authority to project manager, provide information required to develop project charter

• Planning: Define required reports, identify high level risks, and authorize

project management plan,• Execution and M/C: Authorize changes, solving problems out of project

manager scope, answering questions regarding project scope, and impose quality policy

• Closing: Final acceptance for the product (If he was the client)

Lecture 09 : Project Human Resource Management (2/31)Roles & Responsibilities

Functional manager• Individuals who manage resources in specific department• Assign resources with project manager• Approve final schedule and final project management plan• Recommend changes to the project

Page 3: PMP Preparation - 09 Human Resource Management

PMP Lectures Prepared By: Eng. Mohamed ElSaadany

Portfolio Manager• Manage unrelated projects

• Ensure that selected projects provide value to the organization

• Getting the best return from resources invested

Lecture 09 : Project Human Resource Management (3/31)Roles & Responsibilities

Program Manager• Manage group of related projects• Adjust projects for program benefit• Guide and support project managers

Team• Help identifying requirements, constraints, and assumptions• Help creating WBS, and time/cost estimations• Execute/comply with project management plan • Recommend changes

Page 4: PMP Preparation - 09 Human Resource Management

PMP Lectures Prepared By: Eng. Mohamed ElSaadany

Project Manager• In charge of the project and doesn’t have to be technical expert• Influence project team and atmosphere• Coordinate interaction between project and key persons• Select appropriate processes for the project• Lead / direct planning efforts• Identify / analyze constraints and assumptions• Assist and support team during execution• Determine and deliver required levels of quality• Determine need for changes• Maintain control over project• Must say No when necessary• Apply project management knowledge• Spend more time being proactive than reacting with problems

Lecture 09 : Project Human Resource Management (4/31)Roles & Responsibilities

Page 5: PMP Preparation - 09 Human Resource Management

PMP Lectures Prepared By: Eng. Mohamed ElSaadany

Project Manager ( With Human Resources)• Determine what resources will be needed• Create job descriptions• Create project team directory• Create human resource plan• Create recognition and reward system• Make sure that all roles and responsibilities are clearly assigned

• Report team members performance• Understand training needs for team members

Lecture 09 : Project Human Resource Management (5/31)Roles & Responsibilities

Page 6: PMP Preparation - 09 Human Resource Management

PMP Lectures Prepared By: Eng. Mohamed ElSaadany

H u m a n R e s o u r c e M a n a g e m e n t

9.1 Plan Human Resource Management

Inputs : Project Management Plan Activity Resource Requirements Enterprise Environmental Factors Organizational Process Assets

Tools and Techniques : Organization Charts and Position Descriptions Networking Organizational Theory Expert Judgment Meetings

Outputs : Human Resource Management Plan

Lecture 09 : Project Human Resource Management (6/31)01. Plan Human Resource Management

Page 7: PMP Preparation - 09 Human Resource Management

PMP Lectures Prepared By: Eng. Mohamed ElSaadany

Organization Charts and Position Descriptions: Document team members roles and responsibilities to ensure that each work

package has owner using one of the following formats:

Lecture 09 : Project Human Resource Management (7/31)01. Plan Human Resource Management

• HierarchicalEx: OBS, RBS, WBS

• Responsibility Assignment Matrix (RAM)This type illustrates connection between activities and team membersEx: RACI (R= Responsible, A= Accountable, C= Consult, I= Inform)

• Text-Oriented FormatsAlso known as Position Descriptions,and Role-Responsibility- Authority Form

TT

Page 8: PMP Preparation - 09 Human Resource Management

PMP Lectures Prepared By: Eng. Mohamed ElSaadany

Lecture 09 : Project Human Resource Management (8/31)01. Plan Human Resource Management

Networking: Formal and informal interactions with others

Ex: Luncheon meetings, informal conversation, events, and conferences.

TT

Organizational Theory: Addressing the way people and organizational units behave.

Different organizational structures have different individual response, individual

performance, and personal relationship characteristics.

Ex: Scientific management, bureaucracy model, simple structure, hierarchical

structure, functional organizations, and matrix organizations.

TT

Expert Judgment: List required skills and determine reporting relationship needed

TT

Page 9: PMP Preparation - 09 Human Resource Management

PMP Lectures Prepared By: Eng. Mohamed ElSaadany

Lecture 09 : Project Human Resource Management (9/31)01. Plan Human Resource Management

Human Resource Management Plan: How human resources will be defined, staffed, managed, and released.

Part of PM Plan and may include:

O

1- Roles and Responsibilities:• Role: Function assigned to a person in the project. Ex: Civil Engineer

• Authority: The right to make a decision, approval, acceptance … etc.

Ex: Quality acceptance, change approval.

• Responsibility: Assigned duties. Ex: Construction of concrete skeleton.

• Competency: Skills required to complete activities.

2- Project Organization Chart:• Graphic display of project team members and their reporting relationships.

Page 10: PMP Preparation - 09 Human Resource Management

PMP Lectures Prepared By: Eng. Mohamed ElSaadany

Lecture 09 : Project Human Resource Management (10/31)01. Plan Human Resource Management

3- Staffing Management Plan:• Where they will come from (acquisition)

• When recruiting should be start (calendar and histograms)

• Staff release plan (help mitigate risks and improve morale)

• Training Needs (if expecting team members will not have required skills)

• Compliance with HR rules and governmental regulations

• Safety policies and procedures

• Recognition & reward systems :

• Say (Thank You)

• Member of the month prize / performance prize

• Recommend him/her for raises

• Parties, events, and celebrations

• Training courses (paid)

Page 11: PMP Preparation - 09 Human Resource Management

PMP Lectures Prepared By: Eng. Mohamed ElSaadany

H u m a n R e s o u r c e M a n a g e m e n t

9.2 Acquire Project Team

Inputs : Human Resource Management Plan Enterprise Environmental Factors Organizational Process Assets

Tools and Techniques : Pre-Assignment Negotiation Acquisition Virtual terms Multi-Criteria Decision Analysis

Outputs : Project Staff Assignments Resource Calendars Project Management Plan Updates

Lecture 09 : Project Human Resource Management (11/31)02. Acquire Project Team

Page 12: PMP Preparation - 09 Human Resource Management

PMP Lectures Prepared By: Eng. Mohamed ElSaadany

Lecture 09 : Project Human Resource Management (12/31)02. Acquire Project Team

Pre-Assignment: Sometimes resources are assigned in advance (defined within charter)

because of their experience or the sponsor require these resources to be assigned in the project.

TT

Negotiation: • Negotiate with functional manager, other PM teams within organization to

assign scarce and specialized resources, or with external organizations and contractors

• When negotiating from within your organization:1. Know the needs of your project and its priority in the organization2. Understand that the resource manager has his own work to do3. Don’t ask for the best resource if the project does not need them4. Be able to prove why project requires stated resources quantity an quality5. Build relationship with resource manager and discover what he will need

from you

TT

Page 13: PMP Preparation - 09 Human Resource Management

PMP Lectures Prepared By: Eng. Mohamed ElSaadany

Lecture 09 : Project Human Resource Management (13/31)02. Acquire Project Team

Acquisition: When organization is unable to provide the staff needed, you can get the work

done through outsourcing or by subcontracting the work to another organization .

TT

Virtual Teams: Team members with little or no time spent meeting face to face. Advantages:

1. Use special expertise even if the expert is not in the same area2. Incorporate employees who work from home3. Include people with mobility limitations or disabilities4. Work in projects that would have been ignored due to travel expenses

Disadvantage:5. Possibility for misunderstanding6. Difficulties of sharing knowledge and experience between members7. Cost of applying communication technology

TT

Page 14: PMP Preparation - 09 Human Resource Management

PMP Lectures Prepared By: Eng. Mohamed ElSaadany

Lecture 09 : Project Human Resource Management (14/31)02. Acquire Project Team

Multi-Criteria Decision Analysis: Using analysis tool, criteria are used to rate or score team member like:

availability, cost, experience, ability, knowledge, skills, and attitude• Halo effect is the tendency to rate employee on all factors due to one

factor. This action has negative impacts and should be avoidedEx: Assigning a project manager because he is a great programmer

TT

Project Staff Assignments: When appropriate people have been assigned,

1. Document this assignment in Project Team Directory2. Send memos to team members3. Insert name in organization chart

O

Resource Calendar: It documents the time period that each team member can work including

persons availability, vacation time, holidays, work hours, … etc.

O

Page 15: PMP Preparation - 09 Human Resource Management

PMP Lectures Prepared By: Eng. Mohamed ElSaadany

H u m a n R e s o u r c e M a n a g e m e n t

9.3 Develop Project TeamInputs :

Human Resource Management Plan Project Staff Assignments Resource Calendars

Tools and Techniques : Interpersonal skills Training Team-Building Activities Ground Rules Co location Recognition and Rewards Personnel Assessment Tools

Outputs : Team Performance Assessments Enterprise Environmental Factors Updates

Lecture 09 : Project Human Resource Management (15/31)03. Develop Project Team

Page 16: PMP Preparation - 09 Human Resource Management

PMP Lectures Prepared By: Eng. Mohamed ElSaadany

Lecture 09 : Project Human Resource Management (16/31)03. Develop Project Team

Interpersonal Skills: (Soft Skills)Assessing and controlling team members sentiments مشاعر and following up

their issues increase cooperation and reduce tension.Ex: Communication skills, emotional intelligence, conflict resolution,

negotiation, influence, creativity, and team building.Encourage team, communicate honestly, establish and maintain trust.

TT

Training:Enhance competencies to reduce overall project costScheduled training takes place as stated in human resource planUnplanned training takes place as a result of observation

TT

Ground Rules:What behavior is acceptable and what is not acceptable for example:

• How should team member resolve conflicts with others• Who is authorized to give direction to contractors• Acceptable behavior during meetings

TT

Page 17: PMP Preparation - 09 Human Resource Management

PMP Lectures Prepared By: Eng. Mohamed ElSaadany

Lecture 09 : Project Human Resource Management (17/31)03. Develop Project Team

Team-Building ActivitiesTeam building is to help team members work together effectively exercising the

following :• Handle team members problems & discuss them as team members issues• Introduce appropriate rewards and recognition• Manage conflicts effectively• Provide good leadership• Promote trust and open communication among team members• WBS creation is a team-building tool

In Matrix organization you don’t have the ability to give team a rise or promotion. Trust as well as recognition and reward system will make you able to get people to cooperate.

TT

Page 18: PMP Preparation - 09 Human Resource Management

PMP Lectures Prepared By: Eng. Mohamed ElSaadany

Lecture 09 : Project Human Resource Management (18/31)03. Develop Project Team

Team Development Stages:

It is one of the models used to describe team development

1. Forming: People are brought together as a team

2. Storming: There are disagreements as people learn to work

together

3. Norming: Team members begin to build good relationships,

begin trust each other

4. Performing: Team members work effectively together as well-

organized unit

5. Adjourning: Team members complete the work and moves on

from the project

Page 19: PMP Preparation - 09 Human Resource Management

PMP Lectures Prepared By: Eng. Mohamed ElSaadany

Lecture 09 : Project Human Resource Management (19/31)03. Develop Project Team

Co-Location:Placing the active team members in the same location (war room) to enhance

their ability to perform as a team.War room is a central location for project coordination usually with WBS,

networks, schedule, … etc. posted on the wall

TT

Personnel Assessment Tools:These tools help project manager assess team members preferences,

aspirations, how they organize information, how they make decisions, and how they prefer to interact with people.

Examples of these tools are surveys, interviews, and focus groups.These tools provide improved understanding, communication, and trust among

the team.

TT

Page 20: PMP Preparation - 09 Human Resource Management

PMP Lectures Prepared By: Eng. Mohamed ElSaadany

Lecture 09 : Project Human Resource Management (20/31)03. Develop Project Team

Team Performance Assessments:The evaluation of a team’s effectiveness may include indicators such as:1. Improvement in skills2. Improvement in competencies3. Increased team cohesiveness4. Reduce staff turnover rate

Note: Team performance assessment is done by project manager or by project management team for all team , not for individuals.

O

Page 21: PMP Preparation - 09 Human Resource Management

PMP Lectures Prepared By: Eng. Mohamed ElSaadany

H u m a n R e s o u r c e M a n a g e m e n t

9.4 Manage Project Team

Inputs : Human Resource Management Plan ■ Project Staff Assignments Team Performance Assessments ■ Issue Log Work Performance Reports ■ Organizational Process

AssetsTools and Techniques :

Observation and Conversation ■ Project Performance Appraisals

Conflict Management ■ Interpersonal SkillsOutputs :

Change Requests Project Management Plan Updates Project Documents Updates Enterprise Environmental Factors Updates Organizational Process Assets Updates

Lecture 09 : Project Human Resource Management (21/31)04. Manage Project Team

Page 22: PMP Preparation - 09 Human Resource Management

PMP Lectures Prepared By: Eng. Mohamed ElSaadany

Lecture 09 : Project Human Resource Management (22/31)04. Manage Project Team

Issue Log:Output of “Manage Stake Holder Engagement“ process and used to manage

and follow up issues .

I

Observation and Conversation:Used to stay in touch with the work and attitude of team members.

TT

IssueNo Issue Date

AddedRaised

ByPerson

AssignedResolution Due Date Status Date

Resolved Resolution

Project Performance Appraisals:Evaluation of employees’ performance by their supervision.360-Degree Review is one of the ways to complete appraisal by including the

input of coworkers, subordinates, and supervisors.

TT

Page 23: PMP Preparation - 09 Human Resource Management

PMP Lectures Prepared By: Eng. Mohamed ElSaadany

Lecture 09 : Project Human Resource Management (23/31)04. Manage Project Team

Conflict Management:TT

A - Conflict Sources:

1- Schedule 2- Project Priorities 3- Technical Opinions

4- Resources 5- Administrative Procedures 6- Cost

7- Personality تذكر أول أربعة وتذكر ان الشخصية هى األخيرة

B - Conflict Properties:

1. Conflict is natural and inevitable

2. Conflict is consequence of organizational interaction

3. Conflict resolution needs openness

4. Conflict resolution should focus on issues not personalities

5. Conflict resolution should focus on present not past

Page 24: PMP Preparation - 09 Human Resource Management

PMP Lectures Prepared By: Eng. Mohamed ElSaadany

Lecture 09 : Project Human Resource Management (24/31)04. Manage Project Team

Conflict Management:TT

C - Conflict Avoiding Techniques:

1- Ground Rules 2- Role Definition 3- Communication Planning

4- Inform team of project objectives, constraints, charter

5- Make work assignments interesting and challenging

D - Resolution Responsibility:

1. Conflict is best resolved by those involved in the conflict

2. If conflict escalate, project manager should help facilitate satisfactory

resolution.

3. If disruptive conflict continues, formal procedures should be used including

disciplinary actions. إجراءات تأديبية

Page 25: PMP Preparation - 09 Human Resource Management

PMP Lectures Prepared By: Eng. Mohamed ElSaadany

Lecture 09 : Project Human Resource Management (25/31)04. Manage Project Team

Conflict Management:TT

E - Conflict Resolution Techniques:

1. Collaborate/Confront (Problem Solving): Incorporate multiple viewpoint

to lead to consensus then problem goes away leading to win-win situation.

2. Compromise/Reconcile : Bring some degree of satisfaction to all parties,

then no party gets everything, leading to lose-lose situation. Compromising

in not the best choice but rather second to confronting.

3. Withdraw/Avoid: Parties retreat يتراجع or postpone a decision.

4. Smooth/Accommodate: Emphasize agreements rather than difference in

opinions, conceding خضوع one’s position to the needs of others to maintain

harmony and relationships.

5. Force/Direct: Pushing one viewpoint at the expense of others.

Page 26: PMP Preparation - 09 Human Resource Management

PMP Lectures Prepared By: Eng. Mohamed ElSaadany

Lecture 09 : Project Human Resource Management (26/31)04. Manage Project Team

Interpersonal Skills: مهارات التعامل مع اآلخرينTT

A. Powers of project manager:

1. Formal (Legitimate): Based on your position )رسمي )شرعي

2. Reward: Giving rewards and prizes.

3. Penalty (Coercive): For example removing from some team )العقاب)اإلكراه 4. Expert: Power comes from being project management expert.

5. Referent: The ability of a leader to influence a follower because of the

follower's loyalty, respect, or admiration. It’s the power of charisma.

Notes:• Best powers are Expert and Reward. The worst is Penalty.

• Powers derived from PM position are Formal, Reward, and Penalty• Power earned on your own is Expert

Page 27: PMP Preparation - 09 Human Resource Management

PMP Lectures Prepared By: Eng. Mohamed ElSaadany

Lecture 09 : Project Human Resource Management (27/31)04. Manage Project Team

Interpersonal Skills: مهارات التعامل مع اآلخرينTT

B. Management and Leadership Styles:

• At the beginning of project use directing styles.• At the project execution use coaching, facilitating, and supporting.

1. Directing: Telling others what to do.2. Facilitating: Coordinating the inputs of others.3. Coaching: Helping other achieve their goal.4. Supporting: Providing assistance along the way.5. Autocratic: Manager has power to do what he want. استبدادي6. Consultative: Manager obtains others’ opinions & act as servant for team7. Consultative- Autocratic: Manager takes input from team members but

retains decision-making authority for him self.8. Consensus: Making decisions base on group agreement.

Page 28: PMP Preparation - 09 Human Resource Management

PMP Lectures Prepared By: Eng. Mohamed ElSaadany

Lecture 09 : Project Human Resource Management (28/31)04. Manage Project Team

Interpersonal Skills: مهارات التعامل مع اآلخرينTT

B. Management and Leadership Styles:

9. Delegation: Establish goals then give team authority to complete the work.10.Bureaucratic : Following procedures exactly. Appropriate for critical work.11. Charismatic: Energize and encourage team in performing.12.Democratic (Participative): Team own the decision made by group.13.Laissez-Faire: Leave alone/Allow to act. Manager is not directly involved in

team work but consult as necessary. دعه يعمل14.Analytical: Manager asks questions to get facts.15.Driver: Constantly giving directions. His attitude drives team to win.16. Influencing: This style emphasizes team work, teambuilding, and team

working. These managers work with their teams to influence project implementation. Influence skills include: persuasive – listening – mutual trust – consideration of various perspectives.

Page 29: PMP Preparation - 09 Human Resource Management

PMP Lectures Prepared By: Eng. Mohamed ElSaadany

Lecture 09 : Project Human Resource Management (29/31)04. Manage Project Team

Important Notes

Problem Solving Method:1- Define the real problem 2- Analyze problem3- Identify solutions 4- Pick a solution5- Implement solution 6- Confirm solution solved problem

Special Terms :A. Expectancy Theory: Employees who expect to be rewarded for their

accomplishments remains productive as rewards meet their expectations.B. Perquisites (Perks): Some employees receive special rewards such as

assigned parking space or executive dining. االمتيازات االستثنائية C. Fringe Benefits : Standard benefits formally given to all employees such

as educational benefits, insurance, and profit sharing. المزايا االضافية

Page 30: PMP Preparation - 09 Human Resource Management

PMP Lectures Prepared By: Eng. Mohamed ElSaadany

Lecture 09 : Project Human Resource Management (30/31)04. Manage Project Team

Motivation Theories

A- McGregor’s theory of X & Y:Theory X: Managers who believe that people need to be watched every minute.Theory Y: Managers who believe people are willing to work without supervision

B- Maslow’s theory hierarchy of need:

To ascend next level you should fulfill levels below.

Starting from the pyramid base :

1. Physiological: Air, water, ... etc.

2. Safety: Security, Stability, ... etc.

3. Social: Like, love, friends, ... etc.

4. Esteem: Attention, respect, ... etc.

5. Self Actualization: Learning, growth, … etc.

Page 31: PMP Preparation - 09 Human Resource Management

PMP Lectures Prepared By: Eng. Mohamed ElSaadany

Lecture 09 : Project Human Resource Management (31/31)04. Manage Project Team

C- David McClelland's Theory of Needs:Also Called Acquired Needs Theory1. People need achievement They like recognition Give them challenging

projects.2. People need Affiliation They seek approval rather than recognition Let

him cooperate with others.3. People need Power Effective Leader If socially oriented(not personally

oriented), allow him to manage others.

D- Herzberg’s Theory:1. Hygiene Factors: Work condition, salary, security, personal life, relationship at

work.2. Motivating Agents: Responsibility, self-actualization, recognition, professional

growth.Poor hygiene factors may destroy motivation but improving them will not improve

motivation