West Plumb Lane Project Preliminary Design

Public Information MeetingJune 4, 2012

Presentation Goals

Review the project history and community outreach process

Present the preferred improvements supported by the community for the Plumb Lane reconstruction project

Provide details on design developmentRequest input on some design elementsAnswer questions and address your concerns

Project Limits

Public EngagementCommunity Outreach To Date Community Survey 2 Community Workshops One-on-one meetings with residents Meetings with: Councilman Gustin, Councilwoman Zadra, Commissioner

Breternitz, Assemblywoman Benitez-Thompson, Caughlin Ranch HOA, Washoe County West Truckee Meadows CAB, City of Reno Ward 1 NAB

Coordination with City of Reno Community Development and Public Works Coordination with TMWA Media Interviews RTC TAC, CAC and BPAC Reno City Council

Community Engagement Results

1. Pavement2. Bike Lanes

3. Multi-use Path

1. Pavement rehabilitation2. Bike lanes

3. Multi-use Path

Presented Three Concepts:

Preferred Enhancement:Multi-use Path, Parking One Side

Multi-use Path

Design Considerations

Address the needs of the community and provide a safe route for all users

Confine improvements to the existing right-of-way

Address traffic volume and excessive speeds

Evaluate possible safety improvements in the steep, curved section east of Homewood Drive

Maintain existing trees and rural character

Existing Conditions

Preferred Enhancement:Multi-use Path, Parking One Side

N

Multi-use Path, Parking One Side

N

Design ConsiderationsLandscaping, mailboxes, fences & parking

Design ConsiderationsDrainage Options

With Curb and Gutter, Reduced Landscaping Impact

With Drainage Swale, No Curb and Gutter

8’ 8’

50’ ROW

50’ ROW

Design ConsiderationsTraffic Calming and Speed

Plumb Lane Speed Limit Will Remain 25 MPH

Design ConsiderationsTMWA

Construction Schedule & Costs

$3.5 to $4.5 Million

12 weeks(Fuel Tax)

Item and Descriptio

n

UnitUnit C

ost

1.01 Remove existing and construct composite roadw ay structure section 1 SF

$5.00

2.01 Overexcavate unsuitable materials and replace w /imported aggregate base CY

$20.00

2.02 Overexcavate unsuitable materials and replace w /plantmix bituminous CF

$8.00

3.01 Remove existing and construct PCC sidew alk / median f la

tw ork

SF

$10.00

3.02 Remove existing and construct PCC pedestrian ramp

SF

$15.00

3.04 Remove existing and consturct PCC Type 1 curb and gutter

SF

$25.00

4.01 Install 4" solid yellow linear traff ic

paint pavement markings

LF

$0.25

4.02 Install 4" broken w hite linear traff ic

paint pavement markings

LF

$0.15

4.03 Install 4" solid w hite linear traff ic

paint pavement markings

LF

$0.15

4.04 Install 6" solid w hite linear traff ic

paint pavement markings

LF

$0.35

4.05 Install 8" solid w hite linear traff ic

paint pavement markings

LF

$0.50

4.06 Install 8" dotted w hite linear ptraff ic paint pavement m

arkings

LF

$0.50

4.07 Install 24" thermoplastic stop bar/crossw alk strip

ing

LF

$7.50

4.08 Install 8' thermoplastic "O

NLY" word symbol

EA

$140.00

4.09 Install 6' thermoplastic bike lane symbol and through arro

w

EA

$80.00

4.10 Install thermoplastic yield bar tr

iangle symbol

EA

$39.00

4.11 Install 8' thermoplastic rght tu

rn and left turn arro

w symbol

EA

$90.00

Engineer's

Estimate

It

em

How you can help tonight:

Provide your input on comment cards Multi-use path details (concrete color)? Drainage trouble spots? Interest in left turn lanes? Interest in pedestrian crossing? Interest in paved parking adjacent to property? Talk to the project team

We are here to listen to you. Please share your ideas with us!

Thank you!

Information Stations

Seven Stations Station 1: McCarran Boulevard to 3510 West

Plumb Lane Station 2: 3510 West Plumb Lane to Carter Drive Station 3: Carter Drive to Suda Way Station 4: Suda Way to Ferris Lane Station 5: City of Reno Station 6: NV Energy Station 7: Design Input

Questions?

Contact:Michele Dennis, PE, RTC Project Manager at (775) 335-1861