+ PILOT PLANT SCALE UP TECHNIQUES

FACILITATED BY : DR. MANJULA TALLURIDEPT. OF PHARMACEUTICS PRESENTED BY: ANANTHA LAKSHMI IST YEAR M.PHARM PHARMCEUTICS

Page 2: Pilot plant scale up

Introduction and definition

Introduction to Pilot Plant Pilot plant is defined as part of the pharmaceutical industry where a lab scale

formula is transformed into a viable product by development of liable and practical procedure for manufacture that effects the orderly transition from laboratory to routine processing in a full scale production facility.

Introduction to Scale Up Plant The art for designing of prototype using the data obtained from the pilot plant

model. It is a place were the 5 M’s like money, material, man, method and machine are

brought together for the manufacturing of the products

Page 3: Pilot plant scale up

+

Pilot Scale and Scale-Up

Pilot Scale

Scale-Up

R & D

Large Scale Production

Page 4: Pilot plant scale up

+What Do Pilot Scale and Scale-Up Mean ?

INTERMEDIATEBATCH SCALE

MANUFACTURES DRUG PRODUCT BY A PROCEDURE

FULLY REPRESRNTATIVE OF AND SIMULATORY TO THAT OF MANUFACTURING SCALE

PILOT SCALE SCALE-UP

NEXT TO PILOT SCALE

PROCESS OF INCREASING THE BATCH SIZE (MIXING) /PROCEDURE FOR APPLYING

THE SAME PROCESS TO DIFFERENT OUTPUT VOLUMES

(TABLETTING)

Page 5: Pilot plant scale up

+WHY CONDUCT PILOT PLANT STUDIES ?

A pilot plant allows investigation of a product and process on an intermediate scale before large amounts of money are committed to full-scale production

It is usually not possible to predict the effects of a many-fold increase in scale

Reduces the risk associated with the construction of full scale plant. Less capital is required.

Page 6: Pilot plant scale up

+PILOT PLANT CAN BE USED FOR….

Evaluating the results of laboratory studies and making product and process corrections and improvements

Producing small quantities of product for sensory, chemical, microbiological evaluations, limited market testing or furnishing samples to potential customers, shelf-live and storage stability studies

Determining possible salable by-products or waste stream requiring treatment before discharge

Providing data that can be used in making a decision on whether or not to proceed to a full-scale production process; and in the case of a positive decision, designing and constructing a full-size plant or modifying an existing plant

Page 7: Pilot plant scale up

+CONSIDERATIONS FOR PILOT PLANT DEVELOPMENT ….

Kind and size – depends on goals; evaluating product and process; producing samples of product for evaluation; market testing or furnishing to potential customers

Location: near R&D facility .At an existing plant Close liaison between R&D and pilot plant staff is essential

Labor requirements and costs: engineering staff, skilled operations and maintenance staff- pilot plant costs may exceed those of usual plant production costs. The pilot plant may be used for training personnel for a full- scale plant

Page 8: Pilot plant scale up

+Why Pilot plant needed…………

8

Needed to make supplies for bench studies,

product characterization, purity animal studies

toxicology pharmacokinetics, ADME efficacy

clinical studies

Page 9: Pilot plant scale up

+Regulations for Scale -Up

9

Code of Federal Regulations Title 21 Part 210 and 211 - Good Manufacturing Practices for Drugs Part 600 - 680 Processing of Biological materials Part 820 - Quality System Regulations for Medical Devices

Subpart C: Design Controls

Page 10: Pilot plant scale up

Why Scale-Up needed……

A well defined process

A perfect product in laboratory and pilot

plant

But May fail in QA

Tests

Because process

are scale dependen

t

Processes behave

differently on a small scale and

a large scale

Scale up is

necessary to

determine the effect of scale

on product quality

Page 11: Pilot plant scale up

OBJECTIVES OF SCALE UP….

To provide master manufacturing forumla

To identify the critical features of the process

Evaluation and Validation

Guidelines for production and process control

Review of the processing equipment

To produce physically and chemically stable therapeutic dosage

Page 12: Pilot plant scale up

+CLOSE EXAMINATION OF FORMULA TO DETERMINE…

Physical space required and the layout related functions

Market requirement

Cost factor

Compatibility of the equipment with the formulation

Process Modification

Its ability to withstand batch scale

Page 13: Pilot plant scale up

+SCALE UP EFFORTS IN PILOT PLANT….

Production and Process controls are evaluated, validated and finalized

Product reprocessing procedures are developed and validated

Appropriate records and reports are issued to support cGMP

Page 14: Pilot plant scale up

+

PILOT PLANT DESIGN

Page 15: Pilot plant scale up

+Pilot Plant Design…

Formulation and Process Development

Technology evaluation , Scale-Up and Transfer

Clinical Supply Manufacture

Page 16: Pilot plant scale up

Attributes Required..

cGMP Complian

ce

A flexible highly trained

staff

Equipment to

support multiple dosage

form develop

ment

Equipment at

multiple scales

based on similarly operating principles to those

in productio

n (Interme

diate sized and Full scale equipme

nt)

Portable equipme

nt

Multipurpose rooms

Restricted

access , regulated personnel flow and material

flow

Low maintenance and

operating costs

Page 17: Pilot plant scale up

+

PILOT PLANT OPERATION

Page 18: Pilot plant scale up

+

Organizational

Aspects

Validation

Training

Engineering

Support

Maintenance

and calibration

Material control

Inventory ,Orders

and Labeling

Process and

Manufacturing

Activities

QA & QC

Organizational Aspects…

Page 19: Pilot plant scale up

Validation……

Design Specification

s

Installation Qualification

Operational Qualification

Performance Qualification

Compliance with cGMP and FDA

Standards

Page 20: Pilot plant scale up

+Training…..

Compliance with cGMP

Safety and Environmental Responsibilities

Compliance with SOP’s

Technical Skills and Knowledge

Page 21: Pilot plant scale up

+Engineering Support….

Design, Construction, Commissioning and

validation of the pilot plant facility

Co-ordination ,Scheduling , Direction of ongoing

operations

Page 22: Pilot plant scale up

+MAINTENANCE….

To meet cGMP Norms

To ensure Data Integrity and Equipment Reliability

Page 23: Pilot plant scale up

+CALIBRATION…

Compliance with cGMP

Maintaining the

integrity of data during developme

nt

Well trained and expert

staff

Page 24: Pilot plant scale up

+MATERIAL CONTROL…

CO

MPU

TER

IZED

S

YS

TEM

Material Control

Inventory

Orders (FIFO)

Labeling (GMP-GLP)

Page 25: Pilot plant scale up

+Process And Manufacturing Activities..

Formulation and Process

Management Studies

Technology Evaluation ,

Scale-Up and Transfer

Clinical Supply Manufacture

Page 26: Pilot plant scale up

+QUALITY ASSURANCE….

Auditing pilot plant

Auditing and approval of component suppliers

Reviewing, approval and maintaining batch records for clinical supplies

Sampling and release of raw materials and components required for clinical supplies

Release of clinical supplies

Maintaining and distributing facility and operating procedures (SOPs)

Review and approval of validation and engineering documentation

Page 27: Pilot plant scale up

+QUALITY CONTROL….

Release Testing of finished product

Physical, Chemical and Microbiological testing of finished clinical products, components required for clinical supplies

Testing for validation and revalidation programs

QC in-process testing during development, Scale-Up and Technology transfer activities

Page 28: Pilot plant scale up

+

REQUIREMENTS

Page 29: Pilot plant scale up

+Requirements for pilot plant and Scale-Up…. Personnel Requirements

Space Requirements

Administration and Information Process

Physical Testing Area

Standard Pilot-plant Equipment Floor Space

Storage Area

Review of Formula

Process Evaluation

Preparation of Master Manufacturing Procedures

Product Stability and Uniformity

GMP Considerations

Page 30: Pilot plant scale up

+GENERAL CONSIDERATIONS

REPORTING RESPONSIBILITIES

R & D group with separate

staffing

The formulator who developed the product can take into the production and can provide support even after transition into production has been

completed

Page 31: Pilot plant scale up

+Personnel Requirement

Scientists with experience in pilot

plant operations as well as in actual

production area are the most

preferable.

As they have to understand the intent

of the formulator as well as

understand the perspective of the

production personnel.

The group should have some

personnel with engineering

knowledge as well .As scale up also

involves engineering principles.

Page 32: Pilot plant scale up

Space Requirement

Administration and information processing

Physical testing area

Standard equipment floor space

Storage area

Page 33: Pilot plant scale up

+Administration and information process:

Adequate office and desk space should be provided for both scientist and technicians.

The space should be adjacent to the working area.

Page 34: Pilot plant scale up

+

This area should provide permanent bench top space for routinely used physical- testing equipment.

Physical testing area

Page 35: Pilot plant scale up

+

Discreet pilot plant space, where the equipment needed for manufacturing all types of dosage form is located.

Intermediate – sized and full scale production equipment is essential in evaluating the effects of scale-up of research formulations and processes.

Equipment used should be made portable where ever possible. So that after use it can be stored in the small store room.

Space for cleaning of the equipment should be also provided.

Standard pilot-plant equipment floor space

Page 36: Pilot plant scale up

+Storage Area

It should have two areas divided as approved and unapproved area for active ingredient as well as excipient.

Different areas should provided for the storage of the in-process materials, finished bulk products from the pilot-plant & materials from the experimental scale-up batches made in the production.

Storage area for the packing material should also be provided.

Page 37: Pilot plant scale up

+

A thorough review of the each aspect of formulation is important.

The purpose of each ingredient and its contribution to the final product manufactured on the small-scale laboratory equipment should be understood.

Then the effect of scale-up using equipment that may subject the product to stresses of different types and degrees can more readily be predicted, or recognized.

Review of the formula

Page 38: Pilot plant scale up

+

One purpose/responsibility of the pilot-plant is the approval & validation of the active ingredient & excipients raw materials.

Raw materials used in the small scale production cannot necessarily be the representative for the large scale production

Why?

Raw materials

Page 39: Pilot plant scale up

+Equipment

The most economical and the simplest & efficient equipment which are capable of producing product within the proposed specifications are used.

The size of the equipment should be such that the experimental trials run should be relevant to the production sized batches.

If the equipment is too small the process developed will not scale up,

Whereas if equipment is too big then the wastage of the expensive active ingredients.

Page 40: Pilot plant scale up

+

The immediate as well as the future market trends/requirements are considered while determining the production rates.

Production Rates

Page 41: Pilot plant scale up

+

PARAMETERS

Order of mixing of components

Mixing speed

Mixing time

Rate of addition of granulating agents, solvents,solutions of drug etc.

Heating and coolingRates

Filters size (liquids)

Screen size(solids)

Drying temp.And drying time

Process Evaluation

Page 42: Pilot plant scale up

+

Why to carry out process evaluation????

The knowledge of the effects of various process parameters as few mentioned above form the basis for process optimization and validation.

Page 43: Pilot plant scale up

+Master manufacturing procedures

The three important aspects are

Weight sheet Processing directions Manufacturing Procedure

Page 44: Pilot plant scale up

+Master Manufacturing Procedures

The weight sheet should clearly identify the chemicals required in a batch. To prevent confusion the names and identifying no’s for the ingredients should be used on batch records.

The process directions should be precise and explicit.

A manufacturing procedure should be written by the actual operator.

Various specifications like addition rates, mixing time, mixing speed, heating, and cooling rates, temperature, storing of the finished product samples should be mentioned in the batch record directions.

Page 45: Pilot plant scale up

+Product Stability and Uniformity

The primary objective of the pilot plant is the physical as well as chemical stability of the products.

Hence each pilot batch representing the final formulation and manufacturing procedure should be studied for stability.

Stability studies should be carried out in finished packages as well.

Page 46: Pilot plant scale up

+GMP Considerations….

A checklist of GMP items that should be part of scale-up or new product or processes introduction includes the following:

Equipment qualification

Process validation

Regularly schedule preventative maintenance

Regularly process review & revalidation

Relevant written standard operating procedures

The use of competent technically qualified personnel

Adequate provision for training of personnel

A well-defined technology transfer system

Validated cleaning procedures.

An orderly arrangement of equipment so as to ease material flow & prevent cross- contamination

Page 47: Pilot plant scale up

+Transfer of Analytical Methods

During scale up of new product, the analytic test methods developed in research must be transferred to QA Department.

In early transfer processes, the QA staff should review the processes to make sure that the proper analytic instrumentation is available and personal all trained to perform test.

If requires ASSAY method can be reformatted and re written using technology and procedures consistent with current QA laboratory practice.

To complete transfer, research personal should review the assay procedure and the data obtained during the validation studies, verify the analytical methods have not been altered in a way that might affect the reliability precision or accuracy of the tests.

Page 48: Pilot plant scale up

+Types of organizational structures responsible for pilot operations:

A) Research pharmacist responsible for initial scale-up and initial production runs.

B) Pharmaceutical pilot plant controlled by Pharmaceutical Research.

C) Pharmaceutical pilot plant controlled by production division.

Page 49: Pilot plant scale up

A) Research pharmacist responsible for initial scale-up and initial production runs

Department of pharmaceutical research

Technical director of production

Manager of solid dosage form research

Manager of tablet and capsule production

Pharmaceutical research staff

Section head

operators

Page 50: Pilot plant scale up

+Technical director of productionDirector of

pharmaceutical research and development

Manager of solid dosage form research

Manager of pilot development

Manager of tablet and capsule production

Pharmaceutical research staff

Pharmacists and engineers

Section head in charge of tablet production

Operators

B) Pilot plant controlled by pharmaceutical research

Page 51: Pilot plant scale up

+C) Pharmaceutical pilot plant controlled by production division

Director of Pharmaceutical research

Technical director of production

Manager of solid dosage form research

Manager of tablet and capsule production

Pharmaceutical Research staff

Section head of pilot department

operators operators

Section head in charge of tablet production

Page 52: Pilot plant scale up

+Educational backgrounds of pilot plant personnel

They should possess the knowledge of physicochemical factors which could adversely affect bioavailability of drug component from the tablet dosage form.

An individual with graduate training in industrial pharmacy is well qualified for such a responsibility.

Industrial pharmacy core curriculum and electives usually include the following courses:

Product formulation, mfg. pharmacy, industrial pharmacy, biopharmaceutics, homogeneous system, ph. engineering, evaluation of pharmaceutical dosage form, regulatory aspects, principles of QA.

Page 53: Pilot plant scale up

+

Mechanical and chemical engineers would be advantageous in the selection of new equipment offerings and in the organization of most economical sequences of unit operations.

In addition good communication skills both oral and written are essential, because these individuals must frequently interact with members of the pharmaceutical research and production divisions.

Whatever the technological trend, once the goals are defined, the best combination of trained personnel can be determined for the pilot plant.

Page 54: Pilot plant scale up

+Advantages…..

Members of the production and quality control divisions can readily observe scale up runs

Page 55: Pilot plant scale up

+Disadvantages…..

The frequency of direct interaction of the formulator with the production personnel

in the manufacturing area will be reduced.

Any problem in manufacturing will be directed towards it’s own pilot-plant

personnel's.

Page 56: Pilot plant scale up

+Liquid-Liquid Extraction pilot plant setup

Page 57: Pilot plant scale up

+Pilot plant for medicinal and aromatic plants

Page 58: Pilot plant scale up
Page 59: Pilot plant scale up