59
Resettlement Plan (Tranche - 1) Document Stage: Draft for Consultation Project Number: 43464 July 2011 India: Himachal Pradesh Clean Energy Transmission Investment Program (HPCETIP) HP Power Transmission Corporation Limited (HPPTCL) Government of Himachal Pradesh The Resettlement Plan is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board of Directors, Management, or staff, and may be preliminary in nature.

Himachal Pradesh Clean Energy Transmission Investment

Embed Size (px)

Citation preview

Resettlement Plan (Tranche - 1) Document Stage: Draft for Consultation Project Number: 43464 July 2011

India: Himachal Pradesh Clean Energy Transmission Investment Program (HPCETIP)

HP Power Transmission Corporation Limited (HPPTCL) Government of Himachal Pradesh

The Resettlement Plan is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board of Directors, Management, or staff, and may be preliminary in nature.

TABLE OF CONTENTS ITEMS DESCRIPTION PAGE NO

LIST OF ACRONYMS EXECUTIVE SUMMARY

I PROJECT DESCRIPTION

1. 220 kV double circuit transmission (twin moose conductor) line from Hatkoti to Gumma (Pragati Nagar)

2. 400/220 kV GIS pooling sub-station Gumma (Pragati Nagar) 3. /220/66 kV GIS Pooling station near Sherpa Colony (Wangtoo) 4. 220/66 kV GIS Pooling Station Bhoktoo 5.

II SCOPE OF LAND ACQUISITION AND RESETTLEMENT III SOCIOECONOMIC INFORMATION AND PROFILE IV INFORMATION DISCLOSURE, CONSULTATION AND PARTICIPATION V GRIEVANCE REDRESS MECHANISMS VI POLICY AND LEGAL FRAMEWORK

Land Acquisition Act-1894 National Rehabilitation and Resettlement Policy, 2007 (NRRP-2007) HPPTCL’ s Policy on Safeguards ADB’s Safeguard Policy Statement, 2009 (SPS)

VII ENTITLEMENT, ASSISTANCE AND BENEFITS VIII RELOCATION AND INCOME RESTORATION IX RESETTLEMENT BUDGET AND FINANCIAL PLAN X INSTITUTIONAL ARRANGEMENTS XI IMPLEMENTATION SCHEDULE XII MONITORING AND REPORTING

LIST OF TABLES

Table-1 Tranche 1 Subprojects Table-2 Project Components and Impacts on land Acquisition and Resettlement Table-3 Summary of Land Acquisition and Resettlement Table-4 Land Details on Tower Footings on Private land Table-5 Summary Consultations Table-6 Constitution of Grievance Redress Committee Table-7 Entitlement Matrix Table-8 Resettlement Cost Table-9 Institutional Roles and Responsibilities for Resettlement activities

Table-10 Implementation Schedule LIST OF FIGURES

Figure-1 Tranche 1 subprojects in the state of Himachal Pradesh Figure-2 Tranche 1 - 220 kV Hatkoti-Gumma Transmission Line in the state of

Himachal Pradesh

Figure-3 Grievance Redress Mechanism LIST OF ANNEXURE Annexure-1 Inventorisation Details of Hatkoti – Gumma Transmission Line Annexure-2 Socio Economic Profile Annexure-3 Details on Consultations Annexure-4 Copy of Setion-4 Notification for Gumma Substations Annexure-5 Copy of Notification under Electricity Act, 2003 Annexure-6 Sample Monitoring and Status report

List of Acronyms ADB Asian Development Bank APs Affected Persons DC District Collector DP Displaced Persons EA Executing Agency ESC Environment and Social Cell FGD Focus Group Discussions GOHP Government of Himachal Pradesh GRC Grievance Redress Committee HPCETIP Himachal Pradesh Clean Energy Transmission Investment Program HPPTCL HP Power Transmission Corporation Limited IA Implementing Agency LAA Land Acquisition Act 1894 LAO Land Acquisition Officer MFF Multi-Tranche Financing Facility MRM Management Review Meeting NGOs Non-Government Organizations NRRP National Rehabilitation and Resettlement Policy, 2007 PIU Project Implementation Unit PMU Project Management Unit RF Resettlement Framework RP Resettlement Plan SIA Social Impact Assessment SPS Safeguard Policy Statement, 2009 STs Scheduled Tribes

EXECUTIVE SUMMARY i. The Government of Himachal Pradesh (GoHP) through the Government of India (GoI) has requested Asian Development Bank (ADB) to provide a multi-tranche financing facility (MFF) to partly fund the Himachal Pradesh Clean Energy Transmission Investment Program (HPCETIP) in the state of Himachal Pradesh. HP Power Transmission Corporation Limited (HPPTCL) is both the Executing Agency (EA) and Implementation Agency (IA) for the project. The Tranche-1 of HPTECIP project consists of one transmission lines and three pooling substations. The subprojects under the tranche-1 components are (i) 28 kilometre of 220 kV double circuit transmission (twin moose conductor) line from Hatkoti to Gumma (Pragati Nagar), (ii) 400/220 kV GIS pooling sub – station at Gumma (Pragati Nagar), (iii) 400/220/66 kV GIS Pooling station near Sherpa Colony (Wangtoo), (iv) 220/66 kV GIS Pooling Station at Bhoktoo. The Resettlement plan has been prepared for Tranche-1 components of the investment program. Based on the nature, scale and significance of expected impacts, the tranche-1 component under the investment program has been classified as Category B for impact on Involuntary Resettlement (IR) as per ADB’s Safeguard Policy Statement, 2009. ii. Tranche-1 subproject will entail minimum private land acquisition. Land acquisition will be required for one of the three proposed sub stations at Gumma (Pragati Nagar) in Shimla district where 33 bigha, equivalent to 2.50 hectares (Ha) of private land will be acquired. Land acquisition for this substation will affect one household having 4 persons. The affected household for the substation will lose approximately 14% of his total land holding. Additionally, construction of transmission lines (220 kV Hatkoti-Gumma - Pragati Nagar - 28 km double circuit line) will require small scale private land acquisition for the tower footings. A total of 75 towers will be constructed, out of which 51 towers will be erected on private land, each of which will require approximately 225 square meters (15m X 15m) of land, 2 towers will be erected on community land/temple and the remaining 22 towers will be erected on government land. Total land requirement for installing the towers footing is approximately 1.15 Ha. A total of 49 households (321 affected persons) will be affected by the loss of small portions of land for the construction of tower footings. Hence, a total of 50 households (325 affected persons) will be affected by the loss of small portions of land in tranche-1. However, no physical displacement will occur. A total of 638 trees including 469 fruits, 163 forest trees and 6 non fruit trees will be affected. 6 households will lose more than 10% of their total landholding for the construction of towers’ footings. 2 households are considered to be Women Headed Households (WHH). Additionally, temporary impacts on loss of crop are anticipated on the Right of Way during the construction of transmission line for which the HPPTCL will provide compensation for the loss of crop. As per the current assumption, it is estimated that approximately, 71.44 Ha of land will be considered for crop compensation. iii. Consultations were carried out in the month of February to mid-May 2011 with stakeholders during the program preparation. As integral part of the safeguards planning, affected persons and local communities were consulted during the preparation of tranche-1 safeguards documents, i.e., RP and IEE. All stakeholders were informed and the stream of information will continue during the implementation of the project. Public consultations with the project affected communities, stakeholders, and government officials were carried out at 27 villages around the proposed transmission line/substations. Section-4 notification for private land acquisition has been issued and published in the gazette for Gumma substation. Additionally, notification as per the Electricity Act, 2003 on project information was disclosed in the local news paper on 28 April 2011. The HPPTCL will provide relevant resettlement information, in a timely manner, in an accessible place and in a form and language (Hindi/English) understandable to affected persons and other stakeholders. The RP will be disclosed on ADB website and HPPTCL website.

iv. Through its Environment and Social Safeguards Policy, HPPTCL has established a Grievance Redressal Mechanism (GRM) having suitable grievance redressal procedure for the project affected persons. The grievance redress mechanism would address affected persons’ concerns and complaints promptly, using an understandable and transparent process that is gender responsive, culturally appropriate, and readily accessible to the affected persons at no costs and without retribution. This GRM consists of a Grievance Redressal Committee which is headed by Project head and committee consists of Head of Finance wing at the project level, representative of local Panchayat and affected persons, representative of contractor, project Environment/RR staff. Grievances of APs (minor grievance) will first be brought to the attention at the PIU level. Grievances not redressed by the PIU staff (field level) will be brought to the Grievance Redress Committee (GRC) at PMU level. The GRC will meet every month (if grievances are brought to the Committee), determine the merit of each grievance, and resolve grievances within a month of receiving the complaint—failing which the AP will be free to approach appropriate other forum or court of Law for redressal.

v. The policy framework and entitlements for the Program are based on national laws: The Land Acquisition Act, 1894 (LAA, amended in 1984) when private land acquisition is required and The National Rehabilitation and Resettlement Policy, 2007 (NRRP); ADB’s Safeguards Policy Statement 2009. Additionally, HPPTL’s policies, (i) Environment and Social Safeguard Policy, May 2011 (ESSP) and (ii) Resettlement, Relief, Rehabilitation and Compensation Policy, May, 2011 (RRRCP) were also taken in to consideration. Compensation for the lost assets to all affected persons will be paid on the basis of replacement cost. Resettlement assistance for lost income and livelihoods will be provided to both title holders and non-title holders. Special resettlement and rehabilitation measures will be made available to the vulnerable groups. APs entitled for compensation or at least rehabilitation provisions under the Project are (i) All APs losing land either covered by legal title/traditional land rights, or without legal status; (ii) Tenants and sharecroppers whether registered or not; (iii) Owners of buildings, crops, plants, or other objects attached to the land; and (iv) APs losing business, income, and salaries. Compensation eligibility is limited by a cut-off date to be set for the subproject. vi. HPPTCL is both the Executing Agency (EA) and Implementation Agency (IA) for the project. The Project Management Unit (PMU) at corporate level is headed by Senior Project Manager (Planning) who will be assisted by DGM’s from various functions – Administration and Finance, Projects Planning and Design, Procurement and contracts, Environment and Social Cell and Projects Construction. Project Implementation Units (PIUs) at divisional level of the project construction unit are headed by Executive Engineers at four locations – Rohru (Shimla), Chamba, Bhabanagar (Kinnaur) and Sarabhai (Kullu). The Environment and Social cell (ESC) at the corporate level monitors the policy and implementation of safeguards impacts of all projects of HPPTCL. The Environment and R&R Officers in the ESC assist PIUs in all safeguards aspects of the subprojects in compliance with HPPTCL’s Environment and Social Safeguards Policy, May 2011. This environmental and social cell is also responsible for implementation of Environmental Management Plan and Resettlement Plan for all the subprojects funded by ADB. As per ADB’s Safeguard Policy Statement 2009, PMU and ESC are required to conduct regular monitoring of safeguards compliance of each subproject funded by ADB to ensure compliance with project covenants vii. The resettlement cost estimate for this subproject includes eligible compensation, resettlement assistance and support cost for RP implementation and monitoring. These are part of the overall project cost. The total land acquisition and resettlement cost for the Tranche 1 subproject is estimated to be INR 122.43 million. All land acquisition, resettlement, and compensation for a sub-project will be completed before award of civil works contracts. All land required will be provided free of encumbrances to the contractor prior to handing over of sub-project sites and the start of civil works. However, public

consultation and monitoring will be continued on an intermittent basis as needed during the entire duration of the project.

viii. Monitoring is the responsibility of HPPTCL through its PMU and the Environment Social Cell and it will submit bi-annual monitoring reports to ADB for review .The extent of monitoring activities, including their scope will be commensurate with the project’s risks and impacts. ADB will require HPPTCL to establish and maintain procedures to monitor the progress of implementation of safeguard plans; verify the compliance with safeguard measures and their progress toward intended outcomes; document and disclose monitoring results and identify necessary corrective and preventive actions in the periodic monitoring reports and follow up on these actions to ensure progress toward the release of entitlements and benefits. Monitoring reports documenting progress on resettlement implementation and resettlement plan completion reports will be provided by HPPTCL through its PMU to ADB for review on semi annual basis.

I. INTRODUCTION AND PROJECT DESCRIPTION

1. The Government of Himachal Pradesh (GoHP) through the Government of India (GoI) has requested Asian Development Bank (ADB) to provide a multi-tranche financing facility (MFF) to partly fund the Himachal Pradesh Clean Energy Transmission Investment Program (HPCETIP) in the state of Himachal Pradesh. HP Power Transmission Corporation Limited (HPPTCL) is both the Executing Agency (EA) and Implementation Agency (IA) for the project. The Tranche-1 of HPTECIP project consists of one transmission lines and three pooling substations. The subprojects under the tranche-1 components are (i) 28 kilometre of 220 kV double circuit transmission (twin moose conductor) line from Hatkoti to Gumma (Pragati Nagar), (ii) 400/220 kV GIS pooling sub – station at Gumma (Pragati Nagar), (iii) 400/220/66 kV GIS Pooling station near Sherpa Colony (Wangtoo), (iv) 220/66 kV GIS Pooling Station at Bhoktoo. This Resettlement Plan has been prepared for tranche - 1 component under HPCETIP. Based on the nature, scale and significance of expected impacts, the tranche-1 component under the investment program has been classified as Category ‘B’1 for impact on Involuntary Resettlement (IR) as per ADB’s Safeguard Policy Statement, 2009.

2. Tranche 1 subprojects are located in Shimla and Kinnaur Districts of Himachal Pradesh. Himachal Pradesh extends from the Shivalik Hills in the south to the Great Himalayan ranges including a slice of trans-Himalayas in the north. The state falls between latitude 30’22” and 30’12” north and longitude 75’45” and 79’04” East. It is located between the Ravi River in the west and Yamuna River in the east. Its greatest length is 355 Km from the north-western extremity of Chamba to the South-eastern tip of Kinnaur and the maximum width is 270 Km from Kangra in Southwest to Kinnaur in the northeast. The altitude ranges from 450 to 6500 meters above mean sea level, which increases from West to East and South to North.

1. 220 kV double circuit transmission (twin moose conductor) line from Hatkoti to Gumma (Pragati Nagar)

3. This project is being constructed to evacuate power from 111 MW Sawra Kuddu HEP (will be commissioned by year 2014) of Himachal Pradesh Power Corporation Limited (HPPCL). Other HEPs which will be commissioned in future like 44 MW Tangnu Romai HEP (commissioned by year 2016) of Independent power producers (IPPs) initially followed by other HEPs such as 60 MW Chirgaon Majhgaon (commissioned by year 2016), 24 MW Paudital Lassa (commissioned by year 2016), 70 MW Dhamwari Sunda (commissioned by year 2016) & 45 MW Rupin (commissioned by year 2017) and other small HEPs (will be commissioned in near future) being undertaken by various IPP’s and HP Government. Total available potential in the area is about 524 MW. This 524 MW of power will be evacuated by constructing proposed 220 kV Hatkoti - Gumma (Pragati Nagar) line on twin moose conductor where it will terminate at the proposed 220/400 kV pooling substation Gumma (Pragati Nagar), which will link two circuits of 400 kV Jhakri- Abdullapur Line of PGCIL. This will take care of network reliability and redundancy in the system to evacuate power in case of outage of any transmission line because of unforeseen conditions. Full details of the location of the towers and the profile of the alignment resulting from the surveys undertaken by HPPTCL are presented in Annex 1

1 A proposed project is classified as category B if it includes involuntary resettlement impacts that are not deemed significant which means less than 200 or persons will experience major impacts, which are defined as (i) being physically displaced from housing, or (ii) losing 10% or more of their productive assets (income generating). The level of detail and comprehensiveness of the resettlement plan are commensurate with the significance of the potential impacts and risks. A resettlement plan is required for category B project

2. 400/220 kV GIS pooling sub-station Gumma (Pragati Nagar)

4. The substation is being constructed to pool power from 111 MW under construction Sawra Kuddu HEP (will be commissioned by year 2014) of Himachal Pradesh Power Corporation Limited (HPPCL). Other HEPs which will be commissioned in future include 44 MW Tangnu Romai HEP (commissioned by year 2016) of Independent power producers (IPPs) initially followed by other HEPs such as 60 MW Chirgaon Majhgaon (will be commissioned by year 2016), 24 MW Paudital Lassa (commissioned by year 2016), 70 MW Dhamwari Sunda (will be commissioned by year 2016) & 45 MW Rupin (commissioned by year 2017) and other small HEPs (will be commissioned in near future) being undertaken by various IPP’s and HP Government. As a number of new projects are coming in Pabbar River basin, HPPTCL will implement an Integrated Transmission System that appropriately addresses the usage of the river basin, the limited corridor availability and hilly terrain constraints. Total available potential in the area is about 524 MW. The work involves construction of new 400/220 kV substation at Gumma (Pragati Nagar) in the Shimla district of Himachal Pradesh. The substation is proposed to be constructed on private land identified and to be acquired by HPPTCL

3. 400/220/66 kV GIS Pooling station near Sherpa Colony (Wangtoo)

5. This project is being constructed to evacuate power from 65 MW under construction Kashang-I (will be commissioned by year 2013), 100 MW Tidong-I (will be commissioned by year 2014), 130 MW Kashang-II & III (will be commissioned by year 2014), 20 MW Raura-II (will be commissioned by year 2014), 24 MW Selti Masrang (will be commissioned by year 2014) and other 11 small power houses (commissioning in near future) having a total installed capacity of 81.6 MW through various IPP’s. The substation will cater about 421 MW power from various HEPs of Satluj basin. The substation is proposed to be constructed on vacant and barren government land identified in two separate sites due to limitations of land availability. These sites belong to the HP Government and will be transferred to HPPTCL.

4. 220/66 kV GIS Pooling Station Bhoktoo

6. This project is being constructed to evacuate power from 3 MW Shyang (commissioned by year 2010), 5 MW Tangling (commissioned by year 2011), 5 MW Pangi (commissioned by year 2013) SHEPs of various IPP’s. Projects having an installed capacity of 8 MW have already been commissioned. The substation is proposed to be constructed on vacant and barren government land which is already acquired 7. Tranche 1 of HPTECIP project consists of one transmission line and three pooling substations (details in Table 1). Figure 1 and 2 give the location of each of the projects in the state of Himachal Pradesh.

Table 1: Tranche 1 Subprojects

SNo Name of Work Cost In Million Dollars 1 66/220 kV, 31.5 MVA sub-station at Bhoktoo with LILO of one circuit of 220 kV

Kashang- Bhaba double circuit line. 14.4

2 220 kV D/C (Twin Moose conductor) line from Hatkoti to 220/400 kV Gumma (Pragati Nagar) sub-station

19.4

3 220/400 kV, 1x315 MVA Gumma (Pragati Nagar) substation with LILO of two circuits of 400 kV Jhakri- Abdullapur double circuit line

38.2

4 66/220/400 kV (66/220 kV, 2x80/100 MVA+220/400 kV, 2x315 MVA) substation at Wangtoo with LILO of both circuits of 220 kV Kashang- Bhaba D/C Line and 220 kV interconnection between 220 kV and 400 kV buses.

70.7

Total 142.7

Figure 1: Tranche 1 subprojects in the state of Himachal Pradesh

Figure 2: Tranche 1 - 220 kV Hatkoti-Gumma Transmission Line in the state of Himachal Pradesh

II. SCOPE OF LAND ACQUISITION AND RESETTLEMENT 8. Tranche-1 subproject will entail minimum private land acquisition. Land acquisition will be required for one of the three proposed sub stations at Gumma (Pragati Nagar) in Shimla district where 33 bigha, equivalent to 2.50 hectares (Ha) of private land will be acquired. Land acquisition for this substation will affect one household having 4 persons. The affected household for the substation will lose approximately 14% of his total land holding2. Additionally, construction of transmission lines (220 kV Hatkoti-Gumma - Pragati Nagar - 28 km double circuit line) will require small scale private land acquisition for the tower footings. A total of 75 towers will be constructed, out of which 51 towers will be erected on private land, each of which will require approximately 225 square meters (15m X 15m) of land, 2 towers will be erected on community land/temple and the remaining 22 towers will be erected on government land. Total land requirement for installing the towers footing is approximately 1.15 Ha3. A total of 49 households (321 affected persons) will be affected by the loss of small portions of land for the construction of tower footings.. Hence, a total of 50 households (325 affected persons) will be affected by the loss of small portions of land in tranche-1. However, no physical displacement will occur. A total of 638 trees including 469 fruits, 163 forest trees and 6 non fruit trees will be affected. 6 households will lose more than 10% of their total landholding for the construction of towers’ footings. 2 households are considered to be Women Headed Households (WHH). Additionally, temporary impacts on loss of crop are anticipated on the Right of Way during the construction of transmission line for which the HPPTCL will provide compensation for the loss of crop. As per the current assumption, it is estimated that approximately, 71.44 Ha of land will be considered for crop compensation4. Details on Tranche-2 components and its impact on land acquisition and resettlement are given in Table-2, summary of land acquisition and resettlement is given in Table-3 and details on land requirement for tower footings on private land is given in Table-4 respectively. Details on the inventory of transmission lines is given in Annexure-1

Table 2: Project Components and Impacts on land Acquisition and Resettlement

Sl Nº

Project Components Unit Quantity Impact on Private land Acquisition

and Resettlement

Temporary Impact on Crops

Remarks (Status on Land Ownership and

Possession)

1 400/220 kV GIS pooling sub-station at Gumma (Pragati Nagar)

Number (Area in Ha)

1 (2.50 Ha)

Yes Nil Private land to be acquired by HPPTCL as per the government rules. Section-4 of the Land Acquisition Act, 1894 has been issued. One household having 4 persons will be affected.

2 400/220/66 kV GIS Pooling station near

Number (Area in

1 (4.94 Ha)

Nil Nil This is a government land free from any

2 The total land holding of the affected household for Gumma substation is 233 bigha equivalent to 17.70 Ha 3 225 sqm of land per tower multiplied in to 51 numbers of towers 4 Estimation on temporary loss of crops during construction is based on assumption which as follows:

• Total length of the Line= 28 kms • Standard Right of Way for a 220 Kv Line= 35 Meters • Total Area under the Right of Way= 98 Ha (28X35X1000) • Total forest land = 26.56 Ha • Total Area under private cultivation considered for temporary crop compensation =71.44 Ha

Sl Nº

Project Components Unit Quantity Impact on Private land Acquisition

and Resettlement

Temporary Impact on Crops

Remarks (Status on Land Ownership and

Possession)

Sherpa Colony (Wangtoo)

Ha) encroachment and squatters.

3 220/66 kV GIS Pooling Station Bhoktoo

Number (Area in Ha)

1 (1.5 Ha)

Nil Nil This is a government land free from any encroachment and squatters.

4 220 kV double circuit transmission (twin moose conductor) line from Hatkoti to Gumma (Pragati Nagar),

km

28 Yes 1.15 Ha of permanent land acquisition for 51 tower base

Yes (71.44 Ha of land for crop compensation)

The quantity of the land for crop compensation for temporary impacts has been estimated based on assumptions.

Table 3: Summary of Land Acquisition and Resettlement

Sl. No. Impacts Quantity

1 Total area of private land (Ha) 3.65 2 Total area for crop compensation for temporary Impact (Ha) 71.44 3 Total number of Fruit trees 469 4 Total number of Non fruit trees 06 5 Total Number of Affected Households (HHs) 50 6 Total number of Affected Persons (APs) 325 7 Total Number of Vulnerable Households 8 8 Total number of titleholders 50 9 Total number of non-title holders 0

Table 4: Land Details on Tower Footings on Private land

S. No. Tower No. Ownership

Total Land Holding in

Possession (Square Meter)

Area to be Acquired / Affected Land (Square

Meter)

% of Loss (Affected land compared to

the total landholding

Number of Affected

Households

Number of Affected Persons

Physical Displacement

Households losing more than 10% of

the Productive Assets

Vulnerable Households

1 34 Pvt 22,800 225 1.0 1 4 Nil 0 Nil 2 35 Pvt 21,280 225 1.1 1 9 Nil 0 Nil 3 39 Pvt 3,040 225 7.4 1 7 Nil 0 Nil 4 40 Pvt 5,320 225 4.2 1 7 Nil 0 Nil 5 41 Pvt 3,040 225 7.4 1 9 Nil 0 Nil 6 42 Pvt 4,560 225 4.9 1 9 Nil 0 Nil 7 43 Pvt 3,040 225 7.4 1 5 Nil 0 Nil 8 44 Pvt 6,460 225 3.5 1 9 Nil 0 Nil 9 45 Pvt 3,040 225 7.4 1 6 Nil 0 Nil 10 46 Pvt 2,660 225 8.5 1 5 Nil 0 Nil 11 47 Pvt 6,080 225 3.7 1 6 Nil 0 Nil 12 48 Pvt 5,320 225 4.2 1 9 Nil 0 Nil 13 49 Pvt 9,120 225 2.5 1 7 Nil 0 Nil 14 50 Pvt 7,220 225 3.1 1 9 Nil 0 Nil 15 52 Pvt 10,640 225 2.1 1 8 Nil 0 Nil 16 53 Pvt 14,440 225 1.6 1 3 Nil 0 Nil 17 55 Pvt 6,080 225 3.7 1 6 Nil 0 Nil 18 57 Pvt 4,560 225 4.9 1 4 Nil 0 Nil 19 58 Pvt 2,280 225 9.9 1 10 Nil 0 Nil 20 59 Pvt 760 225 29.6 1 9 Nil 1 Nil 21 60 Pvt 1,520 225 14.8 1 3 Nil 1 Nil 22 61 Pvt 2,66,000 225 0.17 1 13 Nil 0 Nil 23 62 Pvt 225 Nil 0 Nil 24 63 Pvt 3,040 225 7.40 1 7 Nil 0 Nil 25 64 Pvt 1,140 225 19.74 1 11 Nil 1 WHH

S. No. Tower No. Ownership

Total Land Holding in

Possession (Square Meter)

Area to be Acquired / Affected Land (Square

Meter)

% of Loss (Affected land compared to

the total landholding

Number of Affected

Households

Number of Affected Persons

Physical Displacement

Households losing more than 10% of

the Productive Assets

Vulnerable Households

26 66 Pvt 1,520 225 14.80 1 13 Nil 1 Nil 27 67 Pvt 1,520 225 14.80 1 4 Nil 1 Nil 28 70 Pvt 760 225 29.61 1 5 Nil 1 Nil 29 72 Pvt 7,600 225 2.96 1 5 Nil 0 Nil 30 73 Pvt 5,320 225 4.23 1 7 Nil 0 Nil 31 76 Pvt 25,080 225 0.90 1 9 Nil 0 Nil 32 77 Pvt 6,840 225 3.29 1 9 Nil 0 Nil 33 77 A Pvt 8,360 225 2.69 1 9 Nil 0 Nil 34 79 Pvt 37,240 225 1.21 1 8 Nil 0 Nil 35 80 Pvt 225 36 83 Pvt 30,400 225 0.74 1 4 Nil 0 Nil 37 84 Pvt 53,200 225 0.42 1 2 Nil 0 Nil 38 85 Pvt 45,600 225 0.49 1 4 Nil 0 Nil 39 87 Pvt 21,280 225 1.06 1 6 Nil 0 Nil 40 88 Pvt 15,200 225 1.48 1 5 Nil 0 Nil 41 89 Pvt 7,600 225 2.96 1 8 Nil 0 Nil 42 93 Pvt 25,840 225 0.87 1 7 Nil 0 Nil 43 94 Pvt 30,400 225 0.74 1 5 Nil 0 WHH 44 95 Pvt 2,280 225 9.87 1 4 Nil 0 Nil 45 96 Pvt 5,320 225 4.23 1 2 Nil 0 Nil 46 98 Pvt 15,200 225 1.48 1 2 Nil 0 Nil 47 100 Pvt 3,040 225 7.40 1 3 Nil 0 Nil 48 101 Pvt 9,880 225 2.28 1 6 Nil 0 Nil 49 102 Pvt 6,080 225 3.70 1 4 Nil 0 Nil 50 104 Pvt 3,420 225 6.58 1 4 Nil 0 Nil 51 105 Pvt 21,280 225 1.06 1 11 Nil 0 Nil

III. SOCIO ECONOMIC PROFILE

9. Himachal Pradesh is a “rich” state, compared to the rest of the country. Himachal Pradesh is considered as a model of mountain area development, with relatively low poverty rates (7.63%). The success of the region is attributed not only to a prosperous rural economy and high levels of per capita government expenditure but also to focused public interventions, greater participation of women and strong local institutions. Having obtained the status of “tribal state”, the population of HP has benefited from investments and subsidies from the central government. In addition, the State government has approved a series of pro-poor policies, including the abolition of tenancy which resulted in a redistribution of land to the landless to fight exploitation of labor and increase the productivity of the land. Now, 100% of the HP population owns land (with the exception of the immigrant labourers of Nepali descent) and most of them have invested in the highly profitable apple orchards business. Local population, though will still benefit from the Project as it will provide them with a more secure and reliable source of electricity. According to the Human Development Report, 2002 of Himachal Pradesh, life expectancy at birth was 62.8 years higher than the national average of 57.7 years for the period 1986-90. Infant Mortality Rate has fallen from 118 in 1971 to 62 in 1999 (almost half). Decline in crude birth rate from 37.3 in 1971 to 22.6 in 1998 below the national average of 26.5 in 1998 as also crude death rate from 15.6 in 1971 to 7.7 in 1998.Female work force registered an increase from 37.07 per cent in 1981 to 43.66 per cent in 2001. Incidence of income poverty is high, especially in rural areas, so pressure on arable land for food production is increasing. The tranche-1 subprojects cover two districts, Shimla and Kinnaur. According to the human development indices of the UNDP for the district of Himachal Pradesh, the Human Development Index (HDI) Rank of Shimla is 2 and Kinnaur is 3.

10. Himachal Pradesh has a total population of 685,650,9 including 347,389,2 males and 338,261,7 females as per the provisional results of the Census of India 2011, which is only 0.57 per cent of India's total population, placing the state at 21st position and recording a growth of 12.81 per cent. The density of population is 123 per square kilometers. Himachal Pradesh has a literacy rate of 83.78 per cent and gender ratio at 974/1000, according to the 2011 Census figures. Census wise, the state is placed 21st on the population chart Himachal Pradesh has one of the highest literacy rates in India next to Kerala. Hamirpur District is among the top districts in the country for literacy. Education rates among women are quite encouraging in the state. The standard of education in the state has reached to a considerably high level as compared to other states in India. Agriculture contributes over 45% to the net state domestic product. It is the main source of income and employment in Himachal. Over 93% of the population in Himachal depends directly upon agriculture which provides direct employment to 71% of its people. The main cereals grown are wheat, maize, rice and barley. 11. A social analysis was conducted in the subproject area especially along the line route. The survey result revealed that the average family size of the surveyed households is 6.29. The sex ratio of the project affected as estimated from the surveyed households is 828:1000. About 80 % of the households are living in joint family system and the rest 20 % are nuclear families. The survey result reveals that 85% of the families belong to general caste followed by 15% are schedule caste. Agriculture, mainly fruits, (apple) cultivation is the main occupation in the sub project affected area. About 93% of households have apple orchards and remaining households are busy either in service or are having small enterprises. About 98% of households are having land holding and the average possession is 10.23 Bigha equivalents to 0.82 hectares. Apple is the major crop being cultivated by all the households. The average production of apple is 286 boxes per households. The total

average annual income of the household along the project area is Rs. 278,913 out of which agriculture apple production contributes the most to the income. The total annual average expenditure per household is Rs. 60,361 out of which the major expenditure is incurred for the food followed by expenditure on education, clothing and health. All the surveyed households possess household assets like LPG and televisions and radio. There is no major illness reported in the last one year and migration is not prevalent in the project influence zone. The major sources of drinking water piped water and is reported by 100% of the households covered. Around 90% of households are having flush toilet and 10% are having traditional latrine. LPG gas is used by 90% of the households and Wood is used by 10% of the households as cooking fuels. 97 % of the houses are residential and only 3% are commercial structures. Most of the houses are constructed of cement and wooden which is almost 78% of the total households, 11% are brick made and 6% are cemented houses. The average possession of rooms is 5.24 and all the rooms are electrified. All the households are electrified. The main source of electrification is government grid and usually supplied from the government grid.

12. According to the Census of India 2001, 8.2 percent of the Indian population is classified as ST. In comparison to the national figure, Himachal Pradesh has only 4.00 percent of its populations classified as ST (a total of 244,587 peoples). The major tribes of Himachal Pradesh are (1) Bhot, Bodh, (2) Gaddi (Excluding the territories specified in sub-section (1) of section 5 of the Punjab Reorganization Act, 1966 (31 of 1966), other than the Lahaul and Spiti district),(3), Gujjar (excluding the territories specified in sub-section (1) of Section 5 of the Punjab Reorganization Act, 1966 (31 of 1966), (4) Jad, Lamba, Khampa, (5) Kanaura, Kinnara, (6) Lahaula, (7) Pangwala, (8) Swangla, (9) Beta, Beda and (10) Domba, Gara, Zoba. STs in HP are not distinct tribal groups rather they are mainstreamed considering the culture, language, economic activities and source of livelihood,. They have the access to infrastructure facilities such as roads, electricity, schools and hospitals etc. No particular impact or discrimination is expected on indigenous peoples, minorities etc. Provision for additional compensations for IPs is made in the Resettlement framework as vulnerable allowances. No IPs/STs households will be affected by land acquisition. A social screening and census survey was carried out in the project area of influence of tranche-1 components, including areas where land acquisition will be required. Potential impacts of Tranche 1 sub-projects on IPs were evaluated. Of Tranche I components, two new proposed substations located in Sherpa Colony and Bhoktoo in Kinnaur District which is declared as Notified Tribal District (scheduled tribe areas). However, these people are not distinct from the main stream population. Socio-economically, they work in apple cultivation and live well above the poverty line. It is also noted that no land acquisition is required in this project area of Kinnaur as the two proposed substations will be built on government land. Assessment of Tranche 1 subcomponents included consultations with affected persons. Details on the socio-economic profile of the surveyed households are given in Annexure-2

IV. INFORMATION DISCLOSURE, CONSULTATION AND PARTICIPATION 13. Public participation and community consultation has been taken up as an integral part of social and environmental assessment process of the project. Consultation was used as a tool to inform and educate stakeholders about the project. The participatory process helped in involving the local people in project activities. Initial Public consultation has been carried out in the subproject areas with the objectives of minimising probable adverse impacts of the project through alternate design solutions and to achieve speedy implementation of the project through bringing in awareness among the community on the benefits of the project. The broad objectives of the consultation are as follows:

• Understand the views of the people affected, with reference to acquisition of land or loss of property and its due compensation.

• Identification of subproject sites especially the substations locations. • Understand views of people on resettlement options • Identify and assess major economic and social characteristics of the project

area to enable effective planning and implementation. • Examine APs’ opinions on health safety issues during the construction and

selection garbage materials or the waste materials. • Identify levels and extent of community participation in project implementation

and monitoring. • To establish an understanding for identification of overall developmental goals

and benefits of the project. • To develop a thorough coordination between all the stakeholders for the

successful implementation of the project.

14. Consultations were carried out in the month of February to mid-May 2011 with stakeholders during the safeguards assessment of Tranche-1 subprojects. As integral part of the safeguards planning, affected persons and local communities were consulted during the preparation of tranche-1 safeguards documents, i.e., RP and IEE. All stakeholders were informed and the stream of information will continue during the implementation of the project. Public consultations with the project affected communities, stakeholders, and government officials were carried out at 27 villages around the proposed transmission line/substations. Additionally, focused group discussions were also conducted in the villages along the transmission line and at substation sites. Local communities generally support the proposed investment components, as better electricity supply is expected to improve their life. They also expect that employment opportunities will be created. Summary of the list of consultation is given in Table 5 and the details are given in Annexure-3

Table 5: Summary Consultations Sl No Village Panchyat Districts Distance from the

District Head Quarters

Number of Participants

Villages involved in consultation at Shimla district for 220 kV (Hatkoti Gumma) Transmission Line 1 Bakneot Purag Shimla 65 km 09 2 Dalsar Bagdomehar Shimla 66 km 09 3 Pandrog Purag Shimla 67 km 08 4 Pudag Pudag Shimla 65 km 06 5 Galera Bagdomehar Shimla 62 km 05 6 Naktada Deem Shimla 91 km 06 7 Deem Deem Shimla 90 km 05 8 Khara Pathar Deem Shimla 88 km 07 9 Chandel Dharkoti Shimla 80 km 06

10 Dharkoti Patshal Shimla 80 km 07 11 Jhandoli Dharkoti Shimla 81 km 10 12 Sholi Kot kaina Shimla 96 km 07 13 Kaina Kot kaina Shimla 93 km 08 14 Vadot Thana Shimla 105 km 06 15 Rampuri Deem Shimla 92 km 06 16 Virat Nagar (Hatkoti ) Saraswati Nagar Shimla 100 km 09 17 Sari Sari Panchayat Shimla 90 km 08 18 Astandli Sari Shimla 96 km 05 19 Mandhol Mandhol Shimla 110 km 07 20 Mangara Sari Shimla 98 km 07 21 Magouta Kotkhai Shimla 105 km 14 22 Kot Kotkhai Shimla 105 km 13 23 Mhanghali Pudag Shimla 55 km 09 24 Marathu Tharola Shimla 97 km 08

Sl No Village Panchyat Districts Distance from the District Head

Quarters

Number of Participants

25 Purjali Bagdomehar Shimla 53 km 06 26 Bagori Bagori Shimla 50 km 02

Consultation at Shimla district for 400/220 kV Gumma (Pragati Nagar) Substations 1 Bagori Bagori Shimla 50 km 02

Consultation at Kinnaur district for 400/220 kV Sherpa Colony Substations1 Katgaon Katgaon Kinnaur 25 05

15. Section-4 notification for private land acquisition has been issued and published in the gazette for Gumma substation. Copy of the notification is given in Annexure 4. Additionally, notification as per the Electricity Act, 2003 on project information was disclosed in the local news paper on 28 April 2011. Copy of the disclosure notification is given in Annexure-5. HPPTCL will provide relevant resettlement information, in a timely manner, in an accessible place and in a form and language (Hindi/English) understandable to affected persons and other stakeholders. The draft RP will be made available in relevant local government agencies and in relevant HPPTCL/PMU and site offices before the appraisal. The summary RP will be made available in Hindi language. Finalized RP will be disclosed in ADB’s website and in HPPTCL website; and information dissemination and consultation will continue throughout Investment Program implementation. The Resettlement Framework (RF) and the Indigenous Peoples Planning Framework (IPPF) will also be disclosed in the website

V. GRIEVANCE REDRESS MECHANISM

16. Through its Environment and Social Safeguards Policy5, HPPTCL has established a Grievance Redressal Mechanism (GRM) having suitable grievance redressal procedure for the project affected persons. The grievance redress mechanism would address affected persons’ concerns and complaints promptly, using an understandable and transparent process that is gender responsive, culturally appropriate, and readily accessible to the affected persons at no costs and without retribution. This GRM consists of a Grievance Redressal Committee consists of the following persons as listed in Table 6 below:

Table 6: Constitution of Grievance Redress Committee

1 Project Head Chairman 2 Head of Finance wing at the project level Member 3 Representative of local Panchayat Member 4 Representative of contractor Member 5 Project Environment/RR staff Member

Secretary 17. The Grievance Redress Mechanism (GRM) would provide an effective approach for resolution of complaints and issues of the affected community. Project Management Unit (PMU) shall formulate procedures for implementing the GRM. The PIU shall undertake GRM’s initiatives that include procedures of taking/ recording complaints, handling of on-the-spot resolution of minor problems, taking care of complainants and provisions of responses to distressed stakeholders etc. paying particular attention to the impacts on vulnerable groups. Environmental and social grievances will be handled in accordance to the project grievance redress mechanism. Open and transparent dialogue will be maintained with project affected persons as and when needed, in compliance with ADB safeguard policy requirements. The Grievance Redress Mechanism (GRM) for the project provides an 5 Finalized in May 2011

effective approach for complaints and resolution of issues made by the affected community in reliable way. This mechanism will remain active throughout the life cycle of the project. Grievances of APs (minor grievance) will first be brought to the attention at the PIU level. Grievances not redressed by the PIU staff (field level) will be brought to the Grievance Redress Committee (GRC) at PMU level. The GRC will meet every month (if grievances are brought to the Committee), determine the merit of each grievance, and resolve grievances within a month of receiving the complaint—failing which the AP will be free to approach appropriate other forum or court of Law for redressal. Grievance redress mechanism is depicted in Figure 3.

Figure 3: Grievance Redress Mechanism

VI. POLICY AND LEGAL FRAMEWORK

18. The policy framework and entitlements for the Program are based on national laws: The Land Acquisition Act, 1894 (LAA, amended in 1984) when private land acquisition is required and The National Rehabilitation and Resettlement Policy, 2007 (NRRP); ADB’s Safeguards Policy Statement 2009. Additionally, HPPTL’s policies, (i) Environment and Social Safeguard Policy, May 2011 (ESSP) and (ii) Resettlement, Relief, Rehabilitation and Compensation Policy, May, 2011 (RRRCP) were also taken in to consideration. A summary of applicable acts and policies is presented in the following sections and the detailed policy review and comparison is provided in RF 19. Land Acquisition Act-1894: The Land acquisition Act (LAA) 1894, as amended in 1984 provides the legal basis for land acquisition for a public purpose in India. It enables the State Government to acquire private lands for a public purpose, and seeks to ensure that no person is deprived of land except under the Act. Under the Land Acquisition Act 1894, compensation is paid only to the legal titleholders.

20. National Rehabilitation and Resettlement Policy, 2007 (NRRP-2007): The National Rehabilitation and Resettlement Policy, 2007 (NRRP-2007) was adopted by the Government of India in 31st October, 2007 to address development-induced resettlement issues. The policy provides for the basic minimum requirements, and all projects leading to

Grievance Not Redressed (Major Grievances)

Aggrieved Party (Affected Persons) Grievance Redressed

Grievance Redress Committee (GRC) Grievance Redressed

PIU(Filed Level Staff/ESC)

Within 15 working days

Within 30 working days

Appropriate Forum/Court of Law

Grievance Not Addressed

involuntary displacement of people must address the rehabilitation and resettlement issues comprehensively. The State Governments, Public Sector Undertakings or agencies, and other requiring bodies shall be at liberty to put in place greater benefit levels than those prescribed in the NRRP-2007. The principles of this policy may also apply to the rehabilitation and resettlement of persons involuntarily displaced permanently due to any other reason. 21. HPPTCL’ s Policy on Safeguards: HPPTCL is committed to the goal of sustainable development of power transmission network in harmony with nature and natural resources and seeks to avoid, minimize, mitigate or compensate adverse environmental and social impacts. HPPTCL approved its safeguards Policies in the month of May, 2011 which are (i) Environmental and Social Safeguards Policy (ESSP) and (ii) Resettlement, Relief, Rehabilitation and Compensation Policy (RRRCP). The Goal of HPPCL’s Environmental and Social Safeguards Policy (ESSP) is to ensure that development of power transmission system network in environmentally and socially sustainable manner and to bring clarity and transparency about it with public disclosure. HPPTCL shall proactively and voluntarily take all necessary steps to ensure environmental and social sustainability of all its projects. HPPTCL has developed this document of its corporate Environmental and Social Safeguards Policy (ESSP) to address the environmental and socio-economic issues arising from its activities guided by the basic principles of Avoidance, Minimization and Mitigation. The ESSP outlines HPPTCL’s approach and commitment to deal with environmental and social issues relating to its transmission projects. The main aim of ESSP is to give a human face to corporate functioning and to move away from the classical cost-benefit approach to the larger realm of Corporate Social Responsibility, while mainstreaming the environmental and social concerns in its operations. The ESSP has the special provision to deal with social safeguards through its special policy, RRRCP. The RRRCP lays down the guiding policy of HPPTCL for preparation of project specific R&R Plans and its implementation for the transmission projects under HPPTCL. 22. ADB’s Safeguard Policy Statement, 2009 (SPS): ADB has adopted Safeguard Policy Statement (SPS) in 2009 including safeguard requirements for environment, involuntary resettlement and indigenous people. The objective of the involuntary resettlement policy is to avoid involuntary resettlement wherever possible; to minimize involuntary resettlement by exploring project and design alternatives; to enhance, or at least restore, the livelihoods of all displaced persons in real terms relative to pre-project levels; and to improve the standards of living of the displaced poor and other vulnerable groups. 23. The involuntary resettlement safeguards covers physical displacement (relocation, loss of residential land, or loss of shelter) and economic displacement (loss of land, assets, access to assets, income sources, or means of livelihoods) as a result of (i) involuntary acquisition of land, or (ii) involuntary restrictions on land use or on access to legally designated parks and protected areas. It covers them whether such losses and involuntary restrictions are full or partial, permanent or temporary. Followings are the basic policy principle of ADB’s SPS,2009:

• Identification of past, present, and future involuntary resettlement impacts and risks and determination of the scope of resettlement planning.

• Carry out meaningful consultations with affected persons, host communities, and concerned non-government organizations.

• Improvement or at least restoration of the livelihoods of all displaced persons, • Ensure physically and economically displaced persons with needed assistance. • Improvement of the standards of living of the displaced poor and other

vulnerable groups.

• Development of procedures in a transparent, consistent, and equitable manner if land acquisition is through negotiated settlement,

• Ensure that displaced persons without titles to land or any recognizable legal rights to land are eligible for resettlement assistance and compensation for loss of non-land assets.

• Preparation of a resettlement plan elaborating on displaced persons’ entitlements, the income and livelihood restoration strategy, institutional arrangements, monitoring and reporting framework, budget, and time-bound implementation schedule.

• Disclosure of resettlement plan, including documentation of the consultation process in a timely manner to affected persons and other stakeholders.

• Execution of involuntary resettlement as part of a development project or program.

• Payment of compensation and provide other resettlement entitlements before physical or economic displacement.

• Monitoring and assessment of resettlement outcomes, their impacts on the standards of living of displaced persons

24. Based on the above analysis of applicable legal and policy frameworks of government and in consistent with ADB’s policy requirements, broad resettlement principle for the program shall be the following:

• Involuntary resettlement would be avoided wherever possible or minimized as much as possible by exploring project and design alternatives.

• Subprojects under the program will be screened to identify past, present, and future involuntary resettlement impacts and risks. The scope of resettlement planning will be determined through a survey and/or census of displaced persons, including a gender analysis, specifically related to resettlement impacts and risks.

• Consultations with affected persons, host communities, and concerned non-government organizations will be carried out and all displaced persons will be informed of their entitlements and resettlement options. AP’s participation in planning, implementation, and monitoring and evaluation of resettlement programs will be ensured.

• Particular attention will be paid to the needs of vulnerable groups, especially those below the poverty line, the landless, women headed households, and scheduled tribes/indigenous peoples (IP), and those without legal title to land, and ensure their participation in consultations.

• An effective grievance redress mechanism will be established to receive and facilitate resolution of the affected persons’ concerns. Where involuntary resettlement impacts and risks are highly complex and sensitive, compensation and resettlement decisions should be preceded by a social preparation phase.

• Livelihoods of all displaced persons will be improved or at least restored through (i) land-based resettlement strategies when affected livelihoods are land based where possible or cash compensation at replacement value for land when the loss of land does not undermine livelihoods, (ii) prompt replacement of assets with access to assets of equal or higher value, (iii) prompt compensation at full

replacement cost for assets that cannot be restored, and (iv) additional revenues and services through benefit sharing schemes where possible.

• Physically and economically displaced persons will be provided with needed assistance, including (i) if there is relocation, secured tenure to relocation land, better housing at resettlement sites with comparable access to employment and production opportunities, integration of resettled persons economically and socially into their host communities, and extension of project benefits to host communities; (ii) transitional support and development assistance, such as land development, credit facilities, training, or employment opportunities; and (iii) civic infrastructure and community services, as required.

• Standards of living of displaced poor and other vulnerable groups, including women, will be improved to at least national minimum standards. In rural areas legal and affordable access to land and resources will be provided, and in urban areas appropriate income sources and legal and affordable access to adequate housing will be provided to the displaced poor.

• If land acquisition is through negotiated settlement, procedures will be developed in a transparent, consistent, and equitable manner to ensure that those people who enter into negotiated settlements will maintain the same or better income and livelihood status. If, however, the negotiated settlement fails, the normal procedure of land acquisition will be followed.

• Displaced persons without titles to land or any recognizable legal rights to land will be ensured that they are eligible for resettlement assistance and compensation for loss of non-land assets.

• A resettlement plan will be prepared elaborating on displaced persons’ entitlements, the income and livelihood restoration strategy, institutional arrangements, monitoring and reporting framework, budget, and time-bound implementation schedule.

• The draft resettlement plan, including documentation of the consultation process will be disclosed in a timely manner, before project appraisal, in an accessible place and in a form and language(s) understandable to affected persons and other stakeholders. The final resettlement plan and its updates will also be disclosed to affected persons and other stakeholders.

• Involuntary resettlement will be conceived and executed as part of a development project or program. Full costs of resettlement will be included in the presentation of project’s costs and benefits. For a project with significant involuntary resettlement impacts, consider implementing the involuntary resettlement component of the project as a stand-alone operation.

• All compensation will be paid and other resettlement entitlements will be provided before physical or economic displacement. The resettlement plan will be implemented under close supervision throughout project implementation.

• Resettlement outcomes, their impacts on the standards of living of displaced persons will be monitored; it will be accessed whether the objectives of the resettlement plan have been achieved by taking into account the baseline

conditions and the results of resettlement monitoring. Monitoring reports will be disclosed to APs.

• Land acquisition for the project would be done as per LAA,1894

• The uneconomic residual land remaining after land acquisition will be acquired as per the provisions of LAA, if the owner is willing to sell. The owner of such land/property will have the right to seek acquisition of his entire contiguous holding/ property provided the residual land remains unviable.

• People moving in the project area after the cut-off date will not be entitled to any assistance. In case of land acquisition, the date of publication of preliminary notification for acquisition under section 4 of the LAA, 1894 will be treated as the cut-off date. For non-titleholders the date of project census survey or a similar designated date declared by the executing agency will be considered as cut-off date. However, non title holders will have to prove that they have been living in the affected area or using the land/asset not less than six months prior to the declaration of cut-off-date in order to be eligible for project assistance.

• All common property resources (CPR) lost due to the project will be replaced or

compensated by the project. 25. The project will recognize three types of displaced persons like (i) persons with formal legal rights to land lost in its entirety or in part; (ii) persons who lost the land they occupy in its entirety or in part who have no formal legal rights to such land, but who have claims to such lands that are recognized or recognizable under national laws; and (iii) persons who lost the land they occupy in its entirety or in part who have neither formal legal rights nor recognized or recognizable claims to such land. The involuntary resettlement requirements apply to all three types of displaced persons.

VII. ENTITLEMENTS, ASSISTANCE AND BENEFITS 26. Compensation for the lost assets to all affected persons will be paid on the basis of replacement cost. Resettlement assistance for lost income and livelihoods will be provided to both title holders and non-title holders. Special resettlement and rehabilitation measures will be made available to the vulnerable groups. APs entitled for compensation or at least rehabilitation provisions under the Project are (i) All APs losing land either covered by legal title/traditional land rights, or without legal status; (ii) Tenants and sharecroppers whether registered or not; (iii) Owners of buildings, crops, plants, or other objects attached to the land; and (iv) APs losing business, income, and salaries. Compensation eligibility is limited by a cut-off date to be set for the subproject. For the legal title holder, the issuance of Section 4 notification of LA Act will serve as the cut-off-date. For non-titleholder, the day of the census survey will serve as the cut-off-date. APs who settle in the affected areas after the cut-off date will not be eligible for compensation. They, however will be given sufficient advance notice, requested to vacate premises and dismantle affected structures prior to project implementation. The entitlement matrix is described in Table 7.

Table 7: Entitlement Matrix Type of Losses Definition of APs Entitlement Details

1. Land Loss of agricultural land

• Titled owners • affected persons

• Compensation based on market/replacement

• In case of compulsory acquisition of land, Compensation will be based on the Land

Type of Losses Definition of APs Entitlement Details (APs) with traditional land rights

value • Resettlement assistance • Additional Assistance to

vulnerable6 APs

Acquisition Act (inclusive of 30% solatium and 12% interest)

• In case of land to be possessed by the project authority with mutual and voluntary consent of the affected people, compensation will be paid on negotiated market price

• In case of land to be acquired by paying yearly lease money, the titleholder will get yearly compensation as decided by the land acquisition authorities for the life of the project that is 30 years. The compensation once decided shall not be revised during the operation of the lease agreement.

• Transaction costs (documentary stamps, registration costs, etc.) Will be borne by the project authority during registration.

• If the residual plot(s) is (are) not viable, i.e., the AP becomes a marginal farmer, resettlement assistances will be paid in the form of transitional allowances based on three months of minimum wage

• Additional allowances will be paid to vulnerable APs based on three months of minimum wage

2. Trees and Crops Loss of Trees • Land holders

• Share- croppers • Lease holders

• Compensation at Market value to be computed with assistance of horticulture department

• Advance notice to APs to harvest fruits and remove trees.

• For fruit bearing trees compensation at average fruit production for next productive years to be computed at current market value.

• For timber trees compensation at market cost based on type of trees.

Loss of Crops • Land holders • Share- croppers • Lease holders

• Compensation at Market value to be computed with assistance of agriculture department

• Advance notice to APs to harvest crops. • In case of standing crops, cash compensation at

current market cost to be calculated of mature crops based on average production.

3. Government land and Property Government Property (Loss of Land)

- • Lump sum compensation as per government rules

• Departmental transfer of land.

4. Community and Cultural Sites Religious structures, land, Community structures, trust, etc.

• Affected community

• Conservation, protection and compensatory replacement (Schools, community centers, markets, health centers, shrines, other religious sites, places of worship, burial sites, rights to food, medicine, and natural resources)

• Impacts will be documented and mitigated. Cultural properties will be conserved through special measures such as relocation in consultation with the community.

5. Temporary Loss Temporary loss of land and temporary damage on loss of crops during construction

• All APs losing land and crops on temporary basis during the construction period of the lines

• Farming

• Notice to harvest standing crops

• Compensation at market value for one season

• Restoration

• Provision of rent for period of occupation for legal titleholders.

• Compensation for assets lost at replacement value.

• Restoration of land to previous or better quality. • Additionally, Cash Compensation will be paid for

the temporary damage of crop under the RoW

6 women-headed households, scheduled tribe households, below poverty line households, households headed by physically handicapped or disabled persons and severely affected households (household losing more than 10% of productive asset)

Type of Losses Definition of APs Entitlement Details households

• Sharecroppers • Tenants • non-titled

households

during the maintenance and repair after the construction. In case there is a need for repair or maintenance of the transmission lines in the future, the project authorities would consult with land owners land owners for access to the land for maintenance and repairs, when necessary, and that the land owners would continue to use the land for farming activities.

6. Vulnerable Households Impacts on vulnerable APs

• All impacts • Vulnerable APs • Additional assistance based on three months of minimum wage.

• Vulnerable households will be given priority in project construction employment where feasible.

7. Unanticipated Impacts Other Impacts Not Identified

• Affected households or individuals

• Compensation and assistance

• Unforeseen impacts will be documented and mitigated based on the principles agreed upon in the resettlement framework.

8. Additional Benefits by HPPPTCL to the project area. Additional Schemes applicable only to projects with cost of Rs. 50 crores7 and more

applicable to those projects only which are more than Rs. 50 crore worth

Various RR schemes Following additional RR Schemes shall be implemented in the projects with Project Cost of Rs. 50 Crores or more.

• Merit & Support Scholarship Scheme • Medical Fund • Training cum Awareness Camp • Provision of Self Employment • Award of Petty Contracts & Hiring of Vehicle

VIII. RELOCATION AND INCOME RESTORATION 27. Tranche-1 subproject will not result in any physical displacement except minor land acquisition and temporary impacts on loss of crops at few places during the construction. Compensation will be paid by HPPTCL as per the entitlement matrix. Allowance based on three months minimum wage rates will be paid to the affected vulnerable households. Additionally, vulnerable households will be given priority for employment during construction. HPPTCL and contractor will ensure that advance notice is issued to the APs prior to the start of construction works and that compensation is also completed before then. In case of any maintenance work in the future, HPPTCL and contractor will pay the APs for any loss of crop due to the work. Compensation and assistance to affected persons must be made prior to possession of land/assets and prior to the award of civil works contracts.

IX. RESETTLEMENT BUDGET AND FINANCING PLAN 28. The resettlement cost estimate for this subproject includes eligible compensation, resettlement assistance and support cost for RP implementation. These are part of the overall project cost. This is a tentative budget. The unit cost for land and other assets in this budget has been derived through rapid field appraisal, consultation with affected households and relevant government authorities. Contingency provision equivalent to 5% of the total cost has also been made to accommodate any variations from this estimate. The components of the resettlement cost include various features such as, compensation for land; compensation for crops; solatium for land acquisition, allowances for vulnerable groups and cost for implementation of RP. The total land acquisition and resettlement cost for the Tranche 1 subproject is estimated to be INR 156.04 million. Land acquisition and 7 Equivalent to aapproximately 11 million USD

resettlement costs will be considered as an integral component of sub-project costs. The HPPTCL will make the funds available in its annual budget for the disbursement of compensation and assistance. Detail cost estimate is given in Table 8.

Table 8: Resettlement Cost Item Unit Unit Rates

(INR) Quantity Total Cost (INR)

A: Compensation for Acquisition of Private Land A1 Agriculture Land (Private) for

Permanent Acquisition Ha 26,320,000 3.65

96,068,000

A2 Fruit Trees Numbers 25000

469

11,725,000

A-3 Non Fruit Trees Numbers 5000

6

30000

A3 Temporary Loss of agricultural Land for crop compensation for Lines

Ha 40,000 71.44 2,857,600

Subtotal: A 11,0680,600

B: Assistance

B1 Land Acquisition (Agriculture) in case of Permanent Acquisition

30% Solatium 33,204,180

B2 Allowances for Vulnerable Households

Lump Sum 13500

9 121,500

Subtotal: B 33,325,680 C: Support Cost for Implementation of RP

C1 Resettlement Specialist in PMU Person month 150,000 24 3,600,000

C2 Monitoring Lump Sum 5,00,000 Administrative Cost Lump Sum 5,00,000

Subtotal C 4,600,000 TOTAL 148,606,280 Contingency (5% ) 7,430,314 Grand Total 156,036,594 Grand Total (Million INR) 156.04 Grand Total (Million USD) 3.55

X. INSTITUTIONAL ARRANGEMENTS

29. HPPTCL will serve as the Executing Agency (EA) as well as the Implementing Agency (lA) for the investment program and for the Tranche-1 implementation. HPPTCL will establish a Project Management Unit (PMU) for implementing the ADB loan. Associated with the PMU, an Environment and Social Cell (ESC) will be established at HPPTCL which will be headed by Chief Environment Specialist who will be assisted by one Environment Specialist and one Social Development cum Resettlement Specialist. The Project Management Unit (PMU) at corporate level is headed by Senior Project Manager (Planning) who will be assisted by DGM’s from various functions – Administration and Finance, Projects Planning and Design, Procurement and contracts, Environment and Social Cell and Projects Construction. Project Implementation Units (PIUs) at divisional level of the project construction unit are headed by Executive Engineers at four locations – Rohru (Shimla), Chamba, Bhabanagar (Kinnaur) and Sarabhai (Kullu). The Environment and Social cell (ESC) at the corporate level monitors the policy and implementation of safeguards impacts of all projects of HPPTCL.

30. Project Implementation Unit (PIU) will assume primary responsibility for the

safeguards assessment on the site as well as implementation of RPs for their respective components in consultation with ESC. Keeping in view the capacity of HPPTCL, it is proposed that the ESC head to coordinate with each PIU along with other engineering units to address safeguard issues. Additionally, PIU will designate concerned engineer to look after social and resettlement issues at project site. 31. The Chief Specialist Environment must be assisted by the PIU for planning, implementing and monitoring of the RP. The duties of the ESC Specialists (in-charge of environment and social) will include at a minimum: (i) oversight of PIU for implementing the RPs with timely payment of compensation and assistance to the APs (ii) liaising with the PIU and seeking their help to solve any grievance and related issues of project implementation; and (iii) preparation of monitoring reports every 6 months (as required by ADB).

32. For Tranche-1 sub-project RPs, HPPTCL will do the overall coordination, preparation, planning, implementation, and financing of all activities. Additional third-party services may be employed by the HPPTCL as necessary. The EA (HPPTCL) through its PMU will ensure that key institutions including local governments are involved in RP preparation, updation and implementation. Further details on agencies responsible for RP activities are in Table 9.

Table 9: Institutional Roles and Responsibilities for Resettlement activities

Activity Responsible Agency Sub-project Initiation Stage Establishing PMU/PIU EA (HPPTCL) Establishing ESC in PMU EA (HPPTCL) Designating safeguard Specialist in PMU/ESC EA (HPPTCL) Finalization of sites for sub-projects EA (HPPTCL)/PMU/PIU Disclosure of proposed land acquisition and sub-project details by issuing Public Notice

EA (HPPTCL)/PMU/PIU

Meetings at community/household level with APs PMU/PIU RP Preparation and Updating Stage Conducting Census of all APs PMU/PIU/ESC Conducting consultation/FGDs/meetings PMU/PIU/ESC Computation of replacement values of land/properties PMU/PIU/ESC/Competent Authority Finalizing compensation packages and entitlements PMU/PIU/ESC/ Competent Authority Disclosure of final entitlements and rehabilitation packages PMU/PIU/ESC Approval of RP EA/ADB Sale deed execution and payment EA/PMU/PIU/LAO/Appropriate

Government Department Taking possession of land EA/PMU RP Implementation Stage Sale deed execution and payment EA/PMU/PIU/Appropriate

Government Department Taking possession of land EA/PMU/PIU Implementation of proposed rehabilitation measures PMU/PIU/ESC Consultations with APs during rehabilitation activities PMU/PIU/ESC Grievances redress PMU/PIU/GRC Internal monitoring PMU/ PIU/ESC External monitoring8 External Agency

ADB-Asian Development Bank, AP-affected person, EA-Executing Agency, ESC- Environment Social Cell, FGD-focus group discussion, GRC-Grievance Redress Committee, HPPTCL- Himachal Pradesh Power Transmission Corporation Limited, PIU- Project Implementation Unit, PMU- Project Management Unit, RP-Resettlement Plan,

8 External monitoring is required for significant IR impact especially for category A project.

XI. IMPLEMENTATION SCHEDULE

33. All land acquisition, resettlement, and compensation for a sub-project will be completed before award of civil works contracts. All land required will be provided free of encumbrances to the contractor prior to handing over of sub-project sites and the start of civil works. The implementation of the RP will include: (i) identification of cut-off-date and notification, (ii) verification of losses and extent of impacts, (iii) finalization of entitlements and distribution of identity cards, (iv) consultations with APs on their needs and priorities, and (v) resettlement, provision of compensation and assistance, and income restoration for APs. However, public consultation and monitoring will be continued on an intermittent basis as needed during the entire duration of the project. A tentative implementation schedule is described in Table 10.

Table 10: Implementation Schedule

Subproject R&R Component/Activities Months

1 2 3 4 5 6 7 8 9 10 11 12Identification of sub project and notification Community Consultation

Identification of land and Census Survey Submission of RP for ADB Approval Disclosure of RP Establishment of PMU and PIU Establishment of ESMU Establishment of GRC Issue compensation to APs

Payment of all eligible assistance Initiation of Rehabilitation Measures

Schedule for Civil Work Monitoring

XII. MONITORING AND REPORTING

34. Monitoring is the responsibility of HPPTCL through its PMU and the Environment Social Cell and it will submit bi-annual monitoring reports to ADB for review .The extent of monitoring activities, including their scope will be commensurate with the project’s risks and impacts. ADB will require HPPTCL to establish and maintain procedures to monitor the progress of implementation of safeguard plans; verify the compliance with safeguard measures and their progress toward release of entitlements and benefits; document and disclose monitoring results and identify necessary corrective and preventive actions in the periodic monitoring reports and follow up on these actions to ensure progress toward the desired outcomes. Monitoring reports documenting progress on resettlement implementation and resettlement plan completion reports will be provided by HPPTCL through its PMU to ADB for review on semi annual basis. A sample monitoring checklist is given in Annexure-6 which may further be modified as per the need of the project.

ANNEXURES 1: INVENTORISATION DETAILS OF HATKOTI – GUMMA TRANSMISSION LINE SNo. ANGLE POINT

(FROM –TO) D

ista

nce

betw

een

two

angl

e po

ints

App

roxi

mat

e D

ista

nce

of

tran

smis

sion

lin

e fr

om n

earb

y

Nam

e of

Vill

ages

Nam

e of

Teh

sil

Nam

e of

Dis

tric

t

No.

of T

ower

s

Are

a of

tow

er

(in M

²)

Are

a un

der t

he

RO

W (i

n M

²)

Ow

ners

hip

of la

nd

(priv

ate,

Gov

t. Fo

rest

)

Use

of L

and

Nam

e of

Cro

ps

Num

ber o

f tre

es

unde

r cut

ting

No.

of a

ffect

ed

Hou

seho

ld

No.

of a

ffect

ed

trib

al h

ouse

hold

s (if

Any

)

1 T-34 T-35 181 150 Badhot Jubbal Shimla 1 225 6154 Private Cultivated Apple 5 1 Nil

2 T-35 T-36 500 200 Badhot Jubbal Shimla 1 225 17000 Private Cultivated Apple 10 1 Nil

3 T-36 T-37 161 250 Hatkoti Jubbal Shimla 1 225 5474 HP Govt Cultivated Apple 12 Nil Nil

4 T-37 T-38 74 250 Hatkoti Jubbal Shimla 1 225 2516 Mandir Cultivated Apple 6 Nil Nil

5 T-38 T-39 527 280 Hatkoti Jubbal Shimla 1 225 17918 Mandir Cultivated Apple 12 Nil Nil

6 T-39 T-40 544 200 Sari Jubbal Shimla 1 225 18496 Private Uncultivated Apricot 1 1 Nil

7 T-40 T-41 515 100 Sari Jubbal Shimla 1 225 17510 Private Cultivated Apple 12 1 Nil

8 T-41 T-42 184 110 Sari Jubbal Shimla 1 225 6256 Private Cultivated Apple, Apricot 12 1 Nil

9 T-42 T-43 267 200 Sari Jubbal Shimla 1 225 9078 Private Cultivated Apple 13 1 Nil

10 T-43 T-44 199 200 Sari Jubbal Shimla 1 225 6766 Private Cultivated Apple 20 1 Nil

11 T-44 T-45 378 300 Astandli Jubbal Shimla 1 225 12852 Private Uncultivated -- 1 Nil

12 T-45 T-46 470 200 Astandli Jubbal Shimla 1 225 15980 Private Cultivated Apple 24 1 Nil

13 T-46 T-47 456 250 Astandli Jubbal Shimla 1 225 15504 Private Cultivated Apple 4 1 Nil

14 T-47 T-48 189 500 Mandhol Jubbal Shimla 1 225 6426 Private Uncultivated 1 Nil

15 T-48 T-49 160 500 Mandhol Jubbal Shimla 1 225 5440 Private Cultivated Apple 5 1 Nil

16 T-49 T-50 638 110 Mandhol Jubbal Shimla 1 225 21692 Private Cultivated Apple 3 1 Nil

17 T-50 T-51 252 150 Manghara Jubbal Shimla 1 225 8568 Private Cultivated Apricot 4 1 Nil

18 T-51 T-52 269 150 Manghara Jubbal Shimla 1 225 9146 HP Govt Uncultivated -- - nil Nil

19 T-52 T-53 668 50 Kot Jubbal Shimla 1 225 22712 HP Govt Cultivated Apple 13 Nil Nil

20 T-53 T-54 471 40 Gahir Jubbal Shimla 1 225 16014 Private Cultivated Apple 10 1 Nil

21 T-54 T-55 351 220 Sholi Jubbal Shimla 1 225 11934 HP Govt Uncultivated Forest trees 14* Nil Nil

22 T-55 T-56 115 50 Kayana Jubbal Shimla 1 225 3910 Private Cultivated Apple, Forest 10 1 Nil

SNo. ANGLE POINT (FROM –TO)

Dis

tanc

e be

twee

n tw

o an

gle

poin

ts

App

roxi

mat

e D

ista

nce

of

tran

smis

sion

lin

e fr

om n

earb

y

Nam

e of

Vill

ages

Nam

e of

Teh

sil

Nam

e of

Dis

tric

t

No.

of T

ower

s

Are

a of

tow

er

(in M

²)

Are

a un

der t

he

RO

W (i

n M

²)

Ow

ners

hip

of la

nd

(priv

ate,

Gov

t. Fo

rest

)

Use

of L

and

Nam

e of

Cro

ps

Num

ber o

f tre

es

unde

r cut

ting

No.

of a

ffect

ed

Hou

seho

ld

No.

of a

ffect

ed

trib

al h

ouse

hold

s (if

Any

)

trees

23 T-56 T-57 168 200 Kayana Jubbal Shimla 1 225 5712 HP Govt Uncultivated Ban Oak 6 Nil Nil

24 T-57 T-58 754 100 Kayana Jubbal Shimla 1 225 25636 Private Cultivated Apple 10 1 Nil

25 T-58 T-59 151 150 Rampuri Jubbal Shimla 1 225 5134 Private Cultivated Apple 8 1 Nil

26 T-59 T-60 260 150 Rampuri Jubbal Shimla 1 225 8840 Private Cultivated Apple, Forest trees

25* 1 Nil

27 T-60 T-61 305 60 Rampuri Jubbal Shimla 1 225 10370 Private Cultivated Apple 6 1 Nil

28 T-61 T-62 350 250 Naktara Jubbal Shimla 1 225 11900 Private Uncultivated Forest trees 17* 1 Nil

29 T-62 T-63 392 100 Naktara Jubbal Shimla 1 225 13328 Private Uncultivated -- 0 1

Nil

30 T-63 T-64 290 125 Deem Jubbal Shimla 1 225 9860 Private Cultivated Apple 9 Nil

31 T-64 T-65 168 75 Deem Jubbal Shimla 1 225 5712 Private Cultivated Apple 4 1 Nil

32 T-65 T-66 114 100 Deem Jubbal Shimla 1 225 3876 HP Govt Cultivated Apple, 15 Nil Nil

33 T-66 T-67 455 25 Deem Jubbal Shimla 1 225 15470 Private Cultivated Apple, Forest trees

30* 1 Nil

34 T-67 T-67A 220 100 Deem Jubbal Shimla 1 225 7480 Private Cultivated Apple, Forest trees

55* 1 Nil

35 T-67A T-68 546 50 Deem Jubbal Shimla 1 225 18564 Private Uncultivated Forest trees 47* 1 Nil

36 T-68 T-69 175 50 Deem Jubbal Shimla 1 225 5950 HP Govt Cultivated Apple, Forest trees

23* Nil Nil

37 T-69 T-70 331 100 Kharapathar Jubbal Shimla 1 225 11254 HP Govt Uncultivated 17 Nil Nil

38 T-70 T-71 261 150 Kharapathar Jubbal Shimla 1 225 8874 Private Cultivated Apple 8 1 Nil

39 T-71 T-72 189 100 Kharapathar Jubbal Shimla 1 225 6426 HP Govt Cultivated Apple 10 Nil Nil

40 T-72 T-73 486 30 Kharapathar Jubbal Shimla 1 225 16524 Private Cultivated Apple, Walnut 1 1 Nil

41 T-73 T-74 298 100 Kharapathar Jubbal Shimla 1 225 10132 Private Uncultivated 0 1 Nil

42 T-74 T-75 408 250 Kharapathar Jubbal Shimla 1 225 13872 HP Govt Uncultivated Pine 3 Nil Nil

SNo. ANGLE POINT (FROM –TO)

Dis

tanc

e be

twee

n tw

o an

gle

poin

ts

App

roxi

mat

e D

ista

nce

of

tran

smis

sion

lin

e fr

om n

earb

y

Nam

e of

Vill

ages

Nam

e of

Teh

sil

Nam

e of

Dis

tric

t

No.

of T

ower

s

Are

a of

tow

er

(in M

²)

Are

a un

der t

he

RO

W (i

n M

²)

Ow

ners

hip

of la

nd

(priv

ate,

Gov

t. Fo

rest

)

Use

of L

and

Nam

e of

Cro

ps

Num

ber o

f tre

es

unde

r cut

ting

No.

of a

ffect

ed

Hou

seho

ld

No.

of a

ffect

ed

trib

al h

ouse

hold

s (if

Any

)

43 T-75 T-76 500 500 Kharapathar Jubbal Shimla 1 225 17000 HP Govt Uncultivated 0 Nil Nil

44 T-76 T-77 419 30 Chaindal Kotkhai Shimla 1 225 14246 Private Cultivated Apple, Apricot 7 1 Nil

45 T-77 T-77A 361 50 Chaindal Kotkhai Shimla 1 225 12274 Private Cultivated Apple 6 1 Nil

46 T-77A T-78 105 100 Darkoti Kotkhai Shimla 1 225 3570 Private Uncultivated 0 1 Nil

47 T-78 T-79 209 50 Darkoti Kotkhai Shimla 1 225 7106 HP Govt Uncultivated 0 Nil Nil

48 T-79 T-80 338 20 Darkoti Kotkhai Shimla 1 225 11492 Private Uncultivated 0 1

Nil

49 T-80 T-81 189 50 Darkoti Kotkhai Shimla 1 225 6426 Private Cultivated Apple 10 Nil

50 T-81 T-82 169 50 Darkoti Kotkhai Shimla 1 225 5746 HP Govt Uncultivated Nil Nil

51 T-82 T-83 270 400 Sosan Kotkhai Shimla 1 225 9180 HP Govt Uncultivated Nil Nil

52 T-83 T-84 368 70 Sosan Kotkhai Shimla 1 225 12512 Private Cultivated Apple 10 1 Nil

53 T-84 T-85 286 200 Sosan Kotkhai Shimla 1 225 9724 Private Uncultivated 0 1 Nil

54 T-85 T-86 156 300 Sosan Kotkhai Shimla 1 225 5304 Private Uncultivated Apple 0 1 Nil

55 T-86 T-87 538 500 Sosan Kotkhai Shimla 1 225 18292 HP Govt Uncultivated 0 Nil Nil

56 T-87 T-88 273 150 Sosan Kotkhai Shimla 1 225 9282 Private Uncultivated 0 1 Nil

57 T-88 T-89 617 50 Sosan Kotkhai Shimla 1 225 20978 Private Uncultivated 0 1 Nil

58 T-89 T-90 273 30 Marathu Kotkhai Shimla 1 225 9282 Private Cultivated Apple 10 1 Nil

59 T-90 T-90A 238 150 Marathu Kotkhai Shimla 1 225 8092 HP Govt Uncultivated 0 Nil Nil

60 T-90A T-91 286 500 Pujarli Kotkhai Shimla 1 225 9724 HP Govt Uncultivated 0 Nil Nil

61 T-91 T-92 146 400 Pujarli Kotkhai Shimla 1 225 4964 HP Govt Uncultivated 0 Nil Nil

62 T-92 T-93 365 300 Kalala Kotkhai Shimla 1 225 12410 Private Uncultivated 0 1 Nil

63 T-93 T-94 529 250 Ghalera Kotkhai Shimla 1 225 17986 Private Cultivated Apricot Apple 13 1 Nil

64 T-94 T-95 444 220 Ghalera Kotkhai Shimla 1 225 15096 Private Cultivated Apple 22 1 Nil

65 T-95 T-96 164 150 Ghalera Kotkhai Shimla 1 225 5576 Private Cultivated Apple 4 1 Nil

SNo. ANGLE POINT (FROM –TO)

Dis

tanc

e be

twee

n tw

o an

gle

poin

ts

App

roxi

mat

e D

ista

nce

of

tran

smis

sion

lin

e fr

om n

earb

y

Nam

e of

Vill

ages

Nam

e of

Teh

sil

Nam

e of

Dis

tric

t

No.

of T

ower

s

Are

a of

tow

er

(in M

²)

Are

a un

der t

he

RO

W (i

n M

²)

Ow

ners

hip

of la

nd

(priv

ate,

Gov

t. Fo

rest

)

Use

of L

and

Nam

e of

Cro

ps

Num

ber o

f tre

es

unde

r cut

ting

No.

of a

ffect

ed

Hou

seho

ld

No.

of a

ffect

ed

trib

al h

ouse

hold

s (if

Any

)

66 T-96 T-97 448 100 Dalsar Kotkhai Shimla 1 225 15232 Private Uncultivated 0 1 Nil

67 T-97 T-98 393 80 Dalsar Kotkhai Shimla 1 225 13362 HP Govt Uncultivated 0 Nil Nil

68 T-98 T-99 433 50 Dalsar Kotkhai Shimla 1 225 14722 Private Cultivated Apple 31 1 Nil

69 T-99 T-100 752 30 Dalsar Kotkhai Shimla 1 225 25568 HP Govt Uncultivated 0 Nil Nil

70 T-100 T-101 765 20 Bakneol Kotkhai Shimla 1 225 26010 Private Uncultivated 7 1 Nil

71 T-101 T-102 643 50 Pudag Kotkhai Shimla 1 225 21862 Private Cultivated Apple, Apricot 9 1 Nil

72 T-102 T-103 609 300 Pandrog Kotkhai Shimla 1 225 20706 Private Cultivated Apple 10 1 Nil

73 T-103 T-104 333 100 Manghali Kotkhai Shimla 1 225 11322 HP Govt Uncultivated 0 Nil Nil

74 T-104 T-105 234 200 Manghali Kotkhai Shimla 1 225 7956 Private Cultivated Apple 14 1 Nil

75 T-105 T-106 396 200 Manghali Kotkhai Shimla 1 225 13464 Private Uncultivated Pine 1* 1 Nil

ANNEXURE 2: SOCIOECONOMIC PROFILE

General

1. Socio economic details of the affected households were collected based on a sample survey. In addition to the demographic and social data collected during census survey, socio economic information was collected from APs through a structured socio-economic questionnaire. This socio-economic questionnaire was administered in the subproject area covering a total of 54 sample households. Following section deals with various socio economic profiles of the households.

Type of Settlement 2. The sub project areas belong to the rural area which shows that all the 54 households reside in rural areas. Various types of settlements covered during the survey is given in Table 1

Table 1 Type of Settlement

Sl No Type of Settlement Total No. of Households % Age 1 Rural 54 100.00 2 Semi Urban 0 0.00 3 Urban 0 0.00 Total 54 100.00

Source: Socio Economic Survey, 2011

Demographic Features of APs 3. The total households covered during the socio economic sample survey are 54 and the average family size 6.29. The sex ratio of the project affected is 1000 males: 828 females. Details are given in Table 2

Table 2: Demographic Feature of APs

Sl No Particulars Number/% Age

1 Total Household 54 2 Sex Ratio 828 3 Average Household Size 6.29

Source: Socio Economic Survey, 2011

Type of Family 4. Most of the families are Joint family in nature. In the sub project area, 80 % of the surveyed households are having joint family and the rest 20 % are nuclear families. Details are given in Table 3

Table 3: Type of Family

Sl No Particulars No. of Households %Age

1 Joint 43 79.63 2 Nuclear 11 20.37 3 Extended 0 0 4 Other 0 0 Total 54 100.00

Source: Socio Economic Survey, 2011

Social Category of Households 5. The survey result reveals that 85% of the families belong to general castes and only 15 % are schedule caste. Details are given in Table 4

Table 4: Social Category

Sl No Particulars No. of Households %Age

1 General 46 85.19 2 SC 8 14.81 3 ST 0 0 4 OBC 0 0 Total 54 100.00

Source: Socio Economic Survey, 2011

Major Economic Activities 6. Earnings from agriculture (apple orchards) are the main activities in the sub project affected area. Nearly 93% of the households have major economic activities which are apple cultivation. This is followed by service as reported by 11% of the households. Small enterprise as an economic activity is reported by 5% of the households. The details are given in Table 5

Table 5: Major Economic Activities of the Households

Sl No Particulars No. of Households %Age

1 Agriculture 50 92.59 2 Working for other farmers 0 0.00 3 Small enterprise 3 5.56 4 Government / Pvt Jobs 6 11.11 5 Business and trading 0 0.00 6 Hunting or gathering 0 0.00 7 Daily Wage 0 0.00 8 Others 2 3.70 Total 54 100.00

Source: Socio Economic Survey, 2011

Landholding Status 7. Almost all the households in the subproject area posses land. Details are given in Table 6.

Table 6: Landholding Status

Sl No Particulars No of Households %Age 1 Land Holder Households 54 100.00 2 Landless Households 0 0 3 Total Households 54 100.00

Source: Socio Economic Survey, 2011

Type of Landholding 8. The Average cultivable land holding is 9.14 Bigha (one bigha is equivalent to 760 square meters) possessed by 53 households, where as the average uncultivable land holding is 10.6 bigha reported by only 5 households. Details are given in Table 7

Table 7: Type of Landholding

Sl No No of HH % of HH Average land in

Bigha 1 Cultivable Land 53 98.15 9.14 2 Non Cultivable Land 5 9.26 10.6

Total 53 98.15 10.23 Source: Socio Economic Survey, 2011

Major Cropping Pattern

9. Fruit is the major and the only crop being cultivated by majority which is about 85.19% of the households in the sub project affected area. Details are given in Table 8.

Table 8: Major Cropping Pattern

Sl No Type of Crop Number of Households %Age

1 Wheat 0 0 2 Dal 0 0 3 Rice 0 0 4 Maize 0 0 5 Vegetables 0 0 6 Fruits (Mainly Apples) 46 85.19 7 Others 0 0 8 Total 54 100.00

Source: Socio Economic Survey, 2011

10. The average production of fruits (apple) is 286 boxes as reported by 46 households. About 48% of the households yield between 51 to 100 boxes of apples annually. However nearly 22% households in the sub project affected area yield more than 500 boxes per year. Details are given in Table 9.

Table 9: Apple Yielding

Sl No Total Yield in boxes Number %

1 Up to 50 boxes 5 10.87 2 51 to 100 boxes 22 47.83 3 101 to 200 boxes 4 8.704 201 to 500 boxes 5 10.87 6 Above 500 boxes 10 21.74 7 Total 46 100.00 8 Average production 286 boxes

Source: Socio Economic Survey, 2011

Average Annual Income 11. Income from agriculture (apple cultivation) is reported from majority of the households. The average annual income form apple cultivation is INR 2, 53,913. Similarly income from service is reported by 6 households and the average annual earning is INR 1,91,668 /-. Although it differs from household to household, but the total average annual income of the household along the project area is INR 2, 78,913. Details are given in Table 10.

Table 10: Average Annual Income

Sl No Source of Income No. of HH Average Annual Income 1 Agriculture 46 2,53,913 2 Service 6 1,91,668 3 Business 0 0 4 Labour 0 0 5 Professional 0 0 6 Any other (5) 0 0 7 Total Average 46 2,78,913

Source: Socio Economic Survey, 2011

Average Annual Expenditure 12. The total annual average expenditure per household is INR. 60,361 out of which the major expenditure is incurred for the food followed by expenditure on education, clothing, health and transportation. Details about the expenditure is described in Table 11

Table 11 Average Annual Expenditure

Sl No Type of expenditure Average Annual Expenditure (Rs.) 1 Food 19918 2 Transportation 5224 3 Clothing 10020 4 Health 5708 5 Education 146006 Communication 4065 7 Social functions - 8 Agriculture -

9 Consumption of fuel for household 4343

10 Electric Bill 3927 11 Others (Specify - 12 Total Average 60361

Source: Socio Economic Survey, 2011

Possession of Durable Goods 13. All the households in the sub project area possess both television and LPG. Besides radio with few households no other durable goods are present with the surveyed households. Details are given in Table 12.

Table 12: Possession of Durable Goods

Sl. No. Items Number of Households %Age 1 Radio 4 7.41 2 Bicycle 0 0.00

3 Television 54 100.00 4 L.P.G Connection/ Gas Cylinder 54 100.00 5 Computer 0 0.00 6 Refrigerator 0 0.00 7 Washing Machine 0 0.00 8 Motor cycle/Scooter 0 0.00 9 Car 1 1.85 10 Air Conditioner 0 0.00 11 Total 54 100.00

Source: Socio Economic Survey, 2011

Benefit from Schemes 14. Among the households in the project affected area, none of the households have reported that they availed benefits from any schemes of the government. Details are given in Table 13.

Table 13: Benefits from Schemes

Sl No Particulars Number of Households %Age 1 Yes 0 0 2 No 54 100.00 3 Total 54 100.00

Source: Socio Economic Survey, 2011

Major Illness 15. There is no major illness reported in the last one year. Only 1 of the surveyed households stated that their household member experienced major illness during the last one year. One member suffered from diabetes. Details are given in Table 14.

Table 14: Major Illness in the Family

Sl No Major illness Number of Households %Age 1 Yes 1 1.85 2 No 53 98.15 3 Total 54 100.00

Source: Socio Economic Survey, 2011

Migration Pattern 16. Migration is not seen in the project influence zone. Only one household reported of migration. Details are given in Table 15.

Table 15: Migration Pattern Sl No Migration Number of Households %Age

1 Yes 1 1.85 2 No 53 98.15 3 Total 54 100.00

Source: Socio Economic Survey, 2011 Women’s Activities

17. The predominant activity of women is household work where they spend most of their time. The women participation in other activities is nil. Details of the activities of women are given in Table 16

Table 16: Type of Activities for Women

Sl No Activities Number of Households %Age

1 Cultivation 0 0.00 2 Allied Activities 0 0.00 3 Collection & Sale of forest products 0 0.00 4 Trade & Business 0 0.00 5 Agricultural Labour 0 0.00 6 Non Agricultural Labour 0 0.00 7 HH Industries 0 0.00 8 Service 0 0.00 9 Households Work 54 100.00 10 Others 0 0.00 11 Total 54 100.00

Source: Socio Economic Survey, 2011

Women’s Say in Decision Making

18. Women do take part in the decision making process of the family. It shows that majority of the households give importance to women in decision making related to family matters. About 85 % of the households stated that women do have say in the household matters. Details are given in Table 17.

Table 17: Women’s Say in Decision Making

Sl No Issues Number of Households % Age 1 Yes 46 85.18 2 No 8 14.81 3 Total 54 100.00

Source: Socio Economic Survey, 2011

19. Women participation in household decision making is more on financial matters (79.63%). Participation of women in the purchase of household assets is the second most important decisions as reported by 70.37% of the households. Details are given in Table 18.

Table 18: Women’s Participation in Decision Making

Sl No Issues Number of Households % Age 1 Financial matters 43 79.63 2 Education of child 25 46.30 3 Health care of child 35 64.81 4 Purchase of assets 38 70.37 5 Day to day activities 36 66.67 6 On social functions and marriages 32 59.26 7 Total 54 100.00

Source: Socio Economic Survey, 2011 Literacy

20. In the project affected area, the literacy rate is nearly 71 % and among the males this is about 78 % and among the females the literacy rate is 62 %. Details are given in Table 19

Table 19: Literacy Status Sl No Particulars Total

Male % Male Total Female % Female Total

Members Total %

1 Literate 145 77.96 96 62.34 241 70.88 2 Illiterate 41 22.04 58 37.66 99 29.12 3 Total 186 100 154 100 340 100.00

Source: Socio Economic Survey, 2011 Source of Drinking Water

21. The major source of drinking water is piped water as reported by 100 % of the households. Details are given in Table 20.

Table 20: Source of Drinking Water Sl No Sources Number of Households %Age

1 Piped Water Supply 54 100.00 2 Spring (Open) 0 0.00 3 Well/Hand Pump 0 0.00 4 Stream (Open) 0 0.00 6 Other 0 0.00 7 Total 54 100.00

Source: Socio Economic Survey, 2011

Sanitation Facilities

22. Around 89.19 % of households are having Flush toilets and 10.81 % of the households use the traditional latrines. Details are given in Table 21.

Table 21: Type of Sanitation Facilities

Sl No Type of Toilet Number of Households %Age 1 Flush Toilet 48 89.19 2 Latrine 6 10.81 3 No Toilet 0 0 4 Total 101 100.00

Source: Socio Economic Survey, 2011

Usage Pattern of Fuel for Cooking 23. LPG is the major source of fuel being used by the households (89.19%) for cooking followed by 10.19% of households use electricity as the source of fuel for cooking. Details are given in Table 22.

Table 22: Type of Fuel Use for cooking Sl No Sources Number of Households %Age

1 Electricity 6 10.19 2 Wood 0 0 3 Gas 48 89.19 4 Diesel/Kerosene 0 0 5 Solar 0 0 6 Total 54 100.00

Source: Socio Economic Survey, 2011

Type of Construction of Structure 24. Most of the houses about 78 % are of wooden. About 11% are of brick made and 5.56 % are cemented houses. Details are given in Table 23.

Table 23: Type of Construction

Sl No Sources Number of Households %Age 1 Mud Made 0 0.00 2 Brick Made 6 11.11 3 Cemented 3 5.56 4 Thatched 0 0.00 5 Wooden 42 77.78 6 Others 3 5.56 7 Total 54 100.00

Source: Socio Economic Survey, 2011

Nature of Structure/Buildings 25. Most of the houses are permanent in nature which is almost 98.15 % of the total households. Only 1 of the households is semi-permanent in nature. These buildings are not to be affected. This gives the idea about the housing pattern of the households living in the project area to assess their standards of living. Details are given in Table 24

Table 24: Nature of Structure

Sl No Sources Number of Households %Age 1 Temporary 0 0 2 Semi-permanent 1 1.85 3 Permanent 53 98.15 4 Total 54 100.00

Source: Socio Economic Survey, 2011

Use of Structure 26. Most of the houses are residential (98.15 %) in nature. Details are given in Table 25.

Table 25: Type of Structure

Sl No Sources Number of Households %Age 1 Residential 53 98.15 2 Commercial 0 0 3 Resident cum commercial 1 1.85 4 Total 54 100.00

Source: Socio Economic Survey, 2011

Interior Details of Structure 27. The average number of rooms per structure, according to the survey, is 5.24 and all the rooms are lighted as far as the electrification is concerned. The average heated room per structure is nil. Details are given in Table 26.

Table 26: Interior Details of Structures Sl No Particulars Total

1 Average Number of rooms in House/Structure 5.24 2 Average Lighted Rooms 5.24 3 Average Heated Rooms 0 Source: Socio Economic Survey, 2011

Status on Electrification

28. All the households are electrified in the sub project area. Details are given in Table 27.

Table 27: Status on Electrification

Sl No Particulars Number of Households % Age 1 Electrified Houses 54 100.00 2 Non-Electrified Houses 0 0 3 Total 54 100.00

Source: Socio Economic Survey, 2011

Source of Electrification 29. The main source of electrification is government and usually supplied from the government grid. Details are given in Table 28.

Table 28: Source of Electrification

Sl No Source of Electrification Number of Households %Age 1 Govt. Grid 54 100.00 2 Micro hydro Power 0 0 3 Generator 0 0 4 Solar 0 0 5 Bio-Gas 0 0 6 Other 0 0 7 Total 54 100.00

Source: Socio Economic Survey, 2011

Average Usage Pattern

30. According to the findings of the survey, it is found that the average years since the area has been electrified are 34 years. The average hours of availability of electricity and the supply are almost 22 hours. Details are given in Table 29.

Table 29: Average Usage Pattern of Electricity

Sl No Particulars Numbers 1 Average Years of Electrification 34 2 Average Hours of Consumption Per day 22

Source: Socio Economic Survey, 2011

Purpose of Electricity Use 31. The main purpose of electricity use is lighting where almost all the households those possess electricity use it as the prime purpose. The average hours of consumption of electricity for lighting are 7.55 hours. Similarly 79.6 % of the households use electricity for

running Television and the average consumption is 2.71 hours. Details are given in Table 30.

Table 3.31: Purpose of Electricity Use

Sl No Purpose Number of

Households %Age

Average hrs of

consumption1 Lighting 54 100.00 7.55 2 Cooking 0 0 3 Heating and cooling 0 0 4 Pumping water 0 0 5 TV and Type Recorder 43 79.6 2.71 6 Computer 0 0 7 Business 0 0 8 Others 0 0 9 Total 54 100.00 -

Source: Socio Economic Survey, 2011 Average Number of Assets for Electricity Use

32. The average number of electric lamps per households is 6 followed by 1 television in 44 households. Details are given in Table 31.

Table 31: Average Number of Assets for Electric Use

Sl No Particulars Number of

households Average Number 1 Lamps 54 6 2 Heater 3 Fans 4 Television 44 1 5 Washing Machines 0 0 6 Water Pumps 0 0 7 Others 0 0

Source: Socio Economic Survey, 2011

Status on Meter System 33. The survey’s findings reveal that all the households have electric meter in their households those have electricity. Details are given in Table 32.

Table 32: Status on Meter System Sl No Particulars Number of Households %Age

1 Yes 54 100.00 2 No 0 0 3 Total 54 100.00

Source: Socio Economic Survey, 2011

Unit Price 34. All the households stated that they usually pay INR 1.20 per unit of consumption of electricity. The average expenditure on electricity by the 54 households is INR 171 per month. All the households stated that they usually pay the electricity bills at the electricity

office. All the households stated that there is no case of electricity theft and the maintenance lies with the power and electricity department Details are given in Table 33.

Table 33: Average expenditure on electricity

Sl No Particulars In Rupees 1 Unit rate of electricity 1.20 2 Average expenditure on electricity bill 171 per month

Source: Socio Economic Survey, 2011

Use of Non Electricity Sources 35. None of the households stated that they use energy from non electricity sources. Details are given in Table 34.

Table 34: Usage of non electricity energy sources Sl No Particulars Number of Households %Age

1 Yes 0 0 2 No 54 100.00 3 Total 54 100.00

Source: Socio Economic Survey, 2011

Views on Electricity Status

36. All the households opined that they are satisfied with the current status on electricity supply to their locality. Details are given in Table 35.

Table 35: Perceive satisfaction

Sl No Particulars Number of Households %Age 1 Satisfied 54 100 2 Not Satisfied 0 0 3 Total 54 100

Source: Socio Economic Survey, 2011

Peoples’ perception on the need of the project 37. All the people perceive that the project will help the households and the standard of living will increase with adequate supply of electricity. Details in Table 37

Table 37: Peoples’ perception on the need of the Project

Sl No Particulars Number of Households % Age 1 Yes 54 100.00 2 No 0 0 3 Total 54 100.00

Source: Socio Economic Survey, 2011

ANNEXURE 3: DETAILS ON CONSULTATIONS

Sl No Issues Discussed People’s Views and perception 1 General Perception

about Project Almost all the villages reported that people are aware about the project and will render full support to the project.

2 Support of local people for proposed project

Out of 26 villages, majority are fully cooperative. However, they expect local employment during the construction of project

3 Critical issue and concern by the local people for the project

15 villages do not foresee any critical issues in the project. However about 5 villages namely Bakneat in Purag Panchayat, Dalsar in Bagdomehar Panchayat, Jhandoli in Dharkoti Panchayat, Mhanghali in Pudag Panchayat and Soshan village in Tharsol Panchayat suggested that necessary precaution should be taken at the time of construction to minimize the damage of orchards in the local area. In Nakatura village under Deem Panchayat, the villagers demand compensation according to the market price. Similarly in Sholi village, the people are concerned about landslide and the quality of the apples the project may affect. In Vadot village under Thana Panchayat, the people feel that the project might create landslides and soil erosion in the village. In Sari Panchayat the people want assurance from the government that they will get jobs. Similarly for the people in Purjali village in Bagdomehar Panchayat, desire that the government should take all safety measures.

4 Criteria liked to see during project design, operation stage and construction

They are not about the technical details of the project, however, they urge that HPPTCL should advise the contractor to adopt best engineering method in safety.

5 Employment potential in the project

About 8 of the villages out of 26 didn’t respond on this. However majority of villages perceive that the youths are educated and they will get jobs during the construction and after the construction of the project.

6 No of households

Majority of the villages, about 16, are having less than 50 households in their respective villages. In 6 villages, the size of the households varies between 50 to 100 households. Only 3 villages covered, are having more that 100 households.

7 Ethnic Minorities

In the project area no ethnic minorities present in any of the villages

8 No of shops/commercial establishments

No big scale commercial activities are found in the villages except few minor small shops in each villages

9 Number of industrial units

There are no industries in the sub project area. However, 2 wood cutting units are present in Maghara and Maghawata village and 1 cutting unit in Kotkhai Village.

10 Socio economic standing: land use, cropping pattern

In all the villages the land is used for horticulture and apple orchards

11 Sources of irrigation

Most of the villages covered under consultation reported that land is cultivated by rain water and that is not enough. However rain water is sufficient reported 6 of the villages namely Bakneat, Dalsar, Pundrog, Pudag, Jhandoli, and Kotkhai.

Sl No Issues Discussed People’s Views and perception

12 Access to Forest Land and Use

Only 3 villages out of 26 villages covered under consultation reported having access to forest land. The names of the villages are Chandel, Dharkoti and Mandhol. The villages mostly use forest as collecting fodder.

13 Current rates for agricultural land

All the villages reported that the price of the land varies between rupees 1 lakh to rupees 1.5 lakh per bigha

14 Sources of power supply

All the areas covered during consultation admitted of getting power from the government sources.

15 Sources of electricity Similarly the sources of electricity are government grid for all the areas covered.

16 Average amount of electricity used by per household

The average unit varies in the range of 3 to 10 units per households per day.

17 Unit Rate

All the villages reported that they spend INR 1.20 only per 1 unit consumption of electricity.

18 Average total monthly expenditure per household on grid electricity

The average monthly bill varies between the range of Rs. 250/- to Rs. 400/- per 2 months as reported by all the households.

19 Other non grid electricity to use in your village and expenditure

Nothing

20 Source of drinking water

For most of the villagers the sources of drinking water is government JPH Supply. In 3 villages, the villagers reported relying on natural sources like, stream, etc. and another 3 villages also rely on Hand pumps but the quality of water is not good.

21 Shortage of water

There is no acute shortage of water but people have to store the govt supply of water which comes once in every 2 to 3 days. Very few villages reported of facing shortage of water.

22 Negative impact on food grain, availability /land use

No

23 Will project cause landslides or soil erosion

Most of the villages feel that landslide or soil erosion may be there during the time of construction.

24 Will project cause widespread imbalance

Few villages feel that the quality of the apples may be affected.

25 Will project cause health and safety issues

No

26 Resettlement and land acquisition

Minimum land acquisition is foreseen which can be mitigated through proper compensation.

27 Protected areas No. 28 Health status

In most of the villages, primary health centres are not present. However registered medical practitioners (RMPs) are available in some of the villages. People usually travel outside of the village to access medical services and mostly they travel to nearby urban towns. The urban towns as named by the villagers are Mehgon, Guna, Daburia, Datia, Garawara,

Sl No Issues Discussed People’s Views and perception Lakhana, Shivpuri, etc. In some villages, Ayurvedic medical services are available. In village Soni in Bhind district, although a government health facility is there, but it is not in working condition. The incidence of malaria as major health problem is reported by some of the villages. Chronic diseases are not reported but a separate health needs assessment can provide details of the diseases prevailing in the project area. Few of the villages reported that people are aware of HIV/AIDS and about sexually transmitted diseases. However, no such cases are found in the project area.

29 Will project setting change migration pattern

No

30 Will project site adversely impact the water and soil

Soil erosion may occur.

31 Poverty Level

Majority of the villages reported that the people are well off. However in Sholi village (50 %), Kaina village (40 %), Sari village (30%), and Mandhol (40 %) of the population are poor.

32 Educational status

Most of the villages have literacy rate of 90 %. In only 2 villages the literacy rate is about 60 %.

33 Employment status

Most of the villages reported that people are educated and work in horticulture and apple orchards.

34 Migration pattern Migration is negligible as reported by all the villages. 35 Type of compensation

expected Cash compensation is expected by all the villages

36 Perceived benefits from project

The people perceive that they will get jobs and compensation due to the project.

37 Perceived loss

Most of the villages fear that they will lose land and apple trees. Few villages feel that the quality of apples will affected.

38 Other organizations active in the area

In 15 of the villages there are no local civil societies active. In all othet 11 villages Mahila Mandal (women groups) are present.

39 Village Committee

In all the villages, the decisions are taken by gram panchayat and gram sabha held on any critical and community related issues. All the panchayat members and Sarpanch actively participate to take a decision on any community related issues.

40 Other issuers

Some of the issues are availability of water, and government should take steps so that orchards are not damaged.

41 Usefulness of consultation

All the villagers admitted that the consultation is useful, and happy as they got an opportunity to share their views before the government officials. They feel that the consultation is useful for sharing views about the project and the details making them serious about electricity.

42 Involvement of people in implementation

All the participants during the consultation admitted that the local people will provide full cooperation and involvement for the implementation of the project.

LIST OF PARTICIPANTS

SL NO NAME OF THE PARTICIPANTS OCCUPATION 1. Name of the Village: BAKNEOT

1 HARE KRISHAN SERVICE MAN 2 KRISHAN LAL SERVICE MAN 3 RAM KRISHAN AGRICULTURE 4 PREM AGRICULTURE 5 LAIK RAM EX.SERVICE MAN 6 RAMA NAND GOVT.SERVICE 7 BALE RAM AGRICULTURE 8 NAIN DUTT PRIVATE JOB 9 MEENA RAM GOVT.SERVICE

2. Name of the Village: DALSAR 1 SH. BRIJESH SHARMA GOVT.SERVICE 2 SH.RAKESH SHARMA GOVT.SERVICE 3 SH .SURESH SHARMA GOVT.SERVICE 4 SH .RAMESH BHARADWAJ GOVT.SERVICE 5 SH.JAGMOHAN SHARMA GOVT.SERVICE 6 SH.PREM MOHAN GOVT.SERVICE 7 SH.NARENDER BHARDWAJ HORTICULTURE 8 SH.ASHOK SHARMA HORTICULTURE 9 SH .RAJESH BHARDWAJ GOVT.SERVICE

3. Name of the Village: PANDROG 1 VIJAY KAPRET PARDHAN 2 VINOD SERVICE 3 BRIJ LAL SERVICE 4 NAND LAL SERVICE 5 RAM LAL SERVICE 6 JIA LAL AGRICULTURE 7 PREM PRAKASH SERVICE 8 RANVIR SERVICE

4. Name of the Village: PUDAG 1 SH.HARERAM SERVICE MAN 2 SH.LAL CHAND SERVICE MAN 3 SH.MANJIT RAM FARMER 4 SH.KRISHAN LAL EX.SERVICE MAN 5 SH.BHAGAT RAM EX.SERVICE MAN 6 SH.ALAT RAM FARMER

5. Name of the Village: GALERA 1 SH.SUNDER BREGTA AGRICULTURE 2 SH.ARJUN BREGTA AGRICULTURE 3 SH.HAMA NAND BREGTA AGRICULTURE 4 CHETAN BREGTA AGRICULTURE 5 SH.SHRIMAM BREGTA AGRICULTURE

SL NO NAME OF THE PARTICIPANTS OCCUPATION 6. Name of the Village: NAKTADA

1 VINOD KUMAR HORTICULTURE 2 NAYAN SINGH HORTICULTURE 3 CHANDEN SINGH HORTICULTURE 4 VIJAY CHOUHAN HORTICULTURE 5 SANDEEP KUMAR STUDENT 6 BALBIR CHOUHAN SERVICE

7. Name of the Village: DEEM 1 MELA RAM HORTICULTURE 2 SALIGRAM HORTICULTURE 3 LLAXMI SINGH HORTICULTURE 4 PRADEEP HORTICULTURE 5 DEVKI CHAND HORTICULTURE

8. Name of the Village: KHARA PATHAR 1 BHAWANI SINGH RETD. 2 JEET SINGH SERVICE 3 BADERI DUTT HORTICULTURE 4 SOHAN SINGH SHOP KEEPER 5 ASHOK JITA HORTICULTURE 6 SHIV LAL HORTICULTURE 7 SURENDER CHOUHAN HORTICULTURE

9. Name of the Village: CHANDEL 1 FIROZDEEN AGRICULTURE 2 BHUPENDER SINGH HORTICULTURE 3 RAHI RAM HORTICULTURE 4 KEWAL RAM HORTICULTURE 5 KHEMPE RAM HORTICULTURE 6 DILIP SINGH HORTICULTURE

10. Name of the Village: DHARKUTI1 JAGAT RAM HORTICULTURE 2 BALBIR HORTICULTURE 3 RAJESH HORTICULTURE 4 BALWAN HORTICULTURE 5 SEEMA HOUSE WIFE 6 KAMLA HOUSE WIFE 7 CHATTER SINGH HORTICULTURE

11. Name of the Village: JHANDOLI 1 SH.PRAVEEN AGRICULTURE 2 MOHAN LAL AGRICULTURE 3 JOGINDER AGRICULTURE 4 BARAT BHUSHAN AGRICULTURE 5 RAVINDER AGRICULTURE 6 SHYAM LAL AGRICULTURE 7 MOHINDER AGRICULTURE

SL NO NAME OF THE PARTICIPANTS OCCUPATION 8 JIYA LAL AGRICULTURE 9 ROSHAN LAL AGRICULTURE

10 MOHAN LAL EX.SERVICE MAN 12. Name of the Village: SHOLI

1 ROPINDER DAULTA HORTICULTURE 2 MADAN MANTA HORTICULTURE 3 KAUSHAL CHANTA HORTICULTURE 4 BRIJ LAL SINHA HORTICULTURE 5 NAND LAL SINHA HORTICULTURE 6 DIWAN MANTA HORTICULTURE 7 NANVEER MANTA HORTICULTURE

13. Name of the Village: KAINA 1 PRABUDAYAL MANTA HORTICULTURE 2 GODU CHANTA HORTICULTURE 3 NARESH CHAUHAN HORTICULTURE 4 TULSI RAM CHANTA HORTICULTURE 5 AMAN MANTA HORTICULTURE 6 YASHWANT CHANTA HORTICULTURE 7 JOGINDER KHINTA HORTICULTURE 8 PRADHAN CHANTA HORTICULTURE

14. Name of the Village: RAMPURI 1 DURGANEANEL HORTICULTURE 2 RAJINDER SERVICE 3 MOHAN SINGH SERVICE 4 LAZZA RAM SHOP KEEPER 5 DEEPAK HORTICULTURE 6 JAI PRAKASH SERVICE

15. Name of the Village: VADOT 1 JAYA LAL HORTICULTURE 2 KAWAL RAM HORTICULTURE 3 LACHU RAM HORTICULTURE 4 YASH WANT HORTICULTURE 5 HAPINDER HORTICULTURE 6 RAJESH GANGTA HORTICULTURE

16. Name of the Village: VIRAT NAGAR (HATKOTI) 1 SH.KISHAN LAL SHARMA SHOP KEEPER 2 SH.BIHARI LAL SHARMA SELF EMPLOYED 3 SH.SHYAM LAL SHARMA SELF EMPLOYED 4 BALDEV AGRICULTURE 5 SANJAY KIMTA AGRICULTURE 6 MIHAN AZAD AGRICULTURE 7 SANJEEV SELF EMPLOYED 8 RAJINDER SELF EMPLOYED 9 BAKSHI AGRICULTURE

SL NO NAME OF THE PARTICIPANTS OCCUPATION 17. Name of the Village: SARI

1 GOPAL BUSINESS 2 PANKAJ VICE PRADHAN 3 ROOP SINGH SHOP KEEPER 4 TRILOK AGRICULTURE 5 LOKINDER AGRICULTURE 6 PRITAM AGRICULTURE 7 JAY SINGH AGRICULTURE 8 MOTILAL GOVT.SERVICE

18. Name of the Village: ASTANDLI1 KEHAR SINGH AGRICULTURE 2 HARDAYAL AGRICULTURE 3 BALBIR CONTRACTOR 4 MANMOHAN AGRICULTURE 5 BELIRAM AGRICULTURE

19. Name of the Village: MANDHOL 1 JASHU RAM FARMER 2 KAMLA RAM FARMER 3 CHHAGAN FARMER 4 CHATTE RAM FARMER 5 ATTRU FARMER 6 DHIRJE FARMER 7 GOPAL FARMER

20. Name of the Village: MANGARA 1 CHAMAN LAL HORTICULTURE 2 ROSHAN LAL HORTICULTURE 3 PREM SINGH HORTICULTURE 4 DHANU RAM HORTICULTURE 5 BIHARI LAL HORTICULTURE 6 RAMESHWAR SINGH HORTICULTURE 7 LOKINDER HORTICULTURE

21. Name of the Village: MAGOUTA 1 SADAN NAND EX.SERVICE MAN 2 RAJESH HORTICULTURE 3 GYAN SINGH HORTICULTURE 4 ISHWARI SINGH GOVT.SERVICE 5 SARAN DASSI HORTICULTURE 6 CHANDER PRAKASH HORTICULTURE 7 HARI SARAN HORTICULTURE 8 ANAND PRAKASH HORTICULTURE 9 BASHIR CHAND GOVT.SERVICE

10 JAWAHAR SHARMA GOVT.SERVICE 11 LOKINDER SHARMA ADVOCATE 12 NARENDER SINGH GOVT.SERVICE

SL NO NAME OF THE PARTICIPANTS OCCUPATION 13 DHARM SINGH HORTICULTURE 14 AMI CHAND HORTICULTURE

22. Name of the Village: KOT 1 RAM GOPAL HORTICULTURE 2 ADIT RAM HORTICULTURE 3 CHANDER LAL GOVT.SERVICE 4 RAVINDER DUTT HORTICULTURE 5 PRADEEP KUMAR HORTICULTURE 6 MANGAT RAM EX.SERVICE MAN 7 LODU RAM EX.SERVICE MAN 8 RAM PRAKASH GOVT.SERVICE 9 BIJA RAM EX.SERVICE MAN

10 DEVI DUTT EX.SERVICE MAN 11 KAMLA NAND GOVT.SERVICE 12 BISASAR DUTT GOVT.SERVICE 13 PAYARI LAL GOVT.SERVICE

23. Name of the Village: MHANGHALI 1 NARAYAN DASS GOVT.SERVICE 2 SATISH KUMAR SELF 3 DAULAT RAM EX.SERVICE MAN 4 MEHU RAM SELF EMPLOYED 5 RAJINDER SINGH AGRICULTURE 6 JAI RAM AGRICULTURE 7 DAULAT RAM EX.SERVICE MAN 8 RATI RAM AGRICULTURE 9 CHET RAM GOVT.SERVICE

24. Name of the Village: MARATHU 1 JAGDISH GOVT.SERVICE 2 RAVINDER AGRICULTURE 3 SURESH AGRICULTURE 4 ROSHAN AGRICULTURE 5 MAHINDER AGRICULTURE 6 SUBHADRA AGRICULTURE 7 DHARPAL AGRICULTURE 8 DURGA SINGH AGRICULTURE

25. Name of the Village: PURJALI 1 AGYA RAM HORTICULTURE 2 KAPIL DEV HORTICULTURE 3 PUNJI RAM HORTICULTURE 4 LAIK RAM HORTICULTURE 5 SENDAR SINGH HORTICULTURE 6 BAL KRISHAN HORTICULTURE

List Of Participants for Consultation in Shimla district For Gumma (Pragati Nagar) Substation

Name of the Village: Bagori (For Gumma Sub Station) 1 N D Chauhan Business 2 Rati Ram Agriculture

List of Participants for Consultation in Kinnaur district for Sherpa Colony (Wangtoo)

Substation Name of the Village: Katgaon (For Sherpa Colony Substation At Kinnaur)

1 Prabhulal Negi Retired Govt. Servant 2 Ravi Negi Horticulture 3 Harman Dass Ex Army Officer 4 Pratap Negi Shop Keeper 5 Shiv Singh Govt. Employee

ANNEXURE-4: COPY OF SETION-4 NOTIFICATION FOR GUMMA SUBSTATIONS

ANNEXURE-5: COPY OF NOTIFICATION UNDER ELECTRICITY ACT, 2003

ANNEXURE 6: SAMPLE MONITORING AND STATUS REPORT

S. N. R&R Activities Progress Remarks

Pre Construction Activities and R&R Activities 1 Assessment of Resettlement impacts due to changes

in project design (If required)

2 Preparation/ updating of Resettlement Plan based on changes in project design

3 Approval of updated Resettlement Plan from ADB 4 Disclosure of updated Resettlement Plan 5 Establishment of Grievance Redressal Committee 6 Inclusion of safeguards official (designated) to PMU

Resettlement Plan Implementation1 Payment of Compensation as per replacement value

of land & assets to APs where applicable

2 Disbursement of assistance to title holders 3 Disbursement of assistance to non-title holders 4 Disbursement of special assistance to Vulnerable

groups

5 Replacement/ shifting of community property resources

6 Reinstallation of public utilities 7 Records of Grievance Redressal 8 Compensation for temporary loss of crop

Social Measures during Construction as per Contract Provisions 1 Prohibition of employment or use of children as labour 2 Prohibition of Forced or Compulsory Labour 3 Ensure equal pay for equal work to both men and

women

4 Implementation of all statutory provisions on labour like health, safety, welfare, sanitation, and working conditions

5 Maintenance of employment records of workers