SCT PL Report Dave Robinson
University of Cambridge May – ID Week -2014
• LS1 Activities
• Manpower & OTP
• SCT M&O
The SCT during LS1 • Maintained at room temperature in nitrogen thoughout LS1,
until the ID volume is resealed • Ground fault monitoring • Backplane resistance measurements • Evaporative heater consolidation • New control & monitor system for heater pads • Installation of dual-output HOLAs (for FTK) • Power infrastructure – complete replacment of fans, Wiener
refurbishments • Expansion of DAQ
– New ROD & BOC production, and installation – New fibre mapping (still in progress for endcaps)
• The ROD BUSY issue – ROD f/w developments & FE simulator
• DAQ developments (inc TDAQ-05 & SLC6) • DCS developments (project migrations to linux) • New TX production
Evaporative heaters repairs & consoldiation to TCS, Plus resistance and isolation measurements Forest & Sergei (UCSC), Koichi & Jacek Also (for pix) Alex (Glasgow), Igor (Protvino)
SCT Performance Paper Submitted to JINST 1st May 2014
Many thanks to the editors and EdBoard (chaired by Pat and Attilio respectively!) A special thank you to Pat Ward and Taka Kondo.
Pixel Cooling tests
IBL connectivity & leak tests
IBL, Pixel and SCT Cooling trials Final opportunity for interventions at flange
IDEP closure
The
Nex
t Se
vera
l wee
ks
+ SCT
ATLAS Integration Milestone 3 (May 19th-23rd): • New systems to join: RPC, HLT • Lar, PIX and IBL originally planned for M3 will
now join M4, as will SCT • Cosmic triggers: TRT FastOR, few RPC towers • Consolidate results of M2:
Muons, TRT, BCM (L1CALO back in M4) • Full chain Trigger+ HLT + Offline Storage • Shifts: TRT staying ON all week Monday
Morning till Friday afternoon 24h Shift Further Milestone Runs • 8th September & 13th October ATLAS Cosmic ray run • 24th November for ~2 weeks
15
SCT Actions in coming weeks
• Complete QA for sufficient LTx for one crate • Finalise mProcessor code for LTx • Replace bad ROD crate, week starting 09.06
– Crate 3 has power supply issues and bad backplane in slot 9 – Full installation of LTx in that crate
• Get SR1 up and running – DCS and evaporative cooling – Complete migrations to SLC6
• Readiness for cooling and powering in July – DAQ & DCS – Cooling loop checks
• Exercise DAQ in P1 – Preparations for M4
Readiness for Run-2
• In general we are in good shape – Key objectives for LS1 are all met, or close to being met
– Final DAQ configuration not yet implemented • Awaiting endcap fibre mapping (finalised about now)
• Awaiting decision on LTx installation schedule
– DCS migrations to linux • Will be tight to implement by time of M4
– All must be implemented by time of ATLAS cosmic ray run
• Key concerns: – Switch on for the first time in 1.5 years
– Manpower to support continuous operation from August
– ROD busy issue • Have we solved it?
Manpower News • SCT IB Chairperson
– Richard Brenner took over Joost Vossebeld from 1st April – Many thanks to Joost for the excellent job over the past 2
years
• SCT offline software coordinator – Pat will stand down from this role in August, replaced by
Nick Barlow • Many thanks to Pat for many years of service in this role. • Nick an excellent choice for replacement, with his technical skills
and wide knowledge of both offline and online
• Run Coordination – I have asked Per to resume run coordination role until mid-
2015 • Per had only two months as RunCo during operations • Currently there is little operations experience at CERN • Hope to identify new candidates for RunCo, and appoint a deputy
from start of 2015 – Call for nominations in last quarter of 2014
Operations Support
• DAQ – Bruce Gallop (core development)
– Carl Gwilliam (SctApi / configuration)
– John Anders (module & global recovery)
– Nick Barlow (Replacement to ROS monitoring)
– Nitesh Soni (set up at Adelaide)
– Dave R (operations at CERN)
– Per (conditions data uploads)
– Vakhtang Tsiskaridze (DSP)
Operations Support (cont’d) • DCS
– Andree Robichaud left SCT a few months ago – Peyton Rose (leaving this summer) – Will Kalderon (leaving this summer) – Chiara Debenedetti – recently started – Alex Madsen (returns this summer) – Koichi Nagai & Katherin Becker (recently appointed by Oxford) – Richard Brenner - iMatrix
• DQ – Big expertise hole now being addressed – Hidetoshi Otono - DQ coordinator
• FSI – Zhijun Liang left to join UCSC (mainly ITK) – Koichi & Katherine to take on local support
• Miscellaneous (qualification tasks) – Jon Hayes working on web configuration editor – Calum MacDonald working on web SCT event dump – Naoki Kimura working on update to web problem tracker
Current ATLAS Agreements (paid by SCT M&O)
• Koichi Nagai (AA expires 30.6.2014) – Critical for SCT operation – Awarded new position by Oxford based at CERN supporting SCT
DCS and FSI • Replacement for Andree Robichaud
• Jacek Pieron (AA expires 30.6.2014) – Countless hardware support tasks, inc heater pad control
system, SCT services etc • Discussed outstanding job list, needs a 2-month extension
– Significant loss of ID expertise
• Sergei Katunin (AA expires 31.12.2014) – Actually funded 50-50 by ID and TRT M&O – Mainly on sonar and TRT gas regulation
OTP
2012 2013 2014 2015
15 10.5 ~12 ~15
Class-3
Class-1 None in 2013 ID shifter from ~August 2014 (3 shifts/day) Class-2 RunCo resumes in July 2014 DAQ/DCS oncall from August 2014 DQ during milestones and cosmics
Manpower needs
• Current pool of expertise is not sufficient to support SCT operations
– Need to train more people as ‘expert operators’
– Need to attract more core developers
• Especially DAQ, also DQ – …with the right skillsets
• AA agreements to be terminated this year
– We will lose our resident technical support (Jacek)
• Concern for repairs to hardware
SCT M&O Book Closing
2012
Entry kCHF
Budget 2012 635
2011 carry over 70
Total spend 799
Carry over to 2013 -94
2013
Entry kCHF
Budget 2013 6372
2012 carry over -94
Total spend 427
Carry over to 2014 116
Entry kCHF
Budget 2014 637
2013 carry over 116
Total spend (by May) 176
To spend 576
2014
Summary of SCT spending in 2012/13
Significant expenditure for LS1 work already in 2012
2012 2013
Transport & Insurance 1.1 1.2
Orders (inc AAs, non manpower)
363.1 272.4 (+92.5 open commitment)
Epool 25.4 24.3
Subsistence 302.3 109.6
Store items 11.3 9.3
GSM 4.9 10.1
Manpower AA 88.08 (JP/KN) 42.7 (KN)
Total 796.1 562.1
Significant LS1 related items (kCHF)
T577030 2012 2013
LightABLEs - 157
ROD construction 137 -
BOC construction - 82
BPM-12 production 82 -
Taiwan TX 44 -
LightABLE TX production
- 39
2013 Orders/AAs Greater than CHF 3K Total Spend 365kCHF
• LightABLE engines 157,354
• BOC production (AA) 82,090
• Electronics for TX production 39,405
• CAN interface 9,134
• Wiener power supply refurbishment 7,020
• DCS Fan replacements 6,991
• DAQ server warrant extension 3,919
• FSI laser service 3,661
• Multiple (hundreds) of small parts. ---
Subsistence
• In 2013 10 individuals supported at CERN for various items – Operations (Jan-Feb)
– LS1 activities (heaters, env, ground monitor)
– Sonar • Max duration (at full subsistence) ~6 months
• First 6 months of 2014: – 2 individuals on AA (KN + JP)
– 3-4 individuals on short trips
• Significant increase from mid 2014
2014 spending & Scrutiny • Fulfill 2013 open commitments
– LTx, server warranties
• New DAQ servers in last quarter
– ~60kCHF
• Subsistence increase
– From 109kCHF in 2013 to ~200kCHF
– (was 300kCHF in 2012)
• Likely underspend in 2014
ID Scrunity Group meeting next week (ID PLs chaired by Marko Mikuz) with presentation to SG (by me or Heinz)
on 27.06.2014