120612 Standard Specification Stage2 Interim Report Appendices

  • Upload
    max

  • View
    218

  • Download
    0

Embed Size (px)

Citation preview

  • 7/21/2019 120612 Standard Specification Stage2 Interim Report Appendices

    1/64

    Standardised Specification

    and Standard Details

    Stage 2 Report

    Progress Report on Local Authority SpecificationVariations

    Appendices to the Report

    June 2012

  • 7/21/2019 120612 Standard Specification Stage2 Interim Report Appendices

    2/64

    Images on cover sheet courtesy of HMEP

    Images in main report courtesy of Midlands Highway Alliance

    1STANDARDISED SPECIFICTION AND STANDARD DETAILS

    JUNE 2012

  • 7/21/2019 120612 Standard Specification Stage2 Interim Report Appendices

    3/64

    REVISION SCHEDULE

    Standard Specification and Standard Details

    Stage 2 Progress Report

    Rev Date Details Prepared by Reviewed by Approved by

    01 13/04/12 Draft Ed Varley

    Principal Engineer

    John Cole

    Principal

    Engineer

    Anna Moore

    Associate

    02 07/06/12 Issue 1 Ed Varley

    Principal Engineer

    John Cole

    Principal

    Engineer

    Anna Moore

    Associate

    2STANDARDISED SPECIFICTION AND STANDARD DETAILS

    JUNE 2012

  • 7/21/2019 120612 Standard Specification Stage2 Interim Report Appendices

    4/64

    Contents

    CONTENTS

    COMMENT AND FEEDBACK 4

    APPENDICES 5

    Appendix 1 Series 500 Drainage andService Ducts 6

    Appendix 2 Series 700/900 RoadPavements - Bituminous Bound Materials 20

    Appendix 3 Series 1100 Footways andPaved Areas 26

    Appendix 4 Series 1200 Road Markingsand Road Studs 50

    Appendix 5 Series 1300 Street LightingColumns and Brackets 52

    Appendix 6 Series 1700 StructuralConcrete 53

    Appendix 7 Series 1800 - StructuralSteelwork 55

    Appendix 8 Winter Maintenance Materials56

    ABBREVIATIONS USED 62

    LIMITATIONS 63

    3STANDARDISED SPECIFICTION AND STANDARD DETAILS

    JUNE 2012

  • 7/21/2019 120612 Standard Specification Stage2 Interim Report Appendices

    5/64

    Foreword

    COMMENT AND FEEDBACK

    The HMEP Programme Board would welcome any comments and feedback onthis report so that the final product may be reviewed, improved and refined to

    give the sector the best advice possible. If you wish to make a comment,please email them to [email protected] the headerFeedback on the Standard Specification and Standard Details.

    4STANDARDISED SPECIFICTION AND STANDARD DETAILS

    JUNE 2012

    mailto:[email protected]:[email protected]
  • 7/21/2019 120612 Standard Specification Stage2 Interim Report Appendices

    6/64

    Appendices

    APPENDICES

    5STANDARDISED SPECIFICTION AND STANDARD DETAILS

    JUNE 2012

  • 7/21/2019 120612 Standard Specification Stage2 Interim Report Appendices

    7/64

    Appendix 1 Series 500 Drainage and Service Ducts

    Appendix 1 Series 500 Drainage and Service Ducts

    Summary of information provided by local highways authorities as part of the HMEP

    survey carried out in October 2011.

    SR Series Supplementary Addi tional Clauses

    The following table summarises where authorities have varied drainage clauses

    together with a commentary on their relevance to the Specification.

    Addi tional Clauses Additions/Changes Comment

    Resetting of Covers

    and Frames;

    Defines further/specific

    requirements for the re-setting

    of footway, and carriagewayironwork;

    The resetting of covers and

    frames is considered to be an

    aspect that requires furtherreview and possible update

    to the current SHW.

    Defines specific requirements

    for the resetting of British

    Telecom carriageway ironwork

    using resin bedding and resin

    mortar;

    Defines specific requirements

    for resetting of British Telecom

    ironwork in footways;

    Defines specific requirements

    for the re-setting Fire Hydrants

    in footways and carriageway.

    Special Treatment

    of Existing Sewers,

    Drains, Ducts,

    Services and the

    like.

    Provides additional general

    requirements in connection with

    existing sewers, drains, ducts

    and services.

    Current SHW considered to

    be acceptable and therefore

    unnecessary to include.

    Works on Existing

    Drains Sewers and

    Manholes;

    Provides general requirements

    with regard to taking measures

    when working on existing drains

    to prevent debris from entering

    the system.

    Also introduces specific

    requirement to prove by CCTV

    survey downstream runs ofexisting drainage and make

    good where necessary where

    Current SHW considered to

    be acceptable and therefore

    unnecessary to include.

    6STANDARDISED SPECIFICTION AND STANDARD DETAILS

    JUNE 2012

  • 7/21/2019 120612 Standard Specification Stage2 Interim Report Appendices

    8/64

    Appendix 1 Series 500 Drainage and Service Ducts

    7STANDARDISED SPECIFICTION AND STANDARD DETAILS

    JUNE 2012

    Addi tional Clauses Additions/Changes Comment

    new connections are made into

    the system.

    Gully Set in Verge; Provides general requirementsfor the construction of new

    gullies set in verge and

    treatment to

    replaced/abandoned gullies.

    Considered to be specific toThe Council and therefore

    inappropriate to include

    within the current SHW.

    Small Headwall; Provides general requirements

    for the construction of small

    headwalls using either concrete

    block and in-situ concrete or

    concrete bag construction.

    Considered to be specific to

    The Council and therefore

    inappropriate to include

    within the current SHW.

    Reinstatement of

    Drainage and

    Service Ducts in the

    Carriageway,

    Footway and Verge

    (Trench

    Reinstatement);

    Provides general requirements

    for trench reinstatement in both

    carriageways and verges.

    Current SHW considered to

    be acceptable and therefore

    unnecessary to include.

    Disconnect and Fill

    Existing Manhole,Catchpit or Gully.

    Provides general requirements

    for the removal and backfilling ofredundant chambers and

    gullies.

    Current SHW considered to

    be acceptable and thereforeunnecessary to include.

    Existing Drainage; Provides general requirements

    for the renewal of filter drains

    and drain runs

    Current SHW considered to

    be acceptable and therefore

    unnecessary to include.

    Deep Bored

    Soakaways;

    Provides specific requirements

    for the construction of deep

    bored soakaways.

    Considered to be specific to

    Kent CC and therefore

    inappropriate to include

    within the current SHW.

    Adjustment of

    Ironwork.

    Reconfirms that the

    replacement/adjustment of

    existing frames, covers and

    gratings shall be carried out in

    accordance with the SHW.

    As per current SHW

    therefore considered

    unnecessary to include.

    Pipes for Drainage

    and for Service

    Ducts;

    Requires Sulphate Resisting

    Portland cement to be used and

    all standard mixes of concrete

    used in drainage works to be the

    GEN series and not ST

    Considered to be specific to

    Council and therefore

    inappropriate to include

    within the current SHW.

  • 7/21/2019 120612 Standard Specification Stage2 Interim Report Appendices

    9/64

    Appendix 1 Series 500 Drainage and Service Ducts

    8STANDARDISED SPECIFICTION AND STANDARD DETAILS

    JUNE 2012

    Addi tional Clauses Additions/Changes Comment

    references.

    Excavations for

    Pipes andChambers;

    Modifies trench widths and

    provides additional generalrequirements for the

    construction of drainage runs.

    Considered to be specific to

    Council and thereforeinappropriate to include

    within the current SHW.

    Bedding, Laying

    and Surrounding of

    Pipes (Including

    Cable Ducts);

    Reconfirms requirements of the

    SHW in respect of laying new

    drainage pipes.

    Reclassifies required pipe

    bedding requirements.

    Provides requirements for whennew drains are laid below

    groundwater level.

    Considered to be specific to

    Council and therefore

    inappropriate to include

    within the current SHW.

    Jointing of Pipes; Provides general requirements

    for jointing of pipes.

    Current SHW considered to

    be acceptable and therefore

    unnecessary to include.

    Backfilling of

    Trenches and Filter

    Drains;

    Requires the use of sub-base

    material Type 2 to be used in

    backfilling of trenches.

    Considered to be specific to

    Council and therefore

    inappropriate to include

    within the current SHW.

    Connecting to

    Existing Drains;

    Chambers and

    Channels;

    Provides additional

    requirements in respect of

    entering/breaking into existing

    drains, sewers or chambers.

    Current SHW considered to

    be acceptable and therefore

    unnecessary to include.

    Chambers; Required GEN series concrete

    mixes to be used in the

    construction of chambers.

    Provided additionalrequirements in connection with

    the construction of chambers.

    Considered to be specific to

    Council and therefore

    inappropriate to include

    within the current SHW.

    Gullies and Pipe

    Junctions.

    Requires the use of sub-base

    material Type 2 to be used in

    backfilling of gullies.

    Considered to be specific to

    Council and therefore

    inappropriate to include

    within the current SHW.

    Low Pressure High

    Volume Jetting of

    Drainage Systems;

    Provides specific requirements

    for the jetting of piped drainage

    systems.

    This additional clause

    replicates what is already

    included within the SHW

    under Clause 521.

  • 7/21/2019 120612 Standard Specification Stage2 Interim Report Appendices

    10/64

    Appendix 1 Series 500 Drainage and Service Ducts

    9STANDARDISED SPECIFICTION AND STANDARD DETAILS

    JUNE 2012

    Addi tional Clauses Additions/Changes Comment

    Existing Drain

    Cleansing;

    Provides specific requirements

    for cleaning/clearing existing

    gullies and chambers

    Considered to be specific to

    Council and relates to

    maintenance requirements,

    therefore inappropriate to

    include within the current

    SHW.

    Replacing, Raising

    or Lowering Covers,

    Gratings and

    Frames on Existing

    Chambers and

    Gullies.

    Provides general requirements

    for replacing, raising or lowering

    frames, covers and gratings on

    existing chambers.

    The resetting of covers and

    frames is considered to be an

    aspect that requires further

    review and possible update

    to the current SHW.

    Closed Circuit TV

    Inspection of Drains

    and Sewers;

    Provides specific requirements

    for undertaking CCTV inspection

    of drains and sewers.

    The requirements for carrying

    out CCTV inspections are

    covered by the current SHW

    under Volume 5, Special

    Activities, Section 9, Model

    Contract Documents For

    CCTV Survey of Highway

    Drainage Systems.

    Oil Interceptor

    Units.

    Provides general requirements

    for Oil interceptors.

    The design and specification

    of Oil Interceptors isconsidered to be contract

    specific and will generally be

    design by the contractor. It is

    therefore considered

    inappropriate to include any

    specific requirements with

    regard to Oil Interceptors

    within the SHW.

    Replacement ofFilter Material in

    Existing Filter

    Drains;

    Provides general requirementsfor replacement of filter material

    in existing drains.

    Considered to be a contractspecific requirement and

    therefore unnecessary to

    include in the general SHW.

    Drainage Grips. Provides general requirements

    for the construction of drainage

    grips.

    Considered to be outside the

    scope of the HMEP project

    brief.

  • 7/21/2019 120612 Standard Specification Stage2 Interim Report Appendices

    11/64

    Appendix 1 Series 500 Drainage and Service Ducts

    AR Series -Amended Clauses

    The following table summarises the various amended clauses received together with a

    commentary on their relevance to the Specification.

    Heading AmendedClause

    Additions/ Changes Comment

    Pipes for

    Drainage

    and Service

    Ducts

    501.8 Removes current

    specification requirements

    for draw rope through

    ducts.

    Considered unnecessary to

    remove current SHW

    requirements.

    Chambers 507.18 Minor addition to current

    specification.

    Considered unnecessary to

    incorporate in current SHW.

    CombinedDrainage

    and Kerb

    Systems

    516.1 Requires that anycombined drainage and

    kerb system shall be the

    Beany Block system as

    supplied by Marshalls.

    Considered inappropriate tospecify a specific type of

    system therefore should not be

    included in the SHW.

    Chambers 507.16 Cross references to

    Appendix 5/1 for further

    specific requirements for

    bedding mortars and

    proprietary quick setting

    mortars.

    Linked to resetting of frames,

    covers and gullies. Further

    review required to establish

    whether current SHW should

    be updated in respect of this

    issue.

    507.19 Provides additional minor

    requirements for the

    construction/resetting of

    chamber covers.

    Considered unnecessary to

    incorporate in current SHW.

    Chambers 507.1 Removes reference to

    motorway communications

    installations and introduces

    interceptors as beingdefined as chambers.

    Considered appropriate to

    remove any reference to

    motorways as these will not

    be encountered by localauthorities.

    507.3 Requires that brickwork to

    chambers should be one

    brick thick.

    Considered unnecessary to

    include this. Sufficient detail is

    provided in the standard

    details with regard to the

    construction of chambers.

    Gullies andPipe 508.1 Removes reference tosumpless gullies as an Considered inappropriate toexclude sumpless gullies as an

    10STANDARDISED SPECIFICTION AND STANDARD DETAILS

    JUNE 2012

  • 7/21/2019 120612 Standard Specification Stage2 Interim Report Appendices

    12/64

    Appendix 1 Series 500 Drainage and Service Ducts

    11STANDARDISED SPECIFICTION AND STANDARD DETAILS

    JUNE 2012

    Heading Amended

    Clause

    Additions/ Changes Comment

    Junctions allowable gully option. acceptable option.

    508.6 Requires that only ST2concrete shall be used as

    backfill to gullies.

    Considered inappropriate toadopt the use of ST2 concrete

    as backfill to gullies throughout

    the sector.

    Combined

    Drainage

    and Kerb

    Systems

    516.1 Cross references to

    Appendix 5/5 for details of

    combined drainage

    systems.

    Current SHW considered

    appropriate therefore

    unnecessary to include

    modification.

    Linear

    Drainage

    Channel

    Systems

    517.1 Cross references to

    Appendix 5/6 for details of

    combined drainage

    systems and removes

    reference to Appendix

    1/11.

    Current SHW considered

    appropriate therefore

    unnecessary to include

    modification.

    The

    Cleaning of

    Existing

    Drainage

    Systems

    520.1 Introduces alternative

    requirements and time

    frame for the contractor to

    carry out cleaning of

    existing drainage systems.

    Current SHW considered

    appropriate therefore

    unnecessary to include

    modification.

    Bedding,

    Laying and

    Surrounding

    of Pipes

    503.3 Introduces minor

    amendment to current

    specification.

    Current SHW considered

    appropriate therefore

    unnecessary to include

    modification.

    Chambers 507.16 Introduces additional

    requirement for the setting

    of frames, covers and

    gratings which is already

    included in Clause 507.18.

    Current SHW considered

    appropriate therefore

    unnecessary to include

    modification.

    Gullies and

    Pipe

    Junctions

    508.4 Introduces

    alternative/additional

    requirements in respect of

    gullies.

    Linked to resetting of frames,

    covers and gullies. Further

    review required to establish

    whether current SHW should

    be updated in respect of this

    issue.

    Permeable

    Backing to

    Earth

    Retaining

    513.1 Introduces

    alternative/additional

    requirements in respect of

    porous concrete blocks

    used in back of wall

    Current SHW considered

    appropriate therefore

    unnecessary to include

    modification.

  • 7/21/2019 120612 Standard Specification Stage2 Interim Report Appendices

    13/64

    Appendix 1 Series 500 Drainage and Service Ducts

    12STANDARDISED SPECIFICTION AND STANDARD DETAILS

    JUNE 2012

    Heading Amended

    Clause

    Additions/ Changes Comment

    Structures drainage.

    Connectingto Existing

    Drains

    Chambers

    and

    Channels

    506.2 Minor addition to currentspecification.

    Considered unnecessary toincorporate in current SHW.

    506.3 Cross references to

    Appendix 5/1 for details on

    disconnection of existing

    drains.

    Current SHW considered

    appropriate therefore

    unnecessary to include

    modification.

    Gullies and

    Pipe

    Junctions

    508.1 Cross references to

    Appendix 5/1 for inclusion

    of alternative drawings for

    gully construction.

    Current SHW considered

    appropriate therefore

    unnecessary to include

    modification.

    Backfilling

    of Trenches

    and Filter

    Drains

    505.10 New sub-clause cross

    referencing to Appendix

    5/1 to introduce need for

    geotextile filter around filter

    drains and filter material.

    The adoption of geotextile

    lining to filter drains is

    considered to be contract

    specific. The current

    specification/ design for filterdrains included in the SHW is

    considered appropriate.

    505.11 New sub-clause detailing

    specific requirements for

    the storage of geotextiles

    used in filter drains.

    505.12 New sub-clause detailing

    specific requirements for

    geotextiles used in andconstruction of filter drains.

    505.13 New sub-clause detailing

    specific requirements for

    the handling of geotextiles

    used in filter drains.

    505.14 New sub-clause

    introducing minor addition

    with regard to information

    to be supplied in respect of

    geotextiles used in filter

  • 7/21/2019 120612 Standard Specification Stage2 Interim Report Appendices

    14/64

    Appendix 1 Series 500 Drainage and Service Ducts

    13STANDARDISED SPECIFICTION AND STANDARD DETAILS

    JUNE 2012

    Heading Amended

    Clause

    Additions/ Changes Comment

    drains.

    505.15 New sub-clauseintroducing minor addition

    with regard to certification

    in respect of geotextiles

    used in filter drains.

  • 7/21/2019 120612 Standard Specification Stage2 Interim Report Appendices

    15/64

    Appendix 1 Series 500 Drainage and Service Ducts

    Summary of Standard Detail Drawings Review- Survey Responses

    14STANDARDISED SPECIFICTION AND STANDARD DETAILS

    JUNE 2012

  • 7/21/2019 120612 Standard Specification Stage2 Interim Report Appendices

    16/64

    Appendix 1 Series 500 Drainage and Service Ducts

    The following table provides a summary of the questions and responses to the survey

    questionnaire along with initial comment on their relevance to the Specification.

    Question Survey Response Comment

    Does therange of

    specified

    material types

    (e.g. pipe

    types) match

    what is readily

    available?

    Yes = 89.5%,

    No = 10.5%

    The results of the survey clearly concludethat the current range of specified

    materials within/included in the MCHW

    SHW is acceptable.

    Do you use

    pipe types not

    specified in the

    MCHW?

    Yes = 15.55%,

    No = 84.4%

    Linked to Qu 16 the results of the survey

    further conclude that the current range of

    specified materials within/included in the

    MCHW SHW is acceptable.

    Is the range of

    specified

    drainage

    systems

    appropriate?

    [Note the HA

    plans topublish a new

    Part listing all

    sustainable

    drainage

    systems, to

    reflect the

    forthcoming

    national

    standards for

    sustainable

    drainage.]

    Yes = 67.9%,

    No = 32.1%

    The direct results to this question are less

    conclusive than for previous questions,

    however, review of the comments

    provided by consultees would suggest

    that this is directly due to the lack of detail

    included in the current Specification on

    Sustainable Drainage Systems (SUDS).

    As identified in the question the HA plans

    to publish a new part to the Specification

    listing all sustainable drainage systems, to

    reflect the forthcoming national standards

    for sustainable drainage.

    It is considered that inclusion of a

    specification for SUDS is outside the

    scope of the current commission. It is not

    possible to pre-empt the outcome of the

    Highways Agencys ongoing work on this

    aspect. It is therefore concluded that no

    further work should be carried out in

    respect of SUDS.

    Should the

    specification

    specify a

    design life for

    constructed

    drainage?

    Yes = 81.4%,

    No = 18.6%

    The results of the survey clearly conclude

    that the Specification should include a

    design life for constructed drainage.

    If so, what 0-10 years 0.0% The results from the survey would

    15STANDARDISED SPECIFICTION AND STANDARD DETAILS

    JUNE 2012

  • 7/21/2019 120612 Standard Specification Stage2 Interim Report Appendices

    17/64

    Appendix 1 Series 500 Drainage and Service Ducts

    16STANDARDISED SPECIFICTION AND STANDARD DETAILS

    JUNE 2012

    Question Survey Response Comment

    design life

    would you

    anticipate?

    20 years 8.0%

    50 years 44.0%

    100 years 32.0%

    Other 16.0%

    suggest that the design life for new

    drainage should be a minimum 50 years.

    There are considered to be two distinctissues that will impact on the operational

    effectiveness of any new drainage asset

    during its operational life as detailed

    below:

    The operational effectiveness of the asset

    in respect of its ability to deal with

    changes (i.e. any increase) in discharge

    flows over time;

    The physical construction of the drainage

    asset being sufficient to remain

    operational and free from major defect.

    In respect of Item 1 above, current design

    guidance dictates that design flows

    include for a 20% uplift to take account of

    Climate Change. It is therefore

    considered that this aspect is currently

    adequately dealt with.

    With regard to the as-constructed system

    being of an adequate standard to

    physically last for the required design life

    this will be dependent upon a number of

    factors which include:

    1. Construction design;

    2. Materials used;

    3. Operational maintenance.

    The construction design of fundamental

    elements of any new drainage system (i.e.

    chambers, gullies and pipe runs) is based,

    in general, on tried and tested principles

    which have resulted in the development of

    the current Standard Details that are

    included within the current SHW.

    It is accepted that these Standard Details

    will be subject to refinement over time as

    new materials and techniques aredeveloped but in principle it is considered

    that they currently meet the requirements

  • 7/21/2019 120612 Standard Specification Stage2 Interim Report Appendices

    18/64

    Appendix 1 Series 500 Drainage and Service Ducts

    17STANDARDISED SPECIFICTION AND STANDARD DETAILS

    JUNE 2012

    Question Survey Response Comment

    for sound construction design.

    It is noted that there are differences

    between the Motorway/ Trunk RoadNetwork (for which the current SHW has

    been developed) and the local road

    network and a number of key drainage

    elements that are required for local roads

    are not included. An aim of this current

    review is to identify and include those

    standard construction details that are

    currently not covered by the SHW.

    The materials to be used in the

    construction of drainage systems are

    considered, in the main, to be defined well

    by the current Specification. Material

    specifications for component elements

    (i.e. pipes, chamber covers and gratings)

    are controlled by standards and codes

    that are referenced within the

    Specification. Where further detail is

    required on the specific requirements of

    materials such as pipe bedding and

    trench backfill this is provided within the

    document.

    Maintenance of the drainage system is a

    fundamental requirement to ensuring the

    operational effectiveness of the system

    and prolonging its operational life.

    The maintenance regime to be adopted

    for drainage systems is not covered by

    the SHW as this is generally dealt with

    separately by other documentation (i.e.

    Network Management Manual).

    It is therefore considered unnecessary to

    include within the SHW maintenance

    requirements for drainage systems.

    What is the

    actual life of

    drainage

    encounteredbefore major

    renewals or

    0-10 years 0.0%

    20 years 0.0%

    Review of the survey results and

    comments received to this question would

    indicate that actual life of drainage before

    renewals is required is 50 years. Thiswould suggest that the current

    Specification is achieving the expectations

  • 7/21/2019 120612 Standard Specification Stage2 Interim Report Appendices

    19/64

    Appendix 1 Series 500 Drainage and Service Ducts

    18STANDARDISED SPECIFICTION AND STANDARD DETAILS

    JUNE 2012

    Question Survey Response Comment

    replacement? 50 years 39.3%

    100 years 19.6%

    Other 41.1%

    of Local Authorities.

    The results of the survey conclude that

    drainage should be specified on a fitnessfor purpose basis.

    Should

    drainage be

    specified on a

    fitness for

    purpose

    basis?

    Yes = 72.9%,

    No = 27.1%

    The adoption of fitness for purpose for

    the design and construction of drainage

    infrastructure may/will impact on both

    Designers and Contractors. The legal

    and insurance (i.e. professional

    indemnity) implications of adopting a

    fitness for purpose basis needs to be

    fully investigated which is currently

    considered to be outside the scope of this

    current review.

    For ductile iron

    covers what

    depth do you

    normally

    specify for

    trafficked

    areas?

    100mm 23.6%

    150mm 76.4%

    The results of the survey clearly indicate

    that Local Authorities currently prefer and

    adopt 150mm deep ductile iron covers for

    trafficked areas.

    The current Specification specifies that

    chamber covers and gully gratings shall

    comply with the requirements of BS EN124. Consideration needs to be given to

    whether the specification for chamber

    covers and gully gratings needs to be

    modified to take account of new products

    and the issues identified in the response

    to Qu 24.

    For gully and

    manhole

    covers in

    trafficked

    areas is there

    an increased

    need to rebed

    or replace the

    covers in the

    last 10 years?

    Yes = 81.4%,

    No = 18.6%

    The results of the survey clearly indicate

    that there is an increased need to rebed

    and replace gully and manhole covers

    located in trafficked areas.

    A review of the responses as to why this

    is occurring identifies the following key

    reasons for this problem:

    1. Increase in traffic volumes andloading (i.e. increased volume andweight of HGVs);

    2. Inappropriate bedding material

    and insufficient time for beddingmaterials to cure before trafficking;

    3. Poor workmanship (linked to

  • 7/21/2019 120612 Standard Specification Stage2 Interim Report Appendices

    20/64

    19

    Appendix 1 Series 500 Drainage and Service Ducts

    STANDARDISED SPECIFICTION AND STANDARD DETAILS

    JUNE 2012

    Question Survey Response Comment

    available time to make repairs);

    4. Design/strength of ironwork;

    5. Deteriorating network condition;

    6. Theft;

    It is considered that further investigation is

    undertaken into all of the above aspects

    to try and improve the design and

    construction specification for chamber

    covers, frames and gullies.

  • 7/21/2019 120612 Standard Specification Stage2 Interim Report Appendices

    21/64

    Appendix 2 Series 700 / 900 Road Pavements Bi tuminous Bound Materials

    Appendix 2 Series 700/900 Road Pavements - Bituminous Bound Materials

    Summary of information provided by local highways authorities as part of the HMEP

    survey carried out in October 2011.

    Title of Sub Clauses Changes from original

    SHW

    Comments on changes

    901 Bituminous

    pavement materials

    Significant changes.

    See comments.

    These were based on SHW (11/04)

    edition, presenting amendment

    (additional and substitute) clauses

    on installation (transportation, laying

    and compaction). The current SHW

    (11/08) specifies these in Clause

    903, where these details should be

    considered

    903SR Placing and

    Compaction of

    Bituminous Mixtures

    Further details were

    added.

    Most of these details are contained

    in BS 594987 (already referenced

    by the current SHW). This clause,

    903SR, also contains application for

    footways however this should not be

    part of Series 900 but to be covered

    by Series 1100.

    Revision to this clause is required to

    accommodate recent best practice

    for laying and to improve durability

    911SR Hot Rolled

    Asphalt (HRA) Surface

    Course (Design

    Mixtures)

    There a number of

    HRA variants which

    are specified based on

    either a conventional

    Marshall Mixture

    Design (MMD) and a

    performance based

    approach.

    It is recommended that these two

    design approaches are separated to

    allow consistency with the current

    SHW (11/08), specifically by

    retaining that using MMD approach

    within this clause but transferring

    those with performance based

    approach to Clause 943. The latter

    will incorporate additional clauses toencompass the use of 30/14 and

    55/14 HRA materials (note: the

    current Clause 943 covers 35/14

    HRA only).

    918SR Slurry

    Surfacing

    Incorporating

    Microsurfacing

    This SR clause covers

    application for

    footways and

    carriageways.

    It is recommended that the former

    should be excluded from Series 900

    and transferred to Series 1100.

    919SR Surface

    Dressing: Recipe

    There are some

    repetitions regarding

    ingredient materials

    Additional references to TRL RN39

    and the recent RSTA code of

    practice should be added. Therefore

    20STANDARDISED SPECIFICTION AND STANDARD DETAILS

    JUNE 2012

  • 7/21/2019 120612 Standard Specification Stage2 Interim Report Appendices

    22/64

    Appendix 2 Series 700 / 900 Road Pavements Bi tuminous Bound Materials

    21STANDARDISED SPECIFICTION AND STANDARD DETAILS

    JUNE 2012

    Title of Sub Clauses Changes from original

    SHW

    Comments on changes

    Specification (e.g. chipping

    gradation and

    properties); these can

    be simplified.

    revision to 919SR is required.

    920SR Bituminous

    sprays

    See comments. These were outdated and based on

    SHW (11/04) edition. The current

    SHW (11/08) is sufficient.

    921SR Surface

    Macrotexture of

    Bituminous Surface

    Courses

    This clause contains

    specific requirements

    from The County

    Council.

    Details in the current SHW (11/08)

    should be sufficient for general use

    and allow options to use

    conventional method ofassessments and well as the

    automated method adopted by The

    County Council.

    926SR In situ recycling

    - the remix and repave

    process

    This clause introduces

    in situ repair process.

    This should be covered in the new

    clause 951AR on Patching.

    931SR Use of Rubber

    in Materials

    Provision on the use of

    rubber in bituminous

    mixtures.

    This clause is now obsolete, making

    a reference to Road Note 36 (1968).

    This clause was allocated for RecipeMixtures: Heavy Duty Macadam

    Base and Binder Course Macadams

    with Paving Grade Bitumen (SHW

    11/04) but now no longer in use

    (since SHW 11/08). This material is

    no longer in use hence may be

    omitted.

    937AR Stone mastic

    asphalt used as

    surface course

    Introduce the use of

    SMA in surface

    course.

    It may be better to address the use

    of in Clause 972AR to avoid conflict

    with the existing SHW.

    942SR Thin Surface

    Course Systems

    Allowance to use

    materials without BBA

    HAPAS certificates.

    Revision to the current SHW (11/08)

    is required, to consider the new IAN

    157/11 and the draft IAN 154

    regarding the installation of this

    material and the approval system

    942SR Thin Surface

    Course Systems

    Surface integrity

    guarantee has been

    reduced to 3 years.

    Consider the new IAN 157/11 and

    the draft IAN 154 regarding the

    installation of this material and the

    approval system

  • 7/21/2019 120612 Standard Specification Stage2 Interim Report Appendices

    23/64

    Appendix 2 Series 700 / 900 Road Pavements Bi tuminous Bound Materials

    22STANDARDISED SPECIFICTION AND STANDARD DETAILS

    JUNE 2012

    Title of Sub Clauses Changes from original

    SHW

    Comments on changes

    945SR Weather

    Conditions for Laying

    of Hot Bituminous

    Mixtures

    It clearly presents

    some details for rolled

    asphalt application but

    not so for other

    materials.

    An update is recommended.

    959AR Bituminous

    mixtures to BS EN

    13108

    Additional clause This clause makes reference to BS

    EN 13108-1, 2, 4 and 5. These are

    unnecessary duplicates of the

    previous clauses. Therefore this

    clause can be omitted.

    959AR Resin basedcoloured surface

    treatment

    Additional clause This clause makes allowance tospecifying the use of this material for

    lane demarcation.

    960AR Use of slag

    aggregate in

    bituminous mixtures

    Additional clause. This

    clause prohibits the

    use of blast furnace

    and steel slag

    aggregates in asphalt

    mixtures.

    This requirement is specific for the

    Council. The use of these slag

    aggregates is generally acceptable

    provided that the aggregates meet

    the requirements of Clause 901 and

    the bituminous mixtures are properly

    designed. Therefore this clause can

    be omitted.

    960AR Guide to use

    slag aggregate in

    asphalt mixtures.

    Additional clause. This

    clause prohibits the

    use of slag aggregate

    in low temperature

    asphalt mixtures.

    The reason behind this is unknown

    and requires further considerations

    by contacting the Council f or

    discussion.

    960AR Stress

    absorbing membrane

    interface (SAMI)

    Additional clause This clause makes allowance to the

    use of SAMI.

    961AR Sand carpet

    asphalt

    Additional clause This clause specifies the use of

    HRA 0/2F surf 70/100 with minimum

    binder content of 10.8% (m/m).

    Without more detailed information

    about this clause it is not possible to

    comment further.

    961AR Stress

    absorbing membrane

    (SAM)

    Additional clause This clause makes allowance to the

    use of SAM.

    962AR PSV

    Requirements of

    Additional clause This clause could have been

    incorporated in the relevant clauses

  • 7/21/2019 120612 Standard Specification Stage2 Interim Report Appendices

    24/64

    Appendix 2 Series 700 / 900 Road Pavements Bi tuminous Bound Materials

    23STANDARDISED SPECIFICTION AND STANDARD DETAILS

    JUNE 2012

    Title of Sub Clauses Changes from original

    SHW

    Comments on changes

    Surface Course

    Asphalt

    of the respective surface course.

    Therefore this clause can be omitted

    963AR removal of

    Existing Asphalt

    Layers

    Additional clause This clause could have been

    incorporated in clause 902.

    Therefore this clause can be

    omitted.

    964AR Surface

    Preparation (Crack

    Filling)

    Additional clause This clause could have been

    incorporated in clause 902.

    Therefore this clause can be

    omitted.

    965AR Ironworks and

    Drainage

    Additional clause Consider adopting this clause, with

    some modifications.

    970SR Shaping

    existing carriageway

    (Bituminous Bound

    Materials)

    Additional clause This clause is about regulating layer

    and it is better included in Clause

    907.

    970AR Compaction

    control of asphalt

    mixtures

    Additional clause Broadly quoting BS 594987

    practices. It may be better included

    in the new Clause 903AR.

    970AR 45% stone

    content hot asphalt

    surface course (for

    hand laying)

    Additional clause This clause allows the use of non-

    standard HRA 45/XX type F 160/220

    and is site specific. For simplicity,

    this clause can be omitted.

    970AR Intermediate

    asphalt concrete

    surface course

    Additional clause This clause allows the use of non-

    standard binder rich AC 20 close

    surf 100/150 and is site specific. For

    simplicity, this clause can be

    omitted.

    970AR Pre-patching

    repairs to carriageway

    using only surface

    course materials

    Additional clause It will be more appropriate to

    consider this clause under the new

    Clause 951SR (Patching).

    971AR Stone Mastic

    Asphalt Surface

    Course

    Additional clause This clause contains extracts from

    BSI PD 6691 and BS 594987. An

    update is required to accommodate

    the most reference update on

    Transport Scotland TS2010 (Ver2.0, 2012).

  • 7/21/2019 120612 Standard Specification Stage2 Interim Report Appendices

    25/64

    Appendix 2 Series 700 / 900 Road Pavements Bi tuminous Bound Materials

    24STANDARDISED SPECIFICTION AND STANDARD DETAILS

    JUNE 2012

    Title of Sub Clauses Changes from original

    SHW

    Comments on changes

    971AR Fine

    Regulating Course

    Additional clause This clause permits the use HRA

    50/10 bin 40/60 only for regulating

    layer. It is better placed in the new

    Clause 907AR

    972AR Cold in situ

    recycled bitumen

    stabilised base

    Additional clause This clause is similar to SHW

    Clause 948 but contained obsolete

    BS. It may be better omitted and

    new reference made to Clause 948.

    972AR Surface

    treatments -

    application of grit toenhance early life

    skidding resistance

    Additional clause This concerns the use of coated and

    non coated grit. It may be better

    placed and/or incorporated in971AR.

    973AR Cold in situ

    recycled bitumen

    stabilised base and

    foamed bitumen

    binder course - mixture

    design and

    characterisation

    Additional clause This clause is similar to SHW

    Clause 948 but contained obsolete

    BS. It may be better omitted and

    new reference made to Clause 948

    973AR Compaction

    Requirements

    Additional clause It may be better included in the new

    Clause 903AR.

    974AR Foamed

    bitumen bound binder

    course

    Additional clause This clause is similar to SHW

    Clause 948 but contained obsolete

    BS. It may be better omitted and

    new reference made to Clause 948.

    974AR Retread

    process

    Additional clause A reference can also be made to

    DMRB HD31/94. An update to this

    clause is recommended.

    975AR Annex B BS

    13108-1 Asphalt

    Concrete Specification

    Additional clause Similar to PD 6691. These are

    unnecessary duplicates of the

    previous/existing SHW clauses.

    Therefore this clause can be

    omitted.

    975AR Surface

    dressing

    Additional clause It is about installation process.

    These have been broadly covered

    by previous clauses (919 and 922).

    Therefore this clause can be

    omitted.

  • 7/21/2019 120612 Standard Specification Stage2 Interim Report Appendices

    26/64

    25

    Appendix 2 Series 700 / 900 Road Pavements Bi tuminous Bound Materials

    STANDARDISED SPECIFICTION AND STANDARD DETAILS

    JUNE 2012

    Title of Sub Clauses Changes from original

    SHW

    Comments on changes

    976AR Annex C BS

    13108-4 Hot rolled

    asphalt Specification

    Additional clause Similar to PD 6691. These are

    unnecessary duplicates of the

    previous/existing SHW clauses.

    Therefore this clause can be

    omitted.

  • 7/21/2019 120612 Standard Specification Stage2 Interim Report Appendices

    27/64

    Appendix 3 Series 1100 - Footways and Paved Areas

    Appendix 3 Series 1100 Footways and Paved Areas

    Summary of information provided by local highways authorities as part of the HMEP

    survey carried out in October 2011.

    Clause Reason for Variation Relevance

    1101AR Kerbs,

    Channels, Edgings

    & Quadrants

    (Note: this clause has been re-titled to

    include stone kerbs and setts laid in

    kerblines)

    Sub Clause 1

    Delete "C7.5 or mix ST1" and substitute

    C12/15 or mix ST3"

    Sub Clause 2

    Insert at end Where kerbs are re-laid against

    existing carriageway the kerbline shall be

    sealed in accordance with clauses 1016 &

    1017.

    Sub Clause 3

    Insert at end "For radii of 12m to 25m,

    600mm long straight kerbs may be used. No

    single kerb shall be less than 450mm long."

    Add Sub Clause 6

    The construction principles and practices set

    out in sub clauses 1-5 above shall apply

    equally to stone kerbs and setts laid in

    kerblines, except that the tolerances for

    longitudinal and vertical accuracy shall be

    6mm along the top outer edge of the kerbs

    to allow for local irregularities in shape.

    Cannot find C7.5 or mix

    ST1 in the original SHW.

    Require clarification to

    consider taking this

    forward.

    This sub clause is worth

    taking forward as it ties in

    sub clauses from other

    SHW sections removing

    any vagueness currently

    associated with particular

    tasks.

    This sub clause is worth

    taking forward as it could

    help other LHAs formalise

    requirements.

    This sub clause is worth

    taking forward as it might

    help other LHAs when

    using setts.

    1104AR Footways

    And Paved Areas

    (Precast Concrete

    Flags)

    Clause 1104 para 2

    Delete "Where permitted in Appendix 11/1 ...

    + 5 mm thick."; and

    Substitute "450 x 450 mm small elemental

    paving shall be laid on 100 mm thick grade

    ST1 concrete base leaving 3 to 4 mm joints,

    levelled using a rubber maul and dry silver

    or silica jointing sand complying with Clause

    1107AR brushed into joints for the full

    depth."

    Add additional paragraph.

    5. Tactile paving is generally laid at

    controlled crossings to delineate the position

    This sub clause is worth

    taking forward as it is likely

    to increase the stability of

    small elemental paving for

    longer. It would also help

    other LHAs.

    Tactile Paving is covered

    in latter clauses. This text

    will need to be reviewed in

    conjunction with the other

    26STANDARDISED SPECIFICTION AND STANDARD DETAILS

    JUNE 2012

  • 7/21/2019 120612 Standard Specification Stage2 Interim Report Appendices

    28/64

    Appendix 3 Series 1100 - Footways and Paved Areas

    27STANDARDISED SPECIFICTION AND STANDARD DETAILS

    JUNE 2012

    Clause Reason for Variation Relevance

    of the crossing for blind and partially sighted

    people. It shall be laid to an exact pattern to

    be specified by the Overseeing Organisation

    for each individual site.

    Flags shall be 450 x 450 x 70 mm with

    domes or dimples protruding from the

    uppermost surface and shall be red or buff in

    colour. Domes shall have a height of 6 mm

    and a diameter of 12 mm and shall number

    approximately 49 per flag.

    Flags shall be cut and laid to fit the contours

    of the vehicular crossings and laid in

    accordance with Clause 1104AR above.

    clauses and merged as

    necessary. This may end

    up an AR to clause 1104

    or a separate clause.

    1104 Footways

    And Paved Areas

    (Precast Concrete

    Slabs And Natural

    Stone Flags)

    Delete Sub Clause 2; and Substitute:

    2. Slabs and flags shall be laid to the

    crossfall detailed in Drawing No. LC.07a,

    with transverse joints perpendicular to the

    kerbline unless agreed otherwise with the

    Project Manager. All longitudinal joints shall

    be offset by a minimum of 150 mm except

    where agreed with the Project Manager.

    Slabs and flags shall be bedded on a

    uniform 25mm thick layer of 1:15 dryPortland (CEM I) cement/bedding sand mix.

    The bedding sand shall be clean sharp

    sand, aggregate size 0/4 CP or 0/4 MP to

    BS EN 13139. Where permitted by the

    Project Manager as an alternative, slabs and

    flags up to 450mm square may be bedded

    on a layer of bedding sand 25mm +/- 10mm

    thick. Bedding of slabs on 5 spot mortar is

    not permitted.

    Insert Sub Clauses 4 - 7

    4. Joints between slabs and flags shall be

    close, i.e. 2 to 4 mm in width. Joints shall be

    grouted to within 2 to 3mm of the surface in

    the following manner:

    The surface of the slabs/flags shall be

    watered. A site-mixed grout with a Portland

    (CEM I) cement:sand ratio of 1:8 to 1:10

    shall then be poured on to the surface and

    brushed into the joints. The bedding sand

    shall be clean sharp sand, aggregate size

    0/4CP or 0/4MP to BS EN 13139. A dry

    This sub clause is worth

    taking forward, though it

    needs to be reviewed in

    association with the similar

    sub clause suggested in

    1104AR above.

    References to specific

    LHA diagrams needs to be

    removed and replacedwith MHA related

    diagrams thus the MHA

    diagram catalogue will

    need to be reviewed. If a

    diagram does not exist, a

    decision will need to be

    made on creating a new

    diagram to share with

    HMEP.

    There is already a sub

    clause 4 in the SHW.

    There is no instruction to

    delete the existing sub

    clause, so the originating

    LHA needs to clarify this

    before it can be taken

    forward.

    Alternatively, if text does

    not relate to the SHW text,

    this sequence of sub

    clauses can be

  • 7/21/2019 120612 Standard Specification Stage2 Interim Report Appendices

    29/64

  • 7/21/2019 120612 Standard Specification Stage2 Interim Report Appendices

    30/64

    Appendix 3 Series 1100 - Footways and Paved Areas

    29STANDARDISED SPECIFICTION AND STANDARD DETAILS

    JUNE 2012

    Clause Reason for Variation Relevance

    1105AR Footways

    And Paved Areas

    (Flexible

    Surfacing)

    Add additional paragraph

    4. The permitted tolerance for the finished

    surface of footway binder course layers shallbe -6 mm to +0 mm. Sand asphalt and 6 mm

    nominal sized asphalt concrete surface

    course shall be laid 20 mm thick with a

    permitted tolerance of - 0 to + 6 mm.

    This sub clause is worth

    taking forward as it furtherspecifies relevant depths

    and tolerances that can be

    used by other LHAs.

    1105 Footways

    And Paved Areas

    (Flexible

    Surfacing)

    Insert Sub Clause 4

    4. The sealing of joints in surfacing or edges

    of repairs shall be by painting of the vertical

    face only (in accordance with Clause 901)

    and shall not include overbanding or surface

    applied sealing unless so directed by theProject Manager.

    This sub clause is worth

    taking forward in parallel

    to the above 1105AR. It

    may be necessary to

    renumber either of thesetwo sub clauses.

    Overbanding is a topic of

    contention across many

    LHAs.

    1106AR Footways

    And Paved Areas

    (In-Situ Concrete)

    Delete paragraph 3. This SHW sub clause

    needs to be reviewed. It

    may appear to be sensible

    for the majority of LHAs to

    take it forward. However,

    initial thoughts would be todismiss it.

    1107AR Footways

    And Paved Areas

    (Concrete Block

    Paving)

    Add additional paragraph

    4. Blocks shall be 200mm x 100mm x 80mm

    thick with a chamfer or radius not exceeding

    6mm. The wearing surface of each block

    shall not be less than 85 per cent of the total

    plan area of the block. The colour and

    pattern of block paving shall be to that

    specified by the Overseeing Organisation or,

    in the case of patching work, shall matchexisting.

    Sands for use in Laying Course (bedding

    sand) and for jointing in clay or concrete

    block pavements shall be naturally occurring

    silica sands. Sands from quaternary

    geological and sea dredged sands are

    preferred; sands from crushed rock sources

    shall not be used, except with the approval

    of the Overseeing Organisation.

    All sands used in block pavements shall be

    essentially free from deleterious salts or

    This sub clause is worth

    taking forward as it further

    clarifies details around

    using concrete blocks.

    This might help other

    LHAs that have not

    specified to this detail

    before.

  • 7/21/2019 120612 Standard Specification Stage2 Interim Report Appendices

    31/64

    Appendix 3 Series 1100 - Footways and Paved Areas

    30STANDARDISED SPECIFICTION AND STANDARD DETAILS

    JUNE 2012

    Clause Reason for Variation Relevance

    other contaminants.

    Unless otherwise agreed by the Overseeing

    Organisation, all laying course sand and allthe jointing sand delivered to any one site

    shall each be from a single source.

    The moisture content of laying course sand

    shall be consistent and within ""1% of

    optimum, as determined with BS1377 : Part

    4 : 1990 : method 3.3.

    The grading of the sands, as determined by

    the washing and sieving method of BS EN

    933-1:1997 (this replaces BS 812:Section

    103.1 but BS812:Section 103.1 remainscurrent) shall be within the limits given

    below:

    BS sieve size Cat I Cat II C III Jointing

    (BS 410) Sand

    10 mm 100 100 100

    5 mm 90-100 90-100 90-100

    2.36 mm 75-100 75-100 75-100 100

    1.18 mm - - - 95-100

    600 Fm 35-60 35-60 35-70 55-100

    300 Fm 8-35 8-35 8-35 15-50

    150 Fm 0-10 0-10 0-10 0-15

    75 Fm 0-0.1 0-1 0-3 0-3

    Category I sites are pavements subject to

    severely channelised traffic, docks,

    harbours, bus stations, loading bays, aircraft

    pavements, and the like.

    Category II sites include adopted highways,

    petrol station forecourts and pedestrian

    precincts, car parks and footways subject to

    some heavy vehicle loading.

    Category III sites are those subject to little or

    no heavy vehicular traffic, e.g. some

    pedestrian areas, car parks, private drives

    and footways.

    Blocks shall be laid on a screeded layer ofsand having grading within the limits set in

    the table above. Sand shall be laid to a

  • 7/21/2019 120612 Standard Specification Stage2 Interim Report Appendices

    32/64

    Appendix 3 Series 1100 - Footways and Paved Areas

    31STANDARDISED SPECIFICTION AND STANDARD DETAILS

    JUNE 2012

    Clause Reason for Variation Relevance

    compacted thickness of 50 mm. The blocks

    shall be laid close together, being brought to

    the laying face over the already laid work

    and the whole area vibrated using a handguided rubber-based vibrating plate. Dry

    silver or silica sand having a grading within

    the limits of the table above shall be brushed

    into the surface of the blocks and the area

    vibrated several times until the joints are

    completely filled with sand.

    1110AR Frost

    Susceptibility

    1. Subject to the tolerances given in Table

    7/1 and unless otherwise stated in Appendix

    7/1, material shall not be frost susceptible if

    it is used within 450mm of the designed finalsurface of a footway or paved area, or

    350mm if the mean annual frost index of the

    site is less than 50. Material shall be

    classified as non-frost susceptible if the

    mean heave is 15mm or less, when tested in

    accordance with BS 812: Part 124: 1989

    amended as given in Sub Clauses 801.7

    and 801.8.

    This sub clause is worth

    taking forward, though the

    text will need to be

    reviewed alongside theother Frost Susceptibility

    related clauses.

    References to Tables and

    Appendices are LHA

    specific, so the text may

    need to be modified

    accordingly.

    1111AR Footways

    And Paved Areas

    (Hard LandscapeAreas)

    1. Footways and paved areas in hard

    landscaped areas shall be constructed in

    accordance with the requirements inAppendix 11/01 and Appendix 11/70.

    Appendix 11 will be

    contract specific for a

    single LHA and might bedifficult to take forward

    without extracting the

    appropriate text from the

    Appendix.

    1112AR Dressed

    Natural Stone

    Kerbs, Channels,

    Quadrants And

    Setts

    1. Dressed natural stone kerbs, channels,

    quadrants and setts shall comply with BS

    EN 1342:2001 and also BS EN 1343:2001

    and be of the type of igneous rock, finish

    and size as described in Appendix 11/71.

    Kerbs, channels and quadrants shall be laid,bedded and backed in compliance with

    Clause 1101.1 and 1101.2. Unless

    otherwise described in Appendix 11/71, setts

    shall be laid, bedded and backed in class

    C16/20 or ST4 concrete in accordance with

    BS 8500-1:2006 and BS8500-2:2006. They

    shall be laid on either a Mix ST4 concrete

    foundation or on the base.

    2. For curves of radius 12m or less, kerbs

    and channels of appropriate radius shall be

    used.

    3. Individual kerbs, channels or quadrants

    Appendix 11 will be

    contract specific for a

    single LHA and might be

    difficult to take forward

    without extracting the

    appropriate text from theAppendix.

    Curves >12m are covered

    in another sub clause.

    Consider appending this

    text to that sub clause.

  • 7/21/2019 120612 Standard Specification Stage2 Interim Report Appendices

    33/64

    Appendix 3 Series 1100 - Footways and Paved Areas

    32STANDARDISED SPECIFICTION AND STANDARD DETAILS

    JUNE 2012

    Clause Reason for Variation Relevance

    shall not deviate by more than 3mm in 3m

    from line and level. Setts shall be laid to a

    flowing alignment.

    1113AR Clay Brick

    or Precast

    Concrete Block

    Kerbs, Channels

    and Edgings

    1. Clay bricks used for kerbs, channels and

    edgings shall comply with BS EN 771-1 :

    2003 and conform to the Class, size and

    type described in Appendix 11/72. Precast

    concrete blocks used for kerbs, channels

    and edgings shall comply with BSEN 1338

    and conform to the shapes, finish,

    dimensions and colours described in

    Appendix 11/72. They shall be laid and

    bedded on a mortar designation (i) in

    accordance with BS5628-3 Table 13 not lessthan 10mm and not more than 40mm thick,

    on Mix ST4 concrete foundation or on the

    base. Alternatively they may be laid and

    bedded directly on Mix ST4 concrete

    foundation whilst it is still plastic. Where

    described in Appendix 11/72 clay brick or

    precast concrete block kerbs, channels and

    edgings shall be backed with Mix ST4

    concrete.

    2. For curves of radius 12m or less, kerbs,

    channels and edgings shall be radially cuton both edges to the required line.

    3.. Units of kerb, channel or edging shall not

    deviate by more than 3mm in 3m from line

    and level.

    This sub clause is worth

    taking forward as it further

    details the requirements

    when laying clay bricks.

    Appendix 11 is specific to

    a single LHA. It may be

    necessary to extract the

    relevant text from the

    Appendix.

    Check with Clause 1108 to

    see if it is a natural AR or

    should remain separate.

    This sub clause is a repeat

    of one found in 1112ARabove.

    This sub clause is a repeat

    of one found in 1112AR

    above. (Note: This sub

    clause would need to be

    renumbered).

    1114AR Timber

    Edging

    1. Timber edging shall be constructed to the

    requirements of Drawing Number K157.

    Need to check if MHA

    have an equivalentdrawing. If not, there may

    be a case for a drawing to

    be created and then

    shared through HMEP.

    Timber edging is

    mentioned in a later

    clause, which will need to

    be reviewed in parallel and

    merged with this sub

    clause, if appropriate.

    1115AR Footways

    and Paved Areas

    1. Slurry surfacing to footways and paved

    areas shall be made and laid in compliance

    These sub clauses need

    to be reviewed in parallel

  • 7/21/2019 120612 Standard Specification Stage2 Interim Report Appendices

    34/64

    Appendix 3 Series 1100 - Footways and Paved Areas

    33STANDARDISED SPECIFICTION AND STANDARD DETAILS

    JUNE 2012

    Clause Reason for Variation Relevance

    (Slurry Surfacing) with Clause 918 and Appendix 11/73.

    2. The colour and any other factors affecting

    the design of the slurry surfacing are to be

    as stated in Appendix 11/73.

    to MHA (1170AR) and The

    Council (1170AR &

    1175AR) with a view to

    merging.

    Also, Appendix 11 is

    proprietary to the LHA.

    The appropriate text may

    need to be extracted to

    take this forward.

    1116AR Bus

    Shelters

    1. The Council preferred style of Bus

    Shelter installed throughout the County is

    the Arun Style manufactured by

    Queensbury, the Contractor shall note that

    new installations will be installed as part of

    the Maintenance Contract. If the contractor

    wishes to use other shelters from different

    manufacturers then they shall match in style

    and colour the already installed shelters

    throughout the Council.

    2. The maintenance of glazing to the existing

    shelters shall be undertaken by fully

    qualified personnel for the style of shelter

    throughout The Council glass sizes for

    replacement shall be 8mm thick and cleartoughened to BS 6206. The glass is retained

    horizontally with glass rails top and bottom,

    and vertically with a one piece u-channel

    extrusion. All fixings are allen key button

    head stainless steel screws, which are

    powder coated to match the framework.

    3. Panels within the Enclosed Shelter and

    Cantilevered Shelter have Glass with the

    Council Logo and the sizes of these are

    1393 x 1210 (enclosed) and 1393 x 916

    (cantilevered). For exploded view of

    Enclosed Shelter see Queensbury drawing

    SK1080.

    4. The contractor shall note that all

    personnel replacing glass and maintaining

    the existing shelters shall have the required

    Street Works registration card for working on

    the Highway.

    5. All new bus shelters shall be as stated in

    Appendix 11/74 and on the works order.

    Although this sub clause is

    specific to one LHA, it is

    worth taking forward to

    benefit others. LHAs

    would probably like to

    specify a particular style

    and a repair/maintenance

    regime for all bus shelters.

    The MHA drawing

    catalogue needs to be

    reviewed for a similar

    existing drawing. If no

    drawing exists it might beappropriate to produce

    one to be shared across

    HMEP.

    Appropriate training and

    qualifications are

    important. This sub clause

    should be taken forward.

    Appendix 11 will be

    contract specific to a

    particular LHA.

    Appropriate text might

    need to be extracted from

    the Appendix to take

    forward.

  • 7/21/2019 120612 Standard Specification Stage2 Interim Report Appendices

    35/64

    Appendix 3 Series 1100 - Footways and Paved Areas

    34STANDARDISED SPECIFICTION AND STANDARD DETAILS

    JUNE 2012

    Clause Reason for Variation Relevance

    1170AR Frost

    Susceptibility

    1. Material used within 450 mm of the

    designed final footway or paved area

    surface shall not be frost susceptible as

    defined in the test method and procedure ofthe Transport Research Laboratory

    Supplementary Report No SR 829.

    Review this clause against

    the other Frost

    Susceptibility clauses from

    other LHAs to see if thereis commonality and

    therefore define common

    text in an Additional

    clause.

    1170AR Natural

    Stone Kerbs, Kerb

    Setts, Channels,

    Channel Setts,

    Edging and Edging

    Setts

    1. Unless otherwise stated in Appendix

    11/70 Natural Stone Kerbs, Kerb Setts,

    Channels, Channel Setts, Edging and

    Edging Setts shall comply with BS EN 1341

    and the 1100 Series of the Specification for

    Highway Works.

    2. The types of Natural Stone Kerbs, Kerb

    Setts, Channels, Channel Setts, Edging and

    Edging Setts shall be as described in

    Appendix 11/70.

    Appendix 11 is proprietary

    to a single contract with a

    LHA. Extracting the

    appropriate text from the

    Appendix to be able to

    take these sub clausesforward.

    1170AR: Footway

    Retread

    1. Treat all emergent weeds, using

    Glyphosate, 7 to 14 days prior to the retread

    process and in accordance with

    manufacturers instructions. Rake out and

    remove all dead weeds, side back grass and

    clear back overhanging vegetationimmediately prior to the retread process.

    2. Areas of prior reconstruction (including

    domestic and wheelchair footway crossings)

    shall be constructed as shown in Drawing

    LC.07a but excluding the surface course.

    3. The position of all service covers shall be

    referenced by marks made on adjacent

    carriageway surfaces or by pegs or other

    similar means. Areas of closely adjacent

    ironwork or street furniture inaccessible to

    the retread process plant shall be defined for

    alternative treatment (see 13 below).

    4. Scarify existing footway (including partially

    reconstructed areas) using a mini cold

    planer or similar approved method to a

    depth of 6510mm. Manually rake over the

    material to remove any individual pieces of

    aggregate in excess of 50mm size.

    5. At the direction of the Project Manager

    any areas showing subgrade weakness shall

    be strengthened by temporary removal of

    the scarified layer, excavation of the existing

    These sub clauses are

    worth taking forward. This

    sub clause needs to be

    reviewed alongside that of

    The Council 1175AR and

    MHA 1170AR on SlurryResurfacing of Footways,

    with a view to either

    merging to a single AR or

    keeping separate.

    The MHA drawing

    catalogue needs to review

    to replace the LHA specific

    reference within this sub

    clause.

  • 7/21/2019 120612 Standard Specification Stage2 Interim Report Appendices

    36/64

    Appendix 3 Series 1100 - Footways and Paved Areas

    35STANDARDISED SPECIFICTION AND STANDARD DETAILS

    JUNE 2012

    Clause Reason for Variation Relevance

    sub-base and/or subgrade and replacement

    with Granular Type 2 sub-base. The

    removed scarified aggregate shall then be

    replaced.

    6. The scarified aggregate shall be shaped

    and graded to the specified level and

    crossfall allowing for the total specified depth

    of surface course. Excess material shall be

    removed, or relocated to positions requiring

    'make-up'. In areas of aggregate deficit,

    'make-up' shall be approved imported

    planings or Granular Type 2 sub-base which

    must be thoroughly mixed into existing

    scarified material.

    7. Compact the scarified layer using a twin

    drum vibrating roller to a tolerance of 6mm

    under a 3m straightedge and to achieve a

    Clegg Impact Soil Tester value greater than

    25.

    8. Protect all covers, kerbs, edges and

    private property by masking or other

    approved method.

    9. Apply K2-55 bitumen emulsion to thesurface at a uniform rate of 4.51.0 l/m.

    10. Apply grade 2.8/6.3 sized dry stone

    chippings (to BS EN 13043) to the surface at

    a rate of spread of 7.00.5kg/m.

    11. Lightly compact to effect full retention of

    the chippings.

    12. Adjust all service covers to finished

    levels (see Appendix 5/72).

    13. Inaccessible areas (see 3 above) shall

    be broken out and replaced with a fully

    compacted 40mm course of 20mm nominal

    size open textured binder course.

    14. The retreaded surface should remain

    exposed for at least 24 hours and shall not

    be surfaced over prior to approval by the

    Project Manager.

    15. Prior to laying the surface course apply

    K1-40 bituminous emulsion tack coat at arate of 0.50.1l/m.

    16. Apply asphalt concrete regulating course

  • 7/21/2019 120612 Standard Specification Stage2 Interim Report Appendices

    37/64

    Appendix 3 Series 1100 - Footways and Paved Areas

    36STANDARDISED SPECIFICTION AND STANDARD DETAILS

    JUNE 2012

    Clause Reason for Variation Relevance

    as directed.

    17. Apply tack coat and 20mm depth of

    0/6mm size close graded surface course(BS 4987-1 Clause 7.5 made with 160/220

    pen bitumen). The surface course must be

    laid within 3 weeks of the retread process on

    any site.

    18. All excess excavated material must be

    removed from site daily unless it is likely to

    be required as 'make-up' elsewhere, in

    which case it shall be secured from

    interference.

    1170 AR Footway

    Slurry Surfacing

    Unless specified otherwise in the Package

    Order the following shall apply:

    SPECIFICATION

    1. GENERAL DESCRIPTION

    1.1 This Specification deals with the

    provision and laying of slurry surfacing

    materials (6.0mm nominal layer thickness

    and over) on footway and other areas notsubject to regular traffic other than private

    vehicular access.

    2. DESCRIPTION OF WORKS

    2.1 The following processes are to be

    included and quantities recorded for items

    (c) and (j).

    (a) Preparatory sweeping and pressure jet

    washing;

    (b) Weedkilling and weed treatment;

    (c) Preliminary regulating of surfaces;

    (d) Protection and masking of ironwork and

    street furniture;

    (e) Applying surfacing including any tack

    coat if required by the process;

    (f) Rolling of surfaces if required by the

    process;

    (g) Protection of newly treated surface;

    These sub clauses are

    worth taking forward and

    combined with those from

    The Council (1115AR) &

    The Council (1170AR &

    1175AR) on Footway

    Retread/Slurry sealing.

  • 7/21/2019 120612 Standard Specification Stage2 Interim Report Appendices

    38/64

    Appendix 3 Series 1100 - Footways and Paved Areas

    37STANDARDISED SPECIFICTION AND STANDARD DETAILS

    JUNE 2012

    Clause Reason for Variation Relevance

    (h) Sweeping of loose materials;

    (i) Provision of signs for carrying out traffic

    control, and informing frontagers;

    (j) Resetting of Ironwork.

    3. TYPE OF BINDER

    3.1 Materials manufactured with bitumen

    emulsion or modified bitumen emulsions

    complying with the appropriate British

    Standards where they exist.

    4. PERIOD OF WORK

    4.1 It is should be judged if weather

    conditions and other circumstances are

    suitable before carrying out the work.

    5. PREPARATORY SWEEPING AND

    CLEANING

    5.1 All vegetation within the surface to be

    covered shall be treated with an approved

    herbicide not less than 14 days before the

    application of the surfacing.

    5.2 Immediately before application of the

    surfacing all loose material from the surface

    to be covered shall be removed (this is to be

    accomplished by high pressure jet washing)

    and any remaining vegetation still growing

    moved, with any remaining root growth

    treated with 2,4D.

    Note: the application of 2,4D shall be made

    after high pressure jet washing has taken

    place.

    5.3 The removal of any foreign matter

    affecting the surface which is likely to prove

    detrimental to the finished product is also

    deemed to be included as part of the

    preparatory cleaning e.g. oils spillage or any

    substance likely to de-bond the layer to be

    applied.

    6. PROTECTION OF STREET FURNITURE

    6.1 The full width and length of the area to

    be treated shall be covered withoutoverlapping kerbs, channels and edgings for

  • 7/21/2019 120612 Standard Specification Stage2 Interim Report Appendices

    39/64

    Appendix 3 Series 1100 - Footways and Paved Areas

    38STANDARDISED SPECIFICTION AND STANDARD DETAILS

    JUNE 2012

    Clause Reason for Variation Relevance

    footways.

    6.2 The material shall not be allowed to

    overlap on to boundary walls fences or anyother structure adjoining the highway nor

    any street furniture actually situated within

    the areas to be treated. All ironwork such as

    manhole covers, hydrants, gullies, catchpit

    covers, stop valves or similar shall be

    masked to give complete protection during

    the operation. Oils, and/or sand or similar

    materials shall not be used.

    7. RESETTING COVERS AND FRAMES

    7.1 Where practicable, gullies and manholecovers and frames, stop valves and all other

    covers shall be set to new levels before the

    final surfacing is laid.

    7.2 When covers etc., are set to new levels

    after the surfacing is laid, the reinstatement

    of the area around the covers etc., shall be

    carried out in the same type of material as

    that used for the new surfacing. Covers shall

    be set to the new levels within two weeks of

    the completion of the surface.

    7.3 Manholes etc., shall be reset flush (+

    3mm) with, and the gullies 6mm (+ 3mm)

    below, the level of the new surface.

    8. JOINTS

    8.1 Longitudinal joints shall be feather

    lapped such that the joints do not exceed the

    nominal layer thickness, longitudinally or

    laterally. Joints with adjacent surfaces shall

    be feathered to neat regular shapesappropriate to the layout, and protective

    mats or paper should be used to achieve

    same. Wherever possible longitudinal joints

    between final applications shall coincide with

    lane lines. In every case, surfacing of the

    highest part of the substrate due to crossfall

    or camber will always be treated last thereby

    ensuring that the upper layer of the feather

    lap at joints will be so formed to shed water

    towards the lower section of surface.

  • 7/21/2019 120612 Standard Specification Stage2 Interim Report Appendices

    40/64

    Appendix 3 Series 1100 - Footways and Paved Areas

    39STANDARDISED SPECIFICTION AND STANDARD DETAILS

    JUNE 2012

    Clause Reason for Variation Relevance

    9. AGGREGATES

    9.1 The final surface shall consist of

    exposed rock aggregate with a minimum psvof 45.

    10. MIXING AND LAYING

    10.1 The material shall be properly

    proportioned and shall be mixed by a

    machine which shall be able to supply

    sufficient material to achieve the nominal

    layer thickness and surface regularity

    required.

    10.2 The surfacing mixtures shall be spreaduniformly by means of mechanical spreader

    or by hand.

    10.3 All material discharged from the mixer

    shall be used without further addition.

    10.5 Where more than one layer is

    necessary each successive layer shall be

    completed where possible within three days

    of completion of the previous layer. Where

    other than full machine width passes are

    necessary these shall not form the final partof the surfacing.

    10.6 It is recognised that in some areas

    laying by mechanical means may not be

    possible.

    10.7 All equipment shall be limited to

    weights which will not cause damage to

    substrates.

    11. FINISHED SURFACE

    11.1 The finished surfacing shall be of

    uniform surface texture and appearance

    throughout the work, without variations

    across the width of the paved area.

    11.2 The finished surfacing shall be free

    from droppings, excess overlapping or badly

    aligned longitudinal or transverse joints,

    damage by rain or frost, or other defects.

    Any surfacing which does not comply with

    this Clause, or is non-uniform in surface

    texture or appearance within 30 days of

    laying shall be made good by removal and

  • 7/21/2019 120612 Standard Specification Stage2 Interim Report Appendices

    41/64

    Appendix 3 Series 1100 - Footways and Paved Areas

    40STANDARDISED SPECIFICTION AND STANDARD DETAILS

    JUNE 2012

    Clause Reason for Variation Relevance

    replacement of fresh material.

    11.3 If fresh material is superimposed any

    area so treated shall be not less than 5mlong and the full width of the machine. The

    completed repair shall meet the overall

    requirements of this Specification and shall

    match the original material. In areas of

    restricted access hand work may be

    necessary but it is essential that a finish is

    achieved compatible with that of the

    mechanically laid material.

    12. PERFORMANCE STANDARDS

    12.1 Surface Regularity

    No irregularity greater than 8mm under a 1m

    straight edge shall be measured at any

    location unless such a profile is required to

    accommodate features such as dropped

    kerbs, cambers and changing gradients.

    12.2 Slip Resistance

    The finished surface shall provide an

    average slip resistance of at least 0.35 Grip

    Number when measured in push mode overany 10m length with a Grip Tester currently

    manufactured by Findlay, Irvine Ltd.,

    Penicuik, Midlothian.

    12.3 Abrasion Loss

    If the effects of normal traffic and/or

    weathering cause abrasion of the slurry

    surfacing so as to completely reveal the

    underlying original footway surface, this

    condition is defined as Total Abrasion Loss.

    Remedial works shall be carried out to any

    single area of total abrasion loss when it

    exceeds 1.0m2.

    12.4 Penetration Resistance

    The slurry surfacing shall, at all natural

    ambient temperatures, be capable of

    supporting pedestrians wearing narrow

    heeled shoes without undue penetration of

    the surface. Objective assessment of any

    such defects shall be carried out as follows:the method of road surface hardness

    measurement published in Appendix C of

  • 7/21/2019 120612 Standard Specification Stage2 Interim Report Appendices

    42/64

    Appendix 3 Series 1100 - Footways and Paved Areas

    41STANDARDISED SPECIFICTION AND STANDARD DETAILS

    JUNE 2012

    Clause Reason for Variation Relevance

    TRL Road Note 39 Design Guide for Road

    Surface Dressing (1992) shall be used with

    the following modifications. The standard

    4mm diameter tip shall be converted to a15mm diameter flat-ended tip using a

    suitable converter, as available from the

    probe manufacturers, SME Machine Tools

    Ltd, Chapel Works, Sheffield Road,

    Sheepbridge, Chesterfield, Derbyshire.

    Measurements shall be made at a surface

    temperature of 30C +2 without the use of

    correction factors or graphs. Slurry

    surfacing shall be regarded as unacceptably

    soft if the main probe penetration exceeds

    10mm.

    13. PROTECTION OF NEWLY LAID

    SURFACE

    13.1 Traffic and pedestrians shall be kept off

    newly treated surfaces until material has set

    and will suffer to detrimental effect.

    14. NOTICE TO CARRY OUT WORK

    14.1 Clear and legible notices are to be

    posted in the road where work is to becarried out giving at least 24 hours notice of

    working being carried out.

    14.2 The owners/occupiers of all properties

    fronting the footway to be surfaced shall be

    notified 24 hours before works are due to

    commence, by means of the 3 CAP

    Highways information leaflet.

    15. TRAFFIC SAFETY MEASURES AND

    CONTROL

    15.1 Traffic control shall be in accordance

    with the Code of Practice for Signing at

    Surface Dressing Sites (produced jointly by

    CSS and RSDA -CCS/RSDA /Eng/3/2000)

    and such other special requirements as

    described in the contract.

    Reference to a particular

    Grip Tester should be

    changed to one that

    complies with a particularBS or BSEN, or check

    HAPAS or other

    accreditation status of it

    and make relevant

    reference.

    Reference to SME

    Machine Tools should be

    removed/revised.

    1171AR Footways

    And Paved Areas

    (Stone Flags)

    1. Natural Yorkstone Flags vary in thickness

    and so shall be individually fully bedded on

    mortar. Joints shall be no greater than 20

    mm and shall be completely buttered, filled

    and pointed with sand/cement mortar 3:1.

    Where overriding of the footways occurs or

    where specified by the Overseeing

    It is worth taking this sub

    clause forward as it might

    apply to other LHAs

    specifying the use of

    specific surfacing.

    Reference to Instarmac

    should be replaced with

  • 7/21/2019 120612 Standard Specification Stage2 Interim Report Appendices

    43/64

    Appendix 3 Series 1100 - Footways and Paved Areas

    42STANDARDISED SPECIFICTION AND STANDARD DETAILS

    JUNE 2012

    Clause Reason for Variation Relevance

    Organisation flags shall be laid on 100 mm

    grade ST1 concrete and levelled using a

    rubber maul.

    Alternatively proprietary mortar may be

    instructed (Instarmac or similar approved).

    2. Second hand Yorkstone flags may be

    provided by the Overseeing Organisation.

    3. On occasion the Employer may request

    that circular work where the radius is 12 m

    or less all flags shall be radially cut on both

    edges.

    reference to HAPAS

    approved materials.

    Reuse of materials is

    worth taking forward.

    This sub clause should be

    merged with the previous

    sub clauses related to

    curves > 12m.

    1171AR: FootwayAnd Paved Areas

    (Gravel Footpaths

    & Timber Edgings)

    1. Self-setting gravel surfacing shall beBreedon Golden Amber Gravel as supplied

    by Messrs. Breedon and Cloud Lime Works

    Ltd., or a similar approved material. The

    gravel shall be evenly spread and

    compacted by 8 passes of a 700-1300 kg

    per metre width, pedestrian controlled dead

    weight roller and have a finished thickness

    of 50mm. Further compaction shall be

    carried out applying water to the rollers, until

    a well-bonded surface finish is obtained to

    the satisfaction of the Project Manager. Anyareas where segregation occurs shall be

    blinded with fine material and re-rolled. The

    surface shall be allowed to dry before being

    trafficked.

    2. Timber edging and supporting stakes

    shall be band sawn, knot free softwood

    which shall be certified to have been

    pressure creosoted with a net retention of

    creosote in the timber of not less than 160kg

    per cubic metre. Edgings shall either be

    fixed and supported by wood stakes or laidand bedded in concrete class ST3 as shown

    on the Drawings.

    It is worth taking these subclauses forward, though

    they may need to be split

    into a Gravel AR and a

    Timber Edging AR, with

    the latter merged with

    1114AR above. Remove /

    amend (as appropriate)

    reference to specific

    supplier.

    Timber edging is already

    part of a previous sub

    clause. The sub clauses

    need to be combined.

    1171 AR Footway

    And Paved Areas

    (Flexible

    Surfacing)

    Unless specified otherwise in the Package

    Order the following shall apply:

    General

    1. Flexible surfacings shall be laid to levels

    and crossfalls as agreed with the

    Overseeing Organisation and materials shall

    be laid in accordance with the appropriate

    Clauses in the 700, 800, 900 and 1100

    This sub clause has the

    same title as 1105.

    These sub clauses need

    to be reviewed against

    1105 and 1105AR to

    either create an AR to

    clause 1105 or keep

    separate with an

  • 7/21/2019 120612 Standard Specification Stage2 Interim Report Appendices

    44/64

    Appendix 3 Series 1100 - Footways and Paved Areas

    43STANDARDISED SPECIFICTION AND STANDARD DETAILS

    JUNE 2012

    Clause Reason for Variation Relevance

    Series and comply with the following:-

    Sub-base

    2. Granular sub-base material in footways

    and paved areas shall be Type 1 granular

    material and comply with the requirements

    of Clause 803 or Class 6F3 granular fill

    (planings, etc) to comply with the

    requirements in Table 6/1. In situ concrete

    sub-base material in footways and paved

    areas shall be Mix ST1 concrete and comply

    with the requirements of Clause 2602. Sub-

    base material shall be laid to the thickness

    as described in the Contract.

    Asphalt Concrete Binder Course

    3. Binder course shall be 20mm maximum

    size aggregate dense binder course

    complying with the requirements of BS EN

    13108-1 with paving grade bitumen, grade

    160/220, laid to the thickness as described

    in the Contract.

    Asphalt Concrete Surface Course

    4. Surface course shall be 6mm maximumsize aggregate dense surface course

    complying with the requirements of BS EN

    13108-1 with paving grade bitumen, grade

    160/220, laid to the thickness as described

    in the Contract.

    Hot Rolled Asphalt Surface Course

    5. Surface course shall be 14mm maximum

    size aggregate hot rolled asphalt surface

    course complying with the requirements of

    BS EN 13108-4 with paving grade bitumen,

    grade 40/60, type F mixture, designation

    55/14F, laid to the thickness as described in

    the contract.

    Sand Asphalt Surface Course

    6. Surface course shall be 2mm maximum

    size aggregate hot rolled asphalt surface

    course complying with the requirements of

    BS EN 13108-4 with paving grade bitumen,

    grade 40/60, type F mixture, designationO/2F, laid to the thickness as described in

    the Contract.

    amendment to the title.

    Tables would need to be

    extracted and included in

    the sub clause.

  • 7/21/2019 120612 Standard Specification Stage2 Interim Report Appendices

    45/64

    Appendix 3 Series 1100 - Footways and Paved Areas

    44STANDARDISED SPECIFICTION AND STANDARD DETAILS

    JUNE 2012

    Clause Reason for Variation Relevance

    Regulating Course

    7. Regulating course material shall be made

    and laid in accordance with the requirementsfor one or other of the surface course or

    binder course materials as described in the

    Contract.

    Limestone and Basalt Aggregate in Surface

    Course

    8. The use of limestone and basalt

    aggregate in the surface course will not be

    permitted.

    1172AR FootwaysAnd Paved Areas

    (Stone Setts)

    1. Stone setts shall be set with lengths atright angles to the street and well rammed

    as they are laid. They shall be laid in

    regular, straight and properly bonded

    courses from side to side with close joints

    (12 to 15 mm) which must be kept perfectly

    clear to receive the bitumen and cement

    grouts. The joints shall be racked with

    clean, dry, single sized 10 mm gritstone

    chippings and grouted with hot bitumen (50

    pen) to within 25 mm of the top of the joints.

    The remainder of the depth shall be filledwith 3:1 sand/cement mortar and flush

    pointed.

    2. Second hand stone setts may be provided

    by the Overseeing Organisation. Second

    hand stone setts shall be sorted by the

    Contractor to comply with the bonding

    requirements in 1 above.

    3. Where stone setts are to be laid in hard

    margins, the chippings and hot bitumen

    grout shall be replaced with semi-dry 3:1sand/cement mortar.

    4. Second hand stone setts can be of either

    Yorkstone or granite and shall be laid to a

    pattern specified by the Overseeing

    Organisation. The pattern of work adjacent

    to gullies chambers and other obstructions

    shall be agreed with the Overseeing

    Organisatio