Upload
max
View
218
Download
0
Embed Size (px)
Citation preview
7/21/2019 120612 Standard Specification Stage2 Interim Report Appendices
1/64
Standardised Specification
and Standard Details
Stage 2 Report
Progress Report on Local Authority SpecificationVariations
Appendices to the Report
June 2012
7/21/2019 120612 Standard Specification Stage2 Interim Report Appendices
2/64
Images on cover sheet courtesy of HMEP
Images in main report courtesy of Midlands Highway Alliance
1STANDARDISED SPECIFICTION AND STANDARD DETAILS
JUNE 2012
7/21/2019 120612 Standard Specification Stage2 Interim Report Appendices
3/64
REVISION SCHEDULE
Standard Specification and Standard Details
Stage 2 Progress Report
Rev Date Details Prepared by Reviewed by Approved by
01 13/04/12 Draft Ed Varley
Principal Engineer
John Cole
Principal
Engineer
Anna Moore
Associate
02 07/06/12 Issue 1 Ed Varley
Principal Engineer
John Cole
Principal
Engineer
Anna Moore
Associate
2STANDARDISED SPECIFICTION AND STANDARD DETAILS
JUNE 2012
7/21/2019 120612 Standard Specification Stage2 Interim Report Appendices
4/64
Contents
CONTENTS
COMMENT AND FEEDBACK 4
APPENDICES 5
Appendix 1 Series 500 Drainage andService Ducts 6
Appendix 2 Series 700/900 RoadPavements - Bituminous Bound Materials 20
Appendix 3 Series 1100 Footways andPaved Areas 26
Appendix 4 Series 1200 Road Markingsand Road Studs 50
Appendix 5 Series 1300 Street LightingColumns and Brackets 52
Appendix 6 Series 1700 StructuralConcrete 53
Appendix 7 Series 1800 - StructuralSteelwork 55
Appendix 8 Winter Maintenance Materials56
ABBREVIATIONS USED 62
LIMITATIONS 63
3STANDARDISED SPECIFICTION AND STANDARD DETAILS
JUNE 2012
7/21/2019 120612 Standard Specification Stage2 Interim Report Appendices
5/64
Foreword
COMMENT AND FEEDBACK
The HMEP Programme Board would welcome any comments and feedback onthis report so that the final product may be reviewed, improved and refined to
give the sector the best advice possible. If you wish to make a comment,please email them to [email protected] the headerFeedback on the Standard Specification and Standard Details.
4STANDARDISED SPECIFICTION AND STANDARD DETAILS
JUNE 2012
mailto:[email protected]:[email protected]7/21/2019 120612 Standard Specification Stage2 Interim Report Appendices
6/64
Appendices
APPENDICES
5STANDARDISED SPECIFICTION AND STANDARD DETAILS
JUNE 2012
7/21/2019 120612 Standard Specification Stage2 Interim Report Appendices
7/64
Appendix 1 Series 500 Drainage and Service Ducts
Appendix 1 Series 500 Drainage and Service Ducts
Summary of information provided by local highways authorities as part of the HMEP
survey carried out in October 2011.
SR Series Supplementary Addi tional Clauses
The following table summarises where authorities have varied drainage clauses
together with a commentary on their relevance to the Specification.
Addi tional Clauses Additions/Changes Comment
Resetting of Covers
and Frames;
Defines further/specific
requirements for the re-setting
of footway, and carriagewayironwork;
The resetting of covers and
frames is considered to be an
aspect that requires furtherreview and possible update
to the current SHW.
Defines specific requirements
for the resetting of British
Telecom carriageway ironwork
using resin bedding and resin
mortar;
Defines specific requirements
for resetting of British Telecom
ironwork in footways;
Defines specific requirements
for the re-setting Fire Hydrants
in footways and carriageway.
Special Treatment
of Existing Sewers,
Drains, Ducts,
Services and the
like.
Provides additional general
requirements in connection with
existing sewers, drains, ducts
and services.
Current SHW considered to
be acceptable and therefore
unnecessary to include.
Works on Existing
Drains Sewers and
Manholes;
Provides general requirements
with regard to taking measures
when working on existing drains
to prevent debris from entering
the system.
Also introduces specific
requirement to prove by CCTV
survey downstream runs ofexisting drainage and make
good where necessary where
Current SHW considered to
be acceptable and therefore
unnecessary to include.
6STANDARDISED SPECIFICTION AND STANDARD DETAILS
JUNE 2012
7/21/2019 120612 Standard Specification Stage2 Interim Report Appendices
8/64
Appendix 1 Series 500 Drainage and Service Ducts
7STANDARDISED SPECIFICTION AND STANDARD DETAILS
JUNE 2012
Addi tional Clauses Additions/Changes Comment
new connections are made into
the system.
Gully Set in Verge; Provides general requirementsfor the construction of new
gullies set in verge and
treatment to
replaced/abandoned gullies.
Considered to be specific toThe Council and therefore
inappropriate to include
within the current SHW.
Small Headwall; Provides general requirements
for the construction of small
headwalls using either concrete
block and in-situ concrete or
concrete bag construction.
Considered to be specific to
The Council and therefore
inappropriate to include
within the current SHW.
Reinstatement of
Drainage and
Service Ducts in the
Carriageway,
Footway and Verge
(Trench
Reinstatement);
Provides general requirements
for trench reinstatement in both
carriageways and verges.
Current SHW considered to
be acceptable and therefore
unnecessary to include.
Disconnect and Fill
Existing Manhole,Catchpit or Gully.
Provides general requirements
for the removal and backfilling ofredundant chambers and
gullies.
Current SHW considered to
be acceptable and thereforeunnecessary to include.
Existing Drainage; Provides general requirements
for the renewal of filter drains
and drain runs
Current SHW considered to
be acceptable and therefore
unnecessary to include.
Deep Bored
Soakaways;
Provides specific requirements
for the construction of deep
bored soakaways.
Considered to be specific to
Kent CC and therefore
inappropriate to include
within the current SHW.
Adjustment of
Ironwork.
Reconfirms that the
replacement/adjustment of
existing frames, covers and
gratings shall be carried out in
accordance with the SHW.
As per current SHW
therefore considered
unnecessary to include.
Pipes for Drainage
and for Service
Ducts;
Requires Sulphate Resisting
Portland cement to be used and
all standard mixes of concrete
used in drainage works to be the
GEN series and not ST
Considered to be specific to
Council and therefore
inappropriate to include
within the current SHW.
7/21/2019 120612 Standard Specification Stage2 Interim Report Appendices
9/64
Appendix 1 Series 500 Drainage and Service Ducts
8STANDARDISED SPECIFICTION AND STANDARD DETAILS
JUNE 2012
Addi tional Clauses Additions/Changes Comment
references.
Excavations for
Pipes andChambers;
Modifies trench widths and
provides additional generalrequirements for the
construction of drainage runs.
Considered to be specific to
Council and thereforeinappropriate to include
within the current SHW.
Bedding, Laying
and Surrounding of
Pipes (Including
Cable Ducts);
Reconfirms requirements of the
SHW in respect of laying new
drainage pipes.
Reclassifies required pipe
bedding requirements.
Provides requirements for whennew drains are laid below
groundwater level.
Considered to be specific to
Council and therefore
inappropriate to include
within the current SHW.
Jointing of Pipes; Provides general requirements
for jointing of pipes.
Current SHW considered to
be acceptable and therefore
unnecessary to include.
Backfilling of
Trenches and Filter
Drains;
Requires the use of sub-base
material Type 2 to be used in
backfilling of trenches.
Considered to be specific to
Council and therefore
inappropriate to include
within the current SHW.
Connecting to
Existing Drains;
Chambers and
Channels;
Provides additional
requirements in respect of
entering/breaking into existing
drains, sewers or chambers.
Current SHW considered to
be acceptable and therefore
unnecessary to include.
Chambers; Required GEN series concrete
mixes to be used in the
construction of chambers.
Provided additionalrequirements in connection with
the construction of chambers.
Considered to be specific to
Council and therefore
inappropriate to include
within the current SHW.
Gullies and Pipe
Junctions.
Requires the use of sub-base
material Type 2 to be used in
backfilling of gullies.
Considered to be specific to
Council and therefore
inappropriate to include
within the current SHW.
Low Pressure High
Volume Jetting of
Drainage Systems;
Provides specific requirements
for the jetting of piped drainage
systems.
This additional clause
replicates what is already
included within the SHW
under Clause 521.
7/21/2019 120612 Standard Specification Stage2 Interim Report Appendices
10/64
Appendix 1 Series 500 Drainage and Service Ducts
9STANDARDISED SPECIFICTION AND STANDARD DETAILS
JUNE 2012
Addi tional Clauses Additions/Changes Comment
Existing Drain
Cleansing;
Provides specific requirements
for cleaning/clearing existing
gullies and chambers
Considered to be specific to
Council and relates to
maintenance requirements,
therefore inappropriate to
include within the current
SHW.
Replacing, Raising
or Lowering Covers,
Gratings and
Frames on Existing
Chambers and
Gullies.
Provides general requirements
for replacing, raising or lowering
frames, covers and gratings on
existing chambers.
The resetting of covers and
frames is considered to be an
aspect that requires further
review and possible update
to the current SHW.
Closed Circuit TV
Inspection of Drains
and Sewers;
Provides specific requirements
for undertaking CCTV inspection
of drains and sewers.
The requirements for carrying
out CCTV inspections are
covered by the current SHW
under Volume 5, Special
Activities, Section 9, Model
Contract Documents For
CCTV Survey of Highway
Drainage Systems.
Oil Interceptor
Units.
Provides general requirements
for Oil interceptors.
The design and specification
of Oil Interceptors isconsidered to be contract
specific and will generally be
design by the contractor. It is
therefore considered
inappropriate to include any
specific requirements with
regard to Oil Interceptors
within the SHW.
Replacement ofFilter Material in
Existing Filter
Drains;
Provides general requirementsfor replacement of filter material
in existing drains.
Considered to be a contractspecific requirement and
therefore unnecessary to
include in the general SHW.
Drainage Grips. Provides general requirements
for the construction of drainage
grips.
Considered to be outside the
scope of the HMEP project
brief.
7/21/2019 120612 Standard Specification Stage2 Interim Report Appendices
11/64
Appendix 1 Series 500 Drainage and Service Ducts
AR Series -Amended Clauses
The following table summarises the various amended clauses received together with a
commentary on their relevance to the Specification.
Heading AmendedClause
Additions/ Changes Comment
Pipes for
Drainage
and Service
Ducts
501.8 Removes current
specification requirements
for draw rope through
ducts.
Considered unnecessary to
remove current SHW
requirements.
Chambers 507.18 Minor addition to current
specification.
Considered unnecessary to
incorporate in current SHW.
CombinedDrainage
and Kerb
Systems
516.1 Requires that anycombined drainage and
kerb system shall be the
Beany Block system as
supplied by Marshalls.
Considered inappropriate tospecify a specific type of
system therefore should not be
included in the SHW.
Chambers 507.16 Cross references to
Appendix 5/1 for further
specific requirements for
bedding mortars and
proprietary quick setting
mortars.
Linked to resetting of frames,
covers and gullies. Further
review required to establish
whether current SHW should
be updated in respect of this
issue.
507.19 Provides additional minor
requirements for the
construction/resetting of
chamber covers.
Considered unnecessary to
incorporate in current SHW.
Chambers 507.1 Removes reference to
motorway communications
installations and introduces
interceptors as beingdefined as chambers.
Considered appropriate to
remove any reference to
motorways as these will not
be encountered by localauthorities.
507.3 Requires that brickwork to
chambers should be one
brick thick.
Considered unnecessary to
include this. Sufficient detail is
provided in the standard
details with regard to the
construction of chambers.
Gullies andPipe 508.1 Removes reference tosumpless gullies as an Considered inappropriate toexclude sumpless gullies as an
10STANDARDISED SPECIFICTION AND STANDARD DETAILS
JUNE 2012
7/21/2019 120612 Standard Specification Stage2 Interim Report Appendices
12/64
Appendix 1 Series 500 Drainage and Service Ducts
11STANDARDISED SPECIFICTION AND STANDARD DETAILS
JUNE 2012
Heading Amended
Clause
Additions/ Changes Comment
Junctions allowable gully option. acceptable option.
508.6 Requires that only ST2concrete shall be used as
backfill to gullies.
Considered inappropriate toadopt the use of ST2 concrete
as backfill to gullies throughout
the sector.
Combined
Drainage
and Kerb
Systems
516.1 Cross references to
Appendix 5/5 for details of
combined drainage
systems.
Current SHW considered
appropriate therefore
unnecessary to include
modification.
Linear
Drainage
Channel
Systems
517.1 Cross references to
Appendix 5/6 for details of
combined drainage
systems and removes
reference to Appendix
1/11.
Current SHW considered
appropriate therefore
unnecessary to include
modification.
The
Cleaning of
Existing
Drainage
Systems
520.1 Introduces alternative
requirements and time
frame for the contractor to
carry out cleaning of
existing drainage systems.
Current SHW considered
appropriate therefore
unnecessary to include
modification.
Bedding,
Laying and
Surrounding
of Pipes
503.3 Introduces minor
amendment to current
specification.
Current SHW considered
appropriate therefore
unnecessary to include
modification.
Chambers 507.16 Introduces additional
requirement for the setting
of frames, covers and
gratings which is already
included in Clause 507.18.
Current SHW considered
appropriate therefore
unnecessary to include
modification.
Gullies and
Pipe
Junctions
508.4 Introduces
alternative/additional
requirements in respect of
gullies.
Linked to resetting of frames,
covers and gullies. Further
review required to establish
whether current SHW should
be updated in respect of this
issue.
Permeable
Backing to
Earth
Retaining
513.1 Introduces
alternative/additional
requirements in respect of
porous concrete blocks
used in back of wall
Current SHW considered
appropriate therefore
unnecessary to include
modification.
7/21/2019 120612 Standard Specification Stage2 Interim Report Appendices
13/64
Appendix 1 Series 500 Drainage and Service Ducts
12STANDARDISED SPECIFICTION AND STANDARD DETAILS
JUNE 2012
Heading Amended
Clause
Additions/ Changes Comment
Structures drainage.
Connectingto Existing
Drains
Chambers
and
Channels
506.2 Minor addition to currentspecification.
Considered unnecessary toincorporate in current SHW.
506.3 Cross references to
Appendix 5/1 for details on
disconnection of existing
drains.
Current SHW considered
appropriate therefore
unnecessary to include
modification.
Gullies and
Pipe
Junctions
508.1 Cross references to
Appendix 5/1 for inclusion
of alternative drawings for
gully construction.
Current SHW considered
appropriate therefore
unnecessary to include
modification.
Backfilling
of Trenches
and Filter
Drains
505.10 New sub-clause cross
referencing to Appendix
5/1 to introduce need for
geotextile filter around filter
drains and filter material.
The adoption of geotextile
lining to filter drains is
considered to be contract
specific. The current
specification/ design for filterdrains included in the SHW is
considered appropriate.
505.11 New sub-clause detailing
specific requirements for
the storage of geotextiles
used in filter drains.
505.12 New sub-clause detailing
specific requirements for
geotextiles used in andconstruction of filter drains.
505.13 New sub-clause detailing
specific requirements for
the handling of geotextiles
used in filter drains.
505.14 New sub-clause
introducing minor addition
with regard to information
to be supplied in respect of
geotextiles used in filter
7/21/2019 120612 Standard Specification Stage2 Interim Report Appendices
14/64
Appendix 1 Series 500 Drainage and Service Ducts
13STANDARDISED SPECIFICTION AND STANDARD DETAILS
JUNE 2012
Heading Amended
Clause
Additions/ Changes Comment
drains.
505.15 New sub-clauseintroducing minor addition
with regard to certification
in respect of geotextiles
used in filter drains.
7/21/2019 120612 Standard Specification Stage2 Interim Report Appendices
15/64
Appendix 1 Series 500 Drainage and Service Ducts
Summary of Standard Detail Drawings Review- Survey Responses
14STANDARDISED SPECIFICTION AND STANDARD DETAILS
JUNE 2012
7/21/2019 120612 Standard Specification Stage2 Interim Report Appendices
16/64
Appendix 1 Series 500 Drainage and Service Ducts
The following table provides a summary of the questions and responses to the survey
questionnaire along with initial comment on their relevance to the Specification.
Question Survey Response Comment
Does therange of
specified
material types
(e.g. pipe
types) match
what is readily
available?
Yes = 89.5%,
No = 10.5%
The results of the survey clearly concludethat the current range of specified
materials within/included in the MCHW
SHW is acceptable.
Do you use
pipe types not
specified in the
MCHW?
Yes = 15.55%,
No = 84.4%
Linked to Qu 16 the results of the survey
further conclude that the current range of
specified materials within/included in the
MCHW SHW is acceptable.
Is the range of
specified
drainage
systems
appropriate?
[Note the HA
plans topublish a new
Part listing all
sustainable
drainage
systems, to
reflect the
forthcoming
national
standards for
sustainable
drainage.]
Yes = 67.9%,
No = 32.1%
The direct results to this question are less
conclusive than for previous questions,
however, review of the comments
provided by consultees would suggest
that this is directly due to the lack of detail
included in the current Specification on
Sustainable Drainage Systems (SUDS).
As identified in the question the HA plans
to publish a new part to the Specification
listing all sustainable drainage systems, to
reflect the forthcoming national standards
for sustainable drainage.
It is considered that inclusion of a
specification for SUDS is outside the
scope of the current commission. It is not
possible to pre-empt the outcome of the
Highways Agencys ongoing work on this
aspect. It is therefore concluded that no
further work should be carried out in
respect of SUDS.
Should the
specification
specify a
design life for
constructed
drainage?
Yes = 81.4%,
No = 18.6%
The results of the survey clearly conclude
that the Specification should include a
design life for constructed drainage.
If so, what 0-10 years 0.0% The results from the survey would
15STANDARDISED SPECIFICTION AND STANDARD DETAILS
JUNE 2012
7/21/2019 120612 Standard Specification Stage2 Interim Report Appendices
17/64
Appendix 1 Series 500 Drainage and Service Ducts
16STANDARDISED SPECIFICTION AND STANDARD DETAILS
JUNE 2012
Question Survey Response Comment
design life
would you
anticipate?
20 years 8.0%
50 years 44.0%
100 years 32.0%
Other 16.0%
suggest that the design life for new
drainage should be a minimum 50 years.
There are considered to be two distinctissues that will impact on the operational
effectiveness of any new drainage asset
during its operational life as detailed
below:
The operational effectiveness of the asset
in respect of its ability to deal with
changes (i.e. any increase) in discharge
flows over time;
The physical construction of the drainage
asset being sufficient to remain
operational and free from major defect.
In respect of Item 1 above, current design
guidance dictates that design flows
include for a 20% uplift to take account of
Climate Change. It is therefore
considered that this aspect is currently
adequately dealt with.
With regard to the as-constructed system
being of an adequate standard to
physically last for the required design life
this will be dependent upon a number of
factors which include:
1. Construction design;
2. Materials used;
3. Operational maintenance.
The construction design of fundamental
elements of any new drainage system (i.e.
chambers, gullies and pipe runs) is based,
in general, on tried and tested principles
which have resulted in the development of
the current Standard Details that are
included within the current SHW.
It is accepted that these Standard Details
will be subject to refinement over time as
new materials and techniques aredeveloped but in principle it is considered
that they currently meet the requirements
7/21/2019 120612 Standard Specification Stage2 Interim Report Appendices
18/64
Appendix 1 Series 500 Drainage and Service Ducts
17STANDARDISED SPECIFICTION AND STANDARD DETAILS
JUNE 2012
Question Survey Response Comment
for sound construction design.
It is noted that there are differences
between the Motorway/ Trunk RoadNetwork (for which the current SHW has
been developed) and the local road
network and a number of key drainage
elements that are required for local roads
are not included. An aim of this current
review is to identify and include those
standard construction details that are
currently not covered by the SHW.
The materials to be used in the
construction of drainage systems are
considered, in the main, to be defined well
by the current Specification. Material
specifications for component elements
(i.e. pipes, chamber covers and gratings)
are controlled by standards and codes
that are referenced within the
Specification. Where further detail is
required on the specific requirements of
materials such as pipe bedding and
trench backfill this is provided within the
document.
Maintenance of the drainage system is a
fundamental requirement to ensuring the
operational effectiveness of the system
and prolonging its operational life.
The maintenance regime to be adopted
for drainage systems is not covered by
the SHW as this is generally dealt with
separately by other documentation (i.e.
Network Management Manual).
It is therefore considered unnecessary to
include within the SHW maintenance
requirements for drainage systems.
What is the
actual life of
drainage
encounteredbefore major
renewals or
0-10 years 0.0%
20 years 0.0%
Review of the survey results and
comments received to this question would
indicate that actual life of drainage before
renewals is required is 50 years. Thiswould suggest that the current
Specification is achieving the expectations
7/21/2019 120612 Standard Specification Stage2 Interim Report Appendices
19/64
Appendix 1 Series 500 Drainage and Service Ducts
18STANDARDISED SPECIFICTION AND STANDARD DETAILS
JUNE 2012
Question Survey Response Comment
replacement? 50 years 39.3%
100 years 19.6%
Other 41.1%
of Local Authorities.
The results of the survey conclude that
drainage should be specified on a fitnessfor purpose basis.
Should
drainage be
specified on a
fitness for
purpose
basis?
Yes = 72.9%,
No = 27.1%
The adoption of fitness for purpose for
the design and construction of drainage
infrastructure may/will impact on both
Designers and Contractors. The legal
and insurance (i.e. professional
indemnity) implications of adopting a
fitness for purpose basis needs to be
fully investigated which is currently
considered to be outside the scope of this
current review.
For ductile iron
covers what
depth do you
normally
specify for
trafficked
areas?
100mm 23.6%
150mm 76.4%
The results of the survey clearly indicate
that Local Authorities currently prefer and
adopt 150mm deep ductile iron covers for
trafficked areas.
The current Specification specifies that
chamber covers and gully gratings shall
comply with the requirements of BS EN124. Consideration needs to be given to
whether the specification for chamber
covers and gully gratings needs to be
modified to take account of new products
and the issues identified in the response
to Qu 24.
For gully and
manhole
covers in
trafficked
areas is there
an increased
need to rebed
or replace the
covers in the
last 10 years?
Yes = 81.4%,
No = 18.6%
The results of the survey clearly indicate
that there is an increased need to rebed
and replace gully and manhole covers
located in trafficked areas.
A review of the responses as to why this
is occurring identifies the following key
reasons for this problem:
1. Increase in traffic volumes andloading (i.e. increased volume andweight of HGVs);
2. Inappropriate bedding material
and insufficient time for beddingmaterials to cure before trafficking;
3. Poor workmanship (linked to
7/21/2019 120612 Standard Specification Stage2 Interim Report Appendices
20/64
19
Appendix 1 Series 500 Drainage and Service Ducts
STANDARDISED SPECIFICTION AND STANDARD DETAILS
JUNE 2012
Question Survey Response Comment
available time to make repairs);
4. Design/strength of ironwork;
5. Deteriorating network condition;
6. Theft;
It is considered that further investigation is
undertaken into all of the above aspects
to try and improve the design and
construction specification for chamber
covers, frames and gullies.
7/21/2019 120612 Standard Specification Stage2 Interim Report Appendices
21/64
Appendix 2 Series 700 / 900 Road Pavements Bi tuminous Bound Materials
Appendix 2 Series 700/900 Road Pavements - Bituminous Bound Materials
Summary of information provided by local highways authorities as part of the HMEP
survey carried out in October 2011.
Title of Sub Clauses Changes from original
SHW
Comments on changes
901 Bituminous
pavement materials
Significant changes.
See comments.
These were based on SHW (11/04)
edition, presenting amendment
(additional and substitute) clauses
on installation (transportation, laying
and compaction). The current SHW
(11/08) specifies these in Clause
903, where these details should be
considered
903SR Placing and
Compaction of
Bituminous Mixtures
Further details were
added.
Most of these details are contained
in BS 594987 (already referenced
by the current SHW). This clause,
903SR, also contains application for
footways however this should not be
part of Series 900 but to be covered
by Series 1100.
Revision to this clause is required to
accommodate recent best practice
for laying and to improve durability
911SR Hot Rolled
Asphalt (HRA) Surface
Course (Design
Mixtures)
There a number of
HRA variants which
are specified based on
either a conventional
Marshall Mixture
Design (MMD) and a
performance based
approach.
It is recommended that these two
design approaches are separated to
allow consistency with the current
SHW (11/08), specifically by
retaining that using MMD approach
within this clause but transferring
those with performance based
approach to Clause 943. The latter
will incorporate additional clauses toencompass the use of 30/14 and
55/14 HRA materials (note: the
current Clause 943 covers 35/14
HRA only).
918SR Slurry
Surfacing
Incorporating
Microsurfacing
This SR clause covers
application for
footways and
carriageways.
It is recommended that the former
should be excluded from Series 900
and transferred to Series 1100.
919SR Surface
Dressing: Recipe
There are some
repetitions regarding
ingredient materials
Additional references to TRL RN39
and the recent RSTA code of
practice should be added. Therefore
20STANDARDISED SPECIFICTION AND STANDARD DETAILS
JUNE 2012
7/21/2019 120612 Standard Specification Stage2 Interim Report Appendices
22/64
Appendix 2 Series 700 / 900 Road Pavements Bi tuminous Bound Materials
21STANDARDISED SPECIFICTION AND STANDARD DETAILS
JUNE 2012
Title of Sub Clauses Changes from original
SHW
Comments on changes
Specification (e.g. chipping
gradation and
properties); these can
be simplified.
revision to 919SR is required.
920SR Bituminous
sprays
See comments. These were outdated and based on
SHW (11/04) edition. The current
SHW (11/08) is sufficient.
921SR Surface
Macrotexture of
Bituminous Surface
Courses
This clause contains
specific requirements
from The County
Council.
Details in the current SHW (11/08)
should be sufficient for general use
and allow options to use
conventional method ofassessments and well as the
automated method adopted by The
County Council.
926SR In situ recycling
- the remix and repave
process
This clause introduces
in situ repair process.
This should be covered in the new
clause 951AR on Patching.
931SR Use of Rubber
in Materials
Provision on the use of
rubber in bituminous
mixtures.
This clause is now obsolete, making
a reference to Road Note 36 (1968).
This clause was allocated for RecipeMixtures: Heavy Duty Macadam
Base and Binder Course Macadams
with Paving Grade Bitumen (SHW
11/04) but now no longer in use
(since SHW 11/08). This material is
no longer in use hence may be
omitted.
937AR Stone mastic
asphalt used as
surface course
Introduce the use of
SMA in surface
course.
It may be better to address the use
of in Clause 972AR to avoid conflict
with the existing SHW.
942SR Thin Surface
Course Systems
Allowance to use
materials without BBA
HAPAS certificates.
Revision to the current SHW (11/08)
is required, to consider the new IAN
157/11 and the draft IAN 154
regarding the installation of this
material and the approval system
942SR Thin Surface
Course Systems
Surface integrity
guarantee has been
reduced to 3 years.
Consider the new IAN 157/11 and
the draft IAN 154 regarding the
installation of this material and the
approval system
7/21/2019 120612 Standard Specification Stage2 Interim Report Appendices
23/64
Appendix 2 Series 700 / 900 Road Pavements Bi tuminous Bound Materials
22STANDARDISED SPECIFICTION AND STANDARD DETAILS
JUNE 2012
Title of Sub Clauses Changes from original
SHW
Comments on changes
945SR Weather
Conditions for Laying
of Hot Bituminous
Mixtures
It clearly presents
some details for rolled
asphalt application but
not so for other
materials.
An update is recommended.
959AR Bituminous
mixtures to BS EN
13108
Additional clause This clause makes reference to BS
EN 13108-1, 2, 4 and 5. These are
unnecessary duplicates of the
previous clauses. Therefore this
clause can be omitted.
959AR Resin basedcoloured surface
treatment
Additional clause This clause makes allowance tospecifying the use of this material for
lane demarcation.
960AR Use of slag
aggregate in
bituminous mixtures
Additional clause. This
clause prohibits the
use of blast furnace
and steel slag
aggregates in asphalt
mixtures.
This requirement is specific for the
Council. The use of these slag
aggregates is generally acceptable
provided that the aggregates meet
the requirements of Clause 901 and
the bituminous mixtures are properly
designed. Therefore this clause can
be omitted.
960AR Guide to use
slag aggregate in
asphalt mixtures.
Additional clause. This
clause prohibits the
use of slag aggregate
in low temperature
asphalt mixtures.
The reason behind this is unknown
and requires further considerations
by contacting the Council f or
discussion.
960AR Stress
absorbing membrane
interface (SAMI)
Additional clause This clause makes allowance to the
use of SAMI.
961AR Sand carpet
asphalt
Additional clause This clause specifies the use of
HRA 0/2F surf 70/100 with minimum
binder content of 10.8% (m/m).
Without more detailed information
about this clause it is not possible to
comment further.
961AR Stress
absorbing membrane
(SAM)
Additional clause This clause makes allowance to the
use of SAM.
962AR PSV
Requirements of
Additional clause This clause could have been
incorporated in the relevant clauses
7/21/2019 120612 Standard Specification Stage2 Interim Report Appendices
24/64
Appendix 2 Series 700 / 900 Road Pavements Bi tuminous Bound Materials
23STANDARDISED SPECIFICTION AND STANDARD DETAILS
JUNE 2012
Title of Sub Clauses Changes from original
SHW
Comments on changes
Surface Course
Asphalt
of the respective surface course.
Therefore this clause can be omitted
963AR removal of
Existing Asphalt
Layers
Additional clause This clause could have been
incorporated in clause 902.
Therefore this clause can be
omitted.
964AR Surface
Preparation (Crack
Filling)
Additional clause This clause could have been
incorporated in clause 902.
Therefore this clause can be
omitted.
965AR Ironworks and
Drainage
Additional clause Consider adopting this clause, with
some modifications.
970SR Shaping
existing carriageway
(Bituminous Bound
Materials)
Additional clause This clause is about regulating layer
and it is better included in Clause
907.
970AR Compaction
control of asphalt
mixtures
Additional clause Broadly quoting BS 594987
practices. It may be better included
in the new Clause 903AR.
970AR 45% stone
content hot asphalt
surface course (for
hand laying)
Additional clause This clause allows the use of non-
standard HRA 45/XX type F 160/220
and is site specific. For simplicity,
this clause can be omitted.
970AR Intermediate
asphalt concrete
surface course
Additional clause This clause allows the use of non-
standard binder rich AC 20 close
surf 100/150 and is site specific. For
simplicity, this clause can be
omitted.
970AR Pre-patching
repairs to carriageway
using only surface
course materials
Additional clause It will be more appropriate to
consider this clause under the new
Clause 951SR (Patching).
971AR Stone Mastic
Asphalt Surface
Course
Additional clause This clause contains extracts from
BSI PD 6691 and BS 594987. An
update is required to accommodate
the most reference update on
Transport Scotland TS2010 (Ver2.0, 2012).
7/21/2019 120612 Standard Specification Stage2 Interim Report Appendices
25/64
Appendix 2 Series 700 / 900 Road Pavements Bi tuminous Bound Materials
24STANDARDISED SPECIFICTION AND STANDARD DETAILS
JUNE 2012
Title of Sub Clauses Changes from original
SHW
Comments on changes
971AR Fine
Regulating Course
Additional clause This clause permits the use HRA
50/10 bin 40/60 only for regulating
layer. It is better placed in the new
Clause 907AR
972AR Cold in situ
recycled bitumen
stabilised base
Additional clause This clause is similar to SHW
Clause 948 but contained obsolete
BS. It may be better omitted and
new reference made to Clause 948.
972AR Surface
treatments -
application of grit toenhance early life
skidding resistance
Additional clause This concerns the use of coated and
non coated grit. It may be better
placed and/or incorporated in971AR.
973AR Cold in situ
recycled bitumen
stabilised base and
foamed bitumen
binder course - mixture
design and
characterisation
Additional clause This clause is similar to SHW
Clause 948 but contained obsolete
BS. It may be better omitted and
new reference made to Clause 948
973AR Compaction
Requirements
Additional clause It may be better included in the new
Clause 903AR.
974AR Foamed
bitumen bound binder
course
Additional clause This clause is similar to SHW
Clause 948 but contained obsolete
BS. It may be better omitted and
new reference made to Clause 948.
974AR Retread
process
Additional clause A reference can also be made to
DMRB HD31/94. An update to this
clause is recommended.
975AR Annex B BS
13108-1 Asphalt
Concrete Specification
Additional clause Similar to PD 6691. These are
unnecessary duplicates of the
previous/existing SHW clauses.
Therefore this clause can be
omitted.
975AR Surface
dressing
Additional clause It is about installation process.
These have been broadly covered
by previous clauses (919 and 922).
Therefore this clause can be
omitted.
7/21/2019 120612 Standard Specification Stage2 Interim Report Appendices
26/64
25
Appendix 2 Series 700 / 900 Road Pavements Bi tuminous Bound Materials
STANDARDISED SPECIFICTION AND STANDARD DETAILS
JUNE 2012
Title of Sub Clauses Changes from original
SHW
Comments on changes
976AR Annex C BS
13108-4 Hot rolled
asphalt Specification
Additional clause Similar to PD 6691. These are
unnecessary duplicates of the
previous/existing SHW clauses.
Therefore this clause can be
omitted.
7/21/2019 120612 Standard Specification Stage2 Interim Report Appendices
27/64
Appendix 3 Series 1100 - Footways and Paved Areas
Appendix 3 Series 1100 Footways and Paved Areas
Summary of information provided by local highways authorities as part of the HMEP
survey carried out in October 2011.
Clause Reason for Variation Relevance
1101AR Kerbs,
Channels, Edgings
& Quadrants
(Note: this clause has been re-titled to
include stone kerbs and setts laid in
kerblines)
Sub Clause 1
Delete "C7.5 or mix ST1" and substitute
C12/15 or mix ST3"
Sub Clause 2
Insert at end Where kerbs are re-laid against
existing carriageway the kerbline shall be
sealed in accordance with clauses 1016 &
1017.
Sub Clause 3
Insert at end "For radii of 12m to 25m,
600mm long straight kerbs may be used. No
single kerb shall be less than 450mm long."
Add Sub Clause 6
The construction principles and practices set
out in sub clauses 1-5 above shall apply
equally to stone kerbs and setts laid in
kerblines, except that the tolerances for
longitudinal and vertical accuracy shall be
6mm along the top outer edge of the kerbs
to allow for local irregularities in shape.
Cannot find C7.5 or mix
ST1 in the original SHW.
Require clarification to
consider taking this
forward.
This sub clause is worth
taking forward as it ties in
sub clauses from other
SHW sections removing
any vagueness currently
associated with particular
tasks.
This sub clause is worth
taking forward as it could
help other LHAs formalise
requirements.
This sub clause is worth
taking forward as it might
help other LHAs when
using setts.
1104AR Footways
And Paved Areas
(Precast Concrete
Flags)
Clause 1104 para 2
Delete "Where permitted in Appendix 11/1 ...
+ 5 mm thick."; and
Substitute "450 x 450 mm small elemental
paving shall be laid on 100 mm thick grade
ST1 concrete base leaving 3 to 4 mm joints,
levelled using a rubber maul and dry silver
or silica jointing sand complying with Clause
1107AR brushed into joints for the full
depth."
Add additional paragraph.
5. Tactile paving is generally laid at
controlled crossings to delineate the position
This sub clause is worth
taking forward as it is likely
to increase the stability of
small elemental paving for
longer. It would also help
other LHAs.
Tactile Paving is covered
in latter clauses. This text
will need to be reviewed in
conjunction with the other
26STANDARDISED SPECIFICTION AND STANDARD DETAILS
JUNE 2012
7/21/2019 120612 Standard Specification Stage2 Interim Report Appendices
28/64
Appendix 3 Series 1100 - Footways and Paved Areas
27STANDARDISED SPECIFICTION AND STANDARD DETAILS
JUNE 2012
Clause Reason for Variation Relevance
of the crossing for blind and partially sighted
people. It shall be laid to an exact pattern to
be specified by the Overseeing Organisation
for each individual site.
Flags shall be 450 x 450 x 70 mm with
domes or dimples protruding from the
uppermost surface and shall be red or buff in
colour. Domes shall have a height of 6 mm
and a diameter of 12 mm and shall number
approximately 49 per flag.
Flags shall be cut and laid to fit the contours
of the vehicular crossings and laid in
accordance with Clause 1104AR above.
clauses and merged as
necessary. This may end
up an AR to clause 1104
or a separate clause.
1104 Footways
And Paved Areas
(Precast Concrete
Slabs And Natural
Stone Flags)
Delete Sub Clause 2; and Substitute:
2. Slabs and flags shall be laid to the
crossfall detailed in Drawing No. LC.07a,
with transverse joints perpendicular to the
kerbline unless agreed otherwise with the
Project Manager. All longitudinal joints shall
be offset by a minimum of 150 mm except
where agreed with the Project Manager.
Slabs and flags shall be bedded on a
uniform 25mm thick layer of 1:15 dryPortland (CEM I) cement/bedding sand mix.
The bedding sand shall be clean sharp
sand, aggregate size 0/4 CP or 0/4 MP to
BS EN 13139. Where permitted by the
Project Manager as an alternative, slabs and
flags up to 450mm square may be bedded
on a layer of bedding sand 25mm +/- 10mm
thick. Bedding of slabs on 5 spot mortar is
not permitted.
Insert Sub Clauses 4 - 7
4. Joints between slabs and flags shall be
close, i.e. 2 to 4 mm in width. Joints shall be
grouted to within 2 to 3mm of the surface in
the following manner:
The surface of the slabs/flags shall be
watered. A site-mixed grout with a Portland
(CEM I) cement:sand ratio of 1:8 to 1:10
shall then be poured on to the surface and
brushed into the joints. The bedding sand
shall be clean sharp sand, aggregate size
0/4CP or 0/4MP to BS EN 13139. A dry
This sub clause is worth
taking forward, though it
needs to be reviewed in
association with the similar
sub clause suggested in
1104AR above.
References to specific
LHA diagrams needs to be
removed and replacedwith MHA related
diagrams thus the MHA
diagram catalogue will
need to be reviewed. If a
diagram does not exist, a
decision will need to be
made on creating a new
diagram to share with
HMEP.
There is already a sub
clause 4 in the SHW.
There is no instruction to
delete the existing sub
clause, so the originating
LHA needs to clarify this
before it can be taken
forward.
Alternatively, if text does
not relate to the SHW text,
this sequence of sub
clauses can be
7/21/2019 120612 Standard Specification Stage2 Interim Report Appendices
29/64
7/21/2019 120612 Standard Specification Stage2 Interim Report Appendices
30/64
Appendix 3 Series 1100 - Footways and Paved Areas
29STANDARDISED SPECIFICTION AND STANDARD DETAILS
JUNE 2012
Clause Reason for Variation Relevance
1105AR Footways
And Paved Areas
(Flexible
Surfacing)
Add additional paragraph
4. The permitted tolerance for the finished
surface of footway binder course layers shallbe -6 mm to +0 mm. Sand asphalt and 6 mm
nominal sized asphalt concrete surface
course shall be laid 20 mm thick with a
permitted tolerance of - 0 to + 6 mm.
This sub clause is worth
taking forward as it furtherspecifies relevant depths
and tolerances that can be
used by other LHAs.
1105 Footways
And Paved Areas
(Flexible
Surfacing)
Insert Sub Clause 4
4. The sealing of joints in surfacing or edges
of repairs shall be by painting of the vertical
face only (in accordance with Clause 901)
and shall not include overbanding or surface
applied sealing unless so directed by theProject Manager.
This sub clause is worth
taking forward in parallel
to the above 1105AR. It
may be necessary to
renumber either of thesetwo sub clauses.
Overbanding is a topic of
contention across many
LHAs.
1106AR Footways
And Paved Areas
(In-Situ Concrete)
Delete paragraph 3. This SHW sub clause
needs to be reviewed. It
may appear to be sensible
for the majority of LHAs to
take it forward. However,
initial thoughts would be todismiss it.
1107AR Footways
And Paved Areas
(Concrete Block
Paving)
Add additional paragraph
4. Blocks shall be 200mm x 100mm x 80mm
thick with a chamfer or radius not exceeding
6mm. The wearing surface of each block
shall not be less than 85 per cent of the total
plan area of the block. The colour and
pattern of block paving shall be to that
specified by the Overseeing Organisation or,
in the case of patching work, shall matchexisting.
Sands for use in Laying Course (bedding
sand) and for jointing in clay or concrete
block pavements shall be naturally occurring
silica sands. Sands from quaternary
geological and sea dredged sands are
preferred; sands from crushed rock sources
shall not be used, except with the approval
of the Overseeing Organisation.
All sands used in block pavements shall be
essentially free from deleterious salts or
This sub clause is worth
taking forward as it further
clarifies details around
using concrete blocks.
This might help other
LHAs that have not
specified to this detail
before.
7/21/2019 120612 Standard Specification Stage2 Interim Report Appendices
31/64
Appendix 3 Series 1100 - Footways and Paved Areas
30STANDARDISED SPECIFICTION AND STANDARD DETAILS
JUNE 2012
Clause Reason for Variation Relevance
other contaminants.
Unless otherwise agreed by the Overseeing
Organisation, all laying course sand and allthe jointing sand delivered to any one site
shall each be from a single source.
The moisture content of laying course sand
shall be consistent and within ""1% of
optimum, as determined with BS1377 : Part
4 : 1990 : method 3.3.
The grading of the sands, as determined by
the washing and sieving method of BS EN
933-1:1997 (this replaces BS 812:Section
103.1 but BS812:Section 103.1 remainscurrent) shall be within the limits given
below:
BS sieve size Cat I Cat II C III Jointing
(BS 410) Sand
10 mm 100 100 100
5 mm 90-100 90-100 90-100
2.36 mm 75-100 75-100 75-100 100
1.18 mm - - - 95-100
600 Fm 35-60 35-60 35-70 55-100
300 Fm 8-35 8-35 8-35 15-50
150 Fm 0-10 0-10 0-10 0-15
75 Fm 0-0.1 0-1 0-3 0-3
Category I sites are pavements subject to
severely channelised traffic, docks,
harbours, bus stations, loading bays, aircraft
pavements, and the like.
Category II sites include adopted highways,
petrol station forecourts and pedestrian
precincts, car parks and footways subject to
some heavy vehicle loading.
Category III sites are those subject to little or
no heavy vehicular traffic, e.g. some
pedestrian areas, car parks, private drives
and footways.
Blocks shall be laid on a screeded layer ofsand having grading within the limits set in
the table above. Sand shall be laid to a
7/21/2019 120612 Standard Specification Stage2 Interim Report Appendices
32/64
Appendix 3 Series 1100 - Footways and Paved Areas
31STANDARDISED SPECIFICTION AND STANDARD DETAILS
JUNE 2012
Clause Reason for Variation Relevance
compacted thickness of 50 mm. The blocks
shall be laid close together, being brought to
the laying face over the already laid work
and the whole area vibrated using a handguided rubber-based vibrating plate. Dry
silver or silica sand having a grading within
the limits of the table above shall be brushed
into the surface of the blocks and the area
vibrated several times until the joints are
completely filled with sand.
1110AR Frost
Susceptibility
1. Subject to the tolerances given in Table
7/1 and unless otherwise stated in Appendix
7/1, material shall not be frost susceptible if
it is used within 450mm of the designed finalsurface of a footway or paved area, or
350mm if the mean annual frost index of the
site is less than 50. Material shall be
classified as non-frost susceptible if the
mean heave is 15mm or less, when tested in
accordance with BS 812: Part 124: 1989
amended as given in Sub Clauses 801.7
and 801.8.
This sub clause is worth
taking forward, though the
text will need to be
reviewed alongside theother Frost Susceptibility
related clauses.
References to Tables and
Appendices are LHA
specific, so the text may
need to be modified
accordingly.
1111AR Footways
And Paved Areas
(Hard LandscapeAreas)
1. Footways and paved areas in hard
landscaped areas shall be constructed in
accordance with the requirements inAppendix 11/01 and Appendix 11/70.
Appendix 11 will be
contract specific for a
single LHA and might bedifficult to take forward
without extracting the
appropriate text from the
Appendix.
1112AR Dressed
Natural Stone
Kerbs, Channels,
Quadrants And
Setts
1. Dressed natural stone kerbs, channels,
quadrants and setts shall comply with BS
EN 1342:2001 and also BS EN 1343:2001
and be of the type of igneous rock, finish
and size as described in Appendix 11/71.
Kerbs, channels and quadrants shall be laid,bedded and backed in compliance with
Clause 1101.1 and 1101.2. Unless
otherwise described in Appendix 11/71, setts
shall be laid, bedded and backed in class
C16/20 or ST4 concrete in accordance with
BS 8500-1:2006 and BS8500-2:2006. They
shall be laid on either a Mix ST4 concrete
foundation or on the base.
2. For curves of radius 12m or less, kerbs
and channels of appropriate radius shall be
used.
3. Individual kerbs, channels or quadrants
Appendix 11 will be
contract specific for a
single LHA and might be
difficult to take forward
without extracting the
appropriate text from theAppendix.
Curves >12m are covered
in another sub clause.
Consider appending this
text to that sub clause.
7/21/2019 120612 Standard Specification Stage2 Interim Report Appendices
33/64
Appendix 3 Series 1100 - Footways and Paved Areas
32STANDARDISED SPECIFICTION AND STANDARD DETAILS
JUNE 2012
Clause Reason for Variation Relevance
shall not deviate by more than 3mm in 3m
from line and level. Setts shall be laid to a
flowing alignment.
1113AR Clay Brick
or Precast
Concrete Block
Kerbs, Channels
and Edgings
1. Clay bricks used for kerbs, channels and
edgings shall comply with BS EN 771-1 :
2003 and conform to the Class, size and
type described in Appendix 11/72. Precast
concrete blocks used for kerbs, channels
and edgings shall comply with BSEN 1338
and conform to the shapes, finish,
dimensions and colours described in
Appendix 11/72. They shall be laid and
bedded on a mortar designation (i) in
accordance with BS5628-3 Table 13 not lessthan 10mm and not more than 40mm thick,
on Mix ST4 concrete foundation or on the
base. Alternatively they may be laid and
bedded directly on Mix ST4 concrete
foundation whilst it is still plastic. Where
described in Appendix 11/72 clay brick or
precast concrete block kerbs, channels and
edgings shall be backed with Mix ST4
concrete.
2. For curves of radius 12m or less, kerbs,
channels and edgings shall be radially cuton both edges to the required line.
3.. Units of kerb, channel or edging shall not
deviate by more than 3mm in 3m from line
and level.
This sub clause is worth
taking forward as it further
details the requirements
when laying clay bricks.
Appendix 11 is specific to
a single LHA. It may be
necessary to extract the
relevant text from the
Appendix.
Check with Clause 1108 to
see if it is a natural AR or
should remain separate.
This sub clause is a repeat
of one found in 1112ARabove.
This sub clause is a repeat
of one found in 1112AR
above. (Note: This sub
clause would need to be
renumbered).
1114AR Timber
Edging
1. Timber edging shall be constructed to the
requirements of Drawing Number K157.
Need to check if MHA
have an equivalentdrawing. If not, there may
be a case for a drawing to
be created and then
shared through HMEP.
Timber edging is
mentioned in a later
clause, which will need to
be reviewed in parallel and
merged with this sub
clause, if appropriate.
1115AR Footways
and Paved Areas
1. Slurry surfacing to footways and paved
areas shall be made and laid in compliance
These sub clauses need
to be reviewed in parallel
7/21/2019 120612 Standard Specification Stage2 Interim Report Appendices
34/64
Appendix 3 Series 1100 - Footways and Paved Areas
33STANDARDISED SPECIFICTION AND STANDARD DETAILS
JUNE 2012
Clause Reason for Variation Relevance
(Slurry Surfacing) with Clause 918 and Appendix 11/73.
2. The colour and any other factors affecting
the design of the slurry surfacing are to be
as stated in Appendix 11/73.
to MHA (1170AR) and The
Council (1170AR &
1175AR) with a view to
merging.
Also, Appendix 11 is
proprietary to the LHA.
The appropriate text may
need to be extracted to
take this forward.
1116AR Bus
Shelters
1. The Council preferred style of Bus
Shelter installed throughout the County is
the Arun Style manufactured by
Queensbury, the Contractor shall note that
new installations will be installed as part of
the Maintenance Contract. If the contractor
wishes to use other shelters from different
manufacturers then they shall match in style
and colour the already installed shelters
throughout the Council.
2. The maintenance of glazing to the existing
shelters shall be undertaken by fully
qualified personnel for the style of shelter
throughout The Council glass sizes for
replacement shall be 8mm thick and cleartoughened to BS 6206. The glass is retained
horizontally with glass rails top and bottom,
and vertically with a one piece u-channel
extrusion. All fixings are allen key button
head stainless steel screws, which are
powder coated to match the framework.
3. Panels within the Enclosed Shelter and
Cantilevered Shelter have Glass with the
Council Logo and the sizes of these are
1393 x 1210 (enclosed) and 1393 x 916
(cantilevered). For exploded view of
Enclosed Shelter see Queensbury drawing
SK1080.
4. The contractor shall note that all
personnel replacing glass and maintaining
the existing shelters shall have the required
Street Works registration card for working on
the Highway.
5. All new bus shelters shall be as stated in
Appendix 11/74 and on the works order.
Although this sub clause is
specific to one LHA, it is
worth taking forward to
benefit others. LHAs
would probably like to
specify a particular style
and a repair/maintenance
regime for all bus shelters.
The MHA drawing
catalogue needs to be
reviewed for a similar
existing drawing. If no
drawing exists it might beappropriate to produce
one to be shared across
HMEP.
Appropriate training and
qualifications are
important. This sub clause
should be taken forward.
Appendix 11 will be
contract specific to a
particular LHA.
Appropriate text might
need to be extracted from
the Appendix to take
forward.
7/21/2019 120612 Standard Specification Stage2 Interim Report Appendices
35/64
Appendix 3 Series 1100 - Footways and Paved Areas
34STANDARDISED SPECIFICTION AND STANDARD DETAILS
JUNE 2012
Clause Reason for Variation Relevance
1170AR Frost
Susceptibility
1. Material used within 450 mm of the
designed final footway or paved area
surface shall not be frost susceptible as
defined in the test method and procedure ofthe Transport Research Laboratory
Supplementary Report No SR 829.
Review this clause against
the other Frost
Susceptibility clauses from
other LHAs to see if thereis commonality and
therefore define common
text in an Additional
clause.
1170AR Natural
Stone Kerbs, Kerb
Setts, Channels,
Channel Setts,
Edging and Edging
Setts
1. Unless otherwise stated in Appendix
11/70 Natural Stone Kerbs, Kerb Setts,
Channels, Channel Setts, Edging and
Edging Setts shall comply with BS EN 1341
and the 1100 Series of the Specification for
Highway Works.
2. The types of Natural Stone Kerbs, Kerb
Setts, Channels, Channel Setts, Edging and
Edging Setts shall be as described in
Appendix 11/70.
Appendix 11 is proprietary
to a single contract with a
LHA. Extracting the
appropriate text from the
Appendix to be able to
take these sub clausesforward.
1170AR: Footway
Retread
1. Treat all emergent weeds, using
Glyphosate, 7 to 14 days prior to the retread
process and in accordance with
manufacturers instructions. Rake out and
remove all dead weeds, side back grass and
clear back overhanging vegetationimmediately prior to the retread process.
2. Areas of prior reconstruction (including
domestic and wheelchair footway crossings)
shall be constructed as shown in Drawing
LC.07a but excluding the surface course.
3. The position of all service covers shall be
referenced by marks made on adjacent
carriageway surfaces or by pegs or other
similar means. Areas of closely adjacent
ironwork or street furniture inaccessible to
the retread process plant shall be defined for
alternative treatment (see 13 below).
4. Scarify existing footway (including partially
reconstructed areas) using a mini cold
planer or similar approved method to a
depth of 6510mm. Manually rake over the
material to remove any individual pieces of
aggregate in excess of 50mm size.
5. At the direction of the Project Manager
any areas showing subgrade weakness shall
be strengthened by temporary removal of
the scarified layer, excavation of the existing
These sub clauses are
worth taking forward. This
sub clause needs to be
reviewed alongside that of
The Council 1175AR and
MHA 1170AR on SlurryResurfacing of Footways,
with a view to either
merging to a single AR or
keeping separate.
The MHA drawing
catalogue needs to review
to replace the LHA specific
reference within this sub
clause.
7/21/2019 120612 Standard Specification Stage2 Interim Report Appendices
36/64
Appendix 3 Series 1100 - Footways and Paved Areas
35STANDARDISED SPECIFICTION AND STANDARD DETAILS
JUNE 2012
Clause Reason for Variation Relevance
sub-base and/or subgrade and replacement
with Granular Type 2 sub-base. The
removed scarified aggregate shall then be
replaced.
6. The scarified aggregate shall be shaped
and graded to the specified level and
crossfall allowing for the total specified depth
of surface course. Excess material shall be
removed, or relocated to positions requiring
'make-up'. In areas of aggregate deficit,
'make-up' shall be approved imported
planings or Granular Type 2 sub-base which
must be thoroughly mixed into existing
scarified material.
7. Compact the scarified layer using a twin
drum vibrating roller to a tolerance of 6mm
under a 3m straightedge and to achieve a
Clegg Impact Soil Tester value greater than
25.
8. Protect all covers, kerbs, edges and
private property by masking or other
approved method.
9. Apply K2-55 bitumen emulsion to thesurface at a uniform rate of 4.51.0 l/m.
10. Apply grade 2.8/6.3 sized dry stone
chippings (to BS EN 13043) to the surface at
a rate of spread of 7.00.5kg/m.
11. Lightly compact to effect full retention of
the chippings.
12. Adjust all service covers to finished
levels (see Appendix 5/72).
13. Inaccessible areas (see 3 above) shall
be broken out and replaced with a fully
compacted 40mm course of 20mm nominal
size open textured binder course.
14. The retreaded surface should remain
exposed for at least 24 hours and shall not
be surfaced over prior to approval by the
Project Manager.
15. Prior to laying the surface course apply
K1-40 bituminous emulsion tack coat at arate of 0.50.1l/m.
16. Apply asphalt concrete regulating course
7/21/2019 120612 Standard Specification Stage2 Interim Report Appendices
37/64
Appendix 3 Series 1100 - Footways and Paved Areas
36STANDARDISED SPECIFICTION AND STANDARD DETAILS
JUNE 2012
Clause Reason for Variation Relevance
as directed.
17. Apply tack coat and 20mm depth of
0/6mm size close graded surface course(BS 4987-1 Clause 7.5 made with 160/220
pen bitumen). The surface course must be
laid within 3 weeks of the retread process on
any site.
18. All excess excavated material must be
removed from site daily unless it is likely to
be required as 'make-up' elsewhere, in
which case it shall be secured from
interference.
1170 AR Footway
Slurry Surfacing
Unless specified otherwise in the Package
Order the following shall apply:
SPECIFICATION
1. GENERAL DESCRIPTION
1.1 This Specification deals with the
provision and laying of slurry surfacing
materials (6.0mm nominal layer thickness
and over) on footway and other areas notsubject to regular traffic other than private
vehicular access.
2. DESCRIPTION OF WORKS
2.1 The following processes are to be
included and quantities recorded for items
(c) and (j).
(a) Preparatory sweeping and pressure jet
washing;
(b) Weedkilling and weed treatment;
(c) Preliminary regulating of surfaces;
(d) Protection and masking of ironwork and
street furniture;
(e) Applying surfacing including any tack
coat if required by the process;
(f) Rolling of surfaces if required by the
process;
(g) Protection of newly treated surface;
These sub clauses are
worth taking forward and
combined with those from
The Council (1115AR) &
The Council (1170AR &
1175AR) on Footway
Retread/Slurry sealing.
7/21/2019 120612 Standard Specification Stage2 Interim Report Appendices
38/64
Appendix 3 Series 1100 - Footways and Paved Areas
37STANDARDISED SPECIFICTION AND STANDARD DETAILS
JUNE 2012
Clause Reason for Variation Relevance
(h) Sweeping of loose materials;
(i) Provision of signs for carrying out traffic
control, and informing frontagers;
(j) Resetting of Ironwork.
3. TYPE OF BINDER
3.1 Materials manufactured with bitumen
emulsion or modified bitumen emulsions
complying with the appropriate British
Standards where they exist.
4. PERIOD OF WORK
4.1 It is should be judged if weather
conditions and other circumstances are
suitable before carrying out the work.
5. PREPARATORY SWEEPING AND
CLEANING
5.1 All vegetation within the surface to be
covered shall be treated with an approved
herbicide not less than 14 days before the
application of the surfacing.
5.2 Immediately before application of the
surfacing all loose material from the surface
to be covered shall be removed (this is to be
accomplished by high pressure jet washing)
and any remaining vegetation still growing
moved, with any remaining root growth
treated with 2,4D.
Note: the application of 2,4D shall be made
after high pressure jet washing has taken
place.
5.3 The removal of any foreign matter
affecting the surface which is likely to prove
detrimental to the finished product is also
deemed to be included as part of the
preparatory cleaning e.g. oils spillage or any
substance likely to de-bond the layer to be
applied.
6. PROTECTION OF STREET FURNITURE
6.1 The full width and length of the area to
be treated shall be covered withoutoverlapping kerbs, channels and edgings for
7/21/2019 120612 Standard Specification Stage2 Interim Report Appendices
39/64
Appendix 3 Series 1100 - Footways and Paved Areas
38STANDARDISED SPECIFICTION AND STANDARD DETAILS
JUNE 2012
Clause Reason for Variation Relevance
footways.
6.2 The material shall not be allowed to
overlap on to boundary walls fences or anyother structure adjoining the highway nor
any street furniture actually situated within
the areas to be treated. All ironwork such as
manhole covers, hydrants, gullies, catchpit
covers, stop valves or similar shall be
masked to give complete protection during
the operation. Oils, and/or sand or similar
materials shall not be used.
7. RESETTING COVERS AND FRAMES
7.1 Where practicable, gullies and manholecovers and frames, stop valves and all other
covers shall be set to new levels before the
final surfacing is laid.
7.2 When covers etc., are set to new levels
after the surfacing is laid, the reinstatement
of the area around the covers etc., shall be
carried out in the same type of material as
that used for the new surfacing. Covers shall
be set to the new levels within two weeks of
the completion of the surface.
7.3 Manholes etc., shall be reset flush (+
3mm) with, and the gullies 6mm (+ 3mm)
below, the level of the new surface.
8. JOINTS
8.1 Longitudinal joints shall be feather
lapped such that the joints do not exceed the
nominal layer thickness, longitudinally or
laterally. Joints with adjacent surfaces shall
be feathered to neat regular shapesappropriate to the layout, and protective
mats or paper should be used to achieve
same. Wherever possible longitudinal joints
between final applications shall coincide with
lane lines. In every case, surfacing of the
highest part of the substrate due to crossfall
or camber will always be treated last thereby
ensuring that the upper layer of the feather
lap at joints will be so formed to shed water
towards the lower section of surface.
7/21/2019 120612 Standard Specification Stage2 Interim Report Appendices
40/64
Appendix 3 Series 1100 - Footways and Paved Areas
39STANDARDISED SPECIFICTION AND STANDARD DETAILS
JUNE 2012
Clause Reason for Variation Relevance
9. AGGREGATES
9.1 The final surface shall consist of
exposed rock aggregate with a minimum psvof 45.
10. MIXING AND LAYING
10.1 The material shall be properly
proportioned and shall be mixed by a
machine which shall be able to supply
sufficient material to achieve the nominal
layer thickness and surface regularity
required.
10.2 The surfacing mixtures shall be spreaduniformly by means of mechanical spreader
or by hand.
10.3 All material discharged from the mixer
shall be used without further addition.
10.5 Where more than one layer is
necessary each successive layer shall be
completed where possible within three days
of completion of the previous layer. Where
other than full machine width passes are
necessary these shall not form the final partof the surfacing.
10.6 It is recognised that in some areas
laying by mechanical means may not be
possible.
10.7 All equipment shall be limited to
weights which will not cause damage to
substrates.
11. FINISHED SURFACE
11.1 The finished surfacing shall be of
uniform surface texture and appearance
throughout the work, without variations
across the width of the paved area.
11.2 The finished surfacing shall be free
from droppings, excess overlapping or badly
aligned longitudinal or transverse joints,
damage by rain or frost, or other defects.
Any surfacing which does not comply with
this Clause, or is non-uniform in surface
texture or appearance within 30 days of
laying shall be made good by removal and
7/21/2019 120612 Standard Specification Stage2 Interim Report Appendices
41/64
Appendix 3 Series 1100 - Footways and Paved Areas
40STANDARDISED SPECIFICTION AND STANDARD DETAILS
JUNE 2012
Clause Reason for Variation Relevance
replacement of fresh material.
11.3 If fresh material is superimposed any
area so treated shall be not less than 5mlong and the full width of the machine. The
completed repair shall meet the overall
requirements of this Specification and shall
match the original material. In areas of
restricted access hand work may be
necessary but it is essential that a finish is
achieved compatible with that of the
mechanically laid material.
12. PERFORMANCE STANDARDS
12.1 Surface Regularity
No irregularity greater than 8mm under a 1m
straight edge shall be measured at any
location unless such a profile is required to
accommodate features such as dropped
kerbs, cambers and changing gradients.
12.2 Slip Resistance
The finished surface shall provide an
average slip resistance of at least 0.35 Grip
Number when measured in push mode overany 10m length with a Grip Tester currently
manufactured by Findlay, Irvine Ltd.,
Penicuik, Midlothian.
12.3 Abrasion Loss
If the effects of normal traffic and/or
weathering cause abrasion of the slurry
surfacing so as to completely reveal the
underlying original footway surface, this
condition is defined as Total Abrasion Loss.
Remedial works shall be carried out to any
single area of total abrasion loss when it
exceeds 1.0m2.
12.4 Penetration Resistance
The slurry surfacing shall, at all natural
ambient temperatures, be capable of
supporting pedestrians wearing narrow
heeled shoes without undue penetration of
the surface. Objective assessment of any
such defects shall be carried out as follows:the method of road surface hardness
measurement published in Appendix C of
7/21/2019 120612 Standard Specification Stage2 Interim Report Appendices
42/64
Appendix 3 Series 1100 - Footways and Paved Areas
41STANDARDISED SPECIFICTION AND STANDARD DETAILS
JUNE 2012
Clause Reason for Variation Relevance
TRL Road Note 39 Design Guide for Road
Surface Dressing (1992) shall be used with
the following modifications. The standard
4mm diameter tip shall be converted to a15mm diameter flat-ended tip using a
suitable converter, as available from the
probe manufacturers, SME Machine Tools
Ltd, Chapel Works, Sheffield Road,
Sheepbridge, Chesterfield, Derbyshire.
Measurements shall be made at a surface
temperature of 30C +2 without the use of
correction factors or graphs. Slurry
surfacing shall be regarded as unacceptably
soft if the main probe penetration exceeds
10mm.
13. PROTECTION OF NEWLY LAID
SURFACE
13.1 Traffic and pedestrians shall be kept off
newly treated surfaces until material has set
and will suffer to detrimental effect.
14. NOTICE TO CARRY OUT WORK
14.1 Clear and legible notices are to be
posted in the road where work is to becarried out giving at least 24 hours notice of
working being carried out.
14.2 The owners/occupiers of all properties
fronting the footway to be surfaced shall be
notified 24 hours before works are due to
commence, by means of the 3 CAP
Highways information leaflet.
15. TRAFFIC SAFETY MEASURES AND
CONTROL
15.1 Traffic control shall be in accordance
with the Code of Practice for Signing at
Surface Dressing Sites (produced jointly by
CSS and RSDA -CCS/RSDA /Eng/3/2000)
and such other special requirements as
described in the contract.
Reference to a particular
Grip Tester should be
changed to one that
complies with a particularBS or BSEN, or check
HAPAS or other
accreditation status of it
and make relevant
reference.
Reference to SME
Machine Tools should be
removed/revised.
1171AR Footways
And Paved Areas
(Stone Flags)
1. Natural Yorkstone Flags vary in thickness
and so shall be individually fully bedded on
mortar. Joints shall be no greater than 20
mm and shall be completely buttered, filled
and pointed with sand/cement mortar 3:1.
Where overriding of the footways occurs or
where specified by the Overseeing
It is worth taking this sub
clause forward as it might
apply to other LHAs
specifying the use of
specific surfacing.
Reference to Instarmac
should be replaced with
7/21/2019 120612 Standard Specification Stage2 Interim Report Appendices
43/64
Appendix 3 Series 1100 - Footways and Paved Areas
42STANDARDISED SPECIFICTION AND STANDARD DETAILS
JUNE 2012
Clause Reason for Variation Relevance
Organisation flags shall be laid on 100 mm
grade ST1 concrete and levelled using a
rubber maul.
Alternatively proprietary mortar may be
instructed (Instarmac or similar approved).
2. Second hand Yorkstone flags may be
provided by the Overseeing Organisation.
3. On occasion the Employer may request
that circular work where the radius is 12 m
or less all flags shall be radially cut on both
edges.
reference to HAPAS
approved materials.
Reuse of materials is
worth taking forward.
This sub clause should be
merged with the previous
sub clauses related to
curves > 12m.
1171AR: FootwayAnd Paved Areas
(Gravel Footpaths
& Timber Edgings)
1. Self-setting gravel surfacing shall beBreedon Golden Amber Gravel as supplied
by Messrs. Breedon and Cloud Lime Works
Ltd., or a similar approved material. The
gravel shall be evenly spread and
compacted by 8 passes of a 700-1300 kg
per metre width, pedestrian controlled dead
weight roller and have a finished thickness
of 50mm. Further compaction shall be
carried out applying water to the rollers, until
a well-bonded surface finish is obtained to
the satisfaction of the Project Manager. Anyareas where segregation occurs shall be
blinded with fine material and re-rolled. The
surface shall be allowed to dry before being
trafficked.
2. Timber edging and supporting stakes
shall be band sawn, knot free softwood
which shall be certified to have been
pressure creosoted with a net retention of
creosote in the timber of not less than 160kg
per cubic metre. Edgings shall either be
fixed and supported by wood stakes or laidand bedded in concrete class ST3 as shown
on the Drawings.
It is worth taking these subclauses forward, though
they may need to be split
into a Gravel AR and a
Timber Edging AR, with
the latter merged with
1114AR above. Remove /
amend (as appropriate)
reference to specific
supplier.
Timber edging is already
part of a previous sub
clause. The sub clauses
need to be combined.
1171 AR Footway
And Paved Areas
(Flexible
Surfacing)
Unless specified otherwise in the Package
Order the following shall apply:
General
1. Flexible surfacings shall be laid to levels
and crossfalls as agreed with the
Overseeing Organisation and materials shall
be laid in accordance with the appropriate
Clauses in the 700, 800, 900 and 1100
This sub clause has the
same title as 1105.
These sub clauses need
to be reviewed against
1105 and 1105AR to
either create an AR to
clause 1105 or keep
separate with an
7/21/2019 120612 Standard Specification Stage2 Interim Report Appendices
44/64
Appendix 3 Series 1100 - Footways and Paved Areas
43STANDARDISED SPECIFICTION AND STANDARD DETAILS
JUNE 2012
Clause Reason for Variation Relevance
Series and comply with the following:-
Sub-base
2. Granular sub-base material in footways
and paved areas shall be Type 1 granular
material and comply with the requirements
of Clause 803 or Class 6F3 granular fill
(planings, etc) to comply with the
requirements in Table 6/1. In situ concrete
sub-base material in footways and paved
areas shall be Mix ST1 concrete and comply
with the requirements of Clause 2602. Sub-
base material shall be laid to the thickness
as described in the Contract.
Asphalt Concrete Binder Course
3. Binder course shall be 20mm maximum
size aggregate dense binder course
complying with the requirements of BS EN
13108-1 with paving grade bitumen, grade
160/220, laid to the thickness as described
in the Contract.
Asphalt Concrete Surface Course
4. Surface course shall be 6mm maximumsize aggregate dense surface course
complying with the requirements of BS EN
13108-1 with paving grade bitumen, grade
160/220, laid to the thickness as described
in the Contract.
Hot Rolled Asphalt Surface Course
5. Surface course shall be 14mm maximum
size aggregate hot rolled asphalt surface
course complying with the requirements of
BS EN 13108-4 with paving grade bitumen,
grade 40/60, type F mixture, designation
55/14F, laid to the thickness as described in
the contract.
Sand Asphalt Surface Course
6. Surface course shall be 2mm maximum
size aggregate hot rolled asphalt surface
course complying with the requirements of
BS EN 13108-4 with paving grade bitumen,
grade 40/60, type F mixture, designationO/2F, laid to the thickness as described in
the Contract.
amendment to the title.
Tables would need to be
extracted and included in
the sub clause.
7/21/2019 120612 Standard Specification Stage2 Interim Report Appendices
45/64
Appendix 3 Series 1100 - Footways and Paved Areas
44STANDARDISED SPECIFICTION AND STANDARD DETAILS
JUNE 2012
Clause Reason for Variation Relevance
Regulating Course
7. Regulating course material shall be made
and laid in accordance with the requirementsfor one or other of the surface course or
binder course materials as described in the
Contract.
Limestone and Basalt Aggregate in Surface
Course
8. The use of limestone and basalt
aggregate in the surface course will not be
permitted.
1172AR FootwaysAnd Paved Areas
(Stone Setts)
1. Stone setts shall be set with lengths atright angles to the street and well rammed
as they are laid. They shall be laid in
regular, straight and properly bonded
courses from side to side with close joints
(12 to 15 mm) which must be kept perfectly
clear to receive the bitumen and cement
grouts. The joints shall be racked with
clean, dry, single sized 10 mm gritstone
chippings and grouted with hot bitumen (50
pen) to within 25 mm of the top of the joints.
The remainder of the depth shall be filledwith 3:1 sand/cement mortar and flush
pointed.
2. Second hand stone setts may be provided
by the Overseeing Organisation. Second
hand stone setts shall be sorted by the
Contractor to comply with the bonding
requirements in 1 above.
3. Where stone setts are to be laid in hard
margins, the chippings and hot bitumen
grout shall be replaced with semi-dry 3:1sand/cement mortar.
4. Second hand stone setts can be of either
Yorkstone or granite and shall be laid to a
pattern specified by the Overseeing
Organisation. The pattern of work adjacent
to gullies chambers and other obstructions
shall be agreed with the Overseeing
Organisatio