8
Simandou SEIA Volume I Mine Annex 7C 7C-1 7C Noise Design Assumptions and Source Data 7C.1 Mine Construction Predicted noise levels at the nearest noise sensitive receptors from construction activities have been modelled and presented as noise contours and these are used to identify settlements that have potential to be significantly affected by noise during the construction of the mine. Construction activity is focussed on the processing and infrastructure area (pre-production development in the pits is treated as part of mine operations) and has been separated into two main phases – Earthworks and General Construction and comprising the following activities. Earthworks: clearing and site preparation for all areas including the rail loop; heavy earthworks, levelling, battering; and pre-loading and ground treatment. General Construction: assembly and erection of the crushing and screening plant; assembly of stackers and reclaimers; conveyor assembly and commissioning; construction of facilities, services, and infrastructure; and track laying on the rail loop. As detailed construction teams and methods are not known, a simplified approach has been adopted of applying an overall sound power level for typical construction teams for the Earthworks and General Construction scenarios. A Sound Power Level (SWL) of 121 dBA for Earthworks and 114 dBA for General Construction has been applied throughout the site in the construction noise calculation. 7C.2 Mine Operations 7C.2.1.1 Overview The mine at Simandou will comprise two open pits using conventional drill, blast, load and haul methods. Each of the Ouéléba and Pic de Fon pits will have primary crushers located within the active mining area and a secondary crusher at the head of the conveyors connecting the pits to the mine plant area. Ore will be transported from each pit via an overland conveyor to the mine plant area where it will be processed by tertiary crushing and screening, before being transported to the stockyard by conveyor and then loaded onto trains. The locations of the principal noise sources for the mining, processing, materials handling and rail loading areas are shown in Figure 7C.1 and described below. 7C.2.1.2 Mining Area Before ore extraction can commence a hard cap over the ore bodies will be removed by drilling and blasting to expose the more friable ore material. Ore will then be extracted from the working face and hauled to crushers located within the pits. After crushing the ore will be transported via overland conveyors to the mine plant area. The following equipment and processes are modelled: pre stripping and clearing - dozers, excavator / shovels, haul trucks; overburden removal, haulage to and deposit in waste emplacements – excavator / shovels, haul trucks dozers; drilling and blasting of ore and haul to primary crusher;

7C Noise Design Assumptions and Source Data 7C.1 · PDF file7C Noise Design Assumptions and Source Data ... of 121 dBA for Earthworks and 114 dBA for General ... to expose the more

  • Upload
    vanliem

  • View
    222

  • Download
    3

Embed Size (px)

Citation preview

Simandou SEIA Volume I Mine Annex 7C

7C-1

7C Noise Design Assumptions and Source Data 7C.1 Mine Construction Predicted noise levels at the nearest noise sensitive receptors from construction activities have been modelled and presented as noise contours and these are used to identify settlements that have potential to be significantly affected by noise during the construction of the mine. Construction activity is focussed on the processing and infrastructure area (pre-production development in the pits is treated as part of mine operations) and has been separated into two main phases – Earthworks and General Construction and comprising the following activities. Earthworks:

clearing and site preparation for all areas including the rail loop; heavy earthworks, levelling, battering; and pre-loading and ground treatment.

General Construction:

assembly and erection of the crushing and screening plant; assembly of stackers and reclaimers; conveyor assembly and commissioning; construction of facilities, services, and infrastructure; and track laying on the rail loop.

As detailed construction teams and methods are not known, a simplified approach has been adopted of applying an overall sound power level for typical construction teams for the Earthworks and General Construction scenarios. A Sound Power Level (SWL) of 121 dBA for Earthworks and 114 dBA for General Construction has been applied throughout the site in the construction noise calculation. 7C.2 Mine Operations 7C.2.1.1 Overview The mine at Simandou will comprise two open pits using conventional drill, blast, load and haul methods. Each of the Ouéléba and Pic de Fon pits will have primary crushers located within the active mining area and a secondary crusher at the head of the conveyors connecting the pits to the mine plant area. Ore will be transported from each pit via an overland conveyor to the mine plant area where it will be processed by tertiary crushing and screening, before being transported to the stockyard by conveyor and then loaded onto trains. The locations of the principal noise sources for the mining, processing, materials handling and rail loading areas are shown in Figure 7C.1 and described below. 7C.2.1.2 Mining Area Before ore extraction can commence a hard cap over the ore bodies will be removed by drilling and blasting to expose the more friable ore material. Ore will then be extracted from the working face and hauled to crushers located within the pits. After crushing the ore will be transported via overland conveyors to the mine plant area. The following equipment and processes are modelled: pre stripping and clearing - dozers, excavator / shovels, haul trucks; overburden removal, haulage to and deposit in waste emplacements – excavator / shovels, haul trucks

dozers; drilling and blasting of ore and haul to primary crusher;

Simandou SEIA Volume I Mine Annex 7C

7C-2

in-pit processing and transport - crushers and in pit conveyors (up to approximately 3 km); and transport to mine plant area by overland conveyor including transfer stations en route. 7C.2.1.3 Mine Plant Area Further processing will be carried out in the mine plant area and the ore transported to the mine stockyard by overland conveyor. The following equipment and processes are included: crushing plant; transfer stations; transfer conveyors; conveyor drives; and overland conveyors to stockyard. 7C.2.1.4 Stockyard and Rail Loading Facility The mine stockyard and rail loading area will include the following significant noise sources: 2 reclaimers and 3 stackers; stacking and reclaim conveyors; load out and transfer conveyors; transfer shuttles; transfer stations enclosed / open; and train loadout facility. 7C.2.2 Fixed and Mobile Equipment Design Expectations The following specifications have been adopted in calculating noise emissions from the operational phase of the Mine, for both the daytime and night-time periods: mobile equipment will be of relatively new technology:

AC electric drive diesel powered haul trucks;

incorporating noise suppression typical of modern mining equipment in shovels, excavators, drills,

graders, front end loaders and dozers; and

all equipment achieves the design sound power levels used in the noise model, presented in Table 7C.1.

fixed plant includes reasonable noise mitigation / design commensurate with the project scope and aligned with Rio Tinto’s Company Standards; and

items such as conveyors and conveyor drives are designed such that they do not emit tonal noise or induce harmonics.

7C.2.3 Power Station The power station will operate continuously for 365 days per year and will include the following significant noise sources: the power plant will have a 100 MW capacity with an additional 20 MW reserve; diesel fuelled and will be situated near the rail spur before the rail loop to the North of the stockyard; and all units are 5 MW units.20 units running at any one time.

Foma

Touréla

Kankoro

Banko

CangaEast

Camp

Mandou

Orono

LamandouMoribadou

Mamouroudou

Korèla

Wataférédou II

Wataférédou ITraoréla Siatouro

505000

505000

510000

510000

515000

515000

520000

520000

9400

00

9400

00

9450

00

9450

00

9500

00

9500

00

9550

00

9550

00

9600

00

9600

00

Client: Taille: Titre:

Date: 07/06/2012

Dessiné par: WB

Vérifié par: RL

Approuvé par: KR

Projet: 0131299

Echelle: Barre d’echelle

Légende:

Figure 7C.1Vue d'ensemble des source de bruit /Noise Sources Overview

Usine et infrastructures minières /Mine Plant & Infrastructure

Contour de mine / Mine OutlineTerril de stériles /Waste EmplacementProjet de route de la mine /Proposed Mine RoadZone de stockage d'explosifs /Explosives Storage AreaZone d'exclusion autour de lazone de stockage d'explosifs /Explosives Area Clearance Zone

Dépôt de carburant / Fuel Farm

Localisation de la base de vie / Camp Location

Centrale électrique / Power StationTracé indicatif de la voie ferrée / Indicative Rail AlignmentAgglomération / Settlement

Route principale / Primary Road

Route secondaire / Secondary Road

Route tertiaire / Tertiary Route

Cours d'eau / Watercourse

Forêt classée / Classified Forest

Projection: WGS 1984 UTM Zone 29N

File:

0131

299S

iman

douG

IS_IG

_CK\M

aps\E

RM\N

oise\M

ine\M

ay20

12_re

vision

s\Ann

ex_C

\mi_N

oise_

Noise

Sourc

es.m

xd

A4

0 2

kilomètres

Activités dans les fosses de mines / In-Pit Activities:- Forage / Drilling- Travail à l'explosif / Blasting- Excavateur, camions de chargement pelle / Excavator, Shovel Loading Trucks- Camions de transport / Haul Trucks- Broyage principale / Primary Crushing- Convoyeurs / Conveyors- OB, flotte de démembrement / OB, Stripping Fleet- Déblaiement par bulldozer / Clearing by Dozer- Transport aux terrils / Haul to DumpsRoutes de transport / Haul Roads:- Camions de transport déplaçant OB vers des terrils / Haul Trucks Moving OB to Dumps- Route de transport du minerai vers les broyeurs en fosse / Haul Roads Moving Ore to In Pit Crushers- Calibreur/Camion citerne pour la maintenance des routes / Graders/Water Cart for Road Maintenance- Equipement de soutien; camion citerne (carburant et lubrifiant), véhicules de service / Support Equipment; Fuel Trucks, Lube Trucks and Service Vehicles

Convoyeur / Conveyor

PIC de FON

OUÉLÉBA

Décharge surchargée / Overburden Dumps:- Déchargement des camions de transport / Unloading of Haul Trucks- Façonnage du sol au bulldozer (profilage) / Dozer Shaping Ground (Profiling)- Camion citerne / Water Cart

Centrale électrique / Power Station

- Chargement du chemin de fer / Rail Loading- Train / Train

Activités de stockage / Stockpile Activities:- Empilement / Stacking- Recupération / Reclaiming- Convoyeurs / Conveyors- Embase vibrante / Conveyor Drives

Infrastructure minière / Mine Infrastructure- Bureaux / Offices- Maintenance / Maintenance- Ateliers / Workshops

Activités de broyage et de filtrage/ Crushing and Screening activities:- Broyage secondaire / Secondary Crushing- Broyage tertiaire / Tertiary Crushing- Convoyeur / Conveyor Belt Transfer- Sac filtrant de dépoussièrage / Dedusting Baghouse- Embase vibrante / Conveyor Drives

Zone HME / HME Area:- Assemblage, maintenance et révision des équipements / Equipment Assembly, Maintenance and Overhaul

Décharge surchargée / Overburden Dumps:- Déchargement des camions de transport / Unloading of Haul Trucks- Façonnage du sol au bulldozer (profilage) / Dozer Shaping Ground (profiling)- Camion citerne / Water Cart

Phase mine / Mine StagesPhase 1 / Stage 1Phase 2 / Stage 2Phase 3 / Stage 3Phase 4 / Stage 4Phase 5 / Stage 5Phase 6 / Stage 6Phase 7 / Stage 7Phase 8 / Stage 8

G u i n e aG u i n e a

M a l iM a l i

S i e r r aS i e r r aL e o n eL e o n e

G u i n e a - B i s s a uG u i n e a - B i s s a uS e n e g a lS e n e g a l

C o t eC o t ed ' I v o i r ed ' I v o i r eL i b e r i aL i b e r i a

Simandou SEIA Volume I Mine Annex 7C

7C-4

7C.2.4 Ancillary Facilities Other non-mining infrastructure at the mine will include: a workshop, hard stand and heavy equipment assembly and maintenance area; pit workshops, stores and offices; and new internal and external site access roads. 7C.2.5 Noise Source Terms Source terms used in the noise model are shown in Table 7C.1. Table 7C.1 Modelled Design Sound Power Levels

Mine area Item Description Rated

Capacity Quantity

Unmitigated SWL dBA re 10-12 Watts

Mitigation Applied

Mitigated SWL dBA re 10-12 Watts

Ouéléba Pit & Pic de Fon Pit

Crushers 7700 tph 7000 tph

120

situated into bench and directed

towards pit

110

In pit Conveyor 90 dBA/ m -- 90 dBA/ m

In pit Conveyor Drive 600 kW 101 -- 101

Komatsu PC1250 Excavator

485 hp 6 116 -- 116

Komatsu PC8000 Excavator

2 900 hp 7 122 -- 122

LeTourneau L1850 FEL 2 000 hp 2 115 -- 115

CAT 777 Haul Truck 100 t 15 117 -- 117

Komatsu 830 E Haul Truck

220 t 6 116 -- 116

Komatsu 930 E Haul Truck

290 t 58 119 -- 119

Atlas Copco Pit Viper 8 120 120

ROC L8-25 Drill 2 117 -- 117

CAT 992G FEL 900 hp 115 -- 115

Dozer D11T (average reversing and pushing)

4 119 -- 119

Dozer D10T (average reversing and pushing)

4 114 -- 114

CAT 844H RTD 2 114 -- 114

CAT 329 rockbreaker 2 118 118

CAT 777 Lube Truck 100 t 4 116 -- 116

CAT 24M Grader 2 112 -- 112

CAT 16M Grader 3 106 -- 106

CAT 777F Water Cart 4 117 -- 117

Simandou SEIA Volume I Mine Annex 7C

7C-5

Mine area Item Description Rated

Capacity Quantity

Unmitigated SWL dBA re 10-12 Watts

Mitigation Applied

Mitigated SWL dBA re 10-12 Watts

Mine plant area

Crushing plant 2 000 tph 115 115

Crushing plant 3 000 tph 112 112

Scalping screening plant

4 800 tph 4 112 112

Transfer conveyors 88 dBA/m 88 dBA/m

Transfer station 100 100

Stockyard Stacker 9 300 tph 3 (2

operating) 110 -- 110

Reclaimer 6 600 tph 2 111 -- 111

Reclaim conveyor 1 800 kw 89 dBA/m -- 89 dBA/m

Stacking conveyors 300 89 dBA/m -- 89 dBA/m

Transfer conveyor 400 89 dBA/m -- 89 dBA/m

Transfer station 100 100

Train loading (material) 103 -- 103

Loco during loading cycle

Lw calculated based on Locomotive achieving RT locomotive specification at various notch settings

89 dB(A) at 100ft (33m)

Power station

Engine generator -- Enclosed/

design to meet 70 dBA at 95m

--

Other Workshop 103 -- 103

HME 103 103

Belt shop 103 -- 103

All Areas Conveyors Capacity Idler Roll

Type Belt speed

SWL dBA re 10-12

Watts

Standard Stockyard Conveyor (open sided or covered)

7 700 tph Steel 4.4 m/s 89 dBA/m

Standard Coarse Ore Conveyor (open sided or covered)

7 700 tph Steel 3.5 m/s 88 dBA/m

All Areas Conveyor Drives Capacity

Standard Conveyor Drives

≤450 kW -- 100

630 kW -- 101

800 kW -- 103

1 000 kW -- 104

Simandou SEIA Volume I Mine Annex 7C

7C-6

Mine area Item Description Rated

Capacity Quantity

Unmitigated SWL dBA re 10-12 Watts

Mitigation Applied

Mitigated SWL dBA re 10-12 Watts

1 200 kW 105

Sources: AMC Phase 2 PEA LOM Schedule Revision 2E Mechanical Equipment List Module: Ore Handling Plant (Fluor Document A4RG-PL2000-55LI-001/ RT Doc SIM-2000-M-LST-00018 Fluor doc A4RG / SIM-9000-F-DC-00053 – Process Design Criteria RT Doc RTIO-SIM-9000-F-DC-00053

7C.2.6 Conformance Levels and Specifications Some items of plant consist of many components, and for the complete item to “conform” with a design emission level (sound power level), the component items will need to meet “specific” sound power levels. Hence the source terms for these items are referred to a “conformance specification” which is reliant upon the individual “item specifications”. Conformance specifications will be developed for conveyor drives, conveyors, reclaimers and stackers including conveyor idlers, belts, frames and frame spacing and stacker / reclaimer belts, idlers, long travel drives, boom drives, luffing and slewing mechanisms. Some further details are provided below. 7C.2.6.1 Idler Rolls Idlers will meet the following specifications so that the conveyor can achieve the conformance specification. The specified idler-roll surface profile upper limiting criteria for the idler-roll surface profile parameters are shown in Table 7C.2. Table 7C.2 Idler-Roll Surface Profile Upper Limiting Criteria

Criterion Surface Profile Parameter Upper Limit

TIR Total indicator runout 600 m (pk-pk)

MIS Maximum Indicated Slope (per 6o of idler rotation) 60 m

Notes: Total Indicator Runout - The Total Indicator Runout (TIR) is the peak to peak variation in roll eccentricity and out of round, measured in micrometers. Maximum Indicated Slope - The Maximum Indicated Slope (MIS) is defined for the purpose of this Specification as the maximum indicated runout per 6° of idler-roll rotation. Note that manual measurements of the MIS may be conducted using a similar test rig to that traditionally used to measure the TIR. The indicated runout displacements shall be determined from a continuous measurement around the idler-roll circumference. The largest difference in the indicated runout for any 6° of idler roll rotation yields the MIS measured in micrometers.

7C.2.6.2 Idler-Roll Self Noise The total sound power emission level of each idler-roll will not exceed the levels shown in Table 7C.3 at the design idler-roll rotational speed. This sound power level relates to the noise emission of each idler-roll operating in isolation from other conveyor components. Table 7C.3 Idler- Roll Self Noise Sound Power Level

Idler-Roll Length Range Overall Sound Power Level (dBA re 1 W)

500 mm - 800 mm 68 dBA

801 mm – 1 100 mm 69 dBA

1 101 mm – 1 500 mm 70 dBA

Simandou SEIA Volume I Mine Annex 7C

7C-7

7C.2.6.3 Idler Frame Spacing Idler frames are built in standard modules illustrated in Figure 7C.2, consisting of variable spacing to minimise the occurrence of harmonics throughout the conveyor’s length. Figure 7C.2 Idler Frame Spacing

7C.3 Blasting Emissions The blast design information contained in Table 7C.4, developed during the Preliminary Engineering Assessment, has been used to inform the blasting assessment. Table 7C.4 Blasting Data

Design Parameter Production Development

Number of holes per blast 200 200

Number of rows per blast 10 10

Average volume per blast 169 213 16 696

Average tonnage per blast 507 509 50 074

MIC (> 8 milliseconds) 515 60

Normal blast management practices will be applied to reduce overpressure and are taken into account in the assessment.

Simandou SEIA Volume I Mine Annex 7C

7C-8

7C.3.1.1 Blast Design All blastholes will be stemmed with an appropriate packing material in order to contain the explosive

gases, achieve an efficient blast and better fragmentation of the rock.

The Maximum Instantaneous Charge (MIC) (ie the maximum mass of explosive detonated in any 8 ms period throughout the blast) will be selected to ensure the relevant criteria are net for example by reducing the number of holes fired at any one time.

Halving the MIC will reduce the airblast level by 1 dB to 3 dBZ. All blasts at the site will be monitored.

Blast designs will be recorded for all individual blast events and the data used with the monitoring results

to assist in the design and optimisation of future blasting and to provide information in case of incident or complaint.

For the purposes of blast emission monitoring, the mine will follow the requirements of AS 2187.2-2006, “Explosive Storage, Transport and Use - Appendix J”. The Blast Emissions Summary Record will record for each blast. Blast Number. Block or Area ID. Date and Time of blast. Shot Type. Centroid of Blast (X,Y,Z coordinates in a referenced mapping system). Distance from the blast to the monitoring locations. MIC (kg). Peak Airblast Level, dB (Lin). Vibration Level, mm/s.