8th Project Steering Committee Meeting ADB Funded
Second Integrated Road Investment Program (iRoad 2)26 August 2019
1
iRoad 2 Map
18/09/2019 3
Tranching Plan
Tranches1
(2017)2
(2018)3
(2019)4
(2020)5
(2021)Total
Amount (U$S Mn)
150 150 200 200 200 900
Tranche 1 loan signed and effective.Tranche 2 in processing.
Province Packages Length (km) Approximate Cost(LKR Mn)
Northern 17 1,060 47,115(Recommended for award)
Eastern 11 845 31,075(Awarded –
Total Contract Sum)
Uva 15 1,045 33,300(Awarded –
Total Contract Sum)
Western 10 700 24,535
Total 53 3,650 136,025
18/09/2019 4
Proposed Road Lengths and Tentative Estimated Cost
18/09/2019 5
Present Status – Overall - Civil Works
Province Status
Uva Works in progress (15 contracts)
Eastern Contracts awarded (11 contracts). Agreements signed. Contractor mobilization
Northern 5 contracts awarded on 20 Aug 2019. balance 12 contracts, awaiting ADB concurrence for award. Expected to be awarded in September 2019.
Western Bids invited. Closing 05 September 2019. expected to be awarded in November 2019.
Overall Status of Rural Road Packages – Uva ProvvinceDistrict No. of
PackagesNo. of Roads
Km Asphalt completed
length
Physical Progress as at 31 May 2019
Planned (%) Actual (%)
Badulla 08 153 555 21 35.9 19.5
Monaragala 07 96 489 90 36.5 31.6
Total 15 249 1,044 111 36.2 25.2
18/09/2019
Expenditure – 2019 – iRoad 2 Program
No Description LKR (Mn)
1 Budget Allocation 8,000
2 Expenditure as at 20 August 2019 3,890
3 % Financial achievement 49%
1. Poor performance of contracts in Uva provincei. Komuthi – HCM JVii. CNTIC – RDCE JV iii. CML – MTD Construction iv. Tissa – PND JV
18/09/2019 8
Issues
Project Steering Committee Meeting -10
PMU/ PIC 6 – iRoad 2 Uva Province
26 August 2019
Road Development AuthorityAsian Development Bank
Project Profile : iRoad Uva Province
Total Cost : Rs. 33.3 bn.
Total Length : 1046 km. (249 nos. of roads)
Packages : 15 Packages ; Badulla 8 nos. & Monaragala 7 nos
Location : Badulla & Monaragala Districts ( MC- 1,UC-2,PS-17)
26 DS Divisions, 475 GN Divisions
Date of Commencement : 20th July 2018
Date of Completion : 19th June 2020
Contractors : (BA) NEM, KOM, CML – MTD (3), CNTIC – RDCE (2), Tissa –PND
(MO) AMSK – CGGC, Tudawa (3), Maga, CML- MTD, Hovael
Consultant : PEC – CEA JV10
Overall Physical Progress
11
Contract
PackageContractor
Original
Planned
Progress %
Revised
Planned
Progress %
Actual
Progress %
Actual /
Planned %
(Original)
Actual /
Planned %
(Revised)
BA-01 NEM 49.63 39.6 80% -
BA-02 KOMUTHI-HCM JV 51.00 18.3 36% -
BA-03 CML-MTD 36.92 25.03 12.18 33% 49%
BA-04 CNTIC-RDCE JV 46.94 13.74 29% -
BA-05 CNTIC-RDCE JV 34.00 22 19.4 57% 88%
BA-06 CML-MTD 46.46 32.81 16.56 36% 50%
BA-07 CML-MTD 46.22 30.45 18.46 40% 61%
BA-08 TISSA-PND JV 44.43 29.3 17.55 40% 60%
MO-01 AMSK-CGGC JV 50.77 32.98 31.13 61% 94%
MO-02 TUDAWE 53.39 38.48 34.37 64% 89%
MO-03 MAGA 39.65 38.6 97% -
MO-04 CML-MTD 44.24 22.54 51% -
MO-05 TUDAWE 52.54 39.52 33.47 64% 85%
MO-06 HOVAEL 56.69 28.55 30.13 53% 106%
MO-07 TUDAWE 52.81 32.39 31.31 59% 97%
12
Month June July August
Target % 5.71 6.28 6.26
Actual % 2.65 3.34
Slipage % 3.06 2.94
22 %
47.05%
25.16 %
13
Month June July August
Target % 5.74 6.5 6.39
Actual % 1.62 3.8
Slipage % 4.12 2.7
25%
44.45 %
19.47 %
14
Month June July August
Target % 5.67 6.04 6.26
Actual % 3.83 3.64
Slipage % 1.84 2.4
18.4%
50.01 %
31.65 %
15
Overall Financial Progress of the Project
June 2019 July 2019 Cumulative %
BA 1 NEM Construction (Pvt.) Ltd 2,056 84 143 488 23.72
BA 2 Kumuthi - HCM Engineering JV 2,263 17 19 290 12.81
BA 3 CML – MTD Construction Limited 2,459 19 - 306 12.46
BA 4 CNTIC – RDCE JV 2,119 13 - 246 11.62
BA 5 CNTIC – RDCE JV 2,505 - 23 292 11.67
BA 6 CML – MTD Construction Limited 2,346 40 21 346 14.73
BA 7 CML – MTD Construction Limited 2,461 38 30 386 15.68
BA 8 Tissa Builders (Pvt.) Ltd – PND JV 1,848 10 27 249 13.45
MO 1 AMSK – CGGC JV 2,241 16 31 537 23.95
MO 2 Tudawe Brothers (Pvt.) Ltd 1,892 62 115 486 25.66
MO 3 Maga Engineering (Pvt.) Ltd 2,201 52 204 817 37.10
MO 4 CML – MTD Construction Limited 2,274 - 32 406 17.87
MO 5 Tudawe Brothers (Pvt.) Ltd 2,057 35 133 489 23.79
MO 6 Hovael Construction (Pvt.) Ltd 2,713 59 110 667 24.59
MO 7 Tudawe Brothers (Pvt.) Ltd 1,858 79 41 375 20.16
TOTAL 33,293 523 928 6,379 19.28
including 2nd mobilization Advance
Expenditure (Rs Mn)Contract
Sum (Rs Mn)Package Name
Package
No
16
Total Financial S-Curve – Uva Province
RS. 10 bn
Rs.6.4 bn.
Rs. 3.6 bn
17
June 2019 July 2019 Cumulative %
BA 1 NEM Construction (Pvt.) Ltd 2,056 84 143 488 23.72
BA 2 Kumuthi - HCM Engineering JV 2,263 17 19 290 12.81
BA 3 CML – MTD Construction Limited 2,459 19 - 306 12.46
BA 4 CNTIC – RDCE JV 2,119 13 - 246 11.62
BA 5 CNTIC – RDCE JV 2,505 - 23 292 11.67
BA 6 CML – MTD Construction Limited 2,346 40 21 346 14.73
BA 7 CML – MTD Construction Limited 2,461 38 30 386 15.68
BA 8 Tissa Builders (Pvt.) Ltd – PND JV 1,848 10 27 249 13.45
SUB TOTAL 18,056 220 261 2,602 14.52
Package
NoPackage Name
Contract
Sum (Rs Mn)
Expenditure (Rs Mn)
Overall Financial Progress of the Project - Badulla
18
Total Financial S-Curve – Badulla District
Rs.
2.62bn.
19
Overall Financial Progress of the Project - Monaragala
June 2019 July 2019 Cumulative %
MO 1 AMSK – CGGC JV 2,241 16 31 537 23.95
MO 2 Tudawe Brothers (Pvt.) Ltd 1,892 62 115 486 25.66
MO 3 Maga Engineering (Pvt.) Ltd 2,201 52 204 817 37.10
MO 4 CML – MTD Construction Limited 2,274 - 32 406 17.87
MO 5 Tudawe Brothers (Pvt.) Ltd 2,057 35 133 489 23.79
MO 6 Hovael Construction (Pvt.) Ltd 2,713 59 110 667 24.59
MO 7 Tudawe Brothers (Pvt.) Ltd 1,858 79 41 375 20.16
SUB TOTAL 15,237 303 667 3,776 24.73
TOTAL 33,293 523 928 6,379 19.28
including 2nd mobilization Advance
Package
NoPackage Name
Contract
Sum (Rs Mn)Expenditure (Rs Mn)
20
Total Financial S-Curve – Monaragala District
Rs. 2.62
21
22
Summary of Asphalt Length , Structure Progress and Certified Amounts in Badulla District
Package NoTotal Asphalt Length Completed/km Total Number of
Structure
Completed/NosJune July Cumulative
BA-01 3.42 2.47 14.14 71
BA-02 - - - 31
BA-03 - - 0.48 25
BA-04 - - - 0
BA-05 - - - 23
BA-06 - - 1.34 23
BA-07 - - 1.78 26
BA-08 0.5 1.6 3.6 8
TOTAL 3.92 4.07 21.34 207
23
Summary of Asphalt Length , Structure Progress and Certified Amounts in Monaragala District
Package NoTotal Asphalt Length Completed/km
Total Number of
Structure
Completed/NosJune July Cumulative
MO-01 1.47 1.62 11.12 44
MO-02 4.75 2.41 12.29 94
MO-03 - 2.28 11.43 74
MO-04 - - 5.02 27
MO-05 2.82 3.37 13.4 54
MO-06 6.3 7.18 26.58 91
MO-07 3.31 1.7 10.44 59
TOTAL 18.65 18.56 90.28 443
24
CONTRACT PACKAGE : RDA/ADB/iROAD-2(UVA)/NCB/BA-01
Contractor : NEM Construction (Pvt) Ltd
Total Length / Number of Roads : 57.97 km/ 14nos. of roads ( 10 nos. started )
District : Badulla
Divisional Secretaries : Mahiyangana & Ridimaliyadda
Accepted Contract Amount : RS. 2,055,896,627.63
Construction Period : 730 Days
Commencement of Work at site : 20th
July 2018
Date of Completion (as per the contract) : 19th
June 2020
Physical Progress – BA-01 (NEM)
25
Cumulative
Planned (%)
Cumulative
Achieved (%)
49.63 39.60
Financial Progress23.72 %
Shoulder construction UBA 005 at
CH.6+100
BA-01
2019/07/182019/07/25
Safety arrangement UBA002 at
CH.2+722
27
CONTRACT PACKAGE : RDA/ADB/iROAD-2(UVA)/NCB/BA-02
Contractor : Komuthi – HCM Engineering JV
Total Length : 82.57 km/ 20 nos. of Roads (13 no. Started )
Accepted Contract Amount : RS. 2,262,823,158.00
Project Period : 730 Days
Commencement of Work at site : 20th
July 2018
Date of Completion (as per the contract) : 19th
July 2020
28
Physical Progress – BA-02 (Komuthi-HCM JV)
Cumulative
Planned (%)
Cumulative
Achieved (%)
51.00 18.30
Financial Progress12.8% %
29
1. Progress remains very poor
2. 2 Rate of Progress notifications issued. Second one on 28 June.
3. Revised WP received and monitored in July and August before a Notice to Correct can be issued after which, termination may be considered.
4. No asphalt to date
5. Clearly have severe cash flow problems
6. Staff turnover is alarmingly high
a) 5th PM
b) 2 DPM have left
7. CR has insufficient authority and has difficulty compiling a revised programme
A Rate of Progress notification was issued on 28 June. Progress must
now be monitored closely in August and September and, if it fails to
improve, a Notice to Correct will be issued after which termination may
be considered in early October
30
Sub Base Overlaying
UBA295 at CH.2+700 to 2+750
BA-02
Road Edge Widening Works
UBA 095 at CH.1+200 - 1+400 (LHS)
2019/07/04 2019/07/17
31
CONTRACT PACKAGE : RDA/ADB/Iroad-2(UVA)/NCB/BA03
Contractor : CML-MTD Construction Ltd
Total Length : 80.58 km/ 36 nos. of Roads ( 6 nos. started )
Accepted Contract Amount : RS. 2,458,963,395.33
Project Period : 730 Days
Commencement of Work at site : 20th July 2018
Date of Completion : 19th July 2020
Physical Progress – BA-03 (CML-MTD)
32
Original
Cumulative
Planned (%)
Revised
Cumulative
Planned (%)
Cumulative
Achieved
(%)
36.92 25.03 12.18
Financial Progress12.46%
1. Site work stopped in late May but slowly resuming from August with the return of certain machines.
2. PM resigned in July, however some new staff have arrived in the last week
3. 0.09% progress in July.
4. Insufficient site staff and poor staff retention.
5. Progress has fallen sharply to 49% of revised programme.
6. Escrow Account Established
7. Field labs to be established.
8. Env. and social safeguards and Routine maintenance recommenced.
9. ROP issued 23 July 2019
33
Revised programme approved, must be monitored closely in September
and October. Further contractual action may be taken in November if he
falls behind again. Termination may be considered in November.
34
CONTRACT PACKAGE : RDA/ADB/i-ROAD-2(UVA)/NCB/BA04
Contractor : CNTIC-RDCE Joint Venture
Total Length : 66.13 km /20 Nos. of roads ( 9 nos. started )
Accepted Contract Amount : RS. 2,118,733,738.12
Project Period : 730 Days
Commencement of Work at site : 20th
July 2018
Date of Completion (as per the contract) : 19th
July 2020
Physical Progress – BA-04 (CNTIC-RDCE JV)
35
Cumulative
Planned (%)
Cumulative
Achieved (%)
46.94 13.74
Financial Progress11.62%
1. 2 Notice to Correct, 1 Rate of Progress notification issued.
2. Second Notice to Correct was issued on 22 June,was satisfied on 1 August and withdrawn. The first NTC remains in place.
3. Actual progress and resources improved considerably in July
a) Site establishment increased from 20% to 54%
b) Plant on site increased from 22% to 56%.
c) Design increased from 66% to 89%.
4. No asphalt laid to date
36
Due to the repeated meetings with the JV partner directly involved in site activities.
There was a considerable improvement in performance in July, which resulted in
withdrawal of the second Notice to Correct. However, the first Notice to Correct
remains and progress will be monitored in September and October, carefully
following the revised programme approved in August.
If progress does not continue, Termination will be reconsidered in November.
37
Line drain base concreting at UBA 090 Concrete Demolishing works UBA 244
at CH.0+400
BA-04
2019/07/08 2019/07/08
38
CONTRACT PACKAGE : RDA/ADB/i-ROAD-2(UVA)/NCB/BA-05
Contractor : CNTIC - RDCE JV
Total Length : 79.35 km / 17 N0s. Of Roads ( 9 nos. started )
Accepted Contract Amount : RS. 2,504,966,968.06
Project Period : 730 Days
Commencement of Work at site : 20th
July 2018
Date of Completion : 19th
July 2020
Physical Progress – BA-05 (CNTIC-RDCE JV)
39
Original
Cumulative
Planned (%)
Revised
Cumulative
Planned (%)
Cumulative
Achieved
(%)
34.00 22.00 19.40
Financial Progress11.67%
1. Notice to Correct issued in February, however this was withdrawn in August following significantly improved performance in May, June and July
2. Achieved 88% progress of their revised accepted work programme
3. Contractor is taking steps to improve performance.
40
Due to the repeated meetings with the JV partner directly
involved in site activities. In conclusion, due to the Contractor’s
improved performance we do not recommend termination at this
stage.
BA-05
Culvert Construction at UBA
361 CH 2+414 (LHS)Lined Drain Construction at UBA 116
CH. 0+050-0+060 (LHS)
42
CONTRACT PACKAGE :RDA/ADB/i- ROAD-2(UVA) NCB/BA 06
Contractor : CML-MTD Constructions Ltd.
Total Length : 62.46 km / 11 nos. of Roads ( 4 nos. started )
Accepted Contract Amount : RS. 2,345,800,424.97
Project Period : 730 Days
Commencement of Work at site : 20th
July 2018
Date of Completion : 19th
July 2020
Physical Progress – BA-06 (CML-MTD)
43
Original
Cumulative
Planned (%)
Revised
Cumulative
Planned (%)
Cumulative
Achieved
(%)
46.46 32.81 16.56
Financial Progress14.73%
1. Permanent works stopped in late May but resumed in early August.
2. PM resigned in July.
3. 0.41% progress in July, however additional resources arrived on site late in the month (some from MO-04) and plant increase from 42% to 93%
4. Progress has fallen abruptly to 50% of revised programme.
5. Routine maintenance is ongoing.
6. Escrow Account Established
7. ROP issued on 23 July.
44
The Contractor is starting to focus his effort on this Contract. A
Rate of Progress notification was recently issued, and this will be
monitored carefully over the coming months. termination cannot
be considered at this stage.
BA-06
Gabion Wall Construction UBA 081 at
CH. 4.358 to 4+364 (LHS)
Edge Widening UBA 088 at
CH. 3+000 to 3+370 (LHS)
2019/07/30 2019/07/28
46
CONTRACT PACKAGE : RDA/ADB/i-ROAD-2(UVA)/NCB/BA-07
Contractor : CML – MTD Construction Ltd.
Total Length : 69.99 km/ 17 Nos.of Roads ( 5 nos. started )
Accepted Contract Amount : RS. 2,461,426,008.14
Project Period : 730 Days
Commencement of Work at site : 20th
July 2018
Date of Completion : 19th
July 2020
Physical Progress – BA-07 (CML-MTD)
47
Original
Cumulative
Planned (%)
Revised
Cumulative
Planned (%)
Cumulative
Achieved
(%)
46.22 30.45 18.46
Financial Progress15.68 %
1. Site work effectively stopped in late May and has not resumed.
2. PM resigned in July.
3. 0.1% progress in July.
4. Progress has fallen abruptly to 61% of revised programme.
5. Routine maintenance is still ongoing.
6. Status of Escrow Account remains unclear.
7. Site establishment was only 55% in June. Some plant has been removed from site. Some staff have been lost. No ABC on site. RoP issued on 23 July
48
A Rate of Progress notification was recently issued, and this will be
monitored carefully over the coming months. However, as the
Contractor has not abandoned the site and not issued a Notice to
Correct, termination may be considered in October.
49
Lined Drain with wall raising at
CH.2+990
BA-07
Concrete of Lined Drain Base at
CH.4+360
50
CONTRACT PACKAGE : RDA/ADB/iROAD-2(UVA)/NCB/BA-08
Contractor : TISSA-PND JOINT VENTURE
Total Length : 61.55 km / 18 nos. Roads ( 7 nos. started )
Accepted Contract Amount : RS. 1,847,725,581.60
Project Period : 730 Days
Commencement of Work at site : 20th
July 2018
Date of Completion : 19th
July 2020
Physical Progress – BA-08 (Tissa-PND JV)
51
Original
Cumulative
Planned (%)
Revised
Cumulative
Planned (%)
Cumulative
Achieved
(%)
44.43 29.30 17.55
Financial Progress13.45 %
1. Progress has improved since the Contractor apparently received additional financing on 19 July.
2. 2 Notice to Correct, 1 Rate of Progress issued.
3. Second Notice to Correct issued on 27 June but the Contractor failed to reach their target before 1 August.
4. Improvements on site since 19 July:
a) Increased stocks of ABC, embankment material, cement, hume pipes and sub-base/shoulder material.
b) Plant increased with the arrival of 2 excavators, 2 tippers, 1 motor grader, 2 concrete mixers and 1 water bowser
c) Manpower increased with the arrival of 1 Technical Officer, 1 works supervisor and 2 new structures gangs
52
The Contractor failed to reach the targets in their second Notice to Correct. As such, the
Employer is now entitled to terminate the Contract giving 14 days’ notice. However,
given the Contractor’s improved performance on site, suggest that the Employer may
wish to delay termination. The Engineer shall monitor further improvements closely in
August. Termination may be reconsidered in September.
53
Asphalt Layer Surface UBA 162 at
CH. 0+430
BA-08
Surface Preparation for Priming
Works UBA 076 at CH.1+100
2019/07/182019/07/31
54
CONTRACT PACKAGE : RDA/ADB/iROAD-2(UVA)/NCB/MO-01
Contractor : AMSK - CGGC Joint Venture
Total Length : 65.10 km / 10 nos. of Roads ( 5 nos. started )
Accepted Contract Amount : RS. 2,241,235,656.00
Project Period : 730 Days
Commencement of Work at site : 20th
July 2018
Date of Completion : 19th
July 2020
Physical Progress – MO-01 (AMSK-CGGC JV)
55
Original
Cumulative
Planned (%)
Revised
Cumulative
Planned (%)
Cumulative
Achieved
(%)
50.77 32.98 31.13
Financial Progress24 %
MO-01
Embankment construction UMO 031 at CH.11+900
Prime coat UMO-110 at CH.11+140
57
CONTRACT PACKAGE : RDA/ADB/i-ROAD-2(UVA)/NCB/MO-02
Contractor : Tudawe Brothers (PVT)LTD
Total Length : 63.46 km / 14nos.Roads ( 11nos. Started )
Accepted Contract Amount : LKR. 1,891,879,866.96
Project Period :730 days
Commencement of Work at site :20th
July 2018
Date of Completion :19th
July 2020
Physical Progress – MO-02 (Tudawe)
58
Original
Cumulative
Planned (%)
Revised
Cumulative
Planned (%)
Cumulative
Achieved
(%)
53.39 38.48 34.37
Financial Progress25.7 %
MO-02
Applying Botting material for Prime Surface
UMO-094 at CH. 04+800
Culvert wall concrete UMO-049
at CH. 1+142
2019/07/03 2019/07/22
60
Physical Progress – MO-03 (Maga)
61
Cumulative
Planned (%)
Cumulative
Achieved (%)
39.65 38.60
Financial Progress37.1 %
MO-03
Field density test at UMO-138Culvert deck reinforcement in
UMO-149 at CH.0+033
2019/07/252019/07/23
63
CONTRACT PACKAGE : RDA/ADB/i ROAD-2 (UVA)/NCB/MO-04
Contractor : CML-MTD Construction Ltd
Total Length : 65.85 km/12 nos. of Roads ( 4 nos. started )
Accepted Contract Amount : RS. 2,274,491,009.04
Project Period : 730 days
Date of Commencement : 20th
July 2018
Expected Date of Completion : 19th
July 2020
Physical Progress – MO-04 (CML-MTD)
64
Cumulative
Planned (%)
Cumulative
Achieved (%)
44.24 22.54
Financial Progress17.9 %
1. Works were abandoned in July.
2. PM resigned in July, Staff turnover is very high
3. Talks with bankers show no progress.
4. ROP issued on 23rd July
5. Routine Maintenance was stopped
6. Machineries and Materials at site which was paid were taken out of the site
7. The Engineer expressed his recommendation for termination of this Contract at a meeting with the Contractor on 9 August.
65
Termination was recommended by the Engineer on 2 August, But no, Notice to Correct was issued ref. to GCC 15.1The Engineer has informed that the NTC is not required.
Further action for termination ………
66
CONTRACT PACKAGE : RDA/ADB/Iroad-2(UVA)/NCB/MO-05
Contractor : Tudawe Brothers (PVT)LTD
Total Length : 64.15km / 12 nos. of Roads ( 8 nos. started )
Accepted Contract Amount : LKR. 2,056,797,645.36
Project Period : 730 days
Commencement of Work at site : 20th
July 2018
Date of Completion : 19th
July 2020
Physical Progress – MO-05 (Tudawe)
67
Original
Cumulative
Planned (%)
Revised
Cumulative
Planned (%)
Cumulative
Achieved
(%)
52.54 39.52 33.47
Financial Progress23.8 %
68
MO-05
Asphalt work in UMO-001
at CH.2+680
Safety Arrangement for Culvert
Construction UMO-006 at CH.4+646
2019/07/222019/07/23
69
CONTRACT PACKAGE : RDA/ADB/Iroad-2(UVA)/NCB/MO-06
Contractor :Hovael Construction (Pvt.) ltd
Total Length : 97.58 km / 16 nos. Roads ( 8 nos. started )
Accepted Contract Amount : RS 2,713,444,633.17
Project Period :730 days
Commencement of Work at site :20th
July 2018
Date of Completion :19th
July 2020
Physical Progress – MO-06 (Hovael)
70
Original
Cumulative
Planned (%)
Revised
Cumulative
Planned (%)
Cumulative
Achieved
(%)
56.69 28.55 30.13
Financial Progress24.6 %
MO-06
Sub base Laying UMO-068 at
CH.7+640 (B/S)
Shoulder Laying in UMO-022
at CH.4+500 (RHS)
2019/07/24 2019/07/24
72
CONTRACT PACKAGE : RDA/ADB/Iroad-2(UVA)/NCB/MO-07
Contractor : Tudawe Brothers (Pvt.) Ltd.
Total Length : 64.83km / 9 nos.of Roads ( 4 nos.
started )
Accepted Contract Amount : LKR. 1,858,087,457.19
Project Period : 730 days
Commencement of Work at site : 20/07/2018
Date of Completion : 20/07/2020
Physical Progress – MO-07 (Tudawe)
73
Original
Cumulative
Planned (%)
Revised
Cumulative
Planned (%)
Cumulative
Achieved
(%)
52.81 32.39 31.31
Financial Progress20.16 %
MO-07
Asphalt laying UMO-077 at CH.0+050 to 0+200
Deck concreting UMO-104 atCH. 3+467 (B/S)
2019/07/23 2019/07/25
75
Land Donation Summary
District
Number of Consent Letters
Number of MOU
Individual Common Individual Common
Badulla 288 0 0 0
Monaragala 404 0 0 0
Total 692 0 0 0
Utility Shifting
868
123
85
0 200 400 600 800 1000
Electricity Pole Shifting/(Nos.)
617
104
29
0 100 200 300 400 500 600 700
Telecom Pole Shifting/(Nos.)
90319
14893
16222
0 20000 40000 60000 80000 100000
Water Line Shifting/(m)
List of Utilities – Badulla District (up to 31 July 2019)
77
Package
Utilities to be Shifted
Electricity Pole/(Nos.) Telecom Pole/(Nos.) Water Line/(m)
Identifiedin
ProgressCompleted Identified
in Progress
Completed Identifiedin
ProgressCompleted
BA - 01 4 2 2 4 2 - - - -BA - 02 46 46 - - - - 10183 10183 -BA - 03 50 - - 100 - - - - -BA - 04 47 - - 26 - 26 973 - -BA - 05 43 - 43 14 14 - 14665 4620 10035BA - 06 43 - - 51 - - 25 -BA - 07 301 7 - 345 39 3 16638 - -BA - 08 15 - 2 7 - - 21172 - -Total 549 55 47 547 55 29 63656 14803 10035
List of Utilities – Monaragala District (up to 31 July 2019)
78
Package
Utilities to be Shifted
Electricity Pole/(Nos.) Telecom Pole/(Nos.) Water Line/(m)
Identifiedin
ProgressCompletedIdentified
in Progress
Completed Identifiedin
ProgressCompleted
MO - 01 45 - - 4 - - 5 - 3MO - 02 210 20 33 23 13 - 15070 - 4620MO - 03 23 19 4 12 12 - 1000 - -MO - 04 13 2 0 6 0 0 2784 - 450MO - 05 5 5 - 24 24 - 6570 - 170MO - 06 16 16 - 1 - - 1234 90 944MO - 07 7 6 1 - - - - - -
Total 319 68 38 70 49 0 26663 90 6187
79
Progress of the Safeguard Social ConsiderationEstablishment of Grievances Redressing Committees (GRCs) in Divisional Secretariat & Grama Niladhari Levels
Pro
vin
ce/
Dis
tric
tPackage
No.Name of the Contractor
Total No.
of DSDs
DSD LevelTotal No.
of GNDs
GND Level
Establishe
d
To be
EstablishedEstablished
To be
Established
Bad
ulla D
istr
ict
Uv
a P
rov
ince
BA - 01 NEM Construction Pvt Ltd 2 2 0 28 20 8
BA - 02Komuthi – HCM Engineering Joint Venture 3 3 0 34 18 16
BA - 03 CML-MTD Construction limited 3 2 1 52 9 43
BA - 04 CINTIC-RDCE Joint Venture 1 1 0 30 7 23
BA - 05 CINTIC-RDCE Joint Venture 2 2 0 47 28 19
BA - 06 CML-MTD Construction limited 2 2 0 35 18 17
BA - 07 CML-MTD Construction limited 2 2 0 36 15 21
BA - 08 TBC – PND Joint Venture 2 2 0 26 8 18
Mo
nara
gala
Dis
tric
t
Uv
a P
rov
ince
MO - 01 AMSK Constructions Pvt Ltd 3 3 0 28 20 8
MO - 02 Tudawe Brothers (Pvt) Ltd 3 3 0 29 29 0
MO - 03 Maga Engineering (Pvt) Ltd 2 2 0 21 20 1
MO - 04 CML-MTD Construction limited 3 2 1 20 18 2
MO - 05 Tudawe Brothers (Pvt) Ltd 3 3 0 30 12 18
MO - 06 Hovael Construction Pvt Ltd 3 3 0 32 24 8
MO - 07 Tudawe Brothers (Pvt) Ltd 2 2 0 27 27 0
Total 36 34 02 475 273 202
Note : There are 15 DS Divisions in Badulla district and 11 DS Divisions in Monaragala district. It was noted that two or three contract packages fall in one DS division. As a result, number of total DS Level GRC formed will exceed the total number of DS Divisions in Uva province.
80
District PackageNumber of Consent Letters Number of MOU
Individual Common Individual Common
Badulla
BA 01 1 0 0 0
BA 02 45 0 0 0
BA 03 41 0 0 0
BA 04 33 0 0 0
BA 05 11 0 0 0
BA 06 132 0 0 0
BA 07 25 0 0 0
BA 08 0 0 0 0
Sub Total 288 0 0 0
Monaragala
MO 01 101 0 0 0
MO 02 165 0 0 0
MO 03 15 0 0 0
MO 04 103 0 0 0
MO 05 9 0 0 0
MO 06 10 0 0 0
MO 07 1 0 0 0
Sub Total 404 0 0 0
Grand Total 692 0 0 0
Status of Land Donation (Up to 31 July 2019)
Summary of Public Complaints – Badulla District (up to 31 July 2019)
81
Dis
tric
t
Package No.
Name of the Contractor
No. of Public Complaints ReceivedNo.
Completely Settled
Solutions in ProgressRequests Suggestions Complaints
Crack Related Issues
Bad
ulla
BA - 01NEM Construction Pvt Ltd 7 - 2 - 8 1
BA - 02Komuthi – HCM Engineering Joint
Venture45 5 2 1 14 39
BA - 03 CML-MTD Construction limited 20 0 2 - 8 14
BA - 04 CINTIC-RDCE Joint Venture 12 1 3 - 5 11
BA - 05 CINTIC-RDCE Joint Venture 22 1 2 - 17 8
BA - 06 CML-MTD Construction limited 29 0 7 - 26 10
BA - 07 CML-MTD Construction limited 20 2 5 - 9 18
BA - 08 TBC – PND Joint Venture 8 0 0 0 1 7
Total 163 9 23 1 88 108
Summary of Public Complaints – Monaragala District (up to 31 July 2019)
82
Dis
tric
t
Package No.
Name of the Contractor
No. of Public Complaints ReceivedNo.
Completely Settled
Solutions in ProgressRequests Suggestions Complaints
Crack Related Issues
Mo
nar
agal
a
MO - 01AMSK Constructions Pvt Ltd 28 - - - 14 14
MO - 02Tudawe Brothers (Pvt) Ltd 92 0 0 3 94 1
MO - 03 Maga Engineering (Pvt) Ltd 33 1 2 - 19 17
MO - 04 CML-MTD Construction limited 22 0 3 - 10 15
MO - 05 Tudawe Brothers (Pvt) Ltd 39 4 8 - 24 27
MO - 06 Hovael Construction Pvt Ltd 27 0 1 - 25 3
MO - 07 Tudawe Brothers (Pvt) Ltd 30 0 12 - 16 26
Total 271 5 26 3 202 103
Asian development Bank funded second integrated roads Investment Program –Eastern Province
Project steering committee Meeting - 10
PRESENTED BY
ENG. T. PATHMARAJAPROJECT DIRECTOR – I ROADS (EP)26.08.2019
Project profile
• Funding Agency : Asian Development Bank
• Total Cost : 31,075 Mn
• Total Length : 845 km
• No of Packages : 11
• Location : Eastern Province
• Consultant : EGIS International (France) Greentech Consultants (Pvt.) Ltd
84
iRoad 2 (Eastern Province)
85
Overview of I- roads in Eastern Province
District Road Category Road Length/ km Total Length
AMPARA
RDA 89.17
408.62PRDD 118.31
PS 201.14
BATTICALOA
RDA 36.29
221.28PRDD 66.89
PS 118.10
TRINCOMALEE
RDA 30.30
215.93PRDD 77.36
PS 108.27
Total 845.83 845.8386
87
iRoad 2 MAP - Ampara District
Contract Details – Ampara District
88
No Description of Package Contract Package No Contractor Name Contract Amount(Rs.)
01 Rehabilitation/ Improvement and Maintenance of 82.67KM Rural Road
RDA/ADB/iROAD02(EP)/NCB/AM - 01 NEM Constructions (PVT) LTD
2,191,974,580.31
02 Rehabilitation/ Improvement and Maintenance of 97.59KM Rural Road
RDA/ADB/iROAD02(EP)/NCB/AM - 02 NEM Constructions (PVT) LTD
2,411,155,243.20
03 Rehabilitation/ Improvement and Maintenance of 80.93KM Rural Road
RDA/ADB/iROAD02(EP)/ICB/AM - 03 AMSK Constructions -CHEC JV
2,857,326,866.40
04 Rehabilitation/ Improvement and Maintenance of 75.46KM Rural Road
RDA/ADB/iROAD02(EP)/NCB/AM - 04 MAGA Engineering (PVT) LTD
2,972,943,809.05
05 Rehabilitation/ Improvement and Maintenance of 71.97KM Rural Road
RDA/ADB/iROAD02(EP)/NCB/AM - 05 Nawaloka Constructions company (PVT)LTD
3,216,982,215.36
• No of packages : 05
• No of roads : 158
• Total Length : 408.62 km
89
iRoad 2 MAP Batticaloa District
Contract Details – Batticaloa District
90
No Description of Package Contract Package No Contractor Name Contract Amount(Rs.)
01 Rehabilitation/ Improvement and Maintenance of 71.98 KM Rural Road
RDA/ADB/iROAD02(EP)/ICB/BT - 01 CICO – Sun JV 2,948,511,936.00
02 Rehabilitation/ Improvement and Maintenance of 76.76 KM Rural Road
RDA/ADB/iROAD02(EP)/ICB/BT – 02 CICO – Sun JV 2,928,375,816.00
03 Rehabilitation/ Improvement and Maintenance of 72.54 KM Rural Road
RDA/ADB/iROAD02(EP)/NCB/BT - 03 NawalokaConstructions Company (PVT)LTD
3,054,476,714.16
• No of packages : 03
• No of roads : 124
• Total Length : 221.28 km
91
iRoad 2 MAPTrincomalee District
Contract Details – Trincomalee District
92
No Description of Package Contract Package No Contractor Name Contract Amount(Rs.)
01 Rehabilitation/ Improvement and Maintence of 74.38 KM Rural Road
RDA/ADB/iROAD02(EP)/ICB/TR - 01 Edward & Christie 2,943,521706.00
02 Rehabilitation/ Improvement and Maintence of 61.23 KM Rural Road
RDA/ADB/iROAD02(EP)/NCB/TR - 02 Maga Engineering (PVT) LTD
2,797,613,374.98
03 Rehabilitation/ Improvement and Maintence of 80.32 KM Rural Road
RDA/ADB/iROAD02(EP)/NCB/TR - 03 Edward & Christie 2,751,921,684.00
• No of packages : 03
• No of roads : 124
• Total Length : 215.93 km
03. CURRENT CONTRACTOR'S OFFICES
Current Status of the project on 23.08.2019 (Achievement of contractual milestones
94
Description
AM-01
NEM Co.
Ltd.
AM-02
NEM Co.
Ltd
AM-03
AMSK -
CHEC JV
AM-04
MAGA
AM-05
Nawaloka
BT-01
CICO-Sun
JV
BT-02
CICO-Sun
JV
BT-03
Nawaloka
TR-01
Edward &
Christie
TR-02
MAGA
TR-03
Edward &
Christie
1 Issue of Letter
of Acceptance
27.06.2019 27.06.2019 27.06.2019 27.06.2019 27.06.2019 27.06.2019 27.06.2019 27.06.2019 27.06.2019 27.06.2019 27.06.2019
2A
Performance
Security
(As per Cl. 4.2)
-28d LOA
25.07.2019 25.07.2019 25.07.2019 25.07.2019 25.07.2019 25.07.2019 25.07.2019 25.07.2019 25.07.2019 25.07.2019 25.07.2019
2BPerformance
Security
(Actual)
16.08.2019 DelayStated subm by
AMSK but not
received by ENG
13.07.2019
(rec.20.08.19)Delay 07.08.2019 07.08.2019 22.08.2019 22.07.2019 17.07.2019 22.07.2019
3A
Contract
Signature
(As per Cl. 1.6)
-28d LOA
25.07.2019 25.07.2019 25.07.2019 25.07.2019 25.07.2019 25.07.2019 25.07.2019 25.07.2019 25.07.2019 25.07.2019 25.07.2019
3BContract
Signature
(Actual)
Delay Delay Delay Delay Delay Delay Delay Delay 31.07.2019 Delay 31.07.2019
4A
Adv. Payment
Guarantee
(As per Cl.
14.2)
Before
Comm Date
Before
Comm Date
Before
Comm Date
Before
Comm Date
Before
Comm Date
Before Comm
Date
Before Comm
Date
Before
Comm Date
Before
Comm Date
Before
Comm Date
Before Comm
Date
4BAdv.Payment
Guarantee
(Actual)
Delay Delay Delay13.07.2019
(rec.20.08.19)Delay Delay Delay 22.08.2019 01.08.2019 23.07.2019 01.08.2019
4CAdv.Payment
(Certified by
Engineer)
---- ---- ---- ---- ---- ---- ---- ---- 16.08.2019 ---- 16.08.2019
95
Description
AM-01
NEM Co.
Ltd.
AM-02
NEM Co.
Ltd
AM-03
AMSK -
CHEC JV
AM-04
MAGA
AM-05
Nawaloka
BT-01
CICO-Sun
JV
BT-02
CICO-Sun
JV
BT-03
Nawaloka
TR-01
Edward &
Christie
TR-02
MAGA
TR-03
Edward &
Christie
5A Subm. Works Program
(As per Cl. 8.3)
Before
Comm
Date
Before
Comm
Date
Before
Comm
Date
Before
Comm
Date
Before
Comm
Date
Before
Comm Date
Before
Comm Date
Before
Comm Date
Before
Comm
Date
Before
Comm
Date
Before
Comm
Date
5B Subm. Works Program
Initial (Actual)
06.08.2019
(To be
rev.)
Delay
22.08.2019
(under
rev.)
20.08.2019
(under
rev.)
14.08.2019
(To be rev.)
23.08.2019
(under rev.)
23.08.2019
(under rev.)
14.08.2019
(To be rev.)
10.08.2019
(To be
rev.)
15.08.2019
(To be
rev.)
10.08.201
9
(To be
rev.)
6ASubm.
Contr.Insurances
(As per Cl. 18)
Before
Comm
Date
Before
Comm
Date
Before
Comm
Date
Before
Comm
Date
Before
Comm
Date
Before
Comm Date
Before
Comm Date
Before
Comm Date
Before
Comm
Date
Before
Comm
Date
Before
Comm
Date
6BSubm.
Contr.Insurances
(Actual)
Delay Delay Delay
Draft
Subm.
(To be rev.)
Draft
Subm.
(To be rev.)
Draft Subm.
(To be rev.)
Draft Subm.
(To be rev.)
22.08.2019
(Under rev.)Delay
Draft
Subm.
(To be
rev.)
Delay
7Commencement Date
(As per Cl.18)
Not yet
declared
Not yet
declared
Not yet
declared
Not yet
declared
Not yet
declared
Not yet
declared
Not yet
declared
Not yet
declared
Not yet
declared
Not yet
declared
Not yet
declared
Current Status of the project on 23.08.2019 (Achievement of contractual milestones
96
Current Status of the project on 23.08.2019 (CONTRACTOR´S MOBILISATION AND ACTIVITIES)
DescriptionAM-01
NEM Co.
Ltd.
AM-02
NEM Co.
Ltd
AM-03
AMSK -
CHEC JV
AM-04
MAGA
AM-05
Nawaloka
BT-01
CICO-Sun
JV
BT-02
CICO-Sun
JV
BT-03
Nawaloka
TR-01
Edward &
Christie
TR-02
MAGA
TR-03
Edward &
Christie
1AAppointment of
Authorised
Representative (PM)
Yes Yes Yes YesNot
AprovedYes Yes
Not
AprovedYes Yes Yes
1B Appointment of Key
Staff
Yes
(Mainly)
Partly
accompl.
Submitted
19.08.19
Yes
(Mainly)
Yes
(Mainly)Yes (Mainly) Yes (Mainly)
Yes
(Mainly)
Yes
(Mainly)
Yes
(Mainly)
Yes
(Mainly)
2 Survey ActivitiesIn progress
(Advanced)
In
progressStarted
In
progress
In
progressIn progress In progress
In
progress
In
progress
In
progress
In
progress
3Submission EMAP
16.08.2019
(comment
s
----- ----- ----- ----- ----- ----- ----- ----- ----- -----
4 Submission QMP
13.08.2019
(comment
s
-----22.08.2019
(under rev)----- ----- ----- ----- ----- ----- ----- -----
5 Soil Investigation ------ ----- ----- ----- ----- ----- ----- ----- Started ----- Started
ONGOING Environmental and social activities
➢Conducting pre-condition crack survey (AM01)
➢Formation of Grievance Redress Committee(GRC) through DS,GN level etc.
➢Collecting Base line environmental data (Started)
➢Collecting Soil Samples (TR1 & TR3) (Started)
98
➢Public and Politicians are requesting to commence their road immediately
➢Some Contractors are slow to providing the contractual deliverables on time, therefore the declaration of the Commencement Date has already been delayed. At present, mainly the submissions of the Contractor´s Insurances are pending
Issues
99
➢Initial Maintenance works on existing roads shall be started immediately after
the date of commencement
➢Contractors need to be notified to expedite the submission of deliverables, in
order to establish the Commencement Date and to enable to commence the
work as per the initial schedules
SOLUTION/ RECOMMENDATION
Thanking You