120
October 2007 Appendix B 1 APPENDIX B WORKSHEETS & EXHIBITS Temporary Construction Ingress/Egress Pad Plan View ................ 5 Worksheet (Large Sites – Two Acres or Larger) Temporary Construction Ingress/Egress Pad Cross-Section .......... 7 View Worksheet (Large Sites – Two Acres or Larger) Temporary Construction Ingress/Egress Pad Plan View ................ 9 Worksheet (Small Sites – Less Than Two Acres) Riprap Slope Protection Worksheet .............................................. 11 Temporary Diversion Worksheet .................................................. 13 Permanent Diversion Worksheet ................................................... 15 Perimeter Diversion Dike Worksheet............................................ 17 Water Bar Worksheet .................................................................... 19 Rock Check Dam Worksheet ........................................................ 21 Temporary Slope Drain Worksheet ............................................... 23 Grass-Lined Channel Worksheet................................................... 25 Riprap-Lined Channel Worksheet ................................................. 27 Energy Dissipater Worksheet 1 ..................................................... 29 Energy Dissipater Worksheet 2 ..................................................... 31 Concrete Block Chute Worksheet ................................................. 33 Excavated Drop Inlet Protection Worksheet ................................. 35 Temporary Sediment Trap Rock Dam Worksheet ........................ 37 Temporary Sediment Trap Outlet Worksheet ............................... 39 A worksheet provides the designer a representation of a measure that allows for input of specific design criteria. The plan designer will be required to assess field conditions and apply engineering principles to determine dimensions and specifications. An exhibit is a representa- tive view of a measure. An exhibit often includes standardized dimensions and specifications. Several exhibits are only a representative view of the measure, and will require the designer to assess field conditions and input dimensions and specifications for the measure. These exhibits have been identified with a note. Worksheet Page

APPENDIX B WORKSHEETS & EXHIBITS - Indiana · APPENDIX B — WORKSHEETS & EXHIBITS ... Excavated Drop Inlet Protection Worksheet ... The plan designer will be required to assess field

Embed Size (px)

Citation preview

October 2007 Appendix B 1

APPENDIX B — WORKSHEETS & EXHIBITS

Temporary Construction Ingress/Egress Pad Plan View ................ 5 Worksheet (Large Sites – Two Acres or Larger)

Temporary Construction Ingress/Egress Pad Cross-Section .......... 7 View Worksheet (Large Sites – Two Acres or Larger)

Temporary Construction Ingress/Egress Pad Plan View ................ 9 Worksheet (Small Sites – Less Than Two Acres)

Riprap Slope Protection Worksheet .............................................. 11

Temporary Diversion Worksheet .................................................. 13

Permanent Diversion Worksheet ................................................... 15

Perimeter Diversion Dike Worksheet ............................................ 17

Water Bar Worksheet .................................................................... 19

Rock Check Dam Worksheet ........................................................ 21

Temporary Slope Drain Worksheet ............................................... 23

Grass-Lined Channel Worksheet ................................................... 25

Riprap-Lined Channel Worksheet ................................................. 27

Energy Dissipater Worksheet 1 ..................................................... 29

Energy Dissipater Worksheet 2 ..................................................... 31

Concrete Block Chute Worksheet ................................................. 33

Excavated Drop Inlet Protection Worksheet ................................. 35

Temporary Sediment Trap Rock Dam Worksheet ........................ 37

Temporary Sediment Trap Outlet Worksheet ............................... 39

A worksheet provides the designer a representation of a measure that allows for input of specific design criteria. The plan designer will be required to assess field conditions and apply engineering principles to determine dimensions and specifications. An exhibit is a representa-tive view of a measure. An exhibit often includes standardized dimensions and specifications. Several exhibits are only a representative view of the measure, and will require the designer to assess field conditions and input dimensions and specifications for the measure. These exhibits have been identified with a note.

Worksheet Page

2 Appendix B October 2007

APPENDIX B — WORKSHEETS & EXHIBITS

Temporary Dry Sediment Basin Earthen Dam/ ............................ 41 Embankment Worksheet

Temporary Dry Sediment Basin Spillway Worksheet 1 ............... 43

Temporary Dry Sediment Basin Spillway Worksheet 2 ............... 45

Concrete Washout (Above Grade System) Worksheet ................. 47

Concrete Washout (Below Grade System) Worksheet ................. 49

Surface Roughening – Stair-Step Worksheet ............................... 51

Surface Roughening – Grooving Worksheet ................................ 53

Sod Exhibit 1 ................................................................................. 55

Perimeter Diversion Dike Exhibit 1 .............................................. 57

Water Bar Exhibit 1 ...................................................................... 59

Rock Check Dam Exhibit 1 .......................................................... 61

Rock Check Dam Exhibit 2 .......................................................... 63

Temporary Slope Drain Exhibit 1 ................................................. 65

Rock-Lined Chute Exhibit 1 ........................................................ 67 (requires inclusion of dimensions and specifications)

Reinforced Vegetated Chute Exhibit 1 ........................................ 69 (requires inclusion of dimensions and specifications)

Excavated Drop Inlet Protection Exhibit 1 ................................... 71

Gravel Donut Drop Inlet Protection Exhibit 1 .............................. 73

Gravel Donut Drop Inlet Protection Exhibit 2 .............................. 75

Geotextile Fabric Drop Inlet Protection Exhibit 1 ........................ 77

Geotextile Fabric Drop Inlet Protection Exhibit 2 ........................ 79

Worksheet Page

Exhibit Page

October 2007 Appendix B 3

APPENDIX B — WORKSHEETS & EXHIBITS

Straw Bale Drop Inlet Protection Exhibit 1 .................................. 81

Straw Bale Drop Inlet Protection Exhibit 2 .................................. 83

Block & Gravel Drop Inlet Protection Exhibit 1 .......................... 85

Block & Gravel Drop Inlet Protection Exhibit 2 .......................... 87

Stone Bag Curb Inlet Protection Exhibit 1 ................................... 89

Stone Bag Curb Inlet Protection Exhibit 2 ................................... 91

Block & Gravel Curb Inlet Protection Exhibit 1 .......................... 93

Block & Gravel Curb Inlet Protection Exhibit 2 .......................... 95

Temporary Dry Sediment Basin Riser Pipe Exhibit 1 .................. 97

Silt Fence Exhibit 1 ....................................................................... 99

Silt Fence Exhibit 2 ..................................................................... 101

Silt Fence Exhibit 3 ..................................................................... 103

Straw Bale Dam Exhibit 1 .......................................................... 105

Straw Bale Dam Exhibit 2 .......................................................... 107

Straw Bale Dam Exhibit 3 .......................................................... 109

Straw Bale Dam Exhibit 4 .......................................................... 111

Temporary Stream Crossing – Bridges Exhibit 1 ....................... 113 (requires inclusion of dimensions and specifications)

Temporary Stream Crossing – Culverts Exhibit 1 ...................... 115 (requires inclusion of dimensions and specifications)

Temporary Stream Crossing – Fords Exhibit 1 .......................... 117 (requires inclusion of dimensions and specifications)

Temporary Stream Crossing – Fords Exhibit 2 .......................... 119 (requires inclusion of dimensions and specifications)

Exhibit Page

This page was intentionally left blank.

October 2007 Appendix B 5

WORKSHEET

Temporary Construction Ingress/Egress Pad Plan View Worksheet

(large sites—two acres or larger)

T = _____ inches W = _____ feet

L = _____ feet

Public Road

Geotextile Fabric Underliner

INDOT CA No. 2 Aggregate

L = Ingress/Egress Pad Length W = Ingress/Egress Pad Width T = Aggregate Thickness (Note: For minimum dimensions, see the “Specifications” section of this measure.)

Top-Dress First 50 Feet Adjacent to Public Roadway with 2-3 Inches of INDOT CA No. 53 Aggregate (optional)

Source: Adapted from North Carolina Erosion and Sediment Control Planning and Design Manual, 1993

For information on this measure, see Chapter 7,

page 17

This page was intentionally left blank.

October 2007 Appendix B 7

WORKSHEET

Temporary Construction Ingress/Egress Pad Cross-Section View Worksheet (large sites two acres or larger)

H = _____ inches

Public Road

15 Feet Grade > 2%

Geotextile Fabric Underliner

Diversion Ridge with 3:1 Side Slopes

H = Height of Diversion Ridge (Note: 8 inches minimum)

Source: Adapted from North Carolina Erosion and Sediment Control Planning and Design Manual, 1993

For information on this measure, see Chapter 7,

page 17

This page was intentionally left blank.

October 2007 Appendix B 9

WORKSHEET

Temporary Construction Ingress/Egress Pad Plan View Worksheet

(small sites—less than two acres)

T = _____ inches W = _____ feet

L = _____ feet

Public Road

Geotextile Fabric Underliner

INDOT CA No. 2 Aggregate

L = Ingress/Egress Pad Length W = Ingress/Egress Pad Width T = Aggregate Thickness

(Note: For minimum dimensions, see the “Specifications” section of this measure.)

Top-Dress with INDOT CA No. 53 Aggregate (optional)

Source: Adapted from North Carolina Erosion and Sediment Control Planning and Design Manual, 1993

For information on this measure, see Chapter 7,

page 21

This page was intentionally left blank.

October 2007 Appendix B 11

WORKSHEET

Smooth foundation under bedding material/ filter medium

Bedding material/ filter medium

Keyway T = Aggregate Thickness (� 2 x d50)

T = _____ feet

1.5 T (min.)

T = ____ feet

Riprap Slope Protection Worksheet

Source: Adapted from North Carolina Erosion and Sediment Control Planning and Design Manual, 1993

For information on this measure, see Chapter 7,

page 69

This page was intentionally left blank.

October 2007 Appendix B 13

WORKSHEET

CD = Channel Depth

CW = Channel Width

RW = Ridge Width

Temporary Diversion Worksheet

For information on this measure, see Chapter 7,

page 75

Protected Area

6 inch freeboard

All constructed slopes 2:1 or flatter

Flow

CD = _____ feet

Allowance for 10% Settlement

CW = _____ feet RW = _____ feet

This page was intentionally left blank.

October 2007 Appendix B 15

WORKSHEET

Permanent Diversion Worksheet

For information on this measure, see Chapter 7,

page 79

Protected Area

6 inch freeboard

All constructed slopes 2:1 or flatter

Flow

CD = _____ feet

CD = Channel Depth

CW = Channel Width

RW = Ridge Width

Allowance for 10% Settlement

CW = _____ feet RW = _____ feet

This page was intentionally left blank.

October 2007 Appendix B 17

WORKSHEET

Perimeter Diversion Dike Worksheet

For information on this measure, see Chapter 7,

page 83

6 inch freeboard

All constructed slopes 2:1 or flatter

RH = _____ inches

CW = _____ feet

Allowance for 10% settlement

Flow

CD = _____ inches

RH = Ridge Height

RW = Ridge Base Width

CD = Channel Depth

CW = Channel Top Width

Note: Drainage channel is optional.

Protected Area

RW = _____ feet

This page was intentionally left blank.

October 2007 Appendix B 19

WORKSHEET

6 inch freeboard

All constructed slopes 2:1 or flatter

RH = _____ inches

CW = _____ feet

Allowance for 10% settlement

Flow

CD = _____ inches

RH = Ridge Height

RW = Ridge Base Width

CD = Channel Depth

CW = Channel Top Width

Note: Drainage channel is optional.

Protected Area

Water Bar Worksheet

For information on this measure, see Chapter 7,

page 89

RW = _____ feet

This page was intentionally left blank.

October 2007 Appendix B 21

WORKSHEET

Rock Check Dam Worksheet

DH = Dam Height

SD = Spillway Depth

(NOTE: For minimum dimensions see the “Specifications” section of this measure.)

Revetment riprap

Filter medium

Geotextile fabric

DH = _____ inches

SD = _____ inches

Filter medium on up-slope side of check dam

Geotextile fabric

SD = _____ inches

Revetment riprap 2:1 or flatter slope

SD = Spillway Depth

(NOTE: For minimum dimensions see the “Specifications” section of this measure.)

Source: Adapted from North Carolina Erosion and Sediment Control Planning and Design Manual, 1993

For information on this measure, see Chapter 7,

page 97

This page was intentionally left blank.

October 2007 Appendix B 23

WORKSHEET

Temporary Slope Drain Worksheet

IBH = _____ feet

LSL = _____ feet

Stabilized outlet

PD = _____ inches

IBH = Island Berm Height

IBW = Island Berm Width

DBH = Diversion Berm Height

DBW = Diversion Berm Width

LSL = Level Section Length

TSS = Tie-Down Stake Spacing

PD = Pipe Diameter

(Note: For minimum and maximum dimensions, see the “Specifications” section of this measure.)

IBW = _____ feet

DBW = _____ feet

DBH = _____ feet

TSS = _____ feet

Source: Adapted from North Carolina Erosion and Sediment Control Planning and Design Manual, 1993

For information on this measure, see Chapter 7,

page 103

This page was intentionally left blank.

October 2007 Appendix B 25

WORKSHEET

BW = _____ feet

CD = _____ feet

Erosion control blanket over turf reinforcement mat

Turf reinforcement mat

BW = Designed Bottom Width of Channel

CW = Designed Top Width of Channel

CD = Designed Depth of Channel

CW = _____ feet

Grass-Lined Channel Worksheet

For information on this measure, see Chapter 7,

page 111

This page was intentionally left blank.

October 2007 Appendix B 27

WORKSHEET

Riprap-Lined Channel Worksheet

For information on this measure, see Chapter 7,

page 115

Geotextile fabric or bedding material T = _____ feet

CD = _____ feet

BW = Designed Bottom Width of Channel

CW = Designed Top Width of Channel

CD = Designed Depth of Channel

T = Thickness of Riprap Layer

BW = _____ feet

CW = ______ feet

This page was intentionally left blank.

October 2007 Appendix B 29

WORKSHEET

AL = _____ feet

AT = _____ feet Geotextile fabric or well-graded aggregate

Check slot (optional)

Drain pipe with flared end section

Stable outlet

Top of apron level with receiving channel Plunge pool

(optional)

AL = Apron Length

AT = Apron Thickness

Energy Dissipater Worksheet 1

For information on this measure, see Chapter 7,

page 121

This page was intentionally left blank.

October 2007 Appendix B 31

WORKSHEET

AT = _____ feet

AW = _____ feet

Drain pipe Stone placed around end of drain pipe to prevent slope erosion and undercutting of the pipe

Stone apron below pipe discharge

Geotextile fabric or well graded aggregate

AT = Apron Thickness AW = Apron Width

Note: AW is the apron width at the narrow end of the apron.

Energy Dissipater Worksheet 2

For information on this measure, see Chapter 7,

page 121

This page was intentionally left blank.

October 2007 Appendix B 33

WORKSHEET

2:1 or flatter slope

Subsurface drain tile offset from center of channel to prevent seepage of up-slope groundwater

Plastic sheeting

Concrete blocks

BTW = Berm Top Width

Geotextile fabric

Bedding material

___:1 slope

BTW = _____ feet

___:1 slope

Concrete Block Chute Worksheet

Source: Adapted from U.S. Department of Agriculture, Natural Resources Conservation Service

For information on this measure, see Chapter 7,

page 131

This page was intentionally left blank.

October 2007 Appendix B 35

WORKSHEET

Excavated Drop Inlet Protection Worksheet

Source: Adapted from North Carolina Erosion and Sediment Control Planning and Design Manual, 1993

For information on this measure, see Chapter 7,

page 145

ED = _____ inches Weep holes for dewatering

Aggregate supported by geotextile fabric or hardware cloth

EA = Excavated Area (as required)

ED = Excavated Depth

2:1 or flatter slope

EA = _____ feet x _____ feet

This page was intentionally left blank.

October 2007 Appendix B 37

WORKSHEET

Temporary Sediment Trap Rock Dam Worksheet

Source: Adapted from North Carolina Erosion and Sediment Control Planning and Design Manual, 1993

SD = _____ feet FPE = _____ feet

AL = Apron Length

DH = Dam Height

FPE = Flood Pool Elevation

SD = Spillway Depth

TW = Top Width

Geotextile filter fabric

AL = ____ feet

DH = _____ feet

____ :1 slope

1 foot thick gravel filter

____:1 slope TW = _____ feet

For information on this measure, see Chapter 7,

page 183

This page was intentionally left blank.

October 2007 Appendix B 39

WORKSHEET

SBW = _____ feet

SD = _____ inches ____ : 1 slope

Overfill 6 inches to allow for settlement

____ : 1 slope

Geotextile filter fabric

T = _____ inches

RBW = _____ feet

RBW = Rock Dam Bottom Width

SD = Spillway Depth

SBW = Spillway Bottom Width

T = Spillway Side-Slope Armament Thickness

Temporary Sediment Trap Outlet Worksheet

Source: Adapted from North Carolina Erosion and Sediment Control Planning and Design Manual, 1993

For information on this measure, see Chapter 7,

page 183

This page was intentionally left blank.

October 2007 Appendix B 41

WORKSHEET

Temporary Dry Sediment Basin Earthen Dam/Embankment Worksheet

Hand-compacted fill around barrel/pipe and anti-seep collar

EH = _____ feet

ETW = _____ feet

___:1 slope ___:1 slope

Allowance for 10% settlement

EH = Earthen Dam/Embankment Height ETW = Earthen Dam/Embankment Top Width (NOTE: For minimum dimensions see the “Specifications” section of this measure.)

Earthen dam/embankment constructed in 6 to 8 inch lifts

Cut-off Trench

Source: Adapted from North Carolina Erosion and Sediment Control Planning and Design Manual, 1993

For information on this measure, see Chapter 7,

page 191

This page was intentionally left blank.

October 2007 Appendix B 43

WORKSHEET

Temporay Dry Sediment Basin Spillway Worksheet 1

Anti-flotation block

Hand-compacted fill around pipe and anti-seep collar

Principal spillway barrel/pipe

Cut-off trench

Anti-seep collar

Stabilized outlet

___:1 slope

Emergency spillway crest elevation = ________ FBD = _____ feet

Flood pool elevation = ________

Riser pipe crest elevation = ________

Source: Adapted from North Carolina Erosion and Sediment Control Planning and Design Manual, 1993

ESW = Emergency Spillway Width

FBD = Free Board Depth

(NOTE: For minimum dimensions see the “Specifications” section of this measure.)

ESW = _____ feet

___:1 slopes

Source: Adapted from U.S. Department of Agriculture, Natural Resources Conservation Service

For information on this measure, see Chapter 7,

page 191

This page was intentionally left blank.

October 2007 Appendix B 45

WORKSHEET

Earthen dam/embankment

Slope

Flow ESW = _____ feet

Slope

Level portion of spillway

Channel approach

1.5 ESW = _____ feet

FBD = _____ feet

LSL = _____ feet

Exit section

Flood pool

Approach channel

___:1 slope

___:1 slope

ESW = Emergency Spillway Width

FBD = Free Board Depth

LSL = Level Section Length

(NOTE: For minimum dimensions see the “Specifications” section of this measure.)

Temporary Dry Sediment Basin Spillway Worksheet 2

Source: Adapted from USDA Natural Resources Conservation Service

For information on this measure, see Chapter 7,

page 191

This page was intentionally left blank.

October 2007 Appendix B 47

WORKSHEET

Concrete Washout (Above Grade System) Worksheet

For information on this measure, see Chapter 7,

page 247

This page was intentionally left blank.

October 2007 Appendix B 49

WORKSHEET

Concrete Washout (Below Grade System) Worksheet

For information on this measure, see Chapter 7,

page 247

This page was intentionally left blank.

October 2007 Appendix B 51

WORKSHEET

H = ____ inches

V = _____ inches Slope

H = Horizontal Cut V = Vertical Cut H > V Note: See “Roughening Slopes (Not to be Mowed)” under the “Specifications” section of this measure.

Surface Roughening – Stair-Step Worksheet

Source: Adapted from North Carolina Erosion and Sediment Control Planning and Design Manual, 1993

For information on this measure, see Chapter 7,

page 297

This page was intentionally left blank.

October 2007 Appendix B 53

WORKSHEET

Surface Roughening – Grooving Worksheet

GW = ____ inches

GD = ____ inches

GD = Groove Depth

GW = Groove Width

Note: See “Roughening Slopes (Not to be Mowed)” under the “Specifications” section of this measure.

Source: Adapted from North Carolina Erosion and Sediment Control Planning and Design Manual, 1993

For information on this measure, see Chapter 7,

page 297

This page was intentionally left blank.

October 2007 Appendix B 55

EXHIBIT

Sod

Exhibit 1

Perspective View

Source: Adapted from North Carolina Erosion and Sediment Control Planning and Design Manual, 1993

For information on this measure, see Chapter 7,

page 47

This page was intentionally left blank.

October 2007 Appendix B 57

EXHIBIT

Flow

Flow

Perimeter Diversion Dike

Exhibit 1

Source: Adapted from North Carolina Erosion and Sediment Control Planning and Design Manual, 1993

For information on this measure, see Chapter 7,

page 83

This page was intentionally left blank.

October 2007 Appendix B 59

EXHIBIT

Water Bar

Exhibit 1

For information on this measure, see Chapter 7,

page 89

This page was intentionally left blank.

October 2007 Appendix B 61

EXHIBIT

Rock Check Dam

Exhibit 1

A B

A B

A = Crest of Dam

B = Toe of Dam

For information on this measure, see Chapter 7,

page 97

This page was intentionally left blank.

October 2007 Appendix B 63

EXHIBIT

Channel bottom width

Channel top width

Flow

Revetment riprap

Filter medium

Exhibit 2

Rock Check Dam

For information on this measure, see Chapter 7,

page 97

This page was intentionally left blank.

October 2007 Appendix B 65

EXHIBIT

Temporary Slope Drain

Exhibit 1

Flow

Earthen island over inlet section of drain

Anchor stake spacing (maximum of 10 feet)

Stablized outlet

Level section (4 foot min.)

Diversion berm Diversion channel

Anchor stakes

Corrugated, non-perforated, plastic drain pipe

For information on this measure, see Chapter 7,

page 103

This page was intentionally left blank.

October 2007 Appendix B 67

EXHIBIT

Flow

Riprap placed over geotextile fabric

Subsurface drain tile offset from center of channel to prevent seepage of up-slope groundwater

Rock-Lined Chute

Exhibit 1

Source: Adapted from USDA Natural Resources Conservation Service

NOTE: This measure requires the designer to provide design specifications and dimensions.

For information on this measure, see Chapter 7,

page 127

This page was intentionally left blank.

October 2007 Appendix B 69

EXHIBIT

Source: Adapted from USDA Natural Resources Conservation Service

Reinforced Vegetated Chute

Flow

Subsurface drain tile offset from center of channel to prevent seepage of up-slope

Riprap over geotextile fabric

Erosion control blanket over turf-reinforcement mat

Aggregate or crushed stone

Exhibit 1

NOTE: This measure requires the designer to provide design specifications and dimensions.

For information on this measure, see Chapter 7,

page 135

This page was intentionally left blank.

October 2007 Appendix B 71

EXHIBIT

Excavated Drop Inlet Protection

Flow Flow

Flow

Main Flow

Exhibit 1

Source: Adapted from North Carolina Erosion and Sediment Control Planning and Design Manual, 1993

For information on this measure, see Chapter 7,

page 145

This page was intentionally left blank.

October 2007 Appendix B 73

EXHIBIT

Gravel Donut Drop Inlet Protection

Exhibit 1

For information on this measure, see Chapter 7,

page 149

This page was intentionally left blank.

October 2007 Appendix B 75

EXHIBIT

3:1 or flatter slope 1 to 2 feet 2:1 or flatter slope

Filter stone (1 foot thick)

Exhibit 2

Gravel Donut Drop Inlet Protection

Source: Adapted from North Carolina Erosion and Sediment Control Planning and Design Manual, 1993

For information on this measure, see Chapter 7,

page 149

This page was intentionally left blank.

October 2007 Appendix B 77

EXHIBIT

36 inches (maximum)

12 to 18 inches

18 inches (minimum)

Cross bracing

Exhibit 1

Geotextile Fabric Drop Inlet Protection

Source: Adapted from North Carolina Erosion and Sediment Control Planning and Design Manual, 1993

For information on this measure, see Chapter 7,

page 153

This page was intentionally left blank.

October 2007 Appendix B 79

EXHIBIT

Geotextile Fabric Drop Inlet Protection

Exhibit 2

Flow

Compacted fill

Geotextile fabric

8 inches

18 inches (min.)

36 inch (min.) hardwood post

Geotextile fabric laid on down-slope side and bottom of trench

4 inches

Secured with lathe

For information on this measure, see Chapter 7,

page 153

This page was intentionally left blank.

October 2007 Appendix B 81

EXHIBIT

Two stakes per straw bale

Exhibit 1

Straw Bale Drop Inlet Protection

Source: Adapted from Michigan Soil Erosion and Sedimentation Control Guidebook, 1975

For information on this measure, see Chapter 7,

page 159

This page was intentionally left blank.

October 2007 Appendix B 83

EXHIBIT

Straw Bale Drop Inlet Protection

Exhibit 2

Bales entrenched four (4) inches into the soil

Compacted fill to prevent piping

Flow

Bale turned on its side to prevent deterioration of bindings

Source: Adapted from Michigan Soil Erosion and Sedimentation Control Guidebook, 1975

For information on this measure, see Chapter 7,

page 159

This page was intentionally left blank.

October 2007 Appendix B 85

EXHIBIT

Block & Gravel Drop Inlet Protection

One concrete block, in bottom row of blocks on each side of structure, laid horizontally to allow for dewatering

Aggregate blanket with 2:1 slope or flatter

Exhibit 1

Source: Adapted from North Carolina Erosion and Sediment Control Planning and Design Manual, 1993

For information on this measure, see Chapter 7,

page 163

This page was intentionally left blank.

October 2007 Appendix B 87

EXHIBIT

Block & Gravel Drop Inlet Protection

2:1 or flatter slope

Concrete block laid horizontally for dewatering

Hardware cloth

Exhibit 2

Source: Adapted from North Carolina Erosion and Sediment Control Planning and Design Manual, 1993

For information on this measure, see Chapter 7,

page 163

This page was intentionally left blank.

October 2007 Appendix B 89

EXHIBIT

Stone Bag Curb Inlet Protection

Exhibit 1

For information on this measure, see Chapter 7,

page 169

This page was intentionally left blank.

October 2007 Appendix B 91

EXHIBIT

Stone Bag Curb Inlet Protection

Flow

Flow

Spillway at or below curb height

Stone bags tightly stacked and abutted together

Upper layer(s) of stone bags overlapped onto back of curb

Exhibit 2

For information on this measure, see Chapter 7,

page 169

This page was intentionally left blank.

October 2007 Appendix B 93

EXHIBIT

Block & Gravel Curb Inlet Protection

Exhibit 1

Source: Adapted from Virginia Department of Conservation and Recreation, Division of Soil and Water Conservation

For information on this measure, see Chapter 7,

page 173

This page was intentionally left blank.

October 2007 Appendix B 95

EXHIBIT

2” x 4” wooden stud

Filter aggregate

Blocks laid with openings horizontal to the pavement to allow for drainage

Hardware cloth

Exhibit 2

Block & Gravel Curb Inlet Protection

For information on this measure, see Chapter 7,

page 173

This page was intentionally left blank.

October 2007 Appendix B 97

EXHIBIT

Temporary Dry Sediment Basin Riser Pipe

Hardware cloth or wire mesh to prevent aggregate from plugging perforations

Riprap or INDOT CA No. 2 aggregate filter pack

INDOT CA No. 5 aggre-gate filter stone over filter pack

12 inches of filter aggregate over perforations (min.)

Perforated riser pipe with trash guard

One foot (min.)

Emergency spillway crest

Anti-flotation block

NOTE: For minimum dimensions see the “Specifications” section of this measure.

Exhibit 1

Source: Adapted from North Carolina Erosion and Sediment Control Planning and Design Manual, 1993

For information on this measure, see Chapter 7,

page 191

This page was intentionally left blank.

October 2007 Appendix B 99

EXHIBIT

Silt Fence

End of silt fence turned up-slope to prevent bypass flow and allow for ponding of stormwater runoff

95

100

105

Exhibit 1

Source: Adapted from Commonwealth of Pennsylvania Erosion and Sediment Pollution Control Program Manual, 1990

Silt Fence

For information on this measure, see Chapter 7,

page 215

This page was intentionally left blank.

October 2007 Appendix B 101

EXHIBIT

Silt Fence

Flow

Compacted fill

8 inches

18 inches (min.)

Geotextile fabric

36 inch (min.) hardwood post

Geotextile fabric laid on down-slope side and bottom of trench

4 inches

Exhibit 2

secured with lathe

For information on this measure, see Chapter 7,

page 215

This page was intentionally left blank.

October 2007 Appendix B 103

EXHIBIT

Silt Fence

Silt Fence Post

Exhibit 3

For information on this measure, see Chapter 7,

page 215

This page was intentionally left blank.

October 2007 Appendix B 105

EXHIBIT

Straw Bale Dam

110

105

100

95

Turn ends of straw bale dam up slope to prevent bypass flow and allow for ponding of storm water runoff

Exhibit 1

Source: Adapted from Minnesota Pollution Control Agency, Minnesota Construction Site Erosion and Sediment Control Planning Handbook, 1987

For information on this measure, see Chapter 7,

page 223

This page was intentionally left blank.

October 2007 Appendix B 107

EXHIBIT

10 foot minimum spacing from toe of slope to allow for ponding of stormwater runoff

Straw Bale Dam

Exhibit 2

Source: California Regional Water Quality Control Board, San Francisco Bay Region Erosion and Sediment Control Field Manual, Second Edition

For information on this measure, see Chapter 7,

page 223

This page was intentionally left blank.

October 2007 Appendix B 109

EXHIBIT

Straw Bale Dam

Exhibit 3

For information on this measure, see Chapter 7,

page 223

This page was intentionally left blank.

October 2007 Appendix B 111

EXHIBIT

Straw Bale Dam

Exhibit 4

For information on this measure, see Chapter 7,

page 223

This page was intentionally left blank.

October 2007 Appendix B 113

EXHIBIT

Temporary Stream Crossing - Bridges

Exhibit 1

NOTE: This measure requires the designer to provide design specifications and dimensions.

For information on this measure, see

Chapter 7, page 267

This page was intentionally left blank.

October 2007 Appendix B 115

EXHIBIT

Temporary Stream Crossing - Culverts

Exhibit 1 NOTE: This measure requires the

designer to provide design specifications and dimensions.

For information on this measure, see

Chapter 7, page 273

This page was intentionally left blank.

October 2007 Appendix B 117

EXHIBIT

Temporary Stream Crossing - Fords

5 foot (max.) bank height

Stone over geotextile fabric

Road alignment straight for a minimum of 30 feet (min.)

All excavated slopes 2:1 or flatter

Flow

Temporary diversion channel

Exhibit 1

Source: Adapted from Virginia Department of Conservation and Recreation, Division of Soil and Water Conservation, 1992

NOTE: This measure requires the designer to provide design specifications and dimensions.

For information on this measure, see Chapter 7,

page 279

This page was intentionally left blank.

October 2007 Appendix B 119

EXHIBIT

Temporary Stream Crossing - Fords

Temporary diversion channel

5:1 slope (max.) Geotextile fabric for stabilization and separation

Temporary diversion channel

5 foot maximum bank height

Exhibit 2

Source: Adapted from Virginia Department of Conservation and Recreation, Division of Soil and Water Conservation, 1992

NOTE: This measure requires the designer to provide design specifications and dimensions.

For information on this measure, see Chapter 7,

page 279

This page was intentionally left blank.