World Energy CouncilMinistry Of Electricity & Energy
Egyptian Holding Company For Electricity
Upper Egypt Electricity Production Company
Boiler life assessmentBY
ENG: IBRAHIM EL SHAHAAT
8/3/2019 Boiler Life Asessment
2/33
ContentsContents
1. The purpose of boiler life assessment
2. Life Evaluation by Inspection3. Preparations for Inspection
4. Data requirement
5. Inspection of high pressure parts.
6. Sample tube inspection.
7. Visual inspection for other parts of boiler .
8. Water quality survey.
9. Visual Inspection for aux Equipment
10. high pressure parts Inspection details
8/3/2019 Boiler Life Asessment
3/33
assessment
Evaluate the present state and the condition of the boilercomponents in order To continue stable and reliable boiler operation
Evaluate the remaining life for Superheater and Reheater bymetallurgical inspection
Evaluation of creep life and future inspection scheme bymetallurgical inspection for water wall, economizer, Superheater and
Reheater tubes Evaluation degree of creep damage for Superheater and Reheater
by hardness test
Evaluate the remaining life based on thickness Measurement forwater wall,
Evaluate the remaining life based on thickness thinning foreconomizer due to low Temperature Corrosion,
Evaluate the remaining life based on thickness thinning forSuperheater and Reheater tubes due to high Temperature Corrosion
Confirm the cause of the inner scale generation
Evaluate the remaining life based on check of metal structure ,innerscale ,etc for sample tube
8/3/2019 Boiler Life Asessment
4/33
2-Life Evaluation by Inspection
FAILURE DAMAG CAUSA PHENOMENON LIFE EVALUATION INSPECTION ITEM
CREEP Clogging withforeign material
Deposition andgrowth of scale onInner surface
Long-term stress
Swelling
Metal structurechange
Outside diameter andthickness measurement
Metallurgicalinspection
Metallurgical inspection for SH, RHheader,
Metallurgical inspection and NDT(UT) for main steam pipe line andhigh temperature RH pipe
FATIGUE Cycle thermalstress
Growth of crackStress analysis
Surface crackinspection (PT,MT)
NDE (PT, MT) of spacer welded forSH and RH Tube
CORROSIONFATIGUE
Cyclic thermalstress undercorrosiveenvironment
Interaction ofcorrosion andfatigue
Ultrasonic test
Sample tubeinspection
Sample tube inspection for SH, RHand water wall
Check of Burner Nozzle and WindBox Damper
CORROSION
EROSION
High tempcorrosion
Low tempcorrosion
Ash erosion
Thicknessthinning
Annual thicknessmeasurement
measurement of tube thicknessfor SH ,RH, Water Wall and Eco byUT
Steam drum
Boiler aux
Eco Hanger tube by endoscope,
etc
8/3/2019 Boiler Life Asessment
5/33
3-Preparations for InspectionBefore inspection
Superheater, reheater, economizer and water wall cleaning
Air heater washing
Scaffolding
Removal of insulation
Open man holes, inspection holes, flanges etc
During inspection Surface preparation of inspection parts
Surface finishing (grinding) of inspection parts
Instrument of apparatus of inspection
Cutting tubes
Welding tubes
Material requirement
New tubes Man hole packing
insulation
Period of inspection Two weeks
8/3/2019 Boiler Life Asessment
6/33
4- Data requirement
Boiler reference data Steam temperature 0cMaximum Steam flow Ton/hr Boiler design pressure Kgm/cm2
Feed water temp 0c Reheated inlet steam temperature 0c Reheated outlet steam temperature 0c Reheater design pressure Kgm/cm2
Kind of fuel Gas, Oil
Functional inspection with boiler in operation Collection of drawings and main technical data Recording of actual operating and functional data at different
loads and conditions at MCR and Verification of the operation ofthe boiler
Collection of data relevant to the thermal history andinterventions ,if any made on the boiler during his operation life
5 I f
8/3/2019 Boiler Life Asessment
7/33
5-Inspect on of g pressureparts
NON Destructive test for the following item1. Economizer headers, coils, Piping from economizer to steam drum,.2. Steam drum.3. Furnace water walls, screen, roof wall, feeders, riser ,Water walls
headers.
4. Saturation steam pipe.5. Primary, secondary super heater.6. Connecting pipe between primary superheater and secondary
superheater.7. Reheater.8. Main SH steam pipes
**Inspection item
1. External visual inspection2. Internal visual inspection with endoscope3. UT for thickness measurements by UT4. MT and UT on circumferential welds5. MT on piping attachments
6. Metallographic inspection by plastic replicas7. MT on nozzles welds of the coil tubes
8/3/2019 Boiler Life Asessment
8/33
the minimum required thickness
t= minimum required thickness.
D = outside diameter of cylinder.
e = thickness factor for expanded tube ends.
P= maximum allowable working pressure.
S= maximum allowable stress value at the design temperature of the metal.
8/3/2019 Boiler Life Asessment
9/33
Design / Operating Informationfor calculation of remaining time based on thickness
Design informationmaterial type or gradeNominal outside diameterDesigning pressure
Design lifeDeign temperatureOriginal nominal thickness
Operating informationMaximum tube metal
temperatureNormal operating pressureOriginal measured minimum
thicknessMetal thinning rate
Thicknessmeasurements
of water walltubes furnace
8/3/2019 Boiler Life Asessment
10/33
Minimum required thickness for
SA178-c
Minimum required thickness for different working
conditions for materials SA178-c
8/3/2019 Boiler Life Asessment
11/33
6-Sample tube-Destructive test for the Sample tubeFor Water Wall ,SR and
RH tubes
Life diagnoses based on check of metal structure, thickness,inner scale, etc
Sample tube takes according to the result of hardness measurement
Investigation Items Visual inspectionNon destructive test Chemical analysisMeasurement of the tube dimension Hardness measurement
Cross sectional microstructure observation Steam oxidation observation Creep rupture testMeasurement of the inner scale thickness
Information
Material of Sample tube tube dimension
8/3/2019 Boiler Life Asessment
12/33
sample tubes
Thinning of bulged zone Internal surface scaleExternal surface scale
8/3/2019 Boiler Life Asessment
13/33
Optical micrograph
Optical micrograph of non-bluged zones tube wall side showingferrite pearlite structure with no
internal defects
8/3/2019 Boiler Life Asessment
14/33
Normal and deterioratedmicrostructure
normal microstructure
( good condition tube)Which shows a
typical ferritic pearliticstructure
deterioratedmicrostructure whichshows thedecomposition of thepearlitic colonies
8/3/2019 Boiler Life Asessment
15/33
8/3/2019 Boiler Life Asessment
16/33
7-Visual inspection for other parts ofboiler
BurnerWind Box
Hanger for riser pipe
Outer casing
Skin casingBuckstay
8/3/2019 Boiler Life Asessment
17/33
8-Water Quality Survey
This inspection to confirm the cause of the scalegeneration
Inspection items
Check of laboratory analysis method for quality items
Confirmation of water quality results at previous loadoperation
Check of instrument condition on sampling rack usedfor water quality control
Confirmation of PH value and iron/copper balance inthe cycle
8/3/2019 Boiler Life Asessment
18/33
9-Visual Inspection for aux Equipment
This inspection to confirm the cause of the scalegeneration
Condenser hot well.Condenser tube side
Deaerator.LP-feed water heater.Feed water tank.HP-feed water heater.
8/3/2019 Boiler Life Asessment
19/33
10-high pressure parts Inspection details
1. Economizer headers ,coils, Piping from economizer to steamdrum,
2. Steam drum
3. Furnace water walls, screen, roof wall, feeders, riser ,Water wallsheaders
4. Saturation steam pipe
5. Primary, secondary superheater
6. Connecting pipe between primary super heater and secondarysuperheater
7. Reheater
8. Main SH steam pipes
8/3/2019 Boiler Life Asessment
20/33
10-1 Economizer
NDE For headers External visual inspection Internal visual inspection with endoscope Measurement of thickness by UT MT on nozzles welds of the coil tubes and headers attachments MT and UT on circumferential welds between header and conical pieces
NDE For tube External visual inspection Measurement of economizer tube and hanger tube thickness with
endoscope UT for thickness measurements
NDE For Piping from economizer to steam drum External visual inspection for piping, hangers and supports UT for thickness measurements MT and UT on circumferential welds MT on piping attachments MT on the elbows extrados
8/3/2019 Boiler Life Asessment
21/33
10-2 steam drumBefore the NDT inspections, the
internal parts of the drum shall bedismantled
NDE For steam drum External visual inspection Internal visual inspection UT for shell thickness measurements UT for head thickness measurements MT and UT on circumferential and longitudinal welds MT on steam drum attachments (saddles and
accessories) MT on nozzles welds
NDE For downcomers External visual inspection for piping, hangers and
supports UT for thickness measurements MT and UT on circumferential welds MT on piping attachments
8/3/2019 Boiler Life Asessment
22/33
10-3 furnace water walls, screen,roof wall, Feeders and Riser
NDE for furnace water walls, screen, roof wall External visual inspection UT for thickness measurementsMetallographic examination by plastic replicas Samples for destructive test
NDE for feeders and riser External visual inspection UT for thickness measurements
NDE for headers External visual inspection
Internal visual inspection with endoscope UT for thickness measurementsMT on nozzles welds of the coil tubesMT on branches welds and headers attachments, including
drains tubes
8/3/2019 Boiler Life Asessment
23/33
10-4 Saturation steam pipe
NDE for each pipe External visual inspection
UT for thickness measurements
MT and UT on circumferential welds
MT on piping attachments
MT on the elbows extrados
8/3/2019 Boiler Life Asessment
24/33
10-5 Primary,Secondary Superheater
NDE for the headers
External visual inspection Internal visual inspection with endoscopeUT for thickness measurementsUT for head thickness measurementsMT on nozzles welds of the coil tubes
MT on nozzles welds to the shell of the inlet/outlet pipeMT and UT on circumferential welds between header and
heads/ pipingMT on headers attachmentsMetallographic examination by plastic replicas
NDE for CoilsExternal visual inspectionUT for thickness measurements Internal visual inspection with endoscopeHardness measurements
Samples for destructive examinations
10 6 C i i b i
8/3/2019 Boiler Life Asessment
25/33
10-6 Connecting pipe between primaryand Secondary Superheater,Desuperheater ATPS
NDE for connecting pipeExternal visual inspectionUT for thickness measurementsMT and UT on circumferential weldsMT on piping attachments
MT on the elbows extradosMetallographic examination by plastic replicas
NDE for desuperheater ATPSExternal visual inspection Internal visual inspection with endoscopeUT for thickness measurementsMT on circumferential weldsMetallographic examination by plastic replicas
8/3/2019 Boiler Life Asessment
26/33
10-7 ReheaterNDE For each one of the headersExternal visual inspection Internal visual inspection with endoscopeUT for thickness measurementsUT for head thickness measurementsMT on nozzles welds of the coil tubesMT on nozzles welds to the shell of the inlet/outlet pipe
MT and UT on circumferential welds between header andheads/ piping
MT on headers attachmentsMetallographic examination by plastic replicas
NDE For Coils
External visual inspectionUT for thickness measurements Internal visual inspection with endoscopeHardness measurementsSamples for destructive examinations
8/3/2019 Boiler Life Asessment
27/33
10-8 Main SH steam pipes
NDE for each pipe External visual inspection
UT for thickness measurements
MT and UT on circumferential welds
MT on piping attachments
MT on the elbows extradosMT on nozzles welds to the pipe
Metallographic examination by plastic replicas
8/3/2019 Boiler Life Asessment
28/33
8/3/2019 Boiler Life Asessment
29/33