CITY OF COLUMBIA, S.C. FLOOD RECOVERY PROGRAM
CITY COUNCIL BRIEFING
QUARTERLY REPORT
APRIL 19, 2016
CITY OF COLUMBIA FLOOD RECOVERY PROGRAM QUARTERLY REPORT April 19,2016
CONTENTS
A timely update of the progress for the City of Columbia’s Flood
Recovery Program.
STATUS OF PROJECTS
Committed funds and applications dedicated to Flood Recovery
Program.
SUMMARY OF FUNDING SOURCES
A look at where the City of Columbia’s Flood Recovery
Program has accomplished and what’s in store.
RECENT MILESTONES & IMMEDIATE GOALS
1
CITY OF COLUMBIA FLOOD RECOVERY PROGRAM QUARTERLY REPORT April 19,2016
SUMMARY OF FUNDING SOURCES FEMA Public Assistance
Grant
FEMA 406 Hazard
Mitigation
NRCS Waterway Debris Removal
CDBG-Disaster Recovery
404 Hazard Mitigation Grant
Program
Pre-disaster Mitigation Grant Program (PDM)
Flood Mitigation Assistance
Grant Program (FMA)
5-Year Hazard Mitigation Program
• NRCS Waterway Debris Removal • 404 Hazard Mitigation Grant Program • Pre-disaster Mitigation Grant Program
(PDM) • Flood Mitigation Assistance Grant
Program (FMA) • 5-year Hazard Mitigation Plan
FLOOD RECOVERY PROJECT
MANAGEMENT SERVICES
• FEMA Public Assistance Grant • FEMA 406 Hazard Mitigation • CDBG-Disaster Recovery
PLANNING:
CURRENT:
2
CITY OF COLUMBIA FLOOD RECOVERY PROGRAM QUARTERLY REPORT April 19,2016
STATUS OF CITY INFRASTRUCTURE PROJECTS: Current Project List
City of Columbia, SC - DR 4241 FEMA Public Assistance & 406 Mitigation
Project Name Category Total Initial Assessment Amount
Debris Removal (1PW) A 4 $584,912.00
Emergency Protective Measures (1PW) B 53 $7,387,910.00
Road Repairs (2 PW) C 14 $832,277.00
Columbia Canal Repairs (2 PW) D 1 $47,480.890.00
City Owned Building Repairs (3 PW) E 24 $239,116.00
Wastewater System/Columbia Hydroplant Repairs (16 PW) F 95 $7,641,685.00
Multiple Parks to be Repaired (1PW) G 11 $104,117.00
Estimated Sub Total 202 $64,270,908.00
CDBG-Disaster Recovery Projects - To be determined - 0 $19,989,000.00
Estimated Program Total $84,259,908.00
3
CITY OF COLUMBIA FLOOD RECOVERY PROGRAM QUARTERLY REPORT April 19,2016
CDBG-DISASTER RECOVERY FUNDING PROCESS:
CONGRESS HUD
Local
State State Agency
Local Agencies
Publishes a Notice in the Federal Register Administers Directly
and/or Distributes
Awards Funds
Calculates & Announces Allocations
Approves Appropriation
4
CITY OF COLUMBIA FLOOD RECOVERY PROGRAM QUARTERLY REPORT April 19,2016
CDBG-DISASTER RECOVERY FUNDING PROCESS: Action Plan Process
Grantee HUD
Creates, publishes and submits action plan
(on paper and in DRGR)
Reviews and accepts plan
Grantee
Implements activities and draws funds
5
CITY OF COLUMBIA FLOOD RECOVERY PROGRAM QUARTERLY REPORT April 19,2016
STATUS OF PROJECTS COMMUNITY DEVELOPMENT BLOCK GRANT – DISASTER RECOVERY (CDBG-DR) • Allocated funding amount: $19,989,000.00 • Federal Register has not been released. (Internal Review by HUD) CDBG-DR Action Plan preparation
• Used for "Necessary expenses related to disaster relief, long term recovery, and restoration of infrastructure, housing, and economic revitalization."
• Disaster-related in that it clearly demonstrates a connection to addressing a direct or indirect impact of the disaster
• Meets the City’s unmet needs • Meet a National Objective Provide a benefit to low- and moderate-income persons Aid in the prevention of elimination of slums or blight Meet a need having a particular urgency.
6
CITY OF COLUMBIA FLOOD RECOVERY PROGRAM QUARTERLY REPORT April 19,2016
RECENT MILESTONES
• Category A PW complete and submitted to FEMA • Two Project Worksheets obligated Canal engineering Emergency work
• Nine draft Project Worksheets in internal review • Two RFQs issued on Canal project • CDBG-DR direct allocation, $19,989,000 • Established list of 404 mitigation opportunities • Distributed voluntary acquisition letters for property
acquisition 41 voluntary interest forms have been received
• City Code Enforcement is addressing safety hazards with fencing, property cleanup, and boarding-up houses and buildings
• Updated City’s Recovery Program website to include reporting and financial dashboard
Recent Milestones
7
CITY OF COLUMBIA FLOOD RECOVERY PROGRAM QUARTERLY REPORT April 19,2016
IMMEDIATE GOALS • Complete approximately 17 remaining draft Project Worksheets by end
of April and submit for State/ FEMA review • Issue RFQ for water/waste engineering/design by week ending Apr. 22,
2016 • Complete and submit 404 Mitigation application due May 5, 2016 • CDBG-DR kickoff meeting with city staff Develop and submit CDBG-DR action plan
• Establish property acquisition review committee Establish property acquisition criteria Begin acquisitions evaluations or eligibility Determine eligibility Prioritize collectively
8
CITY OF COLUMBIA FLOOD RECOVERY PROGRAM QUARTERLY REPORT April 19,2016
9
Thank You Thank you.