Independent Engineering Service
Hosur – Krishnagiri Project Of NH-7
1. PROJECT LOCATION MAP:
Monthly Progress Report – June 2015 Page 1
Independent Engineering Service
Hosur – Krishnagiri Project Of NH-7
2. EXECUTIVE SUMMARY :
The Government of India (GOI) through Ministry of Shipping Road Transport & Highways
(MORT & H) is contemplating to enhance the traffic capacity and safety for efficient
transportation of goods as well as passenger traffic on the very heavy traffic intensity National
Highways. The Government of India had entrusted to National Highways Authority of India
(NHAI) for the development, maintenance and management of NH-7 from km 33+130 to km
93+000 (59.87km) in the state of Tamil Nadu.
In order to provide a better level of service to the vehicular traffic and to augment the capacity of
NH 07 (NH-44 New) by widening the existing four lane to six lanes divided carriageway facility
including rehabilitation/strengthening of the existing four lane, it has been decided to carry out the
works under NHDP Phase V as BOT (Toll) on Design, Build, Finance, Operate & Transfer
(DBFOT) basis.
3. SCOPE OF THE PROJECT:
The scope of the project include the following during the concession period:
Construction of the project highway as set forth in Schedule–A and as specified in Schedule–B
together with provision of Project Facilities as specified in Schedule–C and standards as set
forth in Schedule–D of the concession agreement with other applicable standard specification.
Operation and Maintenance of the project highway in accordance with the provisions of the
concession agreement of Schedule “K”
Performance and fulfillment of all other obligations of the Concessionaire in accordance with
the provisions of Agreement and matters incidental thereto or necessary for the performance of
any or all of the obligations of the concession agreement by the Concessionaire.
Six laning shall be undertaken and completed by the Concessionaire in conformity with
specifications and standards set forth in Annex- I of Schedule –D of CA.
Monthly Progress Report – June 2015 Page 2
Independent Engineering Service
Hosur – Krishnagiri Project Of NH-7
4. PROJECT MILE STONES :
SR. NO
.MILESTONES
PERIOD FROM APPOINTMEN
T DATEDESCRIPTION
1 Milestone - I 255 days
255 days from the appointed date i.e. 16-02-2012 – Commenced construction of project highway and expended not less than ten percentages (10%) of the total capital cost of the project set forth in the financial package.
2 Milestone - II 512 days
512 days from the appointed date i.e. 27-01-2013 – Commenced construction of all bridges and expended not less than thirty five percentage (35%) of the total capital cost of the project set forth in the financial package.
3 Milestone - III 717days
717 days from the appointed date i.e. 28-10-2013 – Commenced construction of all facilities of the project and expended not less than seventy percentage (70%) of the total capital cost of the project set forth in the financial package.
4
Scheduled Six Laning with Service Lane
Date
912days
The Scheduled Six Laning date shall occur on the 912th (Nine Hundred and Twelve) day from the appointed date i.e. 04-12-2013 On or before the scheduled six laning date, the Concessionaire shall have completed six laning projects.
Mile stones –I, II and III have already been achieved by the Concessionaire.Note: For Schedule six laning EOT – I approved up to 30 th May 2014. EOT – II submitted 15th Nov 2015 by the Concessionaire and recommended by IE up to 03rd May 2015 Mile Stone :
Sl Mile Stone
Total days
Date as per CA
Actual date Percentage
EPC Cost (Crores)
To be Expended (Crores)
Expended (Crores)
1Mile Stone -
1 25516.02.2012 16.02.2012
10%925.4
4 92.54 118.14
2Mile Stone -
2 51230.10.2012 27.01.2013
35% 323.90 325.05
3Mile Stone -
3 71723.05.2013 28.10.2013
70% 647.81 666.39
4
Scheduled six laning
date 912
04.12.2013 04.12.2013100% Progress
Time extension recommended
by IE up to 03rd
May-2015Note: 1. Concessionaire submitted “PCC” and it is under progress( Review). 2. Schedule – I Tests are under progress.
Monthly Progress Report – June 2015 Page 3
Independent Engineering Service
Hosur – Krishnagiri Project Of NH-7
5. SALIENT FEATURES :
The Authority National Highways Authority of India
Name of the Project
Six laning of Hosur-Krishnagiri Section of NH-07 from km 33+130 to km: 93+000 (Length – Km 59.87) in the State of Tamil Nadu Under NHDP Phase V as BOT (TOLL) on DBFOT basis.
Independent Engineer / Consultants
CDM Smith Inc. In Joint Venture withWilbur Smith Associates Pvt Ltd
Agreement date of IE: 14th Aug 2012The Concessionaire M/s Hosur-Krishangiri Toll Road LimitedThe EPC Contractor M/s Reliance Utility Engineers Pvt.Ltd.Construction Contractor M/s L & T Limited.Date of agreement 2nd July 2010
Period of Construction 30 Months
Date of Commencement of Construction 7th June 2011
Date of Completion of Construction 4th December 2013
The Concession Period 24 yearsProject Capital Cost 925.44 Crores.₹EPC Cost 840.00 Crores₹Project Length 59.870 kms₹Lenders Engineer M/s. Frischman PrabhuLenders Name Canara Bank-MumbaiLenders Contribution 555.00 Crores.₹Premium to NHAI 66.90 Crores with an escalation of 5% per year₹Contribution by Concessionaire 370.44 Crores₹Flyover 6 Nos (Repair -3, New – 3)Vehicular Under Passes 5 Nos ( New Construction)Pedestrian Under Passes 8 Nos (New Construction)Toll Plaza 1 No (Existing) @Ch:87+500Major Bridges 1 No.Minor Bridges 13 Nos (Widening- 3, New- 4, Repair-6)Box/Slab Culverts 109 Nos (Widening and Repair, Rehabilitation)Pipe Culverts 34 Nos (Widening and Repair, Rehabilitation)Track Lay bay with Rest Area 1 No.Major & Minor Junctions 9 & 66 Nos Respectively Length of Service Road 54.38 kms Bus Byes with Bus Shelters 66 Nos (LHS-30nos,RHS 36nos)
Change of scope Upgraded PUP at Km.44+950, Box culvert at Ch.40+968
6. PROJECT HIGHWAY PAVEMENT CONFIGURATIONS:
Monthly Progress Report – June 2015 Page 4
Independent Engineering Service
Hosur – Krishnagiri Project Of NH-7
Scope of Work and Cross Sections:
Description Scope Design Chainage (km)From To Length
Main Carriage Way Six lane 33.130 93.000 59.87
Service Road Two lane 33.130 93.000 27.19 both sides
The Existing LHS (ie Hosur to Krishnagiri) carriageway between Km 68.100 to Km68+900 is proposed to be used as carriageway of Service road on LHS.Pavement Configurations:
CarriagewayType of
carriageway (Flexible/Rigid)
Chainage (from -
to)
Name of Layer
Design Thickness
in mm
Total Thickness
MCW Flexible
33+130 to 93+000
except toll plaza
location
BC 40 mm
610mmDBM 120 mm
WMM 250 mm
GSB 200 mm
Sub grade 500 mm 500mm
Service road Flexible 33+130 to 93+000
BC 40 mm
540mmDBM 50 mm
WMM 250 mm
GSB 200 mm
Sub grade 500 mm 500mm
Rigid Pavement for Toll Plaza :
The Location at Ch. Km 87+500. Toll Plaza Expansion and Regid pavement (PQC) drawing submitted from Concessionaire for review and work is in progress.
Rest Area:
The available land between the carriageways from Ch. Km 68+300 to 68+800 LHS is to be developed as truck lay bye and Rest area Facilities, and the existing road to be used as carriage way of service road on LHS
7. Typical Cross-Section:
Monthly Progress Report – June 2015 Page 5
Independent Engineering Service
Hosur – Krishnagiri Project Of NH-7 Typical cross sections are detailed as below:Sl. no
Type of Cross Section Code Length ( m)
1
6 – lane cross section with raised median + embankment slope(2H:1V)on both sides + unlined longitudinal drain on both sides + both sides 7.0 m paved service road with 0.75 m earthen shoulder on both sides + utility corridor on both sides in non-built up areas
Type – 1 1460
2 6 – lane cross section with raised median + embankment slope(2H:1V), unlined longitudinal drain & utility corridor on both sides in non-built up areas Type – 2 26880
3
6 – lane cross section with raised median +1.50 m wide separator – cum –lined covered drain (RCC) with M.S railing between paved shoulder & 7.00 m paved service road on both sides- 1.50 m wide footpath – cum – utility duct (RCC) on both sides in urban areas
Type – 3 9430
4
6 – lane cross section with raised median +1.50 m wide separator – cum –lined covered drain (RCC) with M.S railing between paved shoulder & 7.00 m paved service road on both sides- 1.50 m wide footpath – cum – utility duct (RCC) on both sides in urban areas ( Shifting of Existing Center line to L.H.S)
Type – 4 3375
5
6 – lane cross section with raised median +1.50 m wide separator – cum –lined covered drain (RCC) with M.S railing between paved shoulder & 7.00 m paved service road on both sides- 1.50 m wide footpath – cum – utility duct (RCC) on both sides in urban areas ( Shifting of Existing Center line to R.H.S)
Type – 5 530
6
6 – lane Approach cross – section for Flyover/ Underpass with R.E Wall/R.C.C Retaining Wall upto FRL with friction slab & RCC Crash barrier ( excluding Via – Duct portion) + raised median + 1.50 m wide separator – cum – lined covered drain (RCC)between approach & 7.00 m paved service road on both sides + 1.50 m wide footpath – cum – utility duct ( RCC) on both sides
Type – 6 6810
7
6 – lane Approach cross – section for Flyover/ Underpass with R.E Wall/R.C.C Retaining Wall upto FRL with friction slab & RCC Crash barrier ( excluding Via – Duct portion) + raised median + 1.50 m wide separator – cum – lined covered drain (RCC)between approach & 7.00 m paved service road on both sides + 1.50 m wide footpath – cum – utility duct ( RCC) on both sides (Shifting of Existing Center line)
Type – 7 1545
8 6 – lane cross section with raised median + embankment slope (2H:1V)&unlined longitudinal drain on both sides in hilly/forest areas Type – 8 5700
9 Toll Plaza Toll Plaza 450
10 Major bridge Major bridge 120
11 Existing Flyover with 6 – lane configuration with exiting service road. Existing Flyover 2520
12
Uni –directional flyover with 3 – lane Flyover Approach cross – section with 13.50 m deck width R.E Wall/R.C.C Retaining Wall up to FRL with friction slab RCC Crash barrier (excluding Via-Duct portion)+1.50m wide separator-cum-lined covered drain (RCC)between approach & 7.00m paved service road on RHS +1.50m wide footpath-cum utility duct(RCC) ON RHS.
Uni – directional
Flyover1050
8. STATUS OF MOBILIZATION OF INDEPENDENT ENGINEER
Monthly Progress Report – June 2015 Page 6
Independent Engineering Service
Hosur – Krishnagiri Project Of NH-7
SIName Designation
DateNo Mobilized
Key Personnel (Professional Staffs)1 TBN Team Leader Not Mobilized **2 Mr. C.V.Krishna Reddy Acting Team Leader cum
Resident Engineer01.12.2012
3 Mrs. Padmaja Jayakumar Sr. Bridge Design Engineer 05.09.20124 Mr. Gagan Trivedi Highway Design Engineer 05.09.20125 Mr. K.C.Sathiya Murthi Bridge / Structural Engineer 04.09.20126 Dr .Jimmy Thomas Sr. Pavement Specialist 15.10.20127 Mr. N.Madhsudana Chowdary Sr. Quality cum Material Expert 15.10.20128 Mr. P. Hariharan Traffic & Transportation Expert 9 Mr. R. Krishna Murthy Road Safety Expert 05.09.201210 Mr. Shankar Narayana Financial Expert 15.11.201211 Mr. J.Dhanvanth Legal Expert
Sub-Professionals Staffs:1 Mr. S.Ramesh Babu Survey Engineer-1 08.10.20122 TBN Survey Engineer-2 Not Mobilized3 Mr. R.Ashok Kumar Asst. Highway Engineer-1 03.04.20134 TBN Asst. Highway Engineer-2 Not Mobilized5 TBN Asst. Bridge Engineer-1 Not Mobilized
6 TBN Asst. Bridge Engineer-2 Not Mobilized
7 Prasanth .K. DeshpandeAsst. Quality cum Material Engineer-1 19.01.2015
8 Mr. J.Selva KumarAsst. Quality cum Material Engineer-2 11.10.2012
9 TBN Quantity Surveyor -1 Not Mobilized10 Mr. Ayyappan Nair CAD Expert-1 16.11.201211 Mr. Shashikanth.Joshi Electrical Engineer 22.09.201212 Mr. V.Rangarajan HTMS/Toll Expert 22.09.201213 Mr. Rajesh varghese Environmental Engineer 10.10.2012
14 Dr. K. Malla ReddyHorticulture cum Landscaping Expert 22.09.2012
TBN: To be Named **: Shri. P. J. Xavier worked as Team Leader from 27.08.2012 to 06.03.2014 and resigned on personal reason.
Monthly Progress Report – June 2015 Page 7
Independent Engineering Service
Hosur – Krishnagiri Project Of NH-7
8.1 ORGANIZATIONAL CHART :
Monthly Progress Report – June 2015 Page 8
A.Br.Engr-2TBN
A.Br.Engr-1TBN
Sr.B.D.Engr.Padmaja Jayakumar
Fin.Exp. M Sankaranarayana
Sr.Q. cum M.E Madhusudana Chowdary
Acting Team Leader C.V.Krishna reddy
T&TEP. Hariharan
Team Leader TBN
Sr. Pave.Spec. Dr Jimmy Thomas
AHE 2TBN
AHE 1Ashok kumar
ORGANIZATIONAL CHART Project No:- 1213006 CDM SMITH INC.IN JV with WSAPL
Independent Engineer Services for Six Laning of Hosur – Krishnagiri Section of NH-7 from Km33.130 to Km 93.000(Lenth Km-59.870) in the State of Tamil Nadu
on DBFOT Basis under NHDP – Phase - V
Br/St. Engr.K C Sathyamurthi
AQ cum ME-1J.Selvakumar
AQ cum ME-2 Prasanth .K.D
eshpande
Road.S.Exp.R.Krishnamoorty
H.D.E GaganTrivedi
L.Exp. Dhanvanth. J
El.ES. Joshi
HTMS/T.EV.Rangarajan
Env.ERajesh Varghese
Survey Engr-1S.Ramesh Babu
CAD ExpAyyapan Nair
Office ManagerAshok
Com.OperatorHemalatha
StenoSathya
Photocopy M.OperatorDeepa
CashierP.Lokesh
AccountantG.T.Divya
Office BoyRagul
Guard-1Karcithappa
Guard-2 Anbu
HorticulturistDr. Malla
Reddy
Survey Engr- 2TBN
Qty. Surveyor TBN
Independent Engineering Service
Hosur – Krishnagiri Project Of NH-7
9. INSPECTION AND MONITORING OF THE CONSTRUCTION WORKS.
PROGRESS UP TO 30 June 2015
1a. HIGHWAYS - MCW & Service Road
Sl Description Unit Total Scope (Km) Completed Percentage achieved %
1 Clearing & Grubbing Km 159.17 158.49 99.57%2 Excavation Km 159.17 158.09 99.32%3 Embankment Top Km 159.17 157.39 98.88%4 Sub Grade Top Km 159.17 157.29 98.82%5 GSB Km 159.17 157.22 98.77%6 WMM-1 Km 159.17 154.81 97.26%7 WMM - 2 Km 159.17 153.65 96.53%8 DBM - Widening Km 165.87 163.79 98.75%9 DBM - Overlay Km 101.70 101.70 100.00%
10 BC Km 172.92 156.30 90.38%
1b. HIGHWAYS - MCWSl Description Unit Total Scope (Km) Completed Percentage achieved
1 Clearing & Grubbing Km 111.49 111.49 100.00%
2 Excavation Km 111.49 111.49 100.00%3 Embankment Top Km 111.49 111.49 100.00%4 Sub Grade Top Km 111.49 111.49 100.00%5 GSB Km 111.49 111.49 100.00%6 WMM-1 Km 111.49 111.49 100.00%7 WMM - 2 Km 111.49 111.49 100.00%8 DBM - Widening Km 111.49 111.49 100.00%9 DBM - Overlay Km 101.7 101.70 100.00%
10 BC Km 118.54 118.54 100.00%
11 PQC Km 1.2 Existing (Toll Plaza at Ch. 87+330 to 87+930 – Both Sides)
1c. HIGHWAYS -Service Road
Monthly Progress Report – June 2015 Page 9
Independent Engineering Service
Hosur – Krishnagiri Project Of NH-7
Sl Description Unit Total Scope (Km) Completed Percentage achieved
1 Clearing & Grubbing Km 47.68 4798.57%
2 Excavation Km 47.68 46.697.73%
3 Embankment Top Km 47.68 45.996.27%
4 Sub Grade Top Km 47.68 45.896.06%
5 GSB Km 47.68 45.73 95.91%
6 WMM-1 Km 47.68 43.32 90.86%
7 WMM - 2 Km 47.68 42.16 88.42%
8 DBM Km 54.38 52.3 96.18%
9 BC Km 54.38 37.76 69.44%
10 PQC `Km 0.9Existing (At Ch. 39+640 to 40+540 LHS
Service Road)
** The Existing carriageway LHS (i.e. Hosur to Krishnagiri ) carriageway between Km 68.100 to Km 68.900 is proposed to be used as carriageway of service road on LHS.
9.1.d. Structure:
Sl. No Structure Unit As Per
CA Additional Total Work to be done at site
In Progress Completed Remarks
1 Box Culverts Nos 108 1 109 99 1 97 1 no yet to start
2 Pipe Culverts Nos 32 2 34 30 1 29 3 nos not in site,1 no
cross road3 Minor Bridge Nos 10 - 10 4 4 4 Major Bridge Nos 1 - 1 1 1 5 Flyovers Nos 3 - 3 3 3
6 Vehicular Under pass Nos 5 - 5 5 5
7 Pedestrian Under pass Nos 8 - 8 8 8
8 Girders casting - Nos Nos 224 - 224 224
9RE wall Panel Casting
Sqm 68,500 - 68,500 68,500
10 RE wall Erection Sqm 67,252 - 67,265 67,265
9.1.e.Major structures status:
Monthly Progress Report – June 2015 Page 10
Independent Engineering Service
Hosur – Krishnagiri Project Of NH-7
Sl.no Description Location Status Remarks
1 Major Bridge 77+993 Completed miscellaneous works are in progress
2 Minor Bridge 33+297 Completed miscellaneous works are in progress.
3 Minor Bridge 38+520 Completed miscellaneous works are in progress
4 Minor Bridge 47+035Completed miscellaneous works are in progress.
Completed miscellaneous works are in progress.
5 Minor Bridge 68+340 Completed miscellaneous works are in progress. 6 Flyover 39+022 Completed miscellaneous works are in progress.
7 Flyover 40+990Completed miscellaneous works are in progress.
Completed miscellaneous works are in progress.
8 Flyover 92+385 Completed miscellaneous works are in progress.
9 VUP 45+950 Completed miscellaneous works are in progress.
10 VUP 61+845 Completed miscellaneous works are in progress
11 VUP 62+850 Completed miscellaneous works are in progress
12 VUP 77+412 Completed miscellaneous works are in progress
13 VUP 84+760 Completed miscellaneous works are in progress
14 PUP 34+000 Completed miscellaneous works are in progress.
15 PUP 36+550 Completed miscellaneous works are in progress
16 PUP (VUP) 44+950 Completed miscellaneous works are in progress
17 PUP 53+620 Completed miscellaneous works are in progress
18 PUP 78+536 Completed miscellaneous works are in progress
19 PUP 82+475 Completed miscellaneous works are in progress
20 PUP 87+010 Completed miscellaneous works are in progress
21 PUP 91+500 Completed miscellaneous works are in progress
RE WALL STATUS - As on 30.06.2015
Monthly Progress Report – June 2015 Page 11
Independent Engineering Service
Hosur – Krishnagiri Project Of NH-7
StructureLocation Wall Structure RE WALL
AREA (Sqm) Completed Balance Remarks
34+000 RE WALL PUP 2,676.0
2,675.980 - completed
36+550 RE WALL PUP 2,820.9
2,820.910 - completed
39+022 RE WALL Flyover 9,365.0
9,365.000 - completed
40+990 RE WALL Flyover 5,951.4
5,951.407 - completed
44+950 RE WALL PUP 4,047.4
4,047.350 - completed
45+950 RE WALL VUP 6,320.0
6,320.000 - completed
61+845 RE WALL VUP 5,623.5
5,623.514 - completed
62+850 RE WALL VUP 5,964.0
5,964.000 - completed
77+410 RE WALL VUP 7,050.4
7,050.420 - completed
82+475 RE WALL PUP 2,580.0
2,580.000 - completed
84+760 RE WALL VUP 7,095.5
7,095.507 - completed
87+000 RE WALL PUP 2,717.3
2,717.300 - completed
91+510 RE WALL PUP 2,550.0
2,550.000 - completed
92+385 RE WALL Flyover 2,503.2
2,503.157 - completed
67,265
67,265
-
53+620 Retaining wall (RCC) PUP 2,520.
0 2,520.00
0 - completed
78+536 Retaining wall (RCC) PUP 1,750.
0 1,750.00
0 - completed
- 4,270.
00 4,270.
00 -
-
9.1.f. STATUS OF PROJECT FACILITIES :
Monthly Progress Report – June 2015 Page 12
Independent Engineering Service
Hosur – Krishnagiri Project Of NH-7
Sl.No Description UoM Scope Status
1 Toll Plaza Ls 1
Toll plaza administration building structure work in progress.Toilet block completed.ETC work in progress.
2 Rest Area No 1
Paver Block fixing work in progress in parking area. Restaurant, toilet block and dormitory buildings work in progress.
3 Bus Bay No 66
45 No’s Paver block completed.03 No’s Bus Bay GSB Completed08 Nos Bus bay subgrade completed06 No’s WMM completed.04 No’s excavation in progress
4 Bus Shelter No 66 40 No’s erected.
5 Minor Junction No 6722 No’s BC completed14 No’s DBM completed20 No’s WMM completed
6 Major Junction No 9 2 No’s BC completed
7 Road Marking Km 172.82 130 Km completed
8
Providing All Sign Boards No 1115 901 No’s competed
Delineatorsa) Curve Sectionb) Above 3m height of
Embankment
No 1928 Nos163 nos 750 Nos completed
Studs No 24180 18,000 No’s completed
9 MS Railing/Guard Rails KM 40.000 26 Km completed. 18.5 km metal beam crash barrier completed.
10
Highway Lightinga) Built up Area b) Rest Area c) Toll Plaza d) Structural
location( PUP& VUP in rural section
Km/Nos14.970Km1 No 1 No9.00 Km
435 No’s EB poles erected.707No’s foundation pedestal completed. Laying of HDPE / DWC pipes and laying of UE cables is in progress.Bus bay -66 nos
11
Pedestrian Facilities: a) Pedestrian guard railb) Pedestrian walk wayc) Foot path/ Utility Duct
Km/Nos66 Nos
44.430 Kms44.430 Kms
Pedestrian guard rail- 40 NosPedestrian Walkway- 1 Km CompletedFoot Path/ Utility Duct-1 km Completed
12 Landscaping and Tree Plantation No 15000 3000 Nos Planted.
13 Avenue Plantation No 12000 5650 No’s completed
Progress up to 30-06-2015.
Monthly Progress Report – June 2015 Page 13
Independent Engineering Service
Hosur – Krishnagiri Project Of NH-7
Description Target Achieved Ahead / -Behind
Physical Progress ( % ) 100.00 94.75 -5.25
Cumulative Physical Progress:
Physical ProgressUp to May -2015 This month Up to June-2015
Cumulative Schedule Progress (%) 100 0 100.00Cumulative achieved progress (%) 93.62 1.13 94.75
Cumulative Financial Progress - work done 840.00 Crs₹
DetailsUp to May -2015 This month Up to June-2015
Cumulative Schedule Expenditure (Rs. in Crores) 817.750 20.230 837.980
Cumulative Achieved Expenditure (Rs.in Crores) 788.992 11.007 799.999
(%) Cumulative Achieved Progress 93.93% 1.31% 95.24%
Financial Progress – (Expended Project Cost)
Sl Description Amount Remarks
1 Total work done up to June - 2015 Rs. 800.00 Crores
Expended EPC cost up to June. - 2015 Rs. 800.00Crores For 840 Crores
Overheads and other expenses Rs.83.50Crores
Expended Total Project cost up to June - 2015 Rs. 883.00 Crores For 925.44Crores
9.2 Design / Drawing Submission Status :
Monthly Progress Report – June 2015 Page 14
Independent Engineering Service
Hosur – Krishnagiri Project Of NH-7
9.2.b. Structures:
Sl. No Description Unit
Total Scope Submitted
Balance to be submitted Remarks
1 Major Bridges No 1 1 -
2 Minor Bridges No 4 4 -
4 Fly Over No 3 3 -
5 Vehicular Under Pass No 5 5 -
6 Pedestrian Under Pass No 8 8 -
7 Pipe Culverts No 30 29 -
8 Box/Slab culverts No 99 98 1
9 RE wall No 14 14 -
10 RCC Wall No 2 2 -
9.2.C.Drawing Status of Project Facilities For Six-Laning (Schedule - C)Sl Description
as per CA schedule -
'C'
Drawings submitted to IE
from Concessionaire
Reviewed from IE Lr. No
Status Drawing
Remarks
Monthly Progress Report – June 2015 Page 15
9.2.a. Highways :Sl.n
o Description Remarks1 Base plan Submitted2 Project Quality Plan Submitted3 Construction Programme Submitted4 Survey & Engineering Report Submitted5 Environmental Management Plan Submitted6 Health & safety Management Plan Submitted7 Typical C/S Submitted8 Submission of Traffic Assessment and pavement Design Report Submitted
9Submission of plan and profile drawing for Main Carriageway and Service Road Submitted
10 Submission of Project Facilities as per modified Schedule – “C”Under
Progress
Independent Engineering Service
Hosur – Krishnagiri Project Of NH-7
Lr. no.
1 Toll plaza 1661/15.06.2015 1598/06.05.2015
824 / 11.02.2015 134/27.05.2015
Review in progress
Administrative Building and Toll Plaza expansion on LHS started without layout approval of Toll
Plaza Expansion
2 Road side furniture plan
i
Traffic Signs: It includes Road side signs, over head signs and kerb mounted signs.
1211 / 10.7.2014 742/ 19.12.2014 Review in
progress Work is in progress
ii
Over head signs :- 16nor (excluding toll plaza)
1554/07.04.2015 1082/08.06.2015 Review Completed Work is in progress
a) 14 Nos - cantiliver (4.00 × 1.2 m)
b) 2 Nos over head sign (3 lane width × 1.2 m)
iiiPavement Marking
1359/ 28.10.2014
789 14.01.2015
Review Completed Work is in progress
iv
LED Traffic Beacons
1619 /15.05.2015
136/ 29.05.2015 Review
Completed Work is in progress
v
Delineators and studs
1606/08.05.2015
780 / 12.01.2015 and
069/18.03.2015
Review in progress
Delineators and studs work in progress
vi
Boundary stones & 200m stones 1026 /
06.05.2014 789/14.01.2015 Review Completed
Work Started, GFC has to be submit
vii
Hectometer / Kilometer stones
3 Highway Lighting
1274 / 25.08.2014
768 / 31.12.2015 Review in progress
Work is in progress
Monthly Progress Report – June 2015 Page 16
Independent Engineering Service
Hosur – Krishnagiri Project Of NH-7
4 Pedestrian Facilities
(i)Pedestrian guardrail (ii)Walkway
1236 / 28.07.2014 529 / 11.8.2014
Pending with
HKTRPL
Work is in progress
(iii) Ramp/Steps - - - Not required
(iv) Pedestrian Crossing
- - - Drawings Not submitted
5 Landscaping and tree plantation
i) Median Plantation 442 / 27.08.2013 279 / 20.09.2013 Review
Completed Started but slow progress
ii) Landscaping
1160 / 11.06.2014 153 / 24.06.2014 Review in
progress Work is in progress
iii) Avenue Plantation 442 / 27.08.2013 279 / 20.09.2014 Review
CompletedStarted but very
slow progress6 Rest Area (Service Area)
Rest area layout
1387 / 21.11.2014 759 / 26.12.2014
Review in progress Work is in progress
Rest area building and other facilities
1632/25.05.2015 757 / 26.12.2014
7 Bus lay bay & Bus Shelter
i) Bus lay bay Drawings - Main carriageway & service road
1216 / 14.07.2014 795/ 20.01-2015 Review in
progress Work in Progress
ii) Bus Shelter 912 / 25-12-2013 789 / 14-01-2015 Review Completed Work is in progress
8Highway Patrol Facility provided
9 Ambulance Facility provided10 Cranes Facility Provided
11 ATMS 1106 / 29.04.2014 306 / 06.12.2014
Pending with
HKTRPL
Design and Drawing not submitted
9.2.d. Drawing Status for StructuresSl. Structure Chainage Submitted Status1 Pipe Culvert 23Nos CDM/252 dated 12.02.2014 GFC
Monthly Progress Report – June 2015 Page 17
Independent Engineering Service
Hosur – Krishnagiri Project Of NH-7CDM/307 dated 18.03.2014
6 NosCDM 376 dated 12.05.2014
GFCCDM: 377 dated 13 May 2014
2 Box Culvert98 Nos
CDM/ 935 dated 31.03.2015CDM/308 dated 18.03.2014CDM/464 dated 26.06.2014CDM/444 dated 16.06.2014
HKTRPL/1011 dated 28.02.2014CDM/934 dated 31.03.2015
Reviewed
1 no CDM 230/ 10.06.2013 Under Review
3 MNB
33+297 HKTRPL:1099/ 21.04.2014 CDM : 413 dated 29.05. 2014 Reviewed
38+520 CDM:920 dated 24.03.2015 GFC
47+030 CDM/921 dated 24.03.2015 Reviewed
68+342 HKTRPL 382 dated 04.01.2014 Approved
4 MJB
77+993 Sub Structure
HKTRPL: 1043 dated 26.03.2014 GFC submitted
77+993 Super Structure HKTRPL 684 Dated 18.07.2013 GFC Submitted
5PUP
7 Nos HKTRPL 381 dated 04.01.2014 GFC1 no HKTRPL: 1156 dated 26.5.2014 Reviewed
6
VUP
5 Nos Sub Structure HKTRPL : 382 dated 04.01.13 GFC
5 Nos Superstructure
HKTRPL: 1039 dated 20.03.2013 CDM : 332 dated 04.04.2014
Review completed,
queries from IE to be complied by Concessionaire
7 FO
39+022 CDM 722 dated 03.12.2014 Reviewed40+990 CDM 217 dated 22.01.2014 GFC
92+385 Except Pier P3 HKTRPL: 382 dated 04.01. 2013 GFC92+385 Pier P3 CDM 214 dated 21 Jan 2014 GFC
40m Obligatory Span HKTRPL: 1170 dated 12.06.2013CDM : 332 dated 04.04.2014
Review completed,
queries from IE to be complied by Concessionaire
20m Span- Superstructure HKTRPL: 385 dated 04.01.2013
GFC
8 RE Wall
6 Nos CDM 402 dated 22.05.2014 GFC
8 Nos
CDM : 635 dated 20.10.2014CDM: 636 dated 20.10.2014CDM: 637 dated 20.10.2014
HKTRPL: 1348 dated 09.10.2014
Review Completed
.
Monthly Progress Report – June 2015 Page 18
Independent Engineering Service
Hosur – Krishnagiri Project Of NH-7
9
Miscellaneous Drawings
( VUP, FO MJB & MNB
HKTRPL letter no. 386 dated 04.01.2013 CDM : 458 dated 26.06.2014 Reviewed
10Expansion
Joint CDM: 214 dated 21.01.2014 GFC
11
Floor Protection
works CDM: 214 dated 21.01.2014GFC
12 PCC Toe wall HKTRPL letter no. 233 dated 08.09.2012 Under Review
13PCC Retaining
WallCDM: 280 dated 26.02.2014
HKTRPL: 1071 dated 03.04.2014 Review Completed
14
Design and Drawings for
RCC HKTRPL: 782 dated 23.09.2013Under Review
15
Drainage Design Report with precast
box drain HKTRPL: 783 dated 23.09.2013
Under Review
16POT- PTFE Bearings HKTRPL: 868 dated 02.12.2013 Reviewed
17Rectangular
Drain CDM: 426 dated 04.06.2014 GFC
18
Friction slab (Except RE wall
Portion)CDM: 397 dated 20.05.2014 GFC
19
Friction slab with Crash
Barrier
HKTRPL: 800 dated 09.10.2013 CDM: 251 dated 13 Feb 2014
20
Toll Plaza -Administrative
Building
HKTRPL: 1661 dated 15.06.2015CDM : 146 dated 02.06.2015 Under Review
21Toll Plaza-
Toilet BlockHKTRPL: 1387 dated 21.11.2014
CDM 411 dated 28.05.2014 Under Review
22
Rest Area - Restaurant
Building CDM: 534 dated 12.08.2014 Under Review
23Rest Area –
Toilet Building HKTRPL Letter No.1632 Dated 28 May 2015 Under Review
24
Rest Area - Dormitory
Building HKTRPL letter no.1572 dated 21.04.2015 GFC
25Rehabilitation of Structures
HKTRPL: 778 dated 28.09.2014 HKTRPL: 1639 dated 01.06.2015 Under Review
9.2.e. Correspondence with NHAI:S.No Date Letter No Subject
1 01.06.2015 CEI-Pj/NHAI/1236006/PD/2015/97 VIP- reference - Matter raised under Zero Hour by Sh. K. Ashok Kuumar
2 01.06.2015 CEI-Pj/NHAI/1236006/PD/2015/98 Monthly Inspection Report may 2015
Monthly Progress Report – June 2015 Page 19
Independent Engineering Service
Hosur – Krishnagiri Project Of NH-7
3 02.06.2015 CEI-Pj/NHAI/1236006/PD/2015/99 RTI application from Mr. S. N. Selvaraj
4 03.06.2015 CEI-Pj/NHAI/1236006/PD/2015/100Comments Requested - The Commissioner, depertment of Rural Development & Panchayat Raj, shoolagiri- seeking Approval
5 03.06.2015 CEI-Pj/NHAI/1236006/PD/2015/101 VIP - Reference - Hon'ble MP Shri. Ashok Kumar
6 11.06.2015 CEI-Pj/NHAI/1236006/PD/2015/102
Modified Typical Cross Section at Km. 39+450 to km. 39+650 BHS & Km. 40+520 to Km. 40+665 BHS and Proposal to retain the existing drain at Km. 40+665 to Km. 40+950 RHS.
7 12.06.2015 CDM/CEI/1213006/1091 Notice to Commence Arbitration
8 18.06.2015 CEI-Pj/NHAI/1236006/PD/2015/103Change of Scope revised estimate - Box Culvert at Rayakottai Junction (Km. 40+970) - Submission of Comprehensive Proposal
9 18.06.2015 CEI-Pj/NHAI/1236006/PD/2015/104 Invoice for the Month of May 201510 17.06.2015 CDM/CEI/1213006/1109 Typical details of Utility Duct
11 17.06.2015 CDM/CEI/1213006/1113Article 41 of Concession Agreement - Change in Law - Claim for Reimbursement of additional Payment due to Change in minimum Wages.
12 19.06.2015 CEI-Pj/NHAI/1236006/PD/2015/105 Requesting for Flyover and its importance in Hosur Town - Shri Manohraran Ex-MLA
13 20.06.2015 CEI-Pj/NHAI/1236006/PD/2015/106 Damages to the works (PGR) at Bus Bay Km. 71+920 RHS
14 20.06.2015 CEI-Pj/NHAI/1236006/PD/2015/107
Road to Guru Bhagawan Temple at Sy. No. 69/1A & 69/1B, Nallaganakothapalli Village - Konneripalli, Hosur Taluk - Requested by Shri Ponnurangam
15 20.06.2015 CEI-Pj/NHAI/1236006/PD/2015/108 Request to Provide "U" Turn at Seetharam Medu in Nh - 7 of Hosur Town
16 20.06.2015 CEI-Pj/NHAI/1236006/PD/2015/109 Comments Requested - Hitha Shree - Seeking Approval
17 20.06.2015 CEI-Pj/NHAI/1236006/PD/2015/110 Damages to the MBCB works between Km. 34+000 to 38+000
18 23.06.2015 CEI-Pj/NHAI/1236006/PD/2015/111 Submission of Monthly Progress Report May 2015
19 24.06.2015 CEI-Pj/NHAI/1236006/PD/2015/112 Addakuruki at Ch. 55+180 RHS Public request not to Close by Grill Gate
20 29.06.2015 CDM/CEI/1213006/1133 Review Comments on Junction Improvement Drawings for flyovers, VuP's and PUP's
9.2.f. Correspondence with CPM – HKTRPL :S.No Date Letter No Subject1 01.06.2015 CEI-Pj/NHAI/1213006/HKTRPL/2015/140 Implementation of Safety Measures
Monthly Progress Report – June 2015 Page 20
Independent Engineering Service
Hosur – Krishnagiri Project Of NH-7
2 01.06.2015 CEI-Pj/NHAI/1213006/HKTRPL/2015/141 Provision of Safety Barrier at Medians from 23m to 4.0
3 01.06.2015 CEI-Pj/NHAI/1213006/HKTRPL/2015/142 Non Compliance report4 01.06.2015 CEI-Pj/NHAI/1213006/HKTRPL/2015/143 Typical details of Utility Duct5 02.06.2015 CEI-Pj/NHAI/1213006/HKTRPL/2015/144 Non Compliance Report6 02.06.2015 CEI-Pj/NHAI/1213006/HKTRPL/2015/145 Monthly inspection Report
7 02.06.2015 CEI-Pj/NHAI/1213006/HKTRPL/2015/146 Revised Drawings of toll Plaza Administrative Building
8 06.06.2015 CEI-Pj/NHAI/1213006/HKTRPL/2015/147 Submission of DLC & PQC Method statement9 08.06.2015 CEI-Pj/NHAI/1213006/HKTRPL/2015/148 Methodology for Closing NCR - 56
10 08.06.2015 CDM/CEI/1213006/1081 Laying of kerb at Ch. 38+580 to 38+800 LHS
11 08.06.2015 CDM/CEI/1213006/1082Review Comments for Gantry sign boards (cantilever type and overhead sign) from Km. 33+130 to Km. 93+000
12 09.06.2015 CEI-Pj/NHAI/1213006/HKTRPL/2015/149 Non Compliance Report13 09.06.2015 CEI-Pj/NHAI/1213006/HKTRPL/2015/150 Revised Toll Plaza Layout14 09.06.2015 CEI-Pj/NHAI/1213006/HKTRPL/2015/151 Review and Concurrence of Bar Bending Schedule
15 13.06.2015 CEI-Pj/NHAI/1213006/HKTRPL/2015/153 Issuance of Provisional Completion Certificate - Status of works under Schedule - "B" and "C"
16 16.06.2015 CEI-Pj/NHAI/1213006/HKTRPL/2015/154
Modified Typical Cross Section at Km. 39+450 to Km. 39+650 BHS & Km. 40+520 to Km. 40+665 BHS and proposal to retain the existing drain at Km. 40+665 to Km. 40+950 RHS
17 18.06.2015 CEI-Pj/NHAI/1213006/HKTRPL/2015/155 Mix Design for Pavement Quality concrete
18 19.06.2015 CEI-Pj/NHAI/1213006/HKTRPL/2015/156 Procurement of Paver Blocks - M/s. Vinayaka Business Corporation
19 19.06.2015 CEI-Pj/NHAI/1213006/HKTRPL/2015/157 Review and Concurrence of Bar Bending Schedule
20 25.06.2015 CEI-Pj/NHAI/1213006/HKTRPL/2015/158Review of Concrete Mix Design for M15 PCC, M20 RCC, M20 Kerb & M25 RCC (Plant at Km. 61+900)
21 26.06.2015 CEI-Pj/NHAI/1213006/HKTRPL/2015/159
Implementation of Electronic Toll Collection, Provision of Traffic Aid & Medical Aid posts and ATMS, WIM & Static Weigh Bridge in Toll Plaza - Action Plan
22 26.06.2015 CEI-Pj/NHAI/1213006/HKTRPL/2015/160 Major Bridge at Ch. 77+950 construction of super Structure - Deviation from CA - Cost Estimate
23 26.06.2015 CEI-Pj/NHAI/1213006/HKTRPL/2015/161Methodology for Rectification of Pedestal foundation and Inspection for verification of LUX Levels
24 27.06.2015 CEI-Pj/NHAI/1213006/HKTRPL/2015/162 Revised Drawings of toll Plaza Administrative Building
9.3. Construction Programme:Construction Programme submitted to IE by the Concessionaire vide, Letter no. 208 - Dated 25.11.2011.Concessionaire has been advised to review the program vide, IE Letter no 102A - Dated 07 Nov 2012 taking in to account the progress achieved till date. Revised Construction Programme as per article 12.1 of CA for balance works are not submitted as per interim EOT recommended by IE. For 2nd EOT construction programme submitted it is reviewed by IE.
Monthly Progress Report – June 2015 Page 21
Independent Engineering Service
Hosur – Krishnagiri Project Of NH-7
9.4. Construction Safety The National Highways Authority of India has engaged M/s. HAKS Engineers, Architects and Land Surveyors, PC in association with Info Trans Engineers Pvt Ltd, as Road Safety Consultant. Safety consultant are visiting the project site Regularly, and carry out Safety audit also. The safety audit report are being submitted to PD as well as to IE. The recommendation of safety consultant in their report are being implemented at site to the extent of provision in CA.
9.5. Method Adopted in Construction:The method of construction adopted has been regularly checked and reviewed by the IE through conducting field and laboratory tests on compaction, whether materials used are in compliance with specifications and standards.
9.6. Conformity of Construction Works:The source of materials used for construction works are regularly checked by IE for conformity with the specifications and standards. Routine checks were regularly conducted by the IE field team. The Team Leader and Key Personnel also attended some tests like Concrete Cube strengths testing, Core thickness, Gradations, Bituminous Extractions tests etc. during their site visits. Casting of RCC/PSC girders are in completed at camp locations and regularly inspected by IE field team. 9.7. Defects and Deficiencies:Along with concessionaire EPC contractor and IE team visited site on 30/06/2015. (Ref. IE Monthly inspection Report enclosed)
9.8. Maintenance of the Existing 4 lane Highway:The concessionaire is regularly maintaining the existing road and IE is constantly monitoring the maintenance works.
9.9. Road Accident Report:The Concessionaire is submitting regularly the Accident occurrence report to IE through mail. (Annexure – c) 9.10. Survey Works:
1) IE is in the process of reviewing survey reports containing traverse points, TBMs & etc.
2) Erection of New TBM pillars from Km. 33+130 to Km. 93+000 is completed.
3) Checking of GPS points, TBMs and Reference Pillars / Boundary pillars at Km. 33+130 to Km. 93+000 is completed.
4) Checking of Top level of all layers being done (Embankment, Sub-grade, GSB, WMM, DBM and BC.)
5) Checking of layouts for all structures is being done.9.11. Source Approval of Materials:
S. No.
Source Name / Locations
Material
Name
To be used for Lead to site
(Km)
Date of approval of source
Name of Independent quality
check done before
approving
Monthly Progress Report – June 2015 Page 22
Independent Engineering Service
Hosur – Krishnagiri Project Of NH-7
source.
1 Bukkasagaram @Km 47+000
Aggregate
GSB/WMM/DBM/BC and Concrete
works4.5km
CEI Pj/NHAI/1213006/2012/1
28A dt 20.11.20123rd party test
2 Thuppukanapalli @ km 61+900
Aggregate
GSB/WMM/DBM/BC and Concrete
works6.9km
CEI Pj/NHAI/1213006/2012/1
28A dt 20.11.20123rd party test
3 Palar River Sand Concrete 200kmCEI
Pj/NHAI/1213006/2012/128A dt 20.11.2012
3rd party test
4
Thuppukanapalli &
Bukkasagaram (L&T Camp)
Water Concrete, WMM6.9km
& 4.5km
CEI Pj/NHAI/1213006/2012/1
24A dt 20.11.20123rd party test
Sl. No Details Submitted to IE/ NHAI Date Reply From NHAI/IE Date RemarksA. Hump Pipe
1
M/s. South India Spun Pipe Company
HKTRPL/NHAI/2011/Site/09830-
Aug-11
NHAI/PIU-K'giri/MC-II/BOT-HK/CW/2011/1107
28-Jun-12 Approved
2M/s. India Spun Pipes
HKTRPL/NHAI/2011/Site/11713-
Sep-11
NHAI/PIU-K'giri/MC-II/BOT-HK/CW/2011/1144
03-Jul-12 Approved
3M/s. RBBR Infrastructure
HKTRPL/NHAI/2011/Site/24519-
Dec-11
NHAI/PIU-K'giri/MC-II/BOT-HK/CW/2011/775
09-May-
12 Approved
4M/s.PK RCC Pipie works ,Karur
HKTRPL/NHAI/2014/Site/127125-
Aug-14 CEI-IE/NHAI/1213006/HKTRPL/2014/219
27-Aug-14 Approved
5M/s. Amaravathi Spun Pipes
HKTRPL/IE/2015/Site/1558 09
Apr-2015 CEI-IE/NHAI/1213006/HKTRPL/2015/086
14 Apr-15 Approved
6M/s. Premier Spun Pipes
HKTRPL/IE/2015/Site/157120-Apr-15 CEI-IE/NHAI/1213006/HKTRPL/2015/097
21-Apr-15 Approved
7M/s. Vikas Spun Pipes works
HKTRPL/IE/2015/Site/157827-Apr-15 CEI-IE/NHAI/1213006/HKTRPL/2015/101
27-Apr-15 Approved
8M/s. Vijay Spun Pip[es
HKTRPL/IE/2015/Site/157827-Apr-15 CEI-IE/NHAI/1213006/HKTRPL/2015/103
28-Apr-15 Approved
9 M/s. PK RCC PipesHKTRPL/IE/2015/Site/1594
30-Apr1
5 CEI-IE/NHAI/1213006/HKTRPL/2015/105
02-May-
15 Approved
10
M/s. Sree Veerakumar Hume Pipes
HKTRPL/IE/2015/Site/159502-Apr-15 CEI-IE/NHAI/1213006/HKTRPL/2015/106
05-May-
15 ApprovedB. Cement
1
M/s. Ultra Tech Cement (OPC 43 & 53 Grade)
HKTRPL/NHAI/2011/Site/09930-
Aug-11 NHAI/PIU-K'giri/MC-II/BOT/CW/2009/627
08-Nov-
11 Approved
2
M/s. Zuari Cement (OPC 43 & 53 Grade)
HKTRPL/NHAI/2011/Site/15929-Oct-11 NHAI/PIU-K'giri/MC-II/BOT/CW/2009/627
08-Nov-
11 Approved3 M/s. Birla Cement
(OPC 43 & 53 HKTRPL/NHAI/2011/Site/188 15-
Nov-NHAI/PIU-K'giri/MC-II/BOT/CW/2009/644 11-
Nov-Approved
Monthly Progress Report – June 2015 Page 23
Independent Engineering Service
Hosur – Krishnagiri Project Of NH-7Grade) 11 11
4
M/s. Dalmia Cement (OPC 43 & 53 Grade)
HKTRPL/NHAI/2011/Site/20122-
Nov-11 NHAI/PIU-K'giri/MC-II/BOT/CW/2009/691
02-Dec-11 Approved
C. Steel
1
M/s. TATA, M/s. sail and M/s. RINL
HKTRPL/NHAI/2011/Site/12320-
Sep-11
NHAI-PIU-K'giri/MC-II/BOT-HK/CW/2009/506
22-Sep-11 Approved
HKTRPL/NHAI/2011/Site/148
18-Oct-11
NHAI-PIU-K'giri/MC-II/BOT-HK/CW/2009/506
22-Sep-11 Approved
2M/s. TATA Steel Fe 500D
HKTRPL/NHAI/2011/Site/20222-
Nov-11 NHAI/PIU-K'giri/MC-II/BOT/CW/2009/690
02-Dec-11 Approved
3 M/s. JSWHKTRPL/NHAI/2012/Site/423
20-Mar-
12NHAI-PIU-K'giri/MC-II/BOT-HK/CW/
2011/1070
22-Jun-12 Approved
D. Admixture and Chemicals
1
M/s. BASF Constrcution chemicals
HKTRPL/NHAI/2011/Site/15119-Oct-11
NHAI/PIU-K'giri/MC-II/BOT-HK/CW/2011/1187
10-Jul-12 Approved
2M/s. Fosroc Chemicals
HKTRPL/NHAI/2011/Site/23213-
Dec-11
NHAI-PIU-K'giri/MC-II/BOT-HK/CW/2011/1141
03-Jul-12 Approved
3
M/s. Fosroc Chemicals- Plasticizer & retarding Agent
HKTRPL/NHAI/2012/Site/596 19-Jul-12
NHAI/PIU-K'giri/MC-II/BOT-HK/CW/2011/1302
23-Jul-12 Approved
M/s. Fosroc Chemicals - Nitobond and Lokfix
HKTRPL/NHAI/2011/Site/265 27-Dec-11
NHAI-PIU-K'giri/MC-II/BOT-HK/CW/2011/1188
16-Jul-12 Approved
4M/s. SWC Curing Compound
HKTRPL/NHAI/2012/Site/31831-Jan-12
NHAI/PIU-K'giri/MC-II/BOT-HK/CW/2011/1091
28-Jun-12 Approved
5
M/s. Fosroc Chemicals(I) PVt. Ltd - Grouting matrl
HKTRPL/IE/2012/ Site/258 24-Sep-12 Cei-PJ/NHAI/1213006/HKTRPL/2012/125A
20-Nov-
12 ApprovedE Bitumen
1
M/s. HINCOL - Prime coat, Tack coat
HKTRPL/NHAI/2011/Site/26224-
Dec-11
NHAI/PIU-K'giri/MC-II/BOT-HK/CW/2011/1095
28-Jun-12 Approved
2
M/s. HPCL - VG 30 Grade Paving Bitumen
HKTRPL/NHAI/2011/Site/31330-Jan-12
NHAI/PIU-K'giri/MC-II/BOT-HK/CW/2011/778
09-May-
12 Approved
3
M/s. IOCL - VG 30 Grade Paving Bitumen
HKTRPL/NHAI/2011/Site/31430-Jan-12
NHAI/PIU-K'giri/MC-II/BOT-HK/CW/2011/777
09-May-
12 Approved
4
M/s. IWL India Limited - Prime coat , tack coat
HKTRPL/NHAI/2012/Site/33107-
Feb-12
NHAI/PIU-K'giri/MC-II/BOT-HK/CW/2011/1094
28-Jun-12 Approved
5M/s. MRPL - VG 30 and CRMP
HKTRPL/NHAI/2012/Site/40613-
Mar-12
NHAI/PIU-K'giri/MC-II/BOT-HK/CW/2011/776
09-May-
12 Approved
6 M/s. TINNA Overseas Ltd HKTRPL/IE/2012/ Site/286
17-Oct-12
Cei-PJ/NHAI/1213006/HKTRPL/2012/080A16-Oct-12
Approved
F RE Wall
Monthly Progress Report – June 2015 Page 24
Independent Engineering Service
Hosur – Krishnagiri Project Of NH-7
1M/s. Reinforced Earth wall
HKTRPL/NHAI/2012/Site/35014-
Feb-12 Cei-PJ/NHAI/1213006/2012/128B
20-Nov-
12 Approved
2M/s. Tech Fab (India) Limited
HKTRPL/IE/2013/Site/399 11-Jan-13 Under Review
To be approved
G Girder Casting works
1
M/s. Tata Steel and Usha Martin - HT Strands
HKTRPL/NHAI/2012/Site/38229-
Feb-12
NHAI-PIU-K'giri/MC-II/BOT-HK/CW/2011/1071
22-Jun-12 Approved
H Bearing and Expansion Joints
1
M/s. Sanfield and M/s. Megaba Bridge Products
HKTRPL/NHAI/2012/Site/38603-
Mar-12
NHAI-PIU-K'giri/MC-II/BOT-HK/CW/2011/1040
20-Jun-12 Approved
2 M/s. Kantaflex HKTRPL/NHAI/2012/Site/408
13-Mar-
12NHAI/PIU-K'giri/MC-II/BOT-HK/CW/
2011/1093
28-Jun-12 Approved
I Pre stressing works
1M/s. Usha Martin Limited
HKTRPL/NHAI/2012/Site/43931-
Mar-12
NHAI-PIU-K'giri/MC-II/BOT-HK/CW/2011/1069
22-Jun-12 Approved
2 M/s. Freyssinet HKTRPL/IE/2012/ Site/084
31-Mar-
12NHAI-PIU-K'giri/MC-II/BOT-HK/CW/
2011/1069
22-Jun-12 Approved
J Antistripping Agent
1M/s. Suvris (Sales) Pvt Ltd.
HKTRPL/NHAI/2012/Site/39407-
Mar-12
NHAI-PIU-K'giri/MC-II/BOT-HK/CW/2011/1087
28-Jun-12 Approved
2M/s. Eswari Petro Tech
HKTRPL/NHAI/2012/Site/43426-
Mar-12
NHAI-PIU-K'giri/MC-II/BOT-HK/CW/2011/1092
28-Jun-12 Approved
3M/s. IWL India Limited
HKTRPL/NHAI/2012/Site/48726-Apr-12
NHAI-PIU-K'giri/MC-II/BOT-HK/CW/2011/1090
28-Jun-12 Approved
4
M/s. Indomines & M/s.Petrochem Specialist
HKTRPL/IE/2012/ Site/23508-
Sep-12 Cei-PJ/NHAI/1213006/HKTRPL/2012/073
18-Oct-
12 ApprovedK Lime
1M/s. Reddys lime supplier
HKTRPL/NHAI/2012/Site/50711-
May-12 Cei-PJ/NHAI/1213006/HKTRPL/2012/085A
30-Oct-12 Approved
2
M/s. Sree Hyothsna Minerals
HKTRPL/NHAI/2012/Site/48626-Apr-12 Cei-PJ/NHAI/1213006/HKTRPL/2012/081A
26-Oct-12 Approved
L. Road Signages
1 M/s. Sri BalajiHKTRPL/IE/2012/ Site/288
17-Oct-12 Cei-PJ/NHAI/1213006/HKTRPL/2012/113
14-Nov-
12 Approved
2 M/s. 3M IndiaHKTRPL/IE/2012/ Site/287
17-Oct-12 Cei-PJ/NHAI/1213006/HKTRPL/2012/112
14-Nov-
12 ApprovedM Thermoplastic paints
1M/s. Kataline, Nagpur
HKTRPL/IE/2012 /Site/287 27-Dec-12 Cei-PJ/NHAI/1213006/HKTRPL/2013/011
23-Jan-13
Approved
N Paints
1M/s Asian Paints ,Mumbai
HKTRPL/IE/2014/Site/127627-
Aug-14 Cei-PJ/NHAI/1213006/HKTRPL/2014/221
30-Aug-14 Approved
O LED TRAFFIC BEACONS
Monthly Progress Report – June 2015 Page 25
Independent Engineering Service
Hosur – Krishnagiri Project Of NH-7
1
M/s .BONS LIGHT Pvt. Ltd ,Ahmadebad.
HKTRPL/IE/2014/Site/1206 09-Jul-14 Cei-PJ/NHAI/1213006/HKTRPL/2014/179
17-Jul-14 Approved
P METAL BEAM CROSS BARRIER
1
M/s.AIRCON GUARDRAILS Pvt. Ltd
HKTRPL/IE/2014/Site/125718-
Aug-14 Cei-PJ/NHAI/1213006/HKTRPL/2014/214
22-Aug-14 Approved
2
M/s. Lysasht Taperline Poles Pvt Ltd, Sriperumpudhur
HKTRPL/IE/2014/Site/1390 21-Nov-
14 Cei-PJ/NHAI/1213006/HKTRPL/2014/297
27-Nov-
14 Approved
3
M/s. NS Rolling steel Pvt Ltd, Mumbai
HKTRPL/IE/2014/Site/139121-
Nov-14 Cei-PJ/NHAI/1213006/HKTRPL/2014/296
27-Nov-
14 ApprovedQ TILES
1
M/s. Mayura RCC Precasting Industries, Hosur
HKTRPL/IE/2014/Site/137814-
Nov-14 Cei-PJ/NHAI/1213006/HKTRPL/2014/287
15-Nov-
14 Approved
2
M/s. Vinayaka Business Corporation
HKTRPL/IE/2015/Site/157321-Apr-15 CEI-IE/NHAI/1213006/HKTRPL/2015/100
25-Apr-15 Approved
3
M/s. Vinayaka Business Corporation(paver block)
HKTRPL/IE/2015/Site/1658 13-Jun-15 CEI-IE/NHAI/1213006/HKTRPL/2015/156
19-Jun-15 Approved
R REHABILITATION (STRUCTRE)
1
M/s.Varshitha Concrete Technologies Pvt. Ltd,Hydeabad
HKTRPL/IE/2014/Site/1164 12-Jun-14 Cei-PJ/NHAI/1213006/HKTRPL/2014/146
19-Jun-14 Approved
9.12. Borrow Area Test Results(Annexure – d)
9.13. Requests for Inspection (RFI):RFIs are being taken care of by field staff of IE regularly.
9.14. Non Conformance Report (NCR):(Annexure – e)
9.15. Progress Report from the Concessionaire:The Concessionaire submitted their monthly progress report for the Month of June- 2015 to Independent Engineer on 11.07.2015. The report is under review.
9.16. IE Factory Visit Report:
1 Project : Hosur - Krishnagiri NHAI -7 Road Project.Material : RCC Pipes ( NP2) 300 mm diaWitnessed by : 1. Mr J. Selvakumar, AQME, CDM Smith-WSAPL(JV)
Monthly Progress Report – June 2015 Page 26
Independent Engineering Service
Hosur – Krishnagiri Project Of NH-7
2. Mr. Yuvaraj, ME, HKTRPL 3. Mr. Manikandan, HKTRPLContractor : M/s.Amaravathi Spun Pipes companyTest Conducted at : M/s.Amaravathi Spun Pipes company, KarurDate of Testing : 29.06.2015
2
Project : Hosur - Krishnagiri NHAI -7 Road Project.Material : Hume Pipes ( NP2) 300 mm dia Witnessed by : 1. Mr J. .Selvakumar , AQME, CDM Smith-WSAPL(JV) 2. Mr. Yuvaraj, ME, HKTRPL 3. Mr. Manikandan, HKTRPLContractor : M/s. Premier Spun Pipes Company, Test Conducted at : M/s. Premier Spun Pipes Company, Velur, Namakkal.Date of Testing : 29.06.2015
3
Project : Hosur - Krishnagiri NHAI -7 Road Project.Material : Hume Pipes ( NP2) 300 mm dia Witnessed by : 1. Mr J. .Selvakumar , AQME, CDM Smith-WSAPL(JV) 2. Mr. Yuvaraj, ME, HKTRPL 3. Mr. Manikandan, HKTRPLContractor : M/s. Vikas Spun Pipes CompanyTest Conducted at : M/s. Vikas Spun Pipes Company, Dharapuram.Date of Testing : 30.06.2015
4
Project : Hosur - Krishnagiri NHAI -7 Road Project.Material : Hume Pipes ( NP2) 300 mm dia Witnessed by : 1. Mr J. .Selvakumar , AQME, CDM Smith-WSAPL(JV) 2. Mr. Yuvaraj, ME, HKTRPL 3. Mr. Manikandan, HKTRPLContractor : M/s. Shanmugam Pipe works Test Conducted at : M/s. Shanmugam Pipe works Date of Testing : 30.06.2015, Pothanur, Near Karur
9.17. Meeting & Site Visit of Dignitaries:1) IE, Monthly Road Inspection of the project starting from Ch:93+000 to Ch:33+130 has
been held on 30.06.2015 along with Concessionaire, EPC Contractor and Construction
Contractor to inspect the progress and also deficiencies if an.
Monthly Progress Report – June 2015 Page 27
Independent Engineering Service
Hosur – Krishnagiri Project Of NH-7
2) Hon’ble K. Ashok Kumar, MP visited the site along with PD NHAI, IE and Concessionaire
on 08 June 2015
3) Third Party testing, Environmental Audit completed at Ch.62+000 on 10th & 11 June 2015
along with our Environmental Engineer, Mr. Rajesh Varghese, IE and Concessionaire &
L&T
4) Road Safety Meeting held on 23 June 2015 at Collector Office, Krishnagiri.
5) NP2 300 mm dia pipe Third Party Testing at Karur on 29 & 30 June 2015.
9.18. SHEDULE - I COMPLIANCES
Sl. No.
Description of Test Status
2.1 Visual and Physical Test On Progress2.2 Test Drive Conducted2.3 Riding Quality Conducted2.4 Pavement Composition Test Completed
2.5 Cross-section Test Completed2.6 Structural Test for Bridges
Rebound Hammer and Ultrasonic Pulse Velocity test on all minor and major bridges
Completed
Load Test on bridges with a span of 15m or more
Chainage Type of Structures
Span Status of Load test
77+993 Major Bridge
20m Load Test Completed and report not submitted
68+342 Minor Bridge
20.65m Load Test Completed and the report is received
47+030 Minor Bridge
14.95 say 15.0m Load test yet to start
2.7 Other Tests
Rebound Hammer and Ultrasonic Pulse Velocity test on all PUP's, VUP's and Flyovers
Completed
Chainage Type of Structures
Length of Span Status of Load test
Monthly Progress Report – June 2015 Page 28
Independent Engineering Service
Hosur – Krishnagiri Project Of NH-7
Load Test on Flyover / VUP with a span of 15m or More
40+990 Flyover 20m Span Load test Completed and report not received
39+020 Flyover 20m Span Load test Completed and report not received
92+387 Flyover
20m Span Load Test Completed and the report is received
40m Span Load Test Completed and the report is received
77+450 VUP
30m Span Load Test Completed and the report is received
45+950 VUP 30m Load Test Completed and the report is received
19. Approved independent 3rd Party laboratory :Sl.no Type of
MaterialType of Testing
Name of Laboratory
Accredited By Location Remarks
1 Reinforcement Physical & Chemical
CIVIL AID NABL Bangaluru Raghavendra Lab NABL Bangaluru
2 CementPhysical & Chemical CIVIL AID NABL Bangaluru
3 AdmixturePhysical & Chemical CIVIL AID NABL Bangaluru
4 AggregatePhysical & Chemical CIVIL AID NABL Bangaluru
5 WaterPhysical & Chemical CIVIL AID NABL Bangaluru
6 LimePhysical & Chemical NAWAL NABL Hosur
7Antistripping agent Chemical CIVIL AID NABL Bangaluru
8 Bitumen VG 30 All Tests CIVIL AID NABL Bangaluru L & T NABL Bangaluru
9 CRMB 60 All Tests CIVIL AID NABL Bangaluru
10Emulsion RS1,SS1 All Tests CIVIL AID NABL Bangaluru
11 Soil Physical & CIVIL AID NABL Bangaluru
Monthly Progress Report – June 2015 Page 29
Independent Engineering Service
Hosur – Krishnagiri Project Of NH-7
Chemical12 Nitobond EP All Tests CIVIL AID NABL Bangaluru
13Thermoplastic Road marking All Tests ANACON NABL New Delhi
14 HT Stands All TestsTATA (Bombay) Bombay
15 Sheathing All TestsREX Polymers ( Factory Visit)
16Elastomeric Bearing All Tests
Mageba (Factory Visit ) Kolkata
17Geo-Grids
All Tests
The Bombay Textile Research Association NABL Bombay
18Wedges,Cones, Anchor cone All Tests Usha Martin Ranchi
19Highwy Lighting cables All Tests
Bajaj Electricals Ltd., NABL
Alwar, Rajastan
10. PROJECT AFFECTED FOR WANT OF LA STATUS :
HOSUR - KRISHNAGIRI PROJECT
LAND STATUS AS ON 30.06.2015
Sl. no AREA Total Length
Available for MCW Effected for MCW (Km)
in KM In %
1 LHS 59.87 59.87 100.0% -
2 RHS 59.87 59.87 100.0% -
B. SERVICE ROAD
Sl. no AREA Total Available for SR Effected for Service
Monthly Progress Report – June 2015 Page 30
Independent Engineering Service
Hosur – Krishnagiri Project Of NH-7
Length Road (KM)in KM In %
1 LHS 27.19 27.04 99.4% 0.150
2 RHS 27.19 26.84 98.7% 0.350
C. PROJECT FACILITIES
Sl. no AREA Total Length
Available for PFEffected for Project
facilities (KM)in KM In %
1 LHS 59.87 59.72 99.7% 0.150
2 RHS 59.87 59.45 99.3% 0.420
PHYSICAL OBSTRUCTION / LAND NOT AVAILABLE DETAILS FROM CHAINAGE: 33+130 TO 93+000 (LHS) AS ON DATED:30.06.2015
LHS Effected for MCW
Effected for SR
Effected for
Project facilities
Obstruction Details Remarks CHAINAGE
Name of Village
From To
38.050 38.200 Mookondapalli 0.150 0.150 Temple
(Mariamma ) Temple @14.25 to 16.Mtr
Total - 0.150 0.150
PHYSICAL OBSTRUCTION / LAND NOT AVAILABLE DETAILS FROM CHAINAGE: 33+130 TO 93+000 (RHS) AS ON DATED: 30.06.2015
RHS Name of Village
Effected for MCW
Effected for SR
Effected for
Project facilitie
s
Obstruction Details REMARKS CHAINAGE
From To
Monthly Progress Report – June 2015 Page 31
Independent Engineering Service
Hosur – Krishnagiri Project Of NH-7
37.960 38.100 Mookondapalli
0.140 0.140Mosque and Grave Yard
E.Ploes 2 No's @17.5, E.Drain @14.25 to 18.250 Varies&Mosque/[email protected]
39.460 39.530 Hosur 0.070 Buildings
43.490 43.650 Chennathur
0.160 0.160 Buildings/ EB poles
E.Poles 6 No's @ 15.70 to 19.00mtr Varies & [email protected] to 22.50mtr Varies
90.230 90.280 Kattiganapalli
0.050 0.050 Buildings/ EB poles
Buildings @ 19.100 & 3.No's EB poles@ 14.800 to 17.500
Total 0.000 0.350 0.420
11. Progress of Quality Control Test Report of June - 2015:
Details are inclosed (Annexure – f)
12.WEATHER REPORT OF June -2015 :
Monthly Progress Report – June 2015 Page 32
Independent Engineering Service
Hosur – Krishnagiri Project Of NH-7
Monthly Progress Report – June 2015 Page 33
Independent Engineering Service
Hosur – Krishnagiri Project Of NH-7
13. LOGISTICS PLAN
1 4 . PLANTS & MACHINERY AVAILABLE AT SITE :
SL Resource Model & Capacity Number1 Excavator CK-90 22 Excavator EX-120 23 Excavator EX-200 34 Dumper TATA,MAN,AL-16Cum 95 Dumper TATA,MAN,AL-8Cum 96 Motor Grader 164 HP-Komatsu-GD 555-3A 37 Vibratory Roller 10T 38 Water Tanker 12000, 4000 L 59 Hot Mix Plant Marini-120TPH 1
10 WMM Plant Apollo-120TPH 111 Paver-Voggle Voggle- 500TPH 212 Tandem Vibratory Roller 8T 313 Pneumatic Tyre Roller Bittelli/IR 114 Batching Plant Schwing Scetter-30 cum/Hour 115 Transit Mixers AN6SHN/ 2516-6Cum 116 GANTRY Anupam-40T 217 Kerb Casting Machine Arrow 740 118 Bitumen Sprayer Appolo 1
Monthly Progress Report – June 2015 Page 34
Sl No ITEM STATUS AT SHOOLAGIRI
STATUS AT PERANDAIPPALLI
I BATCHING PLANT Functional NAII WMM PLANT Functional NAIII HMP Functional NA
IVSemi Mobile Crusher - 200 TPH NA
NA
V Mobile crusher for GSB NA NAVI Pre Cast Yard Functional NA
Independent Engineering Service
Hosur – Krishnagiri Project Of NH-7
19 Hydra crane 12& 15T capacity 220 Truck Mounted Crane 3T 121 Mini Roller 2T,3T 122 Weigh Bridge 100T,60T 123 JCB 3DX 1024 Trailer 22MT 325 Tractor John Deere-45HP 426 Wheel loader 580-3S,430Z 327 Bar bending machine B42,B52 228 Bar cutting machine C42,C52 229 Welding machine EDW400 5
Labour Details
Description FTM CumulativeTotal no. of workmen 712 41374
Total man-hours worked 202540 13199071
15.C HANGE OF SCOPE : i) Upgraded Vehicular Under Pass at 44+950 of size 8mx4.5m
Details of change of scope (COS) - Pedestrian Underpass of size 8m x 2.5m has been upgraded as Vehicular Underpass of size 8m x 4.5m
Reason for COS: VIP Reference Dr. Thambi Durai, Hon'ble Member of Parliament (LS), Karur to consider a Vehicular Underpass instead of Pedestrian underpass in front of Adhiyamman Educational & Research Institute, Hosur. Whether COS initiated by concessionaire / NHAI – NHAI Issue of change of scope (Cos) Notice: NHAI issued the change of scope (Cos) notice as per
Clause16 of CA vide letter No. NHAI/PIU-Krishnagiri/MC-II/BOT-HK/CW/2009 /552 dated 24thMarch 2012.
According to above change of scope (Cos) notice, Concessionaire submitted the tentative cost Estimate. IE reviewed the cost estimate and returned the estimate with observation, for Re submission vide IE letter No: 004 dated 19th Jan 2013.
As per NHAI requirement revised proposal submitted by Concessionaire vide their Letter no HKTRPL/IE/2013/Site/909 dated 24th Dec 2013.
COS recommended by IE vide letter no.CEI-Pj/NHAI/1213006 /PD/2014/007. Dated 09th February 2014
ii) Additional Box Culvert at ch.40+955 of size 2x2m
Monthly Progress Report – June 2015 Page 35
Independent Engineering Service
Hosur – Krishnagiri Project Of NH-7
Details of change of scope (COS)- Additional Box culvert of 2x2m size at Rayakottai Junction( Km.40+955).
Reason for COS: Local Administration of Hosur Municipality Commissioner, Sub- Collector and Public are requested Additional Box Culvert as the existing Box Culvert at Ch.40+935 is unable to discharge rain water stagnation frequently during heavy showers leading to huge traffic jam at this Junction.
Whether COS initiated by Concessionaire/ NHAI/ IE- NHAI
According to above Change of Scope submitted by Concessionaire vide their letter no. HKTRPL/IE/2015/Site/1469 dated 31 Jan 2015.
COS recommended by IE vide letter no. CEI-IE/NHAI/1213006/PD/2015/016 dated 03 February 2015.
Issue of Change of Scope Notice : NHAI issued Change of Scope Notice as per Clause 16 of CA vide their letter no. NHAI/NHDP-V/MC-II/BOT/HIC/029 dated 16 April 2015. PD issued a letter to IE vide letter no. 11015/2/2009/PIU-K’giri/924 dated 20 April 2015.
16. Extension of Time (EOT) :
Concessionaire submitted Interim application for Extension of Time to the Intermediate Milestones and Scheduled Six Laning Date for the Project considering the delays in the Project up to 30.11.2012 vide letter No. HKTRPL/IE/2013/Site/502 dated 16th March 2013
IE send the reply vide letter No. CEI-Pj/NHAI/1213006/HO/1798 dated 25th July 2013 to resubmit the EOT taking in to consideration the present site condition.
Concessionaire vides its letter. no. HKTRPL/IE/2013/Site/717 dated 12 th September 2013 requested the Independent Engineer to review the interim EOT submissions in accordance with clause 3.1(vii) of schedule “Q” of the concession agreement in line with the clause 6 of the Schedule G. It is under review by IE.
IE has recommended interim Extension of time to scheduled six laning date up to 30.05.2014 vide letter no.CDM/CE/ 1213006/124/dated 19.11.2013.
Concessionaires vide his letter No. HKTRPL/IE/2014/Site/1059 dated 31st March 2014 requested the Independent engineer to review the 2nd interim EOT submissions in accordance with clause 3.1(vii) of schedule “Q” of the concession agreement in line with the clause 6 of the Schedule G.
IE has recommended interim extension of time to Scheduled six laning date up to 03.05.2015 vide letter no. CDM/CEI/1213006/435 dated 11.06.2014 to Authority for Approval, pursuant to clauses 4.1.3, 10.3.1, 10.3.2, 12.4.2, 13.4 and Schedule ‘G’ of Concession Agreement.
Monthly Progress Report – June 2015 Page 36
Independent Engineering Service
Hosur – Krishnagiri Project Of NH-7
Concessionaires vide his letter No. HKTRPL/IE/2015/Site/1575 dated 24 April 2015 requested the Independent engineer to review the 3rd interim EOT submissions in accordance with clause 3.1(vii) of schedule “Q” of the concession agreement in line with the clause 6 of the Schedule G.
IE does not consider 3rd EOT application of the Concessionaire since the request by the Concessionaire for consideration of the PCC is under review.
17. Safety Constraints / Maintenance:-
1. Median Openings are to be closed wherever BC is completed as per final List at Median openings communicated issued vide to letter No: CEI-Pj/NHAI/1213006/PD/2014/078 dated 16 Apr, 2014.
2. As per clause 4.8.1 & 4.8.3 Metal beam crash barrier shall be provided wherever High embankment 3m or more and wherever median is depressed, finished or having the width less than 4.50 meters and the barrier shall be on both directions .
3. Diversions are to be maintained as per IRC SP-55 with proper safety arrangements.
4. Traffic sign boards, Cautions boards, reflectors and safety barriers are to be provided for parapets of Bridges, Culvert and Such other structures.
5. Service roads are to be connected to the Main Carriageway with proper designed acceleration and deceleration lanes.
6. Median Plantation and Avenue Plantation wherever is missing will have to be taken up under maintains immediately.
7. Wherever the road is formed in cutting is observed to be not to the required side slopes 2:1. As such the stretches is cutting will have to be developed to the requires side slopes inorder to prevent strippage of earth and loose boulders on to the highway during heavy rains.
Monthly Progress Report – June 2015 Page 37
Independent Engineering Service
Hosur – Krishnagiri Project Of NH-7
8. The Crash barriers which were removed from the existing for four lane highway at ponds for using in the road work are to be restored at the earliest.
9. LED Traffic beacons are to be provided on the entire project highway at pedestrian crossing, public gathering locations, cross roads and entry / exit of service roads.
10. Delineators & studs are to be provided wherever lane marking is completed.
11. Safety measures are to be provided at the construction zones in Hosur built up area in to avoid untoward incidents.
12. Debris & bituminous waste dumped in the median and road side will have to be cleared as environmental safety measures.
18. Incident Management System :-HKTRPL TOLL PLAZA - KRISHNAGIRI
S.No Description Mobile No Vehicle NoI HIGHWAY PATROL
1 HIGHWAY PATROL I 9367311001 TN-24K - 70232 HIGHWAY PATROL II 9367311002 TN-24K - 7153
II AMBULANCE 9367311011
TN-29AB - 2371(Medicines and Equipments - 84 Nos and checked every week)
III HELP LINE 9345212345
IV CRANE - I TN-24J - 0383 (15 T Capacity)
a) Shoolagiri (Panali Crane Service) b) Hosur (MA Salchi Crane Servcice)
9750270696
9442558061
V OFFICE LAND LINE 04343 - 322433
VI TRAFFIC AID POST Temporary Arrangement at Toll Plaza
VII MEDICAL AID POST Temporary Arrangement at Toll Plaza
VIII COMPLAINT REGISTER Available at Toll Plaza
NOTE: Vehicle Tracking System is Working
Monthly Progress Report – June 2015 Page 38
Independent Engineering Service
Hosur – Krishnagiri Project Of NH-7
19. Work execution not As per CA Provision :1. Median width in Rural Area has to be minimum 4.50m, but Concessionaire has widened the
road retrofitting. The existing median for major portion is less than 4.50m . 2. Concessionaire is providing Hume Pipe (900mm dia. NP3) longitudinal drain in place of
1.5m wide separator cum – lined covered drain, which is not in line with provisions of CA. The Concessionaire has been informed that construction of longitudinal Hume pipe drain is entirely at their “Risk & Cost”. NCRs also issued to Concessionaire.
3. As per clause : 2.4 of Schedule ‘C’ Highway lighting at flyover, underpasses(PUP&VUP) to be provided as per IRC:SP:87-2010 clause no.12.3.3 (V) grade separated structures, interchanges, flyover, underpass(VUP&PUP) and overpasses at the ground level 50m beyond the point from where flaring of main carriageway takes place(clause:3.3.4 page no 42 of code).
4. As per CA , all road signs shall be with high intensity micro prismatic grade sheeting (type iv) as per ASTM standards. But in the site all road signs of diamond grade retro reflective sheeting (Type IX & XI) are being provided.
5. As per CA at Ch. 77+950 (RHS) Major Bridge to be constructed PSC Pretention 5-Girder system for super structure and RCC for Substructure. But in site it is constructed with PCC Substructure and RCC 4-Girder system.
20. Scope of Work as per O & M:
As per CA Clause no. 12.2 the concessionaire shall maintain, at its cost, the existing lane(s) of the Project Highway so that the traffic worthiness and safety thereof are at no time materially inferior as compared to their condition 7 (seven) days prior to the date of this Agreement, and shall undertake the necessary repair and maintenance works for this purpose; provided that the Concessionaire may, at its cost, interrupt and divert the flow of traffic if such interruption and diversion is necessary for the efficient progress of Construction works and conforms to Good Industry Practice; provided further that such interruption and diversion shall be undertaken by the Concessionaire only with the prior written approval of the Independent Engineer which approval shall not be unreasonably withheld. For the avoidance of doubt, it is agreed that the Concessionaire shall at all times be responsible for ensuring safe operation of the Project Highway
Applicability of Schedule – K (Details in Pages 303 to 309 of CA)
As per the view of PD and IE that during the Construction period of widening of existing four lane to six lane all the requirement of Schedule ‘K’ (Annexure – I)
i) Routine maintenance of Roads:
Monthly Progress Report – June 2015 Page 39
Independent Engineering Service
Hosur – Krishnagiri Project Of NH-7
a) Carriageway & Paved shouldersb) Hard / Earth shoulders, side slopes, drains and culverts.c) Road side furniture including road signs & pavement markingd) Street lighting and telecom (ATMS)e) Tree and plantation (median & Landscaping below Flyovers)f) Rest Areag) Toll Plazah) Other Project Facilities and approach of road.
ii) Routine maintenance of Bridges: a) Super structure of Bridgesb) Foundation of Bridgesc) Piers, Abutments, Return walls and Wing walls of Bridgesd) Bearing (Metallic) of Bridgese) Joints on Bridgesf) Other items relating to Bridges.
21. Inspection Report of IE :Inspection Report of IE for the Month of June 2015
Introduction:The project site of Hosur-Krishnagiri of NH-7 from Ch.93+000 to Ch.33+130 was inspected on 30,
June 2015, jointly with Concessionaire HKTRPL, construction contractor L & T representative and members of IE team headed by:
Independent Engineer : Mr. C. V. Krishna Reddy, Acting Team Leader, IEConcessionaire : Mr. Shafi Mohammed, GM , HKTRPLConstruction Contractor : Mr. R L Naidu, L& T.
Progress & Quality of Works:1) Even though the Concessionaire has given assurance to start the bus bay location at Ch.91+580
RHS on or before 2nd June 2015, the work has not yet been started.2) Toll Plaza monthly monitoring is carried out regarding Ambulance; Highway Patrol and ETC
system and found to be satisfactory.3) Laying of 2 nos of 300mm dia pipes for Utility Duct are in progress from Ch.92+250 to 92+400
RHS of Service Road. 4) Long pending issue of Land Acquisition of D.K. Swamy at Ch.88+950 RHS has been cleared
now and the Concessionaire has to take up the work immediately.5) BC laying work is in progress at Ch. 87+300 RHS of Toll plaza area and temperature has been
checked and found to be within the limits of tolerance. 6) Earthen shoulders are not maintained at the merging portion of service road and MCW at
Ch.87+000 PUP approaches on Hosur side.
Monthly Progress Report – June 2015 Page 40
Independent Engineering Service
Hosur – Krishnagiri Project Of NH-7
7) Construction of bus bay location at Ch.84+830 RHS can be taken up immediately in as much as LA problem is already resolved.
8) The Bus bay location at Ch. 83+700 RHS is yet to be started.9) The progress of Quadrant pitching is observed to be at snail’s pace for Major Bridge at
Ch.77+993 RHS and the progress is to be stepped up.10) Flow from Pipe Culvert at Ch.68+585 on the downstream is totally blocked by forming an
approach road to the Rest Area. Since functioning of the Culvert is under question the same is to be solved by clearing the formed approach road to the extent required to connect to the Minor Bridge at Ch.68+350.
11) Paver blocks fixing work is in progress at ch: 68+500 of Rest Area without submission of methodology. The Concessionaire is there for requested to submit methodology and proceed with further work.
12) Paver blocks laying work is in progress at Bus bay location at Ch.53+520 RHS. It is observed that, the laying of paver blocks are not matching with the adjacent BC and the same should be rectified simultaneously while laying work is in progress.
13) The camber corrections are to be done immediately for BC laid locations of Thali Junction, Ch.39+020 to Ch.39+500 and Ch.36+300 to Ch.36+500 of Service Road RHS.
14) Pipe drain chambers are to be raised to the required level before the laying of 2nos of 300mm dia pipes for Utility duct work.
15) Pot holes are observed in two locations needs to be rectified immediately from Ch. 35+180 to Ch.35+300 RHS and Ch.35+600 RHS of Service Road.
16) 2nos of 300mm dia pipe laying of utility duct work is in progress at Ch.35+000 to Ch.35+800 .It is observed that the pipe is not in alignment from Ch.35+400 to Ch.35+420 and the same is to be rectified before further activity.
17) Deck slab of Box culvert at ch:40+935 is completed and lot of honey combing observed in the concrete surface of wall at final lift needs to be rectified immediately.
18) The existing earthen drain is not maintained from Ch. 54+360 to Ch.54+700 LHS and the same has to be maintained as per CA.
19) The work of rehabilitation is in progress for the existing minor bridge at ch:38+500 RHS.Inspite of pointing out in the earlier reports, the following items are once again repeated as the same are not attended to date. 1. The Project Information board is not provided.2. The plantation in median shall comprise shrubs whose height would normally not exceed 1.0m to 1.5m and shall be as per IRC-SP-21 needed to be trimmed immediately.3. Housekeeping is to be maintained. 4. Number of Pot holes found to have developed in Ch.92+250 to 93+000 on Service Road LHS which are to be closed within 48 hours as per Schedule – “K” ( clause :17.2) of CA.5. The item of providing Landscaping and beautification is yet to be started under all Flyovers. This may be taken up without any further delay.6. MS grills fixed in between MCW and service road from Ch.-88+340 to -88/500 RHS are not true to the line and the same should be rectified immediately7. Safety guardrails (RCC) are to be provided for all PUP’s and VUP’s approaches as a Safety measure to avoid accidents.
Monthly Progress Report – June 2015 Page 41
Independent Engineering Service
Hosur – Krishnagiri Project Of NH-7
8. The existing RCC drain in between RE wall and Service Road is to be closed from Ch.40+600 to 40+980 RHS as shown in the approved Plan and Profile of MCW and Service Road.9. Potholes and patches should be closed immediately.10. Avenue Plantation and Median Plantation are to be maintained regularly.11.Proper safety measures should be provided wherever fixing of metal beam crash barrier, studs fixing works and road cleaning works service road formation and miscellaneous works etc., are in progress.12. Unauthorized openings in the median portions should be closed immediately to avoid accidents.13. Chainages shall be marked throughout the stretch wherever activities are in progress.14. LED traffic beacons and chevron boards are to be provided at curve locations of radius less than 400m and up to 400m radius.15.The level of Paver blocks laid in the bus bay at ch: 92+600 RHS is not matching with the Service Road BC level and the same is to be rectified immediately.16.BC in the left out portion of Service Road RHS from Ch.91+100 to Ch.91+120 has to be completed immediately. 17.The existing drain in the on RHS of Service Road at Rayakotta flyover from Ch.89+400 to 90+100 RHS is to be cleaned and damaged portion need to be reconstructed. 18.Paver blocks found to be damaged badly at Bus bay location at Ch.86+960 RHS needs to be replaced without further delay as the same is pending since more than 6 months period.19.The footpath cover slabs found to be damaged for the Major Bridge at Ch.77+900 RHS are to be replaced with new one and debris on approaches to be cleaned. 20.The Bus bay separator (Island) in the two locations at Ch.52+200 and Ch.76+630 are removed in order to match with the reviewed drawings.21.The opening in the median portion at box culvert location at Ch.74+580 is to be closed immediately to avoid accidents.
******************************************************************************
22. ANNEXURES
a) Progress Photographs.
b) Strip Chart – Highway and Structure
c) Accident data for June - 2015.
d) Borrow Area Abstract for - June 2015.
e) Summary of NCR.
f) Quality Control Test for June - 2015
g) Monitoring of Project Facilities on Project Highway.
h) Input of Intermittent key Professional Staffs for the month of June - 2015.
Monthly Progress Report – June 2015 Page 42
Independent Engineering Service
Hosur – Krishnagiri Project Of NH-7
Monthly Progress Report – June 2015 Page 43