    DistrictofColumbiaWaterandSewerAuthority . ,

    Briefingon:DC CLEAN RIVERS PROJECT

    First Street Tunnel

    Revised First Street NW

    Maintenance of Traffic Plan, APA Eligibility,

    Garbage Collection Services, and More

    Briefingfor:First Street Tunnel Forum /Community Group

    May29,2014

    11

  • 8/12/2019 DC Water 1st Street Tunnel SDIVP-Tunnel_Forum_Brief_FINAL, Dated 2014 05 29

    2/32

    Tunnel Forum

    Location / Group Representative Alternate

    rs ree r. ar yn as ey omas ncarac on

    Bryant /Channing Streets Renee Peres Philomena FritzFlagler Place Victoria Leonard Pia Brown

    Adams Street Shelly Parker Dianne Barnes

    W Street Joe Levesque Neal Herman

    First and V Streets Angela Ray Theodore Bush

    U Street Serita Sanders John Salatti

    Thomas St /Rhode Island Ave Chris Von Ferro Harvey Hartsfield

    Local Blo s Scott Roberts Bets McDaniel

    Government-ANC Mark Mueller Teri Janine Quinn

    Civic Associations Sherry Howard

    22

    All meetings are open to the public.

  • 8/12/2019 DC Water 1st Street Tunnel SDIVP-Tunnel_Forum_Brief_FINAL, Dated 2014 05 29

    3/32

    Revised First Street NW Main-

    Construction Update, continuedtenance of Traffic Plan/Q&A

    Alternative Parking Areas

    Addressing Community

    Concerns

    Freeze Trench Construction

    Residential Parking Tag Process

    Security

    Schedule

    Garbage Collection Plan alongFreeze Trench Alignment and

    Escort

    Shuttle

    Construction U date

    near ons ruc on ag ng reas

    First Street Tunnel Project

    Website Launched Six-Week Look-Ahead and

    Street Activity

    Next Steps

    Ground Breaking Ceremony

    33

    ,

    Tunnel Forum June 26, at 7PM

  • 8/12/2019 DC Water 1st Street Tunnel SDIVP-Tunnel_Forum_Brief_FINAL, Dated 2014 05 29

    4/32

    JohnKennedy,DCCleanRiversProject

    44

  • 8/12/2019 DC Water 1st Street Tunnel SDIVP-Tunnel_Forum_Brief_FINAL, Dated 2014 05 29

    5/32

  • 8/12/2019 DC Water 1st Street Tunnel SDIVP-Tunnel_Forum_Brief_FINAL, Dated 2014 05 29

    6/32

    Revised First Street NW Traff ic Plan

    2113 First St NW

    2115 First St NW2114 First St NW

    2105 First St NW

    2107 First St NW2109 First St NW

    2111 First St NW

    2106 First St NW

    2108 First St NW

    2110 First St NW

    Area of Tree Box, Curband Sidewalk Impacts

    Tree Boxes

    Removed in front

    of 14 Residences

    Construction

    2103 First St NW

    2100 First St NW

    2102 First St NW

    rs

    87 V St NW

    Construction

    Closures(Typical)

    t

    2035 First St NW2034 First St NW

    2036 First St NW 2037 First St NW

    Staging Area

    tNW

    2033 First St NW

    2031 First St NW

    2029 First St NW

    2027 First St NW

    2032 First St NW

    2030 First St NW

    2028 First St NW

    2026 First St NW

    Area of Tree Box, Curband Sidewalk Impacts

    66

    First

    2025 First St NW2023 First St NW

    2021 First St NW

    2024 First St NW2022 First St NW

    2020 First St NW

  • 8/12/2019 DC Water 1st Street Tunnel SDIVP-Tunnel_Forum_Brief_FINAL, Dated 2014 05 29

    7/32

    Revised First Street NW Traff ic Plan

    - -

    4'-0" sidewalkwidth10

    Extends to2113 First St

    TemporaryConcreteBarrier

    Construction

    Construction

    Lane Closures

    (Typical)

    N B

    rs reeDiversionChamber

    ConstructionLane Closures

    V St NWTruck &EquipmentDelivery

    Access

    FirstSt

    NW

    Install concrete barrier for edestrian safet

    (Typical)

    77

    N B Temporary 4-0 wide sidewalk

    10-0 NB travel lane

    Construct First Street Diversion Chamber support of excavation

    Extends to2025 First StNW

  • 8/12/2019 DC Water 1st Street Tunnel SDIVP-Tunnel_Forum_Brief_FINAL, Dated 2014 05 29

    8/32

    Revised First Street NW Traff ic Plan

    - -

    '- "

    10'-0" Travel Lane

    East RetainingWall

    West

    Retaining Wall

    Temporary ConcreteBarrier

    88

    Approx. 44-0 Deep

  • 8/12/2019 DC Water 1st Street Tunnel SDIVP-Tunnel_Forum_Brief_FINAL, Dated 2014 05 29

    9/32

    Revised First Street NW Traff ic Plan

    - -

    6'-0" sidewalkwidth

    10

    Extends to2113 First StNW

    TemporaryConcreteBarrierT ical

    Construction

    Construction

    Lane Closures

    ConstructionLane Closures

    rs ree vers onChamber

    V St NWTruck &EquipmentDelivery

    Access

    Travel lane shifts

    FirstSt

    NW

    (Typical)

    99

    Extends to2025 First StNW

    Concrete barriers shift Widen sidewalk to 6-0

    Construct First Street Diversion Chamber

  • 8/12/2019 DC Water 1st Street Tunnel SDIVP-Tunnel_Forum_Brief_FINAL, Dated 2014 05 29

    10/32

    Revised First Street NW Traff ic Plan

    - -

    '- "

    10'-0" Travel Lane

    East Retaining

    Wall

    West

    Retaining Wall

    Temporary ConcreteBarrier

    1010

    Approx. 44-0 Deep

  • 8/12/2019 DC Water 1st Street Tunnel SDIVP-Tunnel_Forum_Brief_FINAL, Dated 2014 05 29

    11/32

    Revised First Street NW Traff ic PlanOne-wa Northbound 6-ft Sidewalk & Buffer A rox. 12 Months

    Extends to2113 First St

    6'-0" sidewalkwidth

    Temporary

    ConcreteBarrierT ical

    Construction

    Construction

    Lane Closures

    N B

    ChannelizingDevice(Typical)

    ConstructionLane Closures

    rs ree vers onChamber

    V St NWTruck &EquipmentDelivery

    Access

    Travel lane shifts

    FirstSt

    NW

    (Typical)

    1111

    N BExtends to2025 First StNW

    Increase buffer zone

    6-0 Sidewalk width maintained

    Construct remaining structures

  • 8/12/2019 DC Water 1st Street Tunnel SDIVP-Tunnel_Forum_Brief_FINAL, Dated 2014 05 29

    12/32

    Revised First Street NW Traff ic Plan

    - - +

    '- "

    11'-0" Travel Lane

    4'-0" Buffer

    East Retaining

    Wall

    West

    Retaining Wall

    anne z ngDevice

    Temporary ConcreteBarrier

    1212

    Approx. 44-0 Deep

  • 8/12/2019 DC Water 1st Street Tunnel SDIVP-Tunnel_Forum_Brief_FINAL, Dated 2014 05 29

    13/32

    Revised First Street NW Traff ic PlanRenderin One-wa NB 6-ft Sidewalk & Buffer A rox. 12 Mo.

    1313

  • 8/12/2019 DC Water 1st Street Tunnel SDIVP-Tunnel_Forum_Brief_FINAL, Dated 2014 05 29

    14/32

    Revised First Street NW Traff ic Plan

    Plan maintains existing sidewalk width for all but a

    -

    One-waying First Street NW provides additionalbuffer zone to provide further separation of

    vehicular and pedestrian traffic

    Posted speed limit signage and traffic calming ons ruc on spee m re uc ons roug

    staging area

    Reinforced concrete barriers rovided to rotectpedestrians

    1414

  • 8/12/2019 DC Water 1st Street Tunnel SDIVP-Tunnel_Forum_Brief_FINAL, Dated 2014 05 29

    15/32

    First Street NW Closure

    6800

    220% Increase

    470% Increase

    Lane Widths

    Between Parked

    10004700

    3100

    4200500

    Street Width (ft)

    First St NW 19.5

    U St NW 20

    840% Increase

    Traffic Flow

    2nd St NW 18.5

    W St NW 16

    XXXX 2013 Volume Count

    LaneClosures/CSA

    XXXX 2013 Volume with NBDetour Count (vehicles/day)

    151515

    Close First Street NW during construction of First Street Diversion Chamber (8 Months) One-way traffic for the remainder of construction (12 Months) Southbound traffic along First Street is detoured to North Capitol Street via Bryant Street NW

  • 8/12/2019 DC Water 1st Street Tunnel SDIVP-Tunnel_Forum_Brief_FINAL, Dated 2014 05 29

    16/32

    First Street NW Closure

    Significant increase in traffic along narrow

    to handle estimated traffic volumes

    Greater amount of residents affected by

    W Street NW would need to be one-wayed or

    parking restricted to accommodate plan

    Level of service reductions and increase in

    queue lengths along U, W and 2nd Streets NW

    response times (fire, medical emergencies) to

    homes and businesses

    1616

  • 8/12/2019 DC Water 1st Street Tunnel SDIVP-Tunnel_Forum_Brief_FINAL, Dated 2014 05 29

    17/32

    Skanska to submit revised plan to

    Work at the V Street ConstructionStaging Area to begin June 2014

    Tree boxes will be removed in July

    2014

    1717

  • 8/12/2019 DC Water 1st Street Tunnel SDIVP-Tunnel_Forum_Brief_FINAL, Dated 2014 05 29

    18/32

    aintenance o Tra ic Plan

    1818

  • 8/12/2019 DC Water 1st Street Tunnel SDIVP-Tunnel_Forum_Brief_FINAL, Dated 2014 05 29

    19/32

    ThomasMarch,SKJD

    SharonRobinsonGoods,SKJD

    1919

  • 8/12/2019 DC Water 1st Street Tunnel SDIVP-Tunnel_Forum_Brief_FINAL, Dated 2014 05 29

    20/32

    Alternative Parking Areas

    McMillan ReservoirN Alternative Parking Areas

    Alternative Parking Areasfor eligible residents areshown as

    are shown in blue

    Residents whose property

    area ( ) are eligible to

    apply for an APA Parking Tag

    2020

  • 8/12/2019 DC Water 1st Street Tunnel SDIVP-Tunnel_Forum_Brief_FINAL, Dated 2014 05 29

    21/32

    APAs

    An APA Application for an APA Parking Tag was provided at the frontdoor of your residence the week of May 19, 2014

    Priority will be given to: Special-needs residents

    Those whose property is directly fronting a Construction Staging Area

    and who have no off-street parking

    Area bounded by Second Street NW, alleyway just east of First, Thomas,

    To apply for an APA Parking Tag and Shuttle Pass, you will need:

    APA Application and Terms of Service Agreement

    Current insurance carrier and policy number

    DC vehicle registration

    2121

  • 8/12/2019 DC Water 1st Street Tunnel SDIVP-Tunnel_Forum_Brief_FINAL, Dated 2014 05 29

    22/32

    APAs

    ,

    Dates and times to present the items at the Site Office(at 2036 First St NW) and apply for an APA Parking Tag are:

    Fridays

    May 30, June 6, 13, and 20 from 6PM to 8PM

    , ,

    Call the Hotline at 1-844-FST-INFO (1-844-378-4636)

    for additional dates and times Upon approval, you will receive an

    APA information package that includes:

    APA Parking Tag Shuttle Pass, schedule, and map

    Site Office hours at 2036 First Street NW

    2222

    APA application is the upper portion of the

    Registration and Terms of Service Agreement

    form

  • 8/12/2019 DC Water 1st Street Tunnel SDIVP-Tunnel_Forum_Brief_FINAL, Dated 2014 05 29

    23/32

    APAs

    A Security Emergency Response Plan is in place for thisproject

    Security personnel are trained in basic First Aid, CPR, and useof Automated External Defibrillation AED units

    Contingency plans are in place to respond to emergencies

    Video surveillance cameras at all APA locations Security personnel will provide 24/7 continuous monitoring of

    APAs and surrounding areas

    Securit ersonnel will be dressed in a uniform

    Security communication hub will be equipped with computer,phone, internet, and two-way radio base station

    2323

  • 8/12/2019 DC Water 1st Street Tunnel SDIVP-Tunnel_Forum_Brief_FINAL, Dated 2014 05 29

    24/32

    APAs

    Hours of operation for security and shuttle services are 24/7, includingholidays, for the duration of the project

    Services will be coordinated through the Hotline- - - -

    Operate two special needs-accessible shuttle vans with nine-seat capacity

    Shuttle service will be: Provided with a predetermined route covering all affected areas

    Provided to local residents between their homes and the three APAs

    Available within minutes of request, barring any related service runs inprogress

    Upon entry, shuttle drivers will require all passengers to show their ShuttlePass, which will be provided to approved residents

    2424

  • 8/12/2019 DC Water 1st Street Tunnel SDIVP-Tunnel_Forum_Brief_FINAL, Dated 2014 05 29

    25/32

    Six

    Week

    Look

    Ahead

    ScottHoffman SkanskaJa Dee SKJD

    ThomasMarch,SkanskaJayDee(SKJD)

    2525

  • 8/12/2019 DC Water 1st Street Tunnel SDIVP-Tunnel_Forum_Brief_FINAL, Dated 2014 05 29

    26/32

    Construction

    Main mining shaft activities

    Schedule for freeze trench

    Construction Staging Areas,

    V Streets

    Construction and traffic related

    2626

  • 8/12/2019 DC Water 1st Street Tunnel SDIVP-Tunnel_Forum_Brief_FINAL, Dated 2014 05 29

    27/32

    - -

    Install ground freezing utility trench: Began week of May 12 at 2400 block of First Street

    Cross Bryant Street and enter west alley: Starting May 22

    Status of Construction Staging Areas: Channing St: Fully active site; material delivery, site prep for slurry wall construction, site monitoring

    Adams St, May: Site investigations to confirm existing utilities and prep for installation of a portion of

    30water main

    V St: Mobilize for demolition and site prep in June

    Status of Alternative Parking Areas

    Bryant St: Construction complete

    APA Application distributed

    McMillan late Ma : Install ates lace erse barrier avin and stri in install car bum ers andsigns

    W St, mid May early June: Install temporary lighting; lot demo, grade, and site prep; excavate

    ramps, install stairs and retaining walls; install fence; pave ramp, driveway and install striping

    2727

    ,

  • 8/12/2019 DC Water 1st Street Tunnel SDIVP-Tunnel_Forum_Brief_FINAL, Dated 2014 05 29

    28/32

    As SKJD com letes trench closures construction will move tothe next block south on the following schedule:

    Week of May 19 west alley between Bryant Street and Adams Street

    Week of June 2 west alley between Adams Street and W Street

    Week o f June 16 west alley between W Street and V Street

    Week o f July 21 west alley between U Street and Thomas Street

    2828

  • 8/12/2019 DC Water 1st Street Tunnel SDIVP-Tunnel_Forum_Brief_FINAL, Dated 2014 05 29

    29/32

    SharonRobinsonGoods,SkanskaJayDee(SKJD)

    2929

  • 8/12/2019 DC Water 1st Street Tunnel SDIVP-Tunnel_Forum_Brief_FINAL, Dated 2014 05 29

    30/32

    SKJD developed a plan to ensure uninterrupted garbage collection throughoutthe duration of the two-year project

    SKJD is coordinating efforts with the District Department of Public Works tomeet individual homeowner needs during construction

    The Garbage Collection Plan calls for continued Wednesday morning recycleand garbage collections for affected addresses along the freeze trench area

    and at the Construction Staging Areas SKJD will notify affected homeowners prior to construction of the Garbage

    Collection Plan for their specific block

    Residents will be asked to address-label their receptacles and identify theirback yards so work crews can ensure proper return of receptacles

    DPW will designate the west First Street alley as its first collection location andplan to pick up between 7:30AM and 8AM each Wednesday

    3030

    Fi t St t T l P j t W b it

  • 8/12/2019 DC Water 1st Street Tunnel SDIVP-Tunnel_Forum_Brief_FINAL, Dated 2014 05 29

    31/32

    First Street Tunnel Project Website,

    For construction updates, traffic advisories, historical facts, mitigation efforts,FAQs, and more, visit us at

    www.dcwater.com/click on First Street Tunnel on DC Waters Home Page (lower right)

    Community updates

    Neighborhood support services

    Historical overview of flooding in Bloomingdale

    Previous engineering studies and additional

    resources Mitigation efforts

    Coordination with other agencies

    Fre uentl Asked Questions

    3131

  • 8/12/2019 DC Water 1st Street Tunnel SDIVP-Tunnel_Forum_Brief_FINAL, Dated 2014 05 29

    32/32

    APA application approval process is ongoing

    Ground Breaking Ceremony Wednesday, June 18 at 10AM

    Schedule next Tunnel Forumee ng urs ay, une ,

    from 7PM to 8:30PM

    To ics:

    What would you liketo discuss?