DistrictofColumbiaWaterandSewerAuthority . ,
Briefingon:DC CLEAN RIVERS PROJECT
First Street Tunnel
Revised First Street NW
Maintenance of Traffic Plan, APA Eligibility,
Garbage Collection Services, and More
Briefingfor:First Street Tunnel Forum /Community Group
May29,2014
11
8/12/2019 DC Water 1st Street Tunnel SDIVP-Tunnel_Forum_Brief_FINAL, Dated 2014 05 29
2/32
Tunnel Forum
Location / Group Representative Alternate
rs ree r. ar yn as ey omas ncarac on
Bryant /Channing Streets Renee Peres Philomena FritzFlagler Place Victoria Leonard Pia Brown
Adams Street Shelly Parker Dianne Barnes
W Street Joe Levesque Neal Herman
First and V Streets Angela Ray Theodore Bush
U Street Serita Sanders John Salatti
Thomas St /Rhode Island Ave Chris Von Ferro Harvey Hartsfield
Local Blo s Scott Roberts Bets McDaniel
Government-ANC Mark Mueller Teri Janine Quinn
Civic Associations Sherry Howard
22
All meetings are open to the public.
8/12/2019 DC Water 1st Street Tunnel SDIVP-Tunnel_Forum_Brief_FINAL, Dated 2014 05 29
3/32
Revised First Street NW Main-
Construction Update, continuedtenance of Traffic Plan/Q&A
Alternative Parking Areas
Addressing Community
Concerns
Freeze Trench Construction
Residential Parking Tag Process
Security
Schedule
Garbage Collection Plan alongFreeze Trench Alignment and
Escort
Shuttle
Construction U date
near ons ruc on ag ng reas
First Street Tunnel Project
Website Launched Six-Week Look-Ahead and
Street Activity
Next Steps
Ground Breaking Ceremony
33
,
Tunnel Forum June 26, at 7PM
8/12/2019 DC Water 1st Street Tunnel SDIVP-Tunnel_Forum_Brief_FINAL, Dated 2014 05 29
4/32
JohnKennedy,DCCleanRiversProject
44
8/12/2019 DC Water 1st Street Tunnel SDIVP-Tunnel_Forum_Brief_FINAL, Dated 2014 05 29
5/32
8/12/2019 DC Water 1st Street Tunnel SDIVP-Tunnel_Forum_Brief_FINAL, Dated 2014 05 29
6/32
Revised First Street NW Traff ic Plan
2113 First St NW
2115 First St NW2114 First St NW
2105 First St NW
2107 First St NW2109 First St NW
2111 First St NW
2106 First St NW
2108 First St NW
2110 First St NW
Area of Tree Box, Curband Sidewalk Impacts
Tree Boxes
Removed in front
of 14 Residences
Construction
2103 First St NW
2100 First St NW
2102 First St NW
rs
87 V St NW
Construction
Closures(Typical)
t
2035 First St NW2034 First St NW
2036 First St NW 2037 First St NW
Staging Area
tNW
2033 First St NW
2031 First St NW
2029 First St NW
2027 First St NW
2032 First St NW
2030 First St NW
2028 First St NW
2026 First St NW
Area of Tree Box, Curband Sidewalk Impacts
66
First
2025 First St NW2023 First St NW
2021 First St NW
2024 First St NW2022 First St NW
2020 First St NW
8/12/2019 DC Water 1st Street Tunnel SDIVP-Tunnel_Forum_Brief_FINAL, Dated 2014 05 29
7/32
Revised First Street NW Traff ic Plan
- -
4'-0" sidewalkwidth10
Extends to2113 First St
TemporaryConcreteBarrier
Construction
Construction
Lane Closures
(Typical)
N B
rs reeDiversionChamber
ConstructionLane Closures
V St NWTruck &EquipmentDelivery
Access
FirstSt
NW
Install concrete barrier for edestrian safet
(Typical)
77
N B Temporary 4-0 wide sidewalk
10-0 NB travel lane
Construct First Street Diversion Chamber support of excavation
Extends to2025 First StNW
8/12/2019 DC Water 1st Street Tunnel SDIVP-Tunnel_Forum_Brief_FINAL, Dated 2014 05 29
8/32
Revised First Street NW Traff ic Plan
- -
'- "
10'-0" Travel Lane
East RetainingWall
West
Retaining Wall
Temporary ConcreteBarrier
88
Approx. 44-0 Deep
8/12/2019 DC Water 1st Street Tunnel SDIVP-Tunnel_Forum_Brief_FINAL, Dated 2014 05 29
9/32
Revised First Street NW Traff ic Plan
- -
6'-0" sidewalkwidth
10
Extends to2113 First StNW
TemporaryConcreteBarrierT ical
Construction
Construction
Lane Closures
ConstructionLane Closures
rs ree vers onChamber
V St NWTruck &EquipmentDelivery
Access
Travel lane shifts
FirstSt
NW
(Typical)
99
Extends to2025 First StNW
Concrete barriers shift Widen sidewalk to 6-0
Construct First Street Diversion Chamber
8/12/2019 DC Water 1st Street Tunnel SDIVP-Tunnel_Forum_Brief_FINAL, Dated 2014 05 29
10/32
Revised First Street NW Traff ic Plan
- -
'- "
10'-0" Travel Lane
East Retaining
Wall
West
Retaining Wall
Temporary ConcreteBarrier
1010
Approx. 44-0 Deep
8/12/2019 DC Water 1st Street Tunnel SDIVP-Tunnel_Forum_Brief_FINAL, Dated 2014 05 29
11/32
Revised First Street NW Traff ic PlanOne-wa Northbound 6-ft Sidewalk & Buffer A rox. 12 Months
Extends to2113 First St
6'-0" sidewalkwidth
Temporary
ConcreteBarrierT ical
Construction
Construction
Lane Closures
N B
ChannelizingDevice(Typical)
ConstructionLane Closures
rs ree vers onChamber
V St NWTruck &EquipmentDelivery
Access
Travel lane shifts
FirstSt
NW
(Typical)
1111
N BExtends to2025 First StNW
Increase buffer zone
6-0 Sidewalk width maintained
Construct remaining structures
8/12/2019 DC Water 1st Street Tunnel SDIVP-Tunnel_Forum_Brief_FINAL, Dated 2014 05 29
12/32
Revised First Street NW Traff ic Plan
- - +
'- "
11'-0" Travel Lane
4'-0" Buffer
East Retaining
Wall
West
Retaining Wall
anne z ngDevice
Temporary ConcreteBarrier
1212
Approx. 44-0 Deep
8/12/2019 DC Water 1st Street Tunnel SDIVP-Tunnel_Forum_Brief_FINAL, Dated 2014 05 29
13/32
Revised First Street NW Traff ic PlanRenderin One-wa NB 6-ft Sidewalk & Buffer A rox. 12 Mo.
1313
8/12/2019 DC Water 1st Street Tunnel SDIVP-Tunnel_Forum_Brief_FINAL, Dated 2014 05 29
14/32
Revised First Street NW Traff ic Plan
Plan maintains existing sidewalk width for all but a
-
One-waying First Street NW provides additionalbuffer zone to provide further separation of
vehicular and pedestrian traffic
Posted speed limit signage and traffic calming ons ruc on spee m re uc ons roug
staging area
Reinforced concrete barriers rovided to rotectpedestrians
1414
8/12/2019 DC Water 1st Street Tunnel SDIVP-Tunnel_Forum_Brief_FINAL, Dated 2014 05 29
15/32
First Street NW Closure
6800
220% Increase
470% Increase
Lane Widths
Between Parked
10004700
3100
4200500
Street Width (ft)
First St NW 19.5
U St NW 20
840% Increase
Traffic Flow
2nd St NW 18.5
W St NW 16
XXXX 2013 Volume Count
LaneClosures/CSA
XXXX 2013 Volume with NBDetour Count (vehicles/day)
151515
Close First Street NW during construction of First Street Diversion Chamber (8 Months) One-way traffic for the remainder of construction (12 Months) Southbound traffic along First Street is detoured to North Capitol Street via Bryant Street NW
8/12/2019 DC Water 1st Street Tunnel SDIVP-Tunnel_Forum_Brief_FINAL, Dated 2014 05 29
16/32
First Street NW Closure
Significant increase in traffic along narrow
to handle estimated traffic volumes
Greater amount of residents affected by
W Street NW would need to be one-wayed or
parking restricted to accommodate plan
Level of service reductions and increase in
queue lengths along U, W and 2nd Streets NW
response times (fire, medical emergencies) to
homes and businesses
1616
8/12/2019 DC Water 1st Street Tunnel SDIVP-Tunnel_Forum_Brief_FINAL, Dated 2014 05 29
17/32
Skanska to submit revised plan to
Work at the V Street ConstructionStaging Area to begin June 2014
Tree boxes will be removed in July
2014
1717
8/12/2019 DC Water 1st Street Tunnel SDIVP-Tunnel_Forum_Brief_FINAL, Dated 2014 05 29
18/32
aintenance o Tra ic Plan
1818
8/12/2019 DC Water 1st Street Tunnel SDIVP-Tunnel_Forum_Brief_FINAL, Dated 2014 05 29
19/32
ThomasMarch,SKJD
SharonRobinsonGoods,SKJD
1919
8/12/2019 DC Water 1st Street Tunnel SDIVP-Tunnel_Forum_Brief_FINAL, Dated 2014 05 29
20/32
Alternative Parking Areas
McMillan ReservoirN Alternative Parking Areas
Alternative Parking Areasfor eligible residents areshown as
are shown in blue
Residents whose property
area ( ) are eligible to
apply for an APA Parking Tag
2020
8/12/2019 DC Water 1st Street Tunnel SDIVP-Tunnel_Forum_Brief_FINAL, Dated 2014 05 29
21/32
APAs
An APA Application for an APA Parking Tag was provided at the frontdoor of your residence the week of May 19, 2014
Priority will be given to: Special-needs residents
Those whose property is directly fronting a Construction Staging Area
and who have no off-street parking
Area bounded by Second Street NW, alleyway just east of First, Thomas,
To apply for an APA Parking Tag and Shuttle Pass, you will need:
APA Application and Terms of Service Agreement
Current insurance carrier and policy number
DC vehicle registration
2121
8/12/2019 DC Water 1st Street Tunnel SDIVP-Tunnel_Forum_Brief_FINAL, Dated 2014 05 29
22/32
APAs
,
Dates and times to present the items at the Site Office(at 2036 First St NW) and apply for an APA Parking Tag are:
Fridays
May 30, June 6, 13, and 20 from 6PM to 8PM
, ,
Call the Hotline at 1-844-FST-INFO (1-844-378-4636)
for additional dates and times Upon approval, you will receive an
APA information package that includes:
APA Parking Tag Shuttle Pass, schedule, and map
Site Office hours at 2036 First Street NW
2222
APA application is the upper portion of the
Registration and Terms of Service Agreement
form
8/12/2019 DC Water 1st Street Tunnel SDIVP-Tunnel_Forum_Brief_FINAL, Dated 2014 05 29
23/32
APAs
A Security Emergency Response Plan is in place for thisproject
Security personnel are trained in basic First Aid, CPR, and useof Automated External Defibrillation AED units
Contingency plans are in place to respond to emergencies
Video surveillance cameras at all APA locations Security personnel will provide 24/7 continuous monitoring of
APAs and surrounding areas
Securit ersonnel will be dressed in a uniform
Security communication hub will be equipped with computer,phone, internet, and two-way radio base station
2323
8/12/2019 DC Water 1st Street Tunnel SDIVP-Tunnel_Forum_Brief_FINAL, Dated 2014 05 29
24/32
APAs
Hours of operation for security and shuttle services are 24/7, includingholidays, for the duration of the project
Services will be coordinated through the Hotline- - - -
Operate two special needs-accessible shuttle vans with nine-seat capacity
Shuttle service will be: Provided with a predetermined route covering all affected areas
Provided to local residents between their homes and the three APAs
Available within minutes of request, barring any related service runs inprogress
Upon entry, shuttle drivers will require all passengers to show their ShuttlePass, which will be provided to approved residents
2424
8/12/2019 DC Water 1st Street Tunnel SDIVP-Tunnel_Forum_Brief_FINAL, Dated 2014 05 29
25/32
Six
Week
Look
Ahead
ScottHoffman SkanskaJa Dee SKJD
ThomasMarch,SkanskaJayDee(SKJD)
2525
8/12/2019 DC Water 1st Street Tunnel SDIVP-Tunnel_Forum_Brief_FINAL, Dated 2014 05 29
26/32
Construction
Main mining shaft activities
Schedule for freeze trench
Construction Staging Areas,
V Streets
Construction and traffic related
2626
8/12/2019 DC Water 1st Street Tunnel SDIVP-Tunnel_Forum_Brief_FINAL, Dated 2014 05 29
27/32
- -
Install ground freezing utility trench: Began week of May 12 at 2400 block of First Street
Cross Bryant Street and enter west alley: Starting May 22
Status of Construction Staging Areas: Channing St: Fully active site; material delivery, site prep for slurry wall construction, site monitoring
Adams St, May: Site investigations to confirm existing utilities and prep for installation of a portion of
30water main
V St: Mobilize for demolition and site prep in June
Status of Alternative Parking Areas
Bryant St: Construction complete
APA Application distributed
McMillan late Ma : Install ates lace erse barrier avin and stri in install car bum ers andsigns
W St, mid May early June: Install temporary lighting; lot demo, grade, and site prep; excavate
ramps, install stairs and retaining walls; install fence; pave ramp, driveway and install striping
2727
,
8/12/2019 DC Water 1st Street Tunnel SDIVP-Tunnel_Forum_Brief_FINAL, Dated 2014 05 29
28/32
As SKJD com letes trench closures construction will move tothe next block south on the following schedule:
Week of May 19 west alley between Bryant Street and Adams Street
Week of June 2 west alley between Adams Street and W Street
Week o f June 16 west alley between W Street and V Street
Week o f July 21 west alley between U Street and Thomas Street
2828
8/12/2019 DC Water 1st Street Tunnel SDIVP-Tunnel_Forum_Brief_FINAL, Dated 2014 05 29
29/32
SharonRobinsonGoods,SkanskaJayDee(SKJD)
2929
8/12/2019 DC Water 1st Street Tunnel SDIVP-Tunnel_Forum_Brief_FINAL, Dated 2014 05 29
30/32
SKJD developed a plan to ensure uninterrupted garbage collection throughoutthe duration of the two-year project
SKJD is coordinating efforts with the District Department of Public Works tomeet individual homeowner needs during construction
The Garbage Collection Plan calls for continued Wednesday morning recycleand garbage collections for affected addresses along the freeze trench area
and at the Construction Staging Areas SKJD will notify affected homeowners prior to construction of the Garbage
Collection Plan for their specific block
Residents will be asked to address-label their receptacles and identify theirback yards so work crews can ensure proper return of receptacles
DPW will designate the west First Street alley as its first collection location andplan to pick up between 7:30AM and 8AM each Wednesday
3030
Fi t St t T l P j t W b it
8/12/2019 DC Water 1st Street Tunnel SDIVP-Tunnel_Forum_Brief_FINAL, Dated 2014 05 29
31/32
First Street Tunnel Project Website,
For construction updates, traffic advisories, historical facts, mitigation efforts,FAQs, and more, visit us at
www.dcwater.com/click on First Street Tunnel on DC Waters Home Page (lower right)
Community updates
Neighborhood support services
Historical overview of flooding in Bloomingdale
Previous engineering studies and additional
resources Mitigation efforts
Coordination with other agencies
Fre uentl Asked Questions
3131
8/12/2019 DC Water 1st Street Tunnel SDIVP-Tunnel_Forum_Brief_FINAL, Dated 2014 05 29
32/32
APA application approval process is ongoing
Ground Breaking Ceremony Wednesday, June 18 at 10AM
Schedule next Tunnel Forumee ng urs ay, une ,
from 7PM to 8:30PM
To ics: