Upload
sharlene-murphy
View
214
Download
0
Tags:
Embed Size (px)
Citation preview
Econ 522Economics of Law
Dan Quint
Fall 2011
Lecture 11
2
Contract = legally binding promise Allow for cooperation/trade when transactions aren’t instantaneous First purpose of contract law: enable cooperation
What promises should be enforced? Bargain theory: those given as part of a bargain
Three elements: offer, acceptance, consideration Efficiency: any promise both promisor and promisee wanted to be
enforceable
Information Asymmetric/private info can prevent trade; contract law can help Second purpose: encourage efficient disclosure of information
Contract law: the story so far
3
May become efficient/necessary to break a promise
When should a contract be breached? Breach of contract is efficient when
cost to perform > benefit of performance to promisee Breach is in promisor’s interest when
cost to perform > promisor’s liability from breach Expectation damages: liability from breach = benefit to promisee Leads to breach exactly when it’s efficient Think of this as “designing the law to internalize an externality” Third purpose of contract law: obtain optimal commitment to performance
Contract law: the story so far
4
Reliance
5
Reliance
You expect an airplane to arrive in spring – you might… Sign up for flying lessons Build yourself a hangar Buy a helmet and goggles
Reliance – investments which depend on performance Reliance increases the value of performance to promisee Reliance increases the social cost of breach
The fourth purpose of contract law is to secure optimal reliance
6
When is reliance efficient?
When social benefit of reliance > social cost of reliance
Social benefit is increased benefit to promisee (Value of airplane + hangar) – (Value of airplane without hangar) Value is only realized if the promise is performed
Social cost is cost borne by promisee Cost occurs whether or not promise is performed
Reliance is efficient if
Increase in value of
performance
Cost ofinvestment>Probability of
performanceX
7
How should reliance figure into damages?
Expectation damages = expected benefit from performance
If reliance investments increase the anticipated benefit…
should they increase the damages I owe you in the event of breach?
Can we design damages to get efficient reliance, in addition to efficient breach?
8
You’re buying an airplane from me Price is $350,000, to be paid on delivery Airplane alone gives you benefit of $500,000 Building a hangar costs $75,000 Airplane with hangar gives you benefit of $600,000
Without hangar, expectation damages = $150,000
If you build a hangar and I fail to deliver plane, do I owe… $150,000? (Value of original promise) $250,000? (Value of performance after your investment) $225,000? (Value of original promise, plus reimburse you for investment
you made) Some other amount?
Reliance and damages:example
Price of plane = $350,000 Value of plane = $500,000Cost of hangar = $75,000Value of plane + hangar = $600,000
9
The only way to guarantee efficient breach is if damages included the added benefit from reliance Once you’ve made investment, you anticipate benefit of $250,000
from performance If damages are anything less than that, I’ll breach too often (If damages exclude the added benefit, then I’m back to imposing
an externality when I choose to breach the contract)
So what happens to the incentive for reliance investments if damages will increase to include this added benefit?
To get efficient breach…Price of plane = $350,000 Value of plane = $500,000Cost of hangar = $75,000Value of plane + hangar = $600,000
10
If you don’t build hangar, your payoff will be… $150,000 if I deliver the plane ($500,000 – $350,000) $150,000 if I breach and pay expectation damages
If you build hangar, your payoff will be… $175,000 if I deliver the plane ($600,000 – $350,000 – $75,000) $175,000 if I breach and pay (higher) expectation damages
So if expectation damages include the increased value of performance due to reliance investments… You’ll invest whenever (increase in benefit) > (cost) In this case, you’ll invest (because $100,000 > $75,000)
If exp damages includebenefit from reliance…
Price of plane = $350,000 Value of plane = $500,000Cost of hangar = $75,000Value of plane + hangar = $600,000
11
If expectation damages include increased value of performance, you’ll invest for sure
Is this efficient? Reliance is efficient if
(increase in benefit) X (probability of performance) > (cost)
$100,000 X (probability of performance) > $75,000 Only efficient if probability of performance > ¾ If probability of performance < ¾, reliance is inefficient, but happens
anyway
Overreliance!
If exp damages includebenefit from reliance…
Price of plane = $350,000 Value of plane = $500,000Cost of hangar = $75,000Value of plane + hangar = $600,000
12
Better example:continuous investment
xy 600
Investment in hangar
Additionalvalue ofplane
$100
$10,
000
$40,
000
$160
,000
$640
,000
Tarp and rope - $6,000 benefit
Plywood frame, canvas roof - $60,000
Metal poles, rigid roof - $120,000
Functional heating - $240,000
Designer hangar with Starbucks - $480,000
Price of plane = $350,000Cost: either $250,000 or $1,000,000Value of plane + $x hangar =$500,000 + 600x
13
Let p be probability of breach
Three questions What is the efficient level of reliance?
What will promisee do if expectation damages include anticipated benefit from reliance?
What will promisee do if expectation damages exclude anticipated benefit from reliance?
Three questionsPrice of plane = $350,000Cost: either $250,000 or $1,000,000Value of plane + $x hangar =$500,000 + 600x
14
Let p be probability of breach
Three questions What is the efficient level of reliance?
x = $90,000 (1 – p)2
What will promisee do if expectation damages include anticipated benefit from reliance?
x = $90,000
What will promisee do if expectation damages exclude anticipated benefit from reliance?
x = $90,000 (1 – p)2
Three questionsPrice of plane = $350,000Cost: either $250,000 or $1,000,000Value of plane + $x hangar =$500,000 + 600x
15
Overreliance
If reliance investments increase the damages you’ll receive in the event of breach, you’ll over-rely You’ll rely if
Efficient to rely if
So if damages increase when you make reliance investments, we’re sure to get overreliance!
(Your investment imposes an externality on me)
Increasein benefit
Cost ofinvestment>Prob. of
perform.X Increasein damages
Prob. of breachX+
Increasein benefit
Cost ofinvestment>Prob. of
perform.X
16
Reliance and breach
Just showed: if damages include added benefit from reliance, promisee will invest more than efficient amount
But if damages exclude added benefit… Then promisor’s liability < promisee’s benefit from performance Which means: promisor will breach more often than efficient
“Paradox of compensation” Single “price” (damages owed) sets multiple incentives… …impossible to set them all efficiently!
17
Cooter and Ulen: include only efficient reliance Perfect expectation damages: restore promisee to level of well-
being he would have gotten from performance if he had relied the efficient amount
So promisee rewarded for efficient reliance, not for overreliance
So what do we do?
18
Cooter and Ulen: include only efficient reliance Perfect expectation damages: restore promisee to level of well-
being he would have gotten from performance if he had relied the efficient amount
So promisee rewarded for efficient reliance, not for overreliance
Actual courts: include only foreseeable reliance That is, if promisor could reasonably expect promisee to rely that
much
So what do we do?
19
1850s England Hadley ran flour mill, crankshaft broke Baxendale’s firm hired to transport
broken shaft for repair Baxendale shipped by boat instead of
train, making it a week late Hadley sued for the week’s lost profits
“The shipper assumed that Hadley, like most millers, kept a spare shaft. …Hadley did not inform him of the special urgency in getting the shaft repaired.” Court listed several circumstances where broken shaft would not force mill
to shut down Ruled lost profits not foreseeable Baxendale didn’t have to pay
Foreseeable reliance: Hadley v Baxendale
20
1850s England Hadley ran flour mill, crankshaft broke Baxendale’s firm hired to transport
broken shaft for repair Baxendale shipped by boat instead of
train, making it a week late Hadley sued for the week’s lost profits
“The shipper assumed that Hadley, like most millers, kept a spare shaft. …Hadley did not inform him of the special urgency in getting the shaft repaired.” Court listed several circumstances where broken shaft would not force mill
to shut down Ruled lost profits not foreseeable Baxendale didn’t have to pay
Foreseeable reliance: Hadley v Baxendale
21
Default Rules
22
Gaps: risks or circumstances that aren’t specifically addressed in a contract
Default rules: rules applied by courts to fill gaps
Default rules
23
Gaps: risks or circumstances that aren’t specifically addressed in a contract
Default rules: rules applied by courts to fill gaps
Writing something into a contract vs leaving a gap Allocating a loss (ex post) Versus allocating a risk (ex ante), before it becomes a loss
Default rules
24
Cooter and Ulen: use the rule parties would have wanted, if they had chosen to negotiate over this issue
This will be whatever rule is efficient
What should default rules be?
25
Cooter and Ulen: use the rule parties would have wanted, if they had chosen to negotiate over this issue
This will be whatever rule is efficient
Fifth purpose of contract law is to minimize transaction costs of negotiating contracts by supplying efficient default rules Do this by imputing the terms the parties would have chosen if they
had addressed this contingency
What should default rules be?
26
Don’t want ambiguity in the law
So default rule can’t vary with every case
Majoritarian default rule: the terms that most parties would have agreed to In cases where this rule is not efficient, parties can still override it in the
contract
Court: figure out efficient allocation of risks, then (possibly) adjust prices to compensate
Default rules
27
Example: probability ½, the cost of construction will increase by $2,000 Construction company can hedge this risk for $400 Family can’t do anything about it
Price goes up – who pays for it?
Default rules
28
Example: probability ½, the cost of construction will increase by $2,000 Construction company can hedge this risk for $400 Family can’t do anything about it
Price goes up – who pays for it? Construction company is efficient bearer of this risk So efficient contract would allocate this risk to construction
company Should prices be adjusted to compensate?
Default rules
29
Example: probability ½, the cost of construction will increase by $2,000 Construction company can hedge this risk for $400 Family can’t do anything about it
Price goes up – who pays for it? Construction company is efficient bearer of this risk So efficient contract would allocate this risk to construction
company Should prices be adjusted to compensate?
Default rules
30
So, Cooter and Ulen say: set the default rule that’s efficient in the majority of cases
Most contracts can leave this gap, save on transaction costs
In cases where this rule is inefficient, parties can contract around it
Default rules
31
Ian Ayres and Robert Gertner, “Filling Gaps in Incomplete Contracts: An Economic Theory of Default Rules”
Sometimes better to make default rule something the parties would not have wanted To give incentive to address an issue rather than leave a gap Or to give one party incentive to disclose information “Penalty default”
Default rules: a different view
32
Baxendale (shipper) is only one who can influence when crankshaft is delivered; so he’s efficient bearer of risk
If default rule held Baxendale liable, Hadley has no need to tell him the shipment is urgent
So Hadley might hide this information, which is inefficient Ayres and Gertner: Ruling in Hadley was a good one, not because
it was efficient, but because it was inefficient… …but in a way that created incentive for disclosing information
Penalty defaults: Hadley v Baxendale
33
Real estate brokers and “earnest money” Broker knows more about real estate law Default rule that seller keeps earnest money encourages broker to
bring it up if it’s efficient to change this
Penalty defaults: other examples
34
Real estate brokers and “earnest money” Broker knows more about real estate law Default rule that seller keeps earnest money encourages broker to
bring it up if it’s efficient to change this
Courts will impute missing price of a good, but not quantity Forces parties to explicitly contract on quantity, rather than leave it
for court to decide
Penalty defaults: other examples
35
Look at why the parties left a gap in contract Because of transaction costs use efficient rule For strategic reasons penalty default may be more efficient
Similar logic in a Supreme Court dissent by Justice Scalia Congress passed a RICO law without statute of limitations Majority decided on 4 years – what they thought legislature would have
chosen Scalia proposed no statute of limitations; “unmoved by the fear that this…
might prove repugnant to the genius of our law…” “Indeed, it might even prompt Congress to enact a limitations period that it
believes appropriate, a judgment far more within its competence than ours.”
When to use penalty defaults?