Upload
ely
View
62
Download
1
Embed Size (px)
DESCRIPTION
Electrical Power Systems (WBS 4). S. Ramakrishnan NCSX CDR May 21-23, 2002. Electrical Power System Requirements. Provide Source of all Electric Power for NCSX All AC Power At all Distribution Voltage levels 13.8kV,4.16kV,480V, 208/120V Includes Experimental AC Power - PowerPoint PPT Presentation
Citation preview
NCSX CDRMay 21-23, 2002
S. RamakrishnanSlide 1
NCSX
Electrical Power Systems (WBS 4)
S. RamakrishnanNCSX CDR
May 21-23, 2002
NCSX CDRMay 21-23, 2002
S. RamakrishnanSlide 2
NCSX
Electrical Power System Requirements
• Provide Source of all Electric Power for NCSX– All AC Power
• At all Distribution Voltage levels– 13.8kV,4.16kV,480V, 208/120V
» Includes Experimental AC Power» Includes AC Power to NB» Includes all Auxiliary AC Power up to Power Panels
– All DC Experimental Power• Provide DC power for stellarator coil systems
– 3 Modular, 1 TF, and 5 PF coil circuits» PS requirements based on Initial Ohmic Scenario» Clear path for future upgrades (other scenarios,
flexibility)
• Provide Diagnostics support for Sensor cabling• Grounding
NCSX CDRMay 21-23, 2002
S. RamakrishnanSlide 3
NCSX
PPPL Site Plan
TEST Cell
NCSX C-Site Location
FCPC BLDG
NCSX Control Room Location
FCPC Equipment tray
NCSX CDRMay 21-23, 2002
S. RamakrishnanSlide 4
NCSX
PPPL Partial Site Plan
NCSX CDRMay 21-23, 2002
S. RamakrishnanSlide 5
NCSX
D-Site Power Supplies
• D-site power supplies used for Modular, TF, and PF circuits
• Ample power and stored energy available (475 MVA and 2.2 GJ per MG)
• Ample flexibility for future upgrades (78 PSS)
• C-site supplies available for Trim coils
Parameter (Each Section) Value
Units
No Load Avg. DC Voltage
1012.85 Volts
Max DC Current
30 kA
Nominal Pulse DC current
24 kA
Nominal Pulse ESW
6 s
Nominal pulse repetition period
300 s
Max DC Cont. Current
3.25 kA
NCSX CDRMay 21-23, 2002
S. RamakrishnanSlide 6
NCSX
Power Supplies Shared with NSTX
NCSX M1 M2 M3 PF1/2 PF3 PF4 PF5 PF6 TF
NSTXTF Branch 1 PF5 PF2U PF3U PF2L PF3L PF1aU PF1aL OH
PSS 2 2 2 4 2 2 4 4 8Total PSS 30
PSS 4 4 2 8 2 6 4 4 12Total PSS 46
2T High Beta, 350kA Ohmic
PSS 4 4 2 8 8 12 4 4 12
Total PSS 58
Max current (A) 24000 24000 24000 24000 21000 19000 8000 11000 18000
Initial Ohmic Scenario
1.7T Ohmic, 1.7T High Beta
Typical Ckt. Arrangement
NCSX
CT- Current Transducer
PT-Voltage Transducer
G- Ground fault Relaying
NCSX CDRMay 21-23, 2002
S. RamakrishnanSlide 8
NCSX
Typical Circuit Arrangement Contd.
• DC power transmitted from D-site (FCPC) to C-site (EF/OH Bldg) via overhead transmission (1000 MCM cables)
• Disconnect and grounding switches provided at both ends
• Existing cables used to connect to MG bus to Test Cell
• Current/ Voltage transducers provided• Rapid changeover (4 hrs) possible
NCSX CDRMay 21-23, 2002
S. RamakrishnanSlide 9
NCSX
PS Control and Coil Protection
• NSTX Electrical Power Systems Computer will be shared
• Hardwired Control System (HCS) is provided– Modern PLC based system– Additional interlocks will be transmitted from C-Site to the D-
Site PLC
• Coil protection will also be provided– Instantaneous overcurrent– Ground fault– Timed overcurrent– I2t limit
Electrical Power System Costs
WBS4 Description Design (k$)Fab/Assembl
y k$Install/Tes
t (k$)Grand Total ( k$)
41 411 Aux. AC Power 94 102 303 499412 Exp.AC Power 9 6 28 43
41 Total 102 109 332 543
42 422 AC/DC Conv 15 1542 Total 15 15
43 431 C Site- DC Sys 99 165 102 366432 D to C Site- DC Sys 43 162 1106 1311433 D Site- DC Sys 99 331 289 719
43 Total 241 658 1497 2396
44 441 HCS/PLC 174 61 350 584442 Kirk Keys 26 12 58 96443 Real Time Contr 40 40444 DCCT/DCPT 92 291 225 608445 Coil Protection 86 49 102 237446 Ground Fault 17 8 34 59
44 Total 434 421 769 1624
45 451 Design Integration 378 378452 Diagnostics Support 132 34 301 467453 Testing 43 123 166
45 Total 554 34 424 1011
4 Total 1330 1221 3036 5587 6559.0
With 18% Cont
Schedule: Complete Installation by Dec 2005
NCSX CDRMay 21-23, 2002
S. RamakrishnanSlide 11
NCSX
Conclusions
• Sharing existing D-site power supplies with NSTX is a cost-effective solution for powering NCSX coils
• Existing AC power distribution system at C-site will feed other loads & have been used for PBX/PLT
• Technical & cost risks is minimal – Since this is standard electrical work– Cost is based on industry feedback & PPPL experience on
past projects– Is performed by experienced personnel. – Careful planning will mitigate schedule risk– Highest priority to Personnel Safety
NCSX CDRMay 21-23, 2002
S. RamakrishnanSlide 12
NCSX
NCSX CDRMay 21-23, 2002
S. RamakrishnanSlide 13
NCSX