    Quarterly Review Report 3rd Quarter 09

    Quarterly Report (Jul, Aug, Sep 09) - East Side Access (PM 3.2.62240) 2

    Table of Contents

    Executive Summary........................................................................................................................................................................ 3Status of ESA Budget and Schedule .............................................................................................................................................3Budget and Schedule Review....................................................................................................................................................... 4

    American Recovery and Reinvestment Act (ARRA) ..................................................................................................................... 4Highlights .................................................................................................................................................................................... 4Project Construction Critical Tasks (Page 1 of 2)........................................................................Error! Bookmark not defined.Project Construction Critical Tasks (Page 2 of 2)....................................................................................................................... 7

    Active Construction Contracts Summary..................................................................................................................................... 8 Active Projects Manhattan........................................................................................................................................................ 10

    CM009 Manhattan Tunnels Excavation ................................................................................................................................. 10CM019 Manhattan Structures Part 1 ..................................................................................................................................... 12CM008A Madison Yard Site Clearance.................................................................................................................................. 14CM004 44th St. Demolition & Construct Fan Plant Structure & 245 Park Ave. Entrance..................................................... 16FM216 MNR Traction Power MODs & 13.2 kV Loop ...........................................................................................................17CS790 GCT Protection Works................................................................................................................................................ 19

    Active Projects Queens.............................................................................................................................................................. 20CQE28-01 Emergency Work Civil/Structural......................................................................................................................... 20CQE28-02 Emergency Work Environmental ....................................................................................................................... 21CS810 Queens Instrumentation ..............................................................................................................................................22CQ031 Queens Bored Tunnels and Structures ....................................................................................................................... 23CH053 Harold Structure Part 1 and GO2 Substation ............................................................................................................24CH054A Harold Structures Part 2A .................................................................................................................................... 26FHA01 Harold Stage 1 Amtrak Direct Force Account ........................................................................................................ 27FHA02 Harold Early Stage 2 Amtrak Direct F / A..............................................................................................................29FHL01 Harold Stage 1 LIRR Direct Force Account............................................................................................................ 31FHL02 Harold Early Stage 2 LIRR Direct F/A ...................................................................................................................... 33FHA62 F Interlocking CIH..................................................................................................................................................... 35VHA/L02 Procure Harold Materials Stage 2 ...................................................................................................................... 37VH051 (Part 1) Harold and Point CILs ................................................................................................................................. 38VH051 (Part 2) Harold Tower Supervisory Control System .................................................................................................. 40

    Summary of Completed Contracts .............................................................................................................................................. 42Summary Program Schedule ..................................................................................................................................................... 43Contract Packaging Plan Rev. 8.0.......................................................................................................................................... 45

    Funding and Budget ..................................................................................................................................................................... 46Project Budget Summary (As of Sep 30, 2009) ($ in thousands) ............................................................................................... 46Pending Federal Funding from the American Recovery and Reinvestment Act ........................................................................ 46Project Funding Status (As of Sep 30, 2009) ............................................................................................................................. 47

    Risk Management and Project Execution Strategy FFGA Budget.......................................................................................... 48Force Account Construction Budget (As of Sep 30, 2009) ........................................................................................................ 49Force Account 2009 Commitment Summary (As of Sep 30, 2009) ............................................................................................ 49Changes from Last Quarter....................................................................................................................................................... 49

    Construction Safety, Security and Quality ................................................................................................................................. 50Fourth Quarter 09 Look Ahead ..............................................................................................................................................50Design ....................................................................................................................................................................................... 50

    Grand Central Terminal............................................................................................................................................................ 50Railroad Systems ....................................................................................................................................................................... 50 Operational Readiness/LIRR Start Up ......................................................................................................................................50Construction..............................................................................................................................................................................51

    Budget and Finance................................................................................................................................................................... 52 Quality....................................................................................................................................................................................... 52

    Methods and Procedures........................................................................................................................................................... 52 Safety ......................................................................................................................................................................................... 52Site and Systems Security .......................................................................................................................................................... 52

    Real Estate................................................................................................................................................................................. 53 Public Outreach ........................................................................................................................................................................53

  • 8/2/2019 ESA Quarterly Report 2009 Q3

    3/53

    Quarterly Review Report 3rd Quarter 09

    Quarterly Report (Jul, Aug, Sep 09) - East Side Access (PM 3.2.62240) 3

    Executive Summary

    Status of ESA Budget and Schedule

    BUDGETTOTAL (millions) Budget Awards Invoiced

    $ 7,328.0 $ 3,464.5 $ 1,775.3

    % Budget 47% 24%

    % Awards 51%

    Note: The budget and schedule reflect the September 2009 rebaseline as approved by the MTA Board

    CONSTRUCTION ONLY Budget Awards* Invoiced

    (millions) $ 5,590.5 $ 2,437.9 $ 894.6

    % Budget 44% 16%% Awards 37%

    *Awards reflect current contract values.

    CONTINGENCY(millions) Contingency

    FFGA Baseline $ 855$ 424Sept 09 Baseline

    Current Contingency $ 424

    Fifteen contracts valued at $348.0 millionCOMPLETED CONTRACTS

    Contracts Completed This Quarter Procure Harold Material Stage 1 Amtrak (VHA01)Procure Harold Material Stage 1 LIRR (VHL01)

    Note:As a result of the budget rebaseline, General Conditions contracts are now included in Construction which adds previouslycompleted contracts to the completed contract count.

    ACTIVE CONTRACTS Twenty eight contracts valued $ 2.329 billion

    Contracts Awarded This Quarter

    44th St and 245 Park Ave Entrance (CM004)Queens Bored Tunnels and Structures (CQ031)Harold Structures Part 2A (CH054A)Harold Stage 2 LIRR (FHL02)

    Note:As a result of the budget rebaseline, General Conditions contracts are now included in Construction which adds previouslyactive contracts to the active contracts count. Value includes unexecuted options for CQ031 and CM019.

    2009 PLANNED AWARDS (Budget)Three contracts valued at $0.215 billion (includes forceaccount)

    50th

    St Vent Plant (CM013) 115.8

    3rd

    Party Stimulus Materials (CS099) 37.9

    Northern Boulevard Crossing (CQ039) 61.5

    DESIGN 87% complete as of 9/30/09

    4th Qtr 09 work plan includes:

    1 contracts achieving 60% submittal

    1 contracts achieving 90% submittalNote Above budget values for 2009 Planned Awards may change as project scopes are further developed

  • 8/2/2019 ESA Quarterly Report 2009 Q3

    4/53

    Quarterly Review Report 3rd Quarter 09

    Quarterly Report (Jul, Aug, Sep 09) - East Side Access (PM 3.2.62240) 4

    Budget and Schedule Review

    In September, the MTA Board approved the 2010-14 Capital Program which included a

    revised Budget and Schedule for East Side Access. The Budget was raised to $7.328billion and the Revenues Service date is September 2016, as presented to the MTACCCommittee in July 2009.

    East S ide Acc ess Budget & Schedu le

    Note: July 2009 values exclude $463M in rolling stock costs, now budgeted elsewhere.

    7.244 7.220 7.328

    8.013

    0

    1

    2

    3

    4

    5

    6

    7

    8

    9

    Budget Low Budget HighMTA

    Mar-08Estimate

    MTAJul-09

    Estimates

    $ Billions

    w/o risk

    reserve

    Completion

    Dec-2013

    Completion

    Feb-2015

    Completion

    Mar-2016

    Completion

    Sep-2016

    Completion

    Jan-2017

    Completion

    Apr-2017

    Completion

    Apr-2017

    +The MTA Capital Program Review Board approved a Capital Plan Amendment

    authorizing an additional $1.5 billion in funding for the 2005-2009 Capital Program

    A series of working sessions were held between MTACC, FTA and the PMOC ondeveloping an Enterprise Level Project Execution Plan that will be used as a tool formanaging risks for both the East Side Access and the Second Avenue Subway projects

    American Recovery and Reinvestment Act (ARRA)

    MTA has submitted a grant to the FTA for use of $195.4 million in funds made availablethrough the ARRA. See page 52 for a list of the projects identified for ARRA funds

    Highlights

    Excavation started in the Manhattan East Bound Main Cavern and continues in the WestBound Main Cavern

    Drill and blast excavation at Grand Central Terminal (GCT) started in September 2009.Reframing steel has arrived which will take the load of existing columns surroundingescalator #4 Wellway in the lower level

  • 8/2/2019 ESA Quarterly Report 2009 Q3

    5/53

    Quarterly Review Report 3rd Quarter 09

    Quarterly Report (Jul, Aug, Sep 09) - East Side Access (PM 3.2.62240) 5

    All the Amtrak signal enclosures (case/hut) required for the F Interlocking CentralInstrumentation Houses (FHA62) arrived at Amtraks Lancaster, PA facility

    Achieved substantial completion for contractsMadison Yard Preparation (CS780), GrandCentral Terminal Instrumentation (CS800), Procure Harold Material Stage 1 Amtrak(VHA01), and Procure Harold Material Stage 1 LIRR (VHL01)

    Awarded the 44th St. Demolition & Construct Fan Plant Structure & 245 Park Ave.Entrance (CM004). The work includes construction of building structure and exteriorarchitectural finishes at 44th St., entrance infrastructure, and fit-out mechanical, electrical,and architectural finishes at 245 Park Ave.

    Awarded the last tunneling contract Queens Bored Tunnels and Structures (CQ031) forconstruction of three revenue tunnels and one non-revenue tunnel beneath Sunnyside Yardand Harold Interlocking

    Awarded contractHarold Structures Part 2A (CH054A) for construction of various civilinfrastructure elements at Harold Interlocking. This contract expands the existing LIRRand Amtrak Right of Way to make room for the future tunnels and track diversions

    LIRR began early work onHarold Stage 2 (FHL02) whichincludes cable trough, conduitand pull box installations located in Point Interlocking and the west end of HaroldInterlocking

    Completed the Concept of Operations (Rev A), Asset Management Plan (Rev 0), andOperational Readiness Program Management Plan (Rev 0)

    Reviewing bids forNorthern Boulevard Crossing (CQ039) and 50th St. Ventilation

    Facility (CM013). Awards are scheduled for the fourth quarter 2009.

  • 8/2/2019 ESA Quarterly Report 2009 Q3

    6/53

    Quarterly Report 3rd Quarter 09

    Quarterly Report (Jul, Aug, Sep 09) - East Side Access (PM 3.2.62240)

    Project Construction Critical Tasks (Page 1 of 2)

  • 8/2/2019 ESA Quarterly Report 2009 Q3

    7/53

    Quarterly Report 3rd Quarter 09

    Quarterly Report (Jul, Aug, Sep 09) - East Side Access (PM 3.2.62240)

    Project Construction Critical Tasks (Page 2 of 2)

  • 8/2/2019 ESA Quarterly Report 2009 Q3

    8/53

    Quarterly Report 3rd Quarter 09

    Quarterly Report (Jul, Aug, Sep 09) - East Side Access (PM 3.2.62240)

    Active Construction Contracts Summary

    Substantial CompletionCost Expenditure

    % Complete

    PlanNTP Orig Revised Forecast Plan* Actual

    Current

    Budget($M)

    OriginalContract

    Award($M)

    CurrentApproved

    Contract($M)

    Estimate at

    Completion($M)

    MANHATTAN / BRONXCM009 Manhattan Tunnels Excavations Dragados-Jud

    7/10/06 07/10 03/12 8/12 57.5/61.5% 58.7 449.3 427.9 438.0 449.3Project team is wand recover sche

    CM019 Manhattan Structures 1 Dragados-Jud

    04/01/08 03/12 03/12 8/12 14.9/15.2% 15.0 760.1 734.0 740.3 760.1Project team is wand recover sche

    CM008A Madison Yard Site Clearance Gramercy Gro

    03/09/09 06/10 06/10 06/10 57.1/71.8% 47.4 40.9 39.0 39.0 40.9Progress was limContractor is nowto recover sched

    CM004 44th

    St. Demolition & Construct Fan Plan Structure & 245 Park Ave. Entrance Yonkers Contr09/16/09 08/11 08/11 08/11 0.0% 0.0% 44.3 40.8 40.8 44.3 Contract awarded

    FM216 MNR Traction Power MODs & 13.2 kV Loop TC Electr

    09/25/08 03/10 03/10 07/10 53.9/59.8% 41.1% 14.8 13.8 14.1 14.8Slightly behind scto improve acces

    CS790 GCT Protection Works A

    10/23/08 10/09 06/10 06/10 61.0% 41.0% 12.8 10.3 12.0 12.8Contract Amendmcompletion date.

    *Late/ Early Plan

    QUEENSCQE28-01 Emergency Work Civil/Structural Railroad Cons

    06/11/08 11/08 010/09 11/09 99.5% 96.7% 9.1 5.5 8.7 9.1 Contract winding

    CQE28-02 Emergency Work Environmental Impact Enviro

    07/14/08 08/09 009/09 10/09 99.0% 66.9% 8.4 8.0 3.0 3.0 Remaining work

    CS810 Queens Instrumentation Wang Techno

    05/06/09 05/09 05/10 05/10 25.8% 21.8% 7.0 2.7 2.7 7.0 Slightly behind s

    CQ031 Queens Bored Tunnels and Structures Granite-Trayl

    09/28/09 09/12 09/12 09/12 0.0% 0.0% 694.1 659.2 659.2 694.1 Contract awarde

  • 8/2/2019 ESA Quarterly Report 2009 Q3

    9/53

  • 8/2/2019 ESA Quarterly Report 2009 Q3

    10/53

    Quarterly Report 3rd Quarter 09

    Quarterly Report (Jul, Aug, Sep 09) - East Side Access (PM 3.2.62240) 10

    Active Projects Manhattan

    CM009 Manhatt an Tunnels Exc avat ion J ul , Aug, Sep 09

    Contractor: Dragados/JudlauConstruction Manager: Mike Pujdak LONP#:: 8FTA Grant: NY-03-0344

    Description: The Manhattan tunnels excavation contract includes procurement of two 22 foot diameter rock tunnel boringmachines, installation of temporary utilities, excavation of chambers and wyes, TBM (4 drives) excavation ofapproximately 25,000 linear feet of tunnels and final concrete lining of 11,600 lf of the running tunnels.

    Construction

    Concrete Plug Removal at WB GCT 5. Robbins TBM in Anticipated Bad Ground at Lower Level.

    Schedule and Cost

    TBM Mining Data

    Length (lf) Start Date 3rdQtr. (lf) Cum lf % Complete

    EAST 3,108* 05/26/09 A 471 3,108 100

    WEST 5747 07/06/09 A 1,300 1,300 22.6

    * Length adjusted to account for additional footage mined w/ Roadheader (~ 5 ft)

    Progress:1.SELI TBM backed up 2,764 of 6,036 feet and will

    resume backing up after rib removal at GCT 5 EastBound

    2.Robbins TBM mining is ongoing at lower level 1,300 of5,747 LF (22.6 % Completed)

    3.Concrete plug removal completed at GCT 5 West Wye

    4.Begin excavation at GCT 1 and 2 West Wye, topheading by drill and blast

    5.Blasting operation is ongoing at Shaft 5 which is atemporary access entrance (blasted 990 of 1,357 cubicyard)

    Schedule: MTA conditionally approved a recovery schedule.

    Current schedule is showing delay of 4.5 months. Projectteam is working with contractor to mitigate schedule impactand finding new opportunities to recover delays.

    Cost: The project is within budget.

    Contract Modifications: Asof 09/30/09, twentymodifications, for a total of $10,074,942 have been executed.

    Critical Issues: Robbins TBM is currently in bad groundwhich was anticipated but is impacting the schedule to agreater extent than planned.

    Milestones CM009*

    Milestones DescriptionCurrent

    Approved PlanActual

    /Forecast

    Advertise (RFP) 01/06 01/06 (A)

    NTP 07/06 07/06 (A)

    Start Tunnel Mining 09/07 09/07 (A)

    Substantial Completion 03/12 8/12 (F)Close-Out 08/12 10/12 (F)

    Schedule Progress 3rd Qtr Cumulative

    Cost Expenditure Plan** Actual Plan** Actual

    Percent Complete 5.1/9.2 6.9 57.5/61.5 58.7* Milestones reflects combine CM009/CM019 Rebaseline schedule

    * * Late/ Early Plan

    Contract Costs ($000) as of 09/30/09

    CM009 F/A Support Total

    Budget at Award 449,351 4,041 453,393

    Current Budget 449,351 4,120 453,471

    Original Award 427,954 3,924 431,878Approved Changes 10,074 0 10,074

    Current Contract Value 438,028 3,924 441,952

    Invoiced Amount 257,282 1,321 258,603

    Estimate at Completion 449,351 4,120 453,471

  • 8/2/2019 ESA Quarterly Report 2009 Q3

    11/53

    Quarterly Report 3rd Quarter 09

    Quarterly Report (Jul, Aug, Sep 09) - East Side Access (PM 3.2.62240) 11

    Coordination Required

    Real Estate: All properties and easements are secured fortunnel construction. MTA sent mailings to owners regarding

    contract NTP, zones of influence, pre-construction survey,instrumentation, and monitoring.

    Railroad Agencies: Flagging and access protection are beingprovided by MNR and NYCT.

    MOU: N/A

    Permits: The contractor is responsible for securing thefollowing:

    Blasting Permit FDNY: Permit received

    Water Discharge Permit NYCDEP: Permit receivedbut contractor is seeking a variance

    Lane Closure Permits NYCDOT: Permit received for2nd Ave. and Northern Blvd

    Progress (CM009)

    0%

    10%

    20%

    30%

    40%

    50%

    60%

    70%

    80%

    90%

    100%

    Jul-06 Oct-06 Jan-07 Apr-07 Jul-07 Oct-07 Jan-08 Apr-08 Jul-08 Oct-08 Jan-09 Apr-09 Jul-09 Oct-09 Jan-10 Apr-10 Jul-10 Oct-10 Jan-11 Apr-11 Jul-11 Oct-11 Jan-12 Apr-12 Jul-12

    %Complete

    Early Plan % Complete

    Late Plan % Complete

    Actual

    NOTE: 1) The Progress curve is R ebaselined to incorporate Recov ery (UD9 Rev 3)

    Safety

    Project Contract BLS**(07)

    Lost Time Accidents 2.10 3.00 2.60

    Zero Lost Time Accidents this month

    Updated safety training, and reinforced bestpractices

    Continued ongoing safety walk-thru of sites *The project performance statistics are based on construction hours only

    **Bureau of Labor Statistics/National Industry Average

    Site Map

  • 8/2/2019 ESA Quarterly Report 2009 Q3

    12/53

  • 8/2/2019 ESA Quarterly Report 2009 Q3

    13/53

  • 8/2/2019 ESA Quarterly Report 2009 Q3

    14/53

  • 8/2/2019 ESA Quarterly Report 2009 Q3

    15/53

    Quarterly Report 3rd Quarter 09

    Quarterly Report (Jul, Aug, Sep 09) - East Side Access (PM 3.2.62240) 15

    Coordination Issues

    Real Estate: N/A

    Railroad Agencies: MNR

    MOU:

    Permits: Demolition permit received. Construction permit received

    Progress (CM008A)

    0%

    10%

    20%

    30%

    40%

    50%

    60%

    70%

    80%

    90%

    100%

    Mar-09 Apr-09 May-09 Jun-09 Jul-09 Aug-09 Sep-09 Oct-09 Nov-09 Dec-09 Jan-10 Feb-10 Mar-10 Apr-10 May-10 Jun-10 Jul-10

    Complete

    Early Plan

    Late Plan

    Actual

    Safety

    Safety Statistics*(Cumulative Incidents per 200,000 work-hours)

    Project Contract BLS**(07)

    Lost Time Accidents 2.10 0.00 2.60

    Zero Lost Time Accidents

    Continued ongoing safety walk-thru of sites

    The contractor continues to maintain appropriate

    ventilation and housekeeping during demolition *The project performance statistics are based on construction hours only

    **Bureau of Labor Statistics/National Industry Average

    Site Map

  • 8/2/2019 ESA Quarterly Report 2009 Q3

    16/53

    Quarterly Report 3rd Quarter 09

    Quarterly Report (Jul, Aug, Sep 09) - East Side Access (PM 3.2.62240) 16

    CM00 4 44t h St . Demol i t ion & Const ruct Fan Plant

    St ruc ture & 245 Park Ave. Ent ranceJ ul , Aug, Sep 09

    Contractor: Yonkers Contracting Company, Inc.Construction Manager: Daniel Connor FTA Grant: ARRA Stimulus Funds

    Construction

    Description: 47 E. 44th Street: Removehazardous material, demolish existingbuilding, perform soil and rockexcavation. Construct shell of newbuilding. Frame and partially fit out newbuilding245 Park Avenue Entrance:Conductenvironmental abatement anddemolition; construct new foundations,walls and supports, Furnish and installescalator; Install architectural finishes,plumbing, fire protection, HVAC,lighting, power, fire alarm, andcommunication systems.

    Schedule and Cost

    Progress:

    1. Contract awarded September 09

    2. Receipt and review of submittals are ongoing

    3. Weekly meetings with the contractor are being held

    4. Coordination of all MNR related work with the railroadhas commenced

    5. Contractor is acquiring all required permits for alldemolition and construction work

    Schedule: Preliminary schedule has been received and isunder review

    Cost: Budget reflects the award amount.

    Critical Issues: None.

    Milestones CM004

    Milestones DescriptionCurrent

    Approved Plan

    Actual/

    Forecast

    Advertise (IFB) 12/08 12/08 (A)

    NTP 09/09 9/09 (A)

    Substantial Completion 08/11 08/11

    Close-Out 12/11 12/11

    Schedule Progress 3nd Qtr Cumulative

    Cost Expenditure Plan Actual Plan Actual

    Percent Complete TBD TBD TBD TBD

    Contract Costs ($000) as of 09/30/09

    CM004 F/A Support Total

    Budget at Award 44,259 44,259

    Current Budget 44,259 44,259

    Original Award 40,765 40,765

    Approved Changes

    Current Contract Value 40,765 40,765

    Invoiced Amount

    Estimate at Completion 44,259 44,259

    Note: Force Account costs are reported with CM019.

    Coordination Required

    Real Estate: 47 E 44th St. acquired and vacated; NYC PlanningCommission approved 245 Park Ave. place change of use in Plaza area.Agreement was signed on April 14, 2009.

    Railroad Agencies: MNR and LIRR.

    Permits: Acquiring demolition, sidewalk and lane closingpermits.

    MOU: MOU with MNR executed.

  • 8/2/2019 ESA Quarterly Report 2009 Q3

    17/53

    Quarterly Report 3rd Quarter 09

    Quarterly Report (Jul, Aug, Sep 09) - East Side Access (PM 3.2.62240) 17

    FM216 MNR Tract ion Pow er MODs & 13.2 kV Loop J ul , Aug, Sep 09

    Contractor: TC Electric

    Construction Manager: James Murray FTA Grant: NY-03-0344

    Description: Furnish, deliver and install automated system for motor-operated disconnect switches (MODs). Scope of workalso includes reconfiguration of 13.2kV Traction Power feeder cables.

    Construction

    New Elevator Distribution Board in Switchboard Room. Core Drilling for Negative Feeder Conduit at Track 38.

    Schedule and Cost

    Progress

    1. Continued installation of conduit runs for power and controlfeeder for transformer houses (98% completed)

    2. Continued the installation of conduit runs for low voltagepower feeders in the upper level (95% completed)

    3. Continued the installation of conduit runs for negativefeeders (75% completed) and positive feeders (25%

    complete) in the upper level4. Continued pulling cables for power feeder Q94 and Q47A

    (98% completed)

    5. Continued pulling cables for negatives feeder 703A & B(95% completed)

    6. Started the replacement of existing switchboards inSwitchboard Room D (55% completed)

    7. The new Elevator Distribution Board was energized and cut-over for power super feeder were completed on September

    Schedule: Contract is running behind schedule due to difficultygetting track outage but no impact to follow-on contracts isanticipated.

    Cost: Project is within budget. Current budget includes scopetransfer fromManhattan Structures MNR (FMM19)

    Contract Modifications: Asof 09/30/09, three modifications,for a total of $343,930.04 have been executed.

    Safety: No recorded lost time incidents. Madison Yardshutdown during the period of 8/24/09 to 9/21/2009 was due tocontractMadison Yard Site Clearance (CM008A) constructionequipment fire. Impact is being evaluated.

    Critical Issues: Coordinating with MNR on outages due tooperational needs and other ESA contracts needed to keepperformance on schedule going forward.

    Milestones FM216

    Milestone DescriptionCurrent

    Approved PlanActual/Forecast

    Advertise (IFB) 05/08 05/08(A)

    NTP 09/08 09/08 (A)

    Compl. Work - 100 of Shaft #5 01/09 10/09

    Complete Switchboard D 03/09 11/09

    Complete Work N of 46th St. 12/08 11/09

    Complete Madison Yd. Work 04/09 02/10

    Substantial Completion 03/10 07/10

    Close-Out 06/10 10/10

    Schedule Progress 3rd Qtr Cumulative

    Cost Expenditure Plan* Actual Plan* Actual

    Percent Complete 22.0/23.8 12.7 53.9/59.8 41.1

    *Late/ Early Plan

    Contract Costs ($000) as of 09/30/09

    FM216 MNR Share Total

    Budget at Award 14,479 4,348 18,827Current Budget 14,765 4,348 19,113

    Original Award 13,790 4,140 17,930

    Approved Changes 344 0 344

    Current Contract Value 14,134 4,140 18,274

    Invoiced Amount 7,347 167 7,514

    Estimate at Completion 14,751 4,348 19,099

    * Force Account costs are reported with CM019.

  • 8/2/2019 ESA Quarterly Report 2009 Q3

    18/53

    Quarterly Report 3rd Quarter 09

    Quarterly Report (Jul, Aug, Sep 09) - East Side Access (PM 3.2.62240) 18

    Coordination Issues

    Real Estate: N/A

    Railroad Agencies: MNR

    MOU:

    Permits: N/A

    Progress (FM216)

    0%

    10%

    20%

    30%

    40%

    50%

    60%

    70%

    80%

    90%

    100%

    Oct-08 Nov-08 Dec-08 Jan-09 Feb-09 Mar-09 Apr-09 May-09 Jun-09 Jul-09 Aug-09 Sep-09 Oct-09 Nov-09 Dec-09 Jan-10 Feb-10 Mar-10 Apr-10 May-10 Jun-10 Jul-10

    %Complete

    Early

    Late

    Actual

    Safety

    Safety Statistics*(Cumulative Incidents per 200,000 work-hours)

    Project Contract BLS**(07)

    Lost Time Accidents 2.10 8.36 2.60

    Zero Lost Time Accidents

    Continued ongoing safety walk-thru of sites

    The contractor continues to maintain appropriateventilation and housekeeping during activity*The project performance statistics are based on construction hours only

    **Bureau of Labor Statistics/National Industry Average

    Site Map

  • 8/2/2019 ESA Quarterly Report 2009 Q3

    19/53

    Quarterly Report 3rd Quarter 09

    Quarterly Report (Jul, Aug, Sep 09) - East Side Access (PM 3.2.62240) 19

    CS790 GCT Prote c t ion Work s J ul , Aug, Sep 09Contractor: Ad-Tech EnterprisesConstruction Manager: Larry Nigro FTA Grant: N/A

    Description: Make all necessary concrete repairs to slabs, columns and beams and install protective mesh in GCT asneeded.

    Construction

    Netting Installation at Track 34. Asbestos Abated Pipes at Platform S.

    Schedule and CostProgress:

    1. Completed 75% of netting system installation north of gridline15 in the Upper Level of Grand Central Terminal

    2. Completed 55% of Asbestos Containing Materials (ACM) pipeinsulation abatement in the Upper Level

    3. Completed 30% of beam clamp/cable for netting system aboveplatform U and adjacent tracks 41 & 42

    4. Completed 40% of beam clamp/cable for netting system aboveplatform T and adjacent track 39 & 40

    5. Completed netting for switches 507, 511, 529, 531 and 547North of Gridline 15 in the Upper Level

    Schedule: Contractors schedule has been adjusted to supportblasting operations. Contract completion date modified to 6-30-10

    Cost: Contract costs are within budget

    Contract Modifications:As of 9/30/09, four modifications for atotal of $ 1,630,948 have been executed.

    Safety: No recorded lost time incidents.

    Critical Issues: Coordination with MNR on outages for North ofGridline 15 (Upper Level) for netting system installation in supportofManhattan Tunnels Excavation and Structures (CM009/19)blasting at shafts 4 & 5.

    Milestones CS790

    MilestonesDescription

    CurrentApproved Plan

    Actual/Forecast

    Advertise (RFP) 06/08 08/08 (A)

    NTP 10/08 10/08 (A)

    Substantial Completion 6/10 6/10

    Close-Out 7/10 7/10Schedule Progress 3rd Qtr Cumulative

    Cost Expenditure Plan Actual Plan Actual

    Percent Complete 6.0 12.0 61.0 41.0

    Contract Costs ($000) as of 09/30/09

    CS790F/A

    Support*Total

    Budget at Award 12,841 N/A 12,841

    Current Budget 12,841 N/A 12,841

    Original Award 10,329 N/A 10,329

    Approved Changes 1,631 N/A 1,631

    Current Contract

    Value

    11,960 N/A 11,960

    Invoiced Amount 4,912 N/A 4,912

    Estimate atCompletion

    12,841 N/A 12,841

    *Force Account costs are included in FMM19.

    Coordination Required

    Real Estate: N/A

    Railroad Agencies: MNR

    Permits: Issued

    MOU: This contract is covered by existing MNR MOU.

  • 8/2/2019 ESA Quarterly Report 2009 Q3

    20/53

    Quarterly Report 3rd Quarter 09

    Quarterly Report (Jul, Aug, Sep 09) - East Side Access (PM 3.2.62240) 20

    Active Projects Queens

    CQE28-01 Emerg enc y Work Civi l /Struc tura l J ul , Aug, Sep 09Contractor:Railroad Construction Co., Inc.Construction Manager: John Annoni FTA Grant: N/A

    Description: Perform work at open-cut excavation south of Northern Blvd. under the civil and structural emergency workcontract. The scope of work includes, resolving site safety/security issues, completing in-progress struts, completing Amtrakdeck and track work, investigating and repairing defective slurry wall panels, and completing slurry wall interface grouting(This scope was previously part of CQ028).

    Construction

    Asbestos Abatement. Coring Slurry Wall Panels.

    Schedule and CostProgress:

    1. Completed asbestos abatement at Amtrak Buildings 1 and 5.The asbestos abatement will continue at Amtraks building 2.

    2. Continue investigation of open-cut slurry wall repairs. Theinvestigation includes pump test and coring the slurry wallpanels. Information is being given to the Queens BoredTunnels and Structures (CQ031) contractor who willcomplete the investigation and do the repairs.

    Schedule:

    1. Delay in asbestos abatement work due to finalizing theeasement agreement of Amtraks building 1, 2 and 5 andbecause additional asbestos was found in Buildings 2 and 5.

    2. Time extension to be granted for additional work from theoriginal survey discovered during the abatement.

    Cost: Budget for additional work was funded from GeneralConditions.

    Contract Modifications: As of 09/30/09, thirteen modificationsto the original scope for a total of $3,222,980 were executed.

    Safety: No recorded lost time incidents.

    Critical Issues: None.

    *Substantial Completion extended for additional work from the originalscope.

    Milestones CQE28-01

    Milestones DescriptionCurrent

    Approved PlanActual/Forecast

    NTP 06/08 06/08(A)

    Safety & Security Issues 07/08 07/08 (A)

    Complete Amtrak Deck 08/08 08/08(A)

    Complete in-Progress Struts 09/08 09/08 (A)

    Substantial Completion* 10/09 11/09

    Schedule Progress 3rd Qtr Cumulative

    Cost Expenditure Plan Actual Plan Actual

    Percent Complete 2.6 17.3 99.5 96.7

    Contract Costs ($000) as of 09/30/09

    CQE28-01 F/A Support** Total

    Budget at Award 6,827 N/A 6,827

    Current Budget 9,087 N/A 9,087

    Original Award 5,548 N/A 5,548Approved Changes 3,223 N/A 3,223Current Contract Value 8,771 N/A 8,771Invoiced Amount 8,483 N/A 8,483

    Estimate at Completion 9,087 N/A 9,087

    ** F/A Access and Protection is currently being managed thru othercontracts (FQA28 and FQL28)

  • 8/2/2019 ESA Quarterly Report 2009 Q3

    21/53

    Quarterly Report 3rd Quarter 09

    Quarterly Report (Jul, Aug, Sep 09) - East Side Access (PM 3.2.62240) 21

    CQE28-02 Emerge nc y Work Environm ent al J ul , Aug, Sep 09

    Contractor:Impact Environmental Consulting, Inc.

    Construction Manager: John Annoni FTA Grant: N/ADescription: The scope of work includes disposing of current stockpiles on site and excavated materials by other contractors,monitoring groundwater, sampling water quality, environmental reporting and obtaining renewal of discharge permits (This scopewas previously part of CQ028).

    C

    onstructio

    Collecting Water Sample for Quality. Water Elevation Reading.

    Schedule and Cost

    Progress:

    1. Continued water quality and elevation readings

    2. Completed amendment to Long Island Well and

    Discharge PermitSchedule:

    1. Substantial completion is delayed pending the transfer ofthe Long Island Well Permit monitoring to Queens BoredTunnels and Structures (CQ031) contract

    Cost: The contract value is reduced because the remainingscope for disposal of excavated materials in this contract wastransferred to Queens Bored Tunnels and Structures (CQ031).

    Contract Modifications: As of 09/30/09, five modifications tothe original scope for the total of ($4,958,079) were executed.

    Safety: No recorded lost time incidents.

    Critical Issues: None.

    Milestones CQE28-02

    Milestones DescriptionCurrent

    Approved PlanActual/Forecast

    NTP 07/08 07/08 (A)

    Renewal of Discharge Permit 07/08 08/08 (A)

    Disposal of current stockpile 10/08 10/08 (A)

    Substantial Completion 10/09 10/09

    Schedule Progress 3rd Qtr Cumulative

    Cost Expenditure Plan Actual Plan Actual

    Percent Complete 22.3 4.3 99.0 66.9

    Contract Costs ($000) as of 09/30/09

    CQE28-02F/A

    Support** Total

    Budget at Award 8,388 N/A 8,388

    Current Budget 8,388 N/A 8,388

    Original Award 7,989 N/A 7,989Approved Changes -4,958 N/A -4,958

    Current Contract Value 3,031 N/A 3,031

    Invoiced Amount 2,027 N/A 2,027

    Estimate at Completion 3,031 N/A 3,031

    ** F/A Access and Protection is currently being managed thru othercontracts (FQA28 and FQL28)

  • 8/2/2019 ESA Quarterly Report 2009 Q3

    22/53

    Quarterly Report 3rd Quarter 09

    Quarterly Report (Jul, Aug, Sep 09) - East Side Access (PM 3.2.62240) 22

    CS810 Queens Inst rument at i on J ul , Aug, Sep 09

    Contractor:Wang Technology, LLCConstruction Manager: John Annoni FTA Grant: N/A

    Description: Procurement, installation and establishment of initial readings for structural instrumentation, geotechnicalinstrumentation, and data acquisition systems in Sunnyside Yard and Harold Interlocking to support Queens tunnel excavation.

    Co

    nstruction

    Installing Surface Monitoring Points. Drilling Deep Bench Mark.

    Schedule and Cost

    Progress:

    1. Installed track dynamic profile monitoring points atSunnyside Yard, Loop tracks and LIRR tracks (90%installation completed)

    2. Installed two deep bench marks and two inclinometers

    3. Tested prisms on LIRR tracks have been installed fortesting interference with train operation. No issuereported.

    4. Began installation of surface and structural monitoringpoints

    Schedule:Contractors baseline schedule is accepted. Thefirst update was submitted.

    The contractor was issued a modification to adjust interimmilestone. The installation schedule is being adjusted tocorrespond to the Queens Bored Tunnels and Structures(CQ031) schedule. Some work activities will begin laterthan the original schedule. As contract Queens Bored

    Tunnels and Structures (CQ031) was not awarded untilSeptember 2009 items behind schedule are no longer critical.

    Cost:The Estimate at Completion is within budget.

    Contract Modifications: As of 9/30/09, one modificationhas been executed with no dollar value.

    Critical Issues: None.

    Milestones CS810

    Milestones DescriptionCurrent

    Approved PlanActual/Forecast

    Notice to Proceed 05/09 05/09 (A)

    Completeprisms at 43rd

    St Bridge 09/09 10/09

    Instrumentation at Yard lead area 12/09 12/09

    Instrumentation near three tunnel exit 02/10 01/10

    Final acceptance 05/10 05/10

    Schedule Progress 3rd Qtr Cumulative

    Cost Expenditure Plan Actual Plan Actual

    Percent Complete 24.4 20.4 25.8 21.8

    Contract Costs ($000) as of 09/30/09

    CS810 F/A Support* Total

    Budget at Award 3,007 - 3,007

    Current Budget 3,007 - 3,007Original Award 2,737 - 2,737

    Approved Changes - - -

    Current Contract Value 2,737 - 2,737

    Invoiced Amount 597 - 597

    Estimate at Completion 3,007 - 3,007

    * Force Account Access and protection costs are reported with CH053.

  • 8/2/2019 ESA Quarterly Report 2009 Q3

    23/53

    Quarterly Report 3rd Quarter 09

    Quarterly Report (Jul, Aug, Sep 09) - East Side Access (PM 3.2.62240) 23

    CQ031 Queens Bored Tunne ls and Struc t ures J ul , Aug, Sep 09

    Contractor: Granite-Traylor-Frontier Joint VentureConstruction Manager: Robert Magnifico FTA Grant: NY-03-0344/ARRA Stimulus Funds

    Construction

    Description: Construct three revenue tunnels andone non-revenue tunnel beneath Sunnyside Yardand Harold Interlocking. Construction includesthe following; complete main open-cut excavation(from CQ028), procurement and assembly of twopressurized face tunnel-boring machines andancillary equipment, tunnel excavation,installation of a one-pass pre-cast concrete tunnelliner segments, installation of ground treatmentalong the alignment to support tunnelconstruction, underpinning bridge piers and LIRRmainline structures, construction of an Amtrakaccess road, and construction of exit/ventilationstructures (below-ground) and TBM reception pit.

    Track ATrack ATrack B/CTrack B/C

    LIRR LeadLIRR Lead

    Track DTrack D

    HoneywellSt

    HoneywellSt

    3939ththStSt

    idid

    --Day

    StorageY

    ard

    Day

    StorageY

    ard

    Sunnysid

    e

    Sunnysid

    e

    Yard

    Yard

    TBM Launch WallTBM Launch Wall

    TBMTBM

    OpenOpen--CutCut

    ExcavationExcavation

    Site Map.

    Schedule and CostProgress:

    1. The award letter and notice to proceed were issued to GTFJV on September 28, 2009

    2. The kick-off meeting will be held early October 2009

    3. Obtained Amtrak Project Initiative on September 19, 2009

    Schedule: Contractors preliminary schedule was submitted forreview.

    Cost: Contract value is $659,200,700 with one option,$58,400,000, to be executed at a future date. Final budget numberwill include the option once the option is awarded.

    Critical Issues: None

    Milestones CQ031

    Milestone DescriptionCurrent

    Approved Plan

    Actual/

    Forecast

    Advertise N/A 03/08 (A)NTP 09/09 09/09 (A)Temporary Substationfor TBM

    09/10 09/10

    Complete Tunnels 03/12 03/12Substantial Completion 09/12 09/12Close-Out 01/13 01/13

    Schedule Progress 3rd Qtr Cumulative

    Cost Expenditure Plan Actual Plan Actual

    Percent Complete TBD TBD TBD TBD

    Contract Costs ($000) as of 09/30/09

    CQ031 F/A Support Total

    Budget at Award 756,763 22,677 779,440

    Current Budget 756,763 22,677 779,440

    Original Award 659,201 0 659,201

    Approved Changes 0 0 0

    Current Contract Value 659,201 0 659,201

    Invoiced Amount 0 0 0

    Estimate at Completion 756,763 22,677 779,440

    Coordination Required

    Real Estate: All Real Estate has been acquired and tenants are beingrelocated.

    Railroad Agencies: Amtrak, LIRR, NYAR.

    Permits: A FDNY blasting permit and a water dischargepermit are required. Long Island well permit has beenobtained (from CQ028).

    MOU: Amtrak Project Initiative obtained and Permit toEnter application submitted

  • 8/2/2019 ESA Quarterly Report 2009 Q3

    24/53

    Quarterly Report 3rd Quarter 09

    Quarterly Report (Jul, Aug, Sep 09) - East Side Access (PM 3.2.62240) 24

    CH053 Harold Struc tur e Part 1 and GO2 Substat ion J ul , Aug, Sep 09Contractor:Perini Corp.Construction Manager: Ray Busch FTA Grant: NY-03-0344

    Description: Construct various civil infrastructure elements at Harold Interlocking and expand the existing LIRR Amtrak Rightof Way for the future TBM tunnels and Mainline track diversions including the design, and installation of a pre-fabricatedsubstation.

    Cons

    truction

    Driving Micro Boring Machine for Tunnel Run 9. Installing Pre-Cast Panels at Retaining Wall 39-S1.

    Schedule and CostProgress:

    1.Completed installation of Harold Access Bridge North and Southabutment

    2.Continued drilling shaft posts for Retaining wall 39-S3 andinstallation of pre-cast panel at Retaining Wall 39-S1

    3.Completed microtunneling Run 9

    4.Installed test piles at 43rd St bridge ML4 and successfullycompleted load test

    5.Continued excavation, rebar and concrete for catenary polefoundations at various locations

    6.Continued liner plates for Jacking pit #1 and receiving pit #2for microtunneling Run 6-7, west of 39th St.

    7.Continued sheeting at G02 substation and jacking pit 4

    8.Continued fabrication of 27 catenary structures, 31 additionalstructures are in fabrication

    9.Installed temporary relocation of 26.5KVfeeder along 39 Stbridge

    Schedule:1. An initial delay was experienced due to late issuance of the

    Amtrak Project Initiative and Amtrak entry permit. Impact ofthis delay on contractor is in negotiation.

    2. An additional delay was experienced for design of catenary andsignal tower foundations and structures. General Engineering

    Consultant (GEC) to issue 100% design drawings by end of theyear.

    3. Continued developing a revised CPM schedule taking intoaccount design related issues.

    4. Contractor hit static catenary line with no equipment orpersonal injuries causing a week plus shutdown. Impact toschedule is being evaluated.

    Cost: Delay to schedule, scope transfers and changes to design areimpacting cost. Full impact is being evaluated. The option work of$2 million for the Thompson Ave. Microtunnel was exercised.

    ** Additional $2 million option from LIRR is not included in the Current Contract

    Value

    Contract Modifications: As of 9/30/09, nineteen modificationsfor a total of $4,750,139 have been executed.

    Critical Issues: Resolve Amtrak ET (electrical traction) and12KV ductbank design issues so this activity can resume.Complete catenary and signal tower design packages. A re-baseline schedule is being developed so as to not impact criticalpath work.

    Milestones CH053

    Milestones DescriptionCurrent

    Approved PlanActual/Forecast

    NTP 01/08 01/08 (A)

    Substantial Completion 05/10 07/11 (F)

    Close-Out 09/10 11/11 (F)

    Schedule Progress 3rd Qtr Cumulative

    Cost Expenditure Plan* Actual Plan* Actual

    Percent Complete 10.3/12.3 6.1 66.5/87.5 30.1

    *Late/ Early Plan

    Contract Costs ($000) as of 09/30/09

    CH053F/A

    Support Total

    Budget at Award 144,144 18,212 162,356

    Current Budget 152,708 20,560 173,268

    Original Award 137,280 18,212 155,492

    Approved Changes 4,750 0 4,750

    Current Contract Value** 142,030 18,212 160,242

    Invoiced Amount 42,341 8,859 51,200

    Estimate at Completion 152,708 20,560 173,268

  • 8/2/2019 ESA Quarterly Report 2009 Q3

    25/53

    Quarterly Report 3rd Quarter 09

    Quarterly Report (Jul, Aug, Sep 09) - East Side Access (PM 3.2.62240) 25

    Coordination RequiredReal Estate: All easements have been secured.

    Railroad Agencies: LIRR and Amtrak will provideflagging protection and perform required support work.

    Permits: Pre-award reviews and approvals have been obtained fromNYCDOT and NYCDEP. Relevant permit have been obtained by the

    contractor. Amtrak Entry Permit approved.

    MOU: Amtrak labor clearance was obtained. LIRR and Amtrak forceaccount agreements were signed. Project Initiative (PI) with Amtrak signed.

    Progress Curve (CH053)

    0%

    10%

    20%

    30%

    40%

    50%

    60%

    70%

    80%

    90%

    100%

    Jan-08 Mar -08 May-08 Jul -08 Sep-08 Nov-08 Jan-09 Mar-09 May-09 Jul -09 Sep-09 Nov-09 Jan-10 Mar -10 May-10 Jul -10 Sep-10 Nov-10 Jan-11 Mar -11

    %C

    omplete

    Early

    Late

    Actual

    Safety

    Safety Statistics*(Cumulative Incidents per 200,000 work-hours)

    Project Contract BLS**(07)

    Lost Time Accidents 2.10 1.42 2.60

    Contractor hit static catenary line with no equipment orpersonal injuries

    Perini and ESA have worked with the railroads to establishand implement a Truck Access Management Protocol todefine truck routes, staging areas and minimize hazardsassociated with truck movements

    Train additional 3rd party safety representatives andcontinued to advise contractor management

    Continue ongoing safety walk-thru of sites. The contractorcontinues to implement improvements in training whilemaintaining area vigilance and housekeeping

    *The project performance statistics are based on constructionhours only

    **Bureau of Labor Statistics/National Industry Average

    Site Map

    G02Subs

    tation

    Retaining

    Wall(RW

    )HON-N1

    APit&A

    pproach

    Structure

    43rdStre

    etBridge

    (WBY)

    43rdStre

    etBridge

    (WBY)

    48thStre

    etBridge

    (WBY)

    RW39-N2

    RW43-N2

    RW43-N1

  • 8/2/2019 ESA Quarterly Report 2009 Q3

    26/53

    Quarterly Report 3rd Quarter 09

    Quarterly Report (Jul, Aug, Sep 09) - East Side Access (PM 3.2.62240) 26

    CH054A Harol d Struc t ures Part 2A J ul , Aug, Sep 09Contractor:Perini Corp.Construction Manager: Ray Busch FTA Grant: NY-03-0344/ARRA Stimulus Funds

    Description: Construct various civil infrastructure elements at Harold Interlocking and expand the existing LIRR and AmtrakRight of Way for the future TBM tunnels and Main-line track diversions including: 1) the construction of retaining walls, 2)Track D TBM Reception Pit, 3) AC Traction Power Duct Bank, 4) access road work, 5) demolition of existing CatenaryFoundations, 6) procurement of 2 Signal Bridges, and 7) other utility relocations and adjustments.

    Construction

    CHO054A Overview Map at Harold Interlocking.

    Schedule and CostProgress:

    1. Awarded to Perini Corp. August 19, 2009

    2. Contractor transmitted required submittals and work plansfor reviews prior to field activities

    3. Contractor will submit the Permit to Enter application toAmtrak in Oct 09

    Schedule: The contractor submitted the baseline schedulewhich is under review.

    Cost: The budget includes changes to the 12KV ductbankwork which has not yet been awarded.

    Critical Issues: Resolve Amtrak ET 12KV ductbank designissues to commence work on this activity.

    Milestones CH054A

    Milestones DescriptionCurrent

    Approved PlanActual/Forecast

    Advertise 12/08 12/08(A)

    NTP 08/09 08/09 (A)Substantial Completion 12/10 12/10

    Closeout 02/11 02/11

    Schedule Progress 3rd Qtr Cumulative

    Cost Expenditure Plan Actual Plan Actual

    Percent Complete TBD TBD TBD TBD

    Contract Costs ($000) as of 09/30/09

    CH054A F/A Support Total

    Budget at Award 39,225 3,199 42,424

    Current Budget 39,225 3,199 42,424

    Original Award 21,778 0 21,778

    Approved Changes

    Current Contract Value 21,778 0 21,778

    Invoiced Amount

    Estimate at Completion 39,225 3,199 42,424

    Coordination RequiredReal Estate: All work on railroad property or incity streets.

    Railroad Agencies: Amtrak and LIRR.

    Permits: NYCDOT permits needed. Water discharge permit (DEP) needed.

    MOU: Amtrak Project Initiative needed. Permit to Enter application to besubmitted.

  • 8/2/2019 ESA Quarterly Report 2009 Q3

    27/53

    Quarterly Report 3rd Quarter 09

    Quarterly Report (Jul, Aug, Sep 09) - East Side Access (PM 3.2.62240) 27

    FHA01Harold Stage 1 Amt rak Direct Force Acc ount J ul , Aug, Sep 09

    Contractor: Amtrak

    Construction Manager: Peter Malvese FTA Grant: N/ADescription: Install one track crossover (723); Relocate catenary and signal power at several locations, perform modificationsand removal of poles; Third-rail installation; Signal infrastructure installation, cable pulls, tie-ins, testing and cut-over of the723 crossover incorporating changes to F Interlocking and software and hardware modification for the Penn Station CentralControl (PSCC) ; Clear debris, materials and other incidentals from the Amtrak Maintenance-of-Way Yard; electrical tractionrelocations in support of the CH053 civil work.

    Construction

    Connecting Spur Track at North of Harold Interlocking.

    Schedule and Cost

    Progress:

    1. Completed removal of Long Island connector track

    2. Provided protection for catenary and signal gang

    Project Initiative (P.I.) status:

    P.I. for C&S, O1-O2 Switch and #51 switch CompletedP.I. for 68 Spur track - CompletedP.I. for Stage 1 ET Catenary In Progress

    Schedule: The schedule variance is the result of the delayedstart ofHarold Structures Part 1 (CH053) and Harold Stage 1catenary work. The catenary work drives the substantialcompletion date.

    Cost: The increase in budget and forecast is due to the scopetransfer of the signal trough installation from Harold Stage 2to Harold Stage 1 plus the addition of the 68 spur track and 51

    switch installations.

    Critical Issues: Completion of final design for electrictraction and subsequent Amtrak approval.

    Milestones FHA01

    Milestones DescriptionCurrent

    Approved PlanActual/Forecast

    100% Design 11/07 11/07 (A)

    Commence Stage 1 06/07 06//07 (A)

    Cutover Switch O1/O2 08/08 10/08 (A)

    Compl. 68 Spur Track 11/09 11/09

    Compl. Signal Power Cable 12/09 01/10

    Substantial Completion 09/10 07/11

    Schedule Progress 3rd Qtr Cumulative

    Cost Expenditure Plan Actual Plan Actual

    Percent Complete 6.3 2.8 81.3 47.9

    Contract Costs ($000) as of 09/30/09

    Stage 1F/A

    Support Total

    Budget at Award 12,100 N/A 12,100

    Current Budget 16,825 N/A 16,825

    Original Award 12,448 N/A 12,448

    Approved Changes 1,500 N/A 1,500

    Current Contract Value 13,948 N/A 13,948

    Invoiced Amount 10,209 N/A 10,209

    Estimate at Completion 16,825 N/A 16,825

  • 8/2/2019 ESA Quarterly Report 2009 Q3

    28/53

    Quarterly Report 3rd Quarter 09

    Quarterly Report (Jul, Aug, Sep 09) - East Side Access (PM 3.2.62240) 28

    Progress Curve (FHA01)

    0%

    10%

    20%

    30%

    40%

    50%

    60%

    70%

    80%

    90%

    100%

    Ap r-08 Ju n-08 Au g-08 Oct -08 Dec-08 Feb -09 Apr -09 Ju n-09 Au g-09 Oct -09 Dec-09 Feb -10 Ap r-10 Ju n-10 Au g-10 Oct-10

    %Complete

    Plan

    Actual

    Coordination Required

    Real Estate: None required.

    Railroad Agencies: LIRR and Amtrak.

    Permits: None required.

    MOU: Amtrak Force Account Agreement has been signed.

    Site Map

    Subset J

    Amtrak Signal Tower

  • 8/2/2019 ESA Quarterly Report 2009 Q3

    29/53

    Quarterly Report 3rd Quarter 09

    Quarterly Report (Jul, Aug, Sep 09) - East Side Access (PM 3.2.62240) 29

    FHA02Harold Ear ly Stage 2 Am trak Direct F / A J ul , Aug, Sep 09

    Contractor: Amtrak

    Construction Manager: Peter Malvese FTA Grant: N/A

    Description: Convert air switches 735, 737, 741, and 743 from air to electric; Install new electric switch machines; Installtemporary signal case, cable pulls, tie-ins, testing and cut-over switches; Install signal troughs, pull boxes, 9-ways/conduits,and case foundations for F1 and F2 Central Instrument Houses;

    Construction

    Retaining Wall for Future Signal Case Queens Blvd. Pull Box Installation at Thomson Ave.

    Schedule and CostProgress:

    1. Continued installing pull boxes, troughs, conduits and 9-way ducts for F1 / F2 Central Instrument House (CIH)

    2. Completed installation of case foundation for signal caseWest of Queens Blvd

    3. Completed surveying trough lines and case foundationsfor new F1 Central Instrument House

    4. Continued to develop Stage 2 estimate and schedulebased on the 90% design

    Project Initiative (P.I.) status:

    P.I for Early Stage 2 Signal Work CompletedP.I for the remaining Stage 2 Work In progress

    Schedule: Progress ahead of schedule, work started early.

    Cost: The current budget will be finalized once the PI forremaining Stage 2 is approved.

    Critical Issues: None

    Milestones Early FHA02

    Milestones DescriptionCurrent

    Approved PlanActual/Forecast

    Commence Early Stage 2 12/08 12/08 (A)

    Cutover Switch Machine-741 06/09 06/09 (A)

    Cutover Switch Machine-743 06/09 06/09 (A)

    Cutover Switch Machine-735 07/09 05/09 (A)

    Cutover Switch Machine-737 07/09 06/09 (A)

    Complete Early Stage 2 08/10 04/10

    Schedule Progress 3rd Qtr Cumulative

    Cost Expenditure Plan Actual Plan Actual

    Percent Complete 10.1 21.0 35.1 69.3

    Contract Costs ($000) as of 09/30/09

    EarlyStage 2

    F/ASupport Total

    Budget at Award** 4,161 N/A 4,161

    Current Budget** 4,161 N/A 4,161

    Original Award 4,161 N/A 4,161

    Approved Changes - N/A -

    Current Contract Value 4,161 N/A 4,161

    Invoiced Amount 2,056 N/A 2,056

    Estimate at Completion 4,161 N/A 4,161

    **Note: Stage 2 partial budget (early work only)

  • 8/2/2019 ESA Quarterly Report 2009 Q3

    30/53

    Quarterly Report 3rd Quarter 09

    Quarterly Report (Jul, Aug, Sep 09) - East Side Access (PM 3.2.62240) 30

    Progress Curve (FHA02)

    Coordination Required

    Real Estate: None required.

    Railroad Agencies: LIRR and Amtrak.

    Permits: None required.

    MOU: Amtrak Force Account Agreement has been signed.

    Site Map

    0%

    10%

    20%

    30%

    40%

    50%

    60%

    70%

    80%

    90%

    100%

    Oct-08 Dec-08 Feb-09 Apr-09 Jun-09 Aug-09 Oct-09 Dec-09 Feb-10 Apr-10 Jun-10 Aug-10 Oct-10

    %Complete

    Plan

    Actual

  • 8/2/2019 ESA Quarterly Report 2009 Q3

    31/53

    Quarterly Report 3rd Quarter 09

    Quarterly Report (Jul, Aug, Sep 09) - East Side Access (PM 3.2.62240) 31

    FHL01Harold Stage 1 LIRR Direct Force Ac count J ul , Aug, Sep 09Contractor: LIRR

    Construction Manager: Peter Malvese FTA Grant: NY-03-0344Description: Installeight track switches into the existing signal system; remove two switches; Install signal infrastructurein preparation of Stage 2 (Harold and Point CILs); Reroute signal power cables: Install third rail for new switches & track.Pull traction power cables from G02 Substation final manholes to Harold Main Line tracks; Energize and commission therelocated G02 Substation installed by CH053. Install and relocate signal and communications cables. Cut and throwMain Line 4 and relocated Main Line 2 upon CH053 expanding the South ROW East of 43rd Street.

    Construction

    Installation of Snowmelter at 863 Switch. Repairing Communication Duct at 39th St. Bridge.

    Schedule and CostProgress:

    1. Completed 3rd rail ductbank work for 863 switches

    2. Completed switch point and insulated joints for 863

    Switch3. Completed point installation and insulated joints for

    821 switch

    4. Continued testing of hut and Harold control panels andcircuit revision

    5. Continued installation of conduit, trough and pull box

    Schedule: The schedule variance is the result of the delaytoHarold Structures Part 1 (CH053) work. LIRR hasincreased their signal force to two gangs to expedite thework for the planned switch installations and cutovers.

    Cost: Approved changes reflect the scope transfer of theM2 switch installation from Stage 1 to Stage 3.

    Critical Issues: Schedule being impacted by delays toHarold Structures Part 1 (CH053).

    Milestones FHL01

    Milestones DescriptionCurrent

    ApprovedPlan

    Actual/Forecast

    100% Design 07/07 07/07 (A)Commence Stage 1 06/07 06/07 (A)

    Install 823 Switch 09/09 03/10

    Compl. Signal power Cable 01/10 01/10

    Cutover 821 & 823 Switch 06/10 06/10

    Substantial Completion 10/10 05/11

    Schedule Progress 3rd Qtr Cumulative

    Cost Expenditure Plan Actual Plan Actual

    Percent Complete 9.2 7.4 64.4 47.4

    Contract Costs ($000) as of 09/30/09

    Stage 1F/A

    Support Total

    Budget at Award 28,781 N/A 28,781

    Current Budget 20,782 N/A 20,782

    Original Award 28,781 N/A 28,781Approved Changes (7,999) N/A (7,999)Current Contract Value 20,782 N/A 20,782Invoiced Amount 7,536 N/A 7,536

    Estimate at Completion 20,782 N/A 20,782

  • 8/2/2019 ESA Quarterly Report 2009 Q3

    32/53

    Quarterly Report 3rd Quarter 09

    Quarterly Report (Jul, Aug, Sep 09) - East Side Access (PM 3.2.62240) 32

    Progress Curve (FHL01)

    0%

    10%

    20%

    30%

    40%

    50%

    60%

    70%

    80%

    90%

    100%

    A pr -08 Jun -08 A ug-08 Oct-08 Dec-08 Feb -09 Ap r-09 Ju n-09 Au g-09 Oct-09 Dec-09 Feb -10 A pr -10 Ju n-10 A ug -10 Oct-10

    %Complete

    Plan

    Actual

    Coordination Issues

    Real Estate: None required.

    Railroad Agencies: LIRR and Amtrak.

    MOU: Amtrak Force Account Agreement signed. LIRR ForceAccount Agreement signed.

    Permits: None required.

    Site Map

  • 8/2/2019 ESA Quarterly Report 2009 Q3

    33/53

    Quarterly Report 3rd Quarter 09

    Quarterly Report (Jul, Aug, Sep 09) - East Side Access (PM 3.2.62240) 33

    FHL02Harol d Early Stage 2 LIRR Direc t F/A J ul , Aug, Sep 09Contractor: LIRR

    Construction Manager: Peter Malvese FTA Grant: NY-03-0344

    Description: Advanced signal work for Stage 2 including cable trough, conduit and pull box installations, located in PointInterlocking and the West End of Harold Interlocking.

    Construction

    Trough Installation at Hunters Point.

    Schedule and CostProgress:

    1. Started installation of trough and pull boxes at Hsignal case location and Hunters Point

    2. Continued developing the Stage 2 estimate andschedule based on 90% design

    Schedule: Progress on schedule.

    Cost: The current budget will be revised once the MOU forremaining Stage 2 is approved.

    Critical Issues: None

    Milestones FHL02

    Milestones DescriptionCurrent

    ApprovedPlan

    Actual/Forecast

    Commence Stage 2 08/09 08/09 (A)Compl. Trough - Point CIL 10/09 10/09

    Compl. Trough - H4 CIL 03/10 03/10

    Complete. Early Stage 2 04/10 04/10

    Schedule Progress 3rd Qtr Cumulative

    Cost Expenditure Plan Actual Plan Actual

    Percent Complete 10.6 13.5 10.6 13.5

    Contract Costs ($000) as of 09/30/09EarlyStage 2

    F/ASupport Total

    Budget at Award** 2,417 N/A 2,417Current Budget** 2,417 N/A 2,417

    Original Award 2,417 N/A 2,417

    Approved ChangesCurrent Contract Value 2,417 N/A 2,417Invoiced Amount 132 132

    Estimate at Completion 2,417 N/A 2,417

    **Note: Stage 2 partial budget (early work only)

  • 8/2/2019 ESA Quarterly Report 2009 Q3

    34/53

    Quarterly Report 3rd Quarter 09

    Quarterly Report (Jul, Aug, Sep 09) - East Side Access (PM 3.2.62240) 34

    Progress Curve (FHL02)

    0%

    10%

    20%

    30%

    40%

    50%

    60%

    70%

    80%

    90%

    100%

    Jul-09 Aug -09 Sep- 09 O ct -09 Nov-09 Dec-09 Jan- 10 Feb- 10 Mar- 10 Apr-10 May-10 Jun-10 Jul- 10 Aug- 10

    %

    Complete

    Plan

    Actual

    Coordination Issues

    Real Estate: None required.

    Railroad Agencies: LIRR and Amtrak.

    MOU: Amtrak Force Account Agreement signed. LIRR ForceAccount Agreement signed.

    Permits: None required.

    Site Map

    Early Stage 2 Trough Line

  • 8/2/2019 ESA Quarterly Report 2009 Q3

    35/53

    Quarterly Report 3rd Quarter 09

    Quarterly Report (Jul, Aug, Sep 09) - East Side Access (PM 3.2.62240) 35

    FHA62 F Inter loc k ing CIH J ul , Aug, Sep 09Contractor:Amtrak

    Construction Manager: Chuck Miller FTA Grant: N/ADescription: Amtrak manufacture and delivery of Central Instrumentation Houses (CIHs) and cases for the F2 and F1Interlockings.

    Co

    nstruction

    Main Terminal and Supplemental Boards. Wire Distribution Between Relay Racks.

    Schedule and Cost

    Progress:

    1. Continued wiring on the nine huts and six cases

    2. Changes to control line due to agreement betweenAmtrak and LIRR resolving operating issues in

    Harold F and Point Interlockings

    3. Modifications have begun on the cases and huts.Hut and case deliveries will continue through the4th quarter, with completion targeted for the 1stquarter of 2010.

    4. Due to control line changes and reassessment ofthe level of effort required by Amtrak to completeassociated revisions, delivery of the CentralInstrumentation Houses (CIH) is anticipated inJuly and October of 2010 for F2 and F1,respectively.

    Schedule: Substantial completion and close-out

    schedules have been revised to reflect delivery schedulechanges. No impact on critical path is anticipated.

    Cost: Project is within budget.

    Critical Issues: None.

    Note: All work will be performed by Amtrak.

    Milestones FHA62

    Milestones DescriptionCurrent

    Approved PlanActual/Forecast

    100% Design 08/08 08/08 (A)

    NTP 09/08 09/08 (A)Delivery of F2 CIL 12/09 07/10

    Delivery of F1 CIL 03/10 10/10

    Substantial Completion 08/10 11/10

    Close-Out 10/10 12/10

    Schedule Progress 3rd Qtr Cumulative

    Cost Expenditure Plan* Actual Plan* Actual

    Percent Complete 14.3/32.5 19.0 43.5/78.2 49.0

    * Late/ Early Plan

    Contract Costs ($000) as of 09/30/09FHA62 F/A Support Total

    Budget at Award 8,894 8,894

    Current Budget 8,178 8,178

    Original Award 6,954 6,954

    Approved Changes

    Current Contract Value 6,954 6,954

    Invoiced Amount 2,477 2,477

    Estimate at Completion 8,178 8,178

    * F/A support costs are not applicable as there are no 3rdparty contractorsworking as part of FHA/L01.

  • 8/2/2019 ESA Quarterly Report 2009 Q3

    36/53

    Quarterly Report 3rd Quarter 09

    Quarterly Report (Jul, Aug, Sep 09) - East Side Access (PM 3.2.62240) 36

    Progress Curve(FHA62)

    0%

    10%

    20%

    30%

    40%

    50%

    60%

    70%

    80%

    90%

    100%

    Oct-08 Nov-08 Dec-08 Jan-09 Feb-09 Mar-09 Apr-09 May-09 Jun-09 Jul-09 Aug-09 Sep-09 Oct-09 Nov-09 Dec-09 Jan-10 Feb-10 Mar-10 Apr-10 May-10 Jun-10 Jul-10

    %Complete

    Early

    Actual

    Late

    Coordination Issues

    Real Estate: N/A

    Railroad Agencies: Amtrak

    MOU: Amtrak Force Account Agreement signed. Amtrak ProjectInitiative required signed.

    Permits: N/A

    Site Map

  • 8/2/2019 ESA Quarterly Report 2009 Q3

    37/53

    Quarterly Report 3rd Quarter 09

    Quarterly Report (Jul, Aug, Sep 09) - East Side Access (PM 3.2.62240) 37

    VHA/L02 Procur e Harol d Mat erial s Stage 2 J ul , Aug, Sep 09Contractor: Various

    Construction Manager: Mark Denise FTA Grant: NY-03-0344/Stimulus Funds (Only VHL02)Description: Procure LIRR and Amtrak Force Account material in support of Stage 2 construction. LIRR will manage and operatethe project warehouse with ESA oversight. Example of materials include: Track - switches, rail, concrete ties and ballast; Third-Rail& Power rail, cables, boards, brackets, wire, power connectors, bus bar; Signal Equipment switch machines, cables, signals,relays, heaters, troughs, impedance bonds; and Structures signal bridges, retaining walls etc.; Communications equipment, wire,cables, and poles.

    Procurement

    Force Account Materials at Warehouse Storage Area.

    Schedule and Cost

    Status: Awarded purchase orders for materials andproceeding with bids for material

    Cost: Table shows awards to date. Variouspurchase orders for are expected in the comingmonths. Half ofProcure Material Stage 2 LIRR(VHL02) procurements are ready to be initiated inNovember 2009 in concurrence with the AmericanRecovery and Reinvestment Act.

    Critical Issues: Alternate materials are beingsubmitted by the vendors with bids which hamperan effective bid award process. Working withAmtrak to ensure timely reviews going forward.

    Amtrak VHA02 Budget Summary (09/30/09)

    Material Budget

    Harold Stage 2

    Awarded POValue to Date

    Percent

    ProcurementCompleted Estimate atCompletion

    Signals 6,074,955 846,422 14% 6,074,955

    Track 3,434,215 0 TBD TBD

    Third Rail 491,632 7170 2% 622,689

    DC Traction 431,615 0 TBD TBD

    Communication 126,716 0 TBD TBD

    Catenary 553,007 0 TBD TBD

    Elec. Traction 2,106,948 283,200 13% 2,106,948

    Totals 13,219,087 1,136,792 9% TBD

    LIRR VHL02 Bid Value Summary (09/30/09)

    Material Budget

    Harold Stage 2Bid Values to

    Date

    PercentProcurementCompleted

    Estimate atCompletion

    Signals 10,444,523 1,815,790 17% 10,444,523

    Track 13,264,679 0 TBD TBD

    Third Rail / ET 1,944,087 0 TBD TBD

    DC Traction 0 0 TBD TBD

    Communication 510,111 0 TBD TBD

    Totals 26,163,400 1,815,790 7% TBD

  • 8/2/2019 ESA Quarterly Report 2009 Q3

    38/53

    Quarterly Report 3rd Quarter 09

    Quarterly Report (Jul, Aug, Sep 09) - East Side Access (PM 3.2.62240) 38

    VH051 (Part 1 ) Harol d and Point CILs J ul , Aug, Sep 09

    Contractor: Ansaldo STS USA, Inc

    Construction Manager: Chuck Miller FTA Grant: NY-03-0344

    Description: This is the procurement of six Harold Interlocking Central Instrument Locations (CILs) and one PointInterlocking Central Instrument Location and the purchase of a fully operational Vital Microprocessor-BasedInterlocking Control System for the referenced interlockings.

    Con

    struction

    Schedule and CostProgress:

    1. Conduct weekly technical meetings with contractor toassist with staging, interface and other technical issues

    2. Finalize review of submittal #1 (of six submittals) andelements of subsequent submittals as completed by thecontractor

    3. Reviewed Point Central Instrument Location andforward comments to the vendor

    4. Reviewing H3 Central Instrument Location foundation toconfirm for build by construction contractor

    5. Reviewing detailed schedule update. Follow-ondiscussions with the vendor will take place in October2009

    Schedule: The detailed schedule update has been submittedand is under review. Follow-on discussions with the vendorwill take place in October to finalize.

    Cost: See contract costs.

    Critical Issues: None.

    Milestones VH051 (Part 1)

    Milestones DescriptionCurrent

    Approved PlanActual/Forecast

    Advertise 04/08 03/08 (A)

    NTP 05/09 05/09 (A)Compl. Point Huts & Cases 07/10 07/10Compl. H4-H6 Huts & Cases 12/10 12/10Compl. H1-H3 Huts & Cases 01/11 01/11

    Compl. H4 CIL 04/11 04/11Compl. H5 CIL 05/11 05/11Compl. H6 CIL 07/11 07/11Compl. H1, H2, H3 CILs 08/11 08/11Substantial Completion 06/12 06/12

    Final Completion 07/12 07/12

    Schedule Progress 3rd Qtr Cumulative

    Cost Expenditure Plan* Actual Plan* Actual

    Percent Complete 1.1/3.0 2.5 2.1/4.0 3.5* Late/ Early Plan

    Contract Costs ($000) as of 09/30/09

    VH051-1 F/A Support TotalBudget at Award 30,891 N/A 30,891

    Current Budget 30,753 N/A 30,753

    Original Award 25,840 N/A 25,840

    Approved Changes N/A

    Current Contract Value 25,840 N/A 25,840

    Invoiced Amount N/A

    Estimate at Completion 30,753 N/A 30,753

  • 8/2/2019 ESA Quarterly Report 2009 Q3

    39/53

    Quarterly Report 3rd Quarter 09

    Quarterly Report (Jul, Aug, Sep 09) - East Side Access (PM 3.2.62240) 39

    Coordination Required

    Real Estate: N/A

    Railroad Agencies: LIRR/ Amtrak

    Permits: N/A

    MOU: LIRR Force Account MOU signed.

    Progress Curve (VH051 Part 1)

    0%

    10%

    20%

    30%

    40%

    50%

    60%

    70%

    80%

    90%

    100%

    Apr-09 Jun-09 Aug-09 Oct-09 Dec-09 Feb-10 Apr-10 Jun-10 Aug-10 Oct-10 Dec-10 Feb-11 Apr-11 Jun-11 Aug-11 Oct-11 Dec-11 Feb-12 Apr-12 Jun-12 Aug-12 Oct-12

    %C

    omplete

    Month/Year

    Early

    Late

    Actual

    Coordination Issues

    Real Estate: N/A

    Railroad Agencies: LIRR/ Amtrak

    Permits: N/A

    MOU: LIRR Force Account MOU signed.

    Site Map

  • 8/2/2019 ESA Quarterly Report 2009 Q3

    40/53

    Quarterly Report 3rd Quarter 09

    Quarterly Report (Jul, Aug, Sep 09) - East Side Access (PM 3.2.62240) 40

    VH051 (Part 2) Harold Tow er Superv isory Contro l

    SystemJ ul , Aug, Sep 09

    Contractor: ARINC, Inc.Construction Manager: Chuck Miller FTA Grant: NY-03-0344

    Description: This procurement contract requires purchase of a fully operational Supervisory Control System for controlof signal at Harold and Point Interlocks.

    Construction

    Supervisory Control System (Sample). Harold Tower Supervisory Control System - Existing Tower.

    Schedule and CostProgress:

    1. Reviewing final elements of submittal #3 and elementsof submittal #4 for final design

    2. Vendor procurement of Harold Tower hardware isunderway

    3. Final General Engineering Consultant (GEC) checksof the alternate control system specifications anddrawings modification to include Amtrakrequirements was completed. Information wassubmitted to Amtrak and LIRR for review.

    4. Vendor is working with Central Instrument Location(CIL) contractor on the interface design

    Schedule: Updates to the detailed schedule from ARINChave been received and are under review. However, finalassessment will be made upon the addition of Amtraksalternate control system.

    Cost: See contract costs.

    Critical Issues: None.

    Milestones VH051 (Part 2)

    Milestones DescriptionCurrent

    Approved PlanActual/Forecast

    Advertise 04/08 03/08 (A)NTP 02/09 02/09 (A)

    Delivery of Control Systems 03/10 03/10

    Substantial Completion 08/10 08/10

    Final Completion 05/12 05/12

    Schedule Progress 3rd Qtr Cumulative

    Cost Expenditure Plan Actual Plan Actual

    Percent Complete 12.0/12.0 12.0 24/24.0 24.0

    * Late/ Early Plan

    Contract Costs ($000) as of 09/30/09

    VH051-2F/A

    Support Total

    Budget at Award 7,061 N/A 7,061

    Current Budget 7,061 N/A 7,061Original Award 5,354 N/A 5,354Approved Changes N/ACurrent Contract Value 5,354 N/A 5,354Invoiced Amount 1,266 N/A 1,266

    Estimate at Completion 7,061 N/A 7,061

  • 8/2/2019 ESA Quarterly Report 2009 Q3

    41/53

    Quarterly Report 3rd Quarter 09

    Quarterly Report (Jul, Aug, Sep 09) - East Side Access (PM 3.2.62240) 41

    Progress Curve (VH051 Part 2)

    0%

    10%

    20%

    30%

    40%

    50%

    60%

    70%

    80%

    90%

    100%

    Apr-09 Jun-09 Aug-09 Oct-09 Dec-09 Feb-10 Apr-10 Jun-10 Aug-10 Oct-10 Dec-10 Feb-11 Apr-11 Jun-11 Aug-11 Oct-11 Dec-11 Feb-12 Apr-12 Jun-12 Aug-12 Oct-1

    %Complete

    Early

    Late

    Actual

    Coordination Issues

    Real Estate: N/A

    Railroad Agencies: LIRR.

    Permits: N/A

    MOU: LIRR Force Account MOU signed.

    Site Map

  • 8/2/2019 ESA Quarterly Report 2009 Q3

    42/53

  • 8/2/2019 ESA Quarterly Report 2009 Q3

    43/53

    Quarterly Review Report 3rd Quarter 09

    FTA Quarterly Report (Jul, Aug, Sep 09) - East Side Access (PM 3.2.62240)

    Summary Program Schedule

  • 8/2/2019 ESA Quarterly Report 2009 Q3

    44/53

  • 8/2/2019 ESA Quarterly Report 2009 Q3

    45/53

  • 8/2/2019 ESA Quarterly Report 2009 Q3

    46/53

    Quarterly Review Report 3rd Quarter 09

    FTA Quarterly Report (Jul, Aug, Sep 09) - East Side Access (PM 3.2.62240) 46

    Funding and Budget

    Project Budget Summary (As of Sep 30, 2009) ($ in thousands)

    ComponentFFGABudget

    CurrentBudget

    Awarded

    Value

    Paid

    To Date EAC

    EIS & Engineering $486,270 $564,665 $544,279 $440,287 $564,665

    Construction 4,441,776 5,590,491 2,437,926 901,506 5,590,491

    Contracts Awarded 1,838,859 2,925,040 N/A N/A

    Contracts To Be Awarded 2,602,917 2,665,451 N/A N/A

    OCIP* 250,000 190,853 91,636 88,201 190,853

    Management/General Conditions(FFGA only) 475,652 608,623 296,272 256,957 608,623

    Real Estate 165,000 171,368 84,371 83,108 171,368

    Rolling Stock 531,202 202,000 0 0 202,000

    Total $6,349,900 $7,328,000 $3,464,484 $1,770,059 $7,328,000

    Capital Program Authorization** $4,106,674 $4,373,951

    2010-2014 Capital Program $2,243,226 $2,954,049

    * OCIP budget does not include $84 million paid with surety funds that are not includes in the project budget.

    **The NYS Capital Program Review Board approved a plan amendment increasing ESA 2005-2009 funding by $1.5 billion onAugust 13, 2009.

    Pending Federal Funding from the American Recovery and Reinvestment Act

    ACEP

    Contract

    No. Project Brief Description

    FederalAmount

    RequestedG509-01-45 VS099 ESA - Pre-Order Materials -

    SystemsAdvanced procurement of constructionmaterials to be installed by various systemscontractors. Material includes wire and cable,conduit, rail and crossties. Partial funding.

    $16.0

    G509-01-18 VHL02 ESA - Pre-Order Materials -Harold Interlocking

    Advanced procurement of constructionmaterials for Harold Interlocking, including wireand cable, conduit, rail and crossties. Partialfunding.

    $6.7

    G509-01-22 CQ031 ESA - Queens Bored Tunnels Excavate tunnels and ventilation shafts underSunnyside yard and the LIRR's MainlineTracks. Partial funding.

    $132.3

    G409-01-43 CM004 ESA - 44th Street VentStructure & 245 Park Avenue

    Entrance

    47 East 44th Street demolition and constructionof fan plant structure and 245 Park Avenue

    Entrance. Partial funding.

    $14.2

    G509-01-28 CM008A ESA - Madison YardDemolition and Site Clearance

    Demolition and site clearance in Madison Yard,including environmental abatement and utilityrelocation, in GCT. Partial funding.

    $17.2

    G409-01-26 CH054A ESA - Harold Structures Part 2 Construct various civil infrastructure elementsat Harold Interlocking and expand the existingLIRR Amtrak ROW for the future TBM tunnelsand Main-line track diversions. Partial funding.

    $9.2

    Total $195.4

  • 8/2/2019 ESA Quarterly Report 2009 Q3

    47/53

    Quarterly Review Report 3rd Quarter 09

    FTA Quarterly Report (Jul, Aug, Sep 09) - East Side Access (PM 3.2.62240) 47

    Project Funding Status (As of Sep 30, 2009)

    Total Budget (exclusive of financing costs) $7,328.0

    MTA Capital Programs Budget FundingFederal Local

    New Starts Other

    New Starts ARRA

    1995-1999 $ 157.7 $ 45.7 0 0 $ 112.0

    2000-2004 1,533.5 564.1 0 28.8 940.6

    2005-2009 2,682.8 1,826.9 195.4 21.7 638.8

    2010-2014 2,954.0 0 0 0 2,954.0

    Total $7,328.0 $2,436.7 195.4 50.5 $4,645.4

    *Totals may not add due to rounding.Value of Contract Awards $3,464.5

    Federal Share of Contract Awards 1,146.6 33.1%

    Local Share of Contract Awards 2,317.9 66.9%

    Value of Finance Charges Incurred (based on prorated share) $90.9 million

    Summary of Federal Grants Received (FFGA)

    Grant No.FTA

    Award Date FFYObligation

    Amount Disbursement

    NY-03-0344 22-Jun-99 1998 $19.9 $19.9

    1999 23.8 23.8

    NY-03-0344-01 25-Apr-00 2000 2.0 2.0

    NY-03-0344-02 14-May-01 2001 7.9 7.9NY-03-0344-03 13-Jun-02 2002 14.6 14.6

    NY-03-0344-04 05-Aug-03 2003 13.3 13.3

    NY-03-0344-05 21-Sep-04 2004 73.8 73.8

    NY-03-0344-06 10-May-05 2005 65.2 65.2

    NY-03-0344-07 27-Jan-06 2005 34.0 34.0

    NY-03-0344-08 21-Dec-06 2006 333.2 333.2

    NY-03-0344-09 01 Aug 07 2007 300.0 244.3

    NY-03-0344-10 11 Aug 08 2008 210.7 0

    Subtotal ESA New Starts Grants NY-03-0344 $1,098.5 $832.0

    NY-95-X002 ESA (CMAQ) 14-Sept-07 2007 6.6 6.6

    NY-90-X467 (MNR&LIRR) 29-Mar-02 2002 15.2 15.2

    NY-03-0395 (LIRR) 20-Feb-02 2002 7.5 7.5

    NY-03-0406 (MNR) 12-May-03 2003 5.0 5.0

    NY-90-X489 (MNR) 08-Aug-03 2003 1.1 1.1

    NY-03-0427 (LIRR) 01-Mar-05 2005 2.0 2.0

    NY-05-0108 (LIRR) 27-Jun-06 2006 2.7 2.7

    NY-05-0109 (LIRR) 24 Jul -07 2007 5.8 5.8

    NY-95-X009 ESA (CMAQ) 13-Jan-09 2008 2.3 2.3

    Subtotal Non-New Starts Grants $48.1 $48.1Total All Grants $1,146.6 $880.1

    ($ in Millions)($ in Millions)($ in Millions)($ in Millions)

  • 8/2/2019 ESA Quarterly Report 2009 Q3

    48/53

    Quarterly Review Report 3rd Quarter 09

    FTA Quarterly Report (Jul, Aug, Sep 09) - East Side Access (PM 3.2.62240) 48

    Force Account Summary

    Risk Management and Project Execution Strategy FFGA Budget

    Contingency Rundown Against FFGA Budget ($ in Millions)

    FFGA Baseline Contingency $855.0

    Previous Contingency Changes -241.8

    Contingency last quarter: $613.2

    September 2009 Baseline $551.4

    Third Quarter 09 Adjustments:

    None -

    Total $551.4

  • 8/2/2019 ESA Quarterly Report 2009 Q3

    49/53

    Quarterly Review Report 3rd Quarter 09

    Quarterly Report (Jul, Aug, Sep 09) - East Side Access (PM 3.2.62240) 49

    Force Account Construction Budget (As of Sep 30, 2009)

    Description Labor & Equip. Materials Total

    Amtrak $141.3 $43.7 $133.6

    LIRR 253.8 136.7 390.5

    MNR 95.0 109.7 204.7

    NYCT 7.4 - 7.4

    NYAR 1.0 - 1.0

    Force Account Estimate Total $498.5 $289.7 $788.2

    Force Account 2009 Commitment Summary (As of Sep 30, 2009)

    Description 09 Plan Actual Remaining

    Amtrak $16.2 $4.0 $12.2

    LIRR 68.8 32.3 36.5

    MNR 0 0.4 -0.4

    NYCT 0.3 0 0.3

    NYAR - - -

    Force Account Estimate Total $85.3 $36.7 $48.6

    Changes from Last Quarter

    No significant changes

  • 8/2/2019 ESA Quarterly Report 2009 Q3

    50/53

    Quarterly Review Report 3rd Quarter 09

    Quarterly Report (Jul, Aug, Sep 09) - East Side Access (PM 3.2.62240) 50

    Construction Safety, Security and Quality

    Fourth Quarter 09 Look Ahead

    Design Progress design packageManhattan Structures 2 and Facilities Fit-Out(CM012) to 60%

    Progress design package 38th Street Ventilation Facility (CM013B) to 90%

    Progress design package GCT Concourse and FacilitiesFit-Out (CM014) to Pre-90%

    Progress design package Plaza Substation Structure (CQ032) to 90%

    Progress design packageLoop Interlocking CIL (VQ065A) to 30%

    Progress design packageHarold Stage 2 Amtrak F/A (FHA02) to 100%

    Progress design packageHarold Stage 2 LIRR F/A (FHL02) to 100%

    Progress design packageHarold Tower Renovation (FHL02) to 90%

    Progress design package Track, Third Rail and Tunnel Bench Walk (CS078) to 90%

    Progress design package Fire Detection (CS079) to 60%

    Update design package elements to reflect Contract Packaging Plan 8

    Grand Central Terminal

    Review theManhattan Structures 2 & Facilities Fit-Out(CM012) Pre-90% Submittal

    Prepare the Request for Proposal (RFP) for theEscalators and Elevators (VM014)procurement

    Review the ADA Compliance Report and determine issue resolutions

    Review operating plan and the cost benefit analysis for the Unified Trash Managementand Recycling Facility

    Railroad Systems

    Continue to finalize the tunnel signal design data

    Continue development of Tunnel Misroute Protection Plan with LIRR

    Incorporate comments on the Comprehensive System Testing Plan Volume 1 and 2

    Operational Readiness/LIRR Start Up

    Complete draft of the Master Training Plan

    Develop draft of the Operational Readiness Verification Plan

    Continue identifying components and processes for developing the Asset Inventory, incoordination with the Long Island Rail Road

  • 8/2/2019 ESA Quarterly Report 2009 Q3

    51/53

    Quarterly Review Report 3rd Quarter 09

    Quarterly Report (Jul, Aug, Sep 09) - East Side Access (PM 3.2.62240) 51

    Construction

    Manhattan Tunnel Excavation (CM009) Continue mining at West Bound (WB) lowerlevel drive 3 with Robbins TBM, commence excavation at GCT 5 and continue backing

    up Seli TBM Manhattan Structures Part 1 (CM019) Continue roadheader excavation of top heading

    at WB cavern, excavation of EB Cavern, and drill and blast excavation at Shaft 5.Continue mechanical excavation of Shafts 3 and 4 and Wellway #1, 2, 3, 4.

    Madison Yard Site Clearance (CM008A) Continue demolition work for the 45th St.cross passage and the track slab behind the commissary. Continue excavation for the Eastperimeter wall

    44th St. Demo & Construct Fan Plant Structure & 245 Park Ave. Entrance (CM004) Review submittals and work plans for field activities and mobilize on site

    MNR Traction Power and MODs (FM216) Complete work associated withSwitchboard room D, conduit runs and continue work on motor operated devises (MODs)

    Grand Central Terminal Protective Works (CS790) Continue with inspection andconcrete repair. Commence installation of protective nets on GCT Express Level tosupport demolition and excavation operations in Madison Yard. Continue bracket/cableinstallation at platforms and tracks

    Emergency Work Civil/Structural (CQE28-01) Complete cleanup and asbestosabatement of Amtrak buildings 2

    Emergency Work Environmental (CQE28-02) Complete water quality and elevationreadings

    Queens Instrumentation (CS810) Continue drilling inclinometer in Sunnyside Yard andbegin installation of surface monitoring and structural monitoring points

    Harold Structures I (CH053) Continue installation of retaining walls, completeexcavation and concrete of catenary foundations and continue the fabrication of the GO2Substation

    Harold Structures Part 2A (CH054A) Review submittals and work plans for fieldactivities

    Harold Stage 1 (FHA/L01) Complete pretesting of switches, begin relocating catenarywire to new structures and continue circuit revision and testing for switch cutovers

    Harold Early Stage 2(FHA/L02) Continue installing trough and conduit for the earlystage 2 works and relocating communication cable at Harold South/North

    F Interlocking Central Instrumentation Houses CIHs (FHA62) Wiring of signal huts,cases and CIHs will continue through early first quarter 2010.

    Harold and Point Central Instrument Location CILs Part 1 (VH051) Continue review ofsubmittals for Point Interlocking

  • 8/2/2019 ESA Quarterly Report 2009 Q3

    52/53

    Quarterly Review Report 3rd Quarter 09

    Quarterly Report (Jul, Aug, Sep 09) - East Side Access (PM 3.2.62240) 52

    Harold Tower Supervisory Control System Part 2(VH051) Vendor will continuefinalizing Submittal #3 and submitting elements of Submittal #4 for review. Procurementof control system hardware is underway.

    Budget and Finance Finalize the Enterprise Level Project Execution Plan for both the East Side Access and the

    Second Avenue Subway projects

    Draft the ESA Recovery Plan

    Implement a process to update the Project Management Plan consistent with the ExecutiveLevel Project Execution Plan

    Update the 2005-2009 Capital Program for submission to the MTA

    Coordinate the collection of data to support the Federal Stimulus funding requirements