Upload
others
View
8
Download
2
Embed Size (px)
Citation preview
FINAL DESIGN REPORT
APPENDIX I - VALUE ENGINEERING
September 14, 2016
Reconstruction Project PIN 0016.27.101
NY 112 From I-495 to Granny Road
Town of Brookhaven Suffolk County
APPENDIX I:
VALUE ENGINEERING
I. Value Engineering Report I-2 II. Regional Disposition Forms I-80
I - 1
New York State Department of Transportation
NY 112 from LIE to Granny RoadPIN 0016.27
Value Engineering Report
January 13-15, 2016
I - 3
New York State Department of Transportation NY 112 from LIE to Granny Road
Value Engineering Report January 13-15, 2016
Contents Page 1 Executive Brief .................................................................................................................... 1
1.1 General .................................................................................................................. 1
1.2 Objectives .............................................................................................................. 1
1.3 Value Target Areas ................................................................................................ 2
1.4 Summary of Results ............................................................................................... 2
1.5 Acknowledgements ................................................................................................ 3
2 Value Engineering Alternatives & Design Suggestions ...................................................... 5
Appendix A: Function Analysis ..................................................................................................... 60
Appendix B: Pareto Cost Model .................................................................................................... 63
Appendix C: Creative Idea List with Evaluation Score and Action ............................................... 66
Appendix D: VE Presentation List of Attendees ........................................................................... 69
I - 4
New York State Department of Transportation NY 112 from LIE to Granny Road
Value Engineering Report January 13-15, 2016
Disclaimer This document and its contents have been prepared and are intended solely for the Client’s information and use in relation to the NY 112 from LIE to Granny Road project. It should be understood that the cost figures quoted in this report represent Order of Magnitude only and are used to establish the viability of proposals and may not represent their exact value. Furthermore, the actual total impact on project cost is dependent on a detailed implementation analysis beyond the scope of the VE effort. VE Alternatives and Design Suggestions are provided to the Owner/Designer for their further evaluation and implementation at their exclusive discretion.
Faithful+Gould assumes no responsibility to any other party in respect of or arising out of or in connection with this document and/or its contents.
I - 5
New York State Department of Transportation NY 112 from LIE to Granny Road
Value Engineering Report January 13-15, 2016
1 K:\2016\100047710_GPI\03Deliverables\NY112 VE Rpt Basis Of PDF-Rev.Docx
1 Executive Brief 1.1 General Faithful+Gould conducted a Value Engineering Study of the Draft Design Report dated October 2015 for the NY 112 from Long Island Expressway (LIE) to Granny Road project. The VE Study was under the auspices of the New York State Department of Transportation (NYSDOT) Region 10 Office. The VE Study was held January 13 - 15, 2016 in the Babylon, NY, offices of Greenman-Pedersen, Inc. in compliance with the VE standards and procedures supported by SAVE International®. The $54 M project extends 1.6 miles along NY Route 112 from the LIE South Service Road to Granny Road, located approximately 1.3 mile north of CR 16, Horse Block Road. It includes localized improvements at the Horse Block Road intersection and two recharge basins on the east side of NY 112. Current conditions, highlighted during the design presentation, include:
Roadway flooding
Traffic congestion
Discontinuous sidewalks
No refuge for left turns
Discontinuous curbs
A function analysis of the current project design is presented in Appendix A and cost distributions of the project are highlighted by Pareto Cost Models in Appendix B. The independent VE team consisted of:
Name Discipline Organization
Linda DeSimone, PE Geotechnical / Structural Engineer
Greenman-Pedersen, Inc.
Frank Pearson, PE Transportation Safety Greenman-Pedersen, Inc.
Kevin Padden, PE Constructability Engineer Greenman-Pedersen, Inc.
Jason Stern, PE Structural Engineer Greenman-Pedersen, Inc.
Kurt Weiskotten Environmental Scientist Greenman-Pedersen, Inc.
Tom Wiggins, CVS CVS / VE Team Leader Faithful+Gould
To provide an objective perspective for the VE effort, the Greenman-Pedersen VE team was drawn from staff who had not been involved in the project design.
The final presentation for the VE workshop was held at the New York State Office Building (250 Veterans Highway, Hauppauge, NY). Appendix D has the list of attendees for the presentation.
1.2 Objectives The objectives of the NY 112 from Long Island Expressway (LIE) to Granny Road project, as stated in the Draft Design Report dated October 2015, include:
Improve overall traffic conditions using cost-effective methods to reduce delay and to provide an acceptable level of service for a design period of 20 years.
Correct identified pavement deficiencies that will extend the useful life of the highway and maintain it in a structurally sound condition using cost-effective pavement treatments which provide low life cycle costs.
Correct safety deficiencies using cost-effective accident reduction measures such that accident reduction benefits equal or exceed project costs attributable to safety work.
I - 6
New York State Department of Transportation NY 112 from LIE to Granny Road
Value Engineering Report January 13-15, 2016
2 K:\2016\100047710_GPI\03Deliverables\NY112 VE Rpt Basis Of PDF-Rev.Docx
Provide continuous, standardized accommodations for pedestrians and bicyclists in this corridor, and upgrade facilities to match adjacent sections of the roadway to the north and the south.
Upgrade the corridor to improve transit operations and service.
The main objective of the VE Study was to provide design options to increase value through improved functionality and/or capital and/or life cycle cost avoidance while maintaining a quality project that meets stakeholder needs and overall objectives of the project. In addition, the VE Study was held to meet FHWA VE requirements for federally funded projects over $50 M, in compliance with the standards and procedures of SAVE International®. Finally, the VE Team sought alternatives to:
Improve safety and operations for motorists, pedestrians and bicyclists
Improve constructability of the project
Reduce ROW takings
Mitigate project risks.
1.3 Value Target Areas
The VE Team targeted project areas where value could be increased by either better performance and/or capital or life cycle cost avoidance while maintaining necessary functions, objectives and budget. The result was 32 creative ideas for the NY 112 from LIE to Granny Road project across the five value target areas shown in the table on the right. The abbreviations shown are used in the numbering of the creative ideas as presented in Appendix C. The numbering used for the ideas carries forward to the Alternative numbers.
1.4 Summary of Results The "Alternatives Summary" at the end of this Section, summarizes of the ideas put forward and evaluated and the Alternatives developed by the Value Team. After evaluation, the 32 ideas resulted in 4 Quantitative VE Alternatives (avoid cost), 1 Qualitative VE Alternatives (added value for added cost) and 10 Design Suggestions.
A “Summary of Alternatives and Design Suggestions” table, presented at the beginning of Section 2 of this report, lists the VE Alternatives and Design Suggestions along with their description, rationale and cost implications. The collective impact of the VE Team recommended VE Alternatives is:
A maximum additional capital cost of $158,000 for the value-added Qualitative Alternative
A maximum potential cost avoidance of $2,964,000 from the Qualitative Alternatives.
The costs do not include add-on costs, such as percentage items, contingency, mobilization and construction inspection. If all compatible value improvement or cost avoidance ideas are accepted. Acceptance of all recommended VE Alternatives would yield a net capital cost avoidance of $2,806,000. Of course, NYSDOT implementation decisions will determine the ultimate cost implications. None of the VE Alternatives are mutually exclusive by the Value Team, so all may be included in the summary of recommended VE Alternatives. This net capital cost avoidance of $2,806,000 represents an approximate 5.5% cost avoidance from the total construction cost of $54,205,848 in the Greenman-Pedersen, Inc. estimate, Alternative 2 with Option.
Value Target Area Abbreviation
Drain Roadway DR
Enable Multi-Modal EM
Miscellaneous M
Manage ROW MR
Reduce Congestion RC
I - 7
New York State Department of Transportation NY 112 from LIE to Granny Road
Value Engineering Report January 13-15, 2016
3 K:\2016\100047710_GPI\03Deliverables\NY112 VE Rpt Basis Of PDF-Rev.Docx
A couple of the Alternatives sought to reduce ROW takings by slightly reducing the overall ROW requirements:
Alternative MR-01 suggests reducing the median width from 14' to 12'. This is still within standards, but does not match the current work to the north of the project. This offers a savings of about $719,000.
Alternative MR-06 suggests reducing the sidewalk area width by 2' on each side of the roadway. The reduction would be to the snow storage area and area between sidewalk and Fee Acquisition line. The sidewalk and bike lane width would remain the same. This is still within standards, but does not match the current conditions to the north of NY 25. The potential savings estimate is about $1,096,000.
In Alternative EM-03, which suggests elevating the sidewalk and bike route under the I-495 bridge, the Value Team sought to improve pedestrian and bike safety and mitigate construction risks. There is a modest increase in cost of about $158,000 for the alternative.
All of the VE Alternatives and developed Design Suggestions, as prepared during the VE Workshop, are included in Section 2 following the summary table.
1.5 Acknowledgements Faithful+Gould wishes to thank NYSDOT Region 10 personnel and the Greenman-Pedersen design team for their cooperation and support in preparation for this VE Study, and especially for Greenman-Pedersen's presentation of the design to the VE Team at the start of the VE workshop. The thoughtful reception of the VE Team’s Alternatives during the Presentation Phase from NYSDOT and design team personnel was also much appreciated. In addition, we thank the personnel of Greenman-Pedersen for their expertise and active participation on the VE Team. Finally, we thank Greenman-Pedersen for hosting the VE Workshop in their Babylon offices.
I - 8
ALTERNATIVES SUMMARYNY 112 from LIE to Granny RoadLong Island, NY
Study Dates: January 13-15, 2016
Creative and Evaluation Phase Results
Ideas As: No. of Ideas
Alternative (Quantitative or Qualitative) 7 Manage ROW (MR)
Design Suggestion 8 Reduce Congestion (RC)
Estimate Correction 0 Enable Multi-Modal (EM)
Cost Reduction 0 Drain Roadway (DR)
Already Being Done 1 Miscellaneous (M)
Eliminated by Evaluation 16
Total Creative Ideas 32
Development Phase Results
Alternatives As: DevelopedIncluded In
TotalFirst Costs
(Capital Costs)Present Worth (of
Future Costs)Life Cycle
Costs
Design Suggestion 10
Quantitative 4 4 2,964,000$ -$ 2,964,000$
Qualitative 1 1 (158,000)$ -$ (158,000)$
Subtotal 15 5 2,806,000$ -$ 2,806,000$
Estimate Correction 0 0 -$ -$ -$
Cost Reduction 0 0 -$ -$ -$
Total 15 5 2,806,000$ -$ 2,806,000$
Legend - Alternative Types
Alternative TypesQnt(+) Quantitative
Qlt(-) Qualitative
DS Design Suggestion
EC Estimate Correction
CR Cost Reduction
An alternative to identify the cost impact of a significant issue discovered with the cost estimate during the workshop.
An alternative that results in reduced costs without improving value.
Description
Value Target Functions
An alternative that results in a positive capital and/or life cycle cost avoidance while maintaining required functionality and performance, i.e. improved value.
An alternative that results in additional capital and/or life cycle costs (negative cost avoidance) while improving required functionality and performance, i.e. improved value.
An alternative for which the team cannot define a reasonable cost impact during the workshop or that may simply be a suggestion to consider as design proceeds.
4Version B3.0.1, 1/4/2016 I - 9
New York State Department of Transportation NY 112 from LIE to Granny Road
Value Engineering Report January 13-15, 2016
5 K:\2016\100047710_GPI\03Deliverables\NY112 VE Rpt Basis Of PDF-Rev.Docx
2 Value Engineering Alternatives & Design Suggestions
A “Summary of Alternatives and Design Suggestions” spreadsheet on the following pages summarizes the results of the VE workshop, identifying the Alternative Number, Title, Rationale, Alternative Category, Mutual Exclusivity, Inclusion in the Section 1.4 cost implications (i), and estimated cost avoidance or addition of First Costs (Capital), Present Worth (of future costs) and Life Cycle Costs.
The 4 Quantitative VE Alternatives, the 1 Qualitative VE Alternatives and the 10 Design Suggestions prepared during the VE Workshop are presented in their entirety on the pages following the summary spreadsheet, in order of their appearance in the spreadsheet.
I - 10
SU
MM
AR
Y O
F A
LT
ER
NA
TIV
ES
AN
D D
ES
IGN
SU
GG
ES
TIO
NS
NY
112
fro
m L
IE t
o G
ran
ny
Ro
adL
on
g I
slan
d,
NY
Jan
uar
y 13
-15,
201
6
Alte
r. No
.De
scrip
tive A
ltern
ative
Titl
e (V
ette
d by
Fac
ilitat
or)
Ratio
nale
(Sum
mar
ized)
Alte
r. Ca
t.Mu
tual.
Ex
cl.In
cl. (i
)Fi
rst C
osts
(Cap
ital
Cost
s)Pr
esen
t Wor
th (o
f Fu
ture
Cos
ts)
Life
Cyc
le Co
sts
DR
-00
Dra
in R
oad
way
#TT
DR
-03
Con
stru
ct r
echa
rge
basi
n(s)
alo
ng M
iddl
e Is
land
Roa
dU
ndev
elop
ed la
nd p
arce
ls a
djac
ent
to N
Y
112
(and
clo
sest
to
the
proj
ect)
are
tho
ught
to
hav
e hi
gher
pro
pert
y va
lues
tha
n la
nd
alon
g su
rrou
ndin
g se
cond
ary
urba
n hi
ghw
ay c
orrid
ors.
The
nea
rby
Mid
dle
Isla
nd R
oad
corr
idor
may
incl
ude
unde
velo
ped
land
s th
at a
re s
uita
ble
for
esta
blis
hing
sto
rmw
ater
rec
harg
e ba
sins
at
a re
duce
d ta
king
fee
cos
t.
DS
-$
-
$
-$
DR
-04
Inco
rpor
ate
alte
rnat
ive
stor
mw
ater
tr
eatm
ents
to
redu
ce s
ize
of r
echa
rge
basi
n
Bio
swal
es,
filte
r st
rips,
sto
rmw
ater
pla
nter
s,
and
perm
eabl
e pa
vem
ent
and
pave
rs a
re
usua
lly a
par
t of
a la
rger
sto
rmw
ater
dr
aina
ge s
yste
m,
and
in t
he c
ase
of t
his
proj
ect
(a c
lose
d pi
pe s
yste
m e
ndin
g in
re
char
ge b
asin
s) a
dditi
onal
tre
atm
ents
al
ong
the
flow
pat
h of
run
off
can
impr
ove
over
all w
ater
qua
lity
and
redu
ce o
vera
ll w
ater
qua
ntity
tre
atm
ent
volu
me
requ
ired.
S
ince
the
pur
chas
e of
a la
rge
parc
el o
f un
deve
lope
d la
nd a
long
NY
112
is r
equi
red
to a
ccom
mod
ate
the
rech
arge
bas
ins,
a
cost
sav
ings
is p
ossi
ble
if a
smal
ler
parc
el
is r
equi
red
resu
lting
fro
m a
red
uced
st
orm
wat
er t
reat
men
t vo
lum
e.
DS
-$
-
$
-$
DR
-06
Use
late
rals
to
tie in
to t
runk
line
on
one
side
Red
uce
cost
of
drai
nage
to
the
proj
ect
by
reco
nsid
erin
g tr
unk
line
arra
ngem
ent.
Qnt
(+)
i49
1,00
0$
-
$
491,
000
$
EM
-00
En
able
Mu
lti-
Mo
dal
#TT
EM
-01
Com
bine
sid
ewal
k an
d bi
kew
ay s
outh
of
nort
h se
rvic
e ro
adT
he c
ombi
natio
n of
the
bik
e la
ne a
nd
side
wal
k so
uth
of t
he N
orth
Ser
vice
Roa
d to
the
Sou
ther
n P
roje
ct li
mit
wou
ld a
llow
ex
tend
ing
the
exis
ting
left
tur
n la
nes
on
Rou
te 1
12.
Thi
s w
ould
in t
urn
help
red
uce
cong
estio
n at
the
Nor
th a
nd S
outh
Ser
vice
R
oad
inte
rsec
tions
.
DS
-$
-
$
-$
6V
ersi
on B
3.0.
1, 1
/4/2
016
I - 11
SU
MM
AR
Y O
F A
LT
ER
NA
TIV
ES
AN
D D
ES
IGN
SU
GG
ES
TIO
NS
NY
112
fro
m L
IE t
o G
ran
ny
Ro
adL
on
g I
slan
d,
NY
Jan
uar
y 13
-15,
201
6
Alte
r. No
.De
scrip
tive A
ltern
ative
Titl
e (V
ette
d by
Fac
ilitat
or)
Ratio
nale
(Sum
mar
ized)
Alte
r. Ca
t.Mu
tual.
Ex
cl.In
cl. (i
)Fi
rst C
osts
(Cap
ital
Cost
s)Pr
esen
t Wor
th (o
f Fu
ture
Cos
ts)
Life
Cyc
le Co
sts
EM
-02
Use
gab
ion
or m
odul
ar r
etai
ning
wal
l in
lieu
of c
ast
in p
lace
con
cret
e w
all
Usi
ng g
abio
n or
mod
ular
typ
e w
alls
in li
eu
of c
ast-
in-p
lace
con
cret
e w
alls
for
the
se lo
w
heig
ht w
alls
will
res
ult
in e
asie
r an
d qu
icke
r co
nstr
uctio
n, le
ss in
tric
ate
exca
vatio
n su
ppor
t sy
stem
and
will
be
cost
eff
ectiv
e.
DS
-$
-
$
-$
EM
-03
Ele
vate
the
sid
ewal
k an
d bi
ke la
ne u
nder
th
e br
idge
Ele
vate
the
sid
ewal
k, o
r si
dew
alk
and
bike
ro
ute
on N
Y11
2, u
nder
the
I-4
95 M
ainl
ine
Brid
ge;
so a
s to
pro
vide
a s
afer
pe
dest
rian/
bike
pat
h an
d to
min
imiz
e di
srup
tion
to t
he p
aved
slo
pe in
fro
nt o
f th
e st
ub a
butm
ent.
Qlt(
-)i
(158
,000
)$
-$
(1
58,0
00)
$
M-0
0M
isce
llan
eou
s#T
T
M-0
2R
epla
ce F
itch
barr
els
with
impa
ct
atte
nuat
or a
t LI
E b
ridge
The
exi
stin
g F
itch
barr
els
appe
ar t
o be
in
poor
con
ditio
n an
d m
ay n
ot f
unct
ion
as
orig
inal
ly in
tend
ed.
In o
rder
to
impr
ove
mot
oris
t sa
fety
, w
e re
com
men
d th
at t
hey
be r
epla
ced
with
an
impr
oved
impa
ct
atte
nuat
or s
yste
m.
DS
-$
-
$
-$
MR
-00
Man
age
RO
W
#TT
MR
-01
Red
uce
wid
th o
f m
edia
n fr
om 1
4' t
o 12
'In
ord
er t
o re
duce
the
am
ount
of
RO
W
taki
ng,
it is
pro
pose
d to
red
uce
the
two
way
tu
rn la
ne f
rom
14'
to
12'.
In a
dditi
on,
ther
e w
ould
be
a co
st s
avin
gs f
or a
spha
lt co
ncre
te,
subb
ase,
exc
avat
ion
and
emba
nkm
ent.
Thi
s w
ill a
lso
redu
ce a
mou
nt
of w
ater
tha
t ha
s to
be
colle
cted
.
Qnt
(+)
i71
9,00
0$
-
$
719,
000
$
MR
-05
Red
uce
desi
gn s
peed
of
road
to
redu
ce
lane
wid
ths
The
obs
erve
d tr
avel
spe
eds
in t
he P
M P
eak
Hou
r ra
nge
from
10
mph
to
50 m
ph a
s sh
own
belo
w w
ith t
he m
ajor
ity o
f th
e sp
eeds
und
er 4
0 m
ph.
The
red
uctio
n of
the
de
sign
spe
ed w
ould
just
ify t
he r
educ
tion
of
the
prop
osed
tra
vel l
anes
and
min
imiz
e th
e R
OW
acq
uisi
tion
cost
s.
DS
-$
-
$
-$
7V
ersi
on B
3.0.
1, 1
/4/2
016
I - 12
SU
MM
AR
Y O
F A
LT
ER
NA
TIV
ES
AN
D D
ES
IGN
SU
GG
ES
TIO
NS
NY
112
fro
m L
IE t
o G
ran
ny
Ro
adL
on
g I
slan
d,
NY
Jan
uar
y 13
-15,
201
6
Alte
r. No
.De
scrip
tive A
ltern
ative
Titl
e (V
ette
d by
Fac
ilitat
or)
Ratio
nale
(Sum
mar
ized)
Alte
r. Ca
t.Mu
tual.
Ex
cl.In
cl. (i
)Fi
rst C
osts
(Cap
ital
Cost
s)Pr
esen
t Wor
th (o
f Fu
ture
Cos
ts)
Life
Cyc
le Co
sts
MR
-06
Red
uce
side
wal
k ar
ea w
idth
fro
m 1
3' t
o 11
'R
educ
ing
the
side
wal
k ar
ea w
idth
by
2 fe
et
on e
ach
side
of
Rou
te 1
12 w
ill s
ave
on
RO
W a
cqui
sitio
n co
sts,
incl
udin
g bo
th F
ee
acqu
isito
n an
d te
mpo
rary
eas
emen
ts.
Thi
s re
duct
ion
will
not
aff
ect
the
over
sid
ewal
k w
idth
, bu
t ra
ther
the
sno
w s
tora
ge a
rea
adja
cent
to
the
bike
lane
and
the
are
a be
twee
n th
e si
dew
alk
and
the
Fee
A
cqui
sitio
n lin
e.
Qnt
(+)
i1,
096,
000
$
-$
1,
096,
000
$
MR
-09
Elim
inat
e no
rthb
ound
rig
ht t
urn
lane
at
Cou
ntry
Fai
r E
nter
tain
men
t P
ark
The
rig
ht h
and
turn
lane
is n
ot h
eavi
ly u
sed
acco
rdin
g to
the
tra
ffic
stu
dy.
Elim
inat
e rig
ht h
and
turn
ing
lane
so
as t
o re
duce
the
R
OW
and
ass
ocia
ted
cost
.
DS
-$
-
$
-$
MR
-10
Sho
rten
nor
thbo
und
right
tur
n la
ne a
t C
omm
erci
al D
rive
Red
uce
cost
of
prop
erty
tak
ings
, an
d m
inor
sa
ving
s in
roa
dway
con
stru
ctio
n.D
S-
$
-$
-
$
MR
-11
Mov
e R
OW
tak
ing
to v
acan
t si
de
whe
neve
r po
ssib
leR
educ
e nu
mbe
r of
pro
pert
ies
affe
cted
by
prop
erty
tak
ings
and
pot
entia
lly r
educ
e th
e co
st o
f pr
oper
ty a
cqui
sitio
n.
DS
-$
-
$
-$
MR
-12
Elim
inat
e su
pere
leva
tion
of n
orth
boun
d N
Y
112
betw
een
LIE
NS
R a
nd H
orse
Blo
ck
Rd.
In a
n ef
fort
to
redu
ce R
OW
cos
ts f
or
tem
pora
ry e
asem
ents
and
impr
ove
cons
truc
tabi
lity,
con
side
r el
imin
atin
g th
e pr
opos
ed s
uper
elev
atio
n al
ong
nort
hbou
nd
NY
112
. D
ata
show
s th
is is
not
a f
acto
r co
ntrib
utin
g to
acc
iden
ts.
Qnt
(+)
i65
8,00
0$
-
$
658,
000
$
RC
-00
Red
uce
Co
ng
esti
on
#TT
RC
-07
Add
IT
SA
ddin
g IT
S a
long
the
Lon
g Is
land
E
xpre
ssw
ay,
Nor
thbo
und
Rou
te 1
12
(bet
wee
n th
e N
orth
Ser
vice
Roa
d an
d H
orse
Blo
ck R
oad)
and
Sou
thbo
und
Rou
te
112
(Nor
th o
f H
orse
Blo
ck R
oad)
wou
ld
prov
ide
driv
ers
with
tra
ffic
info
rmat
ion
and
trav
el t
imes
for
the
m t
o ex
plor
e a
ltern
ate
rout
es.
DS
-$
-
$
-$
8V
ersi
on B
3.0.
1, 1
/4/2
016
I - 13
January 13-15, 2016Page 1 of 4
Title Alter. No. DR-03
Cost Summary First Costs (Capital Costs)
Present Worth (of Future Costs)
Life Cycle Cost(Total LCC)
-$ -$ -$
-$ -$ -$
-$ -$ -$
Key ContactsProject Mgr: William Stroh
Team Leader: Tom Wiggins, CVS
Description of Original Concept (Brief)The project corridor needs a uniform closed drainage system with adequate stormwater capacity for the proposed roadway improvements and to alleviate a current site flooding condition. A positive drainage system is proposed that will tie in to the system under construction to the north under Contract D262794. This system will accommodate stormwater runoff from the high point north of Granny Road south to Horse Block Road. Stormwater from this closed system will outlet into a proposed recharge basin located on undeveloped land on the east side of NY 112 approximately 1500 feet north of the NY 112/Horse Block Road intersection.
Description of Alternative Concept (Brief)Instead of locating the recharge basin designed to collect stormwater from the northern portion of the project along the east side of NY 112, the recharge basin would be relocated to available lands along Middle Island Road, running parallel and a short distance to the east of NY 112.
Design SuggestionNY 112 from LIE to Granny Road, Long Island, NY
Construct recharge basin(s) along Middle Island Road
RationaleUndeveloped land parcels adjacent to NY 112 (and closest to the project) are thought to have higher property values than land along surrounding secondary urban highway corridors. The nearby Middle Island Road corridor may include undeveloped lands that are suitable for establishing stormwater recharge basins at a reduced taking fee cost.
Disadvantages of Alternative Concept (Brief)
Further away from project corridor
Requires longer distance of piping for stormwater to reach site (additional construction cost)
Uncertainty of availability of site
Apparent more densely wooded lots, requiring environmental review
Advantages of Alternative Concept (Brief)
Possible overall cost reduction, though uncertain at this time
Releases proposed location(s) along NY 112 for other uses by others
Removes potential "eyesore" of detention basin from NY 112 corridor
Original Concept
Alternative Concept
Difference
9 I - 14
January 13-15, 2016
Page 2 of 4
Alter. No. DR-03
NY 112 from LIE to Granny Road, Long Island, NY
Title
Design Suggestion
Since ROW costs are a large proportion of the total cost of this project (30%), purchasing lands along NY 112 itself may be contributing to the overall high cost. Any remaining undeveloped lands along the ultra-urban, high demand NY 112, are at a premium for purchase and use. This will drive up costs and will play out during ROW fee taking negotiations. In contrast, along nearby Middle Island Road, where business, traffic, and access are far less in demand, land would likely be available at a reduced rate, and through easier ROW negotiations.
Although this may be a viable options for reducing costs of overall ROW activities, there is uncertainly as to where the pipeline for stormwater conveyance would pass through. As proposed the recharge basins would be adjacent to mainline drainage pipes, and outlet connector pipes would be minimal. A likely route for getting stormwater to the Middle Island Road site(s) could be along or through the Medford Fire District property, which would allow for potential streamlined processing.
Construct recharge basin(s) along Middle Island Road
Discussion (Elaborate)
10 I - 15
January 13-15, 2016
Page 3 of 4
Alter. No. DR-03
NY 112 from LIE to Granny Road, Long Island, NY
Title
Design Suggestion
Construct recharge basin(s) along Middle Island Road
Exhibits - Original Concept
11 I - 16
January 13-15, 2016
Page 4 of 4
Alter. No. DR-03
Design SuggestionNY 112 from LIE to Granny Road, Long Island, NY
Title
Construct recharge basin(s) along Middle Island Road
Exhibits - Alternative Concept
12 I - 17
January 13-15, 2016Page 1 of 10
Title Alter. No. DR-04
Cost Summary First Costs (Capital Costs)
Present Worth (of Future Costs)
Life Cycle Cost(Total LCC)
-$ -$ -$
-$ -$ -$
-$ -$ -$
Key ContactsProject Mgr: William Stroh
Team Leader: Tom Wiggins, CVS
Description of Original Concept (Brief)Currently, there is no effective control of stormwater run-off from Granny Road to the LIE South Service Road. The proposed project will address stormwater runoff by development of a positive closed drainage system culminating in two constructed recharge basins to handle collected water from the site.
Description of Alternative Concept (Brief)In exchange of a total closed pipe drainage system, with all conveyed water ending in large recharge basins, it is suggested that alternative bioengineered stormwater treatment practices be incorporated into the overall designed drainage solution. This could include narrow bioswales and filter strips, permeable pavement, and drainage inlet practices.
Design SuggestionNY 112 from LIE to Granny Road, Long Island, NY
Incorporate alternative stormwater treatments to reduce size of recharge basin
RationaleBioswales, filter strips, stormwater planters, and permeable pavement and pavers are usually a part of a larger stormwater drainage system, and in the case of this project (a closed pipe system ending in recharge basins) additional treatments along the flow path of runoff can improve overall water quality and reduce overall water quantity treatment volume required. Since the purchase of a large parcel of undeveloped land along NY 112 is required to accommodate the recharge basins, a cost savings is possible if a smaller parcel is required resulting from a reduced stormwater treatment volume.
Disadvantages of Alternative Concept (Brief)
Lack of opportunities (and space) within NY 112 corridor to implement practices
Higher maintenance required for additional installed practices
Possible negative opinion from traveling public of areas where practices are located
Possible lack of substantial reduction in treatment volume from added practices
Advantages of Alternative Concept (Brief)
Improves water quality treatment during first flush
Reduces stormwater treatment volume required, resulting in smaller recharge basins needed
Reduces cost from reduced ROW takings
Community support for incorporating green concepts into public projects
Original Concept
Alternative Concept
Difference
13 I - 18
January 13-15, 2016
Page 2 of 10
Alter. No. DR-04
NY 112 from LIE to Granny Road, Long Island, NY
Title
Design Suggestion
Although this project will increase impervious surfaces, and will disturb more than one acre of soil cumulatively, the runoff will not drain directly into any protected waters of the United States. Under these circumstances, the project is not subject to the State Pollution Discharge Elimination System (SPDES) general permit. Therefore, no formal quantity and quality treatment facilities for stormwater management are required. However, since there are limited stormwater facilities throughout the corridor from Granny Road to the LIE and there is a recurring flooding problem in the vicinity of Horse Block Road, a designed collection and treatment of stormwater is warranted.
The proposed closed drainage system will be constructed to expand the system being built to the north under Contract D262794. Some initial analyses has been conducted to determine the size of recharge basins needed to accommodate total runoff collected from the closed system. Further analyses will fine tune treatment facility needs. The alternative treatment practices suggested here should be considered for and incorporated into this detailed analysis.
It is likely that flooding occurs on this project from a lack of infiltration opportunity (too much pavement and no drainage channels) and the addition of locations for infiltration will help elevate the problem. In addition to, and along the route of the piped positive drainage system, infiltration systems can be added whenever possible to aid in lessening peak flows and increasing runoff detention. These systems can intercept sheet flow before getting to the closed system, or can be placed along the conduit to a single point of discharge at a recharge basin for added infiltration. Perforated pipe can be placed at the base of facilities to aid in collection of the treated runoff and connect to the closed system.
Bioswales are vegetated, shallow depressions designed to capture, treat, and infiltrate stormwater runoff as it moves offsite. They are typically sized to treat the water quality event, or “first flush,” which is the first and often most polluted volume of water resulting from a storm event. Bioswales are the most effective type of green infrastructure facility in slowing runoff velocity and cleansing water. They have flexible siting requirements, allowing them to be integrated with medians, cul-de-sacs, bulb outs, and other public space or traffic calming strategies.
A vegetated filter strip is a level facility that receives runoff in a distributed fashion along the length of one side and treats stormwater by settling out solids. More flat grades and dense vegetation across the top surface will encourage infiltration into the planting soil and improve treatment.
A stormwater planter is a structural container with soil and plants built to collect and slow runoff. Runoff is ponded and then treated as it passes through plants, roots, and soil. Treatment is provided through physical settling & filtration.
Pervious pavement effectively treats, detains, and infiltrates stormwater runoff where landscape-based strategies are restricted or less desired. Pervious pavements have multiple applications, including sidewalks, street furniture zones, bike paths, and entire roadways (or just their parking lane or gutter strip portions). An underdrain system can be used to convey remaining runoff to the closed drainage system.
Incorporate alternative stormwater treatments to reduce size of recharge basin
Discussion (Elaborate)
14 I - 19
January 13-15, 2016
Page 3 of 10
Alter. No. DR-04
NY 112 from LIE to Granny Road, Long Island, NY
Title
Design Suggestion
Pervious strips are long, linear landscaped areas or linear areas of pervious pavement that capture and slow runoff. Depending on the underlying subsurface soil condition, pervious strips can provide some infiltration, but to a much lesser extent than bioswales. Pervious strips offer an inexpensive initial step in urban stormwater management, but are unlikely to provide enough capacity for treatment of a street’s full water quality event.
Incorporate alternative stormwater treatments to reduce size of recharge basin
Exhibits - Alternative Concept
15 I - 20
January 13-15, 2016
Page 4 of 10
Alter. No. DR-04
Design SuggestionNY 112 from LIE to Granny Road, Long Island, NY
Title
Incorporate alternative stormwater treatments to reduce size of recharge basin
Exhibits - Alternative Concept
16 I - 21
January 13-15, 2016
Page 5 of 10
Alter. No. DR-04
Design Suggestion
Incorporate alternative stormwater treatments to reduce size of recharge basin
Exhibits - Alternative Concept
NY 112 from LIE to Granny Road, Long Island, NY
Title
17 I - 22
January 13-15, 2016
Page 6 of 10
Alter. No. DR-04
Design Suggestion
Incorporate alternative stormwater treatments to reduce size of recharge basin
Exhibits - Alternative Concept
NY 112 from LIE to Granny Road, Long Island, NY
Title
18 I - 23
January 13-15, 2016
Page 7 of 10
Alter. No. DR-04
Design Suggestion
Incorporate alternative stormwater treatments to reduce size of recharge basin
Exhibits - Alternative Concept
NY 112 from LIE to Granny Road, Long Island, NY
Title
19 I - 24
January 13-15, 2016
Page 8 of 10
Alter. No. DR-04Title
Incorporate alternative stormwater treatments to reduce size of recharge basin
Design SuggestionNY 112 from LIE to Granny Road, Long Island, NY
Exhibits - Alternative Concept
20 I - 25
January 13-15, 2016
Page 9 of 10
Alter. No. DR-04Title
Incorporate alternative stormwater treatments to reduce size of recharge basin
Design SuggestionNY 112 from LIE to Granny Road, Long Island, NY
Exhibits - Alternative Concept
21 I - 26
January 13-15, 2016
Page 10 of 10
Alter. No. DR-04Title
Incorporate alternative stormwater treatments to reduce size of recharge basin
Design SuggestionNY 112 from LIE to Granny Road, Long Island, NY
Exhibits - Alternative Concept
22 I - 27
January 13-15, 2016Page 1 of 4
Title Alter. No. DR-06
Cost Summary First Costs (Capital Costs)
Present Worth (of Future Costs)
Life Cycle Cost(Total LCC)
5,692,000$ -$ 5,692,000$
5,201,000$ -$ 5,201,000$
491,000$ -$ 491,000$
Key ContactsProject Mgr: William Stroh
Team Leader: Tom Wiggins, CVS
Description of Original Concept (Brief)For the majority of the project, there are two distinct drainage trunk lines, one each on the southbound and northbound curb lines of Route 112. These eventually drain into recharge basin(s). As they approach the recharge basins, each of these two systems get progressively deeper due to the required slope of the drainage pipes,
Description of Alternative Concept (Brief)Use laterals to tie into one trunk line on the northbound side of NY 112. In areas where drainage structures are closely space on the southbound side, three or more basins can be joined together before the lateral crosses to the trunk line on the northbound side.
Quantitative Value AlternativeNY 112 from LIE to Granny Road, Long Island, NY
Use laterals to tie into trunk line on one side
RationaleReduce cost of drainage to the project by reconsidering trunk line arrangement.
Disadvantages of Alternative Concept (Brief)Trunk line will require larger piping of to accommodate the additional flow on the northbound side.This will require piping up to 60" which has equivalent flow capacity of two 42" pipes,Laterals will have to be constructed in stages as they will cross both sides of the anticipated construction staging.Incremental growth of the size of manholes on the northbound side. (but no depth increase)
Requires on-going involvement of the drainage subcontractor during the project
Advantages of Alternative Concept (Brief)Most of the drainage piping on the southbound side would utilize smaller diameter pipe at shallower depths reducing overall costs and ease of installation with smaller equipmentOverall reduction in length of piping, reducing maintenance
Reduces size and depth of numerous drainage manholes on the southbound side of the roadway
Original Concept
Alternative Concept
Difference
23 I - 28
January 13-15, 2016
Page 2 of 4
Alter. No. DR-06
NY 112 from LIE to Granny Road, Long Island, NY
Title
Quantitative Value Alternative
Each 50 l.f. Lateral crossing replaces 200 l.f of Trunk Line Drainage.We have assumed n overall reduction of 60% of piping from the southbound side due to varying locations where that pipe will be required.
Use laterals to tie into trunk line on one side
Exhibits - Alternative Concept
24 I - 29
January 13-15, 2016
Page 3 of 4
Alter. No. DR-06
Quantitative Value AlternativeNY 112 from LIE to Granny Road, Long Island, NY
Title
Following Chart was utilized to determine required pipe size for single Trunk Drainage Line which would accommodate flow from both northbound and southbound drainage structures.
Use laterals to tie into trunk line on one side
Exhibits - Alternative Concept
25 I - 30
January 13-15, 2016
Page 3 of 4
Alter. No. DR-06
Description Unit Quantity Unit Cost Total
15" Drainage Pipe LF 2370 $105.00 $248,85018" Drainage Pipe LF 2370 $121.56 $288,08724" Drainage Pipe LF 3160 $230.44 $728,20430" Drainage Pipe LF 3950 $282.67 $1,116,53336" Drainage Pipe LF 2370 $326.96 $774,90242" Drainage Pipe LF 1580 $454.00 $717,320Drainage Structures Each 101 $18,000.00 $1,818,000
Subtotal: $5,691,897Project Markup: -$
Total Cost (Rounded): 5,692,000$
Description Unit Quantity Unit Cost Total15" Drainage Trunk Pipe LF 600 $105.00 $63,00021" Drainage Trunk Pipe LF 1185 $128.00 $151,68024" Drainage Trunk Pipe LF 1585 $230.44 $365,24736" Drainage Trunk Pipe LF 2180 $326.96 $712,77342" Drainage Trunk Pipe LF 2400 $454.00 $1,089,60054" Drainage Trunk Pipe LF 1200 $500.00 $600,00060" Drainage Trunk Pipe LF 800 $552.00 $441,60015" Drainage Lateral Pipe LF 1500 $105.00 $157,500Trunk Drainage Structures Each 51 $20,000.00 $1,020,000Lateral Drainage Structures Each 50 $12,000.00 $600,000
Subtotal: 5,201,400$
Project Markup: -$
Total Cost (Rounded): 5,201,000$
Cost Difference: 491,000$
NY 112 from LIE to Granny Road, Long Island, NY
Title
Use laterals to tie into trunk line on one side
Estimated Cost of Original Concept
Quantitative Value Alternative
Estimated Cost of Alternative Concept Proposed
26 I - 31
January 13-15, 2016Page 1 of 4
Title Alter. No. EM-01
Cost Summary First Costs (Capital Costs)
Present Worth (of Future Costs)
Life Cycle Cost(Total LCC)
-$ -$ -$
-$ -$ -$
-$ -$ -$
Key ContactsProject Mgr: William Stroh
Team Leader: Tom Wiggins, CVS
Description of Original Concept (Brief)South of the North Service Road to the southern project limit, the typical section includes the 6-foot bike lane and an 8-foot sidewalk.
Description of Alternative Concept (Brief)Combine the 6-foot bike lane and 8-foot sidewalk into a 10-foot combined sidewalk/bikeway shared use path. This combination along with a reduction of 1-foot in the right lane would extend the left turn lanes on Route 112 (Northbound and Southbound) between the North and South Service Roads.Combining the pedestrian and bicycle path functions for this section reduces some functionality, but the potential for increased storage capacity for left turn vehicles may be a greater priority.
Design SuggestionNY 112 from LIE to Granny Road, Long Island, NY
Combine sidewalk and bikeway south of north service road
RationaleThe combination of the bike lane and sidewalk south of the North Service Road to the Southern Project limit would allow extending the existing left turn lanes on Route 112. This would in turn help reduce congestion at the North and South Service Road intersections.
Disadvantages of Alternative Concept (Brief)
Combines Sidewalk/Bikeway to shared use path
Advantages of Alternative Concept (Brief)
Extends the Route 112 left turn lanes
Original Concept
Alternative Concept
Difference
27 I - 32
January 13-15, 2016
Page 2 of 4
Alter. No. EM-01
NY 112 from LIE to Granny Road, Long Island, NY
Title
Design Suggestion
The cost associated with this design suggestion would be minimal compared to the benefit of extending the left turn lane to reduce the congestion through the intersections. There would be slightly higher quantities of concrete for the combined sidewalk and bikeway while slightly less full depth asphalt concrete pavement on subbase for the reduction in roadway width.
Combine sidewalk and bikeway south of north service road
Discussion (Elaborate)
28 I - 33
January 13-15, 2016
Page 3 of 4
Alter. No. EM-01
Design Suggestion
Combine sidewalk and bikeway south of north service road
Exhibits - Original Concept
NY 112 from LIE to Granny Road, Long Island, NY
Title
Proposed Cross Sections South of North Service RoadDraft Design Report dated October 2015
29 I - 34
January 13-15, 2016
Page 4 of 4
Alter. No. EM-01
Design Suggestion
Combine sidewalk and bikeway south of north service road
Exhibits - Alternative Concept
NY 112 from LIE to Granny Road, Long Island, NY
Title
30 I - 35
January 13-15, 2016Page 1 of 3
Title Alter. No. EM-02
Cost Summary First Costs (Capital Costs)
Present Worth (of Future Costs)
Life Cycle Cost(Total LCC)
-$ -$ -$
-$ -$ -$
-$ -$ -$
Key ContactsProject Mgr: William Stroh
Team Leader: Tom Wiggins, CVS
Description of Original Concept (Brief)Between the LIE South Service Road and LIE North Service Road, NY112 will be widened along the right side in each direction to accommodate a bicycle lane. Behind the reconstructed and realigned curbs, the sidewalks will be reconstructed and small retaining walls will be built for segments under the bridge. Typical Section Sheet No.A-13 depicts this wall as being a precast concrete wall with approximately 4 foot exposed height .
Description of Alternative Concept (Brief)Consider a reinforced concrete modular block wall or gabion wall in lieu of the precast concrete wall.The base of the foundation for a modular or gabion type wall may be placed approximately 2 foot below grade where as the base of footing for a rigid wall such as a cast in place concrete wall will require a minimum of 4 foot below grade.
Design SuggestionNY 112 from LIE to Granny Road, Long Island, NY
Use gabion or modular retaining wall in lieu of cast in place concrete wall
RationaleUsing gabion or modular type walls in lieu of cast-in-place concrete walls for these low height walls will result in easier and quicker construction, less intricate excavation support system and will be cost effective.
Disadvantages of Alternative Concept (Brief)Aesthetically, the caged gabion walls may not be as pleasing as a modular wall system or cast in place concrete system
Original Concept
Advantages of Alternative Concept (Brief)
Reduces excavation depth and excavation support system requirements. There may be inadequate head room to install a simple steel sheet piling system under the overhead bridge structure.
Due to the location and low wall height required, gabion walls and precast modular walls should be cost effective.
Reduces construction time
Alternative Concept
Difference
31 I - 36
January 13-15, 2016
Page 2 of 3
Alter. No. EM-02
NY 112 from LIE to Granny Road, Long Island, NY
Title
Design Suggestion
Cast-in-Place Concrete Retaining Wall-Note required amount of excavation and height of excavation support system
Use gabion or modular retaining wall in lieu of cast in place concrete wall
Exhibits - Original Concept
32 I - 37
January 13-15, 2016
Page 3 of 3
Alter. No. EM-02
NY 112 from LIE to Granny Road, Long Island, NY
Title
Design Suggestion
Precasr Modular Concrete Retaining Wall-Note required amount of excavation and height of excavation support
Use gabion or modular retaining wall in lieu of cast in place concrete wall
Exhibits - Alternative Concept
33 I - 38
January 13-15, 2016Page 1 of 4
Title Alter. No. EM-03
Cost Summary First Costs (Capital Costs)
Present Worth (of Future Costs)
Life Cycle Cost(Total LCC)
42,000$ -$ 42,000$
200,000$ -$ 200,000$
(158,000)$ -$ (158,000)$
Key ContactsProject Mgr: William Stroh
Team Leader: Tom Wiggins, CVS
Description of Original Concept (Brief)Between the LIE South Service Road and LIE North Service Road, NY112 will be widened along the right side in each direction to accommodate a bicycle lane. The bike lane and sidewalk will be at the same elevation as the vehicular traffic lanes. Behind the reconstructed and realigned curbs, the sidewalks will be reconstructed and small retaining walls will be built for segments under the bridge.
Along NY 112, between the I-495 Eastbound Mainline bridge south fascia and the I-495 Westbound Mainline Bridge north fascia, elevate either just the sidewalk or the sidewalk and the bicycle path. The north and south sidewalk / bicycle approaches along NY112 to this area will gradually ramp up to meet this elevated section. Provide bicycle rails are to be provided and the ramped approaches will be ADA compliant.
Qualitative Value AlternativeNY 112 from LIE to Granny Road, Long Island, NY
Elevate the sidewalk and bike lane under the bridge
RationaleElevate the sidewalk, or sidewalk and bike route on NY112, under the I-495 Mainline Bridge; so as to provide a safer pedestrian/bike path and to minimize disruption to the paved slope in front of the stub abutment.
Improves safety of the bicycle riders in this confined area under the bridge
Disadvantages of Alternative Concept (Brief)
The cost along the approach sidewalks/bike path will be higher due to the addition of rampsAdditional granular fill will be required at the approach ramps and at the elevated sections in the expressway bridge areas
Advantages of Alternative Concept (Brief)
Proposed retaining wall will require less excavation and will be placed further from the stem of the stub abutment, beyond the base of the slope thus resulting in minimal disturbance to the slopeBicycle riders and/or pedestrians will feel more comfortable elevated from the main traffic line since the area under the bridge is a more confined spaceConstructability will be easier due to a reduction in excavation depth and the elimination of a complex excavation support system
Cost of adding elevated walkways is minimal compared to the benefit provided
Original Concept
Alternative Concept
Difference
34Version B3.0.1, 1/4/2016 I - 39
January 13-15, 2016
Page 2 of 4
Alter. No. EM-03
NY 112 from LIE to Granny Road, Long Island, NY
Title
Qualitative Value Alternative
Elevate the sidewalk and bike lane under the bridge
Exhibits - Alternative Concept
35Version B3.0.1, 1/4/2016 I - 40
January 13-15, 2016
Page 3 of 4
Alter. No. EM-03
Qualitative Value AlternativeNY 112 from LIE to Granny Road, Long Island, NY
Title
Example of similar sidewalk ramp, L.I.E. over Deer Park Ave., Dix Hills, NY
Elevate the sidewalk and bike lane under the bridge
Exhibits - Alternative Concept
36Version B3.0.1, 1/4/2016 I - 41
January 13-15, 2016
Page 4 of 4
Alter. No. EM-03
Description Unit Quantity Unit Cost Total
Retaining Walls LS 1 $41,500.00 $41,500
It was assumed that the pavement would remain the same for both alternatives.
Subtotal: 41,500$
Project Markup: -$
Total Cost (Rounded): 42,000$
Description Unit Quantity Unit Cost Total
Elevated Bike/Pedestrian Path LS 2 $100,000.00 $200,000
Subtotal: 200,000$
Project Markup: -$
Total Cost (Rounded): 200,000$
Cost Difference: (158,000)$
NY 112 from LIE to Granny Road, Long Island, NY
Title
Elevate the sidewalk and bike lane under the bridge
Estimated Cost of Original Concept
Qualitative Value Alternative
Estimated Cost of Alternative Concept Proposed
37Version B3.0.1, 1/4/2016 I - 42
January 13-15, 2016Page 1 of 2
Title Alter. No. M-02
Cost Summary First Costs (Capital Costs)
Present Worth (of Future Costs)
Life Cycle Cost(Total LCC)
-$ -$ -$
-$ -$ -$
-$ -$ -$
Key ContactsProject Mgr: William Stroh
Team Leader: Tom Wiggins, CVS
Description of Original Concept (Brief)This was not addressed in the original design report.
Description of Alternative Concept (Brief)Replace the existing Fitch barrels that protect motorists from striking the center pier in both the northbound and southbound directions with standard impact attenuators.
Design SuggestionNY 112 from LIE to Granny Road, Long Island, NY
Replace Fitch barrels with impact attenuator at LIE bridge
RationaleThe existing Fitch barrels appear to be in poor condition and may not function as originally intended. In order to improve motorist safety, we recommend that they be replaced with an improved impact attenuator system.
Disadvantages of Alternative Concept (Brief)
Increases construction cost
Advantages of Alternative Concept (Brief)
Replaces old system that is difficult to maintain
Provides better protection for motorists
Easier to maintain
Narrower width which should reduce likelihood of being struck.
Original Concept
Alternative Concept
Difference
38 I - 43
January 13-15, 2016
Page 2 of 2
Alter. No. M-02
NY 112 from LIE to Granny Road, Long Island, NY
Title
Design Suggestion
Replace Fitch barrels with impact attenuator at LIE bridge
Exhibits - Original Concept
39 I - 44
January 13-15, 2016Page 1 of 4
Title Alter. No. MR-01
Cost Summary First Costs (Capital Costs)
Present Worth (of Future Costs)
Life Cycle Cost(Total LCC)
6,032,000$ -$ 6,032,000$
5,313,000$ -$ 5,313,000$
719,000$ -$ 719,000$
Key ContactsProject Mgr: William Stroh
Team Leader: Tom Wiggins, CVS
Description of Original Concept (Brief)A 14' wide median is proposed to be installed within most of the project limits. The median will typically be used as two-way turn lane or a planted median.
Description of Alternative Concept (Brief)It is proposed to reduce the median width to 12' in order reduce construction costs and ROW taking.
Quantitative Value AlternativeNY 112 from LIE to Granny Road, Long Island, NY
Reduce width of median from 14' to 12'
RationaleIn order to reduce the amount of ROW taking, it is proposed to reduce the two way turn lane from 14' to 12'. In addition, there would be a cost savings for asphalt concrete, subbase, excavation and embankment. This will also reduce amount of water that has to be collected.
Disadvantages of Alternative Concept (Brief)
Reduces separation between northbound and southbound roadways
Less room for turning vehicles to wait for gaps
Advantages of Alternative Concept (Brief)
Reduces construction and ROW costs
May reduce impacts to adjacent properties
Reduces runoff that has to be collected in drainage system.
12' width meets design criteria
Original Concept
Alternative Concept
Difference
40 I - 45
January 13-15, 2016
Page 2 of 4
Alter. No. MR-01
NY 112 from LIE to Granny Road, Long Island, NY
Title
Quantitative Value Alternative
Reduce width of median from 14' to 12'
Exhibits - Original Concept
41 I - 46
January 13-15, 2016
Page 3 of 4
Alter. No. MR-01
Quantitative Value AlternativeNY 112 from LIE to Granny Road, Long Island, NY
Title
Reduce width of median from 14' to 12'
Exhibits - Alternative Concept
42 I - 47
January 13-15, 2016
Page 4 of 4
Alter. No. MR-01
Description Unit Quantity Unit Cost TotalAsphalt Concrete TONS 30150 $115.00 $3,467,250
Subbase CY 26000 $45.00 $1,170,000
Excavation CY 27258 $30.00 $817,740
Embankment CY 2328 $20.00 $46,560
ROW Acquisition Cost SF 13250 $40.00 $530,000
Subtotal: 6,031,550$
Project Markup: -$
Total Cost (Rounded): 6,032,000$
Description Unit Quantity Unit Cost TotalAsphalt Concrete TONS 29200 $115.00 $3,358,000
Subbase CY 25000 $45.00 $1,125,000
Excavation CY 26167.68 $30.00 $785,030
Embankment CY 2234.88 $20.00 $44,698
Subtotal: 5,312,728$
Project Markup: -$
Total Cost (Rounded): 5,313,000$
Cost Difference: 719,000$
NY 112 from LIE to Granny Road, Long Island, NY
Title
Reduce width of median from 14' to 12'
Estimated Cost of Original Concept
Quantitative Value Alternative
Estimated Cost of Alternative Concept Proposed
43 I - 48
January 13-15, 2016Page 1 of 2
Title Alter. No. MR-05
Cost Summary First Costs (Capital Costs)
Present Worth (of Future Costs)
Life Cycle Cost(Total LCC)
-$ -$ -$
-$ -$ -$
-$ -$ -$
Key ContactsProject Mgr: William Stroh
Team Leader: Tom Wiggins, CVS
Description of Original Concept (Brief)According to Section 3.2.3.1 from the Draft Design Report dated October 2015, the design speed of 55 mph is consistent with the anticipated off-peak 85th percentile speed within the range of the functional class speeds for terrain and volume.
Description of Alternative Concept (Brief)Reduce the design speed along Route 112 to 45 mph. The minimum lane width for a Low Speed (<50 mph) Urban Arterial is 11-foot minimum.
Design SuggestionNY 112 from LIE to Granny Road, Long Island, NY
Reduce design speed of road to reduce lane widths
RationaleThe observed travel speeds in the PM Peak Hour range from 10 mph to 50 mph as shown below with the majority of the speeds under 40 mph. The reduction of the design speed would justify the reduction of the proposed travel lanes and minimize the ROW acquisition costs.
Disadvantages of Alternative Concept (Brief)
Reduced design speed.
Advantages of Alternative Concept (Brief)
Reduces travel lanes and 2-feet of ROW acquisition on each side of Route 112.
Reduces project cost
Original Concept
Alternative Concept
Difference
44 I - 49
January 13-15, 2016
Page 2 of 2
Alter. No. MR-05
NY 112 from LIE to Granny Road, Long Island, NY
Title
Design Suggestion
Reduce design speed of road to reduce lane widths
Exhibits - Original Concept
Observed Travel Speeds, PM Peak Hour
10 – 20 mph
20 – 30 mph
30 – 40 mph
40 – 50 mph
45 I - 50
January 13-15, 2016Page 1 of 5
Title Alter. No. MR-06
Cost Summary First Costs (Capital Costs)
Present Worth (of Future Costs)
Life Cycle Cost(Total LCC)
1,096,000$ -$ 1,096,000$
-$ -$ -$
1,096,000$ -$ 1,096,000$
Key ContactsProject Mgr: William Stroh
Team Leader: Tom Wiggins, CVS
Description of Original Concept (Brief)Proposed sidewalk area width is 13-feet. This area is make up of a 5-foot strip adjacent to the bike lane, a 5-foot sidewalk and a 3-foot strip between the sidwalk and the Fee Acquistion line.
Description of Alternative Concept (Brief)Reduce the sidewalk area width to 11-feet. The sidewalk width would remain constant while the 3-foot and 5-foot strips on either side of the sidewalk would be reduced 1-foot each.The ROW acquisitions costs were calculated using the total ROW costs divided by the total acre of FEE and TE takings.
Quantitative Value AlternativeNY 112 from LIE to Granny Road, Long Island, NY
Reduce sidewalk area width from 13' to 11'
RationaleReducing the sidewalk area width by 2 feet on each side of Route 112 will save on ROW acquisition costs, including both Fee acquisiton and temporary easements. This reduction will not affect the over sidewalk width, but rather the snow storage area adjacent to the bike lane and the area between the sidewalk and the Fee Acquisition line.
Disadvantages of Alternative Concept (Brief)
Reduces snow storage area between the the bike lane and the sidewalk
Reduces sign and planting area between the sidewalk and the Fee Acquistion line
Advantages of Alternative Concept (Brief)
Reduces 2-feet of ROW acquistion on each side of Route 112
Reduces project cost
Original Concept
Alternative Concept
Difference
46 I - 51
January 13-15, 2016
Page 2 of 5
Alter. No. MR-06
Quantitative Value Alternative
Reduce sidewalk area width from 13' to 11'
Exhibits - Original Concept
NY 112 from LIE to Granny Road, Long Island, NY
Title
Proposed Typical Section from Draft Design Report (October 2015)
47 I - 52
January 13-15, 2016
Page 3 of 5
Alter. No. MR-06
Quantitative Value Alternative
Reduce sidewalk area width from 13' to 11'
Exhibits - Alternative Concept
NY 112 from LIE to Granny Road, Long Island, NY
Title
Revised Typical Section showing reduced Sidewalk Area
48 I - 53
January 13-15, 2016
Page 4 of 5
Alter. No. MR-06
Quantitative Value Alternative
Reduce sidewalk area width from 13' to 11'
Exhibits - Alternative Concept
NY 112 from LIE to Granny Road, Long Island, NY
Title
ROW Cost BreakdownTotal FEE Acquistion for Alternate with Option: 7.697 acresTotal TE for Alternate with Option: 3.105 acresTOTAL = 10.803 acresROW Cost Estimate = $16,750,000 (per S. Muchnick 7/20/15 Memo)Cost/Acre = $1,550,561 SAY $1,600,000/acreCost/SF = $35.50 SAY $40/SF
Reduction in Area due to Reduction of Sidewalk Area WidthFrom Horseblock Road (STA 231+00) to Granny Road (STA 297+50) = 6,650 feet (west side)From Horseblock Road to Granny Road = 6,650 - 50 = 6,600 feet (east side - reduction for Commercial Drive). TOTAL Length = 13,250 feet
Reduction of 2 feet on each side = 13,250 x 2 = 26,500 SF
Topsoil Reduction: 26,500 SF x 6-inches = 13,250 CF = 490 CY SAY 500 CY Seed Reduction: 26,500 SF = 2,944 SY SAY 3,000 SY
49 I - 54
January 13-15, 2016
Page 5 of 5
Alter. No. MR-06
Description Unit Quantity Unit Cost TotalROW Acquisition Cost SF 26500 $40.00 $1,060,000
Topsoil CY 500 $60.00 $30,000
Seed SY 3000 $2.00 $6,000
*Quantities reflect deductions based on the alternative shown
Subtotal: 1,096,000$
Project Markup: -$
Total Cost (Rounded): 1,096,000$
Description Unit Quantity Unit Cost Total
Subtotal: -$
Project Markup: -$
Total Cost (Rounded): -$
Cost Difference: 1,096,000$
NY 112 from LIE to Granny Road, Long Island, NY
Title
Reduce sidewalk area width from 13' to 11'
Estimated Cost of Original Concept
Quantitative Value Alternative
Estimated Cost of Alternative Concept Proposed
50 I - 55
January 13-15, 2016Page 1 of 1
Title Alter. No. MR-09
Cost Summary First Costs (Capital Costs)
Present Worth (of Future Costs)
Life Cycle Cost(Total LCC)
-$ -$ -$
-$ -$ -$
-$ -$ -$
Key ContactsProject Mgr: William Stroh
Team Leader: Tom Wiggins, CVS
Description of Original Concept (Brief)A northbound turn lane from NY 112 to the Country Fair Amusement Park is currently incorporated into the proposed plans. (Dwg. No. 17-A3.)
Description of Alternative Concept (Brief)Eliminate this right hand turn lane.
Design SuggestionNY 112 from LIE to Granny Road, Long Island, NY
Eliminate northbound right turn lane at Country Fair Entertainment Park
RationaleThe right hand turn lane is not heavily used according to the traffic study. Eliminate right hand turning lane so as to reduce the ROW and associated cost.
Disadvantages of Alternative Concept (Brief)
A right hand turn lane currently exists at this location, and the community is accustomed to it
Advantages of Alternative Concept (Brief)
Eliminating this right hand turn lane will reduce the amount of R.O.W taken
Reduces material and construction cost
Original Concept
Alternative Concept
Difference
51 I - 56
January 13-15, 2016Page 1 of 2
Title Alter. No. MR-10
Cost Summary First Costs (Capital Costs)
Present Worth (of Future Costs)
Life Cycle Cost(Total LCC)
-$ -$ -$
-$ -$ -$
-$ -$ -$
Key ContactsProject Mgr: William Stroh
Team Leader: Tom Wiggins, CVS
Description of Original Concept (Brief)The Design Plans currently show a right hand turning lane at Commercial Drive which begins to transition at approx. Station 267+70, and is full 11' width at Station 268+75. It then continues for roughly 200 l.f. to Station 270+70.
Description of Alternative Concept (Brief)Consider modifying the design to shorten this turning lane to 100 l.f., which would then allow the transition to begin at Station 268+70.
Design SuggestionNY 112 from LIE to Granny Road, Long Island, NY
Shorten northbound right turn lane at Commercial Drive
RationaleReduce cost of property takings, and minor savings in roadway construction.
Disadvantages of Alternative Concept (Brief)
Less room for right hand tuning vehicles to queue.
Advantages of Alternative Concept (Brief)
Reduces property takings where there is an active commercial property with numerous head in parking spots
Reduces roadway construction costs
Original Concept
Alternative Concept
Difference
52 I - 57
January 13-15, 2016
Page 2 of 2
Alter. No. MR-10
NY 112 from LIE to Granny Road, Long Island, NY
Title
Design Suggestion
See multiple parking spaces that will be affected.
Shorten northbound right turn lane at Commercial Drive
Exhibits - Original Concept
53 I - 58
January 13-15, 2016Page 1 of 2
Title Alter. No. MR-11
Cost Summary First Costs (Capital Costs)
Present Worth (of Future Costs)
Life Cycle Cost(Total LCC)
-$ -$ -$
-$ -$ -$
-$ -$ -$
Key ContactsProject Mgr: William Stroh
Team Leader: Tom Wiggins, CVS
Description of Original Concept (Brief)The original Design Concept maintained the existing alignment which is virtually tangent north of the curve at Horse Block Road to the project terminus at Granny Road.Property takings are being executed on both the east and west side of NY 112, as required by the project improvements.
Description of Alternative Concept (Brief)Consider modifying the roadway alignment to execute property takings on only one side of the ROW to accomplish the project goals where possible. The side would be dictated by the nature of the properties favoring unimproved lots.
Design SuggestionNY 112 from LIE to Granny Road, Long Island, NY
Move ROW taking to vacant side whenever possible
RationaleReduce number of properties affected by property takings and potentially reduce the cost of property acquisition.
Disadvantages of Alternative Concept (Brief)
Introduces horizontal curves to the roadway alignment
Advantages of Alternative Concept (Brief)
Could reduce overall cost of property takings
Reduces the total number of owners affected by project
Original Concept
Alternative Concept
Difference
54 I - 59
January 13-15, 2016
Page 2 of 2
Alter. No. MR-11
NY 112 from LIE to Granny Road, Long Island, NY
Title
Design Suggestion
After reviewing the project documents, we suggest there may be two general areas where the roadway could be shifted to allow for property takings on only one side of the ROW.
The fist being the vacant properties along the east side of the Northbound Travel Lane from just north of the Medford Fire Station to Lake Drive. This would mitigate the need to coordinate with the numerous existing commercial properties with driveways and parking spaces.
The second area would be on the west side of the Southbound Travel Lane. This would begin with a mild curve from Lake Drive around Station 261+00 to roughly Station 268+00 just past Burleson Reality. The takings would then continue on the west side of the southbound lane until the project termination at Granny Road. There are properties along both the eastern and western sides of the project in this area, however there are more properties on the eastern side and some of the western side properties appear to be residential with less impact.
Move ROW taking to vacant side whenever possible
Discussion (Elaborate)
55 I - 60
January 13-15, 2016Page 1 of 3
Title Alter. No. MR-12
Cost Summary First Costs (Capital Costs)
Present Worth (of Future Costs)
Life Cycle Cost(Total LCC)
658,000$ -$ 658,000$
-$ -$ -$
658,000$ -$ 658,000$
Key ContactsProject Mgr: William Stroh
Team Leader: Tom Wiggins, CVS
Original Concept
Alternative Concept
Difference
Disadvantages of Alternative Concept (Brief)
Will not ameliorate a non-standard feature, but the design only improves and does not eliminate
Advantages of Alternative Concept (Brief)
Reduces amount of truing and leveling that has to be placed to correct banking on Route 112
Reduces the amount of truing and leveling required along Horse Block Rd to meet existing pavement gradesReduces need for and cost of Temporary Easements
Reduces the construction time and simplifies Work Zone control
Description of Original Concept (Brief)Improve banking / superelevation on northbound horizontal curve between LIE NSR and Horse Block Road to extent feasible to eliminate adverse banking of roadway. For widening on east side for right turn lane (DWG - 01, SH A - 11), it is proposed to excavate below existing subbase as per DOT Regional Pavement Mgmt. requirements resulting over two feet of excavation.
Description of Alternative Concept (Brief)Retain existing banking as exists today since a crash problem has not been identified per Design Report. In addition, widening for right lane should be constructed at same grade as existing sub-base.
Quantitative Value AlternativeNY 112 from LIE to Granny Road, Long Island, NY
Eliminate superelevation of northbound NY 112 between LIE NSR and Horse Block Rd.
RationaleIn an effort to reduce ROW costs for temporary easements and improve constructability, consider eliminating the proposed superelevation along northbound NY 112. Data shows this is not a factor contributing to accidents.
56 I - 61
January 13-15, 2016
Page 2 of 3
Alter. No. MR-12
Eliminate superelevation of northbound NY 112 between LIE NSR and Horse Block Rd.
Exhibits - Alternative Concept
Quantitative Value AlternativeNY 112 from LIE to Granny Road, Long Island, NY
Title
57 I - 62
January 13-15, 2016
Page 3 of 3
Alter. No. MR-12
Description Unit Quantity Unit Cost TotalTruing and leveling on NY 112 and Horse Block Rd
tons 5724 $115.00 $658,260
Subtotal: 658,260$
Project Markup: -$
Total Cost (Rounded): 658,000$
Description Unit Quantity Unit Cost Total
Subtotal: -$
Project Markup: -$
Total Cost (Rounded): -$
Cost Difference: 658,000$
Estimated Cost of Alternative Concept Proposed
NY 112 from LIE to Granny Road, Long Island, NY
Title
Eliminate superelevation of northbound NY 112 between LIE NSR and Horse Block Rd.
Estimated Cost of Original Concept
Quantitative Value Alternative
58 I - 63
January 13-15, 2016Page 1 of 1
Title Alter. No. RC-07
Cost Summary First Costs (Capital Costs)
Present Worth (of Future Costs)
Life Cycle Cost(Total LCC)
-$ -$ -$
-$ -$ -$
-$ -$ -$
Key ContactsProject Mgr: William Stroh
Team Leader: Tom Wiggins, CVS
Description of Original Concept (Brief)According to Section 3.3.1.4 from the Draft Design Report dated October 2015, no new ITS measures are proposed and this project is considered "Exempt."
Description of Alternative Concept (Brief)Include ITS measures either on the Long Island Expressway, Northbound Route 112 (between the North Service Road and Horse Block Road) and Southbound Route 112 (before Horse Block Road). These additional measures would inform drivers with updated traffic and travel times so they could use alternate travel routes if there was congestion on Route 112 or the Long Island Expressway. There is an existing INFORM fiber-optic interconnect along the west side of NY 112 within the project limits that could be expanded.
Design SuggestionNY 112 from LIE to Granny Road, Long Island, NY
Add ITS
RationaleAdding ITS along the Long Island Expressway, Northbound Route 112 (between the North Service Road and Horse Block Road) and Southbound Route 112 (North of Horse Block Road) would provide drivers with traffic information and travel times for them to explore alternate routes.
Disadvantages of Alternative Concept (Brief)
Adds cost to project
Location of potential VMS sign(s) on Route 112.
Advantages of Alternative Concept (Brief)
Provides information to drivers to use alternate routes
Reduces congestion by giving drivers choices
Original Concept
Alternative Concept
Difference
59 I - 64
New York State Department of Transportation NY 112 from LIE to Granny Road
Value Engineering Report January 13-15, 2016
60
Appendix A: Function Analysis
I - 65
New York State Department of Transportation NY 112 from LIE to Granny Road
Value Engineering Report January 13-15, 2016
61
Appendix A: Function Analysis The VE Team conducted a function analysis of the NY 112 from LIE to Granny Road project to help the workshop’s Creative Phase yield VE Alternatives to better meet function requirements of the project. For each item, the VE Team identified functions provided by the current design and classified those functions, as shown on the following page in a Project Function List.
To further analyze project functions, while further training in and understanding function analysis, the VE Team prepared a Customer Function Analysis Systems Technique (FAST) Diagram to demonstrate relationships of functions to one another and how they work together to satisfy project requirements. Customer FAST diagrams graphically illustrate interrelationships of project functions and are often invaluable in accomplishing an in-depth understanding of project issues and functional requirements. The resulting Customer FAST Diagram is presented on the following page.
1. The vertical dashed line, known as Scope Line, define the scope of the project and the VE Study. Functions to the right of the line are part of the scope. Functions to the left are the Task to be accomplished by project.
2. The FAST diagram has two distinct sections, Basic Functions and Supporting Functions.
3. In the Basic Function section of the diagram, Primary Basic Functions are directly to the right of the Scope Line. Secondary Basic Functions branch off to the right of the Primary Basic Functions.
4. Supporting Functions are extremely important in fostering stakeholder acceptance of the project. There are four primary Supporting Functions: Assure Convenience, Assure Dependability, Satisfy Stakeholders, and Attract Stakeholders. Supporting Functions branch off to the right of these primary Supporting Functions.
5. Proper arrangement and relationships of the functions in the FAST diagram can be confirmed with the how-why logic test as follows:
a. Ask the question of any function, "How do I verb-noun?" The answer should be the function to the immediate right.
b. Ask the question "Why do I verb-noun?" The answer should be the function to the immediate left i.e., "So that I can verb-noun."
c. A function that does not pass the how-why test is either described improperly or is in the wrong place. The answer must make sense.
6. Our prime concern when constructing a FAST diagram is the essential functions.
I - 66
HOW? WHY?FAST DIAGRAM
NY 112 from LIE to Granny Road
Bas
ic F
un
ctio
ns
Reduce Congestion
Improve SafetyDrain Roadway
Enable Multimodal
Reduce Delays
Upgrade Travelways
Extend Life
Enhance Appearance
Upgrade Traffic Control Devices
Minimize Disruption
Improve Mobility
Accommodate Utilities
Improve Maintainability
Protect Environment
Manage ROW
Improve Traffic Flow
Allow Emergncy Flow
Maintain Access
Reduce Maintence
Assure Dependability
Assure Convienence
Satisfy Stakeholders
Attract Stakeholders
Su
pp
ort
ing
Fu
nct
ion
s
Satisfy Motorist Expectations
Correct Deficiencies
Safeguard Motorist
Extend Pathways
Maintain Flow
Task
62 I - 67
New York State Department of Transportation NY 112 from LIE to Granny Road
Value Engineering Report January 13-15, 2016
63
Appendix B: Pareto Cost Model
I - 68
64
33
.9%
29
.8%
9.4
%
5.4
%
4.6
%
3.7
%
2.7
%
2.3
%
1.7
%
1.7
%
1.4
%
1.4
%
0.7
%
0.7
%
0.7
%
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
$0
$2,000,000
$4,000,000
$6,000,000
$8,000,000
$10,000,000
$12,000,000
$14,000,000
$16,000,000
$18,000,000
$20,000,000B
ase
Co
nstr
uctio
n C
ost
RO
W C
osts
Co
ntin
genc
y
Co
nstr
uct
ion
Insp
ect
ion
Infla
tion
Bas
ic M
& P
of
Tra
ffic
Util
ities
Mo
biliz
atio
n
ITS
Fie
ld C
hang
e P
aym
ent
Land
scap
ing
Sur
vey
& S
take
out
Ero
sion
Con
tro
l Mea
sure
s
Ha
zMat
Re
me
dia
tion
637
Item
s
Cu
mu
lati
ve
Per
cen
tag
e
Co
st
Pareto Cost Model
NY 112 Reconstruction Cost, LIE to Granny Road Item: Total Cost
I - 69
65
33
.0%
30
.6%
16
.8%
5.4
%
4.0
%
3.8
%
2.3
%
1.5
%
1.5
%
0.6
%
0.2
%
0.2
%
0.0
%
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
$0
$1,000,000
$2,000,000
$3,000,000
$4,000,000
$5,000,000
$6,000,000
Dra
inag
e
Pav
eme
nt
Exc
avat
ion
Sid
ew
alk
Tra
ffic
Sig
nals
Cu
rb
Cle
arin
g &
Gru
bbin
g
Tur
f and
To
psoi
l
Em
bank
men
t
Pav
eme
nt M
arki
ngs
Re
tain
ing
Wal
ls
Sig
ns
Ligh
ting
Cu
mm
ula
tiv
e P
erce
nta
ge
Co
st
Pareto Cost Model
NY 112 Reconstruction Cost, LIE to Granny Road Item: Base Construction Cost
I - 70
New York State Department of Transportation NY 112 from LIE to Granny Road
Value Engineering Report January 13-15, 2016
66
Appendix C: Creative Idea List with Evaluation Score and Action
I - 71
LIST OF CREATIVE IDEASNY 112 from LIE to Granny RoadLong Island, NYJanuary 13-15, 2016
Alter. No. Creative Idea Description Rank ActionGrouped
With Comments / NotesMR-03 Use a multiuse path in lieu of separate
bikeway and sidewalk5
MR-04 Provide 2-way bikeway on one side only 1
DR-04 Use bio-swales and filter strips to reduce size of recharge basin
8 A
M-01 Defer all improvements under LIE until future project where all work will be performed
2
DR-06 Use laterals to tie into trunk line on one side 9 A
DR-01 Use pervious pavement in lieu of impervious to reduce run-off
1 Non-mainline travelways
EM-00 Enable Multi-Modal #T #T
EM-01 Combine sidewalk and bikeway south of north service road
8 A
RC-02 Elevate Horse Block Road at NY 112 1
DR-02 Raise elevation of NY 112 to reduce flooding 1
EM-02 Use gabion or modular retaining wall in lieu of cast in place concrete wall
8 DS
RC-03 Dead end Middle Island Road before Horse Block Road
1
RC-04 Make Middle Island Road one way in from Horse Block
5
EM-03 Elevate the sidewalk and bike lane under the bridge
8 A
M-00 Miscellaneous #T #T
M-02 Replace Fitch barrels with impact attenuator at LIE bridge
8 DS
MR-07 Construct separate shoulder 3 Take more ROW
MR-08 Combine bike route and shoulder 6 Do not designate as bike lane, use as both
RC-05 Provide turnouts for breakdowns 1
RC-06 Make Horse Block Road a roundabout 4 Could incorporate Middle Island Road
MR-00 Manage ROW #T #T
MR-01 Reduce width of median from 14' to 12' 9 A Center turn lane
MR-05 Reduce design speed of road to reduce lane widths
8 DS
DR-05 Switch out planted median with storm water bio-swales
3
RC-08 Make NY 112 a divided highway 2
MR-06 Reduce sidewalk area width from 13' to 11' 8 A
MR-09 Eliminate northbound right turn lane at Country Fair Entertainment Park
8 DS
MR-10 Shorten northbound right turn lane at Commercial Drive
8 DS
67Version B3.0.1, 1/4/2016 I - 72
LIST OF CREATIVE IDEASNY 112 from LIE to Granny RoadLong Island, NYJanuary 13-15, 2016
RC-09 Provide roundabouts at all signal intersections 5 Commercial and Executive
DR-07 Have design meeting with regulatory agencies to resolve stormwater issues
1 ABD
Action
A - Alternative (Quantitative or Qualitative)
DS - Design Suggestion
EC - Estimate Correction
CR - Cost Reduction
ABD - Already Being Done
X - Dropped during Development
68Version B3.0.1, 1/4/2016 I - 73
New York State Department of Transportation NY 112 from LIE to Granny Road
Value Engineering Report January 13-15, 2016
69
Appendix D: VE Presentation List of Attendees
I - 74
I - 77
AUTHORIZATION Faithful+Gould
Approved for issue:
Scot McClintock
One Midtown Plaza
1360 Peachtree Street
Suite 850
Job manager:
Tom Wiggins
Date: January 21, 2016
Atlanta, GA 30309
Telephone: 1 404.874.3638
Fax: 1 404.874.1473
I - 78