45
Revision 5 OCTOBER 2019 HENRY & HYMAS LEVEL 5, 79 VICTORIA AVENUE CHATSWOOD NSW 2067 Our Ref: 19459 Tel: (02) 9417 8400 Fax: (02) 9417 8337 E-mail: [email protected] FLOOD MANAGEMENT PLAN PROPOSED AGED CARE FACILITY Northbourne Drive MARSDEN PARK, NSW

FLOOD MANAGEMENT PLAN PROPOSED AGED CARE FACILITY ... · Flood Management Plan – Opal Marsden Park 3 Introduction This Flood Management Plan (the Report) has been prepared for Opal

  • Upload
    others

  • View
    3

  • Download
    0

Embed Size (px)

Citation preview

Page 1: FLOOD MANAGEMENT PLAN PROPOSED AGED CARE FACILITY ... · Flood Management Plan – Opal Marsden Park 3 Introduction This Flood Management Plan (the Report) has been prepared for Opal

Revision 5

OCTOBER 2019

HENRY & HYMAS LEVEL 5, 79 VICTORIA AVENUE CHATSWOOD NSW 2067 Our Ref: 19459 Tel: (02) 9417 8400 Fax: (02) 9417 8337

E-mail: [email protected]

FLOOD MANAGEMENT PLAN

PROPOSED AGED CARE FACILITY

Northbourne Drive

MARSDEN PARK, NSW

Page 2: FLOOD MANAGEMENT PLAN PROPOSED AGED CARE FACILITY ... · Flood Management Plan – Opal Marsden Park 3 Introduction This Flood Management Plan (the Report) has been prepared for Opal

Flood Management Plan – Opal Marsden Park

2

Executive Summary

This Flood Management Plan (the Report) has been prepared for Opal Aged Care to supplement the Development Application for the proposed Aged Care Facility on Northbourne Drive, Marsden Park. The site comprises an area of approximately 10,050 m2, with a proposed building footprint of 6,400m2 as well as associated car parking and landscaping facilities. It has been established that the proposed development is at risk of inundation from extreme flood events, with inundation possibility occurring during the PMF (Probable Maximum Flood) event from flooding of the Hawkesbury Nepean Valley. The PMF is the largest flood event that could conceivably occur at a particular location, usually estimated from the probable maximum precipitation. The PMF defines the extent of flood liable land, that is, the floodplain. It is difficult to define a meaningful Annual Exceedance Probability (AEP) for the PMF but is commonly understood to be in order of 10,000 to 10,000,000 years. The floor level for the development has been established at RL 24.25m AHD to accommodate vehicular and pedestrian access from the already constructed Northbourne Drive and as such there is very little flexibility in adjusting this floor level. The PMF level that will apply for the site is RL 26.7m AHD. As it can be seen, the floor level is below the PMF. Whilst there is no Council requirement to set the floor level at or above the PMF, due to the nature and frailty of the residents at the proposed Aged Care Facility, it is generally considered to be not appropriate to allow residents to remain on site during an extreme flood event, even if upper floors are available above the PMF level. This is due to the likelihood that services will be interrupted during an extreme flood and as such care of the residents could not be assured. In addition, it is not considered feasible to have residents evacuate the facility to a location within the overall subdivision, even to a point above the PMF level as the necessary services and medical supplies will not be available in such a location, not to mention the stress associated with having to evacuate from a flood. On the basis of the above, it has been established that evacuation of residents from the site during an extreme flood event will be to another Opal facility where services and medical supplies will be readily available. The evacuation will occur with the assistance of the appropriate authorities in a controlled and orderly manner. The proposed decision to evacuate and evacuation procedure itself has been staged in tiers to escalate and to respond and react to the uncertain nature of flooding in the area. An analysis of the available literature and modelling has found there is ample time for the residents to be evacuated during such an event. A review of relevant documentation has shown the dissemination process for evacuation orders and appropriate evacuation routes and methods. Management actions have been proposed that detail the specific actions and roles that are necessary to ensure the Opal team, together with the SES, can effectively and safely evacuate the residents to a nearby Opal facilities. Whilst it is highly unlikely that the development will be impacted by extreme floods (such as the PMF flood event), if extreme flood events occur, the implementation of adequate warning measures and evacuation procedures will ensure the safety of the occupants of the Aged Care Facility.

Page 3: FLOOD MANAGEMENT PLAN PROPOSED AGED CARE FACILITY ... · Flood Management Plan – Opal Marsden Park 3 Introduction This Flood Management Plan (the Report) has been prepared for Opal

Flood Management Plan – Opal Marsden Park

3

Introduction

This Flood Management Plan (the Report) has been prepared for Opal Aged Care to supplement the Development Application for the proposed Aged Care Facility on Northbourne Drive, Marsden Park. The site is located in a rapidly changing context on the northern extent of a master-planned urban release area as part of the larger North West Growth Centre (Marsden Park Precinct) – the Elara Stockland Residential Community. The site comprises an area of approximately 10,050 m2, with a proposed building footprint of 6,400m2 as well as associated car parking and landscaping facilities.

Figure 1: Proposed Development Site (Six Maps August 2019) (left) & Extract from Stockland Elara Master Plan (right)

The topography of the development site can be described as a slight fall with grades that range generally around 2.0%, ranging to 7.0% in the north. The site is divided into two roughly equal catchments, west and east, the first falling towards the north-west of the property and the second towards the north-east. The west catchment falls and is drained by the stormwater system in Northbourne Avenue, which later drains to a temporary water management basin constructed as part of Stages 27-32 of the Elara subdivision - Temporary basin number 4. The east catchment currently drains to the northeast with run-off generated by this catchment sheeting across the boundary to the east and north. Regionally, the proposed site is located on a ridge of two watersheds, to the east Little Creek and to the north and west South Creek. The proposed development is located within Stages 27-32 of the Elara Subdivision which was submitted for Development Application in June 2017 and was designed by Cardno (Development Application number DA-16-05045). For reference, to the north of the development lies the future street (Thompson Street) to be completed as part of Stage 2 of the Clydesdale Precinct works, these works are currently under construction and were designed by J.Wyndam Prince.

As part of due diligence investigation for the proposed development, it was identified through the use of Blacktown City Council’s BLEP 2015 Maps online that the site is located within the Low Flood Risk Precinct (refer Figure 2 for excerpt and Appendix A for a full-size copy). A subsequent formal request to Blacktown City Council’s Flood Advice Portal confirmed the site lies within Low Flood Risk Precinct of the Little Creek floodplain (refer Appendix B). Preliminary advice from Blacktown City Council noted the site is set a minimum of 0.5m meters above the 100-year mainstream flood level from South Creek and backwater flooding from the Hawkesbury Nepean floodplain.

Page 4: FLOOD MANAGEMENT PLAN PROPOSED AGED CARE FACILITY ... · Flood Management Plan – Opal Marsden Park 3 Introduction This Flood Management Plan (the Report) has been prepared for Opal

Flood Management Plan – Opal Marsden Park

4

Figure 2: Excerpt of Blacktown City Council’s BLEP 2015 Maps online – Flood planning layer As part of the Pre-Lodgement Application meeting held on 19 June 2019 and earlier consultation with Council’s Drainage Engineers, Council identified the need to provide a Flood Management Plan as part of the Development Application submission. The Probable Maximum Flood (PMF) was confirmed to be 26.1m AHD and minuted in the Pre-Application Meeting minutes (PAM) (refer to Appendix C). Flood levels will be further discussed in the Flood Mapping & Data section of the report. The site is located within the Elara subdivision and the flood information submitted as part of the subdivision Development Application (DA-16-05045) was reviewed to determine the context of the flood within the greater development. Reporting and design plans prepared by Cardno generally supported and validated flood information provided by Blacktown City Council. The Pedestrian Evacuation Plan prepared by Cardno indicates the site is well above the 100-year mainstream flood levels from South Creek of 17.30m AHD with freeboard (refer Appendix D). Several reports discussing flooding around the proposed development are available and were referred to in the preparation of the Flood Management Plan, these will be periodically introduced and addressed throughout the report where necessary. The main reports relating to the flood management for the development are listed below:

• (BCCLFP2010) Blacktown City Local Flood Plan a sub-plan of Blacktown City Local Disaster Plan (displan) November 2010.

• (HNVRFS2019) Hawkesbury-Nepean Valley Regional Flood Study 2019.

• (HNFP2015) Hawkesbury Nepean Flood Plan and relevant subplans September 2015.

Page 5: FLOOD MANAGEMENT PLAN PROPOSED AGED CARE FACILITY ... · Flood Management Plan – Opal Marsden Park 3 Introduction This Flood Management Plan (the Report) has been prepared for Opal

Flood Management Plan – Opal Marsden Park

5

The Proposed Development

The site comprises an area of approximately 10,050m2 with a proposed Aged Care Facility and building footprint of 6,400m² as well as associated car parking and landscaping facilities. This land is within Zone R2 and zoned as Low-Density Residential. The proposal is to construct a residential care facility over two levels comprising of 148 aged care beds (high care and dementia-specific beds) as well as associated facilities for the care of residents. The development will be predominantly two storeys with vehicular access from Northbourne Drive to 44 car parking spaces, loading area and a separate porte-cochere access to areas comprising a drop-off area, ambulance parking and bus bay. An architectural concept plan of the proposed development is shown below in Figure 3, a full-size drawing is provided in Appendix E.

Figure 3: Architectural Concept Plan provided by Custance dated 20.09.2019 The proposed ground floor finished level (GFL) of the development is 24.25 AHD. During normal operation, the ground floor is accessible by the main entrance adjacent to Northbourne Drive, a secondary main entrance adjacent to Northbourne Drive and numerous auxiliary entrances around the development for fire egress and servicing. The curtilage surrounding the main access points of the development is characterised as a porte-cochere and “kiss and drop” area with designated parallel parking and ambulance zones. It should be noted the curtilage at this key location has been designed and graded in such a manner to have a continually rising grade from the main access point to the site south-western corner of the site boundary. The site-wide grading is detailed on the stormwater management plans prepared by Henry & Hymas (refer Appendix G).

Page 6: FLOOD MANAGEMENT PLAN PROPOSED AGED CARE FACILITY ... · Flood Management Plan – Opal Marsden Park 3 Introduction This Flood Management Plan (the Report) has been prepared for Opal

Flood Management Plan – Opal Marsden Park

6

Flood Context

The site is located in one of the four main identifiable flood plains of the Hawkesbury Nepean Valley area, the Richmond/Windsor/Wilberforce floodplain. The Hawkesbury Nepean Valley has a rather unique feature that dramatically affects the behaviour of floods in the region. The lower reaches of the Hawkesbury Nepean Valley are characterised as narrow angulating sandstone gorges with the upper and middle reaches gentle and wider flood plains. The topography of the lower reaches acts as choke point and causes the floodwaters to back up into the flood plain (HNFP2015). This natural feature causes flood levels well above those typically expected especially in more extreme flood events such as the probable maximum flood (PMF). The HNFP2015 comments on the PMF as “the largest flood event that could conceivably occur at a particular location, usually estimated from the probable maximum precipitation. The PMF defines the extent of flood liable land, that is, the floodplain. It is difficult to define a meaningful Annual Exceedance Probability (AEP) for the PMF but is commonly understood to be in order of 10,000 to 10,000,000 years.” The context and rarity of the flood should also be noted, with the BCCLFP2010, indicating Probable Maximum Precipitation (PMP) in the Hawkesbury-Nepean Valley and the resulting PMF is estimated to have one in 100,000 chance each year of occurring. The HNFP2015 attributes, a similar, and comparatively rare recurrence interval for the event and notes the event as 1 in 45,000 chance in each year. The context for the proposal for vulnerable facilities within the Hawkesbury-Nepean should also be noted. The proposed development is not unique, with Volume 2 of the HNFP2015 noting that several hospitals, numerous schools as well as 18 residential aged care facilities are located, and currently in operation, in the Hawkesbury Nepean Valley.

Flood Mapping, Levels and Data

As the site is subject to backwater flooding from the Hawkesbury Nepean floodplain during the PMF event, and at the direction of Council Drainage Engineers the regional flood study prepared for Infrastructure NSW, the Hawkesbury-Nepean Valley Regional Flood Study 2019 (HNVRFS2019), was reviewed to ascertain key information regarding the flood inundation.

Due to the scale of the study, a limited number of key points of interest were produced to output detailed data regarding the time to rise, rate of rise, and time to subsidence (as well as further more detailed information). The closest location for which detailed data from the study was produced is on South Creek at Richmond Road crossing, which when considering the size of the Hawkesbury Nepean watershed, lies in relatively close proximity to the proposed development (approx. 1350m). The location of the site in relation to the proposed development can be seen in Figure 4 adjacent. Considering the site is subject to potential backwater flooding from the Hawkesbury River, the site’s location downstream of the proposed development is ideally situated to represent the development, with any data relating to the rise of the floodwater having an inherent inbuilt conservatism. For the purpose of the Flood Management Plan data recorded at the South Creek, Richmond Road crossing will be deemed representative of the development.

Figure 4: Location of the data point in relation to the development

Page 7: FLOOD MANAGEMENT PLAN PROPOSED AGED CARE FACILITY ... · Flood Management Plan – Opal Marsden Park 3 Introduction This Flood Management Plan (the Report) has been prepared for Opal

Flood Management Plan – Opal Marsden Park

7

From a review of Volume 3: Map Book Part B: Flood extents, depths and contours, it was that the site remained outside of the floodplain up to and in excess of the 0.02% AEP (1 in 5000 year) event (refer below Figure 5 and Map 10 of Appendix F). The 0.02% AEP flood level at the closest data point to the development was recorded to be 22.6m AHD.

Figure 5: 0.02% AEP Flood Extent and Depths. HNVRFS2019, Volume 3: Map Book.

Further review of the flood mapping data provided in the HNVRFS2019 flood study confirmed the site would be inundated during a PMF flood event. The PMF flood level provided in HNVRFS2019 flood study for the closest data point to the development was recorded to be 26.7m AHD, slightly higher than that of the PMF provided and confirmed by Blacktown City Council. Additionally, it should be noted both the local and regional flood plan presents a PMF level of 26.4m at Windsor Gauge. Proposed PMF flood event levels for each of the relevant reports and data sets are presented below: The Probable Maximum Flood (PMF) level provided by Blacktown City Council = 26.1m AHD The Probable Maximum Flood (PMF) level provided by HNVRFS2019 = 26.7m AHD The Probable Maximum Flood (PMF) level provided by HNFP2015 & BCCLFP2010 = 26.4m AHD For the basis of this Flood Management Plan, the most conservative PMF flood level of 26.7m AHD is adopted. The HNVRFS2019 flood extent and depth mapping displaying the adopted PMF flood event is displayed below, in Figure 6 and Appendix F. It should be noted all proposed PMF flood levels, given the proposed floor level of RL 24.25m AHD, significant inundation of the ground floor would occur.

Proposed Development Location

Page 8: FLOOD MANAGEMENT PLAN PROPOSED AGED CARE FACILITY ... · Flood Management Plan – Opal Marsden Park 3 Introduction This Flood Management Plan (the Report) has been prepared for Opal

Flood Management Plan – Opal Marsden Park

8

Figure 6: PMF Flood Extent and Depths. HNVRFS2019 ,Volume 3: Map Book.

Hazard

Flood hazard represents the impact that flooding would have on people, vehicles and buildings and is usually represented by a combination of depth and velocity of the floodwaters. Considering the most conservative PMF level available of 26.7m AHD, the primary mode of flooding and the proposed finished floor level (RL 24.25m AHD) it is understood the hazard class of floodwaters around the development, under the technical flood risk management guideline: flood hazard, is H5 -Unsafe for vehicles and people. All building types vulnerable to structural damage. Some less robust building types vulnerable to failure.

Rate of Rise and Duration

The rate of rise as presented in the regional flood plan during the PMF event is 0.5m/hour with the possibility of 0.7m/hour for more condensed PMF storm events i.e. 24hr PMF. This is generally supported in the HNVRFS2019 with rate of rise plots presented for the nearest data point having an upper limit during extreme flood events of up to 0.49m/hour. Considering the “standing” water level at the crossing location is approx. 7.4m AHD and the proposed development floor level is 24.25m AHD, floodwaters would need to rise 16.85m to impact the development’s ground floor level (GFL). The duration until the inundation of the ground floor from the beginning of a given PMF event is calculated below for each of the rate of rise figures presented in relevant reports: Duration till inundation of GFL under HNFP2015 & BCCLFP2010, assuming 0.7m/hour equals 24.07 hours Duration till inundation of GFL under HNVRFS2019, assuming 0.49m/hour equals 34.38 hours For the basis of this Flood Management Plan the conservative rate and rise and duration of 0.7m/hour and 24.07 hours were adopted.

Proposed Development Location

Page 9: FLOOD MANAGEMENT PLAN PROPOSED AGED CARE FACILITY ... · Flood Management Plan – Opal Marsden Park 3 Introduction This Flood Management Plan (the Report) has been prepared for Opal

Flood Management Plan – Opal Marsden Park

9

Emergency Response Philosophy

This Flood Management Plan recognises that protection of life is of critical and upmost importance. In order of importance, the protection of all lives takes priority, with the comfort of staff and patrons second and the protection of the property is third. The applicant proposes that a core concept of the emergency response philosophy is the offsite relocation of residents to neighbouring Opal facilities or other suitable health care facilities. This is due to a variety of reasons, namely:

• Occupants: Due to the nature of occupants in aged care facilities, the occupants demand a high level of specialised care that is unlikely to be provided at temporary shelters or evacuation centres.

• Utilities: The severity of the storm will have a detrimental effect on local infrastructure and likely diminish the facilities functionality. Services such as water, electricity and sewerage are expected to be unavailable for a prolonged period of time. Given the level of care required for occupants this disruption to vital utilities is unacceptable. For instance, the HNFP2015 predicts the following impact on local services following a PMF level flood event In the Richmond/Windsor/Wilberforce floodplain:

o All electrical supply to the flood area and surrounds lost for up to 3 months or more. o Telecommunication services will be cut to some areas for between 2 to 4 weeks. After this would

be reliant on emergency generator power for 3 to 5 months more. o Sewerage treatment plants will be inoperable and raw sewerage will be discharged into the river.

Estimated 6 months to repair system. This poses a hazardous environment to high care residents of the development.

o There may be no gas supplies west of the river for around 3 months. o Loss of water to some areas. Pump stations flood water still available under restrictions.

• Location: The Elara subdivision as currently constructed, and due to the layout of the immediate road system, has the potential to become isolated from major evacuation routes during the PMF event. This will be discussed in more detail in the Response and Relocation section.

The BCCLFP2010 notes the practice of evacuation of residents to alternative locations other than evacuation shelters, stating in section 3.20.29 Sector Commanders will direct evacuees who require accommodation or welfare assistance to designated evacuation centres. Evacuees who have their own accommodation arrangements will not be directed to Evacuation Centres. It is proposed Opal Backtown Village will be used as a crisis centre where residents from Marsden Park would be taken in the event of being evacuated from site. From this location the residents would be relocated to other Opal Villages, other providers or depending on time frames to family members or home care. The location of the crisis centre at Opal Blacktown was selected due to the proximity of the village to the proposed facility, the short and simple route connecting the facilities, the flood free nature of the facility and its central location within Sydney.

Page 10: FLOOD MANAGEMENT PLAN PROPOSED AGED CARE FACILITY ... · Flood Management Plan – Opal Marsden Park 3 Introduction This Flood Management Plan (the Report) has been prepared for Opal

Flood Management Plan – Opal Marsden Park

10

Response and Relocation

The governing flood plans for the development are listed below:

• (BCCLFP2010) Blacktown City Local Flood Plan a sub-plan of Blacktown City Local Disaster Plan (displan) November 2010

• (HNFP2015) Hawkesbury Nepean Flood Plan and relevant sub plans September 2015 The response section of the report aims to present a relocation strategy for the residents of the proposed development that adheres to the governing local and regional flood plans and responds to unique flooding characteristics of the flood area. To better interface with the local flood plan and provide the response is broken down into the following subheadings:

• Proposed Route

• Decision to Evacuate

• Evacuation Warning/Order Delivery

• Withdrawal

• Relocation

• Return

Proposed Route

Proposed evacuation routes for Hawkesbury Nepean flood plan are detailed in Volume 3 of the HNFP2015 - Hawkesbury-Nepean valley: NSW SES Flood Evacuation routes, Traffic and transportation arrangement. Map 1 shows the regional evacuation routes within the Hawkesbury Nepean Valley and is included in Appendix H. The proposed evacuation route for the development considering its location within South Creek B (Marsden Park) sector is the Blacktown/Richmond Road evacuation route. The route is shown yellow in Figure 7 below. The exit point for route is located at the intersection of Richmond Road and Quakers Hill parkway. From this point normal traffic management arrangements apply.

Figure 7: Evacuation route: Richmond/ Blacktown Route, HNFP2015

Page 11: FLOOD MANAGEMENT PLAN PROPOSED AGED CARE FACILITY ... · Flood Management Plan – Opal Marsden Park 3 Introduction This Flood Management Plan (the Report) has been prepared for Opal

Flood Management Plan – Opal Marsden Park

11

The designated flood evacuation route is one of several main flood evacuation routes for the Windsor Downs and Londonderry flood evacuation sectors. As with many of the flood evocation routes in the Hawkesbury Valley, the proposed route is potentially subject to inundation from rising floodwaters as flood events progressively become more extreme. Volume 3 of the HNFP2015 notes as a result of the low point at South Creek Bridge crossing the lower portion of the route is cut by mainstream flooding at a level of 14.05m at the Windsor Gauge. However this does not affect the proposed evacuation route of the development as the Elara Subdivision is located south of the bridge and proceeds south towards Blacktown municipality. To provide context, 14.05m at the Windsor gauge is representative of a flood event between the 2% and 5% AEP (1 in 50 and 1 in 20 chance per year respectively). As the flood evacuation route is the primary route for the lower-lying areas of the floodplain, an in-depth investigation was undertaken to ascertain if any locations of the proposed evacuation route are subject to flooding following the closure of the lower portion of the flood evacuation route. The investigation noted a single location where rising floodwater inundated the proposed evacuation route. From Volume 3: Map Book of the HNVRFS2019, the next low point subject to flooding in the Richmond/Windsor/Wilberforce floodplain is immediately following egress from the Elara subdivision at the intersection of Elara Boulevard and Richmond Road. Inundation of the egress path was determined to occur at some event between the 0.1% AEP and 0.05% AEP event between the flood levels 20.6m AHD and 21.7m AHD respectively, refer Figure 8 and 9 below. A review of levels of Richmond Road validates the flood maps with the lowest road level measured in this area reading approx. 21.20m AHD. A review of Hazard Maps in the 0.05% AEP flood event shows the flood hazard category as H3 & H4, in both instances unsafe for vehicles and people. It should be noted the egress location from the Elara subdivision is approximately 1.4km into the evacuation route when coming from the proposed development. Following the Elara Subdivision egress path, investigation of HNVRFS2019 flood mapping did not determine any further locations of inundation on the designate flood route. The primary evacuation route to Opal Balcktown facility is shown on Figure 10. It should be noted past Richmond Road alternative routes via the Westlink M7 area available.

Figure 8 & 9: 0.1% AEP Flood extent and Level (left), 0.05% AEP Flood Extent and Level (right), HNVRFS2019.

Page 12: FLOOD MANAGEMENT PLAN PROPOSED AGED CARE FACILITY ... · Flood Management Plan – Opal Marsden Park 3 Introduction This Flood Management Plan (the Report) has been prepared for Opal

Flood Management Plan – Opal Marsden Park

12

Figure 10: Example primary evacuation route and relocation destination (Opal Blacktown)

Decision to Evacuate

As noted in the local flood plan the decision to evacuate will be controlled by the SES, the following section presents recommendations on the decision to evacuate based on the context of flooding in the area and in the response of the nature and needs of the proposed development’s occupants. Evacuations for the Blacktown Municipality will be conducted on two levels:

• Level 1: Evacuations of areas inundated or at threat of isolation by floods less than about the 15.0m level at the Windsor Gauge. The SES Local Controller controls these evacuations. To give this context when comparing the 15.0m level to the probabilities noted in Volume 2 of the HNFP2015 the probability of this event is comparable to the 2% AEP (1 in 50 chance per year) at 15.7m AHD.

• Level 2: Evacuations of areas threatened by floods of higher levels. It is expected that if such evacuations are required, the Hawkesbury Nepean Flood Emergency Sub Plan will be activated and evacuations throughout the valley will be co-ordinated centrally from the SES Sydney Western Region Headquarters. The evacuation for this proposed development will fall under Level 2 evacuation.

One issue that often arises in relation to flooding and evacuation is at what point in time evacuation should occur. In order to determine a suitable point to evacuate and to monitor the progression of the flood event a datum time is required. On this background, the BCCLFP2010 designates that the “Start Time” will be based on the time the Hawkesbury River reached, or is expected to reach, a prescribed level (6m) on the Windsor Gauge. At this point numerous supporting plans will be requested to be activated, these include traffic and transport procedures, however more importantly to this Flood Management Plan of the NSW Health Plan. The significance of this will be discussed in later chapters.

Page 13: FLOOD MANAGEMENT PLAN PROPOSED AGED CARE FACILITY ... · Flood Management Plan – Opal Marsden Park 3 Introduction This Flood Management Plan (the Report) has been prepared for Opal

Flood Management Plan – Opal Marsden Park

13

HNVRFS2019 flood mapping was investigated to determine a relationship between the local flooding data point (South Creek) and the Windsor Gauge. For floods in excess of 20% AEP event flood levels at the two locations were recorded to be equal. This is a result of the governing flood mode been backwater flooding, on this basis, it is comparable and possible to link the river level at Windsor bridge gauge directly to the flood level encroaching on the proposed egress from Elara subdivision as water levels at the two locations will rise equally during a given event. As a result of this link the decision to evacuate can be primarily based on when the Hawkesbury River reached, or is expected to reach, a prescribed level on the Windsor flood gauge. This is an ideal arrangement as the Windsor Gauge will be heavily monitored by emergency services, is automatic (with manual backup), provides forecasting service to upstream and downstream gauges and is synchronised with the Bureau or Meteorology and NSW SES via flood intelligence cards. Example %AEP storm events in relation to Hawkesbury river levels at Windsor bridge gauge are presented in Table 1 adjacent.

Table 1: %AEP (Chance per year) compared with River level at Windsor Bridge Gauge, HNFP2015.

The Elara Subdivision’s main egress path becomes inundated at RL 21.20m AHD, the rate of rise as presented in the HNFP2015 during the PMF event is 0.5m/hour with the possibility of 0.7m/hour for larger storm events. This is generally supported in the HNVRFS2019 with rise of rate plots presented for the nearest data point having an upper limit during extreme flood events of up to 0.49m/hour. Utilising a conservative estimate of 0.7m/hour for a given rate of rise a connection between the time until the egress path becomes inundated, and Windsor gauge levels can be established, this is presented in tabular form below, refer Table 2.

Hours until inundation of egress path (hrs)

Estimate level at Windsor Gauge M (AHD)

0 21.2 1 20.5 2 19.8 3 19.1 4 18.4 5 17.7 6 17 7 16.3 8 15.6 9 14.9

10 14.2 11 13.5 12 12.8 13 12.1 14 11.4 15 10.7 16 10 17 9.3 18 8.6 19 7.9 20 7.2

Table 2: Relationship between Windsor Gauge and time remaining until inundation of egress path.

Page 14: FLOOD MANAGEMENT PLAN PROPOSED AGED CARE FACILITY ... · Flood Management Plan – Opal Marsden Park 3 Introduction This Flood Management Plan (the Report) has been prepared for Opal

Flood Management Plan – Opal Marsden Park

14

As noted in earlier in the context section of the flooding report, hospitals and aged care facilities are currently in operation in the Hawkesbury-Nepean Valley. Volume 2 of the HNFP2015 notes the some of there facilities including Hawkesbury Hospital will require evacuation when floods are predicted to reach around 16m AHD at the Windsor Gauge. Using a similar evacuation threshold of 16m AHD on the Windsor Gauge, this would translate to a minimum of 7.4 hours to evacuate residents beyond the point of egress from the Elara subdivision. To give context, the 16m AHD on the Windsor Gauge is representative of the peak flood level of a 1.67% AEP (1 in 60 year) flood event. As noted in the local flood plan, the decision to evacuate will be controlled by the SES, if the SES were to issue evacuation of the Facility when the 1% AEP peak flood level was reached on the Windsor Gauge, the total time for evacuation past the egress point would be reduced to a minimum of approximately 5.6 hours. It should be noted the egress location from the Elara subdivision is approximately 1.4km from the proposed development. The regional flood plan notes in Volume 1: section 7.28.4, due to the long lead time required to mobilise the required resources the NSW SES Sydney western region incident controlled will provide an early notice if any of the following facilities may need to be evacuated; aged, disability and residential care facilities. As noted the evacuation warning (refer below) will be delivered to take into account the sufficient time required to prepare the Facility and ensure the Facility is prepared for the order to evacuate (refer below) when required. On this basis, the applicant proposes suitable preparation, mobilisation and evacuation times based of past experience with emergency evacuations and a general understanding of their resident’s needs and constraints. It is suggested during the construction certificate phase of the development the proposed strategies are reviewed in conjunction with the following actors and branches of the SES to ensure evacuation procedures between the two parties are co-ordinated:

• SES Sydney Western Region Controller

• SES Operations Controller

• Representative of the Health Services Functional Area

• Representative of the Transport Services Functional Area

The proposed decision to evacuate, and evacuation procedure itself, is proposed to be staged in tiers to escalate and to respond and react to the uncertain nature of flooding in the area. From close consultation with Opal’s Emergency Planning Committee the maximum time to prepare, mobilise and evacuate residents for a development of this nature and size was conservatively estimated to be 14 hours in duration. A graphical representation of a typical tiered evacuation strategy for the proposed development is provided below in Figure 11.

Page 15: FLOOD MANAGEMENT PLAN PROPOSED AGED CARE FACILITY ... · Flood Management Plan – Opal Marsden Park 3 Introduction This Flood Management Plan (the Report) has been prepared for Opal

Flood Management Plan – Opal Marsden Park

15

Figure 11: Graphical representation of typical tiered evacuation strategy for the proposed development.

Page 16: FLOOD MANAGEMENT PLAN PROPOSED AGED CARE FACILITY ... · Flood Management Plan – Opal Marsden Park 3 Introduction This Flood Management Plan (the Report) has been prepared for Opal

Flood Management Plan – Opal Marsden Park

16

Mobilisation & Evacuation Warning & Order Delivery

As noted in the BCCLFP2010 – Section 3.20.17 The SES Sydney Western Region Controller will mobilise the required number of buses for Sectors via the Transport Services Functional Area Coordination Centre. Volume 3, Chapter 2 of the HNFP2015 - Transport Management and Arrangements states, the Transport Services Functional area will coordinate the provision of bus transport resources including buses in support of evacuation. This includes assisting the Health Service Functional Area in the evacuation of nursing homes, aged care facilities and hospitals (especially noting that health facilities would generally require more specialised transportation than buses). The Transport Services Functional Area will liaise with the Health Services Functional Area to consider and act on the advice of the NSW SES with regard to the warning and evacuation of hospitals, private hospitals and residential aged care facilities. Volume 3 of HNFP2015 notes inbound traffic will be allowed into the area until the NSW SES Sydney Western Region Incident Controller determine that inbound traffic ceases. At that time access to the route is being denied to all traffic except emergency vehicles, buses (differentiation between private and public not specified) being used for evacuation and supporting services. As the evacuation route will be in operation prior to the decision to evacuate the proposed facility, as a result of lower-lying areas been evacuated first, it is possible inbound traffic for private vehicles could be halted at the entrance. To avoid delays in the provision of transportation to the facility it is recommended the facility is evacuated as per the local and regional plan notes, via the Transport Services Functional area and Health Services Functional Area under the supervision of the SES. The BCCLFP2010 - Section 3.20.18 notes, the SES will advise the community of the requirements to evacuate. The SES will issue an Evacuation Warning when the intent of an SES Operations Controller is to warn the community of the need to prepare for a possible evacuation. A sample warning with the information delivered provided in Appendix I. If the evacuation warning does not fit the location and details listed in the plan (this report) the address of the selected nearby Opal facility (Blacktown) or required evacuation time estimated by Opal’s Emergency Planning Committee (14hrs), the SES should be notified immediately. During the period where an evacuation warning has been issued, Opal's management team are to coordinate with the SES to prepare the residents to evacuate. Due to the long lead time required to mobilise the required resources, the NSW SES Sydney Western Sydney Region Incident Controller will provide an early notice if aged, disability and other residential care facilities need to be evacuated (HNFP2015). The BCCLFP2010 - Section 3.20.18 notes, the SES will issue an Evacuation Order when the intent of the SES Operations Controller is to instruct a community to immediately evacuate in response to an imminent threat. A sample evacuation order is provided in Appendix I. If the evacuation warning does not fit the location and details listed in the plan (this report) the address of the selected nearby Opal facility (Blacktown) or required evacuation time estimated in the report (refer Table 2), the SES should be notified immediately. Evacuation warnings will be decimated via a wide variety of mediums including television and radio broadcasting, fax, internet, public announcements as well as warnings and updated distributed to media outlets and emergency services. Of particular interest to the development is the early warning network, which when subscribed will send alerts to mobile devices and door knocking teams. In regards to door knocking teams, the BCCLFP2010 notes in section 3.20.24-26, Sector Command Centres, where established, will distribute Evacuation Warnings and Orders via Emergency Service personnel in doorknock teams to areas under threat of inundation. Field teams conducting doorknocks will record and report back the following information to their Sector Commander: Addresses and locations of houses doorknocked and/or evacuated, the number of occupants: details of support required (such as transport, medical evacuation). It is recommended a liaison for the SES remains on-site to aid Opal management in the preparation and evacuation of its occupants.

It is generally understood that residents of the facility will require a high level of care and this should be reiterated with the SES personnel upon first communication. Once the facility has received the evacuation warning, it will be the responsibility of Opal management, specifically the Emergency Co-ordinator, to start implementing the flood

Page 17: FLOOD MANAGEMENT PLAN PROPOSED AGED CARE FACILITY ... · Flood Management Plan – Opal Marsden Park 3 Introduction This Flood Management Plan (the Report) has been prepared for Opal

Flood Management Plan – Opal Marsden Park

17

management plan and prepare for evacuation. When the evacuation order is received it will involve a group of predetermined and appropriately trained people ensuring that the occupants leave the facility in an orderly manner.

Withdrawal

As noted in the BCCLFP2010, evacuations will generally be done in stages starting from the lowest areas and moving progressively to higher areas. Upon reception of evacuation, the South Creek Sector B Sector commanders will manage the evacuation of the facility and its occupants up until the entrance to the designated regional road evacuation route. During the mobilisation and flood warning phase, the Health Services Functional Area and Transportation Functional Area will be informed by the SES of the evacuation requirements of the occupants in terms of transportation and medical assistance. Additionally, the facility will have been given evacuation warning sufficient time in advance to prepare the residents for transportation. Transportation provided by the Transportation Functional Area will arrive and residents are to be loaded into the transportation. Transportation will proceed under the supervision of the sector commander to the entrance of the evacuation route at the Elara subdivision egress path. Transportation will proceed along the designated evacuation route under predetermined traffic management arrangements to the route exit points under the supervision of the Health Services Functional Area and Transportation Functional Area. The transportation will exit the evacuation route point along Richmond Road and proceed along the suburban road network to one or a number of nearby

Opal facility.

As per the recommendations of the BCCLFP2010 under the direction of the SES (or other emergency authorities), Opal's emergency management team (listed below) will facilitate for the care of its occupant's and co-ordinate evacuation procedure along the predetermined evacuation route to a nearby Opal facility.

Relocation

It is proposed Opal Blacktown Village is used as a crisis centre where residents from Marsden Park would be taken in the event of being evacuated from site. From this location the residents would be relocated to other Opal Villages, other providers, or depending on time frames to family members or home care. The location of the crisis centre at Opal Blacktown was selected due to the proximity of the facility to the proposed facility, the short and simple route connecting the facilities.

Opal is currently operating over 20 aged care villages in the greater Sydney region with numerous additional homes throughout New South Wales. It is understood many of the Opal facilities operating in the area are flood free and accessible given the main evacuation routes documented in the HNFP2015, Appendix H. The larger facilities and closer in proximity include, and are not limited to:

• Winston Hills - 226 Windsor Rd, Winston Hills NSW 2153

• Quakers Hill - 35 Hambledon Rd, Quakers Hill NSW 2763

• Blacktown - 37 Kildare Rd, Blacktown NSW 2148 Following emergency evacuation from the proposed development to the Opal Blacktown Village, residents of the proposed facility are proposed to be relocated to several different Opal facilities where specialist care and attention can be provided to the residents. The residents are proposed to be relocated till such a date where the proposed facility can be ensured safe and functional, refer section Return below. Additionally, it is generally understood that Opal’s villages have a memorandum of understanding with other aged care providers in regards to the temporary housing of residents during emergency situation. This was noted during the potential bushfire at Opal Springwood Village, where residents were relocated to other local providers when evacuated under the threat of bushfire. Furthermore, subject to the duration of utilities disruption at and around the proposed facility the applicant notes the possibility of housing residents with relatives and family members under the support of a Home Care Package, in which Opal staff will attend the homes of the sponsors to provide decentralised care to the residents.

Page 18: FLOOD MANAGEMENT PLAN PROPOSED AGED CARE FACILITY ... · Flood Management Plan – Opal Marsden Park 3 Introduction This Flood Management Plan (the Report) has been prepared for Opal

Flood Management Plan – Opal Marsden Park

18

Return

Once it is considered safe to do so, the SES Local Controller will authorise the return of evacuees to their normal or alternative place of residence. The decision will made in consultation with the Health Services Functional Area, and with the input of the Transport Services Functional Areas. The Transportation Services Functional Area will be responsible for the provision of transportation to return residents to the facility.

In the event that the building is damaged by the flood and the building is unable to be resided in, residents are to remain off-site in nearby Opal facilities (as noted in the Relocation chapter). The final decision to return to the proposed facility will be at the discretion of Opal management and consider the following:

• Access to facility is to be confirmed.

• Sewerage systems and sanitation systems are functional.

• Suitable contamination testing is performed and confirmed safe.

• Plumbing and gas services are functional.

• Electrical services are functional.

• Cleaning and repairs are to be carried out as required depending on the extent of flood damage.

Roles and Responsibilities

The following groups and individuals are responsible for the maintenance and implementation of this flood management plan in accordance with their roles and responsibilities as set out in the Opals general emergency protocols:

• Emergency Planning Committee

• Opal Marsden Park General Manager

• Opal Marsden Park Emergency Control Organisation

• Emergency Coordinator / Chief Warden

• Deputy Emergency Coordinator / Deputy Chief Warden Key emergency actions and roles are addressed in the following management actions section.

Management Actions

The following are management actions specific to flooding on the Opal Marsden Park Site. These are in addition to the general actions set out in the Opal’s general emergency protocols. The general actions in the other documents include actions with regards to induction and training, document control, plan revision and communication protocols. Management actions are divided into three main categories:

• Passive Actions - Prior to flood/ Preparation Phase: to be maintained at all times during the operation of the development.

• Response Phases o Monitoring and preparing/ During a potential flood event/Early flood event/ Evacuation warning

issued by SES. o During ‘evacuation level’ flood event/Evacuation Order issued by SES/ prescribed level on

Windsor Flood Gauge is meet 11.4m AHD/ 1 in 10 peak flood level reached.

• Recover Phase: After a flood.

Page 19: FLOOD MANAGEMENT PLAN PROPOSED AGED CARE FACILITY ... · Flood Management Plan – Opal Marsden Park 3 Introduction This Flood Management Plan (the Report) has been prepared for Opal

Flood Management Plan – Opal Marsden Park

19

Passive Actions - Prior to Flood/Preparation Phase

No trigger required - constant

• Subscribe the General Manager, Emergency Co-ordinator and Deputy Emergency Co-ordinator to a warning alert service, such as the Early Warning Network, which will send alerts of Bureau of Meteorology warnings to their mobile devices.

• Subscribe the General Manager, Emergency Co-ordinator and Deputy Emergency Co-ordinator to SES relevant ‘call-list’, which will send flood alerts to their mobile devices.

• Draft schedule of tiered evacuation strategy to be formed based of recommendations of Opal Emergency Planning committee and coordination with the SES.

• Local SES to be advised and confirm the location and transportation details of proposed evacuation strategy to nearby Opal facility. The Emergency Coordinator is to ensure that the details of the relevant contacts (SES and LEOCon) are located in a prominent location in the Duty Manager’s office. The SES contact number is 132 500.

• Install permanent signage in appropriate locations describing flood risk and evacuation routes within the building and assembly point.

• All staff to be trained in evacuation procedures and refreshed annually.

• Advise SES of the number of residents and their transportation needs if evacuation orders are be issued.

• Duty Manager to confirm emergency capacity of nearby opal facilities and regularly co-ordinate hypothetical relocation numbers with Duty Managers of nearby facilities.

• Residents to be educated of the hazard posed by floods and the evacuation strategy and procedure. This should be undertaken for all new residents and on an ongoing basis thereafter.

Response phase

Monitoring and Preparing/ During potential flood event/ Early flood event/ Evacuation warning issued by SES. Trigger for action: Bureau of Meteorology issues Severe Weather Warning for Metropolitan Sydney OR Severe Thunderstorm Warning for Western Sydney OR Local flood-controlled issue a warning for lesser (level 1) flood OR intense rainfall is observed OR Evacuation warning issued by SES. Actions:

• Emergency coordinator to regularly contact SES for an update on evacuation protocols in the areas. Advise SES of number of potential evacuees and their transportation needs if evacuation order is issued or prescribed level on Windsor flood gauge (11.4m AHD is reached). Confirm likely arrival of transportation if evacuation order is to be issued. Reiterate details of proposed evacuation route and confirm possible acceptance at nearby Opal facilities.

• Emergency coordinator to, based on expected transportation times form a schedule of evacuation with SES representative. Evacuation schedule is to be tiered, focusing on the evacuation of high care residents first. Evacuation schedule is to take into account travel distances to egress path and time required to mobilise high care residents.

• Upon receipt of a severe weather warning, the Emergency Coordinator shall notify all staff, visitors and residents of a potential risk of flood. The warning should be broadcast through the PA system and via door knocking of resident’s rooms. A role call/ headcount should be taken to ensure all residents and staff are accounted for. The visitor book should also be checked to ensure all visitors are accounted for. For each specific major role (please note this list is not exhaustive):

o Emergency Coordinator:

▪ Responsible for all other Supervisors and Duty Manager.

▪ Make initial contact with all Supervisors and Duty Manager.

▪ Stay in regular contact with Supervisors and Duty Manager during a flood event.

Page 20: FLOOD MANAGEMENT PLAN PROPOSED AGED CARE FACILITY ... · Flood Management Plan – Opal Marsden Park 3 Introduction This Flood Management Plan (the Report) has been prepared for Opal

Flood Management Plan – Opal Marsden Park

20

▪ Other responsibilities mentioned above and below.

o Duty Manager

▪ Make initial contact with relevant emergency services and maintain contact during a flood event. Act as emergency coordinators agent for SES.

▪ Liaise with Emergency Coordinator and act on their instructions.

o Kitchen/Catering Supervisor: ▪ Responsible for remaining in contact with Emergency Coordinator and acting on their

instructions. ▪ Undertake headcount of kitchen and catering staff. ▪ Ensure kitchen and catering staff are accounted for. ▪ Advise Nursing Supervisor of residents that are currently using kitchen facilities and

ensure that they are returned to the Nursing Supervisor. ▪ Begin preparation of food and water supply for a six-hour meal cycle. The specific menu

requirements will depend on the time of the day that the flood occurs.

o Nursing Supervisor: ▪ Responsible for remaining in contact with Emergency Coordinator and acting on their

instructions. ▪ Undertake headcount of residents and nursing staff. ▪ Ensure residents and nursing staff are accounted for. ▪ Begin preparation of medical and first aid supplies for a six-hour cycle. The specific

medical requirements will depend on the time of the day that the flood occurs.

o Maintenance Supervisor: ▪ Responsible for remaining in contact with Emergency Coordinator and acting on their

instructions. ▪ Undertake headcount of maintenance staff. ▪ Ensure maintenance staff are accounted for. ▪ Undertake a patrol of the grounds external to the building with a member of the nursing

staff and ensure all residents, staff and visitors are returned to the building. ▪ Begin preparation of maintenance equipment to ensure the building can operate for six

hours.

• Refresh all staff on the provisions of this FMP.

• Ensure all residents are to be bought inside.

• Advise visitors to not leave in order to avoid driving on flooded roads or being caught in heavy traffic. Include visitors into resident evacuation lists and advise SES on the new number of persons.

• Issue SMS and email to residents’ next of kin to advise them that site has been but not to visit until advised due to dangers on approach roads.

• Store or secure all loose items external to the building.

• Keep occupants clear of windows and inside.

• Tune into ABC Radio 702 to following any emergency warnings or instructions.

• Monitor Bureau of Meteorology website for updated weather alerts and approaching rain on radar

• Visually monitor (from inside) parts of property closest to South Creek and little creek for signs of flooding of the property.

Page 21: FLOOD MANAGEMENT PLAN PROPOSED AGED CARE FACILITY ... · Flood Management Plan – Opal Marsden Park 3 Introduction This Flood Management Plan (the Report) has been prepared for Opal

Flood Management Plan – Opal Marsden Park

21

During evacuation level flood event/ evacuation orders issued by SES to Opal Facility/prescribed level on Windsor Flood Gauge is meet 11.4m AHD/ 1 in 10 peak flood level reached. The trigger for action: Local flood-controller issue a warning for 1 in 1000 year flood event (level on Windsor Gauge expected to exceed 21.2m AHD) OR direction given by SES to begin evacuation procedure OR prescribed level on Windsor Flood Gauge is meet 11.4m AHD/ 1 in 10 peak flood level reached.

• If the SES issues the order to evacuate from the site, Duty Manager to remain in constant communication with the SES. The Duty Manager shall convey all information and instructions to the Emergency Coordinator. The Emergency Coordinator in consultation with the Duty Manager is to confirm the location of relocation site, method of evacuation and safest evacuation route with NSW SES, and then inform Supervisors of the necessary details.

• Duty Manager to remain in constant communication with the SES and monitor evacuation warnings and flood levels in the area. If prescribed level is reached without SES notification, duty manager to immediately contact the SES.

• Contact SES to ascertain expected transportation arrival, continue to prepare persons for evacuation, as above.

• Review schedule of evacuation with SES representative and revise if required, as above. Begin evacuations as noted in evacuation schedule. Evacuation schedule is to be tiered, focusing on the evacuation of high care residents first. Evacuation schedule is to take into account travel distances to egress path and time required to mobilise high care residents.

• Duty Manager to confirm nearby Opal Blacktown Village is ready to accept evacuees from Marsden Park facility.

• Prior to moving to the Blacktown Village, Supervisors to perform role call/ headcount to account for all persons. This role call/ headcount should be undertaken again upon the arrival at the Blacktown Village.

• Ensure evacuation staging area (Porte Cochere) is clear and vehicles are moved from evacuation circulation path.

• When transportation arrives Opal management to assist the SES on the loading of residents. Staff are to accompany residents to the nearby Opal facility. Opal staff to monitor condition of residents and advise SES if any special needs are necessary.

• Opal management to assist the SES with the unloading of residents. Staff are to accompany residents to the nearby Opal Facility and aid in settling the residents at the nearby Opal facility.

• Opal staff to monitor condition of residents and advise SES if any special needs are necessary.

• Staff to remain with all persons until the NSW SES advises the situation is all clear.

Page 22: FLOOD MANAGEMENT PLAN PROPOSED AGED CARE FACILITY ... · Flood Management Plan – Opal Marsden Park 3 Introduction This Flood Management Plan (the Report) has been prepared for Opal

Flood Management Plan – Opal Marsden Park

22

Recovery Phase: After a Flood

Trigger for action:

All clear advice from the SES to return to the facility.

• In the event that the building is damaged by the flood and the building is unable to be resided in, residents are to remain off-site in another Opal facility.

• Access to facility to be confirmed.

• Organise for a sewage system to be checked by a licensed contractor and defects rectified.

• The area is to be made free of all contaminates and suitably tested

• Plumbing and gas to be checked by licensed plumber and defects rectified

• Electrical to be checked by licensed electrician and defects rectified

• Cleaning and repairs to be carried out as required depending on the extent of flood damage. This may include property within the building or outside including services. This process should be managed by the relevant Opal maintenance team.

• At satisfaction of Opal management, and pending the successful completion of the above the facility is given the all-clear for residents to return

• Staff and maintenance crews will be reminded to take care as recently flooded surfaces can be slippery and contaminated.

• When transportation arrives to return residents to the facility Opal management is to assist the SES on the loading of residents. Staff are to accompany residents to the facility. Opal staff to monitor the condition of residents and advise SES if any special needs are necessary.

• Opal management to assist the SES with the unloading of residents. Staff are to accompany residents through the facility and aid in settling of the residents.

• Review of each step actioned regardless of outcomes or final flood level

• Review of FMP and amend where required. Review the effectiveness of flood evacuation plan and update if required. If the flood evacuation plan is updated, inform SES of amendments to the plan. All staff are to be informed of an updated flood evacuation plan and retrained as required.

Conclusion

The proposed development is at risk of inundation from extreme flood events, with inundation possibility occurring during the PMF flood event. An analysis of the available literature and modelling has found there is ample time for the residents to be evacuated during such an event. A review of relevant documentation has shown the dissemination process for evacuation orders and appropriate evacuation routes and methods. Management actions have been proposed that detail the specific actions and roles that are necessary to ensure the Opal team, together with the SES, can effectively and safely evacuate the residents to a nearby Opal Facility. Whilst it is highly unlikely that the development will be impacted by extreme floods (such as the PMF flood event), if extreme flood events are to occur, the implementation of adequate warning measures and evacuation procedures detailed above will ensure the safety of the occupants of the Aged Care facility.

Page 23: FLOOD MANAGEMENT PLAN PROPOSED AGED CARE FACILITY ... · Flood Management Plan – Opal Marsden Park 3 Introduction This Flood Management Plan (the Report) has been prepared for Opal

Flood Management Plan – Opal Marsden Park

23

List of Appendices

Appendix A – Blacktown City Council’s BLEP 2015 Maps online. Appendix B – Blacktown City Council Flood information request letter. Appendix C – Pre-DA minutes. Meeting date 19 June 2019. Appendix D – Pedestrian Evacuation Plan, CARDNO Drawing - CardnoUT-CV-ST07-1051. Appendix E– Architectural concept plan A.2000 Revision 20.09.2019. Prepared by Custance. Appendix F – Excerpts of Hawkesbury-Nepean Valley Regional Flood Study, prepared for Infrastructure NSW. Appendix G – Site plan 19459_DA_C001-C102, date 10.10.19 prepared by Henry & Hymas Engineers. Appendix H – Evacuation Routes, BCCLFP2010, Appendix I – Sample Evacuation Orders and Warnings, HNFP2015,

Page 24: FLOOD MANAGEMENT PLAN PROPOSED AGED CARE FACILITY ... · Flood Management Plan – Opal Marsden Park 3 Introduction This Flood Management Plan (the Report) has been prepared for Opal
Page 25: FLOOD MANAGEMENT PLAN PROPOSED AGED CARE FACILITY ... · Flood Management Plan – Opal Marsden Park 3 Introduction This Flood Management Plan (the Report) has been prepared for Opal
Page 26: FLOOD MANAGEMENT PLAN PROPOSED AGED CARE FACILITY ... · Flood Management Plan – Opal Marsden Park 3 Introduction This Flood Management Plan (the Report) has been prepared for Opal
Page 27: FLOOD MANAGEMENT PLAN PROPOSED AGED CARE FACILITY ... · Flood Management Plan – Opal Marsden Park 3 Introduction This Flood Management Plan (the Report) has been prepared for Opal
Page 28: FLOOD MANAGEMENT PLAN PROPOSED AGED CARE FACILITY ... · Flood Management Plan – Opal Marsden Park 3 Introduction This Flood Management Plan (the Report) has been prepared for Opal
Page 29: FLOOD MANAGEMENT PLAN PROPOSED AGED CARE FACILITY ... · Flood Management Plan – Opal Marsden Park 3 Introduction This Flood Management Plan (the Report) has been prepared for Opal
Page 30: FLOOD MANAGEMENT PLAN PROPOSED AGED CARE FACILITY ... · Flood Management Plan – Opal Marsden Park 3 Introduction This Flood Management Plan (the Report) has been prepared for Opal
Page 31: FLOOD MANAGEMENT PLAN PROPOSED AGED CARE FACILITY ... · Flood Management Plan – Opal Marsden Park 3 Introduction This Flood Management Plan (the Report) has been prepared for Opal
Page 32: FLOOD MANAGEMENT PLAN PROPOSED AGED CARE FACILITY ... · Flood Management Plan – Opal Marsden Park 3 Introduction This Flood Management Plan (the Report) has been prepared for Opal
Page 33: FLOOD MANAGEMENT PLAN PROPOSED AGED CARE FACILITY ... · Flood Management Plan – Opal Marsden Park 3 Introduction This Flood Management Plan (the Report) has been prepared for Opal
Page 34: FLOOD MANAGEMENT PLAN PROPOSED AGED CARE FACILITY ... · Flood Management Plan – Opal Marsden Park 3 Introduction This Flood Management Plan (the Report) has been prepared for Opal
Page 35: FLOOD MANAGEMENT PLAN PROPOSED AGED CARE FACILITY ... · Flood Management Plan – Opal Marsden Park 3 Introduction This Flood Management Plan (the Report) has been prepared for Opal
Page 36: FLOOD MANAGEMENT PLAN PROPOSED AGED CARE FACILITY ... · Flood Management Plan – Opal Marsden Park 3 Introduction This Flood Management Plan (the Report) has been prepared for Opal
Page 37: FLOOD MANAGEMENT PLAN PROPOSED AGED CARE FACILITY ... · Flood Management Plan – Opal Marsden Park 3 Introduction This Flood Management Plan (the Report) has been prepared for Opal
Page 38: FLOOD MANAGEMENT PLAN PROPOSED AGED CARE FACILITY ... · Flood Management Plan – Opal Marsden Park 3 Introduction This Flood Management Plan (the Report) has been prepared for Opal
Page 39: FLOOD MANAGEMENT PLAN PROPOSED AGED CARE FACILITY ... · Flood Management Plan – Opal Marsden Park 3 Introduction This Flood Management Plan (the Report) has been prepared for Opal
Page 40: FLOOD MANAGEMENT PLAN PROPOSED AGED CARE FACILITY ... · Flood Management Plan – Opal Marsden Park 3 Introduction This Flood Management Plan (the Report) has been prepared for Opal
Page 41: FLOOD MANAGEMENT PLAN PROPOSED AGED CARE FACILITY ... · Flood Management Plan – Opal Marsden Park 3 Introduction This Flood Management Plan (the Report) has been prepared for Opal
Page 42: FLOOD MANAGEMENT PLAN PROPOSED AGED CARE FACILITY ... · Flood Management Plan – Opal Marsden Park 3 Introduction This Flood Management Plan (the Report) has been prepared for Opal
Page 43: FLOOD MANAGEMENT PLAN PROPOSED AGED CARE FACILITY ... · Flood Management Plan – Opal Marsden Park 3 Introduction This Flood Management Plan (the Report) has been prepared for Opal
Page 44: FLOOD MANAGEMENT PLAN PROPOSED AGED CARE FACILITY ... · Flood Management Plan – Opal Marsden Park 3 Introduction This Flood Management Plan (the Report) has been prepared for Opal
Page 45: FLOOD MANAGEMENT PLAN PROPOSED AGED CARE FACILITY ... · Flood Management Plan – Opal Marsden Park 3 Introduction This Flood Management Plan (the Report) has been prepared for Opal

STAGE 28

STAGE 29

STAGE 30STAGE 31STAGE 32

STAGE 27

RICHMOND ROAD

STAGE 30A

NORT

H

0 50 200

SCALE 1:2500

100 150 250m

@A1

DateRev. Verif. Appd.

Scale

Status

Client

XREF

's: X

-Mas

terpla

n_Lo

tLayo

ut_P2

; X-R

ichmo

ndRo

ad S

tage3

A; X

R-60

0340

-P3-

CI-B

DY; X

R-60

0340

-P3-

C1-P

MF F

LOOD

ZON

E; X

-CO-

Conto

urs-D

esign

-200

0 -St

age 2

7-32

; X-C

O-Co

ntour

s-Des

ign-5

00_S

tages

15-2

0

Drawing Number Revision

DATE

PLO

TTED

: 22 S

eptem

ber 2

016 9

:43 A

M BY

: BRE

NDAN

LARK

IN

Des.

Size

Project

Title

Drawn Date

Checked

Date

Date

DateVerified

Approved

Description

A1

CAD

File:

N:\U

rban

\6000

- 60

99\60

0340

- Ma

rsden

Par

k\5. D

RAW

INGS

\1. B

uild\0

2 Civi

l DA\

13 P

recin

ct 3\D

rawi

ngs\C

ardn

oUT-

CV-S

T07-

1051

-DW

G(1)

.dwg

STOCKLANDELARASTAGES 27-32DEVELOPMENT APPLICATIONPEDESTRIAN EVACUATION PLAN

DATUMAHD

DATE22/09/2016 1:2500

CardnoUT-CV-ST07-1051 1

BML 22/09/2016

KW 22/09/2016

KW 22/09/2016

RPL 22/09/2016

KRW 22/09/2016

Designed

© Cardno Limited All Rights Reserved.This document is produced by Cardno Limited solely for the

benefit of and use by the client in accordance with theterms of the retainer. Cardno Limited does not and shall notassume any responsibility or liability whatsoever to any thirdparty arising out of any use or reliance by third party on the

content of this document.

®

Cardno (NSW/ACT) Pty Ltd | ABN 95 001 145 035Level 9, The Forum, 203 Pacific Highway

St. Leonards, NSW 2065Tel: 02 9496 7700 Fax: 02 9439 5170

Web: www.cardno.com.au1 22/09/2016 PRELIMINARY ISSUE FOR CLIENT REVIEW KW

PRELIMINARYNOT TO BE USED FOR CONSTRUCTION PURPOSES