Upload
tariq-maqsood
View
235
Download
3
Embed Size (px)
Citation preview
7/27/2019 Gen Parallel Operation
1/36
PRODUCT TRAINING
Parallel Operation
7/27/2019 Gen Parallel Operation
2/36
PRODUCT TRAINING
7/27/2019 Gen Parallel Operation
3/36
PRODUCT TRAINING
Parallel Operation - When is it Required?
1. To increase the capacity of available power without loss of
supply to the customers distribution system.
2. To allow the Generator to be connected to a live system ( e.g ;
the Mains, (Grid, Utility,), Multiple Generator systems, C.H.P, etc.
3. To allow shutdown of individual Generators for Maintenance or
repair purposes.
4. To economise operating costs by running multiple generators
according to load demand.
5. To provide an emergency back-up to critical supplies without
loosing power, ( e.g ; Hospitals, Ships, Computer data systems, etc).
7/27/2019 Gen Parallel Operation
4/36
PRODUCT TRAINING
Parallel Operation - Essential Requirements
1. All Generators must have the same voltage.
2. All Generators must have the same phase rotation.
3. All Generators must have the same frequency.
4. All Generators and Prime Movers (Engines), must have similar no
load, to full load, voltage and frequency characteristics.
5. Generator installation must be provided with Synchronising
equipment.
6. Essential protection should include Reverse power, Over-current ,
Over-temperature, Generator Over/Under excitation.
7. Generator of dissimilar design or manufacturer, should have
similar waveform characteristics (harmonics), if Neutrals are joined.
7/27/2019 Gen Parallel Operation
5/36
PRODUCT TRAINING
Parallel Operation - Synchronising AC Generators
Synchronisation is carried out in order to parallel a Generator onto a
live Bus-bar, either in Island mode ( with multiple Generator sets as the
only supply), or to the Utility..
Synchronisation can be achieved Manually, Semi-Automatic with
Check-sync, or by fully automatic P.L.C systems.
Why is Synchronisation of AC Generators necessary ?
7/27/2019 Gen Parallel Operation
6/36
PRODUCT TRAINING
Parallel Operation - Synchronising AC Generators
GEN 2
GEN 1
Consider a simple installation with two Identical Gen-sets, (breakers open circuit).
Normally, one (or more), generators will already be connected to the load, and
supplying power. (GEN 2 is now closed onto the Bus-bar).
DROOP CTAVR
It is also normal that the Generator on line (GEN2) will be running at nominal
frequency (50 or 60 HZ), while the incoming generator (GEN1), can be running at a
higher (NO LOAD), frequency of about 52 or 62 HZ.
AVR DROOP CT
MCB
LOAD
BUS-BARCB1
CB2
7/27/2019 Gen Parallel Operation
7/36PRODUCT TRAINING
Parallel Operation - Synchronising AC Generators
GEN 2
GEN 1
When the relative Engine speeds are different, the Generator waveforms will be
rapidly going in and out of phase with each other.
DROOP CTAVR
AVR DROOP CT
MCB
LOAD
BUS-BARCB1
CB2
Synchronising equipment is required to monitor the Bus Frequency and the
Incoming Generator frequency, to ensure that the Generators are in Synchronism.
Synchronising
Equipment
To correctly Synchronise A.C. Generators, the frequencies must be ALMOST identical.
Frequency (HZ), is the Electrical equivalent of Speed (RPM), which means that the
engine SPEEDS must be ALMOST identical.
7/27/2019 Gen Parallel Operation
8/36PRODUCT TRAINING
EXAMPLE : In this analogy two trucks represent two Generator sets, to be paralleled .
However, if the REAR truck is A FEW RPM FASTER than the FRONT truck, it will
VERY SLOWLY catch up with the truck in front.
SYNCHRONISING is exactly the same process, the RATE OF CHANGE in speed must
be SLOW ENOUGH to allow the BREAKER to close when the Generators are IN PHASE .
If both trucks are travelling at EXACTLY THE SAME SPEED, they will ALWAYS
remain the SAME DISTANCE APART, ( IRRESPECTIVE OF SPEED).
Parallel Operation - Synchronising AC Generators
On-line Generator SetIncoming Generator Set On-line Generator SetIncoming Generator Set
SYNCHRONISED
7/27/2019 Gen Parallel Operation
9/36PRODUCT TRAINING
Parallel Operation - Synchronising AC Generators
GEN 1
GEN 2
Example :- GEN 2 is supplying load and is running at 50HZ (1500 RPM).
GEN 1 is INCOMING, and the engine speed has been adjusted down slightly to
almost 1500 RPM (for example 50.1 HZ).
As there is a SMALL RELATIVE DIFFERENCE between speeds, the Synchronising
equipment should be indicating that the Generators are moving IN and OUT of phase
SLOWLY enough to ALLOW TIME to close the breaker.
50 HZ
(1500 RPM)
50.1 HZ(1503 RPM)
IN PHASE
7/27/2019 Gen Parallel Operation
10/36PRODUCT TRAINING
Parallel Operation - Synchronising AC Generators
GEN 1
GEN 2
50 HZ
50.1 HZ
What will happen if the circuit breaker is closed in the final condition above ?
IN PHASE
Consider above condition:-
The Generator is IN PHASE, , but is now about to go OUT OF PHASE.
180o
OUT OF PHASE
7/27/2019 Gen Parallel Operation
11/36
PRODUCT TRAINING
Parallel Operation - Synchronising AC Generators
GEN 1
GEN 2
The Generator waveforms are 180 OUT OF PHASEwith each other.
180
The transient forces created are both Electrically and Mechanically DESTRUCTIVE
As the breaker closes, GEN 1 will instantly try to reverse the rotation of GEN 2.
This is IMPOSSIBLE, because of the inertia in the Engine/Generator moving parts.The Generators will be INSTANTLY CRASHED into synchronism. .
CR SHEDINTO PH SE
Electrical damage can occur to Diodes, Varistors, and Main Stator windings.
Mechanical damage may also occur to Couplings, Bearings, and Shaft.
7/27/2019 Gen Parallel Operation
12/36
PRODUCT TRAINING
Parallel Operation - Synchronising AC Generators
GEN 1
GEN 2
Example 2 :- GEN 2 is supplying load and is running at 50HZ (1500 RPM).
GEN 1 engine speed has been adjusted to almost 1500 RPM (50.1 HZ).
The Generator waveforms are SLOWLY moving IN and OUT of phase.
50 HZ1500 RPM
50.1 HZ1503 RPM
The circuit breaker can be SAFELY closed in the above condition.
IN PHASE
The Synchronising equipment indicates that the Generator are IN PHASE.
7/27/2019 Gen Parallel Operation
13/36
PRODUCT TRAINING
MCB
LOAD
Parallel Operation - Synchronising AC Generators
GEN 2
GEN 1
The INCOMING Generator should ALWAYS be slightly FASTER than the loaded
Generator. This ensure that the incoming Generator ALWAYS takes a small proportion of
load when the breaker is closed. This will prevent REVERSE POWER protection tripping.
DROOP CTAVR
AVR DROOP CT
BUS-BARCB1
CB2
The Generators are now IN PARALLEL, the next step is LOAD SHARING.
Synchronising
Equipment
When the Synchronising equipment indicates that the incoming Generator (GEN 1) is
IN PHASE with the Bus-bar frequency, the circuit breaker can be safely closed.
OK !
7/27/2019 Gen Parallel Operation
14/36
PRODUCT TRAINING
POWER ( kW )
REACTIVE (kVAr)LEADING
REACTIVE kVArLAGGING
90
ACTIVE CURRENT is the USEFUL CURRENT , which is IN PHASE with the Voltage, and
provides the POWER, or kWATT component of the load.
INDUCTIVE CURRENT is WASTED or WATTLESS CURRENT, which is LAGGING the
Voltage by 90. This is the kVAr component, (POWER FACTOR 0).
ACTIVE CURRENT
p.f 1 (kW)
VOLTAGE
(50 OR 60HZ)
REACTIVE CURRENTLAGGING p.f 0
REACTIVE CURRENTLEADING p.f 0
TIME
VOLTAGE
(50 OR 60HZ)
The VECTORIAL RESULTANT is the kVA , ( APPARENT POWER).
The COSINE of the RESULTANT ANGLE is called the POWER FACTOR ( COS ).
90
CAPACITIVE CURRENT LEADS the Voltage by 90.
COS
COS
Parallel Operation - Load Sharing
REACTIVE CURRENT SHARING is controlled by the GENERATORS, (AVR & DROOP).
7/27/2019 Gen Parallel Operation
15/36
PRODUCT TRAINING
The Brushless AVR controlled Generator has a natural linear voltage DROOPING
characteristic from NO LOAD to FULL LOAD.
0.5% Voltage Regulation for AVR Types MX321, MA325, MA327
1.0% Voltage Regulation for AVR Types MX341
REACTIVE (WATTLESS) CURRENT SHARING
409V
415V
VOLTS
0%
0.5%
1.0%
0% 50% 100%PERCENTAGE LOAD
TO AUTOMATICALLY SHARE REACTIVE LOAD CURRENT, GENERATORS
MUST HAVE SIMILAR NO LOAD TO FULL LOAD VOLTAGE CHARACTERISTICS.
Parallel Operation - Load Sharing
7/27/2019 Gen Parallel Operation
16/36
PRODUCT TRAINING
The PARALLEL DROOP CIRCUIT, provides a signal which allows the AVR to
sense WATTLESS REACTIVE CURRENT, ( ZERO POWER FACTOR ).
At full load 0.8 power factor the voltage DROOP required (single running), is 3%.
This is in addition to the normal (natural) voltage regulation of the AVR, and
allows the DROOP CIRCUIT to automatically control a % of the voltage.
The DROOP SETTING is adjusted on the AVR DROOP CIRCUIT.
A SHORTING SWITCH may be fitted across the DROOP CT for single running.
1.0% (SINGLE)
Parallel Operation - Load Sharing
REACTIVE (WATTLESS) CURRENT SHARING
DROOP kWATT
403 V
415 V
VOLTS
0%
3.0%
0% 50% 100%LOAD AT 0.8 POWER FACTOR
http://localhost/var/www/apps/conversion/tmp/scratch_6/NPT39%20AVR%20DROOP%20CONTROL.ppthttp://localhost/var/www/apps/conversion/tmp/scratch_6/NPT39%20AVR%20DROOP%20CONTROL.ppt7/27/2019 Gen Parallel Operation
17/36
PRODUCT TRAINING
Parallel Operation - Circulating Current
GEN 2
GEN 1
CB1
CB2
EXAMPLE: Two similar 400V Generators are required to operate in parallel
Generator 2 isincorrectlyadjusted to406V (at no load).
GEN 2 is connected to the Bus by closing circuit breaker CB2
400V
406V
MCB
LOADBUS
WHY IS DROOP IS REQUIRED FOR GENERATORS IN PARALLEL ?
AVR 1
AVR 2
SYNCHRONISING
EQUIPMENT
GEN 1 is synchronised with GEN 2, and breaker CB1 is closed
0 LOAD
CB2
CB1
The resultant Bus-Bar Voltage will be approximately average of the two Generators.
403V
403V
403V
7/27/2019 Gen Parallel Operation
18/36
PRODUCT TRAINING
Parallel Operation - Circulating Current
GEN 2
GEN 1
CB1
CB2
MCB
LOAD
GEN 1 EXCITATION SYSTEM is trying to PULL the voltage DOWN to 400 V.
This PRESSURE DIFFERENCE (VOLTS), forces CIRCULATING CURRENT into GEN 1.
AVR
AVR
403V
BUS-BAR
403 V
400V
406V
GEN 2 EXCITATION SYSTEM is trying to PUSH the voltage UP to 406 V.
CIRCULATING CURRENT
The RESULTANT VOLTAGE will be approximately. AVERAGE of the two Generators
CIRCULATING CURRENT is WATTLESS, (POWER FACTOR 0).
WHY IS DROOP IS REQUIRED FOR GENERATORS IN PARALLEL ?
7/27/2019 Gen Parallel Operation
19/36
PRODUCT TRAINING
Parallel Operation - Circulating Current
GEN 2
GEN 1
MCB
LOAD
HIGH LEADING CURRENT ( CAPACITIVE, power factor 0 ) is now flowing INTO GEN 1.
The DROOP CONTROL must REDUCE circulating current to ACCEPTABLE limits.
BUS-BAR
403 V
HIGH LAGGING CURRENT ( INDUCTIVE, power factor 0 ) is now flowing OUT of GEN 2.
CIRCULATING CURRENT
PF
LAG
1 LEADLEAD
PF
LAG
1 LEAD
PF
LAG
LEAD1
PF
LAG
LEAD1PF
LAG
1LEAD
PF
LAG
LEAD1
AVR 1
AVR 2
DROOP CT
DROOP CT
POWER
FACTOR
METERS
CB1
CB2
The MAXIMUM acceptable limit for circulating current is normally 8 %.
7/27/2019 Gen Parallel Operation
20/36
PRODUCT TRAINING
Parallel Operation - Circulating Current
PF
LAG
LEAD1PF
LAG
LEAD1
PF
LAG
LEAD1
GEN 2
GEN 1
MCB
LOAD
AVR 1 receives a signal proportional to the circulating current (LEADING p.f),
which INCREASESthe Generator D.C EXCITATION VOLTAGE.
AVR 1 DROOP CT
BUS-BAR
403 V
CIRCULATING CURRENT
AVR 2 DROOP CT
CB1
CB2
DROOP CT
AVR 2 receives a signal proportional to the circulating current (LAGGING p.f)
which DROOPS (DECREASES), the Generator D.C EXCITATION VOLTAGE.
DROOP CT
AVR 1
AVR 2
POWER
FACTOR
METERS
LEAD
PF
LAG
1 LEAD
PF
LAG
1LEAD
7/27/2019 Gen Parallel Operation
21/36
PRODUCT TRAINING
Parallel Operation - Circulating Current
GEN 2
GEN 1
MCB
LOAD
VR 1 DROOP CT
BUS-BAR
PF
LAG
LEAD1
VR 2 DROOP CT
CB1
CB2
PF
LAG
LEAD1
POWER
FACTOR
METERS
When the MCB is closed, the DROOP CONTROL must also assist in SHARING the
REACTIVE, ( power factor 0 ), component of the LOAD CURRENT.
LOAD CURRENT
DROOP CTVR 1
DROOP CTVR 2
LEAD
PF
LAG
1 LEAD
PF
LAG
1LEAD
PF
LAG
LEAD1
PF
LAG
LEAD1
LOAD403 V
7/27/2019 Gen Parallel Operation
22/36
PRODUCT TRAINING
GEN 2
GEN 1
MCB
LOAD
AVR 1 DROOP CT
BUS-BAR
AVR 2 DROOP CT
kWATT
METER
ACTIVE CURRENT (power factor 1) is the kWATT component of the load, and is
CONTROLLED and SHARED by the PRIME MOVERS (ENGINES).
ENG 2
ENG 1
LEADkW
LEADkW
Parallel Operation - kW Load Sharing
kWATT
METER
LEADkW
LEADkW
The PRIME MOVERS (ENGINES), must have similar NO LOAD to FULL LOAD
GOVERNOR CHARACTERISTICS, in order to share the ACTIVE CURRENT, (PF1).
ACTIVE CURRENT or kW
LOAD
7/27/2019 Gen Parallel Operation
23/36
PRODUCT TRAINING
1500 RPM
1560 RPMSPEED
0%
4.0%
0% 50% 100%PERCENTAGE LOAD
A MECHANICAL ENGINE GOVERNOR REQUIRES A MINIMUM OF 4% SPEED
DROOP IN ORDER TO SHARE THE ACTIVE CURRENT (KW), WHEN IN PARALLEL.
1 HORSE POWER = 746 WATTS , ( OR 0.746 kWATTS .)
HORSE POWER is the mechanical equivalent of kWATTS, (ELECTRICAL POWER).
kWATTS = CURRENT X VOLTAGE X POWER FACTOR ( X 1.732 for 3 phase ).
ACTIVE LOAD CURRENT SHARING, is controlled by the ENGINE GOVERNORS.
Parallel Operation - kW Load Sharing
ACTIVE CURRENT ( kWATT) LOAD SHARING
7/27/2019 Gen Parallel Operation
24/36
PRODUCT TRAINING
ENGINE 2/ 500 H.P
ENGINE 1/ 500 H.P
EXAMPLE : Two Generator Sets are required to run in parallel, both sets have
equal size 500 H.P Engines, with mechanical ENGINE GOVERNORS.
How will ENGINE 1 and 2 share the load AUTOMATICALLY, throughout all load
variations, from NO LOAD to FULL LOAD ?
MCB
LOAD
BUS-BARCB1
CB2
Parallel Operation - kW Load Sharing
7/27/2019 Gen Parallel Operation
25/36
PRODUCT TRAINING
ENGINE GOVERNING
EXAMPLE : In this analogy the truck ENGINE represents the GENSET DIESEL
ENGINE, and the TRUCK represents the GENERATOR.
EngineA.C Generator
Parallel Operation - kW Load Sharing
7/27/2019 Gen Parallel Operation
26/36
PRODUCT TRAINING
ENGINE GOVERNING
LOAD LOAD
EXAMPLE : In this analogy the truck ENGINE represents the GENSET DIESEL
ENGINE, and the TRUCK represents the GENERATOR.
When the truck is UNLOADED, the engine is powering the LOSSES only.
When the truck is LOADED, the engine must provide extra power, and the truck
speed will fall (for example 4% SPEED DROOP), because the ENGINE GOVERNOR is
fixed at constant speed.
What will happen if the trucks are NOW JOINED SOLIDLY TOGETHER??
As with a Genset, the truck engine speed is FIXED, at a constant speed ie.,1500 RPM.
Parallel Operation - kW Load Sharing
7/27/2019 Gen Parallel Operation
27/36
PRODUCT TRAINING
Parallel Operation - kW Load Sharing
ENGINE GOVERNING
The trucks are now JOINED TOGETHER, similar to two GENERATOR SETS when they
are in PARALLEL.
1) Both ENGINES have SIMILAR LOAD CHARACTERISTICS from no load to full load ?
How will the engines SHARE THE LOAD in the following situations ?...
LOAD LOAD
ANSWER - THEY WILL AUTOMATICALLY SHARE THE LOAD - EQUALLY
7/27/2019 Gen Parallel Operation
28/36
PRODUCT TRAINING
Parallel Operation - kW Load Sharing
ENGINE GOVERNING
2) THE TRUCK IN FRONT HAS A STRONGER ENGINE THAN THE ONE AT THE BACK.?
LOADLOAD
ANSWER- THE FRONT ENGINE WILL TAKE LOAD AWAY FROM THE REAR ENGINE.
7/27/2019 Gen Parallel Operation
29/36
PRODUCT TRAINING
Parallel Operation - kW Load SharingENGINE GOVERNING
3) The TRUCK AT THE BACK develops an ENGINE FAULT, and LOOSES POWER ?
LOAD
ANSWER - THE FRONT TRUCK TAKES ALL OF THE LOAD, AND MOTORS
THE REAR TRUCK.
MOTORSMOTORSMOTORSMOTORSMOTORSMOTORSMOTORSMOTORSMOTORS
7/27/2019 Gen Parallel Operation
30/36
PRODUCT TRAINING
ENGINE 2500 H.P
When BOTH Engines have similar GOVERNOR CHARACTERISTICS, they will share
the kW load in parallel, AUTOMATICALLY, from NO LOAD to FULL LOAD.
When the engines have DIFFERENT governor characteristics, (as single running
engines), load sharing will become UNEQUAL as kW load is INCREASED.
ENGINE 1500 H.P
1500 RPM
1560 RPM
ENGINE
SPEED
0% 50% 100%PERCENTAGE LOAD
50% 0%
4.0% SPEED DROOP
Parallel Operation - kW Load Sharing
In above example ENGINE 2 is the STRONGER ENGINE
7/27/2019 Gen Parallel Operation
31/36
PRODUCT TRAINING
ENGINE 2/ 500 H.P
ENGINE 1/ 50 H.P
EXAMPLE: Two different sizes of Generator Sets are required to run in parallel,
Set 1 has a 50 H.P ENGINE, set 2 has a 500 H.P ENGINE.
How will ENGINE 1 know that it must take 10% of the total kW load,
AUTOMATICALLY, from NO LOAD to FULL LOAD ?
MCB
LOAD
BUS-BARCB1
CB2
Parallel Operation - kW Load Sharing
7/27/2019 Gen Parallel Operation
32/36
PRODUCT TRAINING
ENGINE 2500 H.P
When BOTH Engines have similar GOVERNOR CHARACTERISTICS, they will
PROPORTIONALLY share the kW load, AUTOMATICALLY, from NO LOAD to FULL LOAD.
ENGINE 1 should AUTOMATICALLY take 10% of the load throughout all load changes.
ENGINE 150 H.P
1500 RPM
1560 RPM
ENGINE
SPEED
0% 50% 100%PERCENTAGE LOAD
50% 0%
4.0% SPEED DROOP
Parallel Operation - kW Load Sharing
37 kW 370 kW
Parallel Operation kW Load Sharing
7/27/2019 Gen Parallel Operation
33/36
PRODUCT TRAINING
Parallel Operation - kW Load Sharing
ENGINE 2, 500 H.P
ENGINE 1, 50 H.P
Example : Engine 1 (50HP) develops a fault, which causes it to loose speed & power.
What will happen if Engine 1 is running in parallel with Engine 2?
MCB
LOAD
BUS-BARCB1
CB2
Answer; Engine 2 will be supplying ALL OF THE LOAD CURRENT, and feeding
back ACTIVE CURRENT (kWATTS) INTO GEN 1.
ACTIVE CURRENTGEN 2
GEN 1
GEN 1 has now become a MOTOR, DRIVING ENGINE 1.
REVERSE POWER.
WHAT IS REVERSE POWER ?
MOTOR
This is REVERSE POWER, and can severely DAMAGE the ENGINES.
Parallel Operation kW Load Sharing
7/27/2019 Gen Parallel Operation
34/36
PRODUCT TRAINING
ENGINE 2, 500 H.P
ENGINE 1, 50 H.P
REVERSE POWER can occur :-
1. NO LOAD - following synchronisation, if the INCOMING Engine speed is lower than
the BUS BAR speed/frequency.2. ON LOAD - if a FAULT occurs on one of the Engines, causing it to LOOSE POWER,
or if the Governor is INCORRECTLY ADJUSTED relative to the other Generators.
MCB
LOAD
BUS-BARCB1
CB2
GEN 2
GEN 1
The Generator should be DISCONNECTED from the system to avoid damage.
ACTIVE CURRENT
REVERSE
POWER
PROTECTION
THIS IS ACHIEVED WITH REVERSE POWER PROTECTION
MOTOR
Parallel Operation - kW Load Sharing
P ll l O ti kW L d Sh i
7/27/2019 Gen Parallel Operation
35/36
PRODUCT TRAINING
How can kW Load sharing be achieved WITHOUT SPEED DROOP?, i.e., constant
speed from no load to full load?
Answer : The Engines must be fitted with ISOCHRONOUS ELECTRONIC GOVERNORS.
MCB
LOAD
BUS-BARCB1
CB2
ISOCHRONOUS
GOVERNOR kW FEEDBACK
ISOCHRONOUS
GOVERNOR kW FEEDBACK
ACTIVE CURRENT
ISOCHRONOUS
GOVERNOR kW FEEDBACK
ISOCHRONOUS
GOVERNOR kW FEEDBACK
kW LOAD SHARING (kW), is achieved by GOVERNOR CONTROL from a kW feedback
signal, which automatically controls the kW LOAD SHARING.
Parallel Operation - kW Load Sharing
7/27/2019 Gen Parallel Operation
36/36
PRODUCT TRAINING
RETURN TO MAIN MENU
POWER FACTOR CONTROLLER PFC3
PARALLEL DROOP CIRCUIT
http://localhost/var/www/apps/conversion/tmp/scratch_6/NPT01%20MAIN%20MENU%20.ppshttp://localhost/var/www/apps/conversion/tmp/scratch_6/NPT39%20AVR%20DROOP%20CONTROL.ppthttp://localhost/var/www/apps/conversion/tmp/scratch_6/NPT49%20PFC3%20+%20RCI.ppt