Gen Parallel Operation

Embed Size (px)

Citation preview

  • 7/27/2019 Gen Parallel Operation

    1/36

    PRODUCT TRAINING

    Parallel Operation

  • 7/27/2019 Gen Parallel Operation

    2/36

    PRODUCT TRAINING

  • 7/27/2019 Gen Parallel Operation

    3/36

    PRODUCT TRAINING

    Parallel Operation - When is it Required?

    1. To increase the capacity of available power without loss of

    supply to the customers distribution system.

    2. To allow the Generator to be connected to a live system ( e.g ;

    the Mains, (Grid, Utility,), Multiple Generator systems, C.H.P, etc.

    3. To allow shutdown of individual Generators for Maintenance or

    repair purposes.

    4. To economise operating costs by running multiple generators

    according to load demand.

    5. To provide an emergency back-up to critical supplies without

    loosing power, ( e.g ; Hospitals, Ships, Computer data systems, etc).

  • 7/27/2019 Gen Parallel Operation

    4/36

    PRODUCT TRAINING

    Parallel Operation - Essential Requirements

    1. All Generators must have the same voltage.

    2. All Generators must have the same phase rotation.

    3. All Generators must have the same frequency.

    4. All Generators and Prime Movers (Engines), must have similar no

    load, to full load, voltage and frequency characteristics.

    5. Generator installation must be provided with Synchronising

    equipment.

    6. Essential protection should include Reverse power, Over-current ,

    Over-temperature, Generator Over/Under excitation.

    7. Generator of dissimilar design or manufacturer, should have

    similar waveform characteristics (harmonics), if Neutrals are joined.

  • 7/27/2019 Gen Parallel Operation

    5/36

    PRODUCT TRAINING

    Parallel Operation - Synchronising AC Generators

    Synchronisation is carried out in order to parallel a Generator onto a

    live Bus-bar, either in Island mode ( with multiple Generator sets as the

    only supply), or to the Utility..

    Synchronisation can be achieved Manually, Semi-Automatic with

    Check-sync, or by fully automatic P.L.C systems.

    Why is Synchronisation of AC Generators necessary ?

  • 7/27/2019 Gen Parallel Operation

    6/36

    PRODUCT TRAINING

    Parallel Operation - Synchronising AC Generators

    GEN 2

    GEN 1

    Consider a simple installation with two Identical Gen-sets, (breakers open circuit).

    Normally, one (or more), generators will already be connected to the load, and

    supplying power. (GEN 2 is now closed onto the Bus-bar).

    DROOP CTAVR

    It is also normal that the Generator on line (GEN2) will be running at nominal

    frequency (50 or 60 HZ), while the incoming generator (GEN1), can be running at a

    higher (NO LOAD), frequency of about 52 or 62 HZ.

    AVR DROOP CT

    MCB

    LOAD

    BUS-BARCB1

    CB2

  • 7/27/2019 Gen Parallel Operation

    7/36PRODUCT TRAINING

    Parallel Operation - Synchronising AC Generators

    GEN 2

    GEN 1

    When the relative Engine speeds are different, the Generator waveforms will be

    rapidly going in and out of phase with each other.

    DROOP CTAVR

    AVR DROOP CT

    MCB

    LOAD

    BUS-BARCB1

    CB2

    Synchronising equipment is required to monitor the Bus Frequency and the

    Incoming Generator frequency, to ensure that the Generators are in Synchronism.

    Synchronising

    Equipment

    To correctly Synchronise A.C. Generators, the frequencies must be ALMOST identical.

    Frequency (HZ), is the Electrical equivalent of Speed (RPM), which means that the

    engine SPEEDS must be ALMOST identical.

  • 7/27/2019 Gen Parallel Operation

    8/36PRODUCT TRAINING

    EXAMPLE : In this analogy two trucks represent two Generator sets, to be paralleled .

    However, if the REAR truck is A FEW RPM FASTER than the FRONT truck, it will

    VERY SLOWLY catch up with the truck in front.

    SYNCHRONISING is exactly the same process, the RATE OF CHANGE in speed must

    be SLOW ENOUGH to allow the BREAKER to close when the Generators are IN PHASE .

    If both trucks are travelling at EXACTLY THE SAME SPEED, they will ALWAYS

    remain the SAME DISTANCE APART, ( IRRESPECTIVE OF SPEED).

    Parallel Operation - Synchronising AC Generators

    On-line Generator SetIncoming Generator Set On-line Generator SetIncoming Generator Set

    SYNCHRONISED

  • 7/27/2019 Gen Parallel Operation

    9/36PRODUCT TRAINING

    Parallel Operation - Synchronising AC Generators

    GEN 1

    GEN 2

    Example :- GEN 2 is supplying load and is running at 50HZ (1500 RPM).

    GEN 1 is INCOMING, and the engine speed has been adjusted down slightly to

    almost 1500 RPM (for example 50.1 HZ).

    As there is a SMALL RELATIVE DIFFERENCE between speeds, the Synchronising

    equipment should be indicating that the Generators are moving IN and OUT of phase

    SLOWLY enough to ALLOW TIME to close the breaker.

    50 HZ

    (1500 RPM)

    50.1 HZ(1503 RPM)

    IN PHASE

  • 7/27/2019 Gen Parallel Operation

    10/36PRODUCT TRAINING

    Parallel Operation - Synchronising AC Generators

    GEN 1

    GEN 2

    50 HZ

    50.1 HZ

    What will happen if the circuit breaker is closed in the final condition above ?

    IN PHASE

    Consider above condition:-

    The Generator is IN PHASE, , but is now about to go OUT OF PHASE.

    180o

    OUT OF PHASE

  • 7/27/2019 Gen Parallel Operation

    11/36

    PRODUCT TRAINING

    Parallel Operation - Synchronising AC Generators

    GEN 1

    GEN 2

    The Generator waveforms are 180 OUT OF PHASEwith each other.

    180

    The transient forces created are both Electrically and Mechanically DESTRUCTIVE

    As the breaker closes, GEN 1 will instantly try to reverse the rotation of GEN 2.

    This is IMPOSSIBLE, because of the inertia in the Engine/Generator moving parts.The Generators will be INSTANTLY CRASHED into synchronism. .

    CR SHEDINTO PH SE

    Electrical damage can occur to Diodes, Varistors, and Main Stator windings.

    Mechanical damage may also occur to Couplings, Bearings, and Shaft.

  • 7/27/2019 Gen Parallel Operation

    12/36

    PRODUCT TRAINING

    Parallel Operation - Synchronising AC Generators

    GEN 1

    GEN 2

    Example 2 :- GEN 2 is supplying load and is running at 50HZ (1500 RPM).

    GEN 1 engine speed has been adjusted to almost 1500 RPM (50.1 HZ).

    The Generator waveforms are SLOWLY moving IN and OUT of phase.

    50 HZ1500 RPM

    50.1 HZ1503 RPM

    The circuit breaker can be SAFELY closed in the above condition.

    IN PHASE

    The Synchronising equipment indicates that the Generator are IN PHASE.

  • 7/27/2019 Gen Parallel Operation

    13/36

    PRODUCT TRAINING

    MCB

    LOAD

    Parallel Operation - Synchronising AC Generators

    GEN 2

    GEN 1

    The INCOMING Generator should ALWAYS be slightly FASTER than the loaded

    Generator. This ensure that the incoming Generator ALWAYS takes a small proportion of

    load when the breaker is closed. This will prevent REVERSE POWER protection tripping.

    DROOP CTAVR

    AVR DROOP CT

    BUS-BARCB1

    CB2

    The Generators are now IN PARALLEL, the next step is LOAD SHARING.

    Synchronising

    Equipment

    When the Synchronising equipment indicates that the incoming Generator (GEN 1) is

    IN PHASE with the Bus-bar frequency, the circuit breaker can be safely closed.

    OK !

  • 7/27/2019 Gen Parallel Operation

    14/36

    PRODUCT TRAINING

    POWER ( kW )

    REACTIVE (kVAr)LEADING

    REACTIVE kVArLAGGING

    90

    ACTIVE CURRENT is the USEFUL CURRENT , which is IN PHASE with the Voltage, and

    provides the POWER, or kWATT component of the load.

    INDUCTIVE CURRENT is WASTED or WATTLESS CURRENT, which is LAGGING the

    Voltage by 90. This is the kVAr component, (POWER FACTOR 0).

    ACTIVE CURRENT

    p.f 1 (kW)

    VOLTAGE

    (50 OR 60HZ)

    REACTIVE CURRENTLAGGING p.f 0

    REACTIVE CURRENTLEADING p.f 0

    TIME

    VOLTAGE

    (50 OR 60HZ)

    The VECTORIAL RESULTANT is the kVA , ( APPARENT POWER).

    The COSINE of the RESULTANT ANGLE is called the POWER FACTOR ( COS ).

    90

    CAPACITIVE CURRENT LEADS the Voltage by 90.

    COS

    COS

    Parallel Operation - Load Sharing

    REACTIVE CURRENT SHARING is controlled by the GENERATORS, (AVR & DROOP).

  • 7/27/2019 Gen Parallel Operation

    15/36

    PRODUCT TRAINING

    The Brushless AVR controlled Generator has a natural linear voltage DROOPING

    characteristic from NO LOAD to FULL LOAD.

    0.5% Voltage Regulation for AVR Types MX321, MA325, MA327

    1.0% Voltage Regulation for AVR Types MX341

    REACTIVE (WATTLESS) CURRENT SHARING

    409V

    415V

    VOLTS

    0%

    0.5%

    1.0%

    0% 50% 100%PERCENTAGE LOAD

    TO AUTOMATICALLY SHARE REACTIVE LOAD CURRENT, GENERATORS

    MUST HAVE SIMILAR NO LOAD TO FULL LOAD VOLTAGE CHARACTERISTICS.

    Parallel Operation - Load Sharing

  • 7/27/2019 Gen Parallel Operation

    16/36

    PRODUCT TRAINING

    The PARALLEL DROOP CIRCUIT, provides a signal which allows the AVR to

    sense WATTLESS REACTIVE CURRENT, ( ZERO POWER FACTOR ).

    At full load 0.8 power factor the voltage DROOP required (single running), is 3%.

    This is in addition to the normal (natural) voltage regulation of the AVR, and

    allows the DROOP CIRCUIT to automatically control a % of the voltage.

    The DROOP SETTING is adjusted on the AVR DROOP CIRCUIT.

    A SHORTING SWITCH may be fitted across the DROOP CT for single running.

    1.0% (SINGLE)

    Parallel Operation - Load Sharing

    REACTIVE (WATTLESS) CURRENT SHARING

    DROOP kWATT

    403 V

    415 V

    VOLTS

    0%

    3.0%

    0% 50% 100%LOAD AT 0.8 POWER FACTOR

    http://localhost/var/www/apps/conversion/tmp/scratch_6/NPT39%20AVR%20DROOP%20CONTROL.ppthttp://localhost/var/www/apps/conversion/tmp/scratch_6/NPT39%20AVR%20DROOP%20CONTROL.ppt
  • 7/27/2019 Gen Parallel Operation

    17/36

    PRODUCT TRAINING

    Parallel Operation - Circulating Current

    GEN 2

    GEN 1

    CB1

    CB2

    EXAMPLE: Two similar 400V Generators are required to operate in parallel

    Generator 2 isincorrectlyadjusted to406V (at no load).

    GEN 2 is connected to the Bus by closing circuit breaker CB2

    400V

    406V

    MCB

    LOADBUS

    WHY IS DROOP IS REQUIRED FOR GENERATORS IN PARALLEL ?

    AVR 1

    AVR 2

    SYNCHRONISING

    EQUIPMENT

    GEN 1 is synchronised with GEN 2, and breaker CB1 is closed

    0 LOAD

    CB2

    CB1

    The resultant Bus-Bar Voltage will be approximately average of the two Generators.

    403V

    403V

    403V

  • 7/27/2019 Gen Parallel Operation

    18/36

    PRODUCT TRAINING

    Parallel Operation - Circulating Current

    GEN 2

    GEN 1

    CB1

    CB2

    MCB

    LOAD

    GEN 1 EXCITATION SYSTEM is trying to PULL the voltage DOWN to 400 V.

    This PRESSURE DIFFERENCE (VOLTS), forces CIRCULATING CURRENT into GEN 1.

    AVR

    AVR

    403V

    BUS-BAR

    403 V

    400V

    406V

    GEN 2 EXCITATION SYSTEM is trying to PUSH the voltage UP to 406 V.

    CIRCULATING CURRENT

    The RESULTANT VOLTAGE will be approximately. AVERAGE of the two Generators

    CIRCULATING CURRENT is WATTLESS, (POWER FACTOR 0).

    WHY IS DROOP IS REQUIRED FOR GENERATORS IN PARALLEL ?

  • 7/27/2019 Gen Parallel Operation

    19/36

    PRODUCT TRAINING

    Parallel Operation - Circulating Current

    GEN 2

    GEN 1

    MCB

    LOAD

    HIGH LEADING CURRENT ( CAPACITIVE, power factor 0 ) is now flowing INTO GEN 1.

    The DROOP CONTROL must REDUCE circulating current to ACCEPTABLE limits.

    BUS-BAR

    403 V

    HIGH LAGGING CURRENT ( INDUCTIVE, power factor 0 ) is now flowing OUT of GEN 2.

    CIRCULATING CURRENT

    PF

    LAG

    1 LEADLEAD

    PF

    LAG

    1 LEAD

    PF

    LAG

    LEAD1

    PF

    LAG

    LEAD1PF

    LAG

    1LEAD

    PF

    LAG

    LEAD1

    AVR 1

    AVR 2

    DROOP CT

    DROOP CT

    POWER

    FACTOR

    METERS

    CB1

    CB2

    The MAXIMUM acceptable limit for circulating current is normally 8 %.

  • 7/27/2019 Gen Parallel Operation

    20/36

    PRODUCT TRAINING

    Parallel Operation - Circulating Current

    PF

    LAG

    LEAD1PF

    LAG

    LEAD1

    PF

    LAG

    LEAD1

    GEN 2

    GEN 1

    MCB

    LOAD

    AVR 1 receives a signal proportional to the circulating current (LEADING p.f),

    which INCREASESthe Generator D.C EXCITATION VOLTAGE.

    AVR 1 DROOP CT

    BUS-BAR

    403 V

    CIRCULATING CURRENT

    AVR 2 DROOP CT

    CB1

    CB2

    DROOP CT

    AVR 2 receives a signal proportional to the circulating current (LAGGING p.f)

    which DROOPS (DECREASES), the Generator D.C EXCITATION VOLTAGE.

    DROOP CT

    AVR 1

    AVR 2

    POWER

    FACTOR

    METERS

    LEAD

    PF

    LAG

    1 LEAD

    PF

    LAG

    1LEAD

  • 7/27/2019 Gen Parallel Operation

    21/36

    PRODUCT TRAINING

    Parallel Operation - Circulating Current

    GEN 2

    GEN 1

    MCB

    LOAD

    VR 1 DROOP CT

    BUS-BAR

    PF

    LAG

    LEAD1

    VR 2 DROOP CT

    CB1

    CB2

    PF

    LAG

    LEAD1

    POWER

    FACTOR

    METERS

    When the MCB is closed, the DROOP CONTROL must also assist in SHARING the

    REACTIVE, ( power factor 0 ), component of the LOAD CURRENT.

    LOAD CURRENT

    DROOP CTVR 1

    DROOP CTVR 2

    LEAD

    PF

    LAG

    1 LEAD

    PF

    LAG

    1LEAD

    PF

    LAG

    LEAD1

    PF

    LAG

    LEAD1

    LOAD403 V

  • 7/27/2019 Gen Parallel Operation

    22/36

    PRODUCT TRAINING

    GEN 2

    GEN 1

    MCB

    LOAD

    AVR 1 DROOP CT

    BUS-BAR

    AVR 2 DROOP CT

    kWATT

    METER

    ACTIVE CURRENT (power factor 1) is the kWATT component of the load, and is

    CONTROLLED and SHARED by the PRIME MOVERS (ENGINES).

    ENG 2

    ENG 1

    LEADkW

    LEADkW

    Parallel Operation - kW Load Sharing

    kWATT

    METER

    LEADkW

    LEADkW

    The PRIME MOVERS (ENGINES), must have similar NO LOAD to FULL LOAD

    GOVERNOR CHARACTERISTICS, in order to share the ACTIVE CURRENT, (PF1).

    ACTIVE CURRENT or kW

    LOAD

  • 7/27/2019 Gen Parallel Operation

    23/36

    PRODUCT TRAINING

    1500 RPM

    1560 RPMSPEED

    0%

    4.0%

    0% 50% 100%PERCENTAGE LOAD

    A MECHANICAL ENGINE GOVERNOR REQUIRES A MINIMUM OF 4% SPEED

    DROOP IN ORDER TO SHARE THE ACTIVE CURRENT (KW), WHEN IN PARALLEL.

    1 HORSE POWER = 746 WATTS , ( OR 0.746 kWATTS .)

    HORSE POWER is the mechanical equivalent of kWATTS, (ELECTRICAL POWER).

    kWATTS = CURRENT X VOLTAGE X POWER FACTOR ( X 1.732 for 3 phase ).

    ACTIVE LOAD CURRENT SHARING, is controlled by the ENGINE GOVERNORS.

    Parallel Operation - kW Load Sharing

    ACTIVE CURRENT ( kWATT) LOAD SHARING

  • 7/27/2019 Gen Parallel Operation

    24/36

    PRODUCT TRAINING

    ENGINE 2/ 500 H.P

    ENGINE 1/ 500 H.P

    EXAMPLE : Two Generator Sets are required to run in parallel, both sets have

    equal size 500 H.P Engines, with mechanical ENGINE GOVERNORS.

    How will ENGINE 1 and 2 share the load AUTOMATICALLY, throughout all load

    variations, from NO LOAD to FULL LOAD ?

    MCB

    LOAD

    BUS-BARCB1

    CB2

    Parallel Operation - kW Load Sharing

  • 7/27/2019 Gen Parallel Operation

    25/36

    PRODUCT TRAINING

    ENGINE GOVERNING

    EXAMPLE : In this analogy the truck ENGINE represents the GENSET DIESEL

    ENGINE, and the TRUCK represents the GENERATOR.

    EngineA.C Generator

    Parallel Operation - kW Load Sharing

  • 7/27/2019 Gen Parallel Operation

    26/36

    PRODUCT TRAINING

    ENGINE GOVERNING

    LOAD LOAD

    EXAMPLE : In this analogy the truck ENGINE represents the GENSET DIESEL

    ENGINE, and the TRUCK represents the GENERATOR.

    When the truck is UNLOADED, the engine is powering the LOSSES only.

    When the truck is LOADED, the engine must provide extra power, and the truck

    speed will fall (for example 4% SPEED DROOP), because the ENGINE GOVERNOR is

    fixed at constant speed.

    What will happen if the trucks are NOW JOINED SOLIDLY TOGETHER??

    As with a Genset, the truck engine speed is FIXED, at a constant speed ie.,1500 RPM.

    Parallel Operation - kW Load Sharing

  • 7/27/2019 Gen Parallel Operation

    27/36

    PRODUCT TRAINING

    Parallel Operation - kW Load Sharing

    ENGINE GOVERNING

    The trucks are now JOINED TOGETHER, similar to two GENERATOR SETS when they

    are in PARALLEL.

    1) Both ENGINES have SIMILAR LOAD CHARACTERISTICS from no load to full load ?

    How will the engines SHARE THE LOAD in the following situations ?...

    LOAD LOAD

    ANSWER - THEY WILL AUTOMATICALLY SHARE THE LOAD - EQUALLY

  • 7/27/2019 Gen Parallel Operation

    28/36

    PRODUCT TRAINING

    Parallel Operation - kW Load Sharing

    ENGINE GOVERNING

    2) THE TRUCK IN FRONT HAS A STRONGER ENGINE THAN THE ONE AT THE BACK.?

    LOADLOAD

    ANSWER- THE FRONT ENGINE WILL TAKE LOAD AWAY FROM THE REAR ENGINE.

  • 7/27/2019 Gen Parallel Operation

    29/36

    PRODUCT TRAINING

    Parallel Operation - kW Load SharingENGINE GOVERNING

    3) The TRUCK AT THE BACK develops an ENGINE FAULT, and LOOSES POWER ?

    LOAD

    ANSWER - THE FRONT TRUCK TAKES ALL OF THE LOAD, AND MOTORS

    THE REAR TRUCK.

    MOTORSMOTORSMOTORSMOTORSMOTORSMOTORSMOTORSMOTORSMOTORS

  • 7/27/2019 Gen Parallel Operation

    30/36

    PRODUCT TRAINING

    ENGINE 2500 H.P

    When BOTH Engines have similar GOVERNOR CHARACTERISTICS, they will share

    the kW load in parallel, AUTOMATICALLY, from NO LOAD to FULL LOAD.

    When the engines have DIFFERENT governor characteristics, (as single running

    engines), load sharing will become UNEQUAL as kW load is INCREASED.

    ENGINE 1500 H.P

    1500 RPM

    1560 RPM

    ENGINE

    SPEED

    0% 50% 100%PERCENTAGE LOAD

    50% 0%

    4.0% SPEED DROOP

    Parallel Operation - kW Load Sharing

    In above example ENGINE 2 is the STRONGER ENGINE

  • 7/27/2019 Gen Parallel Operation

    31/36

    PRODUCT TRAINING

    ENGINE 2/ 500 H.P

    ENGINE 1/ 50 H.P

    EXAMPLE: Two different sizes of Generator Sets are required to run in parallel,

    Set 1 has a 50 H.P ENGINE, set 2 has a 500 H.P ENGINE.

    How will ENGINE 1 know that it must take 10% of the total kW load,

    AUTOMATICALLY, from NO LOAD to FULL LOAD ?

    MCB

    LOAD

    BUS-BARCB1

    CB2

    Parallel Operation - kW Load Sharing

  • 7/27/2019 Gen Parallel Operation

    32/36

    PRODUCT TRAINING

    ENGINE 2500 H.P

    When BOTH Engines have similar GOVERNOR CHARACTERISTICS, they will

    PROPORTIONALLY share the kW load, AUTOMATICALLY, from NO LOAD to FULL LOAD.

    ENGINE 1 should AUTOMATICALLY take 10% of the load throughout all load changes.

    ENGINE 150 H.P

    1500 RPM

    1560 RPM

    ENGINE

    SPEED

    0% 50% 100%PERCENTAGE LOAD

    50% 0%

    4.0% SPEED DROOP

    Parallel Operation - kW Load Sharing

    37 kW 370 kW

    Parallel Operation kW Load Sharing

  • 7/27/2019 Gen Parallel Operation

    33/36

    PRODUCT TRAINING

    Parallel Operation - kW Load Sharing

    ENGINE 2, 500 H.P

    ENGINE 1, 50 H.P

    Example : Engine 1 (50HP) develops a fault, which causes it to loose speed & power.

    What will happen if Engine 1 is running in parallel with Engine 2?

    MCB

    LOAD

    BUS-BARCB1

    CB2

    Answer; Engine 2 will be supplying ALL OF THE LOAD CURRENT, and feeding

    back ACTIVE CURRENT (kWATTS) INTO GEN 1.

    ACTIVE CURRENTGEN 2

    GEN 1

    GEN 1 has now become a MOTOR, DRIVING ENGINE 1.

    REVERSE POWER.

    WHAT IS REVERSE POWER ?

    MOTOR

    This is REVERSE POWER, and can severely DAMAGE the ENGINES.

    Parallel Operation kW Load Sharing

  • 7/27/2019 Gen Parallel Operation

    34/36

    PRODUCT TRAINING

    ENGINE 2, 500 H.P

    ENGINE 1, 50 H.P

    REVERSE POWER can occur :-

    1. NO LOAD - following synchronisation, if the INCOMING Engine speed is lower than

    the BUS BAR speed/frequency.2. ON LOAD - if a FAULT occurs on one of the Engines, causing it to LOOSE POWER,

    or if the Governor is INCORRECTLY ADJUSTED relative to the other Generators.

    MCB

    LOAD

    BUS-BARCB1

    CB2

    GEN 2

    GEN 1

    The Generator should be DISCONNECTED from the system to avoid damage.

    ACTIVE CURRENT

    REVERSE

    POWER

    PROTECTION

    THIS IS ACHIEVED WITH REVERSE POWER PROTECTION

    MOTOR

    Parallel Operation - kW Load Sharing

    P ll l O ti kW L d Sh i

  • 7/27/2019 Gen Parallel Operation

    35/36

    PRODUCT TRAINING

    How can kW Load sharing be achieved WITHOUT SPEED DROOP?, i.e., constant

    speed from no load to full load?

    Answer : The Engines must be fitted with ISOCHRONOUS ELECTRONIC GOVERNORS.

    MCB

    LOAD

    BUS-BARCB1

    CB2

    ISOCHRONOUS

    GOVERNOR kW FEEDBACK

    ISOCHRONOUS

    GOVERNOR kW FEEDBACK

    ACTIVE CURRENT

    ISOCHRONOUS

    GOVERNOR kW FEEDBACK

    ISOCHRONOUS

    GOVERNOR kW FEEDBACK

    kW LOAD SHARING (kW), is achieved by GOVERNOR CONTROL from a kW feedback

    signal, which automatically controls the kW LOAD SHARING.

    Parallel Operation - kW Load Sharing

  • 7/27/2019 Gen Parallel Operation

    36/36

    PRODUCT TRAINING

    RETURN TO MAIN MENU

    POWER FACTOR CONTROLLER PFC3

    PARALLEL DROOP CIRCUIT

    http://localhost/var/www/apps/conversion/tmp/scratch_6/NPT01%20MAIN%20MENU%20.ppshttp://localhost/var/www/apps/conversion/tmp/scratch_6/NPT39%20AVR%20DROOP%20CONTROL.ppthttp://localhost/var/www/apps/conversion/tmp/scratch_6/NPT49%20PFC3%20+%20RCI.ppt